Page 1
Irrigation Development – The Next Steps
“Lake Diefenbaker offers opportunities for multi-
use water based development in Saskatchewan. It
was envisioned that the associated irrigation work
would carry water to approximately 450,000 acres
of irrigable lands.” Presented to:
Saskatchewan Irrigation Project Association
November 9, 2009
Presented by: Dale Miller, P. Eng., F.E.C.
Page 2
Saskatchewan Irrigation Project Association – November 9, 2009 2
Presentation Overview
1. Current Development Level
2. The Potential
3. Highlights of three major project opportunities
• Westside
• Qu’Sip
• SSRID – Block 5
4. Needed next steps – what, when, why
5. Four Messages
6. Questions
Page 3
Saskatchewan Irrigation Project Association – November 9, 2009 3
Current Development Level
Page 4
Saskatchewan Irrigation Project Association – November 9, 2009 4
Current Development Level
Lake Diefenbaker Development Area Irrigation Projects
2004
Project Acres
South Saskatchewan River Irrigation District 35,271
Macrorie Irrigation District 2,471
Luck Lake Irrigation District 8,602
Riverhurst Irrigation District 9,868
Thunder Creek Irrigation District 1,422
Grainland Irrigation District 2,141
River Lake Irrigation District 985
Brownlee Irrigation District 1,893
Hillcrest Irrigation District (from SSEWS) 3,497
Private Irrigators (from SSEWS) 13,953
Other Private Irrigators 20,928
Total 101,031
Page 5
Saskatchewan Irrigation Project Association – November 9, 2009 5
Current Development Level
Lake Diefenbaker
Existing Irrigation
Development
Page 6
Saskatchewan Irrigation Project Association – November 9, 2009 6
The Potential
Page 7
Saskatchewan Irrigation Project Association – November 9, 2009 7
What is the Potential?
The Potential
Five studies were completed since 2006 identifying
potential infill, expansion and new projects.
3 Existing Projects (infill and expansion)
• Luck Lake Irrigation District
• Riverhurst Irrigation District
• South Saskatchewan River Irrigation District No. 1
(East Side)
and 2 New Projects
• Westside Irrigation Project
• Qu’Appelle South Irrigation Project
Page 8
Saskatchewan Irrigation Project Association – November 9, 2009 8
The Potential
Luck Lake Irrigation District Infill
and Expansion
(Golder, 2006-additional 9,400 Ac)
Page 9
Saskatchewan Irrigation Project Association – November 9, 2009 9
Luck Lake Irrigation District
Infill and Expansion
The Potential
Riverhurst Irrigation System
Expansion (Clifton, 2006 -
additional 10,900 Ac)
Page 10
Saskatchewan Irrigation Project Association – November 9, 2009 10
The Potential
Luck Lake Irrigation District Infill
and Expansion
Riverhurst Irrigation System
Expansion
SSRID Infill and Expansion
(AECOM – Nov/06-additional
28,350 Ac)
Page 11
Saskatchewan Irrigation Project Association – November 9, 2009 11
The Potential
Luck Lake Irrigation District Infill
and Expansion
Westside Irrigation Project
(AECOM-March/06-332,000 Ac)
Riverhurst Irrigation System
Expansion
SSRID Infill and Expansion
Page 12
Saskatchewan Irrigation Project Association – November 9, 2009 12
The Potential
Luck Lake Irrigation District Infill
and Expansion
Westside Irrigation Project
SSRID Infill and Expansion
Riverhurst Irrigation System
Expansion
Qu’Appelle South Irrigation Project
(AECOM-June/07 – 113,000 Ac)
Page 13
Saskatchewan Irrigation Project Association – November 9, 2009 13
The Potential
Summary
1. Current irrigation development from Lake Diefenbaker –
101,000 acres.
2. Potential expansion and infill of existing projects could
add about 55,000 acres.
3. Complete Westside Project – 332,000 acres (lake
portion).
4. Qu’Appelle South – 113,000 acres.
5. Total development could be 600,000 acres.
Page 14
Saskatchewan Irrigation Project Association – November 9, 2009 14
Highlights of Three Major Project Opportunities
Page 15
Saskatchewan Irrigation Project Association – November 9, 2009 15
Highlights of Three Major Project Opportunities
The Development Concepts for:
• SSRID – Area 5 9,620 Ac
• Westside 332,000 Ac
• Qu’Appelle South 113,000 Ac
Page 16
Saskatchewan Irrigation Project Association – November 9, 2009 16
Highlights of Three Major Project Opportunities
SSRID – Area 5 - Overview
• Lands formally considered for irrigation development
as part of Elbow Irrigation Project (Cochrane Lavalin,
1989).
