www.coregrouting.com Installation of LNG Unloading Jetty Case study: Middle East OVERVIEW Core Grouting Services along with sister company Large Diameter Drilling was contracted to complete the installation of drilled and grouted piles for a LNG unloading jetty. EQUIPMENT • OPC grouting spread • Offshore cement silos SCOPE OF WORK • Pre- project grout testing and optimisation • Installation of ~192 piles drilled & grouted piles – vertical and raked • Project cement amount of ~5000 tonnes • Deployment of a grout monitoring system