-
..I' pf C! .' Iv RNIA CALIFORNIA ENVIRONMENTAL PROTECTION AGENCY
PETE WILSON. Governor
PARTMENT OF TOXIC SUBSTANCES CONTROL1011 N . GRANDVIEW AVENU
E
GL LE . CA 9120 1
(f"1800 January 22, 199 6
CERTIFIED MAIL
Mr . Randy UeshiroSSFL Project LeaderRocketdyne DivisionRockwell
International Corporation
6633 Canoga Avenue
Canoga Park, CA 91309-7922
Dear Mr . Ueshiro :
Return Receipt RequestedP 533 720 18 2
NOTICE OF DEFICIENCIES, ROCKWELL, SANTA 8USANA FIELD
LABORATORY
RCRA FACILITY INVESTIGATION WORKPLAN ADDENDUM
The California Environmental Protection Agency, Department
of Toxic Substances Control (DTSC) has reviewed the RCRA
Facility
Investigation Workplan Addendum (Workplan) dated March 1995
.
Enclosed are DTSC's comments on the Workplan . Conditions
which
were added since the draft that you received on December 6
for
our conference call have been highlighted in bold type .
Also,
address the comments in the enclosed memorandums on the
Workplanls Health and SafetyPlan and Risk Assessment .
As discussed during our December 6 conference call, Rockwell
may submit revised sections of the plan as they are completed
.
Please revise the schedule presented in the December 15 letter
to
DTSC and indicate when each of the sections will be completed
by
January 31, 1995 .
If you. have any questions, please contact Carla Slepak of
this office at (818 ) 551-2959 .
Sincerely ,
Philip B . Chandle r
Supervising Hazardous Substances
Engineering Geologist
Facility Permitting Branch
S
Enclosures6
cc: See next page
15 KL
rYM
HDMSe00165886
-
1.r . Randy UeshiroJanuary 22, 1996Page 2
cc: Mr . Phil Rutherford
Manager, Environmental RemediationRocketdyne DivisionRockwell
International corporation6633 Canoga AvenueCanoga Park, CA
91309-7922
Mr . Tom Kelly (H-3-2)
U .S . EPA, Region IX
75 Hawthorne Street
San Francisco, CA 94105
Mr . Jim Ross (w/o attachment )L .A . Regional Water Quality
Control Board101 Centre Plaza DriveMonterey Park, CA 91754-215
6
Mr . Ed Bailey (w/o attachment)California Department of Health
ServicesRadiologic Health BranchP .O . Box 942732
Sacramento, CA 94234-7320
-
ROCKWELL, SANTA SUSANA FIELD LABORATORYRCRA FACILITY
INVESTIGATION WORKPLAN ADDENDUM , MARCH, 1995
NOTICE OF DEFICIENCIE S
GENERAL 'COMMENTS :
The list of analytes for each Solid Waste Management Unit
(SWMU) or Area of Concern (AOC) must be determined based onthe
specific chemical usage and waste handling practices at
that unit . Compounds may not be eliminated from
consideration simply because they have not previously been
encountered at highly elevated concentrations. The field
action levels may not be used to eliminate chemicals from
consideration .
All SWMUs eliminated from the RFI Investigation Phasebecause
they were evaluated under an accelerated programmust be presented
and evaluated in the RFI Report . Thelevels of contaminants must be
compared to background valuesand evaluated using the approved risk
assessment protocols .
Any chemical constituents which were handled at a RCRA unitor
may have migrated to the RCRA unit but not included in
the closure plan must be evaluated in the Workplan . A
sampling plan to determine if the chemical constituent is
present in the soil will be required if the constituent is
not addressed under a different overlapping SWMU .
All soil vapor probes for the active survey need to beinstalled
to an appropriate depth to avoid atmosphericdilution . Generally,
probes need to be installed to atleast five feet below ground
surface (bgs) . However, ifthis proves impossible due to shallow
bedrock, the probesmust be sealed with bentonite and protocols
using low purgevolumes and flow rates followed to minimize possibl
e
latmospheric break-through .
The scope of passive soil vapor sampling should be re-
evaluated . Since contamination has already been identified
in most of the areas under consideration, and the primary
value of the passiveor flux measurement technique is as a
qualitative screening tool, the data produced would not
provide substantial new information . The flux measurement
should only be employed in those specific instances where
site conditions would limit the use of active sampling or
where it would provide data which could not be produced
using active techniques . Instances where passive sampling
would be appropriate would be for the spatial identification
of fractures where dense non-aqueous phase liquids (DNAPLS)
might be lodged under a thin soil cover which could
subsequently be targeted with deep vapor probes set in the
fractures, or low permeability zones where collection of
active samples might be problematic . It is suggested that
HDMSe00165888
-
additional active vapor points be added to fully evaluatethe
distribution of VOC contamination where passive pointsare deleted.
Cr. : !
6 . Each SWMU and AOC should be evaluated in a walk-through
byDTSC staff along with representatives of Rockwell and Ogdento,
decide on final placement of vapor probes and soil matrix
samples .
7 . The Workplan contains no discussion of ground
waterassessment. Ground water must be addressed under the RFI,even
if as a separate phase of RFI activities . Many of theassessment
and production wells located on- and off-site areincluded in the
Post-closure Permits, however , a significant
number are not and should be included in the RFI process.
Furthermore, if currently unknown vadose zone sources
areidentified in areas where coverage is inadequate or
non-existent, additional wells will be required . These wells
would need to be installed as part of the RFI . vr
8 . All above-ground tanks (AGTs) which were used for
solvent
storage need to be evaluated during the RFI process, in
order to determine if these tanks have acted in the past as
sources of contamination or are on-going sources . This
evaluation should consist primarily of soil vapor sampling
which needs to extend from each tank along any piping runs
to the test stands where the solvents were used . A complete
listing of all such tanks and appurtenant piping needs to be
presented in the Workplan together with detail maps at an
appropriate scale . In addition , surface drainage leading
from the tanks may need to be included in the investigation
.
9 . In addition to providing the contaminant histories for
all
wells related to the SWMUs (constituents handled at the
SWMUs or breakdown products ), please provide the following
:
hydrographs or the ground water highs and lows which would
indicate the variable thickness of the vadose zone,comparisons
of upgradient and downgradient ground water
wells for each of the contaminants which may be related to
the SWMU , and a discussion of whether the SWMU appears to
be
the source of the ground water contamination .
10 . The tables included in each individual section contain
onlyre-statementsof material from the text of the Workplan .
Additional information , such as specific materials used and
summaries of releases need to be provided
. 11. Facility boundaries must be displayed on all maps depictin
g
SWMUs or AOCs, where the units are located in close
proximity to the property line . ,,,,,~ ."0,/ ; -- ,i ( S'__
12 . The use of seismic reflection techniques should b e
considered for use in mapping the fracture system in bedrock
beneath the site , since these fractures have not beenadequately
mapped and they provide a significant control on
Pc ,
HDMSe00165889
-
contaminant migration . The data gathered could then be used
I
1
15 .
1
to focus the investigation which could potentially reduc
eoverall costs . At a minimum, Rockwell should conduct a testof
this methodology as part of the R PI . ri i -- Tc
It cannot,be assumed that if an agency is overseeing a
potentially present at the SWMU have been fullyparticularSWMU
that all the chemical constituent s
investigated- Rockwell must present the list of chemical s
investigated , and the results of the investigation. -c -handled
at a particular area, the chemical constituents
DTSC has determined that the risk assessments performed forthe
surface impoundments and drainages subject to PostClosure permits
are not adequate . Until DTSC has approvedHRA protocol, Rockwell
cannot conclude that these SWMUs donot pose a risk to human health
. -~'
According to the CCR, the fuel layer on the runof fcontainment
ponds and impoundments used to collect runofffrom rocket test
operations throughout the facility wa sroutinely burned off .
Because these burning conditions
these compounds must be evaluated in the ponds where thiscould
produce PNAs and dioxin or dibenzofuran compounds ,
practice may have been used and at any areas where
sedimentsLLulu 1.11CJC jJuliu may lldve been empiacea . ~;
S maps presenting sampling results in the RFI Repor tshould be
on topographic maps of sufficient scale t o
sample locations .
