KERALA STATE ELECTRICITY BOARD LIMITED KSEB DATA BOOK for CIVIL WORKS
PREFACE
The existing PWD Data Book is followed by KSE Board for preparation of
estimate of civil works. But it is observed that the majority of civil works in
KSE Board are carried out in hilly and remote area. The nature of works is also
risky, difficult and different than the works as per PWD Data Book. Hence,
KSE Board vide B.O.(FM)No.1787/2011 (MG/General/2003) dated 19.07.2011
constituted a team to prepare KSE Board Data Book for preparation of estimate
for civil works. The team held several sittings and after elaborate discussions,
enquiries and verifications prepared this Data Book.
The emphasis of this Data Book is mainly for preparation of estimate of
hydro electric projects. In line with the present construction scenario, majority
of the data includes incorporation of usage of machineries. Design mixes were
adopted for data of concrete items based on the details obtained from Research
wing, KSE Board, Idamalayar. In general, the data for different items were
arrived based on field observations, prevailing market rates and other technical
considerations.
Separate chapters have been provided for items coming under the same
category as given in the Index. The data have been also prepared in excel linked
format for easy usage of this Data Book. For arriving rates for items using
machineries, separate annexure is provided under ‘Use rate of equipments’. The
use rate of equipments is prepared based on CWC guide lines.
Whenever data for new item of works is found necessary, the same will
have to be prepared based on actual observations and got approved by the Chief
Engineer before inclusion under the respective chapter of this book. The method
of preparation of estimate using this data book is explained separately under
‘Method of preparation of estimate’
The Chairman expresses deep gratitude to the team members for their
sincere efforts and whole-hearted support in preparing this Data Book. The team
is indebted to persons who have given their valuable suggestions and
supplemented with details. The Chairman acknowledges sincere thanks to
Chief Engineer(CC) South and Chief Engineer(CC) North for their valuable
guidance and active support.
Suggestions are invited to make this book more precise and
comprehensive.
23 – 05 - 2014
Chairman, Data Team
Dy.Chief Engineer,
O/o the Chief Engineer (CC) North,
Kozhikode
Chapter Name Page Nos.
I Clearing site and Felling trees…………………………………………. 1
II Dismantling and Demolition…………………………………………… 3
III Excavation and Allied works…………………………………………. 8
IV Drilling and Grouting…………………………………………………. 16
V Reinforcement and Form work……………………………………….. 20
VI Concreting……………………………………………………………. 23
VII Masonry works………………………………………………………. 36
VIII Plastering and Pointing……………………………………………….. 43
IX White washing and Painting…………………………………………… 49
X Doors, Windows and Ventilators…………………………………….. 59
XI Water supply and Sanitory works…………………………………….. 64
XII Flooring………………………………………………………………. 72
XIII Roofing………………………………………………………………. 78
XIV Road works………………………………………………………….. 81
XV Tunnel and Surge…………………………………………………….. 90
XVI Penstock…………………………………………………………….. 100
XVII Gates and Trashrack…………………………………………………. 105
XVIII Miscellaneous works…………………………………………………. 107
XIX Investigation works…………………………………………………… 116
Annexure - A Use Rate of Equipments.
Annexure - B Additional Use Rate of Equipments.
Annexure - C Machinery details.
INDEX
KSEB DATA BOOK
INSTRUCTIONS FOR PREPARATION OF DATA BOOK
1. The data is prepared in excel linked format and the data for
estimate may be prepared using the soft copy made available with
this Data Book.
2. In the data under ‘Use rate of equipments’, the cost of equipments,
charges, capacity and cost of fuel as per prevailing SOR/approved
data may be filled under appropriate columns.
3. In the data, HA and OH may be considered as per the nature of
terrain and nature of work.
4. Item No.2 of chapter III – Excavation and Allied works, may be
taken only for excavation works in which conveyance of excavated
materials by using tipper is considered.
5. In the data, generally for all works, all lifts are considered to be
inclusive, other than stated separately.
6. Considering the availability and economy of form work materials,
steel formwork is only considered in the data. While preparing the
estimate, the same may only be considered.
7. If data of any item is not available in this Data Book, the existing
PWD Data Book may be referred.
Sl.
No.Description of items Rate Amount Remarks
1. 100 m2 Clearing light jungle and removal of rubbish
upto a distance of 150m outside the
periphery of the area cleared.
Note: UR-Hourly use rate
. HA & OH may be
allowed subject to the
nature of works
0.4 hr Grass cutter (up to 2.5 HP) - (UR) 1 hr
% OH
% CP
Total /100m2
2. 100 m2 Clearing thick and thorny jungle and small
trees of girth up to 30cm including removal
of rubbish up to a distance of 150m outside
the periphery of the area cleared.
0.6 hr Grass cutter (up to 2.5 HP) - (UR) 1 hr
0.1 No Man 1 Each
% HA
% OH
% CP
Total /100m2
3. 1 No Felling trees of girth beyond 30cm and upto
120cm including cutting trunks and
branches, removing the roots completely and
stacking serviceable materials .
1 hrChain saw wood cutter (up to 4 HP)- (UR)
1 hr
0.50 No Helper 1 Each
5 % Sundries, ropes, etc. of above two items
% HA
% OH
% CP
Total /Each
4. 1 No Felling trees of girth beyond 120 cm and
upto 240cm including cutting trunks and
branches, removing the roots completely and
stacking serviceable materials .
1.5 hrChain saw wood cutter (above 4 HP)- (UR)
1 hr
1 No Helper 1 Each
5 % Sundries, ropes, etc. of above two items
% HA
% OH
% CP
Total /Each
Quantity Unit
CHAPTER I
CLEARING SITE AND FELLING TREES
1
5. 1 No Felling trees of girth beyond 240cm
including cutting trunks and branches,
removing the roots completely and stacking
serviceable materials .
3.5 hrChain saw wood cutter (above 4 HP)- (UR)
1 hr
2 No Helpers 1 Each
5 % Sundries, ropes, etc. of above two items
% HA
% OH
% CP
Total /Each
6. 1 No Felling arecanut trees including cutting
trunks and removing the roots completely
and stacking serviceable materials .
0.17 hrChain saw wood cutter (up to 4 HP)- (UR)
1 hr
0.08 No Helper 1 Each
5 % Sundries, ropes, etc. of above two items
% HA
% OH
% CP
Total /Each
7. 1 No Felling coconut and palm trees including
cutting trunks and removing the roots
completely and stacking serviceable
materials .
1 hrChain saw wood cutter (up to 4 HP)- (UR)
1 hr
0.25 No Helper 1 Each
5 % Sundries, ropes, etc. of above two items
% HA
% OH
% CP
Total /Each
2
Sl.
No.Description of items Rate Amount Remarks
1 1 m3 Dismantling, clearing away and carefully
stacking materials useful for reuse for any
thickness of walls of brick, laterite or rubble
in mud /dry, including disposal of debris
within a distance of 150 m.
Note: UR-Hourly use
rate . HA & OH may
be allowed subject to the
nature of works
0.70 No Man 1 Each
% HA
% OH
% CP
Total /m3
2 1 m3 Dismantling, clearing away and carefully
stacking materials useful for reuse for any
thickness of walls of brick, laterite or rubble
in cement mortar /Lime/Surkhi mortar
including disposal of debris within a distance
of 150 m.
1.60 No Man 1 Each
% HA
% OH
% CP
Total /m3
3 1 m3 Cutting/chipping and removing portions of
existing RCC works carefully without
damaging the remaining structure and
removing the debris within a distance of 150
m.
12 hr Concrete cutter up to 2.5 HP - (UR) 1 Each
1 No Man 1 Each
5 % Scaffolding,platform, etc. of above two items
% HA
% OH
% CP
Total /m3
4 1 m2 Lifting and removing tiles set in mortar in
floors, including clearing and stacking
materials and removing the debris within a
distance of 150 m.
0.025 No Mason 1 Each
0.025 No Man 1 Each
% HA
% OH
% CP
Total /m2
Quantity Unit
CHAPTER II
DISMANTLING AND DEMOLITION
3
5 1 m2 Dismantling and removing Mangalore tiles
over roofs including ridges, hips, vallery
sheets, wind ties and bordering but excluding
roof timber and stacking materials within a
distance of 150 m.
0.05 No Man 1 Each
% HA
% OH
% CP
Total /m2
6 1 m2 Dismantling and removing pan or pot tiles
over roofs and stacking materials within a
distance of 150 m.
0.10 No Man 1 Each
% HA
% OH
% CP
Total /m2
7 1 m3 Dismantling and removing wrought and
framed timbers in roofs and floors and
stacking materials within a distance of 150 m
1.40 No Carpenter 1 Each
1.40 No Man 1 Each
% HA
% OH
% CP
Total /m3
8 1 Each Dismantling and removing doors with or
without ventilators including removal of
shutters, hinges, holdfasts and all other
fittings and stacking materials within a
distance of 150 m.
0.20 No Mason 1 Each
0.18 No Carpenter 1 Each
0.30 No Man 1 Each
% HA
% OH
% CP
Total /Each
9 1 No Dismantling and removing windows with or
without ventilators including removal of
shutters, hinges, holdfasts and all other
fittings and stacking materials within a
distance of 150 m
0.15 No Mason 1 Each
0.10 No Carpenter 1 Each
0.20 No Man 1 Each
% HA
4
% OH
% CP
Total /Each
10 1 No Dismantling and removing ventilators
including removal of shutters, hinges,
holdfasts and all other fittings and stacking
materials within a distance of 150 m
0.10 No Mason 1 Each
0.05 No Carpenter 1 Each
0.10 No Man 1 Each
% HA
% OH
% CP
Total /Each
11 1 m2 Dismantling, removing and lowering planked
sheeting, boarded floor, ceiling, etc. and
stacking materials within a distance of 150
m.
0.035 No Carpenter 1 Each
0.035 No Man 1 Each
% HA
% OH
% CP
Total /m2
12 1 m2 Taking down shutters of doors, with or
without ventilators including removal of
hinges and all other fittings and stacking
within a distance of 150 m.
0.10 No Carpenter 1 Each
0.10 No Man 1 Each
% HA
% OH
% CP
Total /m2
13 1 m2 Taking down shutters of windows with or
without ventilators including removal of
hinges and all other fittings and stacking
within a distance of 150 m.
0.10 No Carpenter 1 Each
0.05 No Man 1 Each
% HA
% OH
% CP
Total /m2
14 1 m2 Taking down shutters of ventilators
including removal of hinges and all other
fittings and stacking within a distance of 150
m.
0.05 No Carpenter 1 Each
5
0.02 No Man 1 Each
% HA
% OH
% CP
Total /m2
15 1 m2 Dismantling and removing AC sheet over
roof including loosening the purlins,ridge
pieces, nuts, bolts and all other fittings and
stacking materials within a distance of 150m
0.035 No Fitter 1 Each
0.035 No Man 1 Each
% HA
% OH
% CP
Total /m2
16 1 m2 Dismantling and removing roofing sheet
other than AC sheets over roof including
loosening the purlins,ridge pieces, nuts, bolts
and all other fittings and stacking materials
within a distance of 150m
0.02 No Fitter 1 Each
0.02 No Man 1 Each
% HA
% OH
% CP
Total /m2
17 1 Kg Dismantling and removing steel truss, purlins
etc. and all other fittings and stacking
materials within a distance of 150m
0.004 No Blacksmith 1 Each
0.004 No Heavy load mazdoor 1 Each
0.003 No Man 1 Each
% HA
% OH
% CP
Total /Kg
18 1 Kg Dismantling and removing steel gate, grills
etc. and all other fittings and stacking
materials within a distance of 150m
0.005 No Heavy load mazdoor 1 Each
0.003 No Man 1 Each
% HA
% OH
% CP
Total /Kg
6
19 1 m2 Dismantling and removing rolling
shutter,collapsible gate and all other fittings
and stacking materials within a distance of
150m
0.06 No Fitter 1 Each
0.07 No Mason 1 Each
0.10 No Man 1 Each
% HA
% OH
% CP
Total /m2
20 1 m3 Demolishing mud or sundried brick walls of
any thickness including disposal of debris
within a distance of 150 m.
0.50 No Man 1 Each
% HA
% OH
% CP
Total /m3
21 1 m3 Demolishing plain cement concrete and
clearing away the debris within a distance of
150 m.
3.00 hr. Concrete cutter up to 2.5 HP - (UR) 1 hr
0.75 No Man 1 Each
% HA
% OH
% CP
Total /m3
22 1 m3 Demolishing R.C.C. work including
separately removing and stacking available
reinforcement and clearing away the debris
within a distance of 150 m.
4.00 hr. Concrete cutter up to 2.5 HP - (UR) 1 hr
1.00 No Man 1 Each
5 %Scaffolding,platform, etc. of above two items
% HA
% OH
% CP
Total /m3
23 1 m2 Demolishing and removing old cement
plaster and disposal of the debris within a
distance of 150 m.
0.05 No Man 1 Each
% HA
% OH
% CP
Total /m2
7
Sl.
No.Description of items Rate Amount Remarks
1 1 m3 Common excavation in all classes of soil
including boulders up to 500 dm3
in size and
disposing the unserviceable materials within
50 m lead and all lifts
Note: UR-Hourly use rate
. HA & OH may be
allowed subject to the
nature of works
0.04 hr Excavator (0.93 m3) for excavating ,
loading, etc. (UR) 1 hr
% OH
% CP
Total /m3
2 1 m3 Common excavation in all classes of soil
including boulders up to 500 dm3 in size and
disposing the unserviceable materials within
up to 1 km lead and all lifts
Add 0.04 hour for every
additional km lead for
tipper use rate
0.025 hr Excavator (0.93 m3) for excavating ,
loading, etc. (UR) 1 hr
0.100 hr Tipper (7 T) for conveyance (UR) 1 hr
% OH
Quantity
CHAPTER III
EXCAVATION AND ALLIED WORKS
Unit
8
% OH
% CP
Total /m3
3 1 m3 Common excavation in all classes of soil
including boulders up to 500 dm3
in size and
disposing the unserviceable materials ( in or
under water or liquid mud)
Rate of item 1 or 2 above
20 % Add 20% of the above
Total /m3
4 1 m3 Excavation in rock and boulders above 500
dm3
in size in wet/ dry condition at all
elevations using modern explosives with jack
hammer etc. drilling, conveying and
disposing the unserviceable materials with in
50 m lead and all lift and cost of compressed
air, jack hammer, water line, etc.
0.32 Kg Special gelatine 80% 25 Kg
2.50 No. Electric detonator 1 Each
3.13 m Drilling with jack hammer 1 m
0.037 No. Blaster for charging 1 Each
0.018 No. Helper 1 Each
0.04 hr. Excavator (0.93 cum) for excavating ,
loading, etc. (UR) 1 hr.
% HA
% OH
% CP
Total /m3
8
5 1 m3 Excavation in rock and boulders above 500
dm3
in size in wet/ dry condition at all
elevations using modern explosives with jack
hammer etc. drilling, conveying and
disposing the unserviceable materials up to 1
km lead and all lift and cost of compressed
air, jack hammer, water line, etc.
Add 0.04 hour for every
additional km lead for
tipper use rate
0.32 Kg Special gelatine 80% 25 Kg
2.50 No. Electric detonator 1 Each
3.13 m Drilling with jack hammer 1 m
0.037 No. Blaster for charging 1 Each
0.018 No. Helper 1 Each
0.025 hr. Excavator (0.93 cum) for excavating ,
loading, etc. (UR) 1 hr.
0.10 hr Tipper (7 T) for conveyance (UR) 1 hr
% HA
% OH
% CP
Total /m3
6 1 m3 Excavation in rock and boulders above 500
dm3
in size by controlled and protected
9
dm3
in size by controlled and protected
blasting in wet/ dry condition at all
elevations using modern explosives with jack
hammer etc. drilling, conveying and
disposing the unserviceable materials within
50 m lead and all lift and cost of compressed
air, jack hammer, water line, etc.
0.19 Kg Special gelatine 80% 25 Kg
3.00 No. Electric detonator 1 Each
3.75 m Drilling with jack hammer 1 m
0.037 No. Blaster for charging 1 Each
0.018 No. Helper 1 Each
0.04 hr. Excavator (0.93 cum) for excavating ,
loading, etc. (UR) 1 hr.
0.05 No. Man for filling, tying, placing and replacing
gunny bags 1 Each
8.30 No. Gunny bags( used 2 times) 10 No.
% HA
% OH
% CP
Total /m3
9
7 1 m3 Excavation in rock and boulders above 500
dm3
in size by controlled and protected
blasting in wet/ dry condition at all
elevations using modern explosives with jack
hammer etc. drilling, conveying and
disposing the unserviceable materials up to 1
km and all lift and cost of compressed air,
jack hammer, water line, etc.
Add 0.04 hour for every
additional km lead for
tipper use rate
0.19 Kg Special gelatine 80% 25 Kg
3.00 No. Electric detonator 1 Each
3.75 m Drilling with jack hammer 1 m
0.037 No. Blaster for charging 1 Each
0.018 No. Helper 1 Each
0.025 hr. Excavator (0.93 cum) for excavating ,
loading, etc. (UR) 1 hr.
0.10 hr Tipper (7 T) for conveyance (UR) 1 hr
0.05 No. Man for filling, tying, placing and replacing
gunny bags 1 Each
8.30 No. Gunny bags( used 2 times) 10 No.
% HA
% OH
% CP
Total /m3
10
8 1 m3 Excavation in rock and boulders above 500
dm3
in size by non explosive agent/splitter or
any other method with out resorting to the
use of conventional explosive materials with
jack hammer etc. drilling, conveying and
disposing the unserviceable materials within
50m leads and all lifts, cost of compressed
air, jack hammer, water, etc.
34.00 Kg Cost of non explosive 1 Kg
25.00 m Drilling with jack hammer 1 m
0.50 No Hammermen 1 Each
0.50 No Men for picking etc. 1 Each
5 % Usage of wedge, crow bar, dewatering etc.
@ 5% total of above
0.04 hr. Excavator (0.93 cum) for excavating ,
loading, etc. (UR) 1 hr.
% H.A
% OH
% CP
Total /m3
10
9 1 m3 Excavation in rock and boulders above 500
dm3
in size by non explosive agent/splitter or
any other method with out resorting to the
use of conventional explosive materials with
jack hammer etc. drilling, conveying and
disposing the unserviceable materials up to 1
km lead and all lifts, cost of compressed air,
jack hammer, water, etc.
Add 0.04 hour for every
additional km lead for
tipper use rate
34.00 Kg Cost of non explosive 1 Kg
25.00 m Drilling with jack hammer 1 m
0.50 No Hammermen 1 Each
0.50 No Men for picking etc. 1 Each
5 % Usage of wedge, crow bar,dewatering etc. @
5% total of above
0.025 hr. Excavator (0.93 cum) for excavating ,
loading, etc. (UR) 1 hr.
0.10 hr Tipper (7 T) for conveyance (UR) 1 hr
% H.A
% OH
% CP
Total /m3
10 1 hp/hr Bailing out of water with pump including
conveyance to the site and erection, cost of
fuel, lubricating oil and other stores
11
fuel, lubricating oil and other stores
including accessories, labour charges etc.
Rate for 10 hp/hr
10.00 hp/hr Pump charges (UR) 10 hp/hr
20.00 m Accessories (UR) 60 m
5 % Conveyance and erection charges, temporary
bund, etc. @ 5% of above two items
% OH
% CP
Total for 10 hp/hr
Hence for 1 hp/hr /hp/hr
11 1 m2 Providing steel shoring using plates,
angles etc. of suitable size and thickness and
to maintain the shoring so as not to affect the
work till the works are completed including
cost of all labours, materials , erection and
dismantiling charges etc
35.00 Kg steel angles 1 Qtl
60.00 Kg steel plates 1 Qtl
20.00 % Fabrication charges, cost of ties, nails, ropes
etc @ 20% above items
0.10 No Foreman 1 Each
0.30 No Khalasi 1 Each
0.30 No Man 1 Each
% H.A
% OH
% CP
Total /m2
Angles and plates - 20
times usage
11
12 1 m3 Chiselling, Wedging, barring, picking, etc.
on hard rock / concrete wherever necessary
and disposing the unserviceable materials
within 50 m leads including all charges
5.40 m Drilling with jack hammer 1 m
0.50 No. Hammerman 1 Each
0.50 No. Men for picking etc. 1 Each
5 % Usage of wedge, crow bar, etc. @ 5% total
of above
0.04 hr. Excavator (0.93 cum) for excavating ,
loading, etc. (UR) 1 hr.
% HA
% OH
% CP
Total /m3
13 1 m3 Chiselling, Wedging, barring, picking, etc.
on hard rock / concrete wherever necessary
and disposing the unserviceable materials up
to 1 km lead including all charges.
Add 0.04 hour for every
additional km lead for
tipper use rate
5.40 m Drilling with jack hammer 1 m
0.50 No. Hammerman 1 Each
12
0.50 No. Hammerman 1 Each
0.50 No. Man for picking etc. 1 Each
5 % Usage of wedge, crow bar, etc. @ 5% total
of above
0.025 hr. Excavator (0.93 cum) for excavating ,
loading, etc. (UR) 1 hr.
0.10 hr Tipper (7 T) for conveyance (UR) 1 hr
% HA
% OH
%CP
Total /m3
14 1 m3 Stacking rubble for measurment including
all labour charges.
0.175 No Man 1 Each
% HA
% OH
% CP
Total /m3
12
15 1 m2 Foundation preparation for placing concrete
including chisel dressing wherever required
at all elevations and cleaning the surface with
compressed air and water etc.and disposing
the unserviceble materials including all lead,
lift conveyance and labour charges etc.
0.10 No. Man for cleaning 1 Each
2.00 min Cost of compressed air at 100 cfm 1 hr
130.00 litres Water charges 1000 litres
5 % Air and water connection @ 5% of ii and iii
above
% HA
% OH
% CP
Total /m2
16 1 Bag Providing earth filled bag wherever
necessary including cost and conveyance of
all materials, labour charges, etc.
1.00 Bag Empty bag 1 Each
0.01 No. Man 1 Each
% HA
% OH
Note: If earth is not
avilable free of cost, cost
may be included
13
% OH
% CP
Total /Bag
17 1 m3 Back filling with departmental earth within
50m lead and all lift, labour charges, etc.
0.04 hr. Excavator for loading, spreading and
levelling etc. (UR) 1 hr.
% OH
% CP
Total /m3
18 1 m3 Back filling with departmental earth within
up to 1 km lead and all lift, labour charges,
etc.
Add 0.04 hour for every
additional km lead for
tipper use rate
0.03 hr. Excavator for loading,spreading and
levelling etc. (UR) 1 hr.
0.10 hr Tipper (7 T) for conveyance (UR) 1 hr
% OH
% CP
Total /m3
19 1 m3 Back filling with contractors earth including
all leads and lifts, labour charges, etc.
1.00 m3 Earth for filling 1 m
3
0.03 hr. Excavator for spreading and levelling etc.
(UR) 1 hr.
% OH
% CP
Total /m3
13
20 1 m3 Back filling with departmental earth within
50 m lead and lift and compacting in layers
including , labour charges etc.
0.04 hr. Excavator for loading, spreading, levelling
and compacting etc. (UR) 1 hr.
% OH
% CP
Total /m3
21 1 m3 Back filling with departmental earth up to 1
km lead and lift and compacting in layers
including , labour charges etc.
Add 0.04 hour for every
additional km lead for
tipper use rate
0.03 hr. Excavator for loading, spreading, levelling
and compacting etc. (UR) 1 hr.
0.10 hr Tipper (7 T) for conveyance (UR) 1 hr
% OH
% CP
Total /m3
22 1 m3 Back filling with contractors earth and
compacting in layers including all lead and
lift , labour charges etc.
1.00 m3
Earth for filling 1 m3
0.03 hr. Excavator for spreading and levelling etc.
14
0.03 hr. Excavator for spreading and levelling etc.
(UR) 1 hr.
% OH
% CP
Total /m3
23 1 m2 Turfing the slopes with sods including
trimming, dressing and watering as required
until the turf properly takes root and in any
case for a period not less than 1 month
including cost of all materials, labour charges
etc.
0.16 No. Man 1 Each
% HA
% OH
% CP
Total /m2
14
Open well excavation
24(a) 1 m3 Open well excavation in all classes of soil
for all diameters, and disposing the
unserviceable materials within 150m
including all lead and lift.
Note: in or under water
or liquid add 20 % extra.
For rock, 2 times of
corresponding rate of soil
For first depth upto 1.50m
2.60 No.Man for digging, shaping, lifting, conveying,
etc. 1 Each
10 % Cost of tools, lifting arrangements, etc. @
10% of above
% H.A on
% OH on
% CP on
Total /m3
24(b) 1 m3 For every subsequent depth of 1.50m or part
there of.
Rate vide item above 23(a) 1 m3
20 % Add 20% extra
Total /m3
1515
Sl.
NoDescription of items Rate Amount Remarks
1 1 m Drilling holes for providing anchor /dowel
bars varying in depth and diameter in rock or
concrete and cleaning the holes, grouting
with cement grout (CM 1:2) after fixing
dowel bars including cost of all materials,
labour etc. complete as per specification and
drawings.
1.67 Kg Cement 1 MT
0.002 m3 M sand / river sand 1 m
3
1.00 m Drilling with jack hammer 1 m
5 % Conveyance of materials, cleaning, fixing,
grouting charges, etc. @ 5% of above
% OH
% CP
Total /m
2 1 Set Transporting drilling machine, pumpset and
other accessories including loading and
unloading charges, and transporting back
after competion of works as per the direction
of departmental officers.( Approximate wt 5
MT)
Transporting back need
not be considered if the
machine is not conveyed
back.
km Lorry conveyance in plain 1 MT
km Lorry conveyance in hilly 1 MT
3.00 No Khalasis for loading and unloading 1 Each
4.00 No Man for loading and unloading 1 Each
Total
Transporting back @ 100% of above
% HA
% OH
% CP
Total /Set
3 1 No. Conveying the drilling machine, pumpset and
accessories to drilling location, erecting,
dismantling and shifting to nearest location/
road access including all leads, lifts, labour
and machine charges etc.
1.00 No. First class mechanic 1 Each
1.00 No. Fitter 1 Each
2.00 No Khalasis 1 Each
4.00 No Man 1 Each
20.00 No Gunny bags( used 2 times) 10 Nos.
0.05 No. Man for filling, tying, placing and replacing
gunny bags1 Each
% HA
% OH
% CP
Total /Each
Note: 1. UR-Hourly use
rate. HA & OH may be
allowed subject to the
nature of works.
2. Cost of cement may be
included in the item or
excluded and measured
as a separate item.
Quantity Unit
CHAPTER IV
DRILLING AND GROUTING
16
4 1 m Drilling in soil consisting of earth and
boulders using diamond drill, and re-drilling
wherever required, including labour charges,
machinery, air, water, etc.
1.00 m Drilling with diamond drill in soil (UR) 1 m
0.10 hr. 10 hp pump (UR) 1 hr.
5 % Provision for casing pipe, clamp, etc. @ 5%
of above items
% OH
% CP
Total /m
5 1 m Drilling in rock / concrete using diamond
drill(without cores), and re-drilling wherever
required, including labour charges,
machinery, air, water, etc.
1.00 m Drilling with diamond drill in rock(UR) 1 m
2.00 hr 10 hp pump (UR) 1 hr.
