23/08/2018 tak save energy 1 TO KERALA STATE ELECTRICITY BOARD
23/08/2018 tak save energy 2
T A Kuriyakose
Assistant Executive Engineer
9446008482
Power & TelecommunicationCo-ordination Committee
23/08/2018 tak save energy 4
Power & TelecommunicationCo-ordination Committee
Power and Telecom lines constitute two essentiallife lines to any community. Very often they willhave to follow the same road or railwayalignment and thus will have to exist close toeach other.
Any high voltage power line sets up in its vicinityelectric and magnetic fields. Communicationcircuits coming under the influence of thesefields will experience extraneous induction.
23/08/2018 tak save energy 5
PTCC
The extraneous induction under certain conditionsmay induce noise in communication circuits and/ orcause danger to equipments / personnel.
Therefore it is very essential that whenever powerand telecom lines have to take rights of way close toeach other, suitable coordination measures areeffected to derive maximum benefits from both thesystems.
23/08/2018 tak save energy 6
PTCC
For carrying out such coordination, the Govt.of India constituted a central standing bodycalled the Power and TelecommunicationCoordination Committee in 1949.
23/08/2018 tak save energy 7
Various Levels of PTCC
1. Central 2. State 3. SSA or Telecom Dist. 4. Divisional 5. Sub-Divisional
23/08/2018 tak save energy 8
Membership in Central PTCC
1. Chief Engineer (LD & T),Central Electricity Authority,New Delhi
2. Chief General Manager, T&D Circle,Bharat SancharNigamLtd ( BSNL), Jabalpur ( Chairman alternate year )
3. Director ( PTCC ),Central Electricity Authority,NewDelhi ( Secretary (Power) )
4. Deputy General Manger, T&D Circle,BSNL, Jabalpur( Secretary( Telecom)
23/08/2018 tak save energy 9
Membership in Central PTCC
5. Director (Telecom),Railway Board,New Delhi - Member6. Jt. DDG (ML), Ministry of Communication - Member7. Chairman/ Co-Chairman 0f SLPTCC - Member8. Director (GP), Ministry of Communication - Member9. Representative of Dept. of Power - Member10. A representative from the Army Headquarters -
Member11. DDG(NE), TEC, BSNL, Hyderabad - Member12. DET (PTCC), T & D Circle, BSNL - Associate Member
23/08/2018 tak save energy 10
State Level PTCC
After its inception in 1949 all cases for PTCC clearancewere being referred to the Central PTCC. The work at theCentral level increased enormously due to the enormousspurt in both the Power and Communication sectors. Theclearance of 11 KV lines was entrusted to DEs(T) of theTelecom Department on the basis of guidelines prepared bythe Central PTCC. It was necessary to further decentralizethe work relating to lines up to 33 KV. Accordingly, StateLevel Committees were set up in 1968 with representationfrom the Power and Telecom sides. A ‘Simplified Procedure’for issue of clearance in such cases was prepared by theCentral PTCC.
23/08/2018 tak save energy 11
Frequency of SLPTCC meeting
As per the decision taken in 58th Central PTCCmeeting held at Darjeeling on 25.2.1992 theState Level PTCC meetings should be held asfrequently as possible but not later than aquarter/3 months. In Telecom Circles wherelarge number of unguarded power crossings arepending and more electrocution accidentsoccurred, the meetings in those circles shouldbe convened more frequently In order todecide any emergency cases, special State LevelPTCC meetings can also be requisitioned andthe power of requisition of such meetings isvested with Chairman State Level PTCC.
23/08/2018 tak save energy 12
Functions of SLPTCC
(i) To review the progress of route approvalcases of 11 KV lines dealt with by TelecomDivisional Engineers.
(ii)To consider route approval cases up toservice voltages of 33 KV.
23/08/2018 tak save energy 13
Functions of SLPTCC …..
(iii)To consider re-engineering schemes forcases where induction exceeds the protectionlimit for GD tubes.
(iv)To co-ordinate and watch the progress ofinstallation of protective measures and re-engineering works and issue of energizationcertificates on completion of protective works.
23/08/2018 tak save energy 14
Functions of SLPTCC …..
(v) To consider violation of PTCC regulationsand take suitable corrective measures.
(vi) To discuss cases of power lines of 33 KVand above held up for PTCC clearance.
