Top Banner
Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime. Complied by AlNik Solutions for project managers using PMPlan products.
58

Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Dec 22, 2015

Download

Documents

Emory Hodges
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Introduction to Project Management

A basic introduction to common project management processes that may be typically

encountered during a projects lifetime.

Complied by AlNik Solutions for project managers using PMPlan products.

Page 2: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

“Robert’s Rules of Order for Project Management”

1. Get a project charter2. Create the project scope statement3. Create the WBS with the project team4. Create the activity list from the WBS5. Sequence the activities in the order in which

they must – or should – happen6. Estimate the time of the activities based on

which resources you have to complete the activities

7. Assign the needed resources to the activities8. Get it done.

From “Real Life Project Management: Managing the Project Scope” by Joseph Phillips Jan 28, 2005

Page 3: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Agenda of Presentation

• General Project Management

• Work Breakdown Structure

• Scheduling

• Earned Value Management

Page 4: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Common Project Processes

• Initiation– Defines the project objectives and grants authority to the project

manager.• Planning

– Refines the project objectives and scope and plans the steps necessary to meet the project’s objectives.

• Executing– Puts the project plan into motion and performs the work of the

project.• Controlling

– Measures the performance of the executing activities and compares the results with the project plan.

• Closing– Documents the formal acceptance of the project’s product and

brings all aspects of the project to a close.

Page 5: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Managing the Triple Constraint

• Project Scope– How much work is to be done? Increasing the scope

causes more work to be done, and vice versa.

• Time– The schedule of the project. Modifying the schedule

alters the start and end dates for tasks in the project and can alter the project’s overall end date.

• Cost– The cost required to accomplish the project’s

objectives. Modifying the cost of the project generally has an impact on the scope, time, or quality of the project.

Page 6: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Project Manager Roles and Interactions

Page 7: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Elements of Developing a Project Plan

ClientSOW

WorkBreakdown Structure

ActivityDefinition

ResourcePlanning

ResourcePool

ActivitySequencing

ActivityDuration

Estimating

CostEstimating

ScheduleDevelopment

WorkPackages

Project PlanDevelopment

PMPlan can address these elements when developing the project plan.

Page 8: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

What is a Work Breakdown Structure

“The Work Breakdown Structure (WBS) is the foundation for defining the project’s work as it relates to the objectives and establishes a structure for managing the work to its completion. The WBS defines:

• the project’s work in terms of activities that create deliverables.

• the project’s life-cycle process, in terms of process steps appropriate to that project and organization.

And is the basis for establishing:

• All of the effort/cost to be expended to create the deliverables and supporting processes.

• The assigned responsibility for accomplishing and coordinating the work.

” (from the PMI Practice Standard for Work Breakdown Structures, Oct 2000)”

Page 9: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Good WBS Design Principles

• The 100% Rule– The WBS defines 100% of the work of the project– Anything that isn’t defined in the WBS is outside the scope of the project.– The work content on any item is the sum of what is included under that

work item

• Upper Levels are Planned outcomes (deliverables), not planned actions

• Ends of WBS include the activities needed to create the project deliverables

• Mutually-exclusive elements– Work should only appear in one place in the WBS

• WBS must be consistent with the way the project will be performed and controlled

• Must be easy to update

Page 10: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

WBS Role

• Partition the major project deliverables into smaller components to improve the accuracy of cost estimates

• Provide a mechanism for collecting actual costs

• Provide a mechanism for performance measurement and control

Page 11: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Sample WBS – Product Type Project

1 Project Management 2 Ship

2.1 Hull Structure

2.2 Propulsion Plant

2.3 Command and Surveillance

2.4 Auxiliary Systems

2.5 Outfit and Furnishings

2.6 Armament

2.7 Integration/Engineering

2.8 Ship Assembly and Support Systems

3 System Engineering

Product Project - Ship System

4 System Test and Evaluation

5 Integrated Logistics Support

6 Operational/Site Activation

7 Industrial Facilities

Page 12: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Sample WBS – Service Type Project

1 Project Management 2 Attendees

Service Project - International Conference Project

3 Transportation 4 Facilities 5 Program 6 Displays

Page 13: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Sample WBS – Results Type Project

1 Project Management

2 Work Plan 3 Product and Process Analysis

Results Project - HACCP Implementation

4 Hazard Analysis 5 Q.A. Process 6 CCP Plan Process

7 HACCP Implementation

Page 14: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Why create a WBS?

