Page 1: IT Project Management

IT Project Management

Lecture 2-6 – Risk Management

Quiz

Uwe Gühl

Page 2: IT Project Management

Disclaimer

Some of the questions presented in this quiz are based on sample examinations provided by

• Free PMP® Practice Exam Questions, available at https://www.project-management-prepcast.com/pmp-practice-exam-questions-sample-test

• Sample Exam Certified Project Management Associate, IPMA Level D®, available at https://www.ipma-usa.org/cert-sample-exams

• The PRINCE2 ® Foundation Examination Sample Paper, available at https://www.axelos.com/certifications

• IREB (CPRE Foundation Level, Practice examination), available at https://www.ireb.org/en/downloads/tag:foundation-level

• ISTQB (Certified Tester Foundation Level Sample Examination), available at https://www.istqb.org/downloads/

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 2

Page 3: IT Project Management

1. Scope

What describes BEST the scope of

risk management?

a)Analysis, decline or accept, and control

b)Identification, analysis, and monitoring and

control

c)Regular identification and evaluation

d)Identification, quantification, and prioritization

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 3

Page 4: IT Project Management

1. Scope

What describes BEST the scope of

risk management?

a)Analysis, decline or accept, and control

b)Identification, analysis, and monitoring and

control

c)Regular identification and evaluation

d)Identification, quantification, and prioritization

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 4

Page 5: IT Project Management

2. Project and Product Risks

Which of the following is NOT a project risk?

a)Supplier issues

b)Error prone software delivered

c)Organization factors

d)Technical issues

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 5

Page 6: IT Project Management

2. Project and Product Risks

Which of the following is NOT a project risk?

a)Supplier issues

b)Error prone software delivered

c)Organization factors

d)Technical issues

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 6

Page 7: IT Project Management

3. Risk analysis

Which of the following is a risk analysis technique?

a)Outsourcing

b)Acceptance

c)Network diagrams

d)Brain storming

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 7

Page 8: IT Project Management

3. Risk analysis

Which of the following is a risk analysis technique?

a)Outsourcing

b)Acceptance

c)Network diagrams

d)Brain storming

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 8

Page 9: IT Project Management

4. Risk analysis

Which statement is TRUE?

a)All risks must be analyzed.

b)The less severe a risk, the more important is a

deep analysis

c)The more risks identified the better

d)Only less severe risks should be controlled

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 9

Page 10: IT Project Management

4. Risk analysis

Which statement is TRUE?

a)All risks must be analyzed.

b)The less severe a risk, the more important is a

deep analysis

c)The more risks identified the better

d)Only less severe risks should be controlled

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 10

Page 11: IT Project Management

5. Calculation

Concerning the impact of a risk, which statement is

TRUE?

a)The impact is an important part of a risk.

b)The impact could not be guessed.

c)The impact is dependent on price changes.

d)The impact depends on the size of the project.

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 11

Page 12: IT Project Management

5. Calculation

Concerning the impact of a risk, which statement is

TRUE?

a)The impact is an important part of a risk.

b)The impact could not be guessed.

c)The impact is dependent on price changes.

d)The impact depends on the size of the project.

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 12

Page 13: IT Project Management

6. Risk

What determines the level of risk?

a)The probability that an adverse event will occur.

b)The amount of testing planned before release of

a system.

c)The likelihood of an adverse event and the

impact of the event.

d)The cost of dealing with an adverse event if it

occurs.

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 13

Page 14: IT Project Management

6. Risk

What determines the level of risk?

a)The probability that an adverse event will occur.

b)The amount of testing planned before release of

a system.

c)The likelihood of an adverse event and the

impact of the event.

d)The cost of dealing with an adverse event if it

occurs.

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 14

Page 15: IT Project Management

7. Prioritization

Which of the following risks should get highest priority?

a) Risk rated as high probability and impact of 4 weeks

schedule delay

b) Risk rated as high probability and impact of 8 weeks

schedule delay

c) Risk rated as medium probability and impact of 10

weeks schedule delay

d) Risk rated as low probability and impact of 6 weeks

schedule delay

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 15

Page 16: IT Project Management

7. Prioritization

Which of the following risks should get highest priority?

a) Risk rated as high probability and impact of 4 weeks

schedule delay

b) Risk rated as high probability and impact of 8 weeks

schedule delay

c) Risk rated as medium probability and impact of 10

weeks schedule delay

d) Risk rated as low probability and impact of 6 weeks

schedule delay

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 16

Page 17: IT Project Management

8. Risks

Which of the following statements is TRUE?

a)Reviewing problems that occurred on previous projects is helpful in avoiding risks.

b)The review of problems encountered in previous projects can help in identifying risks.

c)Reviewing problems that occurred on previous projects is useful to prioritize risks.

d)The review of problems encountered in previous projects is helpful in monitoring risks.

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 17

Page 18: IT Project Management

8. Risks

Which of the following statements is TRUE?

a)Reviewing problems that occurred on previous projects is helpful in avoiding risks.

b)The review of problems encountered in previous projects can help in identifying risks.

c)Reviewing problems that occurred on previous projects is useful to prioritize risks.

d)The review of problems encountered in previous projects is helpful in monitoring risks.

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 18

Page 19: IT Project Management

9. Risks

Which statements is TRUE?

a)Risks cause project failures.

b)Risks cannot be ignored.

c)Risks cost more than problems to respond to.

d)Risks are always in the future.

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 19

Page 20: IT Project Management

9. Risks

Which statements is TRUE?

a)Risks cause project failures.

b)Risks cannot be ignored.

c)Risks cost more than problems to respond to.

d)Risks are always in the future.

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 20

Page 21: IT Project Management

10. Risk mitigation

How could a cost and schedule risk directly be

mitigated?

a)Use of reserves.

b)Use of simulations.

c)Use of status reports.

d)Use of decision trees.

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 21

Page 22: IT Project Management

10. Risk mitigation

How could a cost and schedule risk directly be

mitigated?

a)Use of reserves.

b)Use of simulations.

c)Use of status reports.

d)Use of decision trees.

Uwe Gühl, 2020 IT Project Management

Risk Management – Quiz 2-6 - 22