• Layout – booster pump station near the start of the M1
Canal (3.5 m3/s @ 156 psi).
• 9,620 Ac block at the lower elevations adjacent to the
shoreline of Diefenbaker Reservoir.
• $32M (2006 dollars) - $3,332/Ac (excludes on-farm).
Page 17
Saskatchewan Irrigation Project Association – November 9, 2009 17
Highlights of Three Major Project Opportunities
Page 18
Saskatchewan Irrigation Project Association – November 9, 2009 18
Highlights of Three Major Project Opportunities
Westside Irrigation Project (not really a new project)
• Construction was initiated in the late 1960’s and abandoned in 1973.
• Earthwork and control structures on Westside Main Canal
completed to Conquest when work was halted.
• Two of three embankments of Conquest Reservoir completed.
• Westside pump plant structure completed.
• 80,000 acres of flood irrigation planned.
In the 1980’s farmers in the Macrorie area petitioned for revival of
the project.
• Two pumps installed and Westside Main Canal dyked off.
• Macrorie Irrigation District irrigates 2,500 acres.
Page 19
Saskatchewan Irrigation Project Association – November 9, 2009 19
Highlights of Three Major Project Opportunities
Existing abandoned Westside Main Canal
Page 20
Saskatchewan Irrigation Project Association – November 9, 2009 20
Highlights of Three Major Project Opportunities
• 332,000 acres serviced from an upgraded Lake Diefenbaker pump
station and an enlarged and extended West Main Canal.
• The extended canal follows the natural land contour to a point 1.2
km north of Tessier, where it divides into two smaller capacity
canals. One proceeds west to a syphon across Eagle Creek, and
the other one heads northeast and east to supply the Delisle West
– Asguith and Donavan Delisle blocks.
• Pump station situated along the main canals with a pipeline
distribution system services the land.
• Blocks at higher elevations (Zealandia, etc.) require a second
booster pump.
• Three reservoirs, Conquest, Eagle Hill Creek and Delisle
proposed, plus several re-regulation reservoirs.
• $1,738 Million (excluding on-farm) or $5,247/acre.
Westside Irrigation Project - Concept Today
Page 21
Saskatchewan Irrigation Project Association – November 9, 2009 21
Highlights of Three Major Project Opportunities
Westside Irrigation Project
South
Saskatchewan
River 25,000 Acres North
Saskatchewan
River 17,500 Acres
Lake Diefenbaker
332,000 Acres
Total =
375,000 Acres
Page 22
Saskatchewan Irrigation Project Association – November 9, 2009 22
Highlights of Three Major Project Opportunities
Irrigable Land Blocks
Within the Westside
Irrigation Project
Saskatoon
Outlook
Gardiner
Dam
Page 23
Saskatchewan Irrigation Project Association – November 9, 2009 23
Highlights of Three Major Project Opportunities
Qu’Appelle South Irrigation Project (Qu’SIP)
• 113,000 acres serviced from a pump station on Lake Diefenbaker
feeding into single main canal system paralleling the Qu’Appelle
Valley.
• Pump stations along main canal feed pressurized pipeline
distribution systems to provide water to individual land parcels.
• One reservoir proposed including a booster pump, plus several re-
regulation reservoirs.
• Main Canal spills into Buffalo Pound Lake. Route is currently
being considered as an alternative water source for Buffalo
Pound Lake and the lower Qu’Appelle system. (AECOM –
July, 2009)
• $559 Million (2007 dollars) or $5,054/acre.
Page 24
Saskatchewan Irrigation Project Association – November 9, 2009 24
Highlights of Three Major Project Opportunities
Qu’SIP Potential Irrigable Land – 113,000 Acres
Option 2A – 110,500 Acres
Page 25
Saskatchewan Irrigation Project Association – November 9, 2009 25
Needed Next Steps
Page 26
Saskatchewan Irrigation Project Association – November 9, 2009 26
Needed Next Steps
1. Establish Entitlement to Water
• SSRID’s current licence is adequate to accommodate
expansion of the District.
BUT
• Both the Westside and Qu’SIP will need to obtain a
water licence.