23/08/2018 tak save energy 15
CODE OF PRACTICE FOR OVER-HEAD TELECOM LINES
Rule 87 of Indian electricity rules ensuresstatutory obligation for both power andtelecom authorities to follow PTCC code ofpractice at the crossings to avoid contacthazard. ( Refer Central Electricity Authority (Measures relating toSafety and Electricity Supply) Regulations, 2007.Section 23. Safetyrequirements pertaining to overhead lines, under ground cablesand generating stations Page 14 :-SCHEDULE-V Safetyrequirements for overhead lines, under ground cables andgenerating stations Page 53 )
The power lines should always cross over thetelecom lines and the angle of crossing shouldbe as nearly a right angle as possible.
23/08/2018 tak save energy 16
CODE OF PRACTICE FOR OVER-HEAD TELECOM LINES
The protection envisaged for negotiating the crossings is based on the voltage category of the power line involved
Wherever guarding is done, it should beearthed at both ends and the earthresistance for this purpose should be < 3ohms and in no condition it should be >10 ohms.
23/08/2018 tak save energy 17
CODE OF PRACTICE FOR OVER-HEAD TELECOM LINES
Power Contact Protectors (PCPs) should beprovided on all top telecom conductors at thepower crossings with power lines of categoryfrom 3 KV up to and including 33 KV. This is inaddition to the guarding arrangementrecommended above. The earth resistance forPCPs should be preferably 1 ohm and in nocondition it should be > 10 ohms for theirsatisfactory performance.
23/08/2018 tak save energy 18
SAFE SEPARATIONS FOR CROSSINGS BETWEEN TELECOM & POWER LINES
Sl.No
Voltage Category of Power Line
Minimum Recommended Safe Separation
1 Low & Medium ( < 650 V )
a With Insulated Power wires >0.75 m
b With bare Power wires
(i)With guarding on PowerPost > 0.915 m
(ii)Guarding onTelecompost >1.22 m
23/08/2018 tak save energy 19
SAFE SEPARATIONS FOR CROSSINGS BETWEEN TELECOM & POWER LINES
Sl.No
Voltage Category of Power Line
Minimum Recommended Safe Separation
2 High Voltage Lines ( HT ) ( 650 to 36KV)
a For 7.2 KV and below >1.07 m
b For 7.2 KV upto 36 KV > 1.22 m
23/08/2018 tak save energy 20
SAFE SEPARATIONS FOR CROSSINGS BETWEEN TELECOM & POWER LINES
Sl.No
Voltage Category of Power Line
Minimum Recommended Safe Separation
3 EHT Lines
a 36 KV to 72.5 KV >2.44 m
b 72.5 KV to 145 KV >2.74 m
c 145 KV to 245 KV > 3.05 m
d Above 245 KV >3.05 m +0.305m for every addl 33 KV
23/08/2018 tak save energy 21
GUIDELINES FOR CROSSING OF
POWER AND TELECOM CABLES
Minimum Depth of laying of UG Cables
3.3KV to 11 KV - 0.9 M
11 KV to 33 KV - 1.05 M
LT & Control Cable - 0.75 M
At road & railway crossing – 1.00 M
23/08/2018 tak save energy 22
GUIDELINES FOR CROSSING OF POWER AND TELECOM CABLES
CLEARANCES POWER CABLES TO POWER CABLES: Not necessary
POWER CABLES TO CONTROL CABLES: 0.2 M
POWER CABLES TO COMMUNICATIONS CABLES: 0.6 M
( Preferably 0.6 M but not less than 0.3 M )
POWER CABLES TO GAS/WATER MAINS: 0.3 M
23/08/2018 tak save energy 23
Protection of Telecom systems
In spite of the Growing sophistication intelecommunication equipments and technologicaladvancements, the DANGER perception continuesfor the electronic equipments in the telecomnetwork because of their vulnerability to voltagesand current induction.
While the voltage transients can damage or destroythe equipment, over current poses a far greaterpotential hazard i.e., Fire, and the voltages ¤ts continuously induced longitudinally resultin disturbances which can affect the performance oftelecommunications systems.
