REMINDER Check in on the COLLABORATE mobile app Integration of Primavera P6 EPPM with Oracle E-Business Suite Prepared by: Nikola Škorić Planning and Scheduling Engineer Krško Nuclear Power Plant Session ID#: 15444
83

Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Aug 08, 2015

Download

Business

p6academy
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

REMINDER

Check in on the COLLABORATE

mobile app

Integration of Primavera P6 EPPM with Oracle E-Business Suite

Prepared by:

Nikola Škorić

Planning and Scheduling Engineer

Krško Nuclear Power Plant

Session ID#: 15444

Page 2: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Presenter info

■ Nikola Škorić

■ Master of Computer Science (University of Zagreb, 2007)

■ Licensed reactor operator (2010)

■ Planning and Scheduling engineer (2012)

Page 3: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Company info

■ Krško Nuclear Power Plant

■ Joint venture of Slovenia and Croatia

■ Westinghouse built pressurized water reactor

■ First criticality reached: 1981

■ Net power output: 696 MW

Page 4: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Presentation overview

■ Specifics of nuclear industry

■ Outage planning

■ Motivation for this project

■ Architecture of the solution

■ Problems encountered in implementation

■ End results

■ Current status and future plans

Page 5: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Outage planning in nuclear industry

Page 6: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Nuclear industry

■ Large power unit: 17 GWh per day

■ Outage lasts 30-40 days

▪ Large number of activities

▪ Large number of workers

▪ Small operating space (especially reactor building)

Page 7: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Nuclear industry

■ Nuclear fuel produces decay heat after shutdown

■ Nuclear safety first

■ A part of safety equipment has to remain operable

▪ Power sources

▪ Water sources

▪ Valve lineups

Page 8: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Outage planning in nuclear

■ "System windows" – a timeframe in which particular system is maintained in certain state

▪ Visual inspection of snubbers on train A

— Can be done anytime

▪ Instrumentation venting for SW01

— Has 20 predecessors

■ Work orders are placed into system windows

Page 9: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Outage planning in nuclear

■ "Tagout" – a safety procedure which ensures equipment or energy source is isolated

■ Hazards:

▪ Hot water

▪ Water under pressure

▪ Electricity

▪ Mechanical forces

■ Tagouts are "placed on" SWs, WOs or operations

▪ Tags have to be hanged before SW/WO/OP starts

Page 10: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Outage planning in NEK

Page 11: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Outage planning in NEK

■ 35 days

■ 850 system windows

■ 1,000 tagouts

■ 5,000 work orders

■ 15,000 operations

■ ∑: 23,000 activities

■ 2 Primavera specialists

Page 12: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Outage planning in NEK

■ Pre 2011

▪ WOs written in in-house built Work Order System

▪ Everything scheduled in Primavera

■ 2011 – transition to Oracle eBS

■ Post 2011

▪ WOs written and scheduled in eAM (eBS module)

▪ SWs scheduled in Primavera

Page 13: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Outage planning in NEK

1. Oracle Primavera P6 Professional (P6)

▪ Only desktop app, web app unusably slow

2. Oracle E-Business Suite (eBS)

▪ Enterprise Asset Management (eAM)

3. Ventyx Shift Operations Management System (eSOMS)

▪ Clearance Module

4. Shift Supervisor Screen (SSS)

▪ In-house built

Page 14: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Outage planning in NEK

Source Approving Start/stop Status Scheduling

Backbone activity P6 N/A SSS SSS P6

System window P6 N/A P6 SSS P6

Tagout eSOMS eSOMS eSOMS eSOMS custom

Work order eAM SSS eAM SSS eAM*

Operation eAM N/A eAM eAM eAM

Resource eAM N/A eAM N/A N/A

* taking into account SWs in P6

Page 15: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Problems with outage planning in NEK

Page 16: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Problems

1. Shift supervisor does not have a single overview of the plant status

▪ Shift supervisor uses 3 different tools

2. Critical path is obfuscated

▪ Only SWs are in Primavera

▪ WOs and operations are in eAM

▪ Tagouts are in eSOMS

3. Detailed planning not possible

▪ No way for linking WOs, operations and tagouts

4. Tagouts planned by custom built tool

5. WOs planned by suboptimal tool

▪ eAM planning capabilities leave a lot to be desired

Page 17: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Problems

6. WO predecessors scattered across tools

▪ Are all predecessors finished?

