GLAST LAT Project CAL Peer Design Review, Mar 17-18, 2003 W. N. Johnson Naval Research Lab Washington DC GLAST Large Area GLAST Large Area Telescope Telescope Calorimeter Subsystem Gamma-ray Large Gamma-ray Large Area Space Area Space Telescope Telescope 2.0 Management W. Neil Johnson Naval Research Lab, Washington DC Calorimeter Subsystem Manager [email protected] (202)–767–6817
13

GLAST Large Area Telescope Calorimeter Subsystem

Mar 21, 2016

Download

Documents

Davina Sn

Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope Calorimeter Subsystem. 2.0 Management W. Neil Johnson Naval Research Lab, Washington DC Calorimeter Subsystem Manager [email protected] (202)–767–6817. Outline. Organization Work Flow / Fabrication Plan - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: GLAST Large Area Telescope Calorimeter Subsystem

GLAST LAT Project CAL Peer Design Review, Mar 17-18, 2003

W. N. Johnson

Naval Research LabWashington DC

GLAST Large Area TelescopeGLAST Large Area TelescopeCalorimeter SubsystemGamma-ray Large Gamma-ray Large

Area Space Area Space TelescopeTelescope 2.0 Management

W. Neil JohnsonNaval Research Lab, Washington DCCalorimeter Subsystem Manager

[email protected](202)–767–6817

Page 2: GLAST Large Area Telescope Calorimeter Subsystem

GLAST LAT Project CAL Peer Design Review, Mar 17-18, 2003

W. N. Johnson 2 - 2Naval Research Lab

Washington DC

OutlineOutline

Organization Work Flow / Fabrication Plan Schedule Summary Critical Path Analysis Procurements

Page 3: GLAST Large Area Telescope Calorimeter Subsystem

GLAST LAT Project CAL Peer Design Review, Mar 17-18, 2003

W. N. Johnson 2 - 3Naval Research Lab

Washington DC

Calorimeter – Institutional OrganizationCalorimeter – Institutional Organization

P. D izon , M echJ . A m pe , E lect

Pe ck Sohn , T hermN . Virm an i, M an u f.

S ys tem EngR . K raeu ter

N R L (Sw a les)

R &Q A / P a rtsN V irm ani

N R L (Swa le s)

C s I C rys ta ls,T e st Ben ch

L . N ilss on, K alm ar

S w ed ish P IsP C ar lso n (P I)

R S ven son (C o-P I)

IN 2 P3 P roj. S c ien t istG B ogaert

IN 2P 3 Eco lePo ly

Sy s te m EngP ie rre P rat

E M B eam T estB . Lo tt

IN 2P 3 Bordeaux

F ren ch IN 2P3H . VIde au

PM : O . F er re iraEco le P o lytech n ique

C E A Ins tru. S c ie nt istB . C ord ier

P ro jec t C on trolY ve s A cke r

Sys tem E ng ineerP . B ourgeo is

Fre nch C E A /D SM /D AP N IAI G ren ier

PM : D . Bédérè deC EA /Sac lay

A na lo g A S IC D es ignD . F rey tag

S L AC

P C B D es ignM . F rey tag

S L AC

E lec trica l D es ign & F abJ . A m pe, L ead Ele c E ng

N R L

E G SE S of tw a reB . Leas

N R L / IC S

Lead C a lib S c ien t istA . C hekh tm an

N R L

A ssy, T es t and Ca lib ra tionE . G rov e, In st ru S c ient ist

N RL

I& T S of tw areB . Leas

N R L / IC S

SA S - C AL M grM . S tric km an

N R L

In tegra tion , Tes t & O psE . G rove

N RL

G LA ST C a lor im e te r S ubs ystemS u bsys M gr: N . Johns on, N R LPM : R . K raeu ter , N R L (S wales)

G LA ST IPOS ta n fo rd

Page 4: GLAST Large Area Telescope Calorimeter Subsystem

GLAST LAT Project CAL Peer Design Review, Mar 17-18, 2003

W. N. Johnson 2 - 4Naval Research Lab

Washington DC

CAL Subsystem WBSCAL Subsystem WBS

4.1.5.1 Calorimeter Program Management and Administration

NRL N. Johnson

4.1.5.2 Systems Engineering NRL R. Kraeuter4.1.5.3 Reliability and Quality Assurance NRL N. Virmani4.1.5.4 Calorimeter Design NRL E. Grove4.1.5.5 Csl Crystal Detector Elements (CDE) NRL R. Kraeuter

4.1.5.5.1 CDE design NRL N. Johnson4.1.5.5.2 Csi(TI) Scintillation Crystals KTH Sweden P. Carlson4.1.5.5.3 Dual PIN photoDiode (DPD) NRL/CEA N. Johnson4.1.5.5.4 Dual PIN Photodiode Interconnect CEA/NRL D. Bederede4.1.5.5.5 CDE I&T CEA-Saclay D. Bederede4.1.5.5.6 CDE Bonding Study NRL R. Kraeuter