% OH
% CP
Total /m
6 1 m Drilling in rock / concrete using diamond
drill (with core), and re-drilling wherever
required, taking cores, serially numbering
with paint, placing the same in core boxes
and transporting including labour charges,
machinery, air, water, etc. (excluding cost of
core box)
1.00 m Drilling with diamond drill in rock(UR) 1 m
2.00 hrs. 10 hp pump (UR) 1 hr.
10 % Provision for core barrel, collecting cores,
numbering, placing in core box, transporting
etc. @ 10% of above items
% OH
% CP
Total /m
7 1 m Drilling in rock / concrete using percussion
drill, and re-drilling wherever required,
including labour charges, machinery, air,
water, etc.
1.00 m Drilling with percussion drill 1 m
0.50 hr. 10 hp pump (UR) 1 hr.
% OH
% CP
Total /m
17
8 1 Set Hook-up to grout holes for washing seams,
cavities, etc. in foundation and testing holes
in such a way that in a group of four holes
are selected for washing foundation, one hole
is capped for water, two for air and other left
open to permit the outflow of washed
materials using compressed air required at
the rate of 200 cfm and water at 500 litres/
minute including cost and conveyance of all
materials, labour charges, shifting, etc
complete as per standard specifications and
as directed by the departmental officers.
0.75 hr. Air compressor 250 cfm(UR) 100 cfm
5000 litres Charges for water 1000 litres
0.25 hr. Grout pump (10 HP) (UR) 1 hr.
0.50 No. Foreman 1 Each
1.00 No. Man 1 Each
% HA
% OH
% CP
Total /Set
9 50 Kg Pressure grouting with cement with/without
packers at required consistency including all
labour charges, machinery, equipment, air,
water, etc. as per specifications and as
directed by the departmental officers, but
excluding cost of cement.
50.00 Kg Cement 1 MT
0.25 hr. Grout pump (10 HP) 1 hr.
375.00 litres Cost of water 1000 litres
0.002 m3 Cost of M sand / R sand 1 m
3
10 % Shifting and mixing charges, sealing seams,
etc. @ 10% of above items
% OH
% CP
Total /50Kg
18
10 1 Kg Supplying M.S core boxes with 150x60x10
cm with 7 inside compartments and hinged
top cover with locking arrangements and 2
Nos. handle on sides, using 2mm thick M.S
plate and 30x5mmM.S flats including
cutting, shaping, welding, applying a coat of
iron primer after scrapping and cleaning,
painting with 2 coats of synthetic enamel
paint, painting bore hole details and name
scheme on both sides of lid for identification,
etc. complete as per direction of
departmental officers.
0.263 Kg MS flats ( assume 25% of weight of box)
1 Qtl.
0.788 Kg MS plates ( assume 75% of weight of box)
1 Qtl.
1.00 No Welding rods, 8g 100 No.
0.05 No Blacksmith 1 Each
0.05 No Fitter 1 Each
0.02 No Welder 1 Each
5 % Hire charges,painting charges, sundries,
conveyance, etc. @ 5% above
% H.A
% OH
% CP
Total /Kg
11 1 Kg Providing rock bolts of specified diameter
and length, cutting and threading steel rods
after drilling at specified locations at all
elevations including cost of all materials,
cement, scaffolding, labour, curing etc,
9.73 Kg 20mm dia. MS rod 3.1m long 1 Qtl
3.14 Kg MS plate 200X200x10mm 1 Qtl
20 % Cutting, threading , fabrication , cost of nut
etc @ 20% of above items
3.00 m Drilling hole with jack hammer 1 m
3.00 Kg Cement 1 MT
0.20 No. Fitter 1 Each
0.50 No. Man 1 Each
5 % Scaffolding, sundries, etc. @ 5% of above
items
% H.A
% OH
% CP
Total
Hence for 1Kg /Kg
19
12 1 Kg Providing anchor bars of varying depth using
Tor steel, bend, jumped, etc. including cost
and conveyance of steel, labour charges, etc.
complete as per the specifications and
drawing as directed by the departmental
officers.
1 Kg Tor steel 1 Qtl
0.015 No. Black smith 1 Each
% H.A
% OH
% CP
Total /Kg
20
Sl.
NoDescription of items Rate Amount Remarks
1 1 Kg Reinforcement for RCC works bent, tied and
placed in position using Tor steel including
cost and conveyance of all materials and all
labour charges etc. complete.
Data for 1 Qtl
1.00 Qtl TMT steel 1 Qtl
0.45 Kg Iron wire for tying (16G) 1 Kg
1.00 No. Black smith 1 Each
1.48 No. Man 1 Each
% H.A
% OH
% CP
Total
Hence for 1 Kg /Kg
2 1 No Welding "V" cut ends for Reinforcement
bars (36 mm dia) including cost and
conveyance of all materials, labour charges
etc. complete but excluding cost of steel.
6.50 No Welding Rod 100 No 36 mm dia - 6.50 nos.
32 mm dia - 5.00 nos.
25 mm dia - 3.50 nos.
22 mm dia - 3.00 nos.
20 mm dia - 2.25 nos.
16 mm dia - 1.50 nos.
12 mm dia 1.00 nos.
Gauge of welding rod
8g/10g/12g may be
decided according to the
reinforcement bar dia.
0.48 hrs Welding set 1 hr 36 mm dia - 0.48 hrs.
32 mm dia - 0.40 hrs.
25 mm dia - 0.36 hrs.
22 mm dia - 0.32 hrs.
20 mm dia - 0.28 hrs
16 mm dia - 0.24 hrs.
12 mm dia - 0.24 hrs.
0.125 No Blacksmith 1 Each 36 mm dia - 0.125 nos.
32 mm dia - 0.100 nos.
25 mm dia - 0.100 nos.
22 mm dia - 0.080 nos.
20 mm dia - 0.070 nos.
16 mm dia - 0.060 nos.
12 mm dia - 0.050 nos.
Quantity Unit
CHAPTER V
REINFORCEMENT AND FORMWORK
21
0.25 No Special Mazdoor 1 Each 36 mm dia - 0.25 nos.
32 mm dia - 0.20 nos.
25 mm dia - 0.20 nos.
22 mm dia - 0.16 nos.
20 mm dia - 0.14 nos.
16 mm dia - 0.12 nos.
12 mm dia - 0.10 nos.
0.25 No Man 1 Each 36 mm dia - 0.25
nos. 32 mm dia -
0.20 nos. 25
mm dia - 0.20 nos.
22 mm dia - 0.16
nos. 20 mm
dia - 0.14 nos.
16 mm dia - 0.12
nos. 12 mm
dia - 0.10 nos.
0.125 No Welder 1 Each 36 mm dia - 0.125 nos.
32 mm dia - 0.100 nos.
25 mm dia - 0.100 nos.
22 mm dia - 0.080 nos.
20 mm dia - 0.070 nos.
16 mm dia - 0.060 nos.
12 mm dia - 0.050 nos.
% HA
% OH
% CP
Total /Each
3 1 m2 Formwork for concrete works including cost
and conveyance of all materials, labour
charges etc. complete.
a For slabs
26.98 Kg Structural steel (average cost of MS channel
and MS joists) 1 Qtl
life 25 times
18.01 Kg MS plate 1 Qtl life 15 times
19.50 Kg MS rounds, pipes etc ( average cost of MS
round and MS plates) 1 Qtl
life 25 times
22
20.00 % Fabrication charges, wooden planks, cleats,
sundries etc@ 20% of above
0.01 No. Foreman 1 Each
0.10 No. Khalasi 1 Each
0.10 No. Man 1 Each
% HA
% OH
% CP
Total
b For lintels, sunshades and beams
Rate for slabs
10 % Add extra 10 %
Total
c For columns
Rate for slabs
20 % Add extra 20 %
Total/m
2
Note: For additional lift
of form work for building
works,for first floor 10 %
of labour over Ground
floor ,for 2 nd floor 20 %
of labour over ground
floor, for 3rd floor 30 %
of labour over ground
floor and so on.For other
than building works, lift
taken as every 3m and %
of labour same as that of
building works.
Note: Form work for
roof slab of more than 4
m height in a single
stretch, add 20% extra
for 2m additional height,
of rate of formwork.
23
Sl.
NoDescription of items Rate Amount Remarks
1 1 m3 Cement concrete M7.5 with 40mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials, labour and conveyance
charges, etc. complete but excluding cost of
cement.
Note:1 UR - Hourly use
rate. HA & OH may
be allowed subject to the
nature of works
Quantity Unit
CHAPTER VI
CONCRETING
All measurements shall be taken to the nearest centimetre, except that thickness of slabs, partition, etc., and sectional dimensions in
case of posts, columns, beams and the like shall be taken to the nearest half centimetre.
No deductions shall be made for (1) ends of dissimilar materials (eg. Joist beams, posts, girders, rafters, purlins, trusses, corbels,
steps, etc.) upto 500 cm2
in section. (2) opening upto 0.10 m2
.Note:- In calculating area of opening upto 0.10 m2
, the size of opening
includes the thickness of any seperate lintels or sills.No extra labour for forming such openings or voids shall be measured.
In volume occupied by water pipes, conduits, etc., not exceeding 25 cm2
each in cross sectional area shall not be deducted.
Reinforcement shall be measured separately and paid for.
In T- beam construction, the floor or roof shall be taken as running continuosly through, and the beams as that portion above or
below the floor or roof.
Columns shall be measured from the floor surface to the underside of beams or slabs as the case may be. Where columns are
connected to beams by haunchings, the columns shall be measured upto the springing of the haunchings and the latter included with the
beams. Where the width of the beam is less than the width of the column, the extra width at the junction shall be included with the beam.
24
cement.
180.00 Kg Cement 1 MT
0.42 m3 M sand / R sand 1 m
3
0.52 m3
40 mm coarse aggregate 1 m3
0.30 m3
20 mm coarse aggregate 1 m3
0.21 m3
12 mm coarse aggregate 1 m3
150.00 litre Water including for curing 1000 litre
0.08 hr. Batching and mixing plant (UR) forbatching
and mixing
1 hr.
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
1 hr.
1.95 No Man for placing 1 Each
0.20 No Mason for placing 1 Each
0.20 hr. Vibrator (UR) 1 hr.
0.25 No. Man for curing 1 Each
% H.A
% OH
% CP
Total /m3
2 1 m3 Cement concrete M10 with 40mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.
210 Kg Cement 1 MT
0.45 m3 M sand / R sand 1 m
3
0.47 m3
40 mm coarse aggregate 1 m3
0.28 m3
20 mm coarse aggregate 1 m3
Note 4. Cost of cement
may be included in the
item or excluded and
measured as separate
items.
Note: 2. Add 0.05 hour
for every additional km
lead for Transit mixer
use rate -Transit mixer -
2m3 volume
Note 3. For additional
lift of concrete, for
building works,for first
floor 15 % of labour over
Ground floor ,for 2 nd
floor 30 % of labour over
ground floor, for 3rd
floor 45 % of labour over
ground floor and so
on.For other than
building works, lift
taken as every 3m and %
of labour same as that of
building works.
24
0.19 m3
12 mm coarse aggregate 1 m3
165 lit. Water including for curing 1000 litre
0.08 hr. Batching and mixing plant (UR) for batching
and mixing 1 hr.
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.
1.95 No Man for placing 1 Each
0.20 No Mason for placing 1 Each
0.20 hr. Vibrator (UR) 1 hr.
0.25 No. Man for curing 1 Each
% H.A
% OH
% CP
Total /m3
3 1 m3 Cement concrete M15 with 75mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.
200.00 Kg Cement 1 MT
0.39 m3 M sand / R sand 1 m
3
0.35 m3
75 mm coarse aggregate 1 m3
0.35 m3
40 mm coarse aggregate 1 m3
Note 5. If the placing of
concrete is done by
pump, instead of 1.95 No.
man for placing, add 0.04
hr. Concrete pump and
accessories for placing
concrete (UR) and 0.02
No. man for placing.
25
0.35 m3
40 mm coarse aggregate 1 m3
0.28 m3
20 mm coarse aggregate 1 m3
0.20 m3
12 mm coarse aggregate 1 m3
165.00 litre Water including for curing 1000 litre
0.08 hr.
Batching and mixing plant (UR) forbatching
and mixing 1 hr.
0.05 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.
1.95 No Man for placing 1 Each
0.20 No Mason for placing 1 Each
0.20 hr. Vibrator (UR) 1 hr.
0.25 No. Man for curing 1 Each
% HA
% OH
% CP
Total /m3
4 1 m3 Cement concrete M15 with 40mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.
230.00 Kg Cement 1 MT
0.43 m3 M sand / R sand 1 m
3
0.48 m3
40 mm coarse aggregate 1 m3
0.33 m3
20 mm coarse aggregate 1 m3
0.21 m3
12 mm coarse aggregate 1 m3
170.00 litre Water including for curing 1000 litre
0.08 hr.
Batching and mixing plant (UR) forbatching
and mixing 1 hr.
25
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.
1.95 No Man for placing 1 Each
0.20 No Mason for placing 1 Each
0.20 hr. Vibrator (UR) 1 hr.
0.25 No. Man for curing 1 Each
% H.A
% OH
% CP
Total /m3
5 1 m3 Cement concrete M15 with 20mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials, labour and conveyance
charges, etc. complete but excluding cost of
cement.
305.00 Kg Cement 1 MT
0.48 m3 M sand / R sand 1 m
3
0.57 m3
20 mm coarse aggregate 1 m3
0.26 m3
12 mm coarse aggregate 1 m3
215.00 litre Water including for curing 1000 litre0.08 hr. Batching and mixing plant (UR) forbatching 1 hr.
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.
26
placement ( up to 1 Km lead) 1 hr.1.95 No Man for placing 1 Each0.20 No Mason for placing 1 Each0.20 hr. Vibrator (UR) 1 hr.0.25 No. Man for curing 1 Each
% HA
% OH % CP
Total /m3
6 1 m3 Cement concrete M20 with 75mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.
245.00 Kg Cement 1 MT
0.38 m3 M sand / R sand 1 m
3
0.37 m3
75 mm coarse aggregate 1 m3
0.32 m3
40 mm coarse aggregate 1 m3
0.30 m3
20 mm coarse aggregate 1 m3
0.19 m3
12 mm coarse aggregate 1 m3
165.00 lit. Water including for curing 1000 litre
0.08 hr.
Batching and mixing plant (UR) forbatching
and mixing 1 hr.
0.05 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.
1.95 No Man for placing 1 Each
0.20 No Mason for placing 1 Each
0.20 hr. Vibrator (UR) 1 hr.
0.25 No. Man for curing 1 Each
% HA
% OH
26
% CP
Total /m3
7 1 m3 Cement concrete M20 with 40mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.
290.00 Kg Cement 1 MT
0.44 m3 M sand / R sand 1 m
3
0.44 m3
40 mm coarse aggregate 1 m3
0.28 m3
20 mm coarse aggregate 1 m3
0.21 m3
12 mm coarse aggregate 1 m3
195.00 lit. Water including for curing 1000 litre
0.08 hr.
Batching and mixing plant (UR) forbatching
and mixing 1 hr.
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.
1.95 No Man for placing 1 Each
0.20 No Mason for placing 1 Each
0.20 hr. Vibrator (UR) 1 hr.
0.25 No. Man for curing 1 Each
% H.A
% OH
27
% OH
% CP
Total /m3
8 1 m3 Cement concrete M20 with 20mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials, labour and conveyance
charges, etc. complete but excluding cost of
cement.
380.00 Kg Cement 1 MT
0.41 m3 M sand / R sand 1 m
3
0.49 m3
20 mm coarse aggregate 1 m3
0.37 m3
12 mm coarse aggregate 1 m3
240.00 litre Water including for curing 1000 litre
0.08 hr.
Batching and mixing plant (UR) forbatching
and mixing 1 hr.
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.
1.95 No. Man for placing 1 Each
0.20 No. Mason for placing 1 Each
0.20 hr. Vibrator (UR) 1 hr.
0.25 No. Man for curing 1 Each
% HA
% OH
% CP
Total /m3
27
9 1 m3 Cement concrete M20 with 12mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials, labour and conveyance
charges, etc. complete but excluding cost of
cement.
395.00 Kg Cement 1 MT
0.44 m3
M sand / R sand 1 m3
0.47 m3
12 mm coarse aggregate 1 m3
0.30 m3
6 mm coarse aggregate 1 m3
245.00 litre Water including for curing 1000 litre0.08 hr. Batching and mixing plant (UR) forbatching 1 hr.
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.1.95 No Man for placing 1 Each0.20 No Mason for placing 1 Each0.20 hr. Vibrator (UR) 1 hr.0.25 No. Man for curing 1 Each
% H.A
% OH % CP
Total /m3
10 1 m3 Cement concrete M25 with 40mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
28
cost of all materials and labour charges, etc.
complete but excluding cost of cement.
390.00 Kg Cement 1 MT
0.37 m3
M sand / R sand 1 m3
0.50 m3
40 mm coarse aggregate 1 m3
0.28 m3
20 mm coarse aggregate 1 m3
0.15 m3
12 mm coarse aggregate 1 m3
215.00 litre Water including for curing 1000 litre0.08 hr. Batching and mixing plant (UR) forbatching 1 hr.
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.1.95 No Man for placing 1 Each0.20 No Mason for placing 1 Each0.20 hr. Vibrator (UR) 1 hr.0.25 No. Man for curing 1 Each
% H.A
% OH % CP
Total /m3
11 1 m3 Cement concrete M25 with 20mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials, labour and conveyance
charges, etc. complete but excluding cost of
cement.
430.00 Kg Cement 1 MT
0.38 m3 M sand / R sand 1 m
3
0.52 m3
20 mm coarse aggregate 1 m3
0.34 m3
12 mm coarse aggregate 1 m3
240.00 litre Water including for curing 1000 litre
0.08 hr. Batching and mixing plant (UR) forbatching 1 hr.
28
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.1.95 No Man for placing 1 Each0.20 No Mason for placing 1 Each0.20 hr. Vibrator (UR) 1 hr.0.25 No. Man for curing 1 Each
% H.A
% OH % CP
Total /m3
12 1 m3 Cement concrete M30 with 40mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.
405.00 Kg Cement 1 MT
0.38 m3 M sand / R sand 1 m
3
0.53 m3
40 mm coarse aggregate 1 m3
0.26 m3
20 mm coarse aggregate 1 m3
0.14 m3
12 mm coarse aggregate 1 m3
220.00 litre Water including for curing 1000 litre
0.08 hr.
Batching and mixing plant (UR) forbatching
and mixing 1 hr.
0.08 hr. Transit mixer (UR) for conveyance to site of
29
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.
1.95 No Man for placing 1 Each
0.20 No Mason for placing 1 Each
0.20 hr. Vibrator (UR) 1 hr.
0.25 No. Man for curing 1 Each
% HA
% OH
% CP
Total /m3
13 1 m3 Cement concrete M30 with 20mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials, labour and conveyance
charges, etc. complete but excluding cost of
cement.
435.00 Kg Cement 1 MT
0.45 m3 M sand / R sand 1 m
3
0.54 m3
20 mm coarse aggregate 1 m3
0.36 m3
12 mm coarse aggregate 1 m3
220.00 litre Water including for curing 1000 litre
0.08 hr.
Batching and mixing plant (UR) forbatching
and mixing 1 hr.
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.
1.95 No Man for placing 1 Each
0.20 No Mason for placing 1 Each
0.20 hr. Vibrator (UR) 1 hr.
0.25 No. Man for curing 1 Each
% HA
% OH
29
% CP
Total /m3
14 1 m3 Cement concrete M35 with 40mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.
420.00 Kg Cement 1 MT
0.36 m3
M sand / R sand 1 m3
0.51 m3
40 mm coarse aggregate 1 m3
0.27 m3
20 mm coarse aggregate 1 m3
0.14 m3
12 mm coarse aggregate 1 m3
225.00 litre Water including for curing 1000 litre0.08 hr. Batching and mixing plant (UR) forbatching 1 hr.
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.1.95 No Man for placing 1 Each0.20 No Mason for placing 1 Each0.20 hr. Vibrator (UR) 1 hr.0.25 No. Man for curing 1 Each
% HA % OH % CP
Total /m3
30
15 1 m3 Cement concrete M35 with 20mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials, labour and conveyance
charges, etc. complete but excluding cost of
cement.
445.00 Kg Cement 1 MT
0.47 m3
M sand / R sand 1 m3
0.54 m3
20 mm coarse aggregate 1 m3
0.31 m3
12 mm coarse aggregate 1 m3
215.00 litre Water including for curing 1000 litre
0.08 hr.
Batching and mixing plant (UR) forbatching
and mixing 1 hr.
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.1.95 No Man for placing 1 Each0.20 No Mason for placing 1 Each0.20 hr. Vibrator (UR) 1 hr.0.25 No. Man for curing 1 Each
% HA % OH % CP
Total /m3
16 1 m3 Cement concrete M40 with 12mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials, labour and conveyance
charges, etc. complete but excluding cost of
cement.
450.00 Kg Cement 1 MT
0.32 m3 M sand / R sand 1 m
3
0.92 m3
12 mm coarse aggregate 1 m3
30
205.00 litre Water including for curing 1000 litre
0.08 hr.
Batching and mixing plant (UR) forbatching
and mixing 1 hr.
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.
1.95 No Man for placing 1 Each
0.20 No Mason for placing 1 Each
0.20 hr. Vibrator (UR) 1 hr.
0.25 No. Man for curing 1 Each
% HA % OH
% CP
Total /m3
17 1 m3 No-sand cement concrete 1:8 with 40mm
graded aggregates laying to lines and levels
at all elevations, consolidating, curing,
including cost of all materials and labour
charges, etc. complete but excluding cost of
cement.
280.00 Kg Cement 1 MT
0.60 m3
40 mm coarse aggregate 1 m3
0.40 m3
20 mm coarse aggregate 1 m3
175.00 litre Water including for curing 1000 litre
Batching and mixing plant (UR) forbatching
31
0.08 hr.
Batching and mixing plant (UR) forbatching
and mixing 1 hr.
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.
1.95 No Man for placing 1 Each
0.20 No Mason for placing 1 Each
0.20 hr. Vibrator (UR) 1 hr.
0.25 No. Man for curing 1 Each
% HA
% OH
% CP
Total /m3
18 1 m3 Second stage concrete (with specified mixes)
at all elevations without disturbing the lines
and levels of embedded parts, proper
consolidating, curing, including cost of all
materials, labour and conveyance charges,
etc. complete but excluding cost of cement.
1 m3
Cement concrete charges
10 %Provision for less efficiency @ 10% of above
Total /m3
19 1 m3 Cement concrete M20 with 20mm graded
aggregates for pre-cast slab laying the same
to lines and levels at all elevations,
consolidating, curing, including cost of all
materials, labour and conveyance charges,
formwork etc. complete but excluding cost of
cement.
380.00 Kg Cement 1 MT
31
0.41 m3 M sand / R sand 1 m
3
0.49 m3
20 mm coarse aggregate 1 m3
0.37 m3
12 mm coarse aggregate 1 m3
240.00 litre Water including for curing 1000 litre
0.08 hr. Batching and mixing plant (UR) forbatching
and mixing 1 hr.
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.
1.95 No Man for placing 1 Each
0.20 No Mason for placing 1 Each
0.20 hr. Vibrator (UR) 1 hr.
0.25 No. Man for curing 1 Each
10 %
Provision for formwork, conveying and
laying the slabs, etc. @ 10% of total above
% HA
% OH
% CP
Total /m3
20 1 m3 Plum cement concrete M10 with 40mm
graded aggregates (60%), over plumming of
broken rubbles of size 10 -23 cm (40%),
laying to lines and levels at all elevations,
consolidating, curing, including cost of all
32
consolidating, curing, including cost of all
materials and labour charges, etc. complete
but excluding cost of cement.
0.60 m3 Cement concrete M10 MSA 40 1 m
3
0.40 m3 Rubble 1 m
3
0.60 No. Man for conversion, laying, etc. 1 Each
% HA
% OH
% CP
Total /m3
32
21 1 m3 Cement concrete 1:1.5:3 using 20mm
nominal size aggregate, laying to lines and
levels at all elevations, consolidating, curing,
including cost of all materials and labour
charges, etc. complete but excluding cost of
cement.
432.00 Kg Cement 1 MT
0.45 m3 M sand / R sand 1 m
3
0.90 m3 20 mm coarse aggregate 1 m
3
260.00 litre Water including for curing 1000 litre
0.20 No Mason 1 Each
1.00 No Man 1 Each
3.50 No Man/Women including watering 1 Each
% HA
% OH
% CP
Total /m3
22 1 m3 Cement concrete 1:2:4 using 20mm nominal
size aggregate, laying to lines and levels at
all elevations, consolidating, curing,
including cost of all materials and labour
charges, etc. complete but excluding cost of
cement.
330.00 Kg Cement 1 MT
33
330.00 Kg Cement 1 MT
0.45 m3 M sand / R sand 1 m
3
0.90 m3 20 mm coarse aggregate 1 m
3
198.00 litre Water including for curing 1000 litre
0.20 No Mason 1 Each
1.00 No Man 1 Each
3.50 No Man/Women including watering 1 Each
% HA
% OH
% CP
Total /m3
23 1 m3 Cement concrete 1:3:6 using 40mm nominal
size aggregate, laying to lines and levels at
all elevations, consolidating, curing,
including cost of all materials and labour
charges, etc. complete but excluding cost of
cement.
228.00 Kg Cement 1 MT
0.48 m3 M sand / R sand 1 m
3
0.95 m3 40 mm coarse aggregate 1 m
3
137.00 litre Water including for curing 1000 litre
0.10 No Mason 1 Each
1.00 No Man 1 Each
1.40 No Man/Women including watering 1 Each
% HA
% OH
% CP
Total /m3
33
24 1 m3 Cement concrete 1:4:8 using 40mm nominal
size aggregate, laying to lines and levels at
all elevations, consolidating, curing,
including cost of all materials and labour
charges, etc. complete but excluding cost of
cement.
171.00 Kg Cement 1 MT
0.48 m3 M sand / R sand 1 m
3
0.95 m3 40 mm coarse aggregate 1 m
3
103.00 litre Water including for curing 1000 litre
0.10 No Mason 1 Each
1.00 No Man 1 Each
1.40 No Man/Women including watering 1 Each
% HA
% OH
% CP
Total /m3
25 1 m2 Shotcreting with 9mm graded aggregates
thickness of 50mm in one layer, laying to
lines and levels at all elevations,
consolidating, curing, including cost of all
materials and labour charges, etc. complete
but excluding cost of cement.
Data for 1m3
588.00 Kg Cement 1 MT
* Note for item nos.
25&26. the percentage of
wastage allowance for
rebound may be taken
accordingly as, (i) for
floor/slabs - 5-15%
(ii) for sloping and
vertical walls - 15-30%
(iii) for overhead work -
25-50%.
34
588.00 Kg Cement 1 MT
0.125 m3 9mm aggregate 1 m
3
0.125 m3 6mm aggregate 1 m
3
0.75 m3 M sand / R sand 1 m
3
225.00 litre Water including for curing 1000 litre
* % Wastage allowance for rebound @ __% of
above
0.08 hr. Batching and mixing plant (UR) forbatching
and mixing 1 hr.
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.
2.00 hrs. Shotcreting charges (UR) 1 hr.
