Top Banner
SECTION NO. 1 PRELIMINARIES 1
30

JBCC - Main Contracts Preliminaries

Mar 02, 2016

Download

Documents

JBCC - Contract
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 1/30

SECTION NO. 1

PRELIMINARIES

1

Page 2: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 2/30

Csa 1362 Clermont Pool

Amount

SECTION NO. 1

PRELIMINARIES

(CPAP WORK GROUP NO. 190 UNLESS OTHERWISE STATED)

NOTES

1. The Principal Building Agreement shall be the JBCC SeriesEdition 4.1, March 2005 as recommended by the Joint BuildingContract Committee and as amended by this Tender Enquiry.

2. The Preliminaries shall be JBCC Series, May 2005 for use withthe Principal Building Agreement as recommended by the JointBuilding Contracts Committee and as amended by this TenderEnquiry shall be deemed to be incorporated herein.

3. Tenderers are referred to the abovementioned documents forthe full intent and meaning of each clause thereof. These clausesare hereinafter referred to by clause number and heading only.

4. Where standard clauses or alternatives are not entirelyapplicable to this contract, such modifications, corrections oradditions as are necessary, are given as far as possible undereach relevant clause.heading. Additional Preliminary clauses arecontained in Section C hereof.

5. No claim whatsoever shall be entertained in respect of errors oromissions in pricing due to brevity of descriptions of items whichare fully described when read in conjunction with the relevantclauses of the said Principal Building Agreement, Preliminaries andPreambles.

6. The Tenderers shall allow opposite each of the clauseswhatever costs and charges he may consider necessary for thecarrying out, complying with and due observance of the provisions,conditions and requirements set out herein. Only priced items willbe considered in respect of any adjustment of this Section. Anyitems left unpriced will be understood to be provided free of chargeand no claim for any extras arising out of the Tenderer's omissionto price any item will be entertained.

7. Where modifications or amendments as described are made,such modifications and/or amendments shall supercede any

conflicting provisions in the relevant clauses of the StandardPreliminaries or the Principal Building Agreement and the Tenderershall make due allowance for whatever costs and charges he mayconsider necessary for the carrying out and observance of theprovisions of the clauses as modified and/or amended.

8. Where any item is not relevant to this specific contract, suchitem is marked N/A.

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

2

Page 3: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 3/30

Csa 1362 Clermont Pool

Amount

9. If Alternative A as set out in clause B10.3 hereinafter is to beused for the adjustment of the preliminaries, each item priced is tobe allocated to one or more of the three categories by insertion of"F","V","T" as the case may be against the price in the "rate"column immediately preceding the "amount" column, where "F"denotes a fixed amount (amount not to be varied), "V" denotes anamount variable in proportion to value, and "T" denotes an amountproportionate to time.

SECTION A: PRINCIPAL BUILDING AGREEMENT

DEFINITIONS

Definitions and interpretation (Clause 1).1 Item

F V T .....................................................................

OBJECTIVE AND PREPARATION

Offer, acceptance and performance (Clause 2).2 Item

F V T .....................................................................

Documents (Clause 3).3

Clause 3.3 is deleted and substituted with:

'The principal agent shall complete the schedule and arrange forformal signing of the agreement once the priced bill ofquantities/lump sum document, security, insurances and waiver oflien, where acceptable, have been provided and effected'. Item

F V T .....................................................................

Design responsibility (Clause 4).4 Item

F V T .....................................................................

Employer's agents (Clause 5).5 Item

F V T .....................................................................

Site representative (Clause 6).6 Item

F V T .....................................................................

Compliance with regulations (Clause 7).7

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

3

Page 4: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 4/30

Csa 1362 Clermont Pool

Amount

Without limiting the generality of the provisions of clause 7.0 of theagreement, the contractor’s attention is drawn to the provisions ofthe Construction Regulations, 2003 issued in terms of theOccupational Health and Safety Act, 1993 in which it is specificallystated that the employer shall prepare a documented health andsafety specification for the works and that the employer shallensure that the contractor has made provision for the cost of healthand safety measures during the execution of the works. Theprincipal agent shall, on behalf of the employer, issue such healthand safety specification and the contractor shall price opposite thisitem for compliance with the act and the regulations and theprovisions of the aforementioned health and safety specification,provided such provisions are reasonable in terms of the act andthe regulations. Item

F V T .....................................................................

Works risk (Clause 8)8 Item

F V T .....................................................................

Indemnities (Clause 9).9

Clause 9.1.1 is deleted and substituted with:

'Claims from other parties consequent upon death of bodily injuryor illness of any person or physical loss or damage to any property,other than the works, arising out or due to the execution of theworks or occupation of the site by the contractor or his subcontractors'. Item

F V T .....................................................................

Works insurances (Clause 10).10 Item

F V T .....................................................................

Liability insurances (Clause 11).11 Item

F V T .....................................................................

Effecting insurances (Clause 12).12 Item

F V T .....................................................................

State Provisions (Clause 13).13 N/A

F V T .....................................................................

Security (Clause 14).14 Item

F V T .....................................................................

EXECUTION

Preparation for and execution of the works (Clause 15).15 Item

F V T .....................................................................

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

4

Page 5: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 5/30

Csa 1362 Clermont Pool

Amount

Access to the works (Clause 16).16 Item

F V T .....................................................................

Contract instructions (Clause 17).17 Item

F V T .....................................................................

