July 9-11 2014 LEReC Review 9 - 11July 2014 Low Energy RHIC electron Cooling Roberto Than CRYOGENICS SYSTEM
Jan 02, 2016
July 9-11 2014
LEReC Review 9 - 11July 2014
Low Energy RHIC electron Cooling
Roberto Than
CRYOGENICS SYSTEM
July 9-11 2014
Outline
• Cryogenic System Scope and Interface• System Description• Cryogenic loads and system requirements• Procurements• Relocated equipment
– used/shared/repurposed– Moved to make space
• Equipment installation location and conventional facilities requirements
• Timeline• Risk list• Summary
2
July 9-11 2014
Scope
• Provide 2K cooling to SRF e-Gun and 2K SRF 5-cell Accelerating cavity
• Provide 3 bar, 5K cooling for heat intercepts for FPC’s and beam line bores.
• Provide 5K cooling for HTS solenoid inside SRFGun cryostat
• Provide cooling to high heat load Cold Cathode– Supercritical, single phase, helium cooling
3
July 9-11 2014
High Level Systems Description: Process Diagram
4
….SUBCOOLER
CeC
2 - 4K
2 - 4K
WR
M
CATHODE
HTR
HTR
HTR
HTR
HTR
HTR
HTR
HTR
HTR
HTR
HTR
SH
IELD
/TU
NE
R
July 9-11 2014
High Level Systems Description: SRF-Gun
PROCESS SUMMARY4.8K, 3.8 bar Helium from M-line tap for CeC–Supply transfer line. –Flow to cathode / Subcooler
Subcooler (Re-use 912 ERL) Remove transfer line heat, cool to 4.5K. Subcooled 4.5K, 3.5 bar to SRFGUN Return heater, then to 1 atm helium comp. Mass flow controller
2K COOLING– 4.5K, 3.5 bar feeds top fill / bottom fill – 2K-4K recovery heat exchanger– Top fill into 2K bath, level control valve– Vapor exits recovery heat exchanger– Back pressure control valve, bath at 23 Torr
– Returns to 20 Torr heaters (CeC equipment)– Sub-atmospheric pumps (CeC equipment)
Heat Intercept Piping in Gun cryostat– FPC’s, Beam line flanges– Return heaters– Mass flow controllers– HTS Solenoid magnet/Current Leads– Heat Shield cooling– Mass flow controller
Small helium compressor (CeC equipment)
RHIC WR (warm return to RHIC plant)
5
July 9-11 2014
High Level Systems Description: CATHODE COOLING
PROCESS SUMMARY
4.8K, 3.8 bar Helium from M-line tap (CeC)–Supply transfer line tee off to: –6K, 3.8 bar Flow to cathode–Control valve supply side–Supply to: Flexible Transfer line–Isolation valve–Bayonet interface to cathode cart–Cathode loop: 700W heat load–Return: Flexible Transfer line–Return pressure control / isolation valve–To Common Return heater
• Subcooler boil-off• Cathode cooling return
CONTINGENCY
(Need LN2 dewar system at RHIC 02:00)
Existing CATHODE COOLING @ ERLChange back to LN2 cooled• Forced convection boiling heat transfer• 15- 30 g/s of flow• 3.5 g/s vapor generation at 700W• 10% vapor mass fraction for flow boiling
