June 7, 2015 Page | 1 HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #16 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY » Total Man Hours Worked This Week: 1716 » Total Man Hours on Project: 20480 » Crafts On Project This Week: 10 » OSHA Recordable Rate: 0
6
Embed
HOLDER CONSTRUCTION COMPANY - Clemson Universityhousing.clemson.edu/wp-content/uploads/2015/06/6-7-15... · 2018-03-31 · Superintendents Weekly Activity Report #16 Douthit Hills
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
June 7, 2015 P a g e | 1
HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #16
Douthit Hills Student Community, Clemson University Project
Joe Jett
SAFETY
» Total Man Hours Worked This Week: 1716
» Total Man Hours on Project: 20480
» Crafts On Project This Week: 10
» OSHA Recordable Rate: 0
June 7, 2015 P a g e | 2
HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #16
Douthit Hills Student Community, Clemson University Project
Joe Jett
CURRENT CONSTRUCTION ACTIVITIES
» Continued installation of orange tree save on new
tree protection fence
» Commenced mobilization and installation of office
trailers
» Continued silt fence and erosion control installa-
tion
» Completed duct-bank installation at trailer com-
pound
» Began installation of deck at trailer compound.
» Completed tree removal at pond and project site
» Continued hauling off tree mulch from project
site
» Continued hardscape demo on project site
» Began grading at detention pond
Project Site Tree Removal
West
Mobilized Office Trailers at Compound
June 7, 2015 P a g e | 3
HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #16
Douthit Hills Student Community, Clemson University Project
Joe Jett
» Continue installation of jobsite erosion control
» Continue hauling off tree mulch
» Continue mobilization of office trailers
» Commence temporary power hook up for trailer
compound
» Continue deck installation at trailer compound
NEXT WEEK’S ACTIVITIES
Silt Fence Installation at West Side of Site
Detention Pond Tree Removal
» Continue tree removal at project site
» Continue hardscape demo on project site
June 7, 2015 P a g e | 4
HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #16
Douthit Hills Student Community, Clemson University Project