Setting out of the works (Clause 18).18

The contractor shall notify the principal agent if any encroachmentsof adjoining foundations, buildings, structures, pavements,boundaries, etc., exist in order that the necessary arrangementsmay be made for the rectification of any such encroachments. Item

F V T .....................................................................

Assignment (Clause 19).19 Item

F V T .....................................................................

Nominated subcontractors (Clause 20).20 Item

F V T .....................................................................

Selected subcontractors (Clause 21).21 Item

F V T .....................................................................

Employer's Direct contractors (Clause 22).22 Item

F V T .....................................................................

Contractor's Domestic subcontractors (Clause 23).23 Item

F V T .....................................................................

COMPLETION

Practical completion (Clause 24).24 Item

F V T .....................................................................

Works completion (Clause 25).25 Item

F V T .....................................................................

Final completion (Clause 26).26 Item

F V T .....................................................................

Latent defects liability period (Clause 27).27

Clause 27.0 is amended by the addition of the following clauses:

"27.3 Any water leakage into the building, whether in the roof,external wall or other element of the building susceptible to waterleakage shall, unless proven to be a design defect, or as a result ofobvious storm damage, be classified as a latent defect in terms ofclause 1.0 Definitions and Interpretations".

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

5

Page 6: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 6/30

Csa 1362 Clermont Pool

Amount

"27.4 The Contractor shall attend to defects during the DefectsLiability Period on a progressive basis, to the satisfaction of thePrincipal Agent and will not be permitted to wait until the end of theDefect Liability Period or until the amount of defects accummulatesin order to attend to a comprehensive list of defects" Item

F V T .....................................................................

Sectional completion (Clause 28).28 Item

F V T .....................................................................

Revision of date for practical completion (Clause 29).29 Item

F V T .....................................................................

Penalty for non-completion (Clause 30).30 Item

F V T .....................................................................

PAYMENT

Interim payment to the contractor (Clause 31).31

The inclusion of materials and goods stored on site in the amountauthorised for payment in terms of clause 31.3 shall be at the solediscretion of the principal agent and such inclusion shall only beconsidered upon the provision, by the contractor, of an approvedguarantee issued by a registered commercial bank and clause31.6.5 is therefore not applicable.

Where prices are submitted by the contractor or

nominated/selected sub contractor during the progress of theworks in respect of contract instructions or in regard to a claimunder the terms of the contract and notwithstanding the fact thatsuch prices may be used in an interim payment certificate, there isto be no presumption of acceptance. Should the principal agentwish to accept any such prices prior to the issue of the finalcertificate, it will be in writing. Item

F V T .....................................................................

Adjustment to the contract value (Clause 32).32 Item

F V T .....................................................................

Recovery of expense and loss (Clause 33).33 Item

F V T .....................................................................

Final account and final payment (Clause 34).34

Clause 34.1 is amended as follows:

'The principal agent shall prepare a final account for submission tothe contractor within one hundred and eighty (180) working days.' Item

F V T .....................................................................

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

6

Page 7: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 7/30

Csa 1362 Clermont Pool

Amount

Payment to other parties (Clause 35).35 Item

F V T .....................................................................

CANCELLATION

Cancellation by Employer - Contractor's default (Clause 36).36 Item

F V T .....................................................................

Cancellation by Employer - Loss and damage (Clause 37).37 Item

F V T .....................................................................

Cancellation by Contractor - Employer's default (Clause 38).38 Item

F V T .....................................................................

Cancellation - Cessation of the works (Clause 39).39 Item

F V T .....................................................................

DISPUTE

Dispute Settlement (Clause 40)40 Item

F V T .....................................................................

CONTRACT VARIABLES

The Schedule: Pre-Tender information (Clause 41).41 Item

F V T .....................................................................

CONTRACTING AND OTHER PARTIES (Clause 41.1)

Employer: Ethekwini Municipality

Postal Address: P.O.Box 1548, Durban, 4000

Telephone: 031 311 7098

Facsimile: 031 311 7111

Physical address: Municipal Centre, 166 Old Fort Road, Durban

Principal Agent: Ethekwini Municipality

Postal Address: P.O.Box 1548, Durban, 4000

Telephone: 031 311 7098

Facsimile: 031 311 7111

Physical address: Municipal Centre, 166 Old Fort Road, Durban

Agent's Service: Quantity Surveyor

Agent ( 1 ): Ethekwini Municipality

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

7

Page 8: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 8/30

Csa 1362 Clermont Pool

Amount

Postal Address: P.O.Box 1548, Durban, 4000

Telephone: 031 311 7098

Facsimile: 031 311 7111

Physical address: Municipal Centre, 166 Old Fort Road, Durban

Agent's Service: Electrical and Mechanical

Agent ( 2 ): Ethekwini Municipality

Postal Address: P.O.Box 1548, Durban, 4000

Telephone: 031 311 7098

Facsimile: 031 311 7111

Physical address: Municipal Centre, 166 Old Fort Road, Durban

Agent's Service: Structural Engineer

Agent ( 3 ): Ethekwini Municipality

Postal Address: P.O.Box 1548, Durban, 4000

Telephone: 031 311 7098

Facsimile: 031 311 7111

Physical address: Municipal Centre, 166 Old Fort Road, Durban

Agent's Service: Hydraulic Engineer

Agent ( 4 ): CBI Consulting Engineers (Pty) Ltd

P.O. Box 37002 OVERPORT

Telephone : (031) 208-7171

Facsimile : (031) 208-7072

contact person: Martin Bright

CONTRACT DETAILS (Clause 41.2)

Clause 41.2.1

Works Description: New swimming pool, paddling pool, ancillarybuildings, external works including upgrading adjoining sportsfield -see brief description under the Notes to Tenderers

Clause 41.2.2

Site Description: 11 Ntsiba Road, Clermont

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

8

Page 9: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 9/30

Csa 1362 Clermont Pool

Amount

Clause 41.2.3

Work or Installations by Others: NIL

Clause 41.2.4

This Agreement is for a State Contract :- Yes

Payment will be made for materials and goods:- Yes

Dispute resolution :- Mediation (in terms of 40.4) followed bylitigation.