Page 27
Saskatchewan Irrigation Project Association – November 9, 2009 27
Needed Next Steps
Estimated Water Needs
Annual Water Needs
Mean Upper Decile
Westside 524,000 dam3 620,000 dam3
Qu’SIP 170,000 dam3 210,000 dam3
Less – Allotment for
Westside 106,079 dam3 106,079 dam3
Total 587,921 dam3 723,921 dam3
Page 28
Saskatchewan Irrigation Project Association – November 9, 2009 28
Needed Next Steps
Availability
In flow – South Saskatchewan River
• After discounting for Alberta’s share
Mean - 5,500,000 dam3
90% Probability 3,000,000 dam3
• Total licenced diversion is presently 616,000 dam3* +
• Need approximately 600,000 dam3 in new licences
• Water is available – Entitlement must be determined
* Not all consumptive
Page 29
Saskatchewan Irrigation Project Association – November 9, 2009 29
Needed Next Steps
• Alberta’s 1.5 million acres of irrigation is supported by
3.0 million dam3 of storage.
• Lake Diefenbaker storage is 9.4 million dam3 (live is
4.3 million dam3).
Page 30
Saskatchewan Irrigation Project Association – November 9, 2009 30
Needed Next Steps
2. Obtain Better Topography Info
• For all three studies topography information consisted of
10 m contour maps.
• The available topographic information is the single most
limiting factor in the refinement of the canal and pipeline
routing.
• Better topographic information is also needed to advance
siting of reservoirs, wasteways, syphons, etc. and to
evaluate drainage.
• Lidar - approximately $400,000.
2. a) Review/Refine Routing – All Three Projects
• With better topography, routing and cost estimates can
be refined.
Page 31
Saskatchewan Irrigation Project Association – November 9, 2009 31
Needed Next Steps
• Eagle Hill Creek
• Qu’SIP Midpoint Reservoir (Eyebrow Hills Reservoir)
• Conquest
• Delisle
• Other possible sites
3. Advance Reservoir Concepts ($2 - 2.5 Million)
Information on any of the proposed reservoir sites is very
limited. The reservoir concepts need to be addressed in
more detail to determine their suitability, cost, impact, etc.
Will require:
• Surveys
• Geotechnical
• Hydrology
• Hydrogeological studies
Page 32
Saskatchewan Irrigation Project Association – November 9, 2009 32
Needed Next Steps
Page 33
Saskatchewan Irrigation Project Association – November 9, 2009 33
Next Needed Steps
4. Conduct Irrigation Suitability Study on Targeted
Lands - 500,000 Ac - 600,000 Ac +
• Previous studies of the available soils information
identified only the best likely soils suitable for irrigation.
• Assumed 130 acres/quarter
• Detailed Soil Suitability will be required virtually for all
the potential development.
• Irrigation certification work could easily take 3-5 years
to do. It should be started NOW.
• Focus on slight to moderately limited lands
• Target easily accessed sites within these lands
• $2,000/quarter.
Page 34
Saskatchewan Irrigation Project Association – November 9, 2009 34
Needed Next Steps
Irrigable Blocks
Page 35
Saskatchewan Irrigation Project Association – November 9, 2009 35
Needed Next Steps
Land Irrigability –
Keeler
• Shallow loam & clay
loam Bradwell / Elstow &
Weyburn loam soils.
• Soil depth / shallow
bedrock may limit
irrigability.
• Saline lands to east
removed.
• Some sloughs.
Page 36
Saskatchewan Irrigation Project Association – November 9, 2009 36
Needed Next Steps
14,300 Acres
Page 37
Saskatchewan Irrigation Project Association – November 9, 2009 37
Needed Next Steps
5. Confirm Project Boundaries
Factors:
• Farmer interest mapping
• Soil classifications
• Available funding
• Policy development – Do we include isolated parcels,
or large blocks significantly away form water source?
• Do we include blocks that are suitable but maybe of
little interest today?
• Politics
Page 38
Saskatchewan Irrigation Project Association – November 9, 2009 38
Needed Next Steps
6. For Qu’SIP - Confirm intake and pump station locations
and regulatory requirements (fish exclusion, etc.)
• Bathymetric surveys will be required to confirm location
• Geotechnical
• Regulatory constraints
• Power supply
• Capacity (part of Upper
Qu’Appelle Conveyance ? ?)
Page 39
Saskatchewan Irrigation Project Association – November 9, 2009 39
Needed Next Steps
Page 40
Saskatchewan Irrigation Project Association – November 9, 2009 40
Needed Next Steps
7. For Qu’SIP - Finalize spill location into Buffalo Pound and
spillway concept and capacity (part of Upper Qu’Appelle??)
• Surveys and geotechnical needed.
• Will it be combined with Qu’Appelle conveyance?
Page 41
Saskatchewan Irrigation Project Association – November 9, 2009 41
Needed Next Steps
8. Geotechnical
• For Westside and Qu’SIP, lining is a major component
of canal costs. A geotechnical investigation of the
proposed canal alignment would provide information
on soil texture and the local water table.