0.25 No. Man for curing 1 Each
10 % Provision for surface cleaning, scaffolding,
admixtures, sundries, etc. @ 10% of total
above
% HA
% OH
% CP
Total
Hence rate per m2
for 50 mm thickness
divided by 20
/20 /m2
Hence rate per m2
for 100 mm thickness
divided by10/10
/m2
26 1 m2 Guniting to average thickness of 50mm in
one layer, laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.
25-50%.
34
Data for 1m3
588.00 Kg Cement 1 MT
1.00 m3 M sand / R sand 1 m
3
225.00 litre Water including for curing 1000 litre
* % Wastage allowance for rebound @ ___% of
above
0.08 hr. Batching and mixing plant (UR) forbatching
and mixing 1 hr.
0.08 hr. Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead) 1 hr.
2.00 hrs. Guniting charges (UR) 1 hr.
0.25 No. Man for curing 1 Each
10 % Provision for surface cleaning, scaffolding,
admixtures, sundries, etc. @ 10% of total
above
% HA
% OH
% CP
Total
Hence rate per m2
for 50 mm thickness /20 /m2
27 1 m2 Supplying, furnishing and installing chain
link / welded mesh for shotcreting/guniting
wherever required at all elevations including
cost of all materials and labour charges, etc.
35
cost of all materials and labour charges, etc.
complete.
1.00 m2 Cost of chain link/welded mesh 1 m
2
0.04 No. Black smith 1 Each
0.01 No. Man 1 Each
20 % Cost of pin, scaffolding, drilling, cutting,
placing, etc. @ 20% above
% HA
% OH
% CP
Total /m2
28 1 MT Supply and usage of cement at site including
cost of cement, conveyance charge, storage
arrangements, charges for stacking and re-
stacking if nescessery, etc. complete.
1 MT Cost of cement at site 1 MT
5 % Charges for stacking/ re-stacking, storage
arrangements, etc. @5 % of above item
Total /MT
29 1 litre Supply and usage of admixture at site
including cost of admixture, conveyance
charge, storage arrangements if nescessery
etc. complete.
1 litre Cost of admixture at site(MR) 1 litre
5 % For conveyance and mixiang charges etc.
Total /litre
35
Sl.
NoDescription of items Rate Amount Remarks
A. STONE MASONRY
1 1 m3 Random rubble masonry in CM 1:5 for
foundation and basement including cost of
all materials, conveyance, labour charges,
etc. complete as per specifications.
Note: Cost of cement may
be included in the item or
excluded and measured
as a separate item.
1.00 m3 Blasted rubble 1 m
3
0.30 m3 River sand / M sand 1 m
3
86.00 Kg Cement 1 MT
0.70 No. Rubble mason 1 Each
1.05 No. Man 1 Each
% HA
% OH
% CP
Total /m3
2 1 m3 Random rubble masonry in CM 1:6 for
foundation and basement including cost of
all materials, conveyance, labour charges,
etc. complete as per specifications.
1.00 m3 Blasted rubble 1 m
3
0.30 m3 River sand / M sand 1 m
3
72.00 Kg Cement 1 MT
0.70 No. Rubble mason 1 Each
1.05 No. Man 1 Each
% HA
% OH
% CP
Total /m3
3 1 m3 Dry rubble masonry for foundation and
basement including cost of all materials,
conveyance, labour charges, etc. complete as
per specifications.
1.05 m3 Blasted rubble 1 m
3
0.80 No. Rubble mason 1 Each
0.70 No. Man 1 Each
% HA
% OH
% CP
Total /m3
4 1 m3 For superstructure above foundation and
basement of Random rubble masonry/ Dry
rubble masonry
Add to corresponding items of work in
foundation and basement
Quantity Unit
CHAPTER VII
MASONRY WORKS
36
15 % Labour required for foundation and basement
( includes hire charges of scaffolding
materials etc.)
% HA
% OH
% CP
Total /m3
5 1 m3 Rubble pitching/ Rough stone dry packing to
lines and levels including cost of all
materials, conveyance, labour charges, etc.
complete as per specifications.
1.05 m3 Blasted rubble 1 m
3
0.35 No. Rubble mason 1 Each
1.40 No. Man 1 Each
% HA
% OH
% CP
Total /m3
6 1 m3 Quarry rubbish backing for revetment
including cost of all materials, labour charges
etc. complete as per specifications.
1.05 m3 Blasted rubble 1 m
3
0.70 No. Man 1 Each
% HA
% OH
% CP
Total /m3
B. LATERITE MASONRY
7 1 m3 Laterite masonry in CM 1:5 for foundation
and basement including cost of all materials,
conveyance, labour charges, etc. complete as
per specifications.
60.00 No. Laterite stones roughly dressed
(44x24x14cm) 100No.
0.16 m3 River sand / M sand 1 m
3
46.00 Kg Cement 1 MT
1.50 No. Laterite/ Brick mason 1 Each
0.85 No. Man 1 Each
% HA
% OH
% CP
Total /m3
Quantity of Laterite stone
of size 35x20x20 cm -
65 Nos 35x20x14 cm -
90 Nos.
37
8 1 m3 Laterite masonry in CM 1:6 for foundation
and basement including cost of all materials,
conveyance, labour charges, etc. complete as
per specifications.
60.00 No. Laterite stones roughly dressed
(44x24x14cm)100
No.
0.16 m3 River sand / M sand 1 m
3
38.00 Kg Cement 1 MT
1.50 No. Laterite/ Brick mason 1 Each
0.85 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m3
9 1 m3 For superstructure in ground floor upto 5m
height
Add to the corresponding items of work in
foundation and basement
15 % Labour required for foundation and basement
( includes hire charges of scaffolding
materials)
% HA
% OH
% CP
Total /m3
10 1 m3 For superstructure in first floor upto 5m
height or in each successive floors upto 5m
height in each floor
Add to the corresponding items of work in
superstructure ground floor or previous
floors
15 % Labour required for foundation and basement
( includes hire charges of scaffolding
materials)
% HA
% OH
% CP
Total /m3
11 1 m3 Laterite masonry in CM 1:5 for flat, semi
circular segmental arch work including cost
of all materials, conveyance, labour charges,
etc. complete as per specifications.
63.00 No. Laterite stones roughly dressed
(44x24x14cm)100
No.
0.16 m3 River sand 1 m
3
46.00 Kg River sand / M sand 1 MT
2.00 No. Laterite/ Brick mason 1 Each
0.94 No. Man 1 Each
2.0 % Scafolding,centering etc complete ( 2 % of
labour)
% HA
% OH
% CP
Total /m3
38
12 1 m3 Laterite masonry in CM 1:5 for well lining,
cornices, copings etc. including cost of all
materials, conveyance, labour charges, etc.
complete as per specifications.
63.00 Nos. Laterite stones roughly dressed
(44x24x14cm)100
No.
0.16 m3 River sand / M sand 1 m
3
46.00 Kg Cement 1 MT
2.00 No. Laterite/ Brick mason 1 Each
1.44 No. Man 1 Each
2.0 % Scafolding,centering etc complete ( 2 % of
labour)
% HA
% OH
% CP
Total /m3
C. BRICK WORK
13 1 m3 Brick work in cement mortar 1:5 with wire
cut bricks for foundation and basement
including cost of all materials, conveyance,
labour charges, etc. complete as per
specifications.
500.00 No. Wire cut bricks (19cmx9cmx9cm) 1000 No.
0.20 m3 River sand / M sand 1 m
3
58.00 Kg Cement 1 MT
0.70 No. Brick mason 1 Each
1.05 No. Man 1 Each
% HA
% OH
% CP
Total /m3
14 1 m3 Brick work in cement mortar 1:5 with
country burnt bricks for foundation and
basement including cost of all materials,
conveyance, labour charges, etc. complete as
per specifications.
500.00 No. Country burnt bricks(19cmx9cmx9cm) 1000 No.
0.24 m3 River sand / M sand 1 m
3
69.00 Kg Cement 1 MT
0.70 No. Brick mason 1 Each
1.05 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m3
15 1 m3 Brick work in cement mortar 1:6 with wire
cut bricks for foundation and basement
including cost of all materials, conveyance,
labour charges, etc. complete as per
specifications.
39
500.00 No. Wire cut bricks (19cmx9cmx9cm) 1000 No.
0.20 m3 River sand / M sand 1 m
3
49.00 Kg Cement 1 MT
0.70 No. Brick mason 1 Each
1.05 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m3
16 1 m3 Brick work in cement mortar 1:6 with
country burnt bricks for foundation and
basement including cost of all materials,
conveyance, labour charges, etc. complete as
per specifications.
500.00 No. Country burnt bricks(19cmx9cmx9cm) 1000 No.
0.24 m3 River sand / M sand 1 m
3
58.00 Kg Cement 1 MT
0.70 No. Brick mason 1 Each
1.05 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m3
17 1 m3 For superstructure in ground floor upto 5m
height
Add to the corresponding items of work in
foundation and basement
15 % Labour required for foundation and basement
( includes hire charges of scaffolding
materials)
% HA
% OH
% CP
Total /m3
18 1 m3 For superstructure in first floor upto 5m
height or in each successive floors upto 5m
height in each floor
Add to the corresponding items of work in
superstructure ground floor or previous
floors
15 % Labour required for foundation and basement
( includes hire charges of scaffolding
materials)
% HA
% OH
% CP
Total /m3
40
19 1 m3 Brick work in cement mortar 1:5 with wire
cut bricks for flat, semicircular or segmental,
arch works, etc. including cost of all
materials, conveyance, labour charges, etc.
complete as per specifications.
525.00 No. Wire cut bricks (19cmx9cmx9cm) 1000 No.
0.20 m3 River sand / M sand 1 m
3
58.00 Kg Cement 1 MT
1.12 No. Brick mason 1 Each
1.66 No. Man 1 Each
2 % Scafolding,centering etc complete ( 2 % of
labour)
% HA
% OH
% CP
Total /m3
D. CEMENT BLOCK MASONRY
20 1 m3 Cement solid/hollow block work in cement
mortar 1:5 for foundation and basement
including cost of all materials, conveyance,
labour charges, etc. complete as per
specifications.
55.00 No. Cement blocks (40cmx20cmx20cm) 100 No.
0.15 m3 River sand / M sand 1 m
3
43.00 Kg Cement 1 MT
1.50 No. Laterite/ Brick mason 1 Each
0.85 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m3
21 1 m3 Cement solid/hollow block work in cement
mortar 1:6 for foundation and basement
including cost of all materials, conveyance,
labour charges, etc. complete as per
specifications.
55.00 No. Cement blocks (40cmx20cmx20cm) 100 No.
0.15 m3 River sand / M sand 1 m
3
36.00 Kg Cement 1 MT
1.50 No. Laterite/ Brick mason 1 Each
0.85 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m3
22 1 m3 For superstructure in ground floor upto 5m
height
Add to the corresponding items of work in
foundation and basement
41
15 % Labour required for foundation and basement
( includes hire charges of scaffolding
materials)
% HA
% OH
% CP
Total /m3
23 1 m3 For superstructure in first floor upto 5m
height or in each successive floors upto 5m
height in each floor
Add to the corresponding items of work in
superstructure ground floor or previous
floors
15 % Labour required for foundation and basement
( includes hire charges of scaffolding
materials)
% HA
% OH
% CP
Total /m3
42
Sl.
NoDescription of items Rate Amount Remarks
A. PLASTERING
1 1 m2 Plastering with CM 1:3, 9mm thick including
cost of all materials, conveyance, labour
charges, etc. complete.
Note: Cost of cement may
be included in the item or
excluded and measured
as a separate item.
0.01 m3
River sand/Msand 1 m3
4.30 Kg Cement 1 MT
0.09 No. Mason 1 Each
0.165 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
2 1 m2 Plastering with CM 1:3, 12 mm thick
including cost of all materials, conveyance,
labour charges, etc. complete.
0.014 m3 River sand/Msand 1 m
3
6.60 Kg Cement 1 MT
0.09 No. Mason 1 Each
0.165 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
3 1 m2 Plastering with CM 1:3, 15 mm thick
including cost of all materials, conveyance,
labour charges, etc. complete.
0.015 m3 River sand/Msand 1 m
3
7.20 Kg Cement 1 MT
0.09 No. Mason 1 Each
0.165 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
4 1 m2 Plastering with CM 1:4, 12 mm thick
including cost of all materials, conveyance,
labour charges, etc. complete.
0.015 m3 River sand/Msand 1 m
3
5.40 Kg Cement 1 MT
0.09 No. Mason 1 Each
0.17 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
Quantity Unit
CHAPTER VIII
PLASTERING AND POINTING
43
5 1 m2 Plastering with CM 1:4, 15 mm thick
including cost of all materials, conveyance,
labour charges, etc. complete.
0.017 m3 River sand/M sand 1 m
3
5.90 Kg Cement 1 MT
0.09 No. Mason 1 Each0.17 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
6 1 m2 Plastering with CM 1:5, 12 mm thick
including cost of all materials, conveyance,
labour charges, etc. complete.
0.015 m3 River sand/M sand 1 m
3
4.30 Kg Cement 1 MT
0.09 No. Mason 1 Each
0.17 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
7 1 m2 Plastering with CM 1:5, 15 mm thick
including cost of all materials, conveyance,
labour charges, etc. complete.
0.017 m3 River sand/Msand 1 m
3
4.80 Kg Cement 1 MT
0.09 No. Mason 1 Each
0.17 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
8 1 m2 Plastering with CM 1:6,12 mm thick
including cost of all materials, conveyance,
labour charges, etc. complete.
0.015 m3 River sand/Msand 1 m
3
3.60 Kg Cement 1 MT
0.09 No. Mason 1 Each
0.17 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
9 1 m2 Plastering with CM 1:6, 15 mm thick
including cost of all materials, conveyance,
labour charges, etc. complete.
0.017 m3 River sand/Msand 1 m
3
4.00 Kg Cement 1 MT
0.09 No. Mason 1 Each
0.17 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
44
10 1 m2 Add to cement plastering items for plastering
with neat cement flushing coat
2.20 Kg Cement 1 MT
0.05 No. Mason 1 Each
% HA
% OH
% CP
Total /m2
11 1 m2 Add to cement plastering items for use of
coloured cement flushing coat
2.20 Kg Add the excess value of coloured cement 1 MT
% HA
% OH
% CP
Total /m2
12 1 m2 Add to cement plastering items for thread
lining to plastered surface
0.02 No. Mason 1 Each
% HA
% OH
% CP
Total /m2
13 1 m2 For plastering works in first floor upto 5m
height or in each successive floors upto 5m
height in each floor
Add to the corresponding plastering items of
work in ground floor or previous floors
15 % Labour required for plastering works (
includes hire charges of scaffolding
materials)
% HA
% OH
% CP
Total /m2
14 1 m2 Providing boarder 75mm wide and 15mm
thick in CM 1:3 including cost of all
materials, conveyance, labour charges, etc.
complete.
0.001 m3 River sand/Msand 1 m
3
0.60 Kg Cement 1 MT
0.05 No. Mason 1 Each
0.011 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
45
15 1 m2 Clearing and removal of old plaster from
walls including racking out joints clearing
the surface for replaster including disposal of
debris within 150m.
0.05 No. Mason 1 Each
0.019 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
B. POINTING
16 1 m2 Pointing brick work with CM 1:3 including
cost of all materials, conveyance, labour
charges, etc. complete.
0.003 m3 River sand/M sand 1 m
3
1.325 Kg Cement 1 MT
0.08 No. Mason 1 Each
0.11 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
17 1 m2 Pointing brick work with CM 1:4 including
cost of all materials, conveyance, labour
charges, etc. complete.
0.003 m3 River sand/M sand 1 m
3
1.00 Kg Cement 1 MT
0.08 No. Mason 1 Each
0.11 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
18 1 m2 Pointing Random rubble masonry with CM
1:2 including cost of all materials,
conveyance, labour charges, etc. complete.
0.003 m3 River sand/M sand 1 m
3
1.858 Kg Cement 1 MT
0.08 No. Mason 1 Each
0.11 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
19 1 m2 Pointing Random rubble masonry with CM
1:3 including cost of all materials,
conveyance, labour charges, etc. complete.
0.003 m3 River sand/M sand 1 m
3
1.325 Kg Cement 1 MT
46
0.08 No. Mason 1 Each
0.11 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
20 1 m2 Pointing Random rubble masonry with CM
1:4 including cost of all materials,
conveyance, labour charges, etc. complete.
0.003 m3 River sand/M sand 1 m
3
1.00 Kg Cement 1 MT
0.08 No. Mason 1 Each
0.11 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
21 1 m2 Pointing Laterite masonry with CM 1:3
including cost of all materials, conveyance,
labour charges, etc. complete.
0.001 m3 River sand/M sand 1 m
3
0.662 Kg Cement 1 MT
0.04 No. Mason 1 Each
0.019 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
22 1 m2 Pointing Laterite masonry with CM 1:4
including cost of all materials, conveyance,
labour charges, etc. complete as per
specification.
0.002 m3 River sand/M sand 1 m
3
0.5 Kg Cement 1 MT
0.04 No. Mason 1 Each
0.019 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
23 1 m2 Pointing Cement block masonry with CM 1:3
including cost of all materials, conveyance,
labour charges, etc. complete.
0.001 m3 River sand/M sand 1 m
3
0.53 Kg Cement 1 MT
0.08 No. Mason 1 Each
0.11 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
47
24 1 m2 Pointing Cement block masonry with CM 1:4
including cost of all materials, conveyance,
labour charges, etc. complete.
0.001 m3 River sand/M sand 1 m
3
0.4 Kg Cement 1 MT
0.08 No. Mason 1 Each
0.11 No. Man/Woman 1 Each
% HA
% OH
% CP
Total /m2
48
Sl.
No.Description of item Rate Amount Remarks
A. CEMENT WORKS
1 1 m² White cement washing one coat for new
surface including cost and conveyance of all
materials, labour charges, etc. complete.
Note: Cost of cement may
be included in the item or
excluded and measured
as a separate item.
0.148 Kg White cement 1 Kg
0.012 No. Special mazdoor 1 Each
0.009 No. Man 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
2 1 m² White cement washing two coats for new
surface including cost and conveyance of all
materials, labour charges, etc. complete.
0.248 Kg White cement 1 Kg
0.02 No. Special mazdoor 1 Each
0.015 No. Man 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
3 1 m² Cement washing one coat for new surface
including cost and conveyance of all
materials, labour charges, etc. complete.
0.148 Kg Cement 1 MT
0.012 No. Special mazdoor 1 Each
0.009 No. Man 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
4 1 m² Cement washing two coats for new surface
including cost and conveyance of all
materials, labour charges, etc. complete.
0.248 Kg Cement 1 MT
0.02 No. Special mazdoor 1 Each
0.015 No. Man 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
Quantity Unit
CHAPTER IX
WHITE WASHING AND PAINTING
49
5 1 m² Cement washing one coat for old surface
including cost and conveyance of all
materials, labour charges, etc. complete.
0.1 Kg Cement 1 MT
0.008 No. Special mazdoor 1 Each
0.006 No. Man 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
6 1 m² Cement washing two coats for old surface
including cost and conveyance of all
materials, labour charges, etc. complete.
0.20 Kg Cement 1 MT
0.016 No. Special mazdoor 1 Each
0.012 No. Man 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
7 1 m² Painting with one coat of primer of approved
quality on new / old surface after cleaning,
including cost and conveyance of all
materials, labour charges, etc. complete.
0.10 litre Wall Primer 1 litre
0.04 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
8 1 m² Finishing new surface with cement water
proof paint of approved quality and color,
one coat including cost and conveyance of all
materials, labour charges, etc. complete.
0.19 Kg Cement water proof paint 1 Kg
0.03 No. Painter 1 Each
0.04 No. Man 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
50
9 1 m² Finishing new surface with cement water
proof paint of approved quality and color,
two coats including cost and conveyance of
all materials, labour charges, etc. complete.
0.32 Kg Cement water proof paint 1 Kg
0.05 No. Painter 1 Each
0.07 No. Man 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
10 1 m² Finishing old surface with cement water
proof paint of approved quality and color,
one coat including cost and conveyance of all
materials, labour charges, etc. complete.
0.14 Kg Cement water proof paint 1 Kg
0.025 No. Painter 1 Each
0.025 No. Man 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
11 1 m² Finishing old surface with cement water
proof paint of approved quality and color,
two coats including cost and conveyance of
all materials, labour charges, etc. complete.
0.28 Kg Cement water proof paint 1 Kg
0.05 No. Painter 1 Each
0.05 No. Man 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
12 1 m² Finishing new surface with distemper of
approved quality and color, one coat
including smoothening with sand paper, cost
and conveyance of all materials, labour
charges, etc. complete.
0.10 Kg Distemper 1 Kg
0.03 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
51
13 1 m² Finishing new surface with distemper of
approved quality and color, two coats
including smoothening with sand paper, cost
and conveyance of all materials, labour
charges, etc. complete.
0.15 Kg Distemper 1 Kg
0.05 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
14 1 m² Finishing old surface with distemper of
approved quality and color, one coat
including smoothening with sand paper, cost
and conveyance of all materials, labour
charges, etc. complete.
0.06 Kg Distemper 1 Kg
0.025 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
15 1 m² Finishing old surface with distemper of
approved quality and color, two coats
including smoothening with sand paper, cost
and conveyance of all materials, labour
charges, etc. complete.
0.11 Kg Distemper 1 Kg
0.045 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
16 1 m² Painting new surface with emulsion paint of
approved quality and color, one coat over a
coat of primer, after smoothening with sand
paper and cleaning the surface, including
cost and conveyance of all materials, labour
charges, etc. complete.
0.115 litre Emulsion paint 1 litre
0.10 litre Wall Primer 1 litre
0.155 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
52
17 1 m² Painting new surface with emulsion paint of
approved quality and color, two coats over a
coat of primer, after smoothening with sand
paper and cleaning the surface, including
cost and conveyance of all materials, labour
charges, etc. complete.
0.155 litre Emulsion paint 1 litre
0.10 litre Wall Primer 1 litre
0.195 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
18 1 m² Painting old surface with emulsion paint of
approved quality and colour, one coat, after
smoothening with sand paper and cleaning
the surface, including cost and conveyance of
all materials, labour charges, etc. complete.
0.04 litre Emulsion paint 1 litre
0.04 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
19 1 m² Painting old surface with emulsion paint of
approved quality and color, two coats, after
smoothening with sand paper and cleaning
the surface, including cost and conveyance of
all materials, labour charges, etc. complete.
0.08 litre Emulsion paint 1 litre
0.08 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
20 1 m² Painting new surface with emulsion paint of
approved quality and color, one coat over
over a coat of primer, after smoothening with
sand paper and finishing with wall putty,
including cost and conveyance of all
materials, labour charges, etc. complete.
0.10 litre Emulsion paint 1 litre
0.08 litre Wall Primer 1 litre
0.20 Kg Wall putty 1 Kg
0.155 No. Painter 1 Each
0.08 No. Man 1 Each
2 % Sundries, of total above
53
% HA
% OH
% CP
Total /m²
21 1 m² Painting new surface with emulsion paint of
approved quality and color, two coats over a
coat of primer, after smoothening with sand
paper and finishing with wall putty, including
cost and conveyance of all materials, labour
charges, etc. complete.
0.14 litre Emulsion paint 1 litre
0.08 litre Wall Primer 1 litre
0.20 Kg Wall putty 1 Kg
0.195 No. Painter 1 Each
0.08 No. Man 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
22 1 m² Painting old surface with emulsion paint of
approved quality and color, two coats over a
coat of primer, after smoothening with sand
paper and the cleaning surface, including
cost and conveyance of all materials, labour
charges, etc. complete.
0.08 litre Emulsion paint 1 litre
0.08 litre Wall Primer 1 litre
0.08 No. Painter 1 Each
0.08 No. Man 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
23 1 m² Painting old surface with emulsion paint of
approved quality and color, two coats over a
coat of primer, after smoothening with sand
paper and finishing with wall putty, including
cost and conveyance of all materials, labour
charges, etc. complete.
0.08 litre Emulsion paint 1 litre
0.08 litre Wall Primer 1 litre
0.20 Kg Wall putty 1 Kg
0.12 No. Painter 1 Each
0.08 No. Man 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
54
24 1 m² Painting new surface with black/ brown
japan paint of approved quality, one coat
after rubbing with sand paper and cleaning
the surface including cost and conveyance of
all materials, labour charges, etc. complete.
0.14 litre Black/ brown japan paint 1 litre
0.05 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
25 1 m² Painting new surface with black/ brown
japan paint of approved quality, two coats
after rubbing with sand paper and cleaning
the surface including cost and conveyance of
all materials, labour charges, etc. complete.
0.23 litre Black/ brown japan paint 1 litre
0.08 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
26 1 m² Painting old surface with black/ brown japan
paint of approved quality, one coat after
rubbing with sand paper and cleaning the
surface including cost and conveyance of all
materials, labour charges, etc. complete.
0.09 litre Black/ brown japan paint 1 litre
0.04 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
27 1 m² Painting old surface with black/ brown japan
paint of approved quality, two coats after
rubbing with sand paper and cleaning the
surface including cost and conveyance of all
materials, labour charges, etc. complete.
0.18 litre Black/ brown japan paint 1 litre
0.07 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
B. WOOD WORKS
55
28 1 m² Painting new wood surface with enamel paint
of approved quality and colour, two coats
over two coats of wood primer, after
smoothening with sand paper and cleaning
the surface, including cost and conveyance of
all materials, labour charges, etc. complete.
Note: Measurement area
may be taken as 1.
Wooden panelled or
framed - add 12.5% of
area fpr each side
2.Fully glazed - Deduct
50% of area for each
side.
0.115 litre Enamel paint 1 litre
0.14 litre Wood Primer 1 litre
0.18 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
29 1 m² Painting old wood surface with enamel paint
of approved quality and colour, two coats,
after smoothening with sand paper and
cleaning the surface, including cost and
conveyance of all materials, labour charges,
etc. complete.
0.095 litre Enamel paint 1 litre
0.095 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
30 1 m² Painting old wood surface with enamel paint
of approved quality and colour, one coat,
after rubbing with sand paper and cleaning
the surface including cost and conveyance of
all materials, labour charges, etc. complete.
0.05 litre Enamel paint 1 litre
0.05 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
C. STEEL WORKS
31 1 m² Painting new iron surface with priming coat
of approved quality one coat, after rubbing
with emery paper and cleaning the surface
including cost and conveyance of all
materials, labour charges, etc. complete.
Note: Measurement area
may be taken as -
guard bars, balustrades,
gates, gratings, grills,
cages, railings, braces,
rails, stays, etc. - Deduct
50% area for each side.
56
0.075 litre Iron primer 1 litre
0.04 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
32 1 m² Painting new iron surface with aluminium
paint of approved quality one coat including
cost and conveyance of all materials, labour
charges, etc. complete.
0.105 litre Aluminium paint 1 litre
0.025 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
33 1 m² Painting old iron surface with aluminium
paint of approved quality, one coat, after
smoothening with sand paper and cleaning
the surface, including cost and conveyance of
all materials, labour charges, etc. complete.
0.08 litre Aluminium paint 1 litre
0.025 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
34 1 m² Painting new iron surface with enamel/
epoxy/ similar paint of approved quality and
color two coats over a coat of iron primer,
after smoothening with sand paper and
cleaning the surface, including cost and
conveyance of all materials, labour charges,
etc. complete.
0.115 litre Enamel/ epoxy/ similar paint 1 litre
0.075 litre. Iron Primer 1 litre.
0.14 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
57
35 1 m² Painting old iron surface with enamel/ epoxy/
similar paints of approved quality and color
two coats, after smoothening with sand paper
and cleaning the surface, including cost and
conveyance of all materials, labour charges,
etc. complete.