4.1.5.6 Pre-Electronics Module (PEM) NRL P. Dizon4.1.5.6.1 PEM Structure Fabrication & Test IN2P3 O. Ferreira4.1.5.6.2 PEM Assembly & Test NRL E. Grove

4.1.5.7 Analog Front End Electronics NRL J. Ampe4.1.5.8 Calorimeter Tower Controller NRL J. Ampe4.1.5.9 Calorimeter Module Assembly, Test &

CalibrationNRL E. Grove

4.1.5.A Instrument I&T Support NRL E. Grove4.1.5.B S/C Integration Support NRL E. Grove4.1.5.C Mission Operations Support NRL E. Grove

Page 5: GLAST Large Area Telescope Calorimeter Subsystem

GLAST LAT Project CAL Peer Design Review, Mar 17-18, 2003

W. N. Johnson 2 - 5Naval Research Lab

Washington DC

Calorimeter Work FlowCalorimeter Work Flow

Crystal Detector Element (CDE) AssemblyFrance (CEA/DAPNIA)

PIN Diode(each end)

CsI Crystal

Optical Wrap

Wireleads

Mechanical StructureFrance (IN2P3/Ecole Polytechnique)

Front-End ElectronicsNRL, SLAC

PreElectronics Module (PEM) AssemblyNRL

Module Assemblyand Test, NRL+collab

CsI CrystalsSweden (KTH)

16 Flight modules + 1 Qual + 1 Spare

1728

18

18

18

Bond

End Cap

Dual PIN Diodes(DPD) NRL/CEA

Page 6: GLAST Large Area Telescope Calorimeter Subsystem

GLAST LAT Project CAL Peer Design Review, Mar 17-18, 2003

W. N. Johnson 2 - 6Naval Research Lab

Washington DC

CAL Hardware CollaboratorsCAL Hardware CollaboratorsOrganization Responsibility Naval Research Lab CAL Subsystem Management & System Engineering

Safety & Mission Assurance, Subsystem Design PIN photodiode spec and shared procurement CAL Electronics Design & Fab, Digital ASIC design, CAL Module Assy & Test, LAT I&T Support

SLAC CAL Analog ASIC Design AFEE PCB layout

Sweden CsI Crystal procurement and acceptance test

France / CEA Crystal Detector Element design, fabrication and test Part of PIN photodiode procurement, PIN Diode assembly

procurement, PIN-CsI bonding, CsI optical wrap.

France / IN2P3 Mechanical Structure design and fabrication Carbon composite cell structure. Al baseplate and closeout

shells, elastomer bumpers and cords. Finite element and thermal analyses. Beam Test Planning and Support

Page 7: GLAST Large Area Telescope Calorimeter Subsystem

GLAST LAT Project CAL Peer Design Review, Mar 17-18, 2003

W. N. Johnson 2 - 7Naval Research Lab

Washington DC

CAL Summary ScheduleCAL Summary Schedule

Module Need Dates (RFI)

Module Available Dates (RFI)

Page 8: GLAST Large Area Telescope Calorimeter Subsystem

GLAST LAT Project CAL Peer Design Review, Mar 17-18, 2003

W. N. Johnson 2 - 8Naval Research Lab

Washington DC

CAL Qual Module (FMA)CAL Qual Module (FMA)Dual PIN PhotodiodeNRL, CEA/Salcay06/18/03 (29)

CsI CrystalsSweden03/21/03 (88)

Crystal Detector Elements (CDE)CEA/Saclay

08/29/03 (1)

Carbon Composite StructureAl base, closeouts, plastic partsLLR/Ecole Polytechnique

07/24/03 (30)

Pre Electronics ModuleNRL10/08/03 (1)

ASICsSLAC, NRL07/30/03 (1) Other EEE parts

Parts Qual/ScreenNRL08/08/03 (1)

PCBNRL, SLAC06/23/03 (34)

Analog Front End Electronics (AFEE) NRL10/09/03 (1)

CAL ModuleNRL11/17/03 (1)

CalibrationEnvironmental TestNRL01/26/04 (0)

Ready for Integration (RFI)02/17/04 (0)(L3: 02/17/04)

Completion Dates (float)

Page 9: GLAST Large Area Telescope Calorimeter Subsystem

GLAST LAT Project CAL Peer Design Review, Mar 17-18, 2003

W. N. Johnson 2 - 9Naval Research Lab

Washington DC

CAL Flight Module 3CAL Flight Module 3Dual PIN PhotodiodeNRL, France08/04/03 (81)