EXECUTIVE SUMMARY
The field action levels (FALs) proposed to drive the
investigation must be protective of ground water . Some ofthese
levels were selected based on threat to ground water,
but when modeling indicated that those levels were not
protective (as in the case of TCE), Ogden and Rockwell
determined that it was acceptable . for ground water to
beimpacted for a period of five years . The rationale for
thisdecision was that since Rockwell is currently pumping and
treating ground water, any contaminants which would bedischarged
would not migrate off-site . First, this fails toacknowledge the
fact that VOC contamination has already
migrated off-site and continues to do so . Secondly,Rockwell
still does not have a sufficient understanding of
the migration of contaminants in ground water beneath the
site due to the complex fractured bedrock aquifer . If
theinvestigation is to be constrained by pre-selected values(i .e
., FALs), then these numbers must be sufficiently
protective to assure that direct exposure is not a concern
and that ground water will not be adversely impacted .
HDMSe00165890
-
In determining FALs, and in conjunction with
health-basedremediation goals, the Workplan must consider
thepossibility of metals contamination migrating to groundwater.
This is especially so given the shallow nature ofground water at
some areas of the site . Although Rockwellasserts that the levels
of metals previously detected in theground water are below Maximum
Contaminant Levels (MCLs),metals contamination may be present in
the soil which hasnot yet migrated to ground water . Additionally,
any metalswhich appear in the ground water at
statisticallysignificant levels above background, even though the
levelsare below MCLs at the present time, could indicate
soilcontamination which is migrating to ground water .
The "cut-off" level of 100 µg/l for soil vapor results is
not acceptable, particularly since this number was not keyed
to the specific compounds detected . For example, vinyl
chloride at 100 µg/1 poses a much more significant
threat!-,wthan other contaminants at the same concentration
.Furthermore, if any fine-grained sediments are encountered,
the 100 Ag/l value in soil vapor would be far lessconservative
and the samples would need to be evaluated on
total VOCs, not just vapor concentrations . An acceptablecut-off
value for vapor cpnce trations wouldbe 1 1
Surface sediment samples need tobe collected at local baselevels
where fine-grained materials would tend to bedeposited. It is not
sufficient to go only 100 feetdownstream, nor to stop at the
fence-line of the facility .The extent of contamination needs to be
evaluated both on-and off-site, based on appropriately
conservativeFALs .
SPECIFIC COMMENTS
SECTION 1 : INTRODUCTION
1 .1 Facility Background : Land use of the
Brandeis-Bardinproperty should be discussed in this document
.Additionally, Brandeis personnel have indicated that cattledrink
water produced from water wells located on thatproperty .
Table 1-1 : Summary ofInvestigation for SWMUs and AOCs
The following comments are provided for SWMUs listed in Table
1-1which were not included in the proposed RFI sampling.
SWMUsincluded in the proposed Workplan are addressed in
latercomments .
4 .1 It is unclear if the underground tank investigation
includedTCE testing . Since TCE was used at the test
area,evaluation of TCE contamination must be included in the
RFIwork to be performed. z , . j
t i
HDMSe00165891
-
4 .2 Indicate any environmental ( soil, ground water , soil
vapor)U-"LP sampling required by Ventura County Environmental
Health .
Samples presented* in the CCR were located at the perimeterof
the landfill only . Soil vapor and soil samples in thelandfill
itself may be warranted .
4 .6 The soil samples collected for VOC analysis were obtained a
t0 .5 to 1 foot depth which is within range of atmosphericeffects
and not deep enough to establish whether VOCcontamination was
present in the soil . This is especiallytrue if the soil has been
disturbed during excavationactivities . Additional deeper soil
samples or soil vaporsurvey should be ,conducted in this area .
,
4 .12- .13 Some concentrations being reported previously below
th ecr-i action levels alone are not an adequate reason to
forgo
defining the extent and maximum concentration . If
Rockwellmaintains that no additional samples are needed to
definethe extent of contamination , Rockwell must demonstrate
thatthe extent of contamination has beenadequately defined inthe
Workplan. The results of the confirmatory samples forthe
accelerated cleanup must then be included in the RFIreport and
included in the background and health basedcomparisons.
4 .14 Soil vapor sampling should be expanded to include the tes
tstand and spillways if not already done in a separateinvestigation
.
r
4 .16- .17 Provide the results of any and all sediment or
soilsamples collected from the R-1 and Perimeter ponds in
theWorkplan . Justification for not recommending furthersampling in
these ponds is necessary since the singl esediment sample
previously collected in each pond may
enough to adequately characterize the VOC and metal
n t b
concentrations in the entire pond .
AOC : Area I Leach Fields : Building 359 Leachfield/drainage
Present any investigation of the drainage and sump at
building 359 . The sump and drainage from the building may
need further investigation . Solid rocket propellent was
stored in this building .
AOC : APTF Tanks
According to the CCR RP-1, NTO, hydrazine was contained in
tanks in these areas . The soil surrounding the tanks shoul
d
be analyzed for all the constituents stored in the tanks .i
5 .1 See comment 4 .2 above . This SWHU should be fully
characterized . ^J ,
5 .6 Soil samples should be taken downslope from the former
ash
pile where rainfall run-off would tend to collect and
HDMSe00165892
-
sediment be deposited . Since two samples may not beadequate to
f•!lly .characterize, this SWMU, samples should beproposed . l
r
5 .7 The waste coolant tank was not included in the closure
plan(CP) submitted to DISC . nr ,,l
5 .14 Indicate if the Bravo Waste Tank is included in the
Post-CPfor the Bravo Drainage Area . Characterization of the
areabeneath the tanks may be warranted
5 .18 Metals were not analyzed at this SWMU . Describe
therationale for leaving this analysis out of the samplingplan .
Characterization of metals maybe warranted at thisSWMU . A t. ~ r .
_ ,,C_ ,= : ,' r
5 .19 The sample resultsfrom previous sampling events must
beincluded and evaluated in the final RFI report (see
GeneralComment #2 above) .
5 .23 All chemical constituents used or generated at this
areamust be included in the investigation . It appears that BNAsand
fluoride were used but no analyses have been performedfor these
constituents .
5 .26 Because these pondsand drainages collected runoff
fromrocket testing/cleaning operations, analysis for dioxins(due to
burning fuel on top of ponds ) and SVOCs i snecessary .
AOC : Building 515 :
Present any soil or soil vapor samples conducted inconjunction
with the NPDES permit . This area should becharacterized for all
the chemicals handled at the building .
6 .3 Soil vapor sampling has not been conducted at this unit
andmay be warranted based on the past chemical usage .
6 .8 The number and location of samples obtained appear to
be
inadequate to represent the large area contained in the
Silvernail Reservoir . Further sampling, therefore, may
bewarranted . Additionally, NPDES permit requirements do notaddress
threat to ground water beneath the unit and do not
address the threat to humans contacting the sediment fromthe
reservoir . The correspondence with the Los AngelesRegional Water
Quality Control Board (LARWQCB) did not
indicate that threat to ground water from individual
chemicals such as arsenic was considered .
6 .9 The results of the accelerated cleanup must be included
inthe RFI report . The cleanup is subject to the approvedhealth
risk assessment .
HDMSe00165893
-
7 .2 The VOC contamination beneath Building 133 must be
assessedas part of the RFI process or the CP must be amended
toinclude assessment of this plume . The current CP does notaddress
VOC investigation .
7 .3 The RCRA Facility Assessment (RFA) Report indicates
thatlarge components were buried west of the disposal pondbetween
two large bedrock outcrops . Results of any soil
sampling in this area should be included in the Workplan . Asoil
sampling plan must be proposed as part of the Workplan .Also , see
General Comment #2 above.
It appears that all not all the chemicals (PAHs),radiological
parameters and chemical byproducts (dioxinshave been fully assessed
in this area . These must beaddressed as part of the Workplan .
Metals, VOCs, TPH were discovered during the
limitedinvestigation . The DOE jurisdiction does not
addresschemical contamination , therefore the extent o
fcontamination from these constituents must befullyaddressed in the
Workplan . Additional soil sampling toassess the extent of
contamination should be included in theWorkplan if necessary to
determine the extent ofcontamination .
7 .8 All chemicals, not just petroleum hydrocarbons, handled
atthis area must be assessed during the RFI process .Additionally,
if drums containing unknown constituents werepresent, as hasbeen
suggested in the CCR, a full suite ofchemicals must be investigated
.
7 .9 Based on the usage of organic solvents in this area, and
thelimited soil sampling conducted (3 samples), a soil vaporsurvey
is warranted .
7 .10 Include the results of this investigation in the RFI
reportso any results above background can be evaluated in .
thehealth risk assessment .