6
July 9-11 2014
High Level Systems Description: 5-Cell Cryostat
PROCESS SUMMARY4.5K, 3.5 bar subcooler to:
5 CELL CAVITY CRYOSTAT & VALVEBOX– To 5K Intercepts in 5-cell cryostat– To 2K Cooling Loop
2K Cooling Loop– 4.5K, 3.5 bar feeds top fill / bottom fill – 2K-4K recovery heat exchanger– Top fill into 2K bath, level control valve– Vapor exits recovery heat exchanger– Back pressure control valve, bath at 23 Torr– Returns to 20 Torr heaters (CeC equipment)– Sub-atmospheric pumps (CeC equipment)
Heat Intercept piping in 5-CELL cryostat– FPC’s– Beam line flanges– Tuner – Heat shield cooling
Return heater
Mass flow controllers
Small helium compressor (CeC equipment)
RHIC WR (warm return to RHIC plant)
7
July 9-11 2014
High Level Systems Description: Equipment List
• Supply Transfer Line existing DX-tap for CeC project.• Interconnecting VJ lines between subcooler and SRFGun valvebox• Interconnecting VJ bundle between Gun valvebox and 5-cell valvebox• Subcooler• ERL SRFGUN Valve box• ERL SRFGUN Cryostat• Flexible VJ Helium lines Cathode cooling • 20 Torr cold vapor return VJ line to CeC Return heaters• Common return heater for subcooler bath / cathode cooling• ERL SRF 5-cell Valve box• ERL SRF 5-cell Cryostat• Return heater 5-cell Tuner/Thermal shield return flow
8
July 9-11 2014
Parameters: SRF cryostats
• SRF Gun– 2.00K, CW– Static heat leak: 14 W– Dynamic load: 10 W– Heat Intercept/ cooling:
FPC x 2: 0.15 to 0.3 g/s Beam line Flanges: Cathode side /
downstream. 2 x 0.3 g/s– HTS Solenoid cooling: 10 W– HTS current leads: ~ 16 W– Heat shield cooling: ~ 25 W
• Gun Cathode– Cooling Duty: 700W– Cathode temperature: <90K– Flexible transfer lines retract
cathode. – Cooling method: Supercritical
helium 3 bar,5K, 6 grams/sec
• SRF 5-Cell– 2.00K, CW– Static heat leak: 21 W– Dynamic load: 5 W [25 W]– Heat Intercept/ cooling:
FPC : 0.15 g/s Beam line Flanges: 0.15 g/s Tuner/Shield: 0.1 g/s
9
July 9-11 2014
Parameters: Cathode Cooling
10
• Updated design of cathode: 650W heat dissipation• Supercritical Helium Cooling• Preliminary analysis shows that this is feasible• Detail ANSYS model: Copper temperature profile
Lumped modelChannel Flow cross section Area 0.000047 m2
Hydraulic Diameter 0.0008 m
Heat transfer Area 248 cm2
k, @ 14K, 3.5bar 0.0218 W/m-K
Viscosity @ 14K, 3.5bar 3.0E-6 Pa-s
Prandtl @ 14K, 3.5bar 0.76
Helium Flowrate 6 g/s
Reynolds 35700
Nusselt 92
Heat transfer coefficient 2400 W/m2-K
LMTD 13 K
July 9-11 2014
Parameters: RHIC CRYO PLANT LOADING
4.5K Ref
Load
Liquefaction loadg/s
Carnot WorkkW
ActualComp.