CsI CrystalsSweden05/16/03 (132)

Crystal Detector Elements (CDE)CEA/Saclay

10/27/03 (68)

Carbon Composite Structure Al base, closeouts, plastic partsLLR/Ecole Poly

09/15/03 (101)

Pre Electronics ModuleNRL11/17/03 (68)

ASICsSLAC, NRL 07/30/03 Other EEE parts

Parts Qual/ScreenNRL 08/08/03

PCB NRL, SLAC 06/23/03

Analog Front End Electronics (AFEE) NRL10/24/03 (85)

CAL ModuleNRL01/15/04 (62)

CalibrationEnvironmental TestNRL03/04/04 (54)

Ready for Integration (RFI)03/30/04 (54)(L3: 06/15/04)

Completion Dates (float)

Page 10: GLAST Large Area Telescope Calorimeter Subsystem

GLAST LAT Project CAL Peer Design Review, Mar 17-18, 2003

W. N. Johnson 2 - 10Naval Research Lab

Washington DC

CAL Flight Module 16CAL Flight Module 16Dual PIN PhotodiodeNRL, France12/18/03 (104)

CsI CrystalsSweden11/19/03 (120)

Crystal Detector Elements (CDE)CEA/Saclay

04/23/04 (45)

Carbon Composite Structure Al base, closeouts, plastic partsLLR/Ecole Poly

03/24/04 (70)

Pre Electronics ModuleNRL05/15/04 (45)

ASICsSLAC, NRL 07/30/03 Other EEE parts

Parts Qual/ScreenNRL 08/08/03

PCB NRL, SLAC 06/23/03

Analog Front End Electronics (AFEE) NRL01/14/04 (177)

CAL ModuleNRL06/02/04 (44)

CalibrationEnvironmental TestNRL06/25/04 (45)

Ready for Integration (RFI)07/22/04 (45)(L3: 09/24/04)

Completion Dates (float)

Page 11: GLAST Large Area Telescope Calorimeter Subsystem

GLAST LAT Project CAL Peer Design Review, Mar 17-18, 2003

W. N. Johnson 2 - 11Naval Research Lab

Washington DC

CAL ProcurementsCAL Procurements

Vendor Element Amcrys-H (Ukraine) CsI(Tl) crystal elements

Procurement in place by Sweden for all CAL CsI (~2000 crystals or 1640 kg) 240 prototypes in hand for Eng Model. Delivery rate: 200 crystals/month, 1st deliveries March ‘03

Hamamatsu Photonics Custom Dual PIN Photodiode NRL and France / CEA shared procurement 600 Design prototypes in hand for Eng Model. Spec for flight version diodes completed, 184 prototypes have been procured. Flight procurement has been initiated: ~4800 diodes Delivery rate: 600 / 4 weeks. 1st deliveries June ‘03

3M Corporation VM2000 Reflective Film (CDE Optical Wrap) Prototype in hand for EM and qualification testing. Approved for flight use.

Page 12: GLAST Large Area Telescope Calorimeter Subsystem

GLAST LAT Project CAL Peer Design Review, Mar 17-18, 2003

W. N. Johnson 2 - 12Naval Research Lab

Washington DC

CAL Procurements (2)CAL Procurements (2)

Vendor Element Competitive (France) CDE Manufacturing – bonding & wrapping

Request for proposals is out. Selection expected end of May. Delivery rate: 108 CDE/two weeks, 1st deliveries end of Aug ‘03

Competitive (France) PIN Photodiode Assembly Request for proposals is out. Selection expected end of May. Delivery rate: 240 PDA/two weeks, 1st deliveries Aug ‘03

Competitive (France) Mechanical Structure components Alum. machined parts, elastomeric parts, carbon prepreg. Prototypes in hand for EM and qualification testing. Selection process is underway, waiting for released flight drawings. 1st delivery June ‘03

Page 13: GLAST Large Area Telescope Calorimeter Subsystem

GLAST LAT Project CAL Peer Design Review, Mar 17-18, 2003

W. N. Johnson 2 - 13Naval Research Lab

Washington DC

CAL Procurements (3)CAL Procurements (3)

Vendor Element MOSIS / ASAT ASIC manufacturing and packaging.

Prototypes in hand for EM and qualification testing. Flight ASICs have been submitted for production. Packaging procurement in process. Need date: July ‘03

Maxim Integrated Products

COTS ADCs and DACs NRL Procurement for all LAT subsystems has been initiated. Avail May ‘03 Prototypes in hand for EM and qualification testing. Flight: 10,000 ADCs (MAX145), 1000 DACs (MAX5121)

QML Vendors EEE Parts/ Circuit Boards / Board Assembly All parts have been approved except qualification needed for connectors and plastic encapsulated parts. Ready for procurement.