7. Planning of operations almost nonexistent

8. Planning of some activities impossible

9. No resource planning

■ Out of sync with industry standards

Page 18: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Problems

■ INPO 06-008 »Guidelines for the Conduct of Outages at Nuclear Power Plants«

▪ Level I: backbone schedule

▪ Level II: activities into schedule to develop system windows,

resource estimates and logic ties for major activities

▪ Level III: resource leveling, logic ties refined

▪ Level IV: cross-discipline horizontal and vertical reviews

Page 19: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Proposed solution

Page 20: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Solution

Source Approving Start/stop Status Scheduling

Backbone activity P6 N/A P6 P6 P6

System window P6 N/A P6 P6 P6

Tagout eSOMS eSOMS eSOMS P6 P6

Work order eAM SSS eAM P6 P6

Operation eAM N/A eAM P6 P6

Resource eAM N/A eAM P6 P6

Page 21: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Existing eAM / P6 integration

■ eAM supports export to P6 format

▪ offline

— must be run manually, cannot be automated easily

▪ not customizable

— no control over what gets exported and in what format

▪ does not work for large projects

— OK for 500 activities

— NEK refueling outage has over 20,000 activities

Page 22: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Solution

eAM This project P6Outside world

eAM P6WOs

Schedule

P6eAM planneddates

eAM P6actual dates

WO authors

workers

Page 23: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Solution

■ New WOs eAM→P6

▪ WOs fall on data date

▪ Makes sense only just

before scheduling

■ Planned dates P6→eAM

▪ Change only on

scheduling

▪ Makes sense only just

after scheduling

eAM This project P6

eAM P6WOs

Schedule

P6eAM planneddates

Page 24: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Solution

■ As frequent as possible

■ We chose 15 minutes eAM This project P6

eAM P6actual dates

Page 25: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Implementation of the solution

Page 26: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

The team

■ Nikola Škorić

▪ NEK, project lead

■ Luka Novosel

▪ Primakon Zagreb

■ Andrej Zalar

▪ OSIR Ljubljana

■ Dušan Urbič

▪ OSIR Ljubljana

■ Simon Jurečič

▪ OSIR Ljubljana

Primavera eAM

Page 27: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Implementation

■ eAM: Oracle RDBMS

■ P6: Oracle RDBMS

■ Preparing output from eAM: PL/SQL

■ Reading from eAM and writing to P6: Java

■ Reading from P6 and writing to eAM: PL/SQL

Page 28: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Implementation

This project

PL/SQL Java

PL/SQL

PL/SQL Java

eAM P6WOs

Schedule

P6eAM planneddates

eAM P6actual dates

Page 29: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Implementation

■ Java

▪ 7,000 lines of code

▪ 36 classes

▪ 700 commits to git repository

■ PL/SQL

▪ 13,000 lines of code

▪ 3 packages

▪ 100 commits to svn repository

Page 30: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Part 1: transfer of work orders from eAM to P6

