May 22, 2016 Page | 1 HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #67 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY » Total Man Hours Worked This Week: 12668 » Total Man Hours on Project: 241141 » Crafts On Project This Week: 16 » OSHA Recordable Rate: 0
7
Embed
HOLDER CONSTRUCTION COMPANY - Clemson Universityhousing.clemson.edu/wp-content/uploads/2016/06/5...TRADE CONTRACTORS ON SITE Subcontractor Trade Employees Man Hours Total Man Hrs.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
May 22, 2016 P a g e | 1
HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #67
Douthit Hills Student Community, Clemson University Project
Joe Jett
SAFETY
» Total Man Hours Worked This Week: 12668
» Total Man Hours on Project: 241141
» Crafts On Project This Week: 16
» OSHA Recordable Rate: 0
May 22, 2016 P a g e | 2
HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #67
Douthit Hills Student Community, Clemson University Project
Joe Jett
CURRENT CONSTRUCTION ACTIVITIES
Bldg. F Plumbing Bldg. G Domestic Water Valve Bldg. E Windows
East Zone
» Continued Window Frame Installation @ Building
E.
» Continued Brick Masonry @ Building G.
» Continued Mechanical Rough-In @ Building F.
» Continued Installing Fascia@ Building G.
» Continued Gutters @ Building G.
» Continued Electrical Rough-In @ Building F.
» Continued Sprinklers @ Building G .
» Continued Stair Rails @ Building F.
» Continued Brick Angle @ Building E.
» Continued Setting Showers @ Building G.
SITE, HUB, & WEST ZONE
» Continued Auger Cast Piles @ Building B.
» Continued Foundation Drains and Backfill @
Building B.
» Installed Weir Inlet on Storm Line 10.
» Continued Stem Walls @ Building B.
» Continued Precast @ Building A.
» Continued Grading @ East Parking Lot Islands.
» Continued Forming Columns @ HUB.
» Began Grading For Transformer Pads @ Buildings
E, F, & G.
Storm Line 10 HUB Elevated Slab 2A
May 22, 2016 P a g e | 3
HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #67
Douthit Hills Student Community, Clemson University Project
Joe Jett
EAST ZONE
» Continue Overhead Rough-In @ Buildings G & F.
» Continue Brick @ Building G.
» Continue Stair Rails @ Building F.
» Continue Temporary Power Wiring @ Building E.
» Continue Brick Angle @ Building E.
» Continue Glazing @ Building E.
» Pour Areaway Slab @ Building E.
» Continue Gutters @ Buildings G & F.
NEXT WEEK’S ACTIVITIES
SITE, HUB, & WEST ZONE
» Continue Precast @ Building A.
» Continue CIP Walls @ Building B.
» Continue Auger Cast Piles @ Building B.
» Pour Elevated Deck 2A @ HUB.
» Continue Forming HUB Elevated Deck 2B and
2C.
» Continue Excavation For Underground Deten-
tion System.
» Pour Transformer Pads @ Buildings E,F, & G.
» Continue Storm Line 10 & Underground
Detention System.
Building A Precast
Building B Backfill and Foundation Drains
May 22, 2016 P a g e | 4
HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #67
Douthit Hills Student Community, Clemson University Project
Joe Jett
MANPOWER
TRADE CONTRACTORS ON SITE
Subcontractor Trade Employees Man
Hours Total Man Hrs.
Holder Construction Company General Contractor 33 1320 48760
American Deep Foundation Auger cast piles 8 360 5670
Baker Roofing Sheathing and Shingles 6 140 3638
Carolina Fire Protection Sprinklers 5 300 1350
C&C Fence Site Fence 0 0 764
Cowart Tree Mulch Tree Removal 0 0 710
Davis Crane Erectors Pre-Cast Erection 12 480 9870 D.H. Griffin Tank Foundation Removal 0 0 90 Gainesville Mechanical Ductwork 35 1960 8596
Gregory Electric Aboveground Electric 3 120 120
Hutch-N-Son Early Site Work 0 0 1337
1st Choice Glass Glass 4 108 2644
Johnson Controls Building Controls 3 120 120
JBR Construction Early Site Work 0 0 2049
Johnsons Modern Electric Aboveground Electrical 14 756 4780
King Asphalt Asphalt 0 0 2264
Labor Finders Labor Force 12 480 20788
Metro Power Underground Electrical 10 332 12875
Old North State Masonry Masonry 22 400 4960
Osteen Chill Water pipe 0 0 2066
Precision Concrete 55 2200 36920
R.E. Mclean Tank Tank Demo 0 0 660
Reeves Young Site Grading & Utilities 15 540 39810
Rival Construction Inc. Concrete 36 1440 7371
RJ Coogan Deck Installers 0 0 560
Ruppert Landscaping Landscape/ Hardscape 0 0 380
Sears Contract Drywall/Metal Trusses 17 544 9150
Silt Fence Installation Site Erosion Control 0 0 999
Southern Mechanical Inc. Electrical/Plumbing 17 680 5980
Steel Toe Labor Force 6 248 2960
Tree South Arborist 0 0 1431
Upstate Curb Curb and Gutter 0 0 460
May 22, 2016 P a g e | 5
HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #67
Douthit Hills Student Community, Clemson University Project
Joe Jett
MANPOWER CONTINED
TRADE CONTRACTORS ON SITE
Subcontractor Trade Employees Man
Hours Total Man Hrs.
Valley Farm Construction Tree removal/Grading 0 0 395
Waterproofing Specialties Waterproofing 4 140 614
Total 317 12668 241141
May 22, 2016 P a g e | 6
HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #67
Douthit Hills Student Community, Clemson University Project