Arbitration rules as recommended by the Association of Arbitrators(SA) :- N/A

Clause 41.2.5

Date on which possession of the site is intended to be given on :-

5 working days from the date of the letter of appointment to theContractor.

Clause 41.2.6

Period for the commencement of the works after the contractortakes possession of the site :- 2 Working days.

Clause 41.2.7

Intended date of practical completion and the penalty per calendarday for the works as a whole :-

250 working days after commencement

Penalty amount R2,500.00 per calendar day

Clause 41.2.8

Intended dates of practical completion and the penalties percalendar day for the works in sections :

N/A

Clause 41.2.9

The law applicable to this agreement shall be that of - South Africa.

INSURANCES

Clause 41.3.1

Contract works insurance to be effected by Contractor for the sumof: Contract Sum plus 20%

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

9

Page 10: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 10/30

Csa 1362 Clermont Pool

Amount

With a deductible of : to be determined by the Contractor but notgreater than the maximum of R50,000.00 as stipulated by theMunicipality.

Clause 41.3.2

Supplementary insurance is required : Yes

SASRIA insurance required to be effected by the Contractor for theamount of: Contract Sum plus 20% (with a deductable to bedetermined by the Insurance company issueing the policy).

Clause 41.3.3

Public liability insurance to be effected by Contractor

For the amount of: R2 million

With a deductible of: R2,500.00

DOCUMENTS (Clause 41.4)

Clause 41.4.1

Waiver of the contractor's lien is required :- YES

Clause 41.4.2

Number of construction document copies to be supplied to theContractor free of charge :- 3

Clause 41.4.3

Bills of Quantities drawn up in accordance with :-

Standard System of Measuring Building Work - Sixth Editionincluding all amendments

Clause 41.4.4

Number of days for submission of priced documents : 5 days.

Clause 41.4.5

JBCC Engineering General Conditions are to be included in thedocuments :- No

Clause 41.4.6

The contract value is to be adjusted using CPAP:- YES

Refer to Clause 32 of these Preliminiaries for details.

Clause 41.4.7

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

10

Page 11: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 11/30

Csa 1362 Clermont Pool

Amount

Details of changes made to the provisions of JBCC standarddocumentation:

Note: The tenderer must study the modifications and amendmentsmade to the relevant clauses in the Preliminaries section of theBills of Quantities, under each clause heading. It should be notedthat reference is made hereunder merely to draw the tenderersattention of clauses that have been amended or modified and thetenderer, when submitting his tender is deemed to have examinedthe relevant clauses for details of the amendments andmodifications of the clauses in the Preliminaries:

Refer to relevant clauses for the full details of changes:

Clause 3 - Documents

Clause 7 - Compliance with regulations

Clause 9 - Indemnities

Clause 18 - Setting out of the Works

Clause 27 - Latent defects liability period

Clause 31 - Interim Payment to the Contractor

Clause 32 - Adjustment to the Contract Value

Clause 34 - Final account and final Payment

SECTION B: PRELIMINARIES

DEFINITIONS AND INTERPRETATION (B1)42 Item

F V T .....................................................................

DOCUMENTS (B2)

Checking of documents (B2.1)43

The items in these Bills of Quantities are to be read and priced inconjunction with, and the descriptions regarded as amplified by theGeneral Preambles to all Trades as published by the EthekwiniMunicipality, December 1992 edition, and no claim arising from

brevity of description of items fully described in the said GeneralPreambles to all Trades and Supplementary documentation will beentertained.

Notwithstanding the issue of the tender drawings, it will remain theresponsibility of the Tenderer to study all available drawings at theoffices of the Principal Agent during normal working hours in orderto acquaint himself with all the cost implications of the design,programming, phasing, etc. Item

F V T .....................................................................

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

11

Page 12: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 12/30

Csa 1362 Clermont Pool

Amount

Provisional Bills of Quantities (B2.2)44

Clause 2.2 is deemed to be deleted and replaced by the following:

"Except where indicated otherwise, the quantities of and classesand kinds of works set out in these Bills of Quantities areprovisional and do not purport to represent the final quantities ofand classes and kinds of work eventually required to be done. Thequantities of and classes and kinds of work contained herein havebeen set down solely in order to form a basis for obtainingcompetitive tenders.

The Bills of Quantities are not to be used for ordering materialsunder any circumstances whether this be with regard to descriptionor specification of materials or goods required, or with regard toquantities. Failure to comply with this condition is entirely at the

Contractor's own risk. The Contractor shall be obliged uponinstruction of the Principal Agent to execute such quantities of andclasses and kinds of work as the Principal Agent in his solediscretion may deem necessary or which, in the Principal Agent'sopinion, become expedient from time to time or which may berequired to meet the Employer's requirements, whether or not suchquantities of and classes or kinds of work may appear in theseBills of Quantities or the contract drawings.