Page 31: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Transfer of work orders

eAM This project P6

eAM P6WOs

Schedule

Page 32: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Data sources

■ Dates

▪ Master: P6

▪ Slave: eAM

■ All other data

▪ Master: eAM

▪ Slave: P6

■ „Limitation“: data in P6 cannot be modified

Page 33: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Data sources

Operation

WaitingWO Planner

WaitingWork Week

Manager

WaitingShift Supervisor

WaitingWO Coordinator

Approved for work

Work finishedWO coordinator

Work finishedShift Supervisor

Draft

Completed

Working

Finished

Page 34: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Data sources

Imported to Primavera

Operation

WaitingWO Planner

WaitingWork Week

Manager

WaitingShift Supervisor

WaitingWO Coordinator

Approved for work

Work finishedWO coordinator

Work finishedShift Supervisor

Draft

Completed

Working

Finished

Page 35: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Data representation

Activity ID Activity Name Activity type Activity code

NNNNN Description from eAM Level of Effort D

NNNNN-Z Start of WO NNNNN Start Milestone ZD

NNNNN-OOO Description from eAM Task Dependent O

NNNNN-K End of WO NNNNN Finish Milestone KD

Activity ID Activity Name Activity type Activity code

OASWNN000Z Start of system window NN Start Milestone Z

OASWNN000K End of system window NN Finish Milestone K

Page 36: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Data representation – work order

Page 37: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Data representation – system window

Page 38: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Data transferred – work orders EAM P6

P6 project ID P6 project ID

System window Link from SW activity to WO activity + AC + UDF

Work order ID Part of activity ID + UDF

Asset Part of activity name + UDF

Description Part of activity name + UDF

Calendar 24/7

Start Constraint on start milestone

Duration Planned duration

WO type AC

ORAM codes ACs

Plant system AC

Safety train AC

Location UDF

Department AC

WO Planner UDF

Work Coordinator UDF

HTTP link to eAM WO Notebook

Page 39: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Data transferred – operations

EAM P6

P6 project ID P6 project ID

System window AC + UDF

Work order ID Link from WO activity to WO activity + AC

Operation ID Part of activity ID + UDF

Description Activity name

Long description UDF

Calendar Calendar

Duration Planned duration

Links Links

Resources/Instances Roles/Resources

Department AC

Tagging required AC

Reference WO UDF

Page 40: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Data transferred – roles / resources

EAM P6

Operation Assignment to operation

Resource ID Role ID

Instance ID Resource ID

Resource sequence number UDF

Duration Original duration

Required Budgeted units

Assigned units Budgeted units / time

Lag Lag

Page 41: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Data not transferred

■ Planned start

▪ Work orders

— Set as „start on or after“ constraint on WO start milestone

▪ Operations

— Calculated by P6 from predecessor relationships

▪ Roles/resources

— Calculated by P6 from parent activity + lag

■ Planned finish

▪ Calculated by P6 from planned start and planned duration

Page 42: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Cancelled/deleted WOs

■ If WO loses status – removed from P6

■ If WO is deleted from eAM – problem

■ If WO is changes project – problem

Page 43: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Part 2: transfer of planned dates from P6 to eAM

Page 44: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Solution

eAM This project P6Outside world

eAM P6WOs

Schedule

P6eAM planneddates

eAM P6actual dates

WO authors

workers

Page 45: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Transfer of work orders

eAM This project P6

Schedule

P6eAM planneddates

Page 46: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Data transferred

■ for each work order

▪ planned start (from P6) → start (in eAM)

▪ planned finish (from P6) → finish (in eAM)

■ for each operation

▪ planned start (from P6) → start (in eAM)

▪ planned finish (from P6) → finish (in eAM)

Page 47: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Part 3: transfer of actual dates from eAM to P6

Page 48: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Solution

eAM This project P6Outside world

eAM P6WOs

Schedule

P6eAM planneddates

eAM P6actual dates

WO authors

workers

Page 49: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Transfer of actual dates

eAM This project P6

eAM P6actual dates

Page 50: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Data sources

■ Master: eAM

■ Slave: P6

Page 51: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Data transferred – work orders and operations