SECTION 2 : DETERMINATION OF FIELD ACTION LEVELS (FALs)
2 .3 .1 Exposure Pathway Analysis and Potential Receptor s
1 . The evaluation of exposure pathways needs to consider
theairborne pathway relative to the transmission of dust,gasses,
vapors , etc ., whichmay have emanated from thefacility and moved
off-site .
2 . It is stated that the pathway for the off-site ingestion
ofimpacted ground water is uncertain due to the
"hydrauliccontainment afforded by the ground-water treatment system
ineffect at the SSFL ." This statement suggests that some ofthe
ground water data previously collected was not fully
HDMSe00165894
-
evaluated during preparation of the Workplan, since
off-siteprivate wells have been found to be impacted by
site-derivedcontaminants . This pathway must be considered complete
forthe purposes of risk assessment, although it must be
notedthatthe full extent of off-site contamination has yet to
bedetermined .
Exposure calculations must consider a residential scenario .It
cannot be assumed that the site will continue to berestricted to
industrial use .
The health risk assessment must also consider
ecologicalreceptors . Lack of existing data on the species located
onsite and the range of these species warrants furtherresearch and
cannot be a reason to exclude these receptorsfrom consideration
.
2 .4 .2 Ground Water Protection
It is not appropriate to dismiss continued impact to groundwater
based on the fact that the pump and treat system is inplace at the
site . The RFI makes the assumption that allcontaminants will be
captured before they migrate off-site .This contention is
unsupported since there has been nodemonstration of containment and
site-derived contaminationhas already been detected in off-site
wells . FALs whichallow continued discharge of contaminants to
ground waterare not acceptable . Furthermore, costs associated with
pumpand treat operations are~~ fAA~,r~ greater than those for
VOCvadose zone remediation the RFI should be focused on
theidentification and remediation of vadose zone
contaminationbefore it reaches ground water .
The FALs proposed for compounds which are listed but
evidently never fully evaluated are unacceptable .Specifically,
compounds such as cis-1,2-dichloroethylene
(c-1,2-DCE) and trans-l,2-dichloroethylene (t-1,2-DCE) have
maximum contaminant levels below 10µg/l but FALs of
4,000mg/kgand 8,1000 mg/kg respectively . These FALs totallyfail to
protect ground water, and it is inappropriate for
them to be less protective than those for other compoundswith
similar health risks such as trichloroethylene (TCE)and
perchloroethylene (PCE) . All FALs need tobe revaluatedfor a number
of reasons, which include the fact that site-
derived contaminants have already migrated off-site, some
exposure pathways were not considered, and many of the
break-down products are more toxic than the parent compounds(i
.e . vinyl chloride ) . The LARWQCB attenuation factormethodology
may also . be used in conjunction with healthapproved health risk
assessment protocols to insure thatFALs are protective of ground
water .
HDMSe00165895
-
SECTION 3 RFI FIELD IMPLEMENTATION
3 .1 .1 Passive Soil Gas Sampling
As stated previously, the use of passive soil vapor
samplingtechniques would not appear to be necessary for much of
thesite . Rockwell has previously expressed concerns regardingVOC
migration from ground water resulting in erroneou sinterpretations
that vadose zone contamination was present .Given the greater
sensitivity of cumulative flux measurementtechniques, this would be
much more of a possibility whenusing passive samplers .
Passive soil vapor sampling should be used only in thosespecific
instances where site conditions would limit theeffectiveness of
active techniques . The following twoinstances are provided as
examples, although there may beother cases where the flux
measurement technique wouldprovide useful data .
In instances where semi-VOCs would be reasonablyexpected to be
present based on chemical and wastehandling practices it may be
reasonable to use the GoreSorber or an equivalent system if it
could identifythose specific semi-VOCs in question .
For those areaswhere very little sediment is present(i .e .,
less than 3 feet), passive samplers could beused to avoid the
problems related to atmosphericbreakthrough associated with the
active technique .Spatial distributions derivedfrom the passive
datacould then be used to target specific fractures wherefree or
DNAPL phase solvents might be present. Deeperactive sampling could
then be conducted within thosetargeted fractures .
In other cases where no specific rationale can be
provided to support the use of flux measurement
sampling, active techniques should be employed . Therole of flux
measurement sampling may be increased ifRockwell demonstrates the
field efficacy of thesetechniques at the SSFL .
3 .1 .2 Active Soil Gas Sampling
Additional active soil vapor points will be required if
thepassive survey is deleted as suggested . These will beneeded to
fill data gaps and to fully delineate the extentof VOC
contamination. These data will be more useful thanthe passive data,
since it will be quantitative . Therefore,the need for additional
sampling can be made in the fieldbased on review of the data in
conjunction with DTSC staff .This will eliminate, at least to some
degree the need togrid large areas, and may ultimately prove to be
less costlythan the combined passive/active proposal .
-
The selection of 100 µg/a as a "cut-off" for total VOCs isnot
acceptable . For example, where more toxic contaminantssuch as
benzene or vinyl chloride might be encountered as asignificant
portion of the contaminants present, or wherethe results do not
allow source areas to be adequatelyseparated . Decisions regarding
the need for additionalpoints should be made in conjunction
withDTSC staff, but asnoted previously, a more appropriate cut-off
would be 1gg/1 . FALs should be compared to numbers derived from
theLARWQCB Attenuation Factor Methodology in order to assurethat
they are adequately conservative .
3 .1 .3 Soil Sampling and Field Test Kit s
The diameter of the direct-push sample to be used for soilmatrix
sampling is not specified inthe Workplan . Due toVOC losses which
can occur due to friction, heating, andsubsequent volatilization,
the diameter of the samplershould be maximized (minimum 2 inch
diameter) . Furthermore,the analytical laboratory shouldbe
instructed to collectaliquots from the center of the sampling
sleeve .
The proposed FALs are not acceptable, because, in additionto the
comments on section 2 .4 .2 above , they are notcalculated using
DTSC accepted health risk assessmentprotocols. (See the attached
memo from TR Hathaway .) Afterrecalculating the FALs in accordance
with approvedprotocols,the soil screening level of 100 mg/kg TPH
mustalso be re -evaluated.
The full extent of contamination must be defined under theRFI
process . Just because a water body is under an NPDESmonitoring
program, does not mean that dischargesinto orout of it can be
ignored . Results of previous sedimentsampling must be provided or
additional sampling proposedfor the water bodies in question, and
other samples may needto be collected down-stream of these bodies
.
In cases where contamination extends off-site, the extentmust be
fully evaluated . Samples in drainages must becollected based on
observations of stream flow andsedimentation . Samples may not
simply be collected at pre-selected distances down-stream of a
unit, nor at thefacility boundary . Sediment samples are also
needed atlocal base-levels where fine-grained sediments would
belikely to drop out of suspension and be deposited . Theseareas
are likely to be off-site in many cases .
The extent of contamination should be defined based
onappropriately conservative FALs or non-detects for nonnaturally
occurring compounds , especially where thosecontaminants may have
migrated off-site and a more rigorou sevaluation is being requested
by the affected party .
10 -
HDMSe00165897
-
3 .1 .4 Background Soil Sampling
1 . Background samples for metals need to be collected away
fromand up-slope of any SWMUs or AOCs . Furthermore, thesesamples
need to be collected at depths greater than theproposed 0 to 6
inches in order to avoid any effects due toairborne transport of
contaminants . The proposal to collectbetween ten and twenty
background samples may be acceptable,but the number of samples must
be sufficient for th estatistical evaluations proposed in the
Workplan .
2 . The need for metals analyses needs to be based on the
usageof chemicals and storage of wastes at the SWMU or AOC
inquestion . Analyses for certain metals cannot be deletedbased on
artificially high FALs not having been exceededduring any previous
sampling . The RFI needs to define theextent of all contaminants
through the selection of FALswhich are appropriately conservative .
For example, FALswhich exceed STLC or TTLC values are not
acceptable .
3 . Explain the rationale for collecting background samples
at0-6 inches depth . Background samples collected at a minimumdepth
of 12 inches may be more appropriate to decrease thelikelihood of
airborne soil contamination . If samplescannot be collected at that
minimum depth in an area becauseof the shallow depth to bedrock,
the sample should berelocated .
3 .2 .3 Offsite Laboratory Analysis
1 . If the decision is made to perform passive soil
vaporsampling as a precursor to the active vapor sampling, andNERI
is chosen as the sub-contractor to perform this work,all analyses
must be conducted using the full ga schromatograph/mass
spectrometer (GC/MS) methods . Thestandard Petrex analyses (i .e .,
MS only) will not beconsidered sufficient .