The consideration payable to the Contractor in respect of the worksshall be determined by the Agent by the application of the ratescontained in the priced Bill of Quantities to the quantities of andclasses and kinds of work actually executed, which quantities of

and classes and kinds of work shall be determined by the Agent.The rates contained in the priced Bills of Quantities shall applyirrespective of the final quantities of the different classes and kindsof work actually executed. No claims for extras, loss of profit,variation of rates or other similar claims will be entertained as aresult of any variations whatsoever between the quantities of workset out in these Bills of Quantities and the quantities of workactually executed, nor as a result of any variation whatsoeverbetween the contract sum and the final value of works.

Prime Cost Amounts, Budgetary Allowances, Provisional Amounts,etc., contained herein may be omitted or reduced at the PrincipalAgent's sole discretion and the Contractor shall not be entitled to

claim for any loss by way of reduction or omission of any discount,or percentage relating to Prime Cost Amounts, BudgetaryAllowances, Provisional Amounts, etc., or loss of profit relatedthereto. Item

F V T .....................................................................

Availability of construction documentation (B2.3)45 Item

F V T .....................................................................

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

12

Page 13: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 13/30

Csa 1362 Clermont Pool

Amount

Interests of Agents (B2.4)46 Item

F V T .....................................................................

Priced documents (B2.5)47 Item

F V T .....................................................................

Tender submission (B2.6)48

Notwithstanding anything contained in this clause, Tenders shall bevalid for a period of 56 (fifty-six) calendar days from the closingdate of tenders. Item

F V T .....................................................................

THE SITE (B3)

Defined works area (B3.1)49

The area of the works to be occupied by the contractor, anyrestriction on the area and the limit of access or exit will be pointedout to the contractor by the principal agent on handing over of thesite.

The Tenderer shall ascertain any other restrictions to the area thatmay be occupied by the Contractor including any restrictionsimposed by any buildings, etc. And any limitations or restrictionsthat may be imposed by any Authorities.

Workmen employed on the site are to be restricted to the

immediate area of the site and access thereto.

Space on the pavement areas for the storage of building materials,etc., must be arranged with the Local Authorities by the Tendererwho will be responsible for all charges in connection therewith.

The Tenderer shall make all necessary provision in all rates to takeinto account these requirements as no claims for extras arisingfrom these matters will be subsequently entertained or admitted. Item

F V T .....................................................................

Geotechnical investigation (B3.2)50 Item

F V T .....................................................................

Inspection of the Site (B3.3)51

No Claim for extras arising from the contractor having failed tocomply with the clause will be entertained. Item

F V T .....................................................................

Existing premises occupied (B3.4) N/A52 Item

F V T .....................................................................

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

13

Page 14: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 14/30

Csa 1362 Clermont Pool

Amount

Previous work - dimensional accuracy (B3.5)53 Item

F V T .....................................................................

Previous work - defects (B3.6)54 Item

F V T .....................................................................

Services - known (B3.7)55 Item

F V T .....................................................................

Services - unknown (B3.8)56 Item

F V T .....................................................................

Protection of trees (B3.9)57 Item

F V T .....................................................................

Articles of value (B3.10)58 Item

F V T .....................................................................

Inspection of adjoining properties (B3.11)59

Tenderer shall inpect acces roads etc and shall be responsible forany damage evident at the end of the contract which has not beenpointed out. Item

F V T .....................................................................

MANAGEMENT OF CONTRACT (B4)

Management of the Works (B4.1)60

Clause 4.1 shall be deemed to be amended by the additon of thefollowing:

'The contractor shall, to the satisfaction of the principal agent,provide the services of an experienced and compententConstruction Manager and Site Agent supported by a managementteam who shall inter alia be responsible for all activities of thecontractor and all sub-contractors and in particular:-

a) Programming

b) Scheduling

c) Reporting

d) Production of shop drawings and samples

e) Procurement and expediting

f) Liaison and co-ordinating of construction

g) Commissioning, instruction, handover and follow up.

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

14

Page 15: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 15/30

Csa 1362 Clermont Pool

Amount

h) Monitoring and reporting on building activities taking place offsite.

The names and CV's on the contractor's site management teamshall be submitted to the principal agent prior to commencementon site and, after the principal agent's agreement on thecomposition thereof has been obtained. No changes shall be madenor shall any member of the said team be removed from site whileremaining in employ of the contractor without the principal agent'sexpress written approval. Item

F V T .....................................................................

Programme for the Works (B4.2)61 Item

F V T .....................................................................

Progress meetings (B4.3)62 ItemF V T .....................................................................

Technical meetings (B4.4)63 Item

F V T .....................................................................

SAMPLES AND SHOP DRAWINGS (B5)

Samples of materials (B5.1)64 Item

F V T .....................................................................

Workmanship samples (B5.2)65 Item

F V T .....................................................................

Shop drawings (B5.3)66 Item

F V T .....................................................................

TEMPORARY WORKS AND PLANT (B6)

Deposits and fees (B6.1)67 Item

F V T .....................................................................

Enclosure of the works (B6.2)68 Item

F V T .....................................................................

Advertising (B6.3)69 ItemF V T .....................................................................

Plant, equipment, sheds and offices (B6.4)70 Item

F V T .....................................................................