P6 EAM status of WO Moment

NNNNN actual start

NNNNN-Z actual start

Approved for work WO Coordinator starts WO

NNNNN actual finish

NNNNN-K actual finish

Work finished WO COOR WO Coordinator ends WO

P6 EAM status of WO Moment

NNNNN-OOO actual start Working First Line Supervisor starts OP

NNNNN-OOO actual finish Finished First Line Supervisor ends OP

Page 52: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Data transferred – work orders

Operation

WaitingWO Planner

WaitingWork Week

Manager

WaitingShift Supervisor

WaitingWO Coordinator

Approved for work

Work finishedWO coordinator

Work finishedShift Supervisor

Draft

Completed

Working

Finished

Page 53: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Data transferred – operations

Operation

WaitingWO Planner

WaitingWork Week

Manager

WaitingShift Supervisor

WaitingWO Coordinator

Approved for work

Work finishedWO coordinator

Work finishedShift Supervisor

Draft

Completed

Working

Finished

Page 54: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Data transferred – resources

■ None for now

■ Resource actuals are:

▪ A complicated issue

▪ Of questionable demand

Page 55: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Testing

Page 56: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Testing

■ Development workflow:

1. Implement solution

2. Run the program

3. Check if data was transferred correctly

■ Checking:

▪ Manual

▪ Automated

Page 57: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Testing

■ SQL view to P6 database

■ SQL view to eAM database

■ Comparison of:

1. WOs

2. operations

3. roles/resources

■ Very robust testing tool

Page 58: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Implementation issues

Page 59: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Implementation issues

■ Deleted and moved work orders

■ Activity type for work order

■ Linking of tagouts to work orders

■ Calendars

■ Time resolution difference

■ 0 time interpretation difference

■ Resource durations and units

■ Performance problems

■ Reference operations actuals

Page 60: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Issues: Deleted and moved work orders

Imported to Primavera

Operation

WaitingWO Planner

WaitingWork Week

Manager

WaitingShift Supervisor

WaitingWO Coordinator

Approved for work

Work finishedWO coordinator

Work finishedShift Supervisor

Draft

Completed

Working

Finished

Page 61: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Issues: Deleted and moved work orders

■ First choice: work order has to be reset to „draft“ status

▪ Program detects WOs in wrong status for that project and

removes them from P6

■ In practice: WO planners are fast

▪ They change WO‘s project (to next outage)

▪ Or they delete WO from eAM

■ Consequence: program does not find WO with wrong status

▪ WO stays in P6

■ Solution: manually remove WO from P6

▪ Administrative solution, albeit effective one

■ Future solution: fully compare eAM and P6

▪ Problem: not a trivial algorithm

Page 62: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Issues: Activity type for work order

■ First choice: task dependent

▪ Relationship loops

▪ Does not adapt to changes in operation duration

■ Second choice: dedicated script

▪ Unpractical, has to be run every time operation duration

changes

▪ Duplicating Primavera features

■ Solution: level of effort

▪ Requires milestones to avoid loops

▪ Cannot be linked to

— Relationships define duration of LoE activity

— Serious drawback

Page 63: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Issues: Linking of tagouts to work orders

■ For each tagout eSOMS:

1. Takes a list of activity IDs

2. Creates hang/remove activities

3. Creates relationships

Page 64: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Issues: Linking of tagouts to work orders

■ First choice: task dependent WOs

▪ Unacceptable

■ WOs have to be level of effort

▪ Relationships should point to milestones

▪ eSOMS doesn't know how to do that

■ Solution: no tagouts on WOs

▪ Tagouts placed only on SWs and operations

■ Future solution: implement our own eSOMS integration

▪ Our implementation will link to milestones

Page 65: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Issues: Calendars

■ eAM has only 24/7 calendar

▪ Planning unrealistic

■ First choice: only 24/7 in P6

▪ Easy solution

▪ Planning unrealistic, defeats the purpose

■ Solution: implementing calendars in eAM

▪ Allows for detailed planning

▪ Considerable effort

Page 66: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Issues: Time resolution difference