Table 3 -1 Decision Level II : SSFL RFI Field Plan
1 . The statement that ground water sampling is being
conducted
under a separate, concurrent environmental program is
notentirely accurate since all monitoring points are not
included under the two Post-closure Permits issued for thesite .
Furthermore, Area IV is not addressed at all underthese Permits .
Ground water issues need to be fully coveredunder the Workplan,
particularly for those wells or areas
not addressed by the Post-closure Permits .
2 . The proposal to collect active soil vapor samples fromdepths
as shallow as two feet is not acceptable . Typically,the minimum
acceptable depth for this type of sampling isfive feet . However,
it is understood that there may beshallow bedrock locations at the
site where 5-foot samplingis impossible . In these instances,
special precautions must
MOMMHDMSeOO165898
-
be taken to assure a low purge volume and that the sampleprobe
is adequately sealed from the surface to the top ofthe sand pack in
order to reduce the possibility o fatmospheric air being drawn into
the probes . The use ofnon-toxic tracer gasses introduced at the
surface around theprobes is suggested as a meansof demonstrating
that leakageis. not occurring .
Table 3-2 Analytical Categories For Potential
ChemicalsWastes
PCDDsshould also be analyzed in areas where solvents wereburned
such as run-off control basins downslope of rockettest stands .
SECTION 4 --PILOT TESTING METHODS AND IMPLEMENTATION
DTSC did not review the Remedial Technologies (Section 4) ofthis
Workplan . The remedial technologies proposed for pilottesting will
be evaluated during the Corrective MeasuresStudy phase of the
Corrective Action Process .
SECTION 5 - PROPOSED FIELD SAMPLING AND ANALYSIS - AREA I
5 .1 - Instrument Lab Hazardous Waste Tank, Building 324,
and
Equipment Lab 1,1,1-Trichloroethane (TCA) Distillation Unit
andUsed Product Tank, Building 30 1
The Workplan indicates that fuel tank assessments for thesite
are being handled by Ventura County, however, no
discussion is provided regarding oversight for the 3,000gallon
TCA/TCE underground tank which was removed in 1987 .Given the date
of removal, it is highly unlikely that any
vapor assessment work was performed in connection with
thisremoval . All data relating to this tank removal should be
provided in the Workplan, and proposals for vapor
assessment/"work included as well .
With respect to the other on-site underground tanks being
overseen by Ventura County, all assessment data relating to
these tanks needs to be included in the Workplan .Particularly,
include the types of chemicals investigated in
conjunctionwith the UTGs . The types of chemicals
investigated must match the types of chemicals stored in the
underground tanks during the entire life of the undergroundtank
.
The area of the 200-gallon l,l,1-TCA spill needs to be
fullyevaluated .
The soil vapor sampling grid in the vicinity of SV-4 .3-3
andSV-4 .3-5, where high VOC concentrations were previously
reported, needs to be more tightly spaced to adequately
define spatial patterns and to determine thesource for the
contaminants detected here .
- 12
HDMSe00165899
-
More than the five proposed semi-permanent probes may berequired
to provide adequate coverage during a vaporextraction remedial
program . It is suggested that whereverpossible, probes be
installed in a semi-permanent manner toavoid the need for later
duplication of this work .
Because, according to the CCR, a rocket test area may havebeen
located near Building 436 and Building 324 was used asa machine
shop,_a metals analysis should be conducted inthis area .
5 .2 - LOX Plant Former Sump and Clarifie r
The proposal for collection of soil vapor samples from adepth of
1-foot bgs is not acceptable due to probableatmospheric
breakthrough and dilution. It appears that thesump and clarifier
previously located in thisarea wereinitially installed to a depth
of 10 to 12 feet bgs andtherefore, a sufficient thickness of soil
should be presen tto allow vapor samples to be collected from below
the bas eo e un1 s . / ,r
•
As stated previously , the down- stream locations for
sedimentsample collection must be selected based on where
fineswould be likely to drop out of suspension .
Pre-selecteddown-stream locations are only appropriate in cases
wherethey coincide with these areas of deposition .
5 .3 - component Test Laboratory
Data from the underground tank removal in this area needs tobe
presented and evaluated . {~ r
The Workplan should describe where all activities such as
engine testing and waste run-off occurred in this area .
Theexact dimensions and orientation for the spillway need to be
presented along with its point of origin . The use for
eachbuilding during each time period needs to be discussed .
The storage and use of TCE mustbe more fully described
.Specifically, any tanks used for storage along with pipingruns
need to be evaluated with soil vapor sampling .
All former test stands need to be identified on the maps ofthe
area . „ , t ,
The previous sampling which did not reveal significantdetects
for fluoride, chloride, or nitrate in the vicinityof the test
stands and pond reveal nothing aboutcontamination which may be
present as a result of thesubsequent laser testing in this area .
Both soil vapor andsoil matrix samples need to be collected to
evaluate ifdischarges of NaOH, hydrogen peroxide, n-heptane, or
Freonresulted from the use of these compounds during the
lasertesting operations .
13
HDMSeOO165900
-
6 . Soil vapor sample points must be located along the
formerspillway .
7 . Dioxin and PNA sample(s) should be collected in the pond
.See discussion in General Comment #13 above .
8 . In all cases where physically possible, vapor probes
shouldbe installed semi-permanently to allow remediation progressto
be monitored .
5 .4 - Bowl Area & 906 Leachfiel d
Building 906 was not identified on the figure for thissection .
Furthermore, the document does not indicate ifleachate was only
received from this building, or ifdischarges from other buildings
were directed to thisleachfield .
Although it is indicated that acetone is a common
laboratorycontaminant, it is not clearly stated if it was
specificallyidentified by the analytical laboratory as such in thi
scase .
There does not appear to have been sampling conducted in
this area for semi-VOCs or PNAs, which could have been
associated with the coal gasificationand pond burningactivities
. If this sampling has been conducted, the
results must be presented for review, if not, the possible
presence of these compounds must be evaluated throughadditional
sampling under the RFI process .
The Workplan must propose sampling for cobalt, lead, zinc,and
mercury in the skim pond and leach field . These metalscannot be
dismissed simply because previous sampling has notrevealed
concentrations above the FALs . The full extent ofall contaminants
needs to be evaluated in the RFI . ~,-
There are currently no wells at the site to monitor, for
ground water releases from the retention and skim ponds .noted
previously, specific ground water elements to deal
with issues such as this need to be included in thi sWorkplan or
as a subsequent phase of RFI work . .
6 . The Workplan does not propose sampling in or around
eitherthe test stands or the retention pond . The document
musteither justify the lack of sampling in these areas o rpropose
adequate characterization activities .
The number of soil vapor locations previously sampled, donot
provide sufficient coverage to limit this phase oftheinvestigation
as severely as proposed . Additional samplingunder the RFI needs to
be proposed , such that the fullnature and extent of contamination
can be reasonablyevaluated .
14
HDMSe00165901
-
5 .5- Happy Valley
1 . The extent of Freon contamination in the Tunnel Facility
hasnot beendefined . The 800 µg/l detected in one sample is
anindication that significant contamination may exist in thisarea ;
the two proposed additional samples will probably notbe .
sufficient to define the extent .
The Workplan does not clearly state if the Thermal Treatment
Facility and Tunnel Facility only treated wastes fromBuilding
372 or if wastes from other buildings were alsotreated . This issue
needs to be clarified, and additional
sampling/analyses proposed if other waste streams werehandled in
this area .
The nature and extent of all metals contamination must bedefined
, not just arsenic .
Sediment sampling needs to address all contaminants whichcould
have been released from the AOC or SWMU, not justthose contaminants
previously detected .
As stated in previous sections, downstream samples need to
be collected at specific locations where sediments would be
expected to be deposited, not at pre-selected distances fromthe
AOC or SWMU .
The Workplan fails to address the areas used for storage ofnew
chemicals and fuels . All tanks, dispensers, pipingruns, etc . must
be included in the RFI process andappropriate sampling proposed
.
SECTION 6 PROPOSED SAMPLING AND ANALYSIS AREA I I
6 .1 - FinalELV Assembly, Building 20 6
It is stated that the contents, size, or use of theunderground
tank formerly located in this area are unknown,however, no sampling
is proposed . Given the uncertainnature of this unit, work
including afull suite of analysesmust be performed here .