Main notice board (B6.5)71

One notice board shall be provided - refer to Annexure 6 Item

F V T .....................................................................

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

15

Page 16: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 16/30

Csa 1362 Clermont Pool

Amount

Subcontractors notice board (B6.6)72 N/A

F V T .....................................................................

TEMPORARY SERVICES (B7)

Location (B7.1)73 Item

F V T .....................................................................

Water (B7.2)74

The contractor shall provide water for the works in accordance with:

Alternative A (i.e. to be provided for by the Contractor) Item

F V T .....................................................................

Electricity (B7.3)75

The contractor shall provide electricity for the works in accordancewith:

Alternative A (i.e. to be provided for by the Contractor) Item

F V T .....................................................................

Telecommunication equipment (B7.4)76

The contractor shall provide telephones on site for the works inaccordance with:

Alternative A (i.e. to be provided for by the Contractor) ItemF V T .....................................................................

Ablution facilities (B7.5)77

The contractor shall provide toilet facilties on site for the works inaccordance with:

Alternative A (i.e. to be provided for by the Contractor) Item

F V T .....................................................................

PRIME COST AMOUNTS (B8)

Responsibility for prime cost amounts (B8.1)78 ItemF V T .....................................................................

ATTENDANCE ON N/S SUBCONTRACTORS (B9)

General Attendance (B9.1)79

Clause 9.1 shall be amended by the addition of the following:

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

16

Page 17: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 17/30

Csa 1362 Clermont Pool

Amount

a) Provide every assistance necessary for the due performance byall sub-contractors of their work and to enable them to executetheir work in a like manner, in a proper order and sequence.

b) Supervise and administer the sub-contractors and arrange andmonitor programmes with each sub-contractor and supplier and co-ordinate the work of all sub-contractors and deliveries by suppliers.

c) Attendance on Nominated/Selected sub-contractors simona Sunincludes co-operating to the fullest extent with all parties andproviding facilities for general attendance. Item

F V T .....................................................................

Special Attendance (B9.2)80 Item

F V T .....................................................................

Commissioning - fuel, water and power (B9.3)81 Item

F V T .....................................................................

FINANCIAL ASPECTS (B10)

Statutory taxes, duties and levies (B10.1)82

Provision is made in the Final Summary of these Bills of Quantitiesfor the inclusion of Value Added Tax (VAT). Item

F V T .....................................................................

Payment of Preliminaries (B10.2)83 Item

F V T .....................................................................

Adjustment of Preliminaries (B10.3)84 Item

F V T .....................................................................

Payment certificate cash flow (B10.4)85 Item

F V T .....................................................................

Contractor information supply (B10.5)86 Item

F V T .....................................................................

GENERAL (B11)

Protection of the Works (B11.1)87 Item

F V T .....................................................................

Protection/isolation of existing/sectionally occupied works (B11.2)88 Item

F V T .....................................................................

Site security (B11.3)89 Item

F V T .....................................................................

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

17

Page 18: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 18/30

Csa 1362 Clermont Pool

Amount

Notice before covering work (B11.4)90 Item

F V T .....................................................................

Disturbance (B11.5)91 Item

F V T .....................................................................

Works cleaning and clearing (B11.6)92 Item

F V T .....................................................................

Vermin (B11.7)93 Item

F V T .....................................................................

Overhand work (B11.8)94 Item

F V T .....................................................................

SCHEDULE OF VARIABLES (B12)

Pre-tender information (B12.1)95

Information necessary for elections and completion of thoseclauses contained in the schedule which are necessary for tenderpurposes is given hereunder. Where no information is given, itshall mean that either no details are available or that the clause isnot relevant to this specific contract. Item

F V T .....................................................................

Provisional Bills of Quantities (B2.2) The quantities are provisional(YES).

Availability of Construction documentation (B2.3)

Interests of Agents (B2.4)

Defined works area (B3.1) Tenderers shall establish by personalviewing of the site conditions any restrictions imposed by existingbuildings, limited means of access and the like.

Geotechnical investigation (B3.2) Refer to Annexure 14

Existing premises occupied (B3.4): N/A

Services - known (B3.7)Protection of trees (B3.9)

Inspection of adjoining properties (B3.11)

Enclosure of the works (B6.2)

Offices (B6.4.3)

Main notice board (B6.5) One main notice board shall beprovided - refer to Annexure 6

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

18

Page 19: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 19/30

Csa 1362 Clermont Pool

Amount

Subcontractors notice board (B6.6) A notice board is required (No).

Water (B7.2) Alternative chosen: A

Electricity (B7.3) Alternative chosen: A

Telecommunications (B7.4) Alternative chosen: A

Ablution facilities (B7.5) Alternative chosen: A

Special Attendance (B9.2)

Protection of the Works (B11.1)

Protection of existing/sectionally occupied works (B11.2)

Disturbance (B11.5)

SECTION C: SPECIFIC PRELIMINARIES

Section C: Specific Preliminaries:

C1. Proprietary branded products96

The contractor shall take delivery of, handle, store, use, applyand/or fix all proprietary branded products in strict accordance withthe manufacturer's instructions after consultation with themanufacturer's authorised representative. Item

F V T .....................................................................

C2. Trade Names, etc.97

All materials, fittings, finishings, etc., specified hereinafter under atrade name, catalogue number or reference, must be exactly asdescribed. The Architect's approval in writing must be obtained forthe use of any alternative to the specification before thesubmission of tenders otherwise the specified materials, fittings,finishings, etc., will be assumed to have been allowed for in thetender.