0.095 litre Enamel/ epoxy/ similar paint 1 litre
0.095 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
36 1 m² Painting old iron surface with enamel/ epoxy/
similar paints of approved quality and color
one coat, after smoothening with sand paper
and cleaning the surface, including cost and
conveyance of all materials, labour charges,
etc. complete.
0.05 litre Enamel/ epoxy/ similar paint 1 litre
0.05 No. Painter 1 Each
2 % Sundries, of total above
% HA
% OH
% CP
Total /m²
58
Sl.
No.Description of item Rate Amount Remarks
1 1 m2 Providing and fixing wood pannelled door in
single leaf with frames of 100 x 70 mm (
with out sill) and shutters of frame 100 x 35
mm panel (four horizondals) with plank of
16mm thick including cost of all materias
and labour charges,etc.complete but
excluding cost of fittings
Note:
1. For I st floor, add 10
% of extra labour of
Ground floor
2. For II nd floor, add 20
% of extra labour of
Ground floor and so on
0.060 m3 Wood log 1 m
3 (If size of frame and
shutter varies, qty of
wood will vary)
0.60 No Sawyers 1 Each (10 nos per cum)
3.27 No Carpenter 1 Each (54 nos per cum)
0.36 No Man 1 Each (6 nos per cum)
0.015 m3 Cost of outerslabs at 25% of cost of wood
log value. 1 m3
% HA
% OH
% CP
Total /m2
2 1 m2 Providing and fixing wood pannelled
windows with frames of 100 x 70 mm and
shutters of frame 70 x 35 mm pannel with
plank of 16mm thick including cost of all
materials andl labour charges,etc.complete
but excluding cost of fittings , grills etc.
(If size of frame and
shutter varies, qty of
wood will vary)
0.085 m3 Wood log 1 m
3
0.85 No Sawyers 1 Each (10 nos per cum)
4.59 No Carpenter 1 Each (54 nos per cum)
0.51 No Man 1 Each (6 nos per cum)
0.021 m3 Cost of outerslabs at 25% of cost wood log
value 1 m3
% HA
% OH
% CP
Total /m2
3 1 m2 Providing and fixing glazed windows with
wooden frames of 100 x 70 mm and shutters
of wooden frame 70 x 35 mm panel with
glass panels including cost of all materials
and labour charges,etc.complete but
excluding cost of fittings , grills etc.
(If size of frame and
shutter varies, qty of
wood will vary)
0.077 m3
Wood log 1 m3
0.77 No Sawyers 1 Each (10 nos per cum)
4.16 No Carpenter 1 Each (54 nos per cum)
0.46 No Man 1 Each (6 nos per cum)
0.36 m2
Glass panels 1 m2
Quantity
CHAPTER X
DOORS, WINDOWS & VENTILATORS
Unit
Deduct
Deduct
59
0.019 m3 Cost of outerslabs at 25% of cost wood log
value1 m
3
% HA
% OH
% CP
Total /m2
4 1 m2 Providing and fixing glazed ventilator with
wooden frames of 100 x 70 mm and
louvered glass panes including cost of all
materials and labour charges,etc. complete
but excluding cost of fittings , etc.
(If size of frame and
shutter varies, qty of
wood will vary)
0.093 m3
Wood log m3
0.93 No Sawyers Each (10 nos per cum)
5.02 No Carpenter Each (54 nos per cum)
0.56 No Man Each (6 nos per cum)
0.70 m2
Glass panels m2
0.023 m3 Cost of outerslabs at 25% of cost wood log
value m3
% HA
% OH
% CP
Total /m2
5 1 dm3 Providing wood pieces for
doors,windows,ventilators,and other items of
suitable size and shape etc.
1.512 dm3
Wood log m3
0.015 No Sawyers Each
0.022 No Carpenter Each
0.012 No Man Each
0.399 dm3 Cost of outerslabs at 25% of cost wood log
value m3
% HA
% OH
% CP
Total /dm3
6 1 m2 Providing wooden planks of 12mm thick of
suitable size and shape after
planing,grooving etc.
(if thickness vary qty will
vary)
18.1 dm3
Wood log m3
0.46 No Sawyers Each
0.055 No Man Each
4.5 dm3 Cost of outerslabs at 25% of cost wood log
value m3
% HA
% OH
% CP
Total /m2
7 1 Kg Providing MS flats to windows and
ventilators including cutting,making
holes,etc. complete.
Deduct
Deduct
Deduct
Deduct
60
1.05 Kg Flat iron Qtl
0.05 No Black smith Each
0.008 No Man Each
% HA
% OH
% CP
Total /Kg
8 1 Kg Providing MS rods to windows and
ventuilators including cutting, etc. complete.
1.05 Kg M S rod Qtl
0.02 No Black smith Each
0.02 No Man Each
% HA
% OH
% CP
Total /Kg
9 1 Kg Fabricating, fixing steel windows including
frames and shutters, fixing arrangements and
fittings such as hinges, stoppers, closers etc.
but excluding glass panels.
1.05 Kg Cost of angles, flat, MS rods, etc (average
cost of angles, rods, flats) Qtl
20 % Fabrication charges, sundries etc ( 20 % of
above)
% OH
% CP
Total /Kg
10 1 m2 Supplying ang fixing glass panels for steel
windows icluding cost of all materials and
labour charges etc. complete.
1.00 m2
Glass m2
20 % For biniding materials, beadings, etc. ( 20 %
of above)
0.15 No Fitter Each
0.15 No Man Each
% HA
% OH
% CP
Total /m2
11 1 m2 Supplying and fitting PVC fully panelled
doors including cost of all fittings and
labour charges etc. complete.
3.50 m Square tubes m
0.86 m2 Shutter m
2
0.12 No Fabricator Each
0.12 No Man Each
5 % Cost of fittings ( 5 % of above total)
% HA
% OH
% CP
Total /m2
61
12 1 m2 Fabricating & fixing Anodised Aluminium
partialy glased single shutter door with 63
x 37 x 1.5 mm door frames and shutter
frames of size 45x45x1.5 mm at top ,middle
and side, 95x45x1.5mm aluminium
rectangular tube at bottom and providing
plain glass and hylam sheet ( equally
devided) for shutter including aluminium
clips and rubber beeding for fixing glass/
sheet, reinforcing with steel rod at top and
bottom of shutter including all materials and
fixing charges etc. but excluding cost of
fittings.
(if size of frame and
shutter varies, quantity of
Aluminium and glass will
vary)
1.95 Kg Aluminium tube for outer frame Kg
2.05 Kg Aluminium tube for sides, top and middle of
shutter Kg
0.53 Kg Aluminium tube for bottom of shutter Kg
0.39 m2 Hylam sheet(prelaminated sheet-12mm) m
2
0.39 m2
Glass m2
3.38 m Rubber beeding with clip m
0.54 No Aluminium fabricator Each
0.54 No Fitter Each
0.54 No Man Each
% HA
% OH
% CP
Total /m2
13 1 m2 Fabricating & fixing Anodised Aluminium
fully glazed double shutter door with 63 x
37 x 1.5 mm door frames and shutter frames
of size 45x45x1.5 mm at top ,middle and
side, 95x45x1.5mm aluminium rectangular
tube at bottom and providing thick plain
glass for shutter, including aluminium clips
and rubber beeding for fixing glass
reinforcing with steel rod at top and bottom
of shutter including all materials and fixing
charges etc. but excluding cost of fittings.
(if size of frame and
shutter varies, quantity of
Aluminium and glass will
vary)
1.72 Kg Aluminium tube for outer frame Kg
3.01 Kg Aluminium tube for sides, top and middle of
shutter Kg
0.53 Kg Aluminium tube for bottom of shutter m
0.74 m2
Glass m2
4.44 m Rubber beeding with clip m
0.55 No Aluminium fabricator Each
0.55 No Fitter Each
0.55 No Man Each
% HA
% OH
% CP
Total /m2
62
14 1 m2 Fabricating & fixing Anodised Aluminium
fully glazed window with aluminium tube
frames of 63 x 37 x 1.5 mm in size and
37x24x1.5 mm frame with glass as shutters
including all materials and fixing charges etc.
but excluding cost of fittings.
(if size of frame and
shutter varies, quantity of
Aluminium and glass will
vary)
3.40 Kg Aluminium tube for outer frame Kg
2.57 Kg Aluminium shutter frame Kg
0.71 m2
Glass m2
4.84 m Rubber beeding with clip m
0.58 No Aluminium fabricator Each
0.58 No Man Each
% HA
% OH
% CP
Total
15 1 m2 Fabricating & fixing Anodised Aluminium
fully glazed ventilator with Aluminium
sections 50 x 25 x 1.5 mm in size with 4mm
thick plain glass as shutters including cost of
all fittings such as aluminium stay , hooks,
hinges etc. complete.
4.45 Kg Aluminium tube for outer frame Kg
3.00 Kg Aluminium shutter frame Kg
0.88 m2
Glass m2
6.71 m Rubber beeding with clip m
1.11 No Aluminium fabricator Each
0.56 No Man Each
% HA
% OH
% CP
Total /m2
63
Sl.
No.Description of items Rate Amount Remarks
Internal work
1 1 m Supplying, laying and jointing 20mm
nominal dia. PVC pipes ( Kgf/cm²) and
specials such as tees, bends, elbows,
checknuts etc. including cutting and making
good the walls, etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 20mm dia. ( Kgf/cm²) 1 m
15 % Add for specials
0.67 No. Fitter 1 Each
0.67 No. Man mazdoor 1 Each
2 % Solvent cement and other sundries (2 % of
% HA
% OH
% CP
Total
Hence for 1m /30 /m
2 1 m Supplying, laying and jointing 25mm
nominal dia. PVC pipes ( Kgf/cm²) and
specials such as tees, bends, elbows,
checknuts etc. including cutting and making
good the walls, etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 25mm dia. (10Kgf/cm²) 1 m
15 % Add for specials
1.00 No. Fitter 1 Each
0.67 No. Man mazdoor 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
% CP
Total
Hence for 1m /30 /m
3 1 m Supplying, laying and jointing 32mm
nominal dia. PVC pipes ( Kgf/cm²) and
specials such as tees, bends, elbows,
checknuts etc. including cutting and making
good the walls, etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 32mm dia. ( Kgf/cm²) 1 m
15 % Add for specials
1.00 No. Fitter 1 Each
1.00 No. Man mazdoor 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
CHAPTER XI
WATER SUPPLY AND SANITARY WORKS
A. WATER SUPPLY WORKS
Quantity Unit
64
% HA
% OH
% CP
Total
Hence for 1m /30 /m
4 1 m Supplying, laying and jointing 40mm
nominal dia. PVC pipes (Kgf/cm²) and
specials such as tees, bends, elbows,
checknuts etc. with clamps including cutting
and making good the walls, painting the paint
two coats, etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 40mm dia. ( Kgf/cm²) 1 m
15 % Add for specials
1.00 No. Fitter 1 Each
1.33 No. Man mazdoor 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
% CP
Total
Hence for 1m /30 /m
5 1 m Supplying, laying and jointing 50mm
nominal dia. PVC pipes ( Kgf/cm²) and
specials such as tees, bends, elbows,
checknuts etc. including cutting and making
good the walls, etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 50mm dia. ( Kgf/cm²) 1 m
15 % Add for specials
1.33 No. Fitter 1 Each
1.33 No. Man mazdoor 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
% CP
Total
Hence for 1m /30 /m
6 1 m Supplying, laying and jointing 63mm
nominal dia. PVC pipes ( Kgf/cm²) and
specials such as tees, bends, elbows,
checknuts etc. including cutting and making
good the walls, etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 63mm dia. ( Kgf/cm²) 1 m
15 % Add for specials
1.33 No. Fitter 1 Each
1.33 No. Man mazdoor 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
65
% CP
Total
Hence for 1m /30 /m
7 1 m Supplying, laying and jointing 75mm
nominal dia. PVC pipes ( Kgf/cm²)
including cutting and making good the walls,
etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 75mm dia. ( Kgf/cm²) 1 m
15 % Add for specials
1.333 No. Fitter 1 Each
1.333 No. Man mazdoor 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
% CP
Total
Hence for 1m /30 /m
8 1 m Supplying, laying and jointing 90mm
nominal dia. PVC pipes ( Kgf/cm²)
including cutting and making good the walls,
etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 90mm dia. ( Kgf/cm²) 1 m
15 % Add for specials
1.333 No. Fitter 1 Each
1.333 No. Man mazdoor 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
% CP
Total
Hence for 1m /30 /m
9 1 m Supplying, laying and jointing 110mm
nominal dia. PVC pipes ( Kgf/cm²)
including cutting and making good the walls,
etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 110mm dia. ( Kgf/cm²) 1 m
15 % Add for specials
1.333 No. Fitter 1 Each
1.333 No. Man mazdoor 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
% CP
Total
Hence for 1m /30 /m
External work
66
10 1 m Supplying, laying and jointing 20mm
nominal dia. PVC pipes ( Kgf/cm²) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 20mm dia.(10Kgf/cm²) 1 m
5 % Add for specials
0.17 No. Fitter 1 Each
0.17 No. Man mazdoor 1 Each
1.50 No. Man mazdoors for trenching and refilling 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
% CP
Total
Hence for 1m /30 /m
11 1 m Supplying, laying and jointing 25mm
nominal dia. PVC pipes ( Kgf/cm²) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 25mm dia.( Kgf/cm²) 1 m
5 % Add for specials
0.25 No. Fitter 1 Each
0.25 No. Man mazdoor 1 Each
1.50 No. Man mazdoors for trenching and refilling 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
% CP
Total
Hence for 1m /30 /m
12 1 m Supplying, laying and jointing 32mm
nominal dia. PVC pipes ( Kgf/cm²) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete .
Details of cost for 30m.
30.00 m PVC pipes 32mm dia.(10Kgf/cm²) 1 m
5 % Add for specials
0.33 No. Fitter 1 Each
0.33 No. Man mazdoor 1 Each
1.50 No. Man mazdoors for trenching and refilling 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
% CP
Total
Hence for 1m /30 /m
67
13 1 m Supplying, laying and jointing 40mm
nominal dia. PVC pipes ( Kgf/cm²) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 40mm dia.( Kgf/cm²) 1 m
5 % Add for specials
0.33 No. Fitter 1 Each
0.33 No. Man mazdoor 1 Each
1.50 No. Man mazdoor for trenching and refilling 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
% CP
Total
Hence for 1m /30 /m
14 1 m Supplying, laying and jointing 50mm
nominal dia. PVC pipes ( Kgf/cm²) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 50mm dia.( gf/cm²) 1 m
5 % Add for specials
0.33 No. Fitters 1 Each
0.33 No. Man mazdoor 1 Each
1.50 No. Man mazdoor for trenching and refilling 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
% CP
Total
Hence for 1m /30 /m
15 1 m Supplying, laying and jointing 63mm
nominal dia. PVC pipes ( Kgf/cm²) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 63mm dia.( Kgf/cm²) 1 m
5 % Add for specials
0.33 No. Fitter 1 Each
0.33 No. Man mazdoor 1 Each
1.50 No. Man mazdoor for trenching and refilling 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
% CP
Total
Hence for 1m /30 /m
68
16 Supplying, laying and jointing 75mm
nominal dia. PVC pipes ( Kgf/cm²) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 75mm dia.(Kgf/cm²) 1 m
5 % Add for specials
0.33 No. Fitter 1 Each
0.33 No. Man mazdoor 1 Each
1.50 No. Man mazdoor for trenching and refilling 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
% CP
Total
Hence for 1m /30 /m
17 Supplying, laying and jointing 90mm
nominal dia. PVC pipes ( Kgf/cm²) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 90mm dia.(Kgf/cm²) 1 m
5 % Add for specials
0.33 No. Fitter 1 Each
0.33 No. Man mazdoor 1 Each
1.50 No. Man mazdoor for trenching and refilling 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
% CP
Total
Hence for 1m /30 /m
18 Supplying, laying and jointing 110mm
nominal dia. PVC pipes ( Kgf/cm²) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 110mm dia.( Kgf/cm²) 1 m
5 % Add for specials
0.330 No. Fitter 1 Each
0.330 No. Man mazdoor 1 Each
1.50 No. Man mazdoor for trenching and refilling 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
% CP
Total
Hence for 1m /30 /m
69
19 Supplying, laying and jointing 160mm
nominal dia. PVC pipes ( Kgf/cm²) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.
Details of cost for 30m.
30.00 m PVC pipes 160mm dia 1 m
5 % Add for specials
0.330 No. Fitter 1 Each
0.330 No. Man mazdoor 1 Each
1.50 No. Man mazdoor for trenching and refilling 1 Each
2 % Solvent cement and other sundries (2 % of
cost of PVC pipe)
% HA
% OH
% CP
Total
Hence for 1m /30 /m
20 1 Each Supplying and fixing European type
earthenware WC pan with trap and
Duroplastic seat with lid , 15 litres PVC low
level flush tank with all fittings, including
cutting and making good the walls and
floors, cost and conveyance of all materials,
labour charges, etc. complete.
1.00 No Earternware European type WC pan 1 Each
1.00 No Duroplastic seat cover 1 Each
1.00 No. PVC low level flush tank 15 litre capacity 1 Each
4.00 Kg Cement 1 MT
0.50 No Plumber 1 Each
0.50 No Mason 1 Each
1.00 No Man mazdoor 1 Each
1 % Sundries etc ( 1 % of above )
% HA
% OH
% CP
Total /Each
21 1 Each Supplying and fixing …….x……mm or
nearest size eartern ware wash hand basin
with fitting like CP angle cock,
couplings,nylone connections,bolts, etc.
including cutting and making good to the
wall etc. complete.
1.00 No. Wash hand basin 1 Each
1.00 No. 15 mm C.P. brass pillar tap 1 Each
1.00 No. 15 mm C.P. angle cock 1 Each
1.00 No. 15 mm C.P. waste coupling.(MR) 1 Each
1.00 No. 15 mm nylone connection 1 Each
1.00 No. 32mm PVC waste pipe heavy 1 Each
1.00 pair Brackets 1 pair
2.00 Kg Cement 1 MT
0.50 No Plumber 1 Each
B. SANITARY WORKS
70
0.50 No Mason 1 Each
1.00 No Man mazdoor 1 Each
2 % Sundries etc ( 2 % of above material)
% HA
% OH
% CP
Total /Each
22 1 Each Supplying and fixing Orissa pan water closet
with trap 'S' or 'P' including embedding the
closet and trap concrete and forming
squatting platform of suitable size plastered
over with cement mortar 1:3, cutting and
making good to the floors including cost and
conveyance of all materials, labour charges,
etc. complete.
1.00 No Orissa pan water closet 1 Each
1.00 No Trap 1 Each
5 % Provision for making platform, Sundries etc (
5 % of above material)
0.60 No Mason 1 Each
0.60 No Man mazdoor 1 Each
% HA
% OH
% CP
Total /Each
23 1 No Supplying and fitting sanitary fittings like
trap, cowl, mirror,soap dish, towel rail etc
including cost of all materials and labour
charges etc. complete
1 No Cost of trap/cowl etc
10 % fitting charges, sundries such as solvent,
plugs, etc. 10 % of above
% HA
% OH
% CP
Total /Each
71
Sl.
No.Description of item Rate Amount Remarks
1 1 m² Flooring with C.C.1:4:8, 75mm thick using
40mm nominal size aggregate and plastered
over with 12mm thick C.M.1:3 one coat
floated hard and trowelled smooth, including
cost of all materials and labour charges etc.
complete.
Note: Cost of cement may
be included in the item or
excluded and measured
as a separate item.
12.825 Kg Cement 1 MT
0.036 m³ M sand / River sand 1 m³
0.0713 m³ 40 mm coarse aggregate 1 m³
0.01 No Mason 1 Each
0.18 No Man 1 Each
% HA
% OH
% CP
1.00 m² Plastering with C.M.1:3, 12mm thick 1 m²
Total /m²
2 1 m² Flooring with C.C.1:4:8, 75mm thick using
40mm nominal size aggregate and plastered
over with 12mm thick C.M.1:3 one coat and
floated hard and trowelled smooth with neat
cement flushing coat including cost of all
materials and labour charges etc. complete.
1.00 m² Cost of 1m2
C.C.1:4:8 75mm thick with
12mm thick plasterin in C.M 1:3 1 m²
1.00 m² Cost of cement flushing coat 1 m²
Total /m²
3 1 m² Flooring with C.C.1:4:8, 75mm thick using
40mm nominal size aggregate and plastered
over with 12mm thick C.M.1:4 one coat and
floated hard and trowelled smooth with neat
cement flushing coat and thread lining
including cost of all materials, labour
charges, etc. complete.
1.00 m² Cost of 1m2
C.C.1:4:8 75mm thick with
12mm thick plasterin in C.M 1:3 including
flushing coat. 1 m²
1.00 m² Thread lining 1 m²
Total /m²
4 1 m² Floor plastering with C.M. 1:3, 12mm thick
one coat and floated hard and trowelled
smooth with neat cement flushing coat mixed
with red / black oxide, including cost of all
materials, labour charges, etc. complete.
Quantity Unit
CHAPTER XII
FLOORING
72
1.00 m² Plastering with C.M.1:3, 12mm thick 1 m²
1.00 m² Cost of cement flushing coat 1 m²
0.10 Kg Cost of red / black oxide powder 1 Kg
% OH
% CP
Total /m²
5.a 1 m² Supplying and paving Ceramic / Vitrified
tiles of approved quality, size and colour on
floors over C.M 1:6, 15mm thick and
flushing coat, pointing with coloured cement,
including cost of all materials and labour
charges etc. complete.
1.05 m² Ceramic / Vitrified tiles 1 m²
1.00 m² Plastering in C.M 1:6, 15mm thick 1 m²
0.48 Kg Cement 1 MT
0.15 No Tile paver 1 Each
0.09 No Man 1 Each
1 % Coloured cement, sundries, etc., 1 % of total
above
% HA
% OH
% CP
Total /m²
5.b 1 m² Supplying and Dadoing walls with Ceramic /
Vitrified tiles of approved quality, size and
colour over a cement flusing coat and
pointing with coloured cement, including
cost of all materials, labour charges etc.
complete.
1.05 m² Ceramic / Vitrified tiles 1 m²
1.00 m² Cement Flushing coat 1 m²
0.30 No Tile paver 1 Each
0.18 No Man 1 Each
1 % Coloured cement, sundries, etc., 1 % of total
above
% HA
% OH
% CP
Total /m²
6.a 1 m² Supplying and paving Marble slabs of
approved quality and colour on floors
overC.M.1:6, 15 mm thick and flushig coat,
pointing with coloured cement, polishing
with machine 3 coats to smooth finish and
wax polishing including cost of all materials,
labour charges, etc. complete.
1.05 m² Marble slabs 1 m²
1.00 m² Plastering in C.M 1:6, 15mm thick 1 m²
0.20 Kg Cement for flushing coat 1 MT
Labour for laying
0.20 No. Tile paver 1 Each
0.1000 No. Man 1 Each
1 % Coloured cement, sundries, etc., 1 % of total
above
Labour for polishing
73
0.40 No. Spl. Mazdoor for polishing 1 Each
0.20 No. Man 1 Each
5.00 % Polishing machine, stones, etc.( 5 % of total
above)
0.01 Kg Mansion polish 1 Kg
% HA
% OH
% CP
Total /m²
6.b 1 m² Supplying and Dadoing walls with Marble
slabs of approved quality and colour over
cement flushing coat and polishing with
machine 3 coats to smooth finish, pointing
with coloured cement and wax polishing,
including cost of all materials, labour charges
etc. complete.
1.05 m² Marble slabs 1 m²
1.00 m² Cement flusging coat 1 m²
Labour for laying
0.30 No. Tile paver 1 Each
0.2000 No. Man 1 Each
1 % Coloured cement, sundries, etc., 1 % of total
above
Labour for polishing
0.40 No. Spl. Mazdoor for polishing 1 Each
0.20 No. Man 1 Each
5.00 % Polishing machine, stones, etc.( 5 % of total
above)
0.01 Kg Mansion polish 1 Kg
% HA
% OH
% CP
Total /m²
7.a 1 m² Supplying, paving and polishing Marble
tiles of approved quality and colour on floors
over C.M.1:6, 15mm thick and flushing coat
and polishing with machine 3 coats to
smooth finish,pointing with coloured cement
and wax polishing, including cost of all
materials and labour charges etc. cement.
1.05 m² Marble tiles 1 m²
1.00 m² Plastering in C.M 1:6, 15mm thick 1 m²
0.20 Kg Cement for flushing coat 1 MT
Labour for laying
0.10 No. Tile paver 1 Each
0.05 No. Man 1 Each
1 % Coloured cement, sundries, etc., 1 % of total
above
Labour for polishing
0.40 No. Spl. Mazdoor for polishing 1 Each
0.20 No. Man 1 Each
5.00 % Polishing machine, stones, etc.( 5 % of total
above)
0.01 Kg Mansion polish 1 Kg
74
% HA
% OH
% CP
Total /m²
7.b 1 m² Supplying and Dadoing walls with Marble
tiles of approved quality and colour over
cement flushing coat and polishing with
machine 3 coats to smooth finish, pointing
with coloured cement and wax polishing,
including cost of all materials, labour charges
etc. complete.
1.05 m² Marble tiles 1 m²
1.00 m² Cement flusging coat 1 m²
Labour for laying
0.15 No. Tile paver 1 Each
0.088 No. Man 1 Each
1 % Coloured cement, sundries, etc., 1 % of total
above
Labour for polishing
0.60 No. Spl. Mazdoor for polishing 1 Each
0.20 No. Man 1 Each
0.01 Kg Mansion polish 1 Kg
% HA
% OH
% CP
Total /m²
8.a 1 m² Supplying and paving Granite slabs of
approved quality and colour on floors
overC.M.1:6, 15 mm thick and flushig coat,
pointing with coloured cement, including
cost of all materials, labour charges, etc.
complete.
1.05 m² Granite slabs 1 m²
1.00 m² Plastering in C.M 1:6, 15mm thick 1 m²
0.20 Kg Cement for flushing coat 1 MT
Labour for laying
0.20 No. Tile paver 1 Each
0.10 No. Man 1 Each
1 % Coloured cement, sundries, etc., 1 % of total
above
% HA
% OH
% CP
Total /m²
75
8.b 1 m² Supplying and Dadoing walls with Granite
slabs of approved quality and colour over
cement flushing coat , pointing with
coloured cement ,including cost of all
materials, labour charges etc. complete.
1.05 m² Granite slabs 1 m²
1.00 m² Cement flusging coat 1 m²
Labour for laying
0.30 No. Tile paver 1 Each
0.20 No. Man 1 Each
1 % Coloured cement, sundries, etc., 1 % of total
above
% HA
% OH
% CP
Total /m²
9.a 1 m² Supplying, paving and polishing Granite
tiles of approved quality and colour on floors
over C.M.1:6, 15mm thick and flushing coat
,pointing with coloured cement , including
cost of all materials and labour charges etc.
cement.
1.05 m² Granite tiles 1 m²
1.00 m² Plastering in C.M 1:6, 15mm thick 1 m²
0.20 Kg Cement 1 MT
Labour for laying
0.10 No. Tile paver 1 Each
0.05 No. Man 1 Each
1 % Coloured cement, sundries, etc., 1 % of total
above
% HA
% OH
% CP
Total /m²
9.b 1 m² Supplying and Dadoing walls with Granite
tiles of approved quality and colour over
cement flushing coat , pointing with
coloured cement ,including cost of all
materials, labour charges etc. complete.