23/08/2018 tak save energy 24
Reasons for over voltage & over current in telecom lines
(i). CONTACT
(ii). INDUCTION- Both Electro Static & Electro
Magnetic
(iii). EARTH POTENTIAL RISE
(iv). LIGHTNING
23/08/2018 tak save energy 25
ELECTOMAGNETIC INDUCTION:
Electromagnetic induction on to a telecomline/cable from nearby power line ispredominant only under the faulty condition ofthe power line.
Single line to ground fault condition on powerline is considered, in view of possiblemaximum current flow to earth, for decidingthe protection on paralleling telecomconductors.
23/08/2018 tak save energy 26
ELECTOMAGNETIC INDUCTION:
As the duration of dangerous voltages on aparalleling telecom conductor is limited to theduration of fault on the inducing power line,human safety can be ensured if these voltagesare limited to the CCITT limits. *430v for lowreliability power lines ( uto 33 KV)
* 650 V for high reliability power lines (>33KV) respectively.
23/08/2018 tak save energy 27
INDUCED VOLTAGE
The quantum of voltage induced dependsupon the following:
(a) Length of parallelism
(b) Fault current
(c) Mutual coupling
(d) Soil Resistivity
23/08/2018 tak save energy 28
SOIL RESISTIVITY Soil Resistivity is an important factor which determines the
magnitude of electromagnetic induction between the power
and telecom circuits. When an earth fault occurs on anyone
phase of the power line, large fault currents flow in the power
conductors and return through earth. Under such conditions,
the power line and the neighboring , telephone line form
two parallel earth return circuits with a high degree of mutual
coupling. The mutual coupling increases with soil resistivity.
Since the induced voltage in the communication circuit is the
product of fault current and mutual impedance, the value of
the induced voltage increases with increase in soil resistivity.
23/08/2018 tak save energy 34
IV Calculation
Details required : Soil resistivity in cm, Fault current in A, Data from Curson Curves .
Calculated values :
Mutual Coupling between power lines and Telecom lines ( MC ) in , Length of parallelism ( LOP ) in metres, Induced Vottage ( IV ) in Volts
23/08/2018 tak save energy 35
Protection - Methods
Gas discharge (GD) tubes should be usedon the paralleling telecom conductors inthe length of parallelism, one each at theend and the remaining in between atequidistance intervals.
23/08/2018 tak save energy 36
The number of GD-tubes to be providedcan be arrived at by dividing the inducedvoltage with 300 and rounding off theresult to the next higher digit, ifnecessary. This procedure is adoptedwhen the induced voltages are in therange of 430 to 2000 volts.
23/08/2018 tak save energy 37
When the induced voltages are 2000 V ormore, the 20-GD-tube formula, given below, isused in order to arrive at the number of GD-tubes and these are limited to (twenty) due tonoise considerations.
(i).FOR HIGH RELIABILITY POWER LINES (i.e.>33KV) ______
650 ≥ E/N [ 1 + l 10N ]
[ √ Z ]
23/08/2018 tak save energy 38
(ii). FOR LOW RELIABILITY POWER LINES,(i.e. up to 33KV) _____
430 ≥ E/N [ 1 + l 10N ]
[ √ Z ]
Where,
E is the Induced Voltage in Volts
N is the number of GD-Tubes required
Z is the Total Impedance of effected portion oftelecom line in Ohms,
And Z= Z0 X L, Where Z0 is the Impedance per kmof telecom line in Ohms and L is Length ofparallelism in kms.
23/08/2018 tak save energy 39
By applying this formula, the maximumnumber of GD-tubes that can be installedon telecom line is limited to 20. If thenumber arrived at is more than 20, itbecomes a case of re-engineering, whenseparation is increased or telecomcircuits are changed to another media.
23/08/2018 tak save energy 40
ABOUT GD TUBE
The gas discharge tube essentiallyconsists of three tungsten electrodessealed in a special glass envelopecontaining a mixture of inert gases,mainly neon. Two of the electrodes arefor connections to the lines and the thirdis connected to the earth electrodes.
23/08/2018 tak save energy 41
ABOUT GD TUBE
If the potential difference across theelectrodes rises to a certain critical value(the striking value) the gas is ionizedand becomes conducting. This conditionwill continue till the potential differenceacross the electrodes falls to theextinction voltage value.
23/08/2018 tak save energy 42
EARTH POTENTIAL RISE
When an earth fault occurs in a powersystem, some of the fault current returnsvia the earth through the earthingsystem, and this current raises thepotential of the earthing system withrespect to a remote earth for theduration of the fault.