Itis noted that significant VOC concentration were detectedin
both soil vapor and soil matrix samples collected in theimmediate
vicinity of the PCB storage building (currentlyundergoing closure)
. However, no additional sampling forVOCs is proposed either under
this RFI or under the RCRAClosure . The presence of VOCs in this
area must beaddressed under one of these programs .
The full nature and extent of all contaminants must bedefined
and sources delineated ; FALs may not be used to
exclude areas from further consideration or to eliminateanalytes
. 11
15
HDMSe00165902
-
Downstream sediment samples must be analyzed for allconstituents
of concern, including PCBs, and the sample scollected at
appropriate locations as described previously .
6 .2 - Alfa Area
1 . The Workplan fails to address the areas used for storage
ofnew chemicals and fuels . All tanks, dispensers , pipingruns, etc
., must be included in the RFI process andappropriate sampling
proposed .
2 . It is not indicated if any semi-VOC analyses were
previouslyperformed on samples from the pond . This is of
importancedue to the prior burning practices in this area . II
I
3 . Figure 6-5 and the text do not agree . The figure
indicatesthat the maximum TCE concentration in this area was
12,000
pg/kg detected in a soil sample collected at a depth of one
foot, while the text states that the highest soil matrixresult
for TCE was 670 pg/kg . This discrepancy needs to beresolved .
The statement that ground water contaminant
concentrationsdecrease with depth is not supportable, since the
groundwater flow regime beneath the site is not yet fullyunderstood
due to the fractured bedrock aquifer andtherefore, source areas and
migration pathways have not yetbeen defined . The pertinent points
here are thatcontaminants have migrated to and impacted ground
water, andthat the contaminated ground water has then migrated
offsite .
Sediments from Silvernail Reservoir need to be analyzed forall
constituents of concern from the Alfa Area .
The number of semi-permanent vapor probes needed to
monitorremediation will almost certainly need to be greater thatthe
4 - 6 proposed . Whenever possible, all vapor p-robesshould be
installed as semi-permanent to avoid needlessrepetition of
work.
7 .' No additional characterization is proposed for the
highlycontaminated surface sediments . These materials need
fullycharacterized and remedial measures proposed such that
thethreat to surface and ground water is eliminated .
6 .3 - Bravo Are a
1 . The work performed or to be performed in the drainage
channels under the Post-Closure Permits must be fullydescribed .
If this work is not comprehensive ( ie . chemicalconstituents which
may have been deposited or migrated tothis SWMU but are not
addressed under the Post-Closure
Permits) or the risk assessment requires additionalinformation,
additional sampling will be required .
16 -
HDMSe00165903
-
Sampling in drainages cannot be excluded because ofSilvernail
Reservoir . Samples from both the drainages andthe reservoir a--e-
needed .
Because the areas upgradient of the ponds may have
generatedmetals which could drain to the skim ponds, sediment in
theskim ponds must be analyzed for metal contamination .
Soilvapor characterization of the skim pond must beincluded in
the Workplan . Although previous sampling didnot reveal VOCs in the
pond , one soil vapor sample is notenough to characterize the skim
pond and soil sedimentsamples for VOCs cannot be relied upon .
Fully characterize the extent of fuel contamination in
thebedrock beneath the spill which took place on July 21 ,in the
Bravo Test Area .
1995,
6 .4 - SPA Area
Activities being undertaken for the drainages andimpoundments
under the Post-Closure Permit must be fullydescribed . Additional
work may be required in these areas .
It appears that a typographical error exists in Table 6-4where
it is stated that additional soil gas work will not bperformed if
the passive soil vapor results are less than100 Ag/l total VOCs .
The table should be corrected to readactive soil vapor results and
the limits on vapor levelsreduced to 1µg/l-
SECTION 7 - PROPOSED FIELD SAMPLING AND ANALYSIS - AREA III7 .1
- ECL Area
Run-off from this area cannot be discounted due to thepresence
of the R-2 Ponds . The full nature and extent ofcontamination must
be defined .
Because an adequate health risk assessment protocol has not
been approved, soil samples cannot be discounted becausethey are
below a predetermined limit . The full nature andextent of
contamination must be determined and the
acceptable limits which are protective of human health andthe
environment will be determined based on thatdetermination .
3 . Additional soil and soil- vapor'samples beneath the
pipelinesleading to the ECL Collection and Run-off Tanks and
buildingleachfield may be needed to fully define the extent o
fmercury and VOC contamination .
7 .2 Compound A Facility
1 . The chemicals used in fluorine gas production must be
fullydocumented, and additional sampling proposed as appropriate
.
17
HDMSe00165904
-
2 . Although there is no indication of the history of
activitiesin the storage shed located in this area, a statement
ismade that there were no releases here . If the history ofthe area
is not documented, sampling will have to beperformed . 1 1
3 . The non-detectable concentrations of TCE reported
forproduction well WS-11 do not demonstrate that releases toground
water have not occurred in this area . Due to longscreens and
associated dilution effects, productions wellsare not good
indicators of actual contaminants present inground water .
All active soil vapor samples need to be collected atminimum
depths of 5 feet bgs,or precautions taken to assurethat atmospheric
dilution is not occurring .
5 . More than two semi-permanent vapor probes will be requiredin
this area to adequately monitor remedial actions .
7 .3 - STL-IV Test Area
1 . The work performedor to be performed in the drainagechannels
under the Post-Closure Permits must be fullydescribed . If this
work is not comprehensive, additionalsampling will be required .
The samples must be evaluatedusing aHRA protocol acceptable to DTSC
in accordance withthe comments in the attached memo from T .R .
Hathaway toCarla Slepak . The location of the drainage channels is
notapparent in figure 7-7 map of the area .
2 . All active soil vapor samples need to be collected atminimum
depths of 5 feet bgs, or precautions taken to assurethat
atmospheric dilution is not occurring .
SECTION 8 - PROPOSED FIELD SAMPLING ANDANALYSIS AREA IV8 .1 -
Building 56 Landfill
The work plan states that the ground water contamination
identified in this area did not result from activities here
however, no rationale or explanation of the source areprovided .
The Workplan must provide an explanation of thesource for the
observed ground water contamination .
No information regarding analyses forTPH , metals, or TCE inwell
RS-16 is provided . Without these analytical results,there can be
no conclusions regarding lack of impact toground water from
activities in this area . .r r : .
The use of radiation badges suggests the presence of
radioactive materials in this area, but there does not
appear to be any analytical work proposed to evaluate
thepresence of such materials . This must either be explained,
or additional sampling/analyses, such as gamma ray
spectrometer work, proposed .
18
HDMSe00165905
-
All geophysical anomalies need to be investigated andtrenching
conducted at the locations of these anomalies .
A discrepancy exists between the text of this section,
whichstates that no diesel contamination was identified, andFigure
8-2 which indicates that 500 mg/kg of diesel wasencountered in soil
sample LF-6 . Either the text or thefigure need to be revised .
Indicate the drum storage location on figure 8-1 ,
SECTION 9 SUMMARY OF DATA NEEDS
Revise the numbers of samples required and the areas
wheresamples will be collected in this section as necessary
toreflect the changes required in the above comments .
SECTION 10 RFI DATA ANALYSIS
10 .1 .1 Background Concentrations
1 . Indicate the locations where background samples will
becollected . Explain the rationale for selecting the
locationincluding a description of past practices at or near
theselected site, practices, tanks or structures wherehazardous
materials were handled located upgradient from thesample location .
Areas which may have been impacted by SSFLpast practices will not
be indicative of true background .
See comments to section 3 .1 .4 above .
10 .2 SWMU and AOC Risk Assessment Approach
See attached memorandum from T .R . Hathaway to Carla Slepak
.
SECTION 12 RFI PROJECT MANAGEMENT AND SCHEDULE
Figure 12-1
The DTSC Project Director is now Philip Chandler .
Figure 12- 2
Submittal deadlines must concur with any timelines in
thePost-Closure Permits .
