Information for Meeting in Sweden. Feedback from uk national agency. Management and Monitoring. Broadly on schedule – must avoid further slippage More hands on management from UK (Decide how October 2010 ) stronger communication closer more regular monitoring - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Information for Meeting in Sweden

Information for Meeting in Sweden

Page 2: Information for Meeting in Sweden

FEEDBACK FROM UK NATIONAL AGENCY

Page 3: Information for Meeting in Sweden

Management and Monitoring

• Broadly on schedule – must avoid further slippage• More hands on management from UK (Decide how

October 2010)– stronger communication– closer more regular monitoring– Concrete deadlines and milestones

• Interim report information from partners (October 2010)

• Use interim Report to emphasise benefits and highlight achievements (October 2010)

Page 4: Information for Meeting in Sweden

WP3 and WP4

• 31 October deadline for all products for “preparation and transfer of materials”

• Decision to transfer production of methodologies for teachers from WP4 to WP3 to be explained (Done)

• Explain which materials are to be translated (October 2010)

• Clarify timeline for testing materials (October 2010)

Page 5: Information for Meeting in Sweden

Budget changes

• Now approved

Page 6: Information for Meeting in Sweden

Partner Monitoring

• To introduce quarterly monitoring reports linked to finance and timesheets (Agree format October 2010, submit 15 January 2011 for October to December)

Page 7: Information for Meeting in Sweden

Quality Assurance

• Recommends producing quarterly quality assurance reports (Due January 2011)

• Self assessment for partnership– Highlights– Lowlights– Opportunities for improvement

Page 8: Information for Meeting in Sweden

Communication

• Recommends an additional partnership meeting to support piloting (Decision October 2010)

• Or bilateral meetings• Must be within existing costs• Must prioritise regular and high volume

communication in second half of project

Page 9: Information for Meeting in Sweden

Impact

• What indicators will we use to measure success? (October 2010)

• What statistics will we gather? (October 2010)• Define realistic indicators per country by

Interim Report (consult application form) (October 2010)

Page 10: Information for Meeting in Sweden

Sustainability

• All partners to start putting into place formal arrangements for using products after the project has finished

Page 11: Information for Meeting in Sweden

Finance

• Carol must have copies of timesheets with signatures (Immediate)

• Simple translation required on invoices (Immediate)

Page 12: Information for Meeting in Sweden

Dissemination

• All partners to report in more detail on dissemination activities (October 2010)

• Common template to be produced to record on a regular basis (October 2010)

• Dissemination to be a key feature of second year of project

Page 13: Information for Meeting in Sweden

Example of template from Sweden

Page 14: Information for Meeting in Sweden

Website

• All online resources to be linked to website by December 2010

• Clear signposting to Angus College website• Website structure to consider needs of target

groups• Clear mapping and signposting• Step by step guide to be considered

(December 2010)

Page 15: Information for Meeting in Sweden

INTERIM REPORT

Page 16: Information for Meeting in Sweden

What is required from partners?

• Interim report pages sent by email• Draft responses in groups (by WPs and

national groups?)

Page 17: Information for Meeting in Sweden
Page 18: Information for Meeting in Sweden
Page 19: Information for Meeting in Sweden
Page 20: Information for Meeting in Sweden

QUALITY ASSURANCE

Page 21: Information for Meeting in Sweden

Evaluation and reporting

• What is your opinion of our method for evaluating meetings?

• What else should we report on?• How should we report?

Page 22: Information for Meeting in Sweden

QUESTIONS ON PROJECT MANAGEMENT

Page 23: Information for Meeting in Sweden

Plans for next meeting

• ?