23/08/2018 tak save energy 44
EPR LIMITSType of Telecom Plant
Power lines upto 33 KV
Power lines >33KV
Terminal Apparatus, Joints,Cabinets, Pillars,
Manholes,Pits, Poles
430 V 650 V
Telephone Exchanges 430 V 430 V
Metal Sheathed cable 430 V 650 V
Plastic Insulated cable 7 KV 7 KV
PIJF Cable 10 KV 10 KV
23/08/2018 tak save energy 45
HAZARD ZONE
The hazard zone near an earthingsystem varies from some tens to somethousands of metres, depending on soilresistivity, layout of the earth mat,power network, fault current and otherlocal conditions.
23/08/2018 tak save energy 46
The EPR zone or the distance ‘X’ in metres at whichthe EPR may rise to a value ‘Ex’ can be determinedfrom the formula:
(i). For Simple Earthing System such as singleelectrode earthing system:
ρ l
X = ------ Metres
2 π Ex
Where, ρ is the Soil Resistivity in Ohm metre
I is the Fault Current in Amps and
Ex is the EPR voltage Limit as specified in the Code ofPractice above.
23/08/2018 tak save energy 47
(ii).For large earthing systems:
Emax x D IR x D
Ex = ------------------ = -------------
(d + D) (d + D)
Where, Ex is the Potential at radial distance of ‘d’ fromthe perimeter of the earth mat in volts.
I is the maximum fault current through theearth mat in Amps.
R is the measured Resistance of the earthmat in ohm.
D is the diagonal distance of the mat inmetres
d is the distance in metres from theperimeter of the earth mat.
23/08/2018 tak save energy 48
GENERAL PRECAUTIONS IN EPR
ZONE
The telecom circuits should be provided in plasticinsulated and unscreened plastic sheathed cable laid inrigid PVC conduit.
Location of cable joints, pillars, cabinets andterminations, which require personnel to attend, shouldbe avoided in EPR zone.
While working in EPR zone, the staff should insulatethemselves from the earth by standing on an insulatingmat having a specified insulation, withstanding voltage ofat least 15 KV for one minute. Insulated tools, gloves andfootwear should also be used.
23/08/2018 tak save energy 49
THE PTCC PROPOSAL
THE ROUTE MAP
SCALE OF MAP AS PER PTCC NORMS
THE QUESTIONNAIRE
THE SINGLE LINE DIAGRAM
THE SOIL RESISTIVITY DATA
TOWER CONFIGURATION WITH DATA OF GENERATORS,TRANSFORMERS, REACTORS
23/08/2018 tak save energy 50
THE ROUTE MAP
THE POWER LINE ON ROUTE MAP MAY BE MARKEDWITH RED COLOUR ONLY
THE SCALE OF THE ROUTE MAP MAY BE SENT AS PERPTCC NORMS SUCH AS 1CM.=1/2 KM. (1:50000) OR 1INCH=1 MILE
THE ROUTE MAP SHOULD SHOW ALL TOPOGRAPHICALDETAILS SUCH AS ROADS,RAIL,RIVERS,FOREST AREAUPTO 5 KMS/ 8KMS. ON EITHER SIDE OF THEPROPOSED POWER LINE
23/08/2018 tak save energy 51
THE NOS. OF CROSSINGS FROM THE TELECOM/RAILWAYLINES SHOULD BE GIVEN.
RAILWAY LINE SHOULD BE MARKED IN YELLOW
INDICATE THE SOIL RESISTIVITY OF THE AREA ALONG THEPOWER LINE.THE SOIL RESISTIVITY SHOULD BEMEASURED BY FOUR ELECTRODE METHOD USING ANINTER ELECTRODE SPACING OF 50M. THE MEASUREMENTMAY BE MADE AT EVERY 2 OR 3 Km. ALONG THE LENGTHOF THE LINE. ALWAYS MEASURE SOIL RESISTIVITY IN DRYSEASON
THE SINLE LINE DIAGRAM MAY BE SENT FOR BOTH OF THESUB-STATIONS
23/08/2018 tak save energy 52
Route Approval & Energisation Approval
Power line Approval Issued by
33 KV S/C Route SLPTCC
Energisation GM,SSA
33 KV D/C & Route Central
Above Energisation CGMT