APPENDIX D HEALTH AND SAFETY PLAN
See attached memorandum
19
HDMSe00165906
-
01/17/96 15 :33 FAX 916 327 2509 OSA DISC ... REG3PERi&IT /
S&E Z002/00 6
STATE OF CAF IFORNI A
(916) 323-375 5
"DEPARTMENT OF TOXIC SUBSTANCES CONTROL40 Street
ox 806mento, CA 95812-080 6
Voica cFax : (916 ) 327-250 9
FROM: Y VM, MS, DABTltff oxi to st
fl4thc of c Affairs (OSA)and Ecological Risk Section (HERS)
DATE :
IVIRONMENTAL PRO F .TION A ENC Y
MEMORANDU M
Carla Slepak, Project ManagerHazardous Waste Management
BranchDepartment of Toxic Substances Control (Region 3
January 17, 1996
PFTE WILSON ,ov mrr
SUBJECT Review ofHRA Portion ofRCRA Facili .yy Investigation
Workplan AddendumSanta Susana Field Laboratory (Rockwell /
R.acketdyne)PCA Code: 25 120 Site Codes : 300381, 300122 ,
300232'Workphase : 33 MPC Co-de- 37
Background
The Rocku e11 International Corporation has pe. formed aerospace
- indust ry research,
including development , manufacture, and testing of space. and
propulsion units and par's at the Santa
Su_Sana Field Laboratory (SSFL) since 1945. The primary wastes
associated with these activities are
liquid rocket test fuels, solvents, metals, and oxidizers .
The total area of the SSFL facility, which is located
approximately 5 miles west ofChatsworth is approximately 2700 acres
. The facility has been divided into five administ arive areas
(Areas I - IV plus a 1200 acre Buffer Zone) .Two groundwater
systems, tivluch are hydraulically connected have been iderin fied
.
Approximately 200 monitoring we'ls and a groundwater r e
mediation system have been installed .
Contamination of both ground\;~water systems has been reported
.AResource Conservation and Recovery Act (RCPA) Facility Invcsti
ation (FYI) wori ;plan
was o riginally prepared by_ICF Kaiser in 1993 . The documents
currently re iewed incorporate
DTSC comments (letter from Alan Sorshcr, June 30, 1994) relative
to the original woricplan anc
provide further detail regarding the RFI sampling plans . These
documents (Addenda Vols . I & U)
are intended to supersede the o ; ig Sal work Ian (Vol. I, page
ES-1) .
HDMSe00165907
-
01/17:96 15 : 33 FAX 916 327 2509 OSA DTSC e.-
REG3PERMIT/S&E t 003'00 8
Carla Slepak - Santa Susana Field Laboratory (RFI
Workplen)January 17, 1996
Page 2
Documents Reviewe d
The documents, "RCRA Facility Investigation Workplan Addendum
Santa Suwa FieldLaboratory Ventura County, California (DTSC Review
Copies - Volumes I & II" were prepared b )Ogden Environmental
and Energy Services for Rockwell International Corporation
(RocketdyneDivision), the National Aeronautics and Space
Administration, and the U .S. Department of Energy .These documents
are dated March, 1995 .
Scope of Review
The Project Manager requested review of the HRA section (Section
10 - RFI Data Analysisand Section 2 - Determination of Field Action
Levels) of the RE workplan . The sections werereviewed for
scientific content . Nfnor grammatical or typographical errors that
do not affectinterpretation have not been noted . However, these
inaccuracies should be corrected in the finalversion of this
document . Any future changes or additions to the document should
be clearly
identified .
General Comments
Direct-exposure Field Action Levels, defined as the level of
cont aminan t which results in a
hazard quotient of unity or a target risk level of 10 '6 , may
not be used to eliminate organic chemicals
from the quantitative risk assessment (QRA). These levels are,
also, unacceptable for use in the
initial determination of the need for further actionat the site,
since they do not correspond to values
calculated using PEA or RAGS equations and approved parameters .
Other (i. e ., site-specific)
parameters may be utilized in later stages of the risk
assessment which allow for more refinement,
however, they may be not be used to calculate screening levels
.
Quality assurance procedures must be documented for samples used
to establish background
concentrations .
Speciation of chromium in maximum onsite samples prior to
comparisons with background
levels is recommended to provide assurance dal Cr(T) levels do
not contribute to potential
carcinoeenic risk .
The subject wockplan addresses (Section 2 .3 .1, Section B 6 of
Appendix B, and Figure 2 .3)
the following exposure scenarios :
1 . Onsite exposure of industrial workers to contaminated soil
via incidental ingestion,
dermal contact and inhalation of particulates or vapors.
Potential exposures of
industrial workers to groundwater contaminants must also be
considered . Continued
operationof the groundwater treatment system for an additional
five years must be
supported .
HDMSe00165908
-
01/17/96 15 :34 FAX 916 327 2509 OSA DISC REG3PERMIT'S&E
Z004r00 8
Carla Slepak - Santa Susana Field Laboratory (RFI Workplan)Janua
ry 17, 1996Page3
2_ Exposure of future onsite residents to contaminants in
groundwater is addressedby consideration of fate and transport of
organic contaminants. Cumulative exposureof residents via the air
and soil pathways is not addressed . Page 10-10 indicates
thatCALTOX will be used to predict potential groundwater
concentrations at theproperty line . Appendix B (page B-6) reports
that the direct-exposure action levelsfor each chemical will be
entered in CALTOX as a soil concentration and th e
t t T .+'tl 1 1 J . Jpredicted grounawater concentration ki ante
b-1) will oe compares to a si d,,ru,i. e., the Maximum
Contamination Level (MCL) . Direct exposure action levels ofonly
TCE are predicted to be above the MCL at any point in time (Figure
B-2) .
The OSA recommends utilization of formulae and default
parameters for aresidential exposure scenario which includes a
potential groundwater pathway for
future onsite residents . Applications of CALTOX for fate and
transport modelingmust be evaluated by OSA and any non-default
parameters utilized must be justified .Future sources of water may
be impacted and risk to surrounding communities and
tofuture residents must be assessed if toxicologically relevant
levels of contaminantsare moving offsite in groundwater .
Specific Comments
1. SECTION 2 (Vol . Wand Appendix B (Vol. II) FieldAction Level
s
ine quality ordatawhich were us eo to evaiuaz C in U- neru iai
it -1 :-) a~cu rL' u nc ic,r leek /has not been evaluated.
Detection levels must be low enough to detect toxicologica lly
significantconcentations. Data quality for samples used to
establish background levels must be adequatelydocumented . Please
provide adequate QA,/QC documentation for the background samples
andindicate the number and location of samples which will be
utilized in comparisons with onsite sar-Iples
2 . SECTION 2.3.1 Residential scenarios have been omitted . DISC
recommends that a residential
scenarios be included at all sites unless a deed restriction is
in force (see Specific Comment `4 b )
3. SECTION 10-1.1 Background Concentrations, page 10-1 and Table
2-4
All chromium (Cr) should be speciated to estimate the amount of
Cr (VI) present . Or,-sitesamples may contain Cr(VI) and Cr may not
be eliminated as a chemical of concern when total Crconcentrations
are less than total Cr concentrations in background samples . Cr
(VT) is not expectedto occur naturally The OSA recommends that the
highest or-sitesamples be speciated to ve'ify the
,.c r' .-r\ m
Paragraph 3, page 10-2, alludes to chemicals of concern which
are usua lly referred to by theacronym COC This section states that
"IC" - the acronym for indicator chemical - will be use
forchemicals of concern . The term `Indicator chemical" implies
that exposure to one chemica lrepresents exposure to other
chemicals . Please use the acronym "COC" to refer to chemicals
ofconcern and , thereby, prevent confusion .
HDMSe00165909
-
01/17/96 15 :35 FAX 916 327 2509 OSA DTSC - REG3PERMIT'S&E
Qi005'008
i
Carla Slepak - Santa Susan Field Laboratory (RFI Wo41an)January
17, 1996Page 4
4. SECTION 10.2.1 Human Health Ris k
. Page 10 -4, paragraph 3, states that ".. .PEA guidance
approach will be modifiedcorruiierisurate with available
information ." Any major modifications of PEA guidance must
beapproved by OSA prior to implementation :
a . Hazard Identification (Selection of Ch micals of Potential
Concern , Page 10-4 . Table 10- 1
The listof candidate chemicals of potential concern (COPCs) must
include : a) all chemicals
found in materials which are known to have been used or stored
at the site, b) possible degradationproducts of these chemicals, c)
other specific chemicals identified in samples of all pertinent
medi a
co:lectee at inc site, and. a') cnerrIucdls wllltil c (JUIU ou p
I C'Scilt as G 1 CSUIL Vl l 1 VJYI Vlll v it iGUVt, u vii iadjacent
sites . Sample analyses must utilize methods capable of detecting
all candidate chemicals ofpotential concern .