1.05 m² Granite tiles 1 m²
1.00 m² Cement flusging coat 1 m²
Labour for laying
0.20 No. Tile paver 1 Each
0.10 No. Man 1 Each
1 % Coloured cement, sundries, etc., 1 % of total
above
% HA
% OH
% CP
Total /m²
10 1 m² Supplying and Fixing PVC / Vinyl sheet
flooring of approved make including cost of
all materials, labour charges, etc. complete.
76
1.05 m² PVC / Vinyl flooring sheet 1 m²
0.03 No. Special Mazdoor 1 Each
0.03 No. Man 1 Each
5.00 % Adhesives, sundries, etc., of total above
% HA
% OH
% CP
Total /m²
77
Sl.
No.Description of item Rate Amount Remarks
1 1 Kg Fabricating supplying and installing steel
roof truss, purlins etc using MS angles, plates
etc. including cost of all materials, labour
charges ,painting with two coats of synthetic
enamel paint over a coat of iron primer etc
complete
1.05 Kg Cost of MS angles, plates , etc ( Average
cost) 1 Qtl
0.002 litre Iron primer 1 litre
0.005 litre Synthetic enamel paint 2 litre
1 No Welding Rod 100 No
0.02 No Blacksmith 1 m3
0.013 No Heavy load Mazdoor 1 Each
0.003 No Fitter 1 Each
0.01 NoWelder
1 Each
0.003 NoPainter
1 Each
10 % Erection charge, hire for welding plant,
grinding stone, current charge etc ( 1 % of
cost of steel materials)
% HA
% OH
% CP
Total /Kg
2 1 Kg Fabricating supplying and installing steel
roof truss, purlins etc using pipes / hollow
section pipes etc. including cost of all
materials, labour charges ,painting with two
coats of synthetic enamel paint over a coat of
iron primer etc complete
1.05 Kg Cost of pipe 1 Qtl
0.002 litre Iron primer 1 litre
0.005 litre Synthetic enamel paint 2 litre
1.00 No Welding Rod 100 No
0.014 No Blacksmith 1 Each
0.009 No Heavy load Mazdoor 1 Each
0.002 No Fitter 1 Each
0.01 No Welder 1 Each
0.003 No Painter 1 Each
10 % Erection charge, hire for welding plant,
grinding stone, current charge etc ( 1 % of
cost of steel materials)
% HA
% OH
% CP
Total /Kg
Quantity Unit
CHAPTER XIII
ROOFING
78
3 1 m2 Roofing with GI corrugated sheet for roofs,
shades including all fittngs like nuts and
bolts, clambs, J -bolts, including cost all
materials, labour charges, etc. complete.
8.60 kg GI corrugated sheet 1 MTWt. considered for 0.8mm
thick sheet. Wt. may be
varied according to the
thickness of sheet
considered.
2.20 No GI hooks with bolt and nuts 1 Each
10 % Sundries, scaffolding etc ( 10 % of cost of
sheet)
0.135 No Fitter 1 Each
0.135 No Man 1 Each
% HA `
% OH
% CP
Total /m2
4 1 m2 Roofing with AC corrugated sheet for roofs,
shades including all fittings like nuts and
bolts, clambs ,J -bolts, including cost all
materials, labour charges etc. complete
1.15 m2 AC Corrugated sheet 1 m
2
1.4 No GI hooks with bolt and nuts 1 Each
10 % Sundries, scaffolding etc ( 10 % of cost of
sheet)
0.16 No Fitter 1 Each
0.16 No Man 1 Each
% HA `
% OH
% CP
Total /m2
5 1 m Providing AC Ridge with all fittings
including cost of all materials, labour charges
etc. complete.
1.03 Pair AC Ridge 1 pair
0.05 No Carpenter 1 Each
0.05 No Man 1 Each
% HA
% OH
% CP
Total /m
6 1 m2 Roofing with MP Ist class tiles for roofs,
shades etc including cost of all materials,
labour charges etc. complete.
16 No MP Tiles 1000 No
10 % Sundries, scaffolding etc ( 10 % of cost of
sheet)
0.035 No Mason 1 Each
0.035 No Man 1 Each
% HA `
% OH
% CP
Total /m2
79
7 1 m Providing MP Hip and Ridge tiles, pointing
with Cement Mortar 1:6 including cost of all
materials, labour charges, etc complete.
2.7 No MP Hip and Ridge tiles 1000 No
0.020 m3 Sand 1 m
3
0.72 kg Cement 1 MT
0.08 No Mason 1 Each
0.05 No Man 1 Each
% HA `
% OH
% CP
Total /m
80
Sl.
No.Description of item Rate Amount Remarks
1 1 m2 Sectioning upto 150mm and forming the
surface of new roads
0.05 No. Man
% HA
% OH
% CP
Total /m2
2 1 m2 Sectioning upto 150mm and forming the
surface of old roads
0.025 No. Man
% HA
% OH
% CP
Total /m2
3 1 m³ Collection and supply of 60mm IRC size
hard granite broken stone including stacking
on road side in standard profiles for
measurements, etc. complete.
1 m³ 60mm broken stone 1 m³
0.18 No. Man for stacking
% HA
% OH
% CP
Total /m³
4 1 m³ Collection and supply of 36mm IRC size
hard granite broken stone including stacking
on road side in standard profiles for
measurements, etc. complete.
1 m³ 36mm broken stone 1 m³
0.18 No. Man for stacking
% HA
% OH
% CP
Total /m³
5 1 m³ Collection and supply of 60mm & 36mm
(7:3) IRC size hard granite broken stone
including stacking on road side in standard
profiles for measurements, etc. complete.
0.70 m³ 60mm broken stone 1 m³
0.30 m³ 36mm broken stone 1 m³
0.18 No. Man for stacking
% HA
% OH
% CP
Total /m³
CHAPTER XIV
ROAD WORKS
Quantity Unit
81
6 1 m³ Collection and supply of 12mm IRC size
hard granite broken stone including stacking
on road side in standard profiles for
measurements, etc. complete.
1 m³ 12mm broken stone 1 m³
0.18 No. Man for stacking
% HA
% OH
% CP
Total /m³
7 1 m³ Collection and supply of 6mm IRC size hard
granite broken stone including stacking on
road side in standard profiles for
measurements, etc. complete.
1 m³ 6mm broken stone 1 m³
0.18 No. Man for stacking
% HA
% OH
% CP
Total /m³
8 1 m³ Collection and supply of good quality red
earth including stacking on road side in
standard profiles for measurements, etc.
complete.
1 m³ Red earth 1 m³
0.12 No. Man for stacking
% HA
% OH
% CP
Total /m³
9 1 m³ Collection and supply of quarry dust
including stacking on road side in standard
profiles for measurements, etc. complete.
1 m³ Quarry dust 1 m³
0.10 No. Man for stacking
% HA
% OH
% CP
Total /m³
82
10 1 m² Metalling the roadway, 100mm spread
thickness compacted to 75mm using
departmental broken stones (grade in the
ratio of 7:3 of 60mm and 36mm sizes) 1m³
per 10m² and departmental blinding
materials 0.20m³ per 10m², bed rolling,
spreading broken stones to template, rolling
dry to compaction from sides to centre until
the movement of broken stones cease,
watering profusely and rolling until the fines
cream up and fill the voids of the stones, then
spreading the gravelly earth and sweeping
into the joints, watering and rerolling until
the gravelly earth has worked into all the
crevises and only a thin coat of slurry
remains, then take off the roller and allow to
set to harden for 24 hours and any deformity
is rectified, including fencing, lighting,
watching and maintaining the surface free of
ruts for 15 days after completion including
hire charges of power roller, all labour
charges, etc. complete for W.B.M.Sub base
course.
(Daily out-turn of roller 840m²)
0.117 No. Man for spreading broken stones and
blinding materials 1 Each
0.067 No. Woman for spreading broken stones and
blinding materials and watering 1 Each
0.022 litre Diesel for roller 1 litre
2 % Sundries(such as fencing, lighting, watching,
etc.)2 % of total of above
0.0012 day Hire charges for power roller 1 day
% HA
% OH
% CP
Total /m2
83
11 1 m² Metalling the roadway, 100mm spread
thickness compacted to 75mm using 36mm
departmental broken stones, 1m³ per 10m²
and departmental blinding materials 0.15m³
per 10m², bed rolling, spreading broken
stones to template, rolling dry to compaction
from sides to centre until the movement of
broken stones cease, watering profusely and
rolling until the fines creame up and fill the
voids of the stones, then spreading the
gravelly earth and sweeping into the joints,
watering and rerolling untiluntil the fines
cream up and fill the voids of the stones, the
gravelly earth has worked into all the
crevises and only a thin coat of slurry
remains, then take off the roller and allow to
set to harden for 24 hours and any deformity
is rectified, including fencing, lighting,
watching and maintaining the surface free of
ruts for 15 days after completion including
hire charges of power roller, all labour
charges, etc. complete for W.B.M. base
course.
(Daily out-turn of roller 840m²)
0.117 No. Man for spreading broken stones and
blinding materials 1 Each
0.067 No. Woman for spreading broken stones and
blinding materials and watering 1 Each
0.022 litre Diesel for roller 1 litre
2 % Sundries(such as fencing, lighting, watching,
etc.)2 % of total of above
0.0012 day Hire charges for power roller 1 day
% HA
% OH
% CP
Total /m2
84
12 1 m² Remetalling the roadway with departmental
broken stones and blinding materials (new
broken stones supplied at 0.50m³ for 10m²
and blinding materials at 0.12m³ for 10m²)
including picking the old metalled surface
for a minimum depth of 50mm, sectioning,
spreading the new broken stones to template,
rolling dry to compaction from sides to
centre until the movement of broken stones
cease, watering profusely and rolling until
fines creame up and fill the voids of the the
stones, then spreading the gravelly earth and
sweeping into the joints, watering and
rerolling until the gravelly earth has worked
into all the crevises and only a thin coat of
slurry remains, then take off the roller and
allow to set to harden for 24 hours and any
deformity is rectified, including fencing,
lighting, watching and maintaining the
surface free of ruts for 15 days after
completion including hire charges of power
roller, all labour charges, etc. complete for
W.B.M. base course.
(Daily out-turn of roller 840m²)
0.035 No. Man for spreading metal and blinding
material 1 Each
0.035 No. Woman for spreading broken stones and
blinding materials and watering 1 Each
0.026 No. Man 1 Each
0.022 litre Diesel for roller 1 litre
2 % Sundries(such as fencing, lighting, watching,
etc.)2 % of total of above
0.0012 day Hire charges for power roller 1 day
% HA
% OH
% CP
Total /m2
13 1 m³ Providing bitumen levelling course with
60mm departmental broken stone by
spreading the broken stone to lines and levels
and rolling until the compacted course
aggregate has a firm surface and applying hot
bitumen with pressure sprayer @
16.33Kg/m³ of aggregates including cost of
bitumen, all conveyance, heating, mixing,
spreading in appropriate locations to proper
levels, compacting with power roller and all
other sundry expenses.
85
Daily out-turn of roller 45m³
0.50 No. Special mazdoor 1 Each
0.25 No. Woman 1 Each
0.65 litre Kerosene 1 litre
0.20 litre Diesel 1 litre
2 % Sundries, of total of above
0.011 day Hire for power roller 1 day
0.011 day Hire for boiler and sprayer 1 day
0.033 day Hire for wheel barrows 1 day
16.33 Kg Cost of bitumen 80/100 1 MT
% HA
% OH
% CP
Total /m³
14 1 m³ Providing bitumen levelling course with
36mm departmental broken stone by
spreading the broken stone to lines and levels
and rolling until the compacted course
aggregate has a firm surface and applying hot
bitumen with pressure sprayer @ 20Kg/m³ of
metal including cost of bitumen, all
conveyance, heating, mixing, spreading in
appropriate locations to proper levels,
compacting with power roller and all other
sundry expenses.
Daily out-turn of roller 45m³
1.00 No. Special mazdoor 1 Each
0.50 No. Woman 1 Each
0.80 litre Kerosine 1 litre
0.40 litre Diesel 1 litre
2 % Sundries, of total of above
0.022 day Hire for power roller 1 day
0.022 day Hire for boiler and sprayer 1 day
0.066 day Hire for wheel barrows 1 day
20.00 Kg Cost of bitumen 80/100 1 MT
% HA
% OH
% CP
Total /m³
15 1 m³ Providing bitumen pre-mix levelling course
with 12mm departmental broken stone by
spreading the pre-mix (formed of 1m3
loose
broken stone mixed with 48Kg of bitumen)
to lines and levels, rolling to dense surface,
including cost of bitumen, all conveyance,
heating, mixing, compacting with power
roller, other sundry expenses, etc. complete.
Daily out-turn of roller 22.20m³
3.75 No. Special mazdoor 1 Each
1.50 No. Woman 1 Each
4.00 litre Kerosene for heating aggregates 1 litre
2.00 litre Kerosene for heating bitumen 1 litre
0.82 litre Diesel for roller 1 litre
1.50 litre Diesel for H.M.plant 1 litre
86
2 % Sundries, of total of above
0.045 day Hire for power roller 1 day
0.045 day Hire for boiler and sprayer 1 day
0.045 day Hire for H.M.plant 1 day
0.135 day Hire for wheel barrows 1 day
48.00 Kg Cost of bitumen 80/100 1 MT
% HA
% OH
% CP
Total /m³
16 1 m² Providing 20mm pre-mixed chipping carpet
over W.B.M. surface with departmental
broken stone after cleaning the base and
applying a priming coat of 7.50Kg of
bitumen per 10m² and spreading the hot pre-
mix (formed of 0.27m³ of departmental
12mm broken stone and 12.96Kg of bitumen
per 10m²) rolling to dense surface, then
spreading the seal coat (comprising of a hot
premix of 0.09m³ of 6mm departmental
broken stone and 8.64Kg of bitumen per
10m² again rolling including the cost of
bitumen, oil and fuel, hire of bass brooms,
camber board, roller and other machineries,
watching, lighting and other charges, etc.
complete. (Total usage of bitumen is
29.10Kg per 10m²)
Daily out-turn of roller 840m²
0.075 No. Special mazdoor 1 Each
0.030 No. Woman 1 Each
0.108 litre Kerosene for heating aggregates 1 litre
0.116 litre Kerosene for heating bitumen 1 litre
0.022 litre Diesel for roller 1 litre
0.040 litre Diesel for H.M.plant 1 litre
2 % Sundries(such as fencing, lighting, watching,
etc.)2 % of total of above
0.0012 day Hire for power roller 1 day
0.0012 day Hire for boiler and sprayer 1 day
0.0012 day Hire for H.M.plant 1 day
0.0036 day Hire for wheel barrows 1 day
2.9100 Kg Cost of bitumen 80/100 1 MT
% HA
% OH
% CP
Total /m2
87
17 1 m² Providing 20mm pre-mixed chipping carpet
over existing black topped surface with
departmental broken stone after cleaning the
base and applying a priming coat of 5.00Kg
of bitumen per 10m² and spreading the hot
pre-mix (formed of 0.27m³ of departmental
12mm metal and 12.96Kg of bitumen per
10m²) rolling to dense surface, then
spreading the seal coat (comprising of a hot
premix of 0.09m³ of 6mm departmental
metal and 8.64Kg of bitumenper 10m²) again
rolling including the cost of bitumen, oil and
fuel, hire of bass brooms, camber board,
roller and other machineries, watching,
lighting and other charges, etc. complete.
(Total usage of bitumen is 26.60Kg per
10m²)
Daily out-turn of roller 840m²
0.075 No. Special mazdoor 1 Each
0.030 No. Woman 1 Each
0.108 litre Kerosene for heating aggregates 1 litre
0.116 litre Kerosene for heating bitumen 1 litre
0.022 litre Diesel for roller 1 litre
0.040 litre Diesel for H.M.plant 1 litre
2 % Sundries(such as fencing, lighting, watching,
etc.)2 % of total of above
0.0012 day Hire for power roller 1 day
0.0012 day Hire for boiler and sprayer 1 day
0.0012 day Hire for H.M.plant 1 day
0.0036 day Hire for wheel barrows 1 day
2.66 Kg Cost of bitumen 80/100 1 MT
% HA
% OH
% CP
Total /m2
18 1 m² Providing heavy seal coat using 6mm
departmental broken stone @ 0.09m³/10m²
with hot bitumen @ 8.64Kg/10m² including
hire charges for power roller, spreading, etc
complete.
0.075 No. Special mazdoor 1 Each
0.016 litre Diesel for roller 1 litre
0.340 Kg Cost of fire wood 1 MT
2 % Sundries, of total of above
0.001 day Hire for power roller 1 day
0.864 Kg Cost of bitumen 80/100 1 MT
% HA
% OH
% CP
Total /m2
19 1 m2 Trimming, dressing and sectioning the road
berms including labour charges, etc.
complete as per the direction of departmental
officers.
88
0.02 No. Man 1 Each
% HA
% OH
% CP
Total /m2
20 1 No Supplying and fixing guard stones 20x20x90
cms size of pre-cast reinforced cement
concrete M15 using 20mm graded
aggregates, fixed in base concrete
45x45x45cms size of M10 using 40mm
graded aggregates, laying to lines and levels
at all elevations, consolidating, curing and
painting with two coats of emulsion paint in
alternate bands of black and white colour
over a coat of priming coat including cost of
all materials and labour charges etc.
complete.
Note: Cost of cement may
be included in the item or
excluded and measured
as a separate item.
30 Kg Cement 1 MT
0.05 m3 M sand / R sand 1 m
3
0.08 m3
40 mm coarse aggregate 1 m3
0.03 m3
20 mm coarse aggregate 1 m3
0.02 No Mason 1 Each
0.12 No Man 1 Each
0.24 No Woman 1 Each
0.44 m2 Form work 1 m
2
0.52 m2 Painting 1 m
2
5 % Provision for excavation, cost of water,
conveyance of post, etc. @ 5% of above
% HA
% OH
% CP
Total /Each
89
Sl.
No.Description of items Rate Amount Remarks
1 1 m3 Driving the tunnel in rock as per approved
cross sections to lines and levels including
all the required operations like drilling,
blasting using modern explosives, mucking,
scaling, etc. and removing and depositng the
excavated materials(muck) at designated
places including all leads and lifts, cost of
all materials, machinery, fuel, labour,
lighting, ventilation, water supply,
compressed air, dewatering, etc. complete as
per specifications and as directed by the
departmental officers.
Note:
1 .This data may be used
for up to 4 m (Excavated
diameter) .
2 . Above 4m dia
(excavated diameter),
less 10% of rate of
driving Tunnel.
3 . A lead of 1 km is
considered. Add
0.06hour, for every
additional km lead, of
Tipper use rate per m3
.
4 . Cost of cement may be
included in the item or
excluded and measured
as a separate item.
Excavated diameter of Tunnel m
Cross sectional Area0.00 m
2
Average pull (if not specified, take as 1.2m) 1.20 m
CHAPTER XV
TUNNEL AND SURGE
A. TUNNEL WORKS
Quantity Unit
90
Average pull (if not specified, take as 1.2m) 1.20 m
Excavated quantity per cycle m3
Average depth of holes to be drilled 1.50 m
Number of holes including dummy (if not
specified, take 5.77 Nos per sq:m)
No.
Total depth of drilling m
Average output of Jack hammer per hour 7.50 m
Number of hours required hrs
1.Material charges
m Drill bit 1 Each life 150 m
5 % Extra for sharpening @ 5% of above
Kg Gelatine (0.45 kg per hole)25 Kg
0 Nos Delay detonators ( 85% number of holes) 1 No.
10 % Other petty consumables, wires, etc. @ 10%
of above two items
10 % Provision for pipe lines for air and water,
electric lines, fixtures, scaffoldings, wire
ropes, safety items, conveyance charges, etc.
@ 10% of above items
Total
Total Material charges per m3
2.Labour charges for 10 m3 ( D - Shape )
Note: For other shapes,
add 10% of extra labour
0.77 No. Foreman 1 Each
0.77 No. Supervisor 1 Each
0.77 No. Fitter1 Each
90
0.77 No. Blaster 1 Each
0.77 No. Electrician 1 Each
0.77 No. Special mazdoor 1 Each
3.08 No. Helper for cleaning holes, scaling, etc. 1 Each
40 % Difficult work allowance
% Hill allowance
Total
Total Material charges per m3
3.Machinery charges per m3
( D - Shape )
hr Jack Hammer 1 hr
0.32 hr Loader - 0. 5 cum 1 hr
0.64 hr Tipper 1 hr
0.91 hr Ventilation blower 1 hr
Total
Total Material charges per m3
4.Shop charges per m3
5 % Machine shop, Structural shop, Steel metal
shop, Air and water pipe shop, Carpentary
shop etc. @ 10% of machinery charges
Total shop charges per m3
5.Maintenance charges per m3
Note: For other shapes,
add 10 % extra
machinery charges
91
5.Maintenance charges per m
0.125 No. Man for maintenance of electrical line, water
line, air line, etc.
1 Each
40 % Difficult work allowance of labour
% Hill allowance
Total Maintenance charges per m3
Total 1 to 5 (A)
6.Electric and Water charges
5 % Electric, Water and Dewatering charges @
5% of (A)
7.Spare Charges
5 % Jack hammer, ventilation blower, water line,
air line, cables, bulbs, pumps etc. @ 5% of
(A)
8.Uninterrupted Power Supply Charges
3 % Maintenance of diesel generator, acessories,
etc. @ 3% of (A)
9.Insurance Charges
2 % Machines, equipments, labour, etc @ 2% of
(A)
10.Maintenance of haul roads
3 % Haul roads @ 3% of (A)
% OH
% CP
Total
Rate per 1m3 of driving tunnel /m
3
91
2 1 m3 Driving the tunnel as per approved cross
sections to lines and levels in weak rock
strata including all the required operations
like drilling, blasting using modern
explosives, mucking, scaling, etc. and
removing and depositng the excavated
materials(muck) at designated places
including all leads and lifts, cost of all
materials, machinery, fuel, labour, lighting,
ventilation, water supply, compressed air,
dewatering, etc. complete as per
specifications and as directed by the
departmental officers.
Rate per 1m3 of driving tunnel
20 % Add 20% of the above
Total /m3
3 1 m3 Mucking loose and jointed rock fallen due to
weak nature of rock in tunnel and depositing
the muck at designated areas including all
leads and lifts, machinery, fuel, labour,
lighting, ventilation, dewatering, etc.
complete as per the direction of departmental
officers.
92
0.05 No. Foreman 1 Each
0.20 No. Man for scaling, etc. 1 Each
0.10 hr. Loader ( 0.5 m3) for loading 1 hr.
0.20 hr. Dumper for conveyance (UR) 1 hr.
5 % Shop, maintenance, electric, water, spare
charges, etc. @ 5% of above items
% HA
% OH
% CP
Total /m3
4 1 m3 Cement concrete (M20MSA40) for lining of
tunnel invert portion including cost of all
materials, form work, labour, conveying,
laying, vibrating , curing etc, complete
Invert may be considered
as: 1 . For D-shape -
level upto which circular
portion starts. 2 . For
circular shape - bottom
half
1.Materials and Labour charges
1 m3 Cost of CCM20 MSA40 1 m
3 Concrete mix may be
suitably taken
0.35 No. Extra man due to inefficiency in conveying
concrete
1 Each
0.1 No. Extra mason due to inefficiency in placing
concrete
1 Each
40 % Difficult work allowance
% HA on
0.3 hr Ventilation blower 1 Hr
Total
Total material and labour charges per m3
(A)
92
2.Extra lead
5 % Extra lead (up to 1 km) @ 5% of (A)
3.Form work
10 % Formwork, scaffolding etc @ 10% of (A)
4.Electric and Water charges
5 % Electric, Water and Dewatering charges @
5% of (A)
5.Spare Charges, maintanance etc
3 % water line, air line, cables, bulbs, pumps etc.
@ 3% of (A)
6.Uninterrupted Power Supply Charges
3 % Maintenance of diesel generator, acessories,
etc. @3% of (A)
% OH
% CP
Total
Rate per 1m3 of lining /m
3
5 1 m3 Cement concrete (M20MSA40) for lining of
tunnel overt portion including cost of all
materials, form work, labour, conveying,
laying, vibrating , curing etc, complete.
1.Materials and Labour charges
1 m3 Cost of CCM20 MSA40
1 m3
Concrete mix may be
suitably taken
0.35 No. Extra man due to inefficiency in conveying 1 Each
Note: Add 5% for every
additional km.
93
0.35 No. Extra man due to inefficiency in conveying
concrete
1 Each
40 % Difficult work allowance
% HA on
4.50 m2 Steel Form work 1 m
2
50 % Add Extra for designed shape (50 % of
above Item)
0.30 hr Ventilation blower 1 hr
Total
Total material and labour charges per m3
(A)
2.Extra lead
5 % Extra lead (up to 1 km) @ 5% of (A)
3.Extra for form work, scaffolding etc
5 % Moving rail platform formwork, scaffolding
etc @ 5% of (A)
4.Extra for placing
5 % Extra fror placing etc @ 5% of (A)
5.Electric and Water charges
5 % Electric, Water and Dewatering charges @
5% of (A)
6.Spare Charges, maintanance etc
3 % water line, air line, cables, bulbs, pumps etc.
@ 3% of (A)
7.Uninterrupted Power Supply Charges
3 % Maintenance of diesel generator, acessories,
etc. @ 3% of (A)
% OH
% CP
Total
Rate per 1m3
of lining /m3
Note: Add 5% for every
additional km.
Note: Form work for
tunnel lining of more
than 4m finished
diameter, add 20% extra
of the normal rate
93
6 1 m3 Driving of pilot shaft in rock of approved
cross section to lines and levels including all
the required operations using modern
explosives and machine drilling, lighting,
ventilation, water supply, dewatering,
compressed air etc and depositing the
excavated material(muck) in the dumpyard
or at designated places including all leads
and lifts, cost of all materials, machinery,
fuel and labour etc complete.
Note:A lead of 1 km is
considered. Add
0.06hour, for every
additional km lead, of
dumper/tipper use rate
per m3
Diameter of Pilot shaft m
Driven Area m2
Average pull 0.90 m
Excavated quantity per cycle m3
Average depth of holes to be drilled 1.50 m
Number of holes (pattern - 0.40 sq:m) No
Total depth of drilling m
Average output of Jack hammer per hour 7.50 m
Number of hr required hr
1.Material charges
m Drill bit 1 Each life 150 m
5 % Extra for sharpening @ 5% of above
Kg Gelatine (0.45 kg per hole) 25 Kg
B. SURGESHAFT
94
Kg Gelatine (0.45 kg per hole) 25 Kg
No Delay detonators 1 No.
10 % Other petty consumables, wires, etc. @ 10 %
of above two items
10 % Provision for pipe lines for air and water,
electric lines, fixtures, scaffoldings, wire
ropes,safety items, conveyance charges, etc.