The Contractor must take delivery of, handle, store, use, applyand/or fix all proprietary branded products in strict accordance withthe manufacturer's instructions after consultation with the

manufacturer's authorised representative. ItemF V T .....................................................................

C3. Contractors responsibility98

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

19

Page 20: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 20/30

Csa 1362 Clermont Pool

Amount

The Employer, the Principal Agent and the other professionalconsultants shall not be responsible for any act or omission on thepart of the Contractor which may result in any patent or latentdefects, in materials or workmanship, breach or neglect of anylocal regulations. The Contractor shall at all times be responsiblefor any such neglect, deviation or wrong act, whether the same isdiscovered before or after the final certificate, or any otherCertificate, has been approved. Item

F V T .....................................................................

C4. Overtime99

Should overtime be required to be worked for any reasonwhatsoever, the costs of such overtime are to be borne by thecontractor unless the principal agent has specifically authorised in

writing, prior to the execution thereof, that costs for such overtimeare to be borne by the employer. Item

F V T .....................................................................

C5. As built drawings100

The position of construction breaks and the extent of individualconcrete pours are to be recorded by the contractor on thestructural engineer's drawings and are to be submitted to theprincipal agent and the structural engineer for their records.

Three full sets of as-built drawings shall be submitted to thePrincipal Agent no later than fourteen days after practical

completion. ItemF V T .....................................................................

C6. Construction Instructions101

Contract instructions issued on site are to be recorded in triplicatein a site instruction book which is to be maintained on site by theContractor. The Contractor shall supply and have available at thesite of the works at all times, the following site books:

a) Construction Instruction Book:

Receiving and recording instructions in a suitable A4 size triplicate

book kept on site. Instructions issued shall be recorded by theArchitect or other Employer's Agents to whom the Architect hasdelegated authority to in the book.

Only instructions issued in such book shall be recognised.

b) Daily Record Book:

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

20

Page 21: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 21/30

Csa 1362 Clermont Pool

Amount

The Contractor shall record in triplicate in a suitable A4 sizetriplicate book kept at the site, a daily record of work done, all sitevisits by the Principal Agent and other professional personnel andall events affecting the Works, such as progress, issue of plans,breakdown of machinery, etc. The labour, plant and material onsite shall be recorded as well as work performed. Entries must bemade by the Contractor and must be signed and forwarded to thePrincipal Agent for his counter-signature on a daily basis. Copies ofthese records shall be for the Architect, Quantity Surveyor andContractor. Item

F V T .....................................................................

C7. Labour record102

At the end of each week the contractor shall provide the principal

agent with a written record, in schedule form, reflecting the numberand description of tradesmen and labourers employed by him andall subcontractors on the works each day. Item

F V T .....................................................................

C8. Plant record103

At the end of each week the contractor shall provide the principalagent with a written record, in schedule form, reflecting thenumber, type and capacity of all plant, excluding hand tools,currently used on the works. Item

F V T .....................................................................

C9. Encroachment104

During the course of the building operations, the Contractor shallbe held entirely responsible for any encroachment onto anyadjoining properties, buildings, etc., or servitudes and the cost ofany remedial measures as required by the Principal Agent shall beborne by the Contractor. Item

F V T .....................................................................

C10. Method Statement105

The Tenderer shall produce, when required to do so by thePrincipal Agent, a Method Statement outlining the methods of

construction and labour and plant resources that he proposes touse in the execution of the Works. Any approval given orobservation made by the Principal Agent shall not relieve theContractor of his sole responsibility to adopt the methods ofconstruction and to provide the labour and plant resourcesnecessary for the due and proper timeous execution of the Works. Item

F V T .....................................................................

C11. Unauthorised Persons/Workmen on Premises106

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

21

Page 22: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 22/30

Csa 1362 Clermont Pool

Amount

The Contractor shall at all times strictly exclude all unauthorisedpersons from the Works and the site and shall set up notice boardsto that effect.

No workmen or labourers (except security guards) are to beallowed under any circumstances to sleep or deposit any kit on thepremises. The Contractor must provide any necessaryindependent shelter or shed required for any labour or watchmenon site, to the approval of the Employer. Item

F V T .....................................................................

C12. Mode of Procedure107

Notwithstanding anything to the contrary contained herein thePrincipal Agent at all times reserves the right to direct the order inwhich the various parts of the Contract are to be executed. TheContractor shall give priority to any individual section or portion ofthe Works that, in the opinion of the Principal Agent, requires to beexpedited.

Should it appear, in the Principal Agent's opinion, that work in anyarea is not being executed in accordance with the requirements ofthe Contract Programme, the Contractor shall provide additionalmanpower and resources and shall work additional overtime anddo everything else required to bring the work back to programme tothe satisfaction of the Principal Agent and to the Contractor's cost. Item

F V T .....................................................................

C13. Shop Drawings108

The term 'shop drawings' shall mean drawings, layout drawings,diagrams, illustrations, schedules, performance charts, brochures,operating manuals and other data which are prepared by theContractor or any Sub-Contractor, manufacturer, supplier ordistributor and which illustrate the specified portion of the work.