A fist of "indicator chemicals (ICs)" or COCs will be determined
for each media at the site
(Table 10-1, Step 2). Please indicate if a separate set of COCs
will be determined for each S`" MUor AOC or if a "global" List will
be prepared for the SSFL . Estimates of. exposure to individual
COCs may underestimate potential risks and hazards to all
chemicals of concern and, as depicted onFigare 10-1, are not
consistent with DTSC guidance (Chapter 5- Indicator Cherlicals,
Supplemental
Guidance for Human Health Multimedia Risk Assessments of
Hazardous Waste Sites and PermittedFacilities, July 1992) . Please
identify chemicals of concern using criteria found ir, the
previousreference, in Chapter 5 of Risk Assessment Guidance for
Superfund (RAGS) Vol I (USEP .A, 1991),
or in the PEA Manual (January, 1994) . Organic chemicals may
only be eliminated from the
quantitative ri sk assessment if strong evidence is presented to
adequately support the natural,
background occurrence of these chemicals (Section 5 .7 .3, page
S-19, RAGS) . In general, ail o gaaic
chemicals must be addressed in the QRA .
Conceptual Site Model . base 10-3
The OSA recommends that concurrence of a DISC geologist be
obtained prior t o
elimination of groundwater pathways, as is implied in section 10
.1 .3 .
The conceptual site model considered in this assessment
considers only an occupation
scenario . OSA guidance requires that health assessments be
based on a residential exposure scenario
(Specific Comment 2). Calculation of risks to future residents
dots not imply remediation to levels
w rich would be necessary for residential land use . The
rcmediation eoal is a risk managemen t
decision Although a deed restriction which prohibits residential
occupancy may be a remedial option,
this option cannot be fully evaluated in the absence of an
assessment of potential exposures of Future
residents . Inclusion of a construction worker scenario may be
rcasonablc, based on current or faturc
i. nd-use . 'Z,
c Selection Criteria, p~ra ph page 10-6
See comment in "Specific Comment
HDMSe00165910
-
01/17/96 15 :36 FAX 916 327 2509 OSA DTSC -++ REG3PERMIT,S&E
006%00 8
Carla Slepak - Santa Susana Field Laboratory (RFI
Workplan)January 17,199 6Page 5
d Toxici Assessment, page 10- 7
The following order of preference for current toxicity cri teria
(Appendix B , Table B-2) mustbe followed. Please revise this
section to correspond with DTSC guidelines .
I.) The most recent update of the California Cancer Potency
Factors prepared by theStandards and Crite ria Workgroup of Cal1EPA
. This database does not includePM s .
II .) U.S . EPA Integrated Risk Information System (IRIS) values
.
III.) U. S . EPA Health Effects Assessment Summary Tables (FAST
)
IV .) If cri te ri a are not identified in any of these
databases , a value may be calculatedfollowing consultation with an
OSA toxicologist .
e, Exposure Assessment. page 10- 8
The gen°ra? exposure formula incorporates a variable, i .e.,
"FC", which implies that exposuremay result from sources other than
the site of interest : Other sources of exposure may
certainlycontribute to total dosage : however , overall exposure of
receptors at this site cannot be reducedbecause of other sources of
exposure . Therefore , "FC" would always equal unity .
Paragraph 2, page 10-9, implies that alternative methods of
dosage calculation may b eapp ropr ate . Justification must be
provided and prior approval obtained for any methodologies wi
ciscorThc with current guidelines
f_Dx ros.ire Point Concentrations, Pace 10-1 0
Paragraph 2 - Calculations of potential exposure at the SSFL
property line are'essential tocalculation of overall risks and
hazards at SSFL ; however, on-site receptors may also be exposed
tolevels of volatile chemicals . Pleas : include potential d . .al
and inhalation exposures to volatilecompounds identified in
groundwater when calculating total exposure of all receptors .
Page 1 C-1 u, paragrapi7 3 - Depth to gr ound'-1,'ater is not a
valid c,-iterion fore intiauoo ofthis source as a potential
contributor to vapor concentrations in air . Approximately 200 meni
Orinwells are in operation at SSFL . Large volumes of water are
pumped to the surface for non-potableuses and retained in holding
ponds . Additionally, remediation systems do not remove 1O0°/ of
thechemicals present . Please include inhalation of contaminant
concentrations, which potentially
vaporize from g; oundwatcr, as a pathway in a residential cxpost
re scenario .Page 1 0- 11 - Air dispersion models and parameter
assumptions, e .g . mixing height = 150
meters, should be reviewed and approved by tnc Ventura County
Air Quality Control Dismct .
HDMSe00165911
-
01%17'96 15 :36 FAX 916 327 2509 OSA DTSC• +•. REG3PERMIT/ SBE
007-'008 '
C.,arla Slepak - Santa Sus-am Field Laboratory (RFI
Workplan)January 17, 199 6
Page 6
Exposure Pathway
Results of analytical tests for all chemicals of concern
identified in surface water and inshallow zone wells must be
reported . The two major groundwater systems at the SSFL have
beenpostulated to be connected by fissures . Any chemicals detected
in ground water must be consideredas potential chemicals of
concern, because additional exposure may occur by inhalation of
vapors orby dermal absorption of chemicals deposited on the skin .
Additionally, semi-volatile chemicals in soilmay be, potentially,
inhaled. Please include all relevant sources of exposure .
h. Intake Rate / Exposure Parameters . Table 10-3
Table 10-3 reports the area of the skin surface for a worker as
2000 cm2/d (sic) . DTSCSupplemental Guidance (September , 1993)
recommends 5800 cm2 for hands, neck, forearms, andlower legs .
Table 10-3 reports an estimated ingestion rate for "workers" of
50 mg/day . This mayunderestimate exposure to soil under the
conditions existing at this site . USEPA has recommended480 mg/day
for construction workers . OSA recommends the estimate of 480 mg/kg
for potentialexposures at this site.
i . Direct exposure soil action levels (vol . II Table B-5) and
field action levels (vol . I . Table 2-6 )
Soil action levels in this table are reportedly calculated by a
formula similar to that used tocalculate LTSEPA Region IX PRGs,
however the values differ by up to 2 orders of magnitude, inv thpr
rli -& -t- nn Piea c' ralnllatP ,nil crre~.nina levels for P.
residential .ccenario that agree with thosewhich arc calculated
using the DTSC PEA equations ,
5 . Sections 2 .3 .1 (page 2-5 1 and 10 .2 .2 Ecological Risk
Assessmen t
These sections describe an acceptable approach to an ecological
screening risk assessmentfor this site according to the guidelines
published in "Guidance for Ecological Risk Assessment atHazardous
Waste Sites and Permitted Facilities Part A Overview and Part B :
ScopingAssessment" Call EPA, Department of Toxic Substances
Control, Office of Scientific Affairs,1994-
Conclusions and Recommendations
The current list of `Dir~-t-Exposure Soil Action Levels"(Table
B-5) is unacceptable ./n .- .~.. L. .. ..1 .. .-+ 1 .~ ~1 : .++
:r~rea r,-n ..~ tl,o nt2 A t,, ^A nn o e-rmnino ~ ..v~~ an~lvCiC
Wl'filPlJl`Q1lll. L-U Ull l.4lJ a11.Lixf 1JVl VV w uvaat Wa..- ~~~
• v~rn• va . u w. .... .a .u .b .v - ....J . .y • . .•..
inorganic chemicals may only be eliminated if levels are below
an adequately supported backgroundlevel . The QRA may contain a
calculation of background risk for comparison with the onsite risk
.
HDMSe00165912
-
of/17/9 6 15 :37 r.kx a s 327 2$09 -- OSA DISC ..1
REG3PERMIT/S&E 2008/00 6
Carla Slcpak - Santa Susaaa Field Laboratory (RFI
Workplan)January 17,1996Page 7
The exposure scenario is unclear . An industrial scenario is
utilized throughout most of thedocument; however the groundwater
pathway is currently considered only for future residents at
theproperty line. The groundwater pathway should be considered
complete for offsitc residents, futureonsite residents , and for
workers in an industrial scenario:
1
Reviewer: Judith Parker, PhD ., D.A.B.TSenior Toxicologist,
HERS
Deborah J . Oudiz, Ph.D.Senior Toxicologist, HERS
c:lssfl roc\rf1wwkplnO117 .h60
HDMSe00165913
-
STATE lTF CR1Ur ORNIA - ENVIRONMENTAL PROTECTION AGENCY PETE
WILSON,Govomo r
DEPARTMENT OF TOXIC SUBSTANCES CONTROLRegion 4245 si Broadway,
Suite 425Lorch . CA 90802
4956
M E M 0 R A N D U . M
TO: Carla SlepakHazardous Substances Scientist
Facilities management Branch, Region 3
1011 Grandview Avenue
Glendale, CA 9120 1
FROM : Frank S . ParrAssistant Industrial Hygienist, Region
4Office of Scientific Affairs (OSA)Industrial Hygiene Section (IHS
)
DATE : October 23, 199 5
SUBJECT ROCKWELL SANTA SUSANA FIELD LABORATOR YHEALTH AND SAFETY
PLAN FOR RCRA FACILITY INVESTIGATIO N
7CA Code : 25120 Site Number :300232r : 33 MP` : 3J
BACKGROUND
The Facilities Management Eranch in Region 3 requested OSA-_ S
to review the Health and Safety Plan ( F?=SP) for a RCRA`~ci=!itti
inve stigation to be conducted at the RockwellInternational
Corporation, Rocketdyne Division ' s Santa SusanaFieldtaboratory,
located in eastern Ventura County, California .