■ eAM has support for fraction of a second

■ P6 has support for minutes

■ NEK plans in hours

■ First choice: transfer data as is

▪ P6 migrates to planning seconds

■ Second choice: round eAM times to hours during transfer to P6

▪ different data in eAM in P6

▪ testing impossible

■ Solution: redesign eAM to accept only hours

Page 67: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Issues: 0 time interpretation difference

Page 68: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Issues: 0 time interpretation difference

■ If:

▪ Last operation in work order has duration 0, and

▪ Operation before that ends on last second of the work day

■ Then

▪ P6 schedules it for start of the next work day (i.e. 7 AM)

▪ eAM schedules it for end of previous work day (i.e. 3 PM)

■ Consequence

▪ 16 hour discrepancy between P6 and eAM

■ Solution: none

▪ We adjusted all of our programs to ignore that issue

Page 69: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Issues: Resource durations and units

■ Primavera: duration * units / time = units

▪ Strictly enforced

■ eAM: whatever

▪ In practice, every planner has his own interpretation

■ First choice: Write eAM data to P6 and hope for the best

▪ Didn‘t work

■ Solution: ignore the problem

▪ We do not analyze/optimize resources (yet)

▪ Most practical solution given time constraints

■ Future solution: teach eAM the P6 way

▪ The right thing to do

▪ A major change to eAM

Page 70: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Issues: Performance problems

■ First choice: iterate through all WOs changed since last run

▪ We relied on eAM‘s internal „last change“ timestamp

▪ WO “changed” every time planned start/finish was changed

— That is: on every reschedule

■ Every run lasted for 2.5 hours

■ Solution: use testing engine to find differences

▪ heavily optimized to take as little time as possible

Page 71: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Issues: Reference operations actuals

■ Reference operation – placeholder operation for another work order

▪ Administratively belongs to parent WO

▪ In practice belongs to some other SW

■ First choice: do not import them to P6

▪ What if RO has several predecessors/successors

■ Second choice: make it a milestone (duration: 0h)

▪ Gives the wrong impression (nothing lasts 0h)

■ Third choice: start when predecessors end, end when successor starts

▪ What if the only successor is RO? Deadlock!

Page 72: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Issues: Reference operations actuals

Has ordinary

predecessor

Has reference

predecessor

Condition for start Date of start

Yes Yes All ordinary

predecessors finished

End of last ordinary

predecessor

Yes No All ordinary

predecessors finished

End of last ordinary

predecessor

No Yes All reference

predecessors finished

End of last reference

predecessor

No No Work order started Start of work order

■ Solution for actual start of reference operation

Page 73: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Changes to eAM

■ eAM had limited support for operation linking

▪ Implemented operation linking

■ eAM had only one calendar: 24/7

▪ Implemented multiple calendars

■ eAM had support for planning up to a second

▪ Restricted dates to hours

■ eAM Gantt charts had minimal resolution of 1 day

▪ Implemented Gantt charts with 1 minute resolution

Page 74: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

End results

Page 75: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

End result

Page 76: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

End result

Page 77: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

End result

Page 78: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

End result

Page 79: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Current status and future plans

Page 80: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Current status

■ Integration operational for

▪ refueling outage

▪ forced outage

▪ online operation

■ Currently we are

▪ Refactoring code

▪ Documenting code

▪ Writing unit tests

▪ Packaging code to run as eAM module

Page 81: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Future plans

■ Custom P6/eSOMS integration tool

▪ linking tagouts to WOs

▪ resources calculation

▪ conflict check and optimization

■ Better support for roles/resources

▪ better eAM resource support

▪ resource actuals

■ Opening the project for others to use?

Page 82: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14

Thank you

■ Thank you for your attention!

■ Email: [email protected]

■ LinkedIn: linkedin.com/in/nskoric

Page 83: Integration of primavera p6 eppm with oracle e business suite - Oracle Primavera P6 Collaborate 14