• Cost Estimating

• Cost Budgeting

• Resource Planning

• Risk Management Planning

• Activity Definition

Page 15: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Scheduling

• Scheduling forces:– Quantification of discrete effort– Placement of tasks in proper relationship

• Two most common scheduling methodologies– Bar Charts (aka Gantt Charts)– Critical Path Method (CPM) using Precedence

Diagramming Method (PDM)

Page 16: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Bar / Gantt Charts Defined:

• Analyze and specify the basic approach in execution

• Segment into reasonable number of activities• Estimate the time required to perform each

activity• Manually places activities in time order

– Sequential performance– Parallel performance

• Adjust to specified completion time

Page 17: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Bar / Gantt Charts Advantages:

• Plan, schedule and progress are all depicted graphically on a single chart

• Easily read

• Provides simple way to schedule small undertaking

• Provides summary display of more detailed plans and schedules

• Best used for management briefings

Page 18: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Bar / Gantt Charts Disadvantages:

• Planning and scheduling are considered simultaneously

• Simplicity precludes sufficient detail for timely detection of slippages

• Activity dependencies cannot adequately be shown

• Difficult to determine how activity progress delays affect project completion

• Difficult to establish and maintain for large projects.

Page 19: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Bar / Gantt Chart Sample

25 01 08 15 22

Jan07

29 05 12 19

Feb07

26 05 12 19

Mar07

26 02 09 16 23

Apr07

30 07 14 21

May07

28 04

Jun07Status Date: 02/Mar/2007

WBS Description

Sample Project Plan

1 Literature Search

2 Concepts Development

3 Lab Models

4 Design

5 Prototype

Planned Progress

Actual Progress

Ahead of Schedule

Behind Schedule

Time Now

Completed Task

Page 20: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Critical Path Method Advantages:

• Identifies activities that control the project length• Determines shortest time for completion• Identifies activities that are critical (i.e. cannot be

delayed)• Shows available float for non-critical activities• Allows evaluation of “what-if” scenarios• Allows monitoring & control of fast-track projects• With software can be resource loaded and leveled

Page 21: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Critical Path Method Disadvantages

• Only as good as the effort put forth to properly model the plan

• Can be difficult to properly update

• Can be easily misused

• May lead to a false sense of security

• Actual conditions may necessitate significant modifications to model to accurately reflect reality

Page 22: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Precedence Diagramming Method (PDM)

• PDM network rules:– Activities are represented by boxes or nodes that are

assigned properties of the activity they represent– Precedences are shown by arrows that have both

direction and time properties– Precedences consist of two parts: A relationship and a

lag value or constraint• Finish – to – Start FS• Finish – to – Finish FF• Start – to – Start SS• Start – to – Finish SF

Lag = x Days ( a negative lag is

called a lead)

Page 23: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

PDM – Precedence Diagram

• PDM activities are comprised of:– Activity descriptions– Nodes representing the activity– Arrows representing relationship / dependency– Points indicating direction of relationship /

dependency

Page 24: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

PDM Logic Relationships

Finish to Start (FS) – Activity A must Finish before Activity B may Start.The lag is usually zero. FS is the most common type.

Start to Finish (SF) – Activity A must start before Activity B may Finish. Thelag is usually greater than either activity duration. FS is the least common type.