The Contractor shall ensure that all shop drawings required for theWorks in terms of this Contract, all Selected/Nominated Sub-Contracts and/or any Principal Agent's instruction, are preparedand submitted timeously in accordance with the followingprocedure:

(a) Three prints of shop drawings of all fabricated work, working orsetting out drawings, shop details and schedules shall besubmitted to the Principal Agent, for approval. Such work shall notbe carried out until such approval has been given.

(b) Shop drawings shall be submitted to the Principal Agents forapproval at least two weeks prior to the date on which suchapproval is required in order to comply with the ContractProgramme.

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

22

Page 23: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 23/30

Csa 1362 Clermont Pool

Amount

(c) All submissions shall be prepared in accordance with theContract drawings and specifications and/or any Principal Agentsinstructions and any deviation shall be specifically highlighted inwriting, with a detailed explanation of the reason for such deviation,together with any cost and/or time implications.

Delays in approval of shop drawings due to non-compliance withdrawings, specifications and/or Principal Agents instruction shallnot constitute grounds for any claims for delay, extension of timeand the like.

(d) When the Principal Agent advises that shop drawings havebeen approved, the original transparencies of such drawings shallimmediately be submitted to the Principal Agent so that thePrincipal Agent's stamp of approval may be appended thereto.Thereafter, four prints of the approved shop drawings, setting out

drawings and schedules shall be furnished to the Principal Agent.As many prints of the approved shop drawings and schedules asrequired shall also be furnished to the Works. No work shall beperformed in accordance with drawings and/or catalogues notstamped with the Principal Agent's approval.

(e) The Contractor, Sub-Contractor or Supplier, as the case maybe, shall be responsible for ensuring that all dimensions affectingshop drawings conform to the dimensions of built work.

(f) The Architects approval of shop drawings is limited to checkingconformity with specification and shall not relieve the Contractor,Sub-Contractor or Supplier of his responsibility for design, erection

or installation fit, nor does it vary his contractual or delictualobligations and liabilities.

(g) Should the Contractor, Sub-Contractor or Supplier be of theopinion that corrections to shop drawings made by the Architectconstitute a change to the scope of work, then he shall immediatelyadvise the Architect in writing of this, together with the cost and/orprogramme implications thereof, in order to obtain the Architectsdirective.

(h) One additional copy of the final approved set of 'Shopdrawings' is to be submitted to the Quantity Surveyors for purposesof valuation remeasurement. Item

F V T .....................................................................

C14. Commodities to be New109

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

23

Page 24: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 24/30

Csa 1362 Clermont Pool

Amount

All commodities, goods, articles or materials throughout thebuilding are to be new except where re-use of existing is specifiedand are to be handled, stored, used, and/or fixed with care toensure that they are in perfect condition when incorporated into theWorks and thereafter properly protected so as to ensure that theyare likewise in perfect condition when handed over at completion ofthe Work. Item

F V T .....................................................................

C15. Standard of Workmanship and Materials110

In the absence of detailed specifications for any item or items,National Building Regulations, the latest applicable South AfricanBureau of Standards Specification, or where such does not exist,then the latest applicable British Standard Specification shall apply. Item

F V T .....................................................................

C16. Making Good111

All materials and workmanship in building up, making good, etc.,are to match existing and where new materials abutt existing, theyare to be neatly jointed to same.

'Making good' existing work where disturbed or damaged shallmean the provision of the necessary new material to matchexisting and the necessary workmanship so that a completerestoration is achieved to the satisfaction of the Principal Agent.

'Making good' where abutting walls, etc., are removed, shall meanthe provision of the necessary material and workmanship in fillingthe gaps to match surrounding finishes so that a complete andperfect surface, continuous with surrounding surfaces andmatching of same, is obtained to the Architect's satisfaction. Item

F V T .....................................................................

C17. Location of Temporary Buildings and Temporary Services112

The Contractor shall provide all necessary temporary works,including temporary roads, tracks, crossings, hardstanding andservices, hoardings, dust screens, tunnelling, etc., required for hisown and sub-contractors use during the construction and

maintenance period.

There is no guarantee given or implied that Site conditions will besuch that the Contractor will be able to erect such temporaryworks, roads, hardhats, offices, stores and temporaryaccommodation within the site boundaries and it shall be theContractor's responsibility to adopt whatever measures he deemsnecessary in this regard and to obtain all necessary permissionand pay all costs in connection therewith. Item

F V T .....................................................................

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

24

Page 25: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 25/30

Csa 1362 Clermont Pool

Amount

C18. Removal and Making Good of Temporary Works, etc, onCompletion

113

The Contractor shall remove (except where specifically statedotherwise) all temporary works, roads, services and the like usedfor this contract and shall make good to the entire satisfaction ofthe Principal Agent any damage resulting therefrom. Item

F V T .....................................................................

C19. Overloading114

The Tenderer shall prior to submitting his tender determine fromthe Engineers any constraints and limitations in respect of Worksto be executed, which have load limitations.

The Contractor shall take all necessary steps to ensure that nodamage occurs due to overloading of any portion of the Works.The Contractor shall submit details of his proposed loading,storage, plant erection, etc., to the Principal Agents for theirapproval prior to proceeding with such loading, storing, erecting orexecuting work and shall comply with and pay for the Engineersrequirements in connection with the provision of temporary supportwork, etc. Any damage caused by the Works by overloading shallbe made good by the Contractor at his sole expense.

Notwithstanding any approval given by the Principal Agent orEngineer, the Contractor shall be entirely responsible for damagecaused to the Works by overloading which damage shall be madegood by the Contractor at his sole expense. Item

F V T .....................................................................