@ 10 % of above items
Total
Total Material charges per m3
2.Labour charges for 10 m3
0.88 No. Foreman 1 Each
0.88 No. Supervisor 1 Each
0.88 No. Fitter 1 Each
0.88 No. Blaster 1 Each
0.88 No. Electrician 1 Each
1.00 No. Special mazdoor 1 Each
4.00 No. Helper for cleaning holes, scaling, etc. 1 Each
40 % Difficult work allowance
% Hill allowance
Total
Total Labour charges per m3
3.Machinery charges per m3
hr Jack Hammer 1 hr
0.32 hr Loader - 0. 5 m3 1 hr
0.64 hr Tipper 1 hr
0.50 hr Crane 1 hr
0.91 hr Ventilation blower 1 hr
Total
Total Machinery charges per m3
94
4.Shop charges per m3
5 % Machine shop, Structural shop, Steel metal
shop, Air and water pipe shop, Carpentary
shop etc. @ 5% of machinery charges
Total shop charges per m3
5.Maintenance charges per m3
0.125 No Man for maintenance of electrical line, water
line, air line, etc.
1 Each
40 % Difficult work allowance of labour
% Hill allowance
Total Maintenance charges per m3
Total 1 to 5 (A)
6.Electric and Water charges
5 % Electric, Water and Dewatering charges @
5% of (A)
7.Spare Charges
5 % Jack hammer, ventilation blower, water line,
air line, cables, bulbs, pumps etc. @ 5% of
(A)
8.Uninterrupted Power Supply Charges
3 % Maintenance of diesel generator, acessories,
etc. @ 3% of (A)
9.Insurance Charges
2 % Machines, equipments, labour, etc @ 2% of
95
2 % Machines, equipments, labour, etc @ 2% of
(A)
10.Maintenance of haul roads
3 % Haul roads @ 3% of (A)
% OH
% CP
Total
Rate per 1m3 of pilot driving /m
3
7 1 m3 Driving the surge shaft in rock to full section
as per approved cross section to lines and
levels including all the required operations
using modern explosives and machine
drilling, lighting, ventilation, water supply,
dewatering, compressed air etc and
depositing the excavated material(muck) in
the dumpyard or at designated places
including all leads and lifts, cost of all
materials, machinery, fuel and labour etc
complete.
Note:A lead of 1 km is
considered. Add
0.06hour, for every
additional km lead, of
dumper/tipper use rate
per m3
Excavated Diameter of surge m
Driven Area m2
Diameter of pilot shaft m
Area of slashing
Average pull 1.20 m
Excavated quantity m3
Average depth of holes to be drilled 1.50 m
Number of holes (pattern - 0.40 m2) No
Total depth of drilling m
Average output of Jack hammer per hour 7.50 m
Number of hours required hr
95
1.Material charges
m Drill bit 1 Each
5 % Extra for sharpening @ 5% of above
Kg Gelatine (0.45 kg per hole) 25 Kg
Nos. Delay detonators 1 No.
10 % Other petty consumables, wires, etc. @10%
of above two items
10 % Provision for pipe lines for air and water,
electric lines, fixtures, scaffoldings, wire
ropes, safety items, conveyance charges, etc.
10% of above items
Total
Total Material charges per m3
2.Labour charges for 10 m3
0.20 No. Foreman 1 Each
0.20 No. Supervisor 1 Each
0.20 No. Fitter 1 Each
0.20 No. Blaster 1 Each
0.20 No. Electrician 1 Each
0.50 No. Special mazdoor 1 Each
2.00 No. Helper for cleaning holes, scaling, etc. 1 Each
40 % Difficult work allowance
96
40 % Difficult work allowance
% Hill allowance
Total
Total Labour charges per m3
3.Machinery charges per m3
hr Jack Hammer 1 hr
0.32 hr Loader - 0. 5 cum 1 hr
0.64 hr Tipper 1 hr
0.50 hr Crane 1 hr
0.45 hr Ventilation blower 1 hr
Total
Total Machinery charges per m3
4.Shop charges per m3
5 % Machine shop, Structural shop, Steel metal
shop, Air and water pipe shop, Carpentary
shop etc. @ 5% of machinery charges
Total shop charges per m3
5.Maintenance charges per m3
0.125 No Men for maintenance of electrical line,
water line, air line, etc.
1 Each
40 % Difficult work allowance of labour
% Hill allowance
Total Maintenance charges per m3
Total 1 to 5 (A)
6.Electric and Water charges
5 % Electric, Water and Dewatering charges @
5% of (A)
96
7.Spare Charges
5 % Jack hammer, ventilation blower, water line,
air line, cables, bulbs, pumps etc. @ 5% of
(A)
8.Uninterrupted Power Supply Charges
3 % Maintenance of diesel generator, acessories,
etc. @ 3% of (A)
9.Insurance Charges
2 % Machines, equipments, labour, etc @ 2% of
(A)
10.Maintenance of haul roads
3 % Haul roads @ 3% of (A)
% OH
% CP
Total
Rate per 1m3 of slashing to full section of
shaft /m3
8 1 m3 Cement concrete (M25MSA20) for lining of
surge shaft including cost of all materials,
form work, labour, conveying, laying,
vibrating, curing etc, complete
Where ever rock is not
available or at upsurge
area, add 15% extra
1 m3 Cost of CC M25 MSA20
1 m3
Concrete mix may be
suitably taken
0.35 No. Extra man due to inefficiency in conveying
concrete
1 Each
97
concrete
0.1 No. Extra mason due to inefficiency in placing
concrete
1 Each
40 % Difficult work allowance for labour
3.50 m2 Steel Form work 1 m
2
40 % Extra for circular formwork
0.5 hr Crane 1 hr
2 % Provision for electric and water charges,
platform etc. @ 2% of cost of concrete
% HA
% OH
% CP
Total
Rate per 1m3 of lining /m
3
9 1 m3 Cement concrete (M20MSA20) for the floor
of surge shaft including cost of all materials,
labour, conveying, laying, vibrating , curing
etc, complete
1 m3 Cost of CC M20 MSA20
1 m3
Concrete mix may be
suitably taken
0.18 No. Extra man due to inefficiency in conveying
and placing of concrete 1 Each
40 % Difficult work allowance
0.5 hr Crane 1 hr
2 % Provision for electric and water charges,
platform etc. @ 2% of cost of concrete
% HA
% OH
% CP
Total
Rate per 1m3
/m3
97
10 1 m3 Driving the tunnel for laying horizontal
pressure pipe in rock as per approved cross
sections to lines and levels including all the
required operations like drilling, blasting
using modern explosives, mucking, scaling,
etc. and removing and depositng the
excavated materials(muck) at designated
places including all leads and lifts, cost of
all materials, machinery, fuel, labour,
lighting, ventilation, water supply,
compressed air, dewatering, etc. complete as
per specifications and as directed by the
departmental officers.
Note:
1 .This data may be used
for up to 2.50 m
(Excavated diameter).
2 . Above 2.50m dia
(excavated diameter),
less 15% of rate of
driving the Tunnel for
pressure pipe.
3 . A lead of 1 km is
considered. Add
0.06hour, for every
additional km lead, of
Tipper use rate per m3
.
Rate per 1m3 of driving tunnel
Add 25% of above
Rate per 1m3 of driving tunnel for
pressure pipe /m3
11 1 m3 Driving the tunnel for laying inclined
pressure pipe in rock as per approved cross
sections to lines and levels including all the
required operations like drilling, blasting
using modern explosives, mucking, scaling,
Note:
1 .This data may be used
for up to 2.50 m
(Excavated diameter).
2 . Above 2.50m dia
(excavated diameter),
C. PRESSURE SHAFT
98
using modern explosives, mucking, scaling,
etc. and removing and depositng the
excavated materials(muck) at designated
places including all leads and lifts, cost of
all materials, machinery, fuel, labour,
lighting, ventilation, water supply,
compressed air, dewatering, etc. complete as
per specifications and as directed by the
departmental officers.
(excavated diameter),
less 15% of rate of
driving the Tunnel for
pressure pipe.
3 . A lead of 1 km is
considered. Add
0.06hour, for every
additional km lead, of
Tipper use rate per m3
.
Rate per 1m3 of driving tunnel
Add 90% of above
Rate per 1m3 of driving tunnel for
pressure pipe /m3
98
Sl. Description of item Rate Amount Remarks
1 m2 Ultrasonic inspection of steel plate (ASTM A
285 Grade C or its equivalent IS) at place of
delivery/ fabrication, prior to fabrication of
plates including all expenses for testing
arrangements, labour charges etc. complete
as per specifications, approved drawings and
as directed by departmental officers.
0.025 No. Technician 1 Each
0.025 No. Man 1 Each
3 min Hire charges of 3T crane 1 hr.
Hire charges of ultrasonic machine @ 70%
of above
% HA
% OH
% CP Total / m
2
1 MT Design, Supply and Fabrication of penstock
pipes at erection site using steel plates
conforming to ASTM A 285 Grade C/or its
equivalent IS specifications, including cost
of steel, electrodes, welding flux and
accessories, carrying out stress relieving and
all tests other than those for which separate
items are included, shot/sand blasting and
protective coating for inside two coats of
Zinc rich primer and two coats of coal tar
epoxy paint, for outside one coat of zinc rich
primer followed by cement wash having a
composition of cement, water and pottassium
dichromate in 20:8:1 ratio first coat at
workshop, insurance charges, all labour
charges, transportation charges etc. complete
as per specifications, approved drawings and
as directed by the departmental officers.
A. Cost of Steel
1.01 MT Cost of steel plates 1 MT
B. Design Charges
Design charges @ 1% of cost of steel
C. Fabrication Charges
a.Cutting and Edge preparation
1.40 m3 Oxygen 1 m
3
0.40 Kg LPG 1 Kg
0.40 No. Fitter 1 Each
0.75 No. Gas Cutter/Blacksmith 1 Each
0.10 No. Supervisor/Skill Asst.(ITI) 1 Each
0.14 No. Khalasi 1 Each
0.70 No. Man 1 Each
5 % Gas cutting nozzle, hose, glouse, punch etc.
@ 5% of total (a) above
CHAPTER XVI
PENSTOCK
1
2
Quantity Unit
99
b.Conveying,lifting,placing etc.
2.00 hrs. Mobile crane (UR) 1 hr.
c.Bending and rolling of sheet
2.50 hrs. Bending machine (UR) 1 hr.
d.Welding of Rolled sheet
205 Nos Welding rods (8G) 100 No.
6.80 hrs. Welding set (UR) 1 hr.
1 % Cotton etc. @ 1% of above total (d)
e. Grinding of cutting plate
2.00 hrs. Grinding machine (UR) 1 hr.
8 Nos Grinding stone 1 Each
D. Shot/Sand blasting
1.00 hr. Shot blasting machine (UR) 1 hr.
10 % Aggregates for shot blasting @ 10% of
above
E. Painting
3.10 litres. Zinc rich primer 1 litres.
1.70 litres. Coal tar epoxy paint 1 litres.
1 % Potassium dichromate @ 1% of total cost of
above
3.70 kg Cement 1 MT
4.70 No. Painter 1 Each
% HA
% OH
% CP
Total /MT
3 1 MT Design, Supply and Fabrication of flanges,
bends, expanders, reducers, Y piece etc by
using steel plates conforming to ASTM A
285 Grade C/or its equivalent IS
specifications, including cost of steel,
electrodes, welding flux and accessories,
carrying out stress relieving and all tests
other than those for which separate items are
included, sand blasting and protective
coating for inside two coats of Zinc rich
primer and two coats of coal tar epoxy paint,
for outside one coat of zinc rich primer
followed by cement wash having a
composition of cement, water and pottassium
dichromate in 20:8:1 ratio first coat at
workshop, insurance charges, all labour
charges, transportation charges etc. complete
as per specifications, approved drawings and
as directed by the departmental officers.
A. Cost of Steel
1.03 MT Cost of steel plates 1 MT
B. Design Charges
Design charges @ 1% of cost of steel
100
C. Fabrication Charges
Fabrication charges @ 120% of Fabrication
charges of penstock pipe vide item (2)
D. Shot/Sand blasting
1.00 hr. Sandblasting machine (UR) 1 hr.
Aggregates for shot blasting @ 10% of
above
E. Painting
3.10 litres. Zinc rich primer 1 litres.
1.70 litres. Coal tar epoxy paint 1 litres.
1.00 % Potassium dichromate @ 1% of total cost of
above
3.70 Kg Cement 1 MT
4.70 No Painter 1 Each
% HA
% OH
% CP
Total /MT
4a. 1 m Radiographic inspection of shop weld carried
out at fabrication site/ factory as per
specifications including all expences for
testing arrangements and labour charges etc.
complete as directed by the departmental
officers.
2 hrs Hire charges of Radiographic testing
machine including licence charges1
hrUR (1m tesing -2hrs.)
0.025 m2 Cost of film (MR) 1 m
2
3 % Provision for ladder, crane etc. @ 3% of
above
% OH
% CP
Total /m
4b. 1 m Radiographic inspection of field weld as per
specification including all expences for
testing arrangements and labour charges etc.
complete as directed by the departmental
officers.
2 hr Hire charges of Radiographic testing
machine including licence charges1
mUR (1m tesing -2hrs.)
0.025 m2 Cost of film (MR) 1 m
2
10 % Provision for ladder, crane etc. @ 10% of
above
% OH
% CP
Total
Say Rs. /m
101
1 MT Erection and installation of pipes, flanges,
bends, Y-piece, expanders, reducers etc.
including conveyance to the haulage position
over the substructure anchors, placing in
position, assembling, welding, followed by
second coat of cement wash having a
composition of cement, water and pottassium
dichromate in 20:8:1 ratio, etc. complete as
per specifications and approved drawings
including all labour charges, transportation
charges, equipments, final protective coating,
insurance charges etc. complete as directed
by the departmental officers.
a.Conveyance charges
0.25 hr. Mobile crane (UR) 1 hr.
0.25 hr. Tipper (UR) 1 hr.
0.05 No. Khalasis 1 Each
0.01 No. Supervisor(ITI) 1 Each
0.05 No. Helper 1 Each
Packing and testing materials @ 10% of
above
b.Lifting, positioning and aligning
6.00 hrs. Mobile crane (UR) 1 hr.
Winch and trolly (75% of Mobile crane)
1.00 No. Fitter 1 Each
0.33 No. Supervisor/Skill Asst.(ITI) 1 Each
0.33 No. Rigger 1 Each
1.00 No. Khalasi 1 Each
2.00 No. Helper 1 Each
Jacky, wooden blocks, steel sections, etc. @
10% of above
c.Welding (circumferencial )
385 No. Welding rods (8G) 100 No.
12.8 hr Welding set (UR) 1 hr
Cotton etc. @ 1% of above
d.Grinding
7.00 hr Grinding machine (UR) 1 hr
15.00 No. Grinding stone (MR) 1 No.
Gloves, Cotton etc. @ 1% of above
e.Painting
3.00 kg Cement 1 MT
Potassium dichromate @ 10% of cost of
cement
0.70 No. Painter 1 Each
% HA
% OH
% CP
Total /MT
5
102
1 MT Design, Supply, Fabrication and Erection of
rocker supports to the penstock using various
size steel sections etc., straightening, cutting
fabricating and hoisting including applying
one coat of iron primer and painting with
coaltar epoxy paint 2 coats, etc. complete. as
per drawing and as directed by the
departmental officers.
A. Cost of Steel
1.05 MT Cost of steel sections 1 MT 0.00
B. Design Charges
Design charges @ 1% of cost of steel
C. Fabrication and Erection Charges
a.Cutting
0.98 m3 Oxygen 1 m
3
0.28 Kg LPG (MR) 1 Kg
0.28 No. Fitter 1 Each
0.53 No. Gas Cutter/Blacksmith 1 Each
0.07 No. Supervisor/Skill Asst.(ITI) 1 Each
0.10 No. Khalasi 1 Each
0.49 No. Man 1 Each
Gas cutting nozzle, hose, glouse, punch etc.
b.Conveying, lifting, placing etc.
1.40 hr Hire charges of Mobile crane (UR) 1 hr.
c.Welding
144 Nos Welding rods (8G) 100 No
4.80 hrs. Welding set 1 hr.
Cotton etc. @ 1% of above
d. Grinding
1.40 hr Grinding machine (UR) 1 hr.
6 No Grinding stone (MR) 1 Each
D. Painting
0.70 litres. Iron primer 1 litres.
1.20 litres. Coal tar epoxy paint 1 litres.
1.50 Nos Painter 1 Each
% HA
% OH
% CP
Total /MT
6
103
Sl.
No. Description of items Rate Amount Remarks
1 1 MT Design, Supply, Fabrication and Erection of
Gate using various size steel sections etc.,
straightening, cutting, fabricating and
hoisting including applying one coat of iron
primer and painting with epoxyl paint 2
coats, etc. complete as per drawings and as
directed by the departmental officers.
A. Cost of Steel
1.01 MT Cost of steel 1 MT
B. Design Charges1 % Design charges @ 1% of cost of steel
C. Fabrication Chargesa.Cutting
2.80 m3 Oxygen 1 m
3
0.80 Kg LPG (MR) 1 Kg
5.00 No Fitter 1 Each
15.00 No Turner I 1 Each
5.00 No Welder 1 Each
10.00 No Blacksmith 1 Each
3.70 No Man 1 Each
Gas cutting nozzle, hose, glouse, punch etc.
@ 5% of total above (a)
hr b.Conveying,lifting,placing etc.
4.00 hr. Mobile crane (UR) 1 hr.
c.Welding 75 No. Welding rods (8G) 100 No.
7.00 hr. Welding set (UR) 1 hr.
Cotton etc. @ 1% of above
d. Grinding 1.50 hr. Grinding machine (UR) 1 hr.
3 No Grinding stone 1 Each
e. Painting1.20 litre. Iron primer 1 litre.
1.80 litre. Coal tar epoxy paint 1 litre.
2.00 No. Painter 1 Each
D.Erection chargesa.Conveyance charges
4.00 hr. Mobile crane (UR) 1 hr.
1.00 hr. Tipper 1 hr.
0.35 No. Khalasis 1 Each
0.10 No. Supervisor(ITI) 1 Each
0.35 No. Helper 1 Each
Packing and testing materials @ 10% of total
above (a)
b.Lifting, aligning and positioning
2.67 hr. Mobile crane (UR) 1 hr.
0.33 No. Fitter 1 Each
0.33 No. Supervisor/Skill Asst.(ITI) 1 Each
1.00 No. Khalasi 1 Each
2.00 No. Man 1 Each
Jacky, wooden blocks, steel sections, etc. @
10% of total above (b)
% HA
Quantity Unit
CHAPTER XVII
GATES AND TRASH RACK
104
% OH % CP
Total /MT
2 1.00 MT Design, Supply, Fabrication and Erection of
Trashrack using various size steel sections
etc., straightening, cutting, fabricating and
hoisting including applying one coat of iron
primer and painting with epoxy paint 2 coats,
etc. complete as per drawings and as directed
by the departmental officers.
A. Cost of Steel
1.05 MT Cost of steel sections 1 MT
B. Design Charges
1 % Design charges @ 1% of cost of steel
C. Fabrication Charges
a. Cutting,Welding, etc.
1000 No Welding rods 100 No
36.00 No Blacksmith 1 Each
12.00 No Heavy load mazdoor / Khalasi 1 Each
6.00 No Welder 1 Each
4 % Current charges , grinding stone,and sundries
4% of (a)
b. Painting
1.20 litre. Iron primer 1 litre.
1.80 litre. Coal tar Apoxy paint 1 litre.
2.00 No. Painter 1 Each
D.Erection charges
a.Conveyance charges
4.00 hr. Mobile crane 1 hr.
1.00 hr. Tipper 1 hr.
0.35 No. Khalasis 1 Each
0.10 No. Supervisor(ITI) 1 Each
0.35 No. Helper 1 Each
Packing and testing materials @ 10% of total
above (a)
b.Lifting,aligning and positioning
2.67 hr. Mobile crane 1 hr.
0.33 No. Fitter 1 Each
0.33 No. Supervisor/Skill Asst.(ITI) 1 Each
1.00 No. Khalasi 1 Each
2.00 No. Man 1 Each
Jacky, wooden blocks, steel sections, etc. @
10% of total above (b)
% HA
% OH
% CP
Total /MT
105
Sl.
No.Description of items Rate Amount Remarks
1 1 Kg Furnishing and placing Copper sealing strips
in joints and at other locations as per
drawings and specifications including cost
of GI strips, conveyance, labour, etc.
complete.
1 Kg Copper sealing strips 1 Kg
0.03 No. Fitter 1 Each
0.035 No. Man 1 Each
5 % Provision for tools, conveyance etc. @ 5 %
of above
% HA
% OH
% CP
Total /Kg
2 1 Kg Furnishing and placing GI strips in joints and
at other locations as per drawings and
specifications including cost of GI strips,
labour, etc. complete.
1 Kg GI strips 1 Qtl
0.03 No. Fitter 1 Each
0.035 No. Man 1 Each
5 % Provision for tools, conveyance etc. @ 5 %
of above
% HA
% OH
% CP
Total /Kg
3 1 m2 Providing and filling the expansion joints
with bitumen pad (25 mm) as per drawings
and specifications and as directed by
departmental officers including cost of all
materials, labour, etc. complete.
1 m2 Cost of bitumen pad 1 m2
0.1 No. Fitter 1 Each
5 % Provision for tools, conveyance etc. @ 5 %
of above
% HA
% OH
% CP
Total /m2
`
CHAPTER XVIII
MISCELLANEOUS WORKS
Quantity Unit
106
4 1 No Providing and fixing elastomeric bearing pad
………...mm or nearest size over the bed
block as per drawings and specifications and
as directed by departmental officers
including cost of all materials, labour etc.
complete.
1 No Cost of bearing pad (MR) 1 Each
5 % Provision for tools, conveyance etc. @ 5 %
of above
% HA
% OH
% CP
Total /Each
5 1 m Furnishing and placing PVC water stops
conforming to IS specifications in joints and
at other locations as per drawings and
specifications and as directed by
departmental officers including cost of all
materials, labour, etc. complete.
1 m Cost of PVC water stops (MR) 1 m
5 % Provision for tools, conveyance etc. @ 5 %
of above
0.05 No. Carpenter for fixing 1 Each
0.05 No. Man for assisting 1 Each
% HA
% OH
% CP
Total /m
6 1 m2 Supplying and laying Tar paper/ HDPE
sheet as per drawings and specifications and
as directed by departmental officers
including cost of all materials, labour, etc.
complete.
1 m2 Cost of HDPE Sheet (MR) 1 m2
5 % Provision for conveyance, laying etc. @ 5%
of above
% HA
% OH
% CP
Total /m2
7 1 m3 Providing course gravel cushion with 20 to
40mm graded aggregates laying to lines and
levels as per drawings and specifications and
as directed by departmental officers
including cost of all materials, labour
charges, etc. complete
0.80 m3 40mm coarse aggregates 1 m3
0.20 m3 20mm coarse aggregates 1 m3
1 No. Man for laying to lines and levels 1 Each
% HA
% OH
% CP
Total /m3
107
8 1 m3 Providing course gravel cushion with 5 to
20mm graded aggregates laying to lines and
levels as per drawings and specifications and
as directed by departmental officers
including cost of all materials, labour
charges, etc. complete
0.40 m3 20mm coarse aggregate 1 m3
0.30 m3 12mm coarse aggregate 1 m3
0.30 m3 6mm coarse aggregate 1 m3
1 No. Man for laying to lines and levels 1 Each
% HA
% OH
% CP
Total /m3
9 1 m³ Providing aggregate cushion using fine
aggregate/coarse sand , laying to lines and
levels as per drawings and specifications and
as directed by departmental officers
including cost of all materials, labour
charges, etc. complete
1 m³ Fine aggregate/ Course sand 1 m³
0.75 No. Man for laying to lines and level 1 Each
% HA
% OH
% CP
Total /m3
10 1 m³ Supplying and spreading 40 mm broken
stone for required thickness, laying to lines
and levels as per drawings and specifications
and as directed by departmental officers
including cost of all materials, labour
charges, etc. complete
1 m³ Cost of 40 mm broken stone 1 m³
1 No. Man for laying to lines and level 1 Each
% HA
% OH
% CP
Total /m3
11 1 m³ Supplying and spreading 20 mm broken
stone for required thickness, laying to lines
and levels as per drawings and specifications
and as directed by departmental officers
including cost of all materials, labour
charges, etc. complete
1 m³ 20mm aggregate at site 1 m3
1 No. Man for laying to lines and level 1 Each
% HA
% OH
% CP
Total /m3
108
12 1 m³ Supplying and spreading sand for required
thickness, laying to lines and levels as per
drawings and specifications and as directed
by departmental officers including cost of all
materials, labour charges, etc. complete
1 m³ Sand 1 m³
0.75 No. Man for laying to lines and level 1 Each
% HA
% OH
% CP
Total /m3
13 1 Kg Supplying and fixing MS pipe of required
diameter and thickness, laying to lines and
levels as per drawings and specifications and
as directed by departmental officers
including cost of all materials, labour
charges, etc. complete
1 Kg Cost of steel pipe 1 Qtl
0.03 No Fitter 1 Each
0.03 No Man 1 Each
0.01 No Welder 1 Each
10 % Provision for welding set, rods etc. @ 10 %
of cost of above all
% HA
% OH
% CP
Total /Kg
14 1 No. Supplying and fixing best quality sluice
valve of approved diameter and make for
connecting with the pipe including cost of
valve, flanges, packings, transportation
charges, installation and painting charges,
etc. complete.
1 No. Cost of Valve (MR) 1 Each
10 % Cost of flanges, packings, transportation
charges, installation and painting charges, etc
@ 10 % of above
% HA
% OH
% CP
Total /Each
15 1 m Supplying and fixing hand rails / ladder with
GI pipes of ……mm including cost of all
materials, labour, fabrication charges,
applying one coat primer coat , etc.
1.05 m Cost of GI Pipe 1 m
0.02 No. Fitter 1 Each
0.02 No Man 1 Each
0.02 No Welder 1 Each
109
10 % Provision for specials, welding, and cost of
priming coat etc @ 10% of above
% HA
% OH
% CP
Total /m
16 1 Kg Supplying and fixing MS Grills / gates
including cost of all materials, labour,
fabrication charges, applying one coat
primer, etc. complete.
1.05 Kg Cost of Ms Square/round , etc 1 Qtl
0.02 No. Fitter 1 Each
0.02 No Man 1 Each
0.02 No Welder 1 Each
10 % Provision for welding, and cost of priming
coat etc @ 10% of above
% HA
% OH
% CP
Total /Kg
17 1 Kg Fabricating, supplying and installing
miscellaneous metal works for various works
or any other steel item specified in drawing
such as hatch cover, frames, gratings,
chequered plates, rails, embedded parts,
angle post of chain link fencing, etc. at all
elevations including cost of all materials,
fabrication, welding and fixing charges,
applying one coat primer, etc. complete.
1.05 Kg MS angles, flat, plates, channel, etc. 1 Qtl
0.01 No. Blacksmith 1 Each
0.01 No. Welder 1 Each
0.02 No. Man 1 Each
10 % Provision for welding, and cost of priming
coat etc @ 10% of above
% HA
% OH
% CP
Total /Kg
18 1 m Supplying and laying PVC perforated pipe
including cost of all materials, labour, etc.
complete.
1 m PVC pipe 1 m
10 % Provision for making perforations, solvent
cement, labour charges and other sundries @
10% of above.
0 % OH
0 % CP
Total /m
110
19 1 m Supplying and laying PVC pipe (other than
for water supply / sanitary works) including
cost of all materials, conveyance, labour, etc.
1 m Cost of PVC pipe 1 m
5 % Solvent cement, labour charges etc @5% of
above.