Activity A Activity B

Activity A Activity B

Page 25: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

PDM Logic Relationships

Finish to Finish (FF) – Activity A must Finish before Activity B may Finish.The lag value is usually greater than zero. FF is a less common type.

Start to Start (SS) – Activity A must Start before Activity B may Start.The lag value is usually greater than zero. SS is a less common type.

Activity A Activity B

Activity A Activity B

Page 26: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

PDM Time Calculations

• Once the Network is constructed and duration of each activity is estimated, we can determined the following four time values:– Earliest Start (ES) – The earliest possible time an

activity can begin– Earliest Finish (EF) – The earliest possible time an

activity can finish– Latest Start (LS) – The latest possible time an activity

can start without delaying project completion– Latest Finish (LF) – The latest possible time an activity

can start without delaying project completion

Page 27: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

PDM Time Calculations

• ES and EF are determined by making a Forward Pass (left-to-right) through the Network. ES of an activity is equal to the latest of early finish times of its predecessors. EF is the total of the activity ES plus its duration.

• LS and LF are determined by making a Backward Pass (right-to-left) through the Network. LF of an activity is equal to the smallest of the LS times of the activities exiting from the activity in question. LS of an activity is equal to its LF minus its duration.

Page 28: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

PDM Activity Notation and Assumptions

• Each activity box consists of six cells

• For the following example assume all activities:– Begin on the morning of the scheduled start

date– End the evening of the scheduled finish date– Using a 7-day workdays per week calendar

4 E 611 2 13

ES EF

Activity

Duration

LS LF

0 Lag

Page 29: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Forward Pass Example

6 D 94

8 E 81

4 F 107

12 G 187

2

0

0

(F to G) 10 + 0 + 1 = 11(E to G) 8 + 0 + 1 = 9(D to G) 9 + 2 + 1 = 12

Largest ES

Early Start Calculations

Early Finish Calculation12 + 7 – 1 = 18

Page 30: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Backward Pass Example

18 H 2425 7 31

18 I 2124 4 27

18 J 1834 1 34

14 K 1719 4 22

2

0

0

(H to K) 25 - 2 - 1 = 22(I to K) 24 - 0 - 1 = 23(J to K) 34 - 0 - 1 = 33

Late Finish Calculations

Late Start Calculation22 - 4 + 1 = 19

Page 31: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

CPM Example Exercise

A6d

B11d

C20d

H20d

J20d

D13d

E9d

F20d

G6d

I13d

Page 32: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

CPM Example Exercise

Forward Pass Results

A6d

B11d

C20d

H20d

J20d

D13d

E9d

F20d

G6d

I13d

1d 6d 7d 17d 18d 37d 63d 82d

1d 20d 21d 33d 34d 42d 43d 62d

34d 39d 40d 52d

Page 33: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

CPM Example Exercise

Backward Pass Results

A6d

B11d

C20d

H20d

J20d

D13d

E9d

F20d

G6d

I13d

1d 6d 7d 17d 18d 37d 63d 82d

1d 20d 21d 33d 34d 42d 43d 62d

34d 39d 40d 52d

4d 9d 10d 20d 43d 62d 63d 82d

1d 20d 21d 33d 34d 42d 43d 62d

44d 49d 50d 62d

Page 34: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

CPM Example Exercise

Backward Pass Results

A6d

B11d

C20d

H20d

J20d

D13d

E9d

F20d

G6d

I13d

1d 6d 7d 17d 18d 37d 63d 82d

1d 20d 21d 33d 34d 42d 43d 62d

34d 39d 40d 52d

4d 9d 10d 20d 43d 62d 63d 82d

1d 20d 21d 33d 34d 42d 43d 62d

44d 49d 50d 62d

Page 35: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

CPM – Float (or Slack) and Critical Path

• Additional Network calculations provides other important information allowing analysis and control:– Total Float (TF) – The amount of time an activity can

be delayed without delaying the overall project completion, which is equal to Late Finish minus Early Finish.