C20. Tender Sum to be Fully Inclusive115

The Tender Sum is deemed to be the fully inclusive price for thefinished work described and is deemed to include inter alia for:

- The supply of all materials

- Labour of every description including additional costs incurred inworking overtime, weekends, public holidays, etc., to meet thestipulated programme dates.

- All making, transport, conveying, cartage, carriage and delivery,etc.

- Taking delivery, unloading, storing, unpacking, hoisting orlowering, settings, fixing and building into positions, cutting andwaste, templates, patterns and models.

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

25

Page 26: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 26/30

Csa 1362 Clermont Pool

Amount

- Provision and maintenance of all plant, equipment, machines,trucks and other vehicles, tackle, tools, staging, sheds, stores andtemporary works necessary for the due and proper performance ofthe Contract Works, establishment charges and all fuel, operatingcosts and depreciation pertaining to plant, equipment, etc.

- All applicable import taxes and duties.

- Overheads and profit

- All obligations arising out of the Bills of Quantities, and all costsand charges deemed necessary for complying with the terms andconditions herein.

All charges required by the Contractor in connection withPreliminary and General, site establishment and the like. Item

F V T .....................................................................

C21. Cost of Claims116

All costs incurred by the Contractor in the preparation of claims tothe satisfaction of the Principal Agent and/or Quantity Surveyorshall be borne by the Contractor. Item

F V T .....................................................................

C22. Media Releases117

All rights of publication of articles in the media, together with anyadvertising relating to, or in any way connected with this project

shall vest in the Employer.

The Contractor, together with his Sub-Contractor shall not, withoutthe written consent of the Principal Agent, cause any statement oradvertisement to be printed, screened or aired by the media. Item

F V T .....................................................................

C23. Guarantees and Maintenance Manuals118

The Contractor shall obtain and hand over to the Principal Agenton Practical Completion, all relevant guarantees, any operating andmaintenance instruction manuals, data or instructions required bythe Principal Agent or provided by manufacturer's, suppliers or Sub-

Contractors.

The Contractor shall ensure that all warranties and guaranteesreceived are fully ceded to the Employer on Final Completion,failing which the release of the Construction Guarantee will bewithheld until this is satisfactorily completed. Item

F V T .....................................................................

C24. Occupational Health and Safety Act119

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

26

Page 27: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 27/30

Csa 1362 Clermont Pool

Amount

The Contractor shall for the duration of this contract be deemed tobe the mandatory of the Council for the purposes of theOccupational Health and Safety Act, Act 85 of 1993, and he shallprior to taking occupation of the site satisfy the Council by meansof written representations that he has fully complied with therelevant requirements of the said Act.

Acceptance by the Council of the Contractors writtenrepresentations in terms of the above shall constitute anagreement in writing to the arrangements and procedures betweenthe parties to ensure compliance by the Contractor with theprovisions of the Act referred to therein, for the purposes ofSection 37(2) of the said Act.

The Council shall at all times have the right to summarily suspendthe performance of the Contractor hereunder pending compliance

by the Contractor with any requirement, regulation and/or directionreferred to.

The Council shall be entitled to set-off against any amount owed bythe Council to the Contractor hereunder any loss or damagesuffered by it as a result of the suspension of the Contractor'sperformance in the circumstances envisaged above.

The Tenderer shall price for all necessary items to comply with theOccupational Safety and Health Specification contained inAnnexure 4 of these Bills of Quantities. Item

F V T .....................................................................

C25. Notes to Tenderers120

Items which the Tenderer wishes to price in order to provide for thedue observance of the requirements of the "Notes to Tenderers"outlines at the beginning of this Bill may be priced under this item:

1. Tenders, Tender Forms and Closing Date

2. Fax Tenderers

3. Withdrawal of Tenders

4. Acceptance of Tender

5. Scope of Contract

6. System of Measurement

7. Documentation to be submitted with Tender

8. Contract Price Adjustment Provisions

9. Conditions pertaining to Targeted Procurement

10. Labour Goals

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

27

Page 28: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 28/30

Csa 1362 Clermont Pool

Amount

11. Community Liaison Officer, etc.

12. Application for Service Connections

13. Viewing the Site

14. Communications with members of Tender Board

15. Tender Fee

16. Market Related Wage Rates

17. Tender Prices and Contingency Sum

18. Value Added Tax

19. Tax Clearance Certificate

20. Occupational Safety and Health Act

21. CIDB Register of Contractors

22. Use of Proprietary Products

23. Termination of Contracts

24. Appeal Process

25. Schedule of Drawings

26. Pricing of "Notes to Tenderers" Item

F V T .....................................................................

Section No. 1 Carried To Section Summary R

Bill No. 1

Preliminaries

28

Page 29: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 29/30

Csa 1362 Clermont Pool

Amount

SECTION NO. 1

PRELIMINARIES

SECTION SUMMARY

Page

2Brought forward from page

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

Section No. 1 Carried to Next R

SECTION SUMMARY

29

Page 30: JBCC - Main Contracts Preliminaries

7/18/2019 JBCC - Main Contracts Preliminaries

http://slidepdf.com/reader/full/jbcc-main-contracts-preliminaries 30/30

Brought from Previous R

Csa 1362 Clermont Pool

Amount

27

28

Section No. 1 Carried to Final Summary R

SECTION SUMMARY