% OH
% CP
Total /m
20 1 No Supplying and fixing PVC specials (other
than for water supply / sanitary works) such
as Tee ,Elbow, Bend, Coupling etc including
cost of all materials, conveyance, labour, etc.
1 No Cost of PVC special 1 Each
5 % Solvent cement, labour charges etc @5% of
above.
% OH
% CP
Total /Each
21 1 m Supplying and fixing PVC rain water gutter
of suitable size including necessary fittings
such as clamps, screws, end stopper etc.
including cost of all materials, labour
charges, scaffolding etc.
1 m 150 mm dia PVC rain water gutter 1 m
10 % Provision for drill, bends, end stoppers,
clamps, screws, scaffolding and other
sundries @ 10% of above.
0.1 No. Plumber 1 Each
0.1 No. Man 1 Each
% HA
% OH
% CP
Total /m
22 1 m Supplying and fixing PVC down water pipe
of suitable dia including necessary fittings
such as, bends, elbows, reducers, clamps,
screws etc., fixing the pipe to the wall ,
cutting masonry/concrete wherever
necessary, scaffolding etc. complete.
1 m Cost of PVC pipe 1 m
10 % Provision for elbow, bends, clamps, screws,
scaffolding and other sundries etc @ 10% of
above.0.07 No. Plumber 1 Each
0.07 No. Man 1 Each
% HA
% OH
% CP
Total /m
111
23 1 m2 Chemical treatment to the wall and slab
wherever necessary with water proofing
slurry applied with brush in 3 coats
consisting of polymer modified pulversied
material based powder and acrylic based
polymer bonding agent working on the
principles of water proofing by crystalline
penetration or equivalent treatment as per
specifications for the purpose including
surface cleaning to remove the deposits of oil
and grease, cost of materials, labour charges,
curing, scaffolding, etc. complete.
Note: Item may be
suitably modified
acording to the
availability of materials
in the market.
3 Kg Dichtament Ds or equivalent (MR) 1 Kg
0.18 Kg Nafufill or equivalent (MR) 1 Kg
0.1 No Man 1 Each
0.3 No Painter 1 Each
5 % Provision for conveyance of materials,
scaffolding and other sundries @ 5% of
above.
% HA
% OH
% CP
Total /m2
24 1 m2 Supplying and fixing mechanically operated
rolling shutters of approved make, made of
80 x 1.25 mm laths interlocked together
through their entire length and jointed
together at the end by the end locks mounted
on specially designed pipe shaft with
brackets, side guides and arrangements for
inside and outside locking with push and pull
operation and painted with two coats of
synthetic enamel paint over a coats of iron
primer including cost of all materials, labour
charges etc.complete
1 m2 Cost of rolling shutter 1 m2
0.3 No. Fitter 1 Each
0.3 No. Man 1 Each
0.3 No. Mason 1 Each
2.28 m2 Painting with two coats of synthetic enamel
paint over two coats of iron primer
1 m2
% HA
% OH
% CP
Total /m2
112
25 1 m2 Supplying and fixing electrically operated
(with reversible switch and accessories)
rolling shutters of approved make, made of
80 x 1.25 mm laths interlocked together
through their entire length and jointed
together at the end by the end locks mounted
on specially designed pipe shaft with
brackets, side guides and arrangements for
inside and outside locking with push and pull
operation and painted with two coats of
synthetic enamel paint over a coats of iron
primer including cost of all materials, labour
charges etc.complete
1 m2 Cost of rolling shutter 1 m2
0.3 No. Fitter 1 Each
0.3 No. Man 1 Each
0.3 No. Mason 1 Each
2.28 m2 Painting with two coats of synthetic enamel
paint over two coats of iron primer
1 m2
1 No. Electric motor and accessories (MR) 20 m2 Shutter size of
4.00x5.00m is assumed.
0.025 No. Mechanic Gr.I 1 Each
0.025 No. Electrician 1 Each
5 % for conveyance, lead wire, fixing foundation
bolt, etc. @ 10% of above three items
% HA
% OH
% CP
Total /m2
26 1 m Supplying and fixing rolling shutter cover
of approved make and painted with two coat
of synthetic enamel paint over a coats of
iron primer including cost and conveyance of
all materials, labour charges etc.complete.
1 m Rolling shutter cover 1 m2
0.15 No. Fitter 1 Each
0.15 No. Man 1 Each
0.15 No. Mason 1 Each
1.5 m2 Painting with two coats of synthetic enamel
paint over a coat of iron primer
1 m2
% HA
% OH
% CP
Total /m
113
27 1 litre Supplying and placing in position PVC
water storage tank of approved make
including all fittings, etc. complete.
1 litre cost 1 lit water tank 1 litre
5 % Fitting charges and sundries etc. @5% above
0 % OH
0 % CP
Total /litre
114
Sl.
No.Description of items Rate Amount Remarks
1 1 Km Assisting departmental Officers for
conducting Reconnaissance survey through
easy terrain including clearing light jungle,
cutting earth for making steps wherever
necessary etc, complete.
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle
2 No. Man Mazdoor 1 Each
10 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Km
2 1 Km Assisting departmental Officers for
conducting Reconnaissance survey through
steep and difficult terrain including clearing
light jungle, cutting earth for making steps
wherever necessary, etc. complete.
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle
3 No. Man Mazdoor 1 Each
10 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Km
3 1 Km Assisting departmental Officers for survey
works for fixing the preliminary alignment of
roads etc. including clearing light jungle,
cutting earth for making steps wherever
necessary, etc. complete.
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle
4 No. Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Km
4 1 Km Assisting departmental Officers for
conducting compass survey for fixing the
bearings of the alignment for preparing
survey drawings, including clearing light
jungle, cutting earth for making steps
wherever necessary, etc. complete.
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle
4 No. Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Km
Quantity Unit
CHAPTER XIX
INVESTIGATION WORKS
115
5 1 Ha Assisting departmental Officers for
conducting contour survey using Theodolite/
Total Station for preparing survey drawings,
through easy terrain including clearing light
jungle, cutting earth for making steps
wherever necessary, etc. complete.
An additional provision
of one Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle
4 No. Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Ha
6 1 Ha Assisting departmental Officers for
conducting contour survey using Theodolite/
Total Station for preparing survey
drawings, through steep and difficult terrain
including clearing light jungle, cutting earth
for making steps wherever necessary, etc.
complete.
An additional provision
of 1.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle
6 No. Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Ha
7 1 Ha Assisting departmental Officers for
conducting detailed site survey for colony
roads, buildings, etc. using Theodolite/
Total Station including clearing jungle
wherever necessary, etc. complete.
1.5 No. Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Ha
8 1 Set Writing Bench mark details like B.M. value,
B.M No. and the letter KSEB on concrete,
rock and other surfaces after cleaning etc.,
with synthetic enamel paint two coats as
directed by departmental officers.
0.1 No. Painter 1 Each
10 % Sundries such as cost of paint, brush, cotton,
etc.
% HA
% CP
Total /Set
116
9 1 Set Establishing permanent Bench mark on solid
rock by engraving B.M. value, B.M No. and
the letter KSEB after chipping and leveling
the surface for an area 30 cms x 30 cms etc.
complete.
0.75 No. Stone Cutter 1 Each
5 % Sundries such as chisel, hammer etc.
% HA
% CP
Total /Set
10 1 No. Establishing cement concrete block of size
45cm x 45cm x 90cm with CC 1:3:6 using
40mm aggregates and having one number
16mm dia M.S rod, 20 cm long at centre and
the block 45 cm above ground level and the
rod projecting 3 mm above top level of the
block including excavation, marking Bench
Mark details, cost of materials, labour
charges etc. complete as directed by the
departmental officers.
0.17 m3 40mm broken stone 1 m
3
0.09 m3 Sand 1 m
3
42 Kg Cement 1 MT
0.02 No. Mason 1 Each
0.18 No. Man Mazdoor 1 Each
0.25 No. Woman 1 Each
15 % Provision for digging pit, formwork, cost of
M.S rod, collecting water, marking B.M
details, etc. @ 15% above total
% HA
% CP
Total /Each
11 1 Km Assisting departmental Officers for
connecting fly levels using levelling
instrument/ Total Station from Bench marks
for establishing permanent or temporary
Bench marks, including daily closing and
other checking of levels through easy terrain
including clearing light jungle, cutting earth
for making steps wherever necessary, etc.
complete.
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle
1.5 No. Special Mazdoor 1 Each
0.5 No Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Km
117
12 1 Km Assisting departmental Officers for
connecting fly levels using levelling
instrument/ Total Station from Bench marks
for establishing permanent or temporary
Bench marks, including daily closing and
other checking of levels found necessary,
through steep and difficult terrain including
clearing light jungle, cutting earth for making
steps wherever necessary, etc. complete.
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle
3 No. Special Mazdoor 1 Each
1 No Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Km
13 1 Km Assisting departmental Officers for
connecting double fly levels using levelling
instrument/ Total Station from Bench marks
for establishing permanent or temporary
Bench marks, including daily closing and
other checking of levels through easy terrain
including clearing light jungle, cutting earth
for making steps wherever necessary, etc.
complete.
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle
2.25 No. Special Mazdoor 1 Each
0.75 No Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Km
14 1 Km Assisting departmental Officers for
connecting double fly levels using levelling
instrument/ Total Station from Bench marks
for establishing permanent or temporary
Bench marks, including daily closing and
other checking of levels found necessary,
through steep and difficult terrain including
clearing light jungle, cutting earth for making
steps wherever necessary, etc. complete.
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle
3.75 No. Special Mazdoor 1 Each
1.25 No Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Km
118
15 1 Ha Assisting departmental Officers for
conducting traverse survey using
Theodolite/ Total Station for locating project
control points, plot locations, measurements
of land, preparation of site plan etc, through
easy terrain including clearing light jungle,
cutting earth for making steps wherever
necessary, etc. complete.
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle
2.25 No. Special Mazdoor 1 Each
0.75 No Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Ha
16 1 Ha Assisting departmental Officers for
conducting traverse survey using
Theodolite/ Total Station for plot locations,
measurements of land, preparation of site
plan etc, through steep and difficult terrain
including clearing light jungle, cutting earth
for making steps wherever necessary, etc.
complete.
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle
3 No. Special Mazdoor 1 Each
1 No Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Ha
17 1 No. Establishing precast survey blocks /
boundary stones / center line blocks etc., of
size 15x15x60cms or nearest size including
excavation upto 45 cms, marking details with
paint, cost of block/stone,conveyance and
labour charges etc. complete as directed by
the departmental officers.
1 No. Block/stone 1 Each MR
0.2 No. Man Mazdoor 1 Each
10 % Provision for conveyance, marking details,
etc.
15 % HA
10 % CP
Total /Each
18 1 Km Assisting departmental Officers for taking
profile along the tunnel/penstock alignment
using levelling instrument/ Total Station
through easy terrain including clearing light
jungle, cutting earth for making steps
wherever necessary, etc. complete.
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle
119
4.5 No. Special Mazdoor 1 Each
1.5 No. Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Km
19 1 Km Assisting departmental Officers for taking
profile along the tunnel/penstock alignment
using levelling instrument/ Total Station
through steep and difficult terrain including
clearing light jungle, cutting earth for making
steps wherever necessary, etc. complete.
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle
7.5 No. Special Mazdoor 1 Each
2.5 No. Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Km
20 1 Km Assisting departmental Officers for taking
longitudinal section (L.S) along road, land
etc., using levelling instrument/ Total
Station at suitable intervals and covering all
requisite points through easy terrain
including clearing light jungle, cutting earth
for making steps wherever necessary, etc.
complete.
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle
2.25 No. Special Mazdoor 1 Each
0.75 No Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Km
21 1 Km Assisting departmental Officers for taking
longitudinal section (L.S) along road, land
etc. using levelling instrument/ Total Station
at suitable intervals and covering all requisite
points through steep and difficult terrain
including clearing light jungle,cutting earth
for making steps wherever necessary, etc.
complete.
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle
3 No. Special Mazdoor 1 Each
1 No Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Km
120
22 1 Km Assisting departmental Officers for taking
longitudinal section (L.S) of river and other
streams using levelling instrument/ Total
Station at suitable intervals and covering all
requisite points through easy terrain
including cutting earth for making steps
wherever necessary, etc. complete.
3 No. Special Mazdoor 1 Each
1 No Man Mazdoor 1 Each
5 % Sundries such as rope, spade, etc.
% HA
% CP
Total /Km
23 1 Km Assisting departmental Officers for taking
longitudinal section (L.S) of river and other
streams using levelling instrument/ Total
Station at suitable intervals and covering all
requisite points through steep and difficult
terrain including cutting earth for making
steps wherever necessary, etc. complete.
5 No. Special Mazdoor 1 Each
2 No. Man Mazdoor 1 Each
5 % Sundries such as rope, spade, etc.
% HA
% CP
Total /Km
24 1 No Assisting departmental Officers for taking
cross section (C.S) along road, land etc., of
width up to 50 m. using levelling
instrument/ Total Station at suitable intervals
and covering all requisite points through
easy terrain including clearing light jungle,
cutting earth for making steps wherever
necessary, etc. complete.
0.11 No. Special Mazdoor 1 Each
0.04 No. Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Each
25 1 No Assisting departmental Officers for taking
cross section (C.S) along road, land etc., of
width up to 50 m. using levelling
instrument/ Total Station at suitable intervals
and covering all requisite points through
steep and difficult terrain including clearing
light jungle, cutting earth for making steps
wherever necessary, etc. complete.
121
0.19 No Special Mazdoor 1 Each
0.06 No. Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Each
26 1 No Assisting departmental Officers for taking
cross section (C.S) along road, land etc., of
width up to 100 m. using levelling
instrument/ Total Station at suitable intervals
and covering all requisite points through
easy terrain including clearing light jungle,
cutting earth for making steps wherever
necessary, etc. complete.
For every additional
100m width, add 0.20
Ordinary Mazdoor.
0.15 No Special Mazdoor 1 Each
0.05 No. Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Each
27 1 No Assisting departmental Officers for taking
cross section (C.S) along road, land etc., of
width up to 100 m. using levelling
instrument/ Total Station at suitable intervals
and covering all requisite points through
steep and difficult terrain including clearing
light jungle, cutting earth for making steps
wherever necessary, etc. complete.
For every additional
100m width, add 0.30
Ordinary Mazdoor.
0.23 No Special Mazdoor 1 Each
0.07 No. Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Each
28 1 No Assisting departmental Officers for taking
cross section (C.S) of river and other streams
of width up to 50 m. covering portions of
adjacent bank using levelling instrument/
Total Station at suitable intervals and
covering all requisite points through easy
terrain including clearing light jungle, cutting
earth for making steps wherever necessary,
etc. complete.
0.19 No Special Mazdoor 1 Each
0.06 No. Man Mazdoor 1 Each
5 % Sundries such as rope, spade, etc.
% HA
% CP
Total /Each
122
29 1 No Assisting departmental Officers for taking
cross section (C.S) of river and other streams
of width up to 50 m. covering portions of
adjacent bank using levelling instrument/
Total Station at suitable intervals and
covering all requisite points through steep
and difficult terrain including clearing light
jungle, cutting earth for making steps
wherever necessary, etc. complete.
0.26 No Special Mazdoor 1 Each
0.09 No. Man Mazdoor 1 Each
5 % Sundries such as rope, spade, etc.
% HA
% CP
Total /Each
30 1 No Assisting departmental Officers for taking
cross section (C.S) of river and other streams
of width up to 100 m. covering portions of
adjacent bank using levelling instrument/
Total Station at suitable intervals and
covering all requisite points through easy
terrain including clearing light jungle, cutting
earth for making steps wherever necessary,
etc. complete.
For every additional
100m width, add 0.30
Ordinary Mazdoor.
0.23 No Special Mazdoor 1 Each
0.07 No. Man Mazdoor 1 Each
5 % Sundries such as rope, spade, etc.
% HA
% CP
Total /Each
31 1 No Assisting departmental Officers for taking
cross section (C.S) of river and other streams
of width up to 100 m. covering portions of
adjacent bank using levelling instrument/
Total Station at suitable intervals and
covering all requisite points through steep
and difficult terrain including clearing light
jungle, cutting earth for making steps
wherever necessary, etc. complete.
For every additional
100m width, add 0.40
Ordinary Mazdoor.
0.38 No Special Mazdoor 1 Each
0.12 No. Man Mazdoor 1 Each
5 % Sundries such as rope, spade, etc.
% HA
% CP
Total /Each
123
32 1 Station Assisting departmental Officers for
reconnaissance and preliminary
establishment of triangulation station using
Theodolite/ Total Station including clearing
jungle, etc. complete.
2 No. Special Mazdoor 1 Each
1 No Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Each
33 1 Station Assisting departmental Officers for
triangulation survey using Theodolite/ Total
Station for all readings from a station
including clearing jungle, etc. complete.
3.5 No. Special Mazdoor 1 Each
2 No. Man Mazdoor 1 Each
5 % Sundries such as rope, knife, axe, spade, etc.
% HA
% CP
Total /Each
34 1 Station/
day
Taking rainfall readings/ river gauge
readings and other meteorological
observations in wet months at specified time
and recording the same in prescribed format
at one station including watching of the
station etc, complete.
For remote station deep
inside the forest, an
additional provision of
0.20 Special mazdoor to
be provided.
0.35 No. Man Mazdoor 1 Each
% HA
% CP
Total /Each
35 1 Station/
day
Taking rainfall readings/ river gauge
readings and other meteorological
observations in dry months at specified time
and recording the same in prescribed format
at one station including watching of the
station etc, complete.
For remote station deep
inside the forest, an
additional provision of
0.20 Special mazdoor to
be provided.
0.2 No. Man Mazdoor 1 Each
% HA
% CP
Total /Each
124
1 70 HP
Note: (i) Hill
allowance may be
provided as per
nature of terrain. (ii)
Indirect Charges for
labour @ 55% for
semi skilled /
unskilled workers
and @ 80% of
skilled workers may
be provided for large
projects in remote
areas.
55,00,000.00
18.00
30000.00
75.00
1500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 183.33
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 165.00
Average hourly depreciation (Rs.),D3= (D1+D2)/2 174.17
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 137.50
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
2 563 25 28150.00
6 377 25 56550.00
0.50 505 25 6312.50
0.50 673 25 8412.50
1.00 377 25 9425.00
108850.00
Total Direct crew charges/year 1306200.00
Increase for hilly area (if necessary)15 195930.00
Total Crew Charges/year (Rs),Cc1 1502130.00
Hourly Crew Charges (Rs),Cc2 =Cc1/O 1001.42
( iii ) POL and Energy Charges
For Electricity
Power of Electric Motor (KW),P
BHP = 70 P =(746*BHP/1000) 52.22
Hourly Energy Consumption(KWH),Ec= P*.4*1 41.78
Rate of Electricity (Rs./KWH),e 4.00
Cost of Electricity (Rs.),Ce=Ec*e 167.10
Lubricant charges,Lc=(Ce*v% 50.13
Lubricants-u%of fuel & v% of electricity charges)
(Generally u = 25% & v = 30%)
Hourly POL and Energy Charges(Rs.), Pe=Ce+Lc 217.24
d For compressed air
Cost of compressed air, Cair 0.00
Hourly POL and Energy Charges(Rs.), Pe=Cair 0.00
( iv ) Miscellaneous charges ,Mc =C*z% 13.75
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 1544.07
ANNEXURE A - USE RATE OF EQUIPMENTSS
Operator
Helper (Man mazdoor)
Mechanic -1
Category
Batching & Mixing plant (27 cum)
Schedule life in Years,Y
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Watchman
Cost of Equipment(Rs.),E
Foreman (Diploma holder)
Total Monthly Wages
1
2 2.7 HP
28,000.00
2.00
2400.00
125.00
1500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 8.40
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 10.50
Average hourly depreciation (Rs.),D3= (D1+D2)/2 9.45
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 14.58
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 377 25 9425.00
1 377 25 9425.00
18850.00
Total Direct crew charges/year 226200.00
Increase for hilly area (if necessary)15 33930.00
Total Crew Charges/year (Rs),Cc1 260130.00
Hourly Crew Charges (Rs),Cc2 =Cc1/O 173.42
( iii ) POL and Energy Charges
a For Petrol
F.H.P of Engine 2.70
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1 0.30
Rate of Petrol (Rs./lit),d 70.00
Cost of Petrol (Rs.), Cd= Fc*d 20.79
Lubricant charges,Lc=(Cd*u%)) 5.20
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc 25.99
( iv ) Miscellaneous charges ,Mc =C*z% 1.46
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 224.90
3 4.9 HP
46,000.00
2.00
2400.00
125.00
1500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 13.80
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 17.25
Average hourly depreciation (Rs.),D3= (D1+D2)/2 15.53
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 23.96
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 377 25 9425.00
1 377 25 9425.00
18850.00
Total Direct crew charges/year 226200.00
Increase for hilly area (if necessary)15 33930.00
Total Crew Charges/year (Rs),Cc1 260130.00
Hourly Crew Charges (Rs),Cc2 =Cc1/O 173.42
Estimated annual operational hours,O
Category
Operator - III
Helper (Man mazdoor)
Total Monthly Wages
Schedule life in Hours,H
Helper (Man mazdoor)
Chain saw wood cutter (heavy)
Life time repair provision(% of cost of Equipment),R
Schedule life in Hours,H
Chain saw wood cutter (light)
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Category
Operator - III
Total Monthly Wages
Cost of Equipment(Rs.),E
Schedule life in Years,Y
Cost of Equipment(Rs.),E
Schedule life in Years,Y
2
( iii ) POL and Energy Charges
a For Petrol
F.H.P of Engine 4.90
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1 0.54
Rate of Petrol (Rs./lit),d 70.00
Cost of Petrol (Rs.), Cd= Fc*d 37.73
Lubricant charges,Lc=(Cd*u%)) 9.43
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc 47.16
( iv ) Miscellaneous charges ,Mc =C*z% 2.40
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 262.46
4 1.5 HP
47,000.00
2.00
2400.00
125.00
1500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 14.10
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 17.63
Average hourly depreciation (Rs.),D3= (D1+D2)/2 15.86
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 24.48
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 377 25 9425.00
1 377 25 9425.00
18850.00
Total Direct crew charges/year 226200.00
Increase for hilly area (if necessary)15 33930.00
Total Crew Charges/year (Rs),Cc1 260130.00
Hourly Crew Charges (Rs),Cc2 =Cc1/O 173.42
( iii ) POL and Energy Charges
a For Electricity
Power of Electric motor(KW),P
BHP = 5 P=(746*BHP/1000) 3.73
Hourly Energy Consumption(KWH),Ec=P*0.8*1 2.98
Rate of Electricity (Rs/KWh),e 4.00
Cost of Electricity(Rs.),Ce=Ec*e 11.94
Lubricant charges,Lc=Ce*v% 3.58
(generally v=30%)
Hourly POL and Energy Charges(Rs.), Pe=Ce+Lc 15.52
( iv ) Miscellaneous charges ,Mc =C*z% 2.45
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 231.73
58,00,000.00
5.00
8000.00
100.00
1500.00
Concrete placerCost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
Estimated annual operational hours,O
Category
Operator - III
Helper (Man mazdoor)
Life time repair provision(% of cost of Equipment),R
Schedule life in Years,Y
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Total Monthly Wages
Estimated annual operational hours,O
Concrete cutterCost of Equipment(Rs.),E
3
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 96.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 90.00
Average hourly depreciation (Rs.),D3= (D1+D2)/2 93.00
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 100.00
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 377 25 9425.00
1 377 25 9425.00
0.167 377 25 1573.98
0.167 505 25 2108.38
0.125 673 25 2103.13
24635.48
Total Direct crew charges/year 295625.70
Increase for hilly area (if necessary)15 44343.86
Total Crew Charges/year (Rs),Cc1 339969.56
Hourly Crew Charges (Rs),Cc2 =Cc1/O 226.65
( iii ) POL and Energy Charges
For compressed air
Cost of compressed air ( 100 cfm), Cair 437.51
Hourly POL and Energy Charges(Rs.), Pe=Cair 437.51
( iv ) Miscellaneous charges ,Mc =C*z% 10.00
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 867.16
6 50 HP
8,70,000.00
8.00
10000.00
100.00
1500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 65.25
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 78.30
Average hourly depreciation (Rs.),D3= (D1+D2)/2 71.78
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 87.00
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 377 25 9425.00
1 377 25 9425.00
0.25 505 25 3156.25
0.125 673 25 2103.13
0.25 377 25 2356.25
26465.63
Total Direct crew charges/year 317587.50
Increase for hilly area (if necessary)15 47638.13
Total Crew Charges/year (Rs),Cc1 365225.63
Hourly Crew Charges (Rs),Cc2 =Cc1/O 243.48
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine 50.00
Hourly fuel consumption in litres,Fc=0.22*FHP*1*0.75 8.25
Rate of Diesel(Rs./lit),d 45.00
Cost of Diesel (Rs.), Cd= Fc*d 371.25
Operator
Operator - III
Helper (Man mazdoor)
Total Monthly Wages
Mechanic -1
Foreman (Diploma holder)
Estimated annual operational hours,O
Category
Cost of Equipment(Rs.),E
Schedule life in Years,Y
Diesel Air Compressor (200 cfm)
Watchman
Foreman (Diploma holder)
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Category
Helper (Man mazdoor)
Mechanic -1
Watchman
Total Monthly Wages
4
Lubricant charges,Lc=(Cd*u%)) 92.81
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc 464.06
( iv ) Miscellaneous charges ,Mc =C*z% 8.70
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 875.02
437.51
7 10 HP
4,20,000.00
10.00
10,000.00
80.00
1,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 25.20
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 37.80
Average hourly depreciation (Rs.),D3= (D1+D2)/2 31.50
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 33.60
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount(in Rs.)
2 377 25 18850.00
1 377 25 9425.00
0.25 505 25 3156.25
0.125 673 25 2103.13
0.25 377 25 2356.25
35890.63
Total Direct crew charges/year 430687.50
Increase for hilly area (if necessary)15 64603.13
Total Crew Charges/year (Rs),Cc1 495290.63
Hourly Crew Charges (Rs),Cc2 =Cc1/O 330.19
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine 10.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1 1.10
Rate of Diesel(Rs./lit),d 45.00
Cost of Diesel (Rs.), Cd= Fc*d 49.50
Lubricant charges,Lc=(Cd*u%)) 12.38
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc 61.88
( iv ) Miscellaneous charges ,Mc =C*z% 3.36
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 460.53
8 10 HP
93,000.00
12.00
20,000.00
70.00
1,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 4.65
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 4.19
Average hourly depreciation (Rs.),D3= (D1+D2)/2 4.42
Hourly Use Rate ofor 100 cfm
Diamond DrillCost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Category
Total Monthly Wages
Mechanic -1
Foreman (Diploma holder)
Watchman
Operator - III
Helper (Man mazdoor)
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Electric PumpCost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
5
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 3.26
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount(in Rs.)
1 377 25 9425.00
0.25 471 25 2943.75
0.125 443 25 1384.38
13753.13
Total Direct crew charges/year 165037.50
Increase for hilly area (if necessary)15 24755.63
Total Crew Charges/year (Rs),Cc1 189793.13
Hourly Crew Charges (Rs),Cc2 =Cc1/O 126.53
( iii ) POL and Energy Charges
a For Electricity
Power of Electric motor(KW),P
BHP = 10 P=(746*BHP/1000) 7.46
Hourly Energy Consumption(KWH),Ec=P*0.8*1 5.97
Rate of Electricity (Rs/KWh),e 4.00
Cost of Electricity(Rs.),Ce=Ec*e 23.87
Lubricant charges,Lc=Ce*v% 7.16
(generally v=30%)
Hourly POL and Energy Charges(Rs.), Pe=Ce+Lc 31.03
( iv ) Miscellaneous charges ,Mc =C*z% 0.33
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 165.56
9 5 HP
25,000.00
12.00
20,000.00
70.00
1,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 1.25
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 1.13
Average hourly depreciation (Rs.),D3= (D1+D2)/2 1.19
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 0.88
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount(in Rs.)