Site information included within the HASP revealed the siteis
comprised of approximately 2,700 acs-es of mountainous
terrainranging from 1,700 to 2,200 feet above sea level . The SSFL
issirroundc by Sims Valley to the north, the San Fernando Valleyto
the east, and Thousand Oaks to the southwest .
A var_etV C` operations are conducted at the SSFL
includ_ngaerospace,inndustrV research, including the development
antmanufacture of propulsion units and space units and parts .
Laserresearch and development is also conducted at the SSFL _
The scope of work addressed within the HASP includes
sitereconnaissance of solid waste management units (SWMUs ) and
areasof concern (AOCs) identified throughprior assessment
activities
HDMSeOO165914
-
Carla SlepakRocketdyne RFI HASP
October 23, 1995Page 2
soil gas sampling , and soil sampling employing hand augers
andhollow- stem auger drill rigs .
OSA-IHS reviewed the "Health and Safety Plan, RCRA
FacilityInvestigation, Work Plan Addendum, Santa Susana Field
Laboratory,
Ventura County, California" . This document was prepared by
OgdenEnvironmental and Energy Services, Co ., Inc . The HASP was
dated
March, 1995 and was received by OSA on October 5, 1995 .
GENERAL COMMENTS
The Department of Toxic Substances Control (DTSC) hasreviewed
the HASP for compliance with Title 8, California Code of
Regulations (8 CCR), section 5192 : "Health and Safety
forHazardous Waste Operations and Emergency Response" as well
as
other appropriate State and Federal Occupational Health
andSafety Regulations . Please note that in addition to the
requirements of this section, the employer is responsible for
the
implementation of an effective Illness and Injury Prevention
program which is required by the 8 CCR, sections 1509 and 3203
..The requirements of those sections have not been included in
this
review .
An industrial hygienist from the OS T_-IHS may perform a
fieldaudit in order to confirm the implementation of the
provisions
and specifications presented in the HASP .
The DTSC is unable to foresee all the health and safety
hazards in try work-place by the review of the submitted plan
.
Continuous surveillance of the work-site and creation of an
efec e health and safety program by the employer will reducework
place in3uries and reduce liability .
CSA-IHS review of this HASP is nut a guarantee that it will
be properly and Safely implemenLed. Is the
emolov°_r's r sponsibility .
SPECIFIC COrg`_ENTS
-) ;z Se Table of Contents . Please tabl e of contentsso that
sections match referenced pa3es .
2 . Page Scope of Work/Planned Site =;ctiv(:ties_ -he
anticipated duration of field activities is not discussed . (8
CCR
5"192 (c) (4) (C) .
3 . Page 1-, Radiation . 90Sr is considered to be a primary
beta
emitter only . Please include language Y:i`thin this section
ssflrfi_h p
HDMSe00165915
-
describing how beta particle screening shall be accomplished .
(8CCR 5192 (c) (6) (A )
4 . Page 15, Site Characterization . SWWJ 4 .5 : LOX Plant
FormerWaste Oil Sump and Clarifier- Please clarify
statement"Anticipated chemicals refer to those chemicals that
weredetected above screening or action levels during the
previoussampling or that will be sampled for during the RFI" .
Pleasedefine screening and action levels and discuss the method(s)
usedto derive them and their significance relating to
potentialoccupational exposures .
S . Page 30, Table 3, Summary of Physical and Operational
SafetyHazards, Electrocution .
A) When heavy equipment (i .e . drill rigs) is used on
siteswhere high voltage overhead power lines may be encountered,the
minimum safe distances to be maintained from these linesare
outlined in 8 CCR 2946 must be followed . Please modifyas indicated
. ( 8 CCR 2946) .
B) Procedures describing borehole clearance are notdiscussed in
sufficient detail . 8 :CR 1541 requires thatall regional
notification centers be contacted a minimum oftwo working days
prior to the start of any digging orexcavation work .
6 . Page 30, Table 3, Summary of Physical and Operational
SafetyHazards, Heat Stress . Please provide greater detail
describingTo :itoring protocols for heat-related disorders such as
pulsemonitoring or aural temperature monitor__n:g procedures .
Ensureaction levels, time frames and reference. : are included
.
Pane 30, Table 3, Summary of Physical and Operational
Safet•~~razards, _tat Stress . Description of nc-se hazards
andcorresponding monitoring procedures to be employed on site
rerui_es clarification and/or modificat_zn . P.n employer
isobligated to quantify their emplcvees' ex•_aosure to noise
when
there is a cossibilli y of exposure to an eight-hour
time-weightedaverage of 85 dEA . Provide personnel monitoring data
fro mp_ o s -m:lar site activities or describe noise
monitoring~rotocoic to be employed on site, inclu _nc a description
of theinstrumentation, frequency of mon ;-torinc . and
correspondingaction ie-.els . 8 CCRGeoup 75, Article =05 (Control
of Nois e
Pace 31, Hazard !alysis of Field Casks, S7t ~=eccnus ssance,
Personal Protective Eou_ument . Level D personalprotective
eouipment (PPE), outlined within this section does notin :icate the
use of safety evewear as outlined on page 38,
HDMSeOO165916
-
s4Vla SlepakRocketdyne RFI HASPOctober 23,1995Page 4
Personal Protective Equipment section . Please modify
forconsistency . ( 8 CCR 5192(g)) .
9 Page 38, Illumination . Explain how adequate lighting shallbe
provided during work activities . Ensure minimum
illuminationintensities outlined in table H-l, 8 CCR 5192 (m) are
provided .
10 . Page 41 , Table 5 , Air Monitoring Action Levels .
Pleaseverify that organic vapor /acid gas respirator cartridge
willprovide adequate protection for vinyl chloride up to the PEL .
( 8CCR 5192(j), and 8 CCR 5210 )
11 . Page 4 2, Decontamination Procedures . A description
ofsanitary facilities which will be available to site personnel
isnot Included . Please describe provisions for providing
personnelwith adequate potable and non-potable water and
toiletfacilities . ( 8 CCR 5192(n)) .
12 . Page 43, Emergency Contingency Plan . Please describe
anyRocketdyne SSFL facility-specific emergency evacuation alarms
andprocedures within this section . 98 CCR 5192(1)) _
13 . Page 44, Bloodborne Pathogen Exposure Control Plan .
Includea discussion of training requirements specified for
personnelu t potential occupational exposures to bloodborne
pathogens
- 8 CCR 5193 .
1 A discussionofconfin_ ed space hazards and entryprocedures is
not provided . Describe hazards associated withcc-fi-ed spaces and
corres ponding entry procedures . If n o
__ed space entry is anticipated (i . e no utility vault oration
entry) then include a section within the HA SP stating
--a : confined space haza_^ds do not exist . (8 CCR(4) 1 ) (9)
& 5157 )
CONCLUSION S
The submitted HASP does not contain all of the elementssneclfred
in 8 CCR, section 5792 . Areas identified asdeficien t
e corrected or clarified and resubmitted for furthert--_• . _
Recommendations are attached for review and
ration . Please reline or otherwise delineate anycation to this
document ro facilitate a timely response
HDMSe00165917
-
`Carla SlepakRocketdyne RFI HASPOctober 23, 1995Page 5
OSA is available to participate in a meeting or conferencecall
to discuss this document or related items . Thank you forthe
opportunity to review this document . Should questions arise
,please contact Frank Parr at (310) 590-4956 .
HDMSe00165918
-
HDMSe00165919