– Free Float (FF) – The amount of time an activity can be delayed without delaying the start of another activity. Can be determine by subtracting the smallest Total Float going into an activity from each predecessor into that activity.

– Critical Path – The path through the Network that has the longest total duration, thus it defines the shortest period of time in which the project may be completed.

Page 36: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Float Calculation Example

21 V 3035 10 45

29 W 3539 7 45

36 X 4046 5 50

44 Y 5044 1 50

51 Z 6051 10 60

FT = 15

FF = 5

FT = 10

FF = 0

FT = 10

FF = 0

FT = 0

FF = 0

FT = 0

FF = 0

Page 37: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

CPM Example Exercise

Continue with Exercise

A6d

B11d

C20d

H20d

J20d

D13d

E9d

F20d

G6d

I13d

1d 6d 7d 17d 18d 37d 63d 82d

1d 20d 21d 33d 34d 42d 43d 62d

34d 39d 40d 52d

4d 9d 10d 20d 43d 62d 63d 82d

1d 20d 21d 33d 34d 42d 43d 62d

44d 49d 50d 62d

Page 38: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

CPM Example Exercise

Float Results

A6d

B11d

C20d

H20d

J20d

D13d

E9d

F20d

G6d

I13d

1d 6d 7d 17d 18d 37d 63d 82d

1d 20d 21d 33d 34d 42d 43d 62d

34d 39d 40d 52d

4d 9d 10d 20d 43d 62d 63d 82d

1d 20d 21d 33d 34d 42d 43d 62d

44d 49d 50d 62d

3d 3d 25d 0d

0d 0d 0d 0d

10d 10d

Page 39: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

CPM Example Exercise

Critical Path Traced

A1d 6d 6d4d 3d 9d

B7d 11d 17d10d 3d 20d

C18d 20d 37d43d 25d 62d

H63d 20d 82d63d 0d 82d

J1d 20d 20d1d 0d 20d

D21d 13d 33d21d 0d 33d

E34d 9d 42d34d 0d 42d

F43d 20d 62d43d 0d 62d

G34d 6d 39d44d 10d 49d

I40d 13d 52d50d 10d 62d

Page 40: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Scheduling Basics Review

• Two widely used scheduling techniques:– Bar / Gantt Charts

• Project, schedule & progress depicted on a single chart

• Easy to read• Good for management review and oversight

– Critical Path Method (CPM)• Identifies activities that control the project length• Identifies activities that are critical• Shows available float for non-critical activities

Page 41: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Earned Value Tracking

Earned Value (EV) based performance measurement systems “Link

Expenditures to accomplishments”

Page 42: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

This review of Earned Value Concept will:

• Describe a simple project and its progress

• Define Earned Value and related terms

• Show how Earned Value defines project performance

Page 43: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Earned Value System

• Can:– Provide early (Difficult to ignore) performance

problem identification– Improve financial Reporting

• Does not:– Recognize Critical Paths

• Will not:– Take management action

Page 44: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Measurement Terminology• Budget at Completion (BAC)

– The sum of the total budget for a work package, major task, or project.• Planned Value (PV)

– The scheduled cost based on the allocation cost items such resources and material during the timeline of an activity

– Also called Budgeted Cost for Work Scheduled (BCWS)• Earned Value (EV)

– The value of the work performed to-date using any reasonably accurate, mutually acceptable methodology for determining value (i.e.; 0/100%, 50/50%, 30/40/40, ratio of units completed versus total units, manager estimate, level of effort, being some examples).

– Also called Budgeted Cost for Work Performed (BCWP)• Actual Valve (AV)

– Total incurred costs charged to a work package by the company’s accounting system, which can include labor costs, direct costs (overhead), and indirect costs (material, travel, and etc.)

– Also called Actual Cost for Work Performed (ACWP)

These values are used to calculate performance.