1 377 25 9425.00
0.25 471 25 2943.75
0.125 443 25 1384.38
13753.13
Total Direct crew charges/year 165037.50
Increase for hilly area (if necessary)15 24755.63
Total Crew Charges/year (Rs),Cc1 189793.13
Hourly Crew Charges (Rs),Cc2 =Cc1/O 126.53
( iii ) POL and Energy Charges
a For Electricity
Power of Electric motor(KW),P
BHP = 5 P=(746*BHP/1000) 3.73
Hourly Energy Consumption(KWH),Ec=P*0.8*1 2.98
Rate of Electricity (Rs/KWh),e 4.00
Cost of Electricity(Rs.),Ce=Ec*e 11.94
Lubricant charges,Lc=Ce*v% 3.58
(generally v=30%)
Hourly POL and Energy Charges(Rs.), Pe=Ce+Lc 15.52
Cost of Equipment(Rs.),E
Schedule life in Years,Y
Category
Operator - III
Mechanic -1I
Electrician
Total Monthly Wages
Electric Pump
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Category
Operator - III
Mechanic -1I
Electrician
Total Monthly Wages
6
( iv ) Miscellaneous charges ,Mc =C*z% 0.09
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 144.20
10 2.7 HP
25,000.00
15.00
18,000.00
120.00
1,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 1.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 1.25
Average hourly depreciation (Rs.),D3= (D1+D2)/2 1.13
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 1.67
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount(in Rs.)
0.5 456 25 5700.00
0.5 471 25 5887.50
1 456 25 11400.00
0.5 377 25 4712.50
27700.00
Total Direct crew charges/year 332400.00
Increase for hilly area (if necessary)15 49860.00
Total Crew Charges/year (Rs),Cc1 382260.00
Hourly Crew Charges (Rs),Cc2 =Cc1/O 254.84
( iii ) POL and Energy Charges
a For Electricity
Power of Electric motor(KW),P
BHP = 2.7 P=(746*BHP/1000) 2.01
Hourly Energy Consumption(KWH),Ec=P*0.8*1 1.61
Rate of Electricity (Rs/KWh),e 4.00
Cost of Electricity(Rs.),Ce=Ec*e 6.45
Lubricant charges,Lc=Ce*v% 1.93
(generally v=30%)
Hourly POL and Energy Charges(Rs.), Pe=Ce+Lc 8.38
( iv ) Miscellaneous charges ,Mc =C*z% 0.17
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 266.18
11 10 HP
2,00,000.00
10.00
2,400.00
100.00
1,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 12.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 75.00
Average hourly depreciation (Rs.),D3= (D1+D2)/2 43.50
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 83.33
Schedule life in Years,Y
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Grinding MachineCost of Equipment(Rs.),E
Estimated annual operational hours,O
Category
Fitter
Mechanic -1I
Grinder
Total Monthly Wages
Helper
Grout PumpCost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
7
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 377 25 9425.00
1 377 25 9425.00
0.167 471 25 1966.43
0.125 673 25 2103.13
0.167 377 25 1573.98
24493.53
Total Direct crew charges/year 293922.30
Increase for hilly area (if necessary)15 44088.35
Total Crew Charges/year (Rs),Cc1 338010.65
Hourly Crew Charges (Rs),Cc2 =Cc1/O 225.34
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine 10.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1 1.10
Rate of Diesel(Rs./lit),d 45.00
Cost of Diesel (Rs.), Cd= Fc*d 49.50
Lubricant charges,Lc=(Cd*u%)) 12.38
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc 61.88
( iv ) Miscellaneous charges ,Mc =C*z% 8.33
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 422.38
12 128 HP
47,00,000.00
10.00
12,000.00
100.00
1,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 282.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 352.50
Average hourly depreciation (Rs.),D3= (D1+D2)/2 317.25
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 391.67
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 563 25 14075.00
1 377 25 9425.00
0.25 505 25 3156.25
0.25 673 25 4206.25
0.25 377 25 2356.25
33218.75
Total Direct crew charges/year 398625.00
Increase for hilly area (if necessary)15 59793.75
Total Crew Charges/year (Rs),Cc1 458418.75
Hourly Crew Charges (Rs),Cc2 =Cc1/O 305.61
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine 128.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1 14.08
Rate of Diesel(Rs./lit),d 45.00
Cost of Diesel (Rs.), Cd= Fc*d 633.60
Lubricant charges,Lc=(Cd*u%)) 158.40
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc 792.00
Operator I
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Schedule life in Hours,H
Category
Helper
Watchman
Helper
Category
Operator III
Mechanic -1I
Foreman (Diploma holder)
Total Monthly Wages
Hydraulic Excavator (0.93 cum)Cost of Equipment(Rs.),E
Schedule life in Years,Y
Mechanic -1
Foreman (Diploma holder)
Watchman
Total Monthly Wages
8
( iv ) Miscellaneous charges ,Mc =C*z% 39.17
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 1845.70
13 12 kg
58,000.00
10.00
8000.00
80.00
1500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 3.48
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 6.53
Average hourly depreciation (Rs.),D3= (D1+D2)/2 5.00
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 5.80
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 377 25 9425.00
0.5 377 25 4712.50
0.2 505 25 2525.00
0.125 471 25 1471.88
0.125 377 25 1178.13
19312.50
Total Direct crew charges/year 231750.00
Increase for hilly area (if necessary)15 34762.50
Total Crew Charges/year (Rs),Cc1 266512.50
Hourly Crew Charges (Rs),Cc2 =Cc1/O 177.68
( iii ) POL and Energy Charges
For compressed air
Cost of compressed air ( 100 cfm), Cair 437.51
Hourly POL and Energy Charges(Rs.), Pe=Cair 437.51
( iv ) Miscellaneous charges ,Mc =C*z% 0.58
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 626.57
14 100 HP
12,00,000.00
10.00
12,000.00
150.00
1,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 72.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 90.00
Average hourly depreciation (Rs.),D3= (D1+D2)/2 81.00
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 150.00
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 396 25 9900.00
2 377 25 18850.00
0.25 471 25 2943.75
0.25 443 25 2768.75
0.5 673 25 8412.50
1 377 25 9425.00
52300.00
Life time repair provision(% of cost of Equipment),R
Jack hammerCost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
Cost of Equipment(Rs.),E
Category
Estimated annual operational hours,O
Operator - III
Electrician
Foreman
Schedule life in Years,Y
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Operator II
Total Monthly Wages
Estimated annual operational hours,O
Helper
Helper (Man mazdoor)
Mechanic -II
Watchman
Total Monthly Wages
Mobile Crane 10 T
Category
Mechanic -II
Watchman
Supervisor
9
Total Direct crew charges/year 627600.00
Increase for hilly area (if necessary)15 94140.00
Total Crew Charges/year (Rs),Cc1 721740.00
Hourly Crew Charges (Rs),Cc2 =Cc1/O 481.16
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine 100.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1 11.00
Rate of Diesel(Rs./lit),d 45.00
Cost of Diesel (Rs.), Cd= Fc*d 495.00
Lubricant charges,Lc=(Cd*u%)) 123.75
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc 618.75
( iv ) Miscellaneous charges ,Mc =C*z% 15.00
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 1345.91
15 10 HP
5,00,000.00
10.00
9,000.00
80.00
1,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 30.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 50.00
Average hourly depreciation (Rs.),D3= (D1+D2)/2 40.00
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 44.44
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 396 25 9900.00
1 377 25 9425.00
0.25 471 25 2943.75
0.125 673 25 2103.13
0.25 377 25 2356.25
26728.13
Total Direct crew charges/year 320737.50
Increase for hilly area (if necessary)15 48110.63
Total Crew Charges/year (Rs),Cc1 368848.13
Hourly Crew Charges (Rs),Cc2 =Cc1/O 245.90
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine 10.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1 1.10
Rate of Diesel(Rs./lit),d 45.00
Cost of Diesel (Rs.), Cd= Fc*d 49.50
Lubricant charges,Lc=(Cd*u%)) 12.38
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc 61.88
( iv ) Miscellaneous charges ,Mc =C*z% 4.44
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 396.66
Percussion DrillCost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Helper
Mechanic -II
Foreman (Diploma holder)
Category
Operator II
Watchman
Total Monthly Wages
10
16 32 HP
10,00,000.00
8.00
10,000.00
175.00
1,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 75.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 90.00
Average hourly depreciation (Rs.),D3= (D1+D2)/2 82.50
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 175.00
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 436 25 10900.00
1 377 25 9425.00
0.125 505 25 1578.13
0.167 377 25 1573.98
23477.10
Total Direct crew charges/year 281725.20
Increase for hilly area (if necessary)15 42258.78
Total Crew Charges/year (Rs),Cc1 323983.98
Hourly Crew Charges (Rs),Cc2 =Cc1/O 215.99
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine 32.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.3*1 2.11
Rate of Diesel(Rs./lit),d 45.00
Cost of Diesel (Rs.), Cd= Fc*d 95.04
Lubricant charges,Lc=(Cd*u%)) 23.76
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc 118.80
( iv ) Miscellaneous charges ,Mc =C*z% 17.50
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 609.79
17 100 HP
20,00,000.00
10.00
10,000.00
120.00
1,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 120.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 180.00
Average hourly depreciation (Rs.),D3= (D1+D2)/2 150.00
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 240.00
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 396 25 9900.00
1 377 25 9425.00
0.25 471 25 2943.75
0.125 673 25 2103.13
0.25 377 25 2356.25
26728.13
Mechanic -I
Watchman
Helper
Mechanic -II
Life time repair provision(% of cost of Equipment),R
Tipper 5 TCost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
Schedule life in Years,Y
Total Monthly Wages
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Category
Driver
Helper
Watchman
Total Monthly Wages
Transit Mixer (4 cum)Cost of Equipment(Rs.),E
Estimated annual operational hours,O
Category
Operator II
Foreman (Diploma holder)
11
Total Direct crew charges/year 320737.50
Increase for hilly area (if necessary)15 48110.63
Total Crew Charges/year (Rs),Cc1 368848.13
Hourly Crew Charges (Rs),Cc2 =Cc1/O 245.90
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine 100.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1 11.00
Rate of Diesel(Rs./lit),d 45.00
Cost of Diesel (Rs.), Cd= Fc*d 495.00
Lubricant charges,Lc=(Cd*u%)) 123.75
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc 618.75
( iv ) Miscellaneous charges ,Mc =C*z% 24.00
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 1278.65
18 50 HP
15,00,000.00
12.00
20,000.00
175.00
1,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 75.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 67.50
Average hourly depreciation (Rs.),D3= (D1+D2)/2 71.25
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 131.25
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 396 25 9900.00
1.5 377 25 14137.50
1.5 471 25 17662.50
0.5 396 25 4950.00
2 456 25 22800.00
0.5 673 25 8412.50
1 505 25 12625.00
90487.50
Total Direct crew charges/year 1085850.00
Increase for hilly area (if necessary)15 162877.50
Total Crew Charges/year (Rs),Cc1 1248727.50
Hourly Crew Charges (Rs),Cc2 =Cc1/O 832.49
( iii ) POL and Energy Charges
a For Electricity
Power of Electric motor(KW),P
BHP = 50 P=(746*BHP/1000) 37.30
Hourly Energy Consumption(KWH),Ec=P*0.8*1 29.84
Rate of Electricity (Rs/KWh),e 4.00
Cost of Electricity(Rs.),Ce=Ec*e 119.36
Lubricant charges,Lc=Ce*v% 35.81
(generally v=30%)
Hourly POL and Energy Charges(Rs.), Pe=Ce+Lc 155.17
( iv ) Miscellaneous charges ,Mc =C*z% 13.13
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 1203.28
Sheet Bending MachineCost of Equipment(Rs.),E
Khalasi
Schedule life in Years,Y
Schedule life in Hours,H
Fabricator
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Category
Operator II
Helper
Mechanic -II
Foreman (Diploma holder)
Supervisor
Total Monthly Wages
12
19 6 cum/hr
3,00,000.00
5.00
6000.00
100.00
1500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 36.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 45.00
Average hourly depreciation (Rs.),D3= (D1+D2)/2 40.50
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 50.00
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 396 25 9900.00
1 377 25 9425.00
0.5 471 25 5887.50
0.125 673 25 2103.13
0.25 377 25 2356.25
29671.88
Total Direct crew charges/year 356062.50
Increase for hilly area (if necessary)15 53409.38
Total Crew Charges/year (Rs),Cc1 409471.88
Hourly Crew Charges (Rs),Cc2 =Cc1/O 272.98
( iii ) POL and Energy Charges
For compressed air
Cost of compressed air ( 100 cfm), Cair 437.51
Hourly POL and Energy Charges(Rs.), Pe=Cair 437.51
( iv ) Miscellaneous charges ,Mc =C*z% 5.00
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 805.99
20 1.8 HP
20,000.00
2.00
2,400.00
125.00
1,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 6.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 7.50
Average hourly depreciation (Rs.),D3= (D1+D2)/2 6.75
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 10.42
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount(in Rs.)
1 377 25 9425.00
0.5 377 25 4712.50
14137.50
Total Direct crew charges/year 169650.00
Increase for hilly area (if necessary)15 25447.50
Total Crew Charges/year (Rs),Cc1 195097.50
Hourly Crew Charges (Rs),Cc2 =Cc1/O 130.07
Shortcrete/Guniting machine
Weed cutterCost of Equipment(Rs.),E
Estimated annual operational hours,O
Category
Watchman
Total Monthly Wages
Foreman (Diploma holder)
Mechanic -II
Cost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
Operator - II
Helper (Man mazdoor)
Life time repair provision(% of cost of Equipment),R
Schedule life in Years,Y
Schedule life in Hours,H
Category
Operator III
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Helper
Total Monthly Wages
13
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine 1.80
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1 0.20
Rate of Diesel(Rs./lit),d 45.00
Cost of Diesel (Rs.), Cd= Fc*d 8.91
Lubricant charges,Lc=(Cd*u%)) 2.23
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc 11.14
( iv ) Miscellaneous charges ,Mc =C*z% 1.04
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 159.41
21 2.7 HP
53,000.00
5.00
10,000.00
50.00
1,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 6.36
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 4.77
Average hourly depreciation (Rs.),D3= (D1+D2)/2 5.57
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 2.65
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 377 25 9425.00
0.5 471 25 5887.50
1 456 25 11400.00
1 471 25 11775.00
0.25 443 25 2768.75
41256.25
Total Direct crew charges/year 495075.00
Increase for hilly area (if necessary)15 74261.25
Total Crew Charges/year (Rs),Cc1 569336.25
Hourly Crew Charges (Rs),Cc2 =Cc1/O 379.56
( iii ) POL and Energy Charges
a For Electricity
Power of Electric motor(KW),P
BHP = 2.7 P=(746*BHP/1000) 2.01
Hourly Energy Consumption(KWH),Ec=P*0.8*1 1.61
Rate of Electricity (Rs/KWh),e 4.00
Cost of Electricity(Rs.),Ce=Ec*e 6.45
Lubricant charges,Lc=Ce*v% 1.93
(generally v=30%)
Hourly POL and Energy Charges(Rs.), Pe=Ce+Lc 8.38
( iv ) Miscellaneous charges ,Mc =C*z% 0.27
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 396.42
22 2 HP
19,500.00
3.00
6,000.00
70.00
1,500.00
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Helper
Mechanic -II
Fitter
Welder
Electrician
Total Monthly Wages
Welding SetCost of Equipment(Rs.),E
Schedule life in Years,Y
Vibrator ( Diesel)Cost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
Estimated annual operational hours,O
Category
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
14
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 3.90
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 2.93
Average hourly depreciation (Rs.),D3= (D1+D2)/2 3.41
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 2.28
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 377 25 9425.00
0.5 377 25 4712.50
14137.50
Total Direct crew charges/year 169650.00
Increase for hilly area (if necessary)15 25447.50
Total Crew Charges/year (Rs),Cc1 195097.50
Hourly Crew Charges (Rs),Cc2 =Cc1/O 130.07
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine 2.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1 0.22
Rate of Diesel(Rs./lit),d 45.00
Cost of Diesel (Rs.), Cd= Fc*d 9.90
Lubricant charges,Lc=(Cd*u%)) 2.48
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc 12.38
( iv ) Miscellaneous charges ,Mc =C*z% 0.23
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 148.36
23 75 HP
7,80,000.00
10.00
15,000.00
200.00
1,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 46.80
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 46.80
Average hourly depreciation (Rs.),D3= (D1+D2)/2 46.80
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 104.00
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
1 377 25 9425.00
0.25 505 25 3156.25
0.125 673 25 2103.13
1 396 25 9900.00
0.167 377 25 1573.98
13577.10
Total Direct crew charges/year 162925.20
Increase for hilly area (if necessary)15 24438.78
Total Crew Charges/year (Rs),Cc1 187363.98
Hourly Crew Charges (Rs),Cc2 =Cc1/O 124.91
Estimated annual operational hours,O
Life time repair provision(% of cost of Equipment),R
Watchmen
Category
Operator III
Helper
Total Monthly Wages
Category
Loader 0.5 cumCost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
Total Monthly Wages
Helper
Mechanic I
Operator II
Foreman (Diploma holder)
15
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine 75.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.58*1 9.57
Rate of Diesel(Rs./lit),d 45.00
Cost of Diesel (Rs.), Cd= Fc*d 430.65
Lubricant charges,Lc=(Cd*u%)) 107.66
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc 538.31
( iv ) Miscellaneous charges ,Mc =C*z% 10.40
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 824.42
24 50 HP
3,00,000.00
12.00
20,000.00
80.00
1,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 15.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 13.50
Average hourly depreciation (Rs.),D3= (D1+D2)/2 14.25
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 12.00
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
0.25 396 25 2475.00
0.25 471 25 2943.75
0.5 377 25 4712.50
4712.50
Total Direct crew charges/year 56550.00
Increase for hilly area (if necessary)15 8482.50
Total Crew Charges/year (Rs),Cc1 65032.50
Hourly Crew Charges (Rs),Cc2 =Cc1/O 43.36
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine 50.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1 5.50
Rate of Diesel(Rs./lit),d 45.00
Cost of Diesel (Rs.), Cd= Fc*d 247.50
Lubricant charges,Lc=(Cd*u%)) 61.88
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc 309.38
( iv ) Miscellaneous charges ,Mc =C*z% 1.20
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 380.18
2517,167.50
6.00
12,000.00
70.00
1,500.00
Life time repair provision(% of cost of Equipment),R
Operator II
Schedule life in Hours,H
Ventilation BlowerCost of Equipment(Rs.),E
Mechanic II
Helper
Schedule life in Years,Y
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Category
Total Monthly Wages
Accessories for pumping
Estimated annual operational hours,O
Cost of Equipment(Rs.),E
Schedule life in Years,Y
16
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 1.72
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 1.29
Average hourly depreciation (Rs.),D3= (D1+D2)/2 1.50
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 1.00
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
0.5 377 25 4712.50
0.25 471 25 2943.75
7656.25
Total Direct crew charges/year 91875.00
Increase for hilly area (if necessary)15 13781.25
Total Crew Charges/year (Rs),Cc1 105656.25
Hourly Crew Charges (Rs),Cc2 =Cc1/O 70.44
( iii ) Miscellaneous charges ,Mc =C*z% 0.10
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 73.04
26 0 HP
3,15,000.00
10.00
10,000.00
80.00
1,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 18.90
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 28.35
Average hourly depreciation (Rs.),D3= (D1+D2)/2 23.63
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 25.20
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
0.5 673 25 8412.50
1 377 25 9425.00
17837.50
Total Direct crew charges/year 214050.00
Increase for hilly area (if necessary)15 32107.50
Total Crew Charges/year (Rs),Cc1 246157.50
Hourly Crew Charges (Rs),Cc2 =Cc1/O 164.11
( iv ) Miscellaneous charges ,Mc =C*z% 2.52
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 215.45
27 38 cum/ hr.
42,00,000.00
5.00
8,000.00
100.00
2,500.00
1 Ownership Cost:
( i ) Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O) 302.40
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H 472.50
Average hourly depreciation (Rs.),D3= (D1+D2)/2 387.45
Concrete PumpCost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Schedule life in Hours,H
Total Monthly Wages
Category
Helper
Plumber
Total Monthly Wages
Radiografic testing machine
Category
Foreman (Diploma holder)
Helper (Man mazdoor)
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Cost of Equipment(Rs.),E
Schedule life in Years,Y
17
2 Operational Cost:
( i ) Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H 525.00
( ii ) O&M crew charges
Nos Wages/ shift Days/month Amount (in Rs.)
0.125 673 25 2103.13
1 396 25 9900.00
0.17 471 25 2001.75
1 377 25 9425.00
0.17 377 25 1602.25
11027.25
Total Direct crew charges/year 132327.00
15 19849.05
Total Crew Charges/year (Rs),Cc1 152176.05
Hourly Crew Charges (Rs),Cc2 =Cc1/O 503.23
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine 75.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1 9.57
Rate of Diesel(Rs./lit),d 45.00
Cost of Diesel (Rs.), Cd= Fc*d 430.65
Lubricant charges,Lc=(Cd*u%)) 107.66
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc 538.31
( iv ) Miscellaneous charges ,Mc =C*z% 52.50
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc 2006.49
Total Monthly Wages
Increase for hilly area
(if necessary)
Category
Foreman
Operator Gr II
Mechanic Gr. II
Helper
Watchman
18
Sl.
No.Description of items Rate Amount Remarks
1 1 mDrilling charges using jack hammer
0.13 hr Jack hammer (UR) 1 hr out turn 7.5 m/hr
0.01 No Drill bit 1 Each Life 150 m
5 % Extra for sharpening @ 5% of above
Total /m
2 1 m Drilling charges using Diamond drill
for earth and boulders
0.10 hr Diamond drill (UR) 1 hr out turn 10m/hr
5 % Shifting charges @ 5 % of above
0.1 No Drill bit 1 Each Life 10 m
5 % Extra for sharpening @ 5% of above
Total /m
3 1 m Drilling charges using Diamond drill
for rock
2.00 hr Diamond drill (UR) 1 hr out turn 0.5 m/hr
5 % Shifting charges @ 5 % of above
0.10 No Drill bit 1 Each Life 10 m
5 % Extra for sharpening @ 5% of above
Total /m
4 1 m Drilling charges using percussion drill
0.50 hr Percussion drill (UR) 1 hr out turn 2 m/hr
5 % Shifting charges @ 5 % of above
0.03 No Drill bit 1 Each Life 30 m
5 % Extra for sharpening @ 5% of above
Total /m
5 1 hp/hrCost of accessories for pumping
Accessories for 60m
60.00 m 75 mm dia. Pipe (12 Kg/ cm2) 1 m
5.00 No Bend 1 Each
1.00 No Foot valve 1 Each
1.00 No Non-Return valve 1 Each
1.00 No Ball valve 1 Each
5.00 No Pipe Nipple 1 Each
5 % Spares @ 5% of accessories
Total /hp/hr
ANNEXURE B - ADDITIONAL USE RATE OF EQUIPMENTS
Quantity Unit
Sl.No Machinery
Co
st
of
Eq
uip
me
nt
(E)
Sc
he
du
le lif
e in
Ye
ar
(Y)
Sc
he
du
le lif
e in
Ho
ur
(H
)
Lif
e t
ime
re
pa
ir p
rov
isio
n (
R)
Es
tim
ate
d a
nn
ua
l o
pe
rati
on
al
ho
urs
(O
)
Op
era
tor-
I
Op
era
tor
- II
Op
era
tor
-III
He
lpe
r
Rig
ge
r (M
ec
ha
nic
II)
Fit
ter
Kh
ala
si
Gri
nd
er
We
lde
r
Fa
bri
ca
tor
Me
ch
an
ic -
I
Fo
rem
an
(D
iplo
ma
)
Su
pe
rvis
or
(IT
I)
Ele
ctr
icia
n
Plu
mb
er
Dri
ve
r
Wa
tch
me
n
Ho
url
y U
se
ra
te
1 Batching & Mixing plant (27 cum) 70 kw 5500000 18 30000 75 1500 2 6 0.5 0.5 1
2 Chain saw wood cutter (light) 2.7 HP 28000 2 2400 125 1500 1 1
3 Chain saw wood cutter (heavy) 4.9 HP 46000 2 2400 125 1500 1 1
4 Concrete cutter 1.5 HP 47000 2 2400 125 1500 1 1
5 Concrete placer 45 800000 5 8000 100 1500 1 1 0.167 0.125 0.167
6 Diamond Drill 10 HP 420000 10 10000 80 1500 2 1 0.25 0.125 0.25
7 Diesel Air Compressor (200 cfm) 50 HP 870000 8 10000 100 1500 1 1 0.25 0.125 0.25
8 Electric Pump 10 HP 93000 12 20000 70 1500 1 0.25 0.125
9 Electric Pump 5 HP 25000 12 20000 70 1500 1 0.25 0.125
10 Grinding Machine 2.7 HP 25000 15 18000 120 1500 0.5 0.5 0.5 1
11 Grout Pump 10 HP 200000 10 2400 100 1500 1 1 0.167 0.125 0.167
12 Hydraulic Excavator (0.93 cum) 128 HP 4700000 10 12000 100 1500 1 1 0.25 0.25 0.25
13 Jack hammer 12 Kg 58000 10 8000 80 1500 1 0.5 0.125 0.2 0.125
14 Loader 0.5 cum 75 HP 780000 10 15000 200 1500 1 1 0.25 0.125 0.167
15 Mobile Crane 10 T 100 HP 1200000 10 12000 150 1500 1 2 0.25 0.5 0.5 0.33 0.25 1
16 Percussion Drill 10 HP 500000 10 9000 80 1500 1 1 0.25 0.125 0.25
17 Tipper 5 T 32 HP 1000000 8 10000 175 1500 1 0.125 1 0.167
18 Transit Mixer (4 cum) 100 HP 2000000 10 10000 120 1500 1 1 0.25 0.125 0.25
19 Sheet Bending Machine 50 HP 1500000 12 20000 175 1500 1 1.5 1.5 0.5 2 0.5 1
20 Shortcrete/Guniting machine 6 cum/hr 300000 5 6000 100 1500 1 1 0.5 0.125 0.25
21 Ventilation Blower 50 HP 300000 12 20000 80 1500 0.25 0.5 0.25
22 Weed cutter 1.8 HP 20000 2 2400 125 1500 1 0.5
23 Welding Set 2.7 HP 53000 5 10000 50 1500 1 0.5 1 1 0.25
24 Vibrator ( Diesel) 2 HP 19500 3 6000 70 1500 1 0.5
25 Accessories for pumping 10 HP 17167.5 6 12000 70 1500 0.5 0.25
26 Radiografic testing machine 315000 10 10000 80 1500 1 0.5
27 Concrete Pump 38 cum/hr 4200000 5 8000 100 2500 1 1 0.17 0.125 0.17
Cost of Labour
ANNEXURE C - MACHINERY DETAILS
Ca
pa
cit
y