kW
Supply lineSubcooler load
[46 W] 2.57 17.6 93
SRFgun Cathode cooling 6 41.2 217
SRFgun intercepts coolingHTS solenoid
1.4 9.4 52
SRF Gun 2K, 39W 2.3 15.8 83
SRF 5-cell 2K 2.7 18.5 97
SRF 5-cell intercept coolingThermal shield
0.6 4.1 22
0.562
11
All loads returns as liquefaction loads on main RHIC Plant
July 9-11 2014
Procurements
1. 20 Torr cold vapor return VJ transfer line 2.5”x 4 VJ
2. Cryogenic transfer line, ½”Tx 2”VJ
3. Cryogenic transfer line jumpers between subcooler & valve boxes.
4. Flexible Cryogenic transfer lines set for cathode cooling loop 3.5bar, 5K helium.
5. Return heater for cathode cooling / subcooler boil-off
6. Control system I/O cards (Quantum series) and instrumentation cables, rack components
7. Platform around SRF Cryostats/valveboxes
12
July 9-11 2014
Relocated Equipment
Relocated• Subcooler from ERL cryosystem• Cryogenic valves from ERL cryosystem• Valvebox for SRFGun• Valvebox for SRF 5-cell• Mass flow controllers and manifold for Intercepts cooling circuits
Use/Share of CeC project equipment:• 20 Torr Return heaters• Sub-atmospheric pumps• Small helium compressor
13
July 9-11 2014
Location in LEReC
14
VALVEBOX
SRFGUN
SUBCOOLER
SEPARATOR/SRF-5CELL
SRF 5-cellVALVEBOX
LHe supply
20 Torr return
CEC 20 Torr Return heaters
Tap Existing LHe supply
July 9-11 2014
Conventional facilities requirements
• Instrument Air for valve actuators• 480 VAC, 3 phase for large return heaters• 208 VAC, 1 phase for small return heaters• DI water for FPC thermal loops• Cable trays: tunnel to racks in trailer/service bldg• Utilities for shared equipment from CeC experiment
15
July 9-11 2014
Timeline
16
Oct 2014 Cathode cooling helium lines, Design complete
Nov 2014 - April 2015 Cathode cooling helium lines: RFQ, Manufacture, deliver.
Jan – Jun 2015: Shutdown for gun modifications and LEReC test preparation (in 912 blockhouse).
Apr – Jun 2015 Re-install SRFGun into ERL
July- Dec 2015 Test new cathode with nitrogen coolingTest new Cathode with helium cooling
June 2015 Supply VJ line, Coldbox interconnects, subcooler jumpers, Design complete. 20 Torr Return VJ Line, Design complete. Return heater, 1 bar helium, Design complete.
Nov 2015 SRF Gun Valvebox mods/interface, Design and dwgs completeSRF 5-cell Valvebox mods/interface, Design and dwgs complete
July 2015 - Apr 2016 Supply VJ line, Coldbox interconnects, subcooler jumpers. RFQ, Manufacture, deliver. 20 Torr Return VJ Line. RFQ, Manufacture, deliver.Return heater, 1 bar helium. RFQ, Manufacture, deliver.
Feb 2016 SRF Gun Valvebox mods/interfaces, Parts procured. SRF 5-cell Valvebox mods/interfaces, Parts procured.
July 9-11 2014
Timeline
17
July 2016 – Oct 2016 Install SRF 5-cell CryostatInstall SRFGun Valvebox 5-Cell valvebox, Subcooler, Return heaterInterface modifications, interconnecting VJ linesInstall Instrumentation/controls cables in cable tray
Nov 2016 - Dec 2016 Install Supply and 20Torr Return transfer lines
Nov 2016 Install SRFGun
Dec 2016 - Mar 2017 Install VJ transfer lines between SRFGun and valvebox
April 2017 Warm check out complete CRYOGENICS
May 2017 Cooldown SRF gun w/RHIC refrigerator
July 9-11 2014
Risk list
18
WBS Risk Description Type of Risk
ConsequenceLikeli-hood
Cost Impact
(burdened $k)
Risk Expiration
Mitigation Plan
1.6
The present plan is to use He from the RHIC refrigertor to cool the cathode. If the heat load is too high then an LN2 cooling system will be need for the cathode to improve cooling performance. Cost Level 2 L 380 3QFY15
The new cathode design will be tested in 912 ERL . A cost estimate as been done for adding an LN2 cooling system at 02:00 in RHIC which will be installed if the heat load is too high or inefficient for the RHIC refrigerator.
Medium Risk
RISK / CONTINGENCYExisting CATHODE COOLING ERLChange to LN2 cooled• Forced convection boiling heat transfer• 15 - 30 g/s of flow• 3.5 g/s vapor generation at 700W• 10% vapor mass fraction for flow boiling
July 9-11 2014
Summary
• Re-use existing ERL equipment as much as possible• Cathode Cooling with helium will be tested in ERL 912 Fall ‘15• To minimize equipment and installation work no 4.5K return is
implemented. All loads are returned as liquefaction load to plant. ~ 0.25 MW higher operating power.
19