Page 42
Saskatchewan Irrigation Project Association – November 9, 2009 42
Needed Next Steps
9. Start Regulatory Approval Process (2 - 4 Years)
Several approvals will be required under various Provincial and
Federal Legislation.
• Environmental Assessment Act (Provincial)
• Environmental Management and Protection Act (Provincial)
• Canadian Environmental Assessment Act
• Fisheries Act (DFO)
• Saskatchewan Watershed Authority (Provincial)
• Wildlife Habitat Protection Act (Provincial)
• Species at Risk Act
• Heritage Property Act
• Navigable Waters Act
Page 43
Saskatchewan Irrigation Project Association – November 9, 2009 43
Needed Next Steps
Any of the Previous Activities May Trigger Other
Requirements – Be Prepared for Surprises
In particular, regulatory approvals will take significant time and
may have cost impacts.
Page 44
Saskatchewan Irrigation Project Association – November 9, 2009 44
Other Steps (Lower Priority)
10. Balancing Reservoirs - Qu’SIP and Westside will
require several balancing reservoirs to improve
management and operations, to reduce capacity of the
system and supply surge protection, etc. Initial sizing
and siting needs to be done.
11. Drainage - An allowance for land drainage, particularly
in parts of the Westside Project, was included in the
Study. To what extent it is needed is unknown.
• Include screening in soil irrigability assessment
• Combine with topography survey and mapping
Needed Next Steps
Page 45
Saskatchewan Irrigation Project Association – November 9, 2009 45
Other Steps (Lower Priority)
*12. Water Management Plan - Water will allow countless
opportunities for other enhancement. This study would
look at opportunities to enhance regional development
and the environment as part of the Project.
Needed Next Steps
Page 46
Saskatchewan Irrigation Project Association – November 9, 2009 46
Four Messages
Page 47
Saskatchewan Irrigation Project Association – November 9, 2009 47
Four Messages
• Engineering is a straight-forward application of
mathematics and physics. Once decisions are made it
is a matter of following an implementation plan.
• Government delays, regulatory hurdles, policy
decisions (or indecisions), public support, bureaucratic
structure: all will have a bigger impact on the
implementation and eventual cost than the engineering.
1. Politics Trumps Physics
Page 48
Saskatchewan Irrigation Project Association – November 9, 2009 48
Four Messages
• The economics show it has a significant cost benefit.
• It fits well with the need for economic stimulus.
• You have been talking about it for years.
2. To the Politicians
“!@#$% or get off the pot”.
• Commitment is needed with real money, $10M/year for
2 to 3 years, and $50 - $100 M/year during
construction.
• Without a firm commitment with adequate funding,
nothing will move forward.
Page 49
Saskatchewan Irrigation Project Association – November 9, 2009 49
Four Messages
• Federally or Provincially, you are not currently structured to
undertake such a massive capital project.
• Ask yourself “How you would spend $50 million, or even
$5 million if you were given it”
3. To the Government Departments
“Start looking at the mechanism that will be
needed to make it happen”.
• You may require legislative changes to structure and
procedures.
• You may require the creation of new government agencies.
• In any event, the structure will require timely decisions on
spending large sums of money.
• The governments ability or inability to implement such a
major undertaking should not impact the project.
Page 50
Saskatchewan Irrigation Project Association – November 9, 2009 50
Four Messages
• You are being heard, but more needs to be done.
• The decision to proceed will be based on politics.
4. To SIPA and the Landowners
“Keep spreading the word”.
• In particular, develop strong allies: the cities, rural
economic development groups.
• Keep control. Do not expect others to sell irrigation.
• When the money comes, stay involved.
• Sell it as a Required Water Supply System that
benefits everyone, and not just irrigators.
Page 51
Saskatchewan Irrigation Project Association – November 9, 2009 51
Implementation
1. Feasibility Studies – Completed
• AECOM Reports
• Clifton’s Economic Study
Typical Project Development
2. Complete Needed Next Step Tasks (Pre-Design)
• Appropriate funding must be provided
• Tasks could be completed in 3-4 years
• Typically 1 ½ - 2 % of project costs
• For Qu’SIP, would need $4-5 million/year budgeted – cannot do
it with a bunch of $300,000 studies.
3. With Proper Implementation Plan Design/Construction of Project
• SSRID - 4 years
• Qu’SIP - 10 years
• Westside – 15-20 years
Page 52
Saskatchewan Irrigation Project Association – November 9, 2009 52
Questions