Page 45: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Performance Terminology

• Cost Variance (CV)– CV = EV – AV = BCWP – ACWP

• Cost Performance Index (CPI)– The cost efficiency ratio of earned value to actual costs (CPI = EV/AV)– In PMPlan, the CPI is used to calculate Estimate at Completion (EAC)

(EAC = BAC/CPI)• Schedule Variance (SV)

– SV = EV – PV =BCWP – BCWS• Schedule Performance Index (SPI)

– The schedule efficiency ratio of earned value accomplished against planned value (SPI = EV/PV). The SPI describes what portion of the planned schedule was actually accomplished.

• Variance at Completion (VAC)– The predicted magnitude of possible underrun or overrun at completion of

work package, major task, or project (VAC = BAC – EAC)

Page 46: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Review of Earned Value Concept

• Will– Describe a simple project and its progress– Define earned value and related terms– Show how earned value defines project

performance

Note: Sample tables and graphics shown in following slides are from PMPlan

Page 47: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Schedule

• This shows a sample project schedule

Page 48: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Planned Budget

• The sample project is loaded with resources which results in an allocated spend plan.

Page 49: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Time-Phased Spend Plan

• This shows the time-phased spend plan if the project proceeds as planned.

Page 50: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Typical Approach of Tracking of Actual versus Planned

• The chart tells us we have spent less than planned to date, but

• We cannot tell if we are behind schedule, nor if the cost for work completed matches the actual costs.

Page 51: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Using Earned Value Method

• For Earned Value Method to work well you need to breakdown the project into measurable activities (Note: in PMPlan,Cost Budgeting is done at the activity level not work package).

• It is recommended that your work packages (where you accumulate actual costs) be one or two levels above the activities.

• The following five slides show different performance results of our sample project.

Page 52: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Example PMPlan Earned Value Worksheet

• The project manager or task leader enters either a earned percentage or a $ value.

• Actual Cost is also entered. In this worksheet, actual cost can also include open commitments such as unpaid invoices for material and equipment.

• The ‘Threshold’ is a percent of the AV to the BAC, which determines when the application uses the CPI to calculate VAC. If AV is less than ‘Threshold’, the VAC equals CV.

• Based on the data entered, this project is both behind schedule and over budget. Even though the current CV = $4,000, the VAC indicates a potential overrun of $5,517.

• The next slide shows two other views of this data.

Page 53: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Project has Negative SV and CV

• In the lower half of the graph, the EV is below both the PV and AC indicating problems with cost and schedule.

• The upper half of the graph shows both CPI and SPI relative to a value of 1. It is showing that progress is being made to improve the schedule, but cost problem remains.

• The black EV bars in the Gantt schedule at the right shows that ‘Design’ and ‘Prototype’ activities are behind schedule.

Page 54: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Status when have - SV and zero (0) CV

• The EV and AC are equal, thus actual cost are inline with accomplishments.

• Even though the project is behind schedule, the schedule variance trend shows a strong improvement in schedule.

Page 55: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Status when have zero (0) SV, + CV

• This project is on schedule and should be completed under budget.

• With the project all of the earned bars line up with the green status line.

Page 56: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Why 50% Complete may not be half the schedule bar!

• In the above sample, all three activities have earned values of 50% of BAC, but the black earned bars are not the same length even though the planned bars are the same.

• Task A is behind schedule, because 75% of the budget was to be spent by end of December.• Task B is ahead of schedule, because only 25% of the budget was to be spent by end of

December.

Page 57: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

In Summary – an Earned Value System

• Can:– Provide early (Difficult to ignore) performance

problem identification– Improve financial Reporting

• Does not:– Recognize Critical Paths

• Will not:– Take management action

Page 58: Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Project Management Methods Summary

• We have described three major processes used in project management– Work Breakdown Structure– Scheduling– Earned Value Management

• We are ready now to see how PMPlan can help you with these processes