Top Banner
Placement instructions Practical advice General Trackunit 401 DualID installation Do NOT install the GPS/GSM unit directly under a layer of metal or next to wires. Make sure that water can run off the unit. 1. Mount the bracket on the machine using 3 screws. Ø11 mm 3. Click the DualID into the bracket starting at the top. A click is felt when pressing the bottom part of the DualID firmly in place. 2. Drill a hole in the back panel for the unit cable and drag the cable through the hole. The hole must be big enough for the plug! Serial number located on the back of the GPS/GSM unit. GSM number and unit serial number is located on the box. Label can be peeled off and placed on page 4 of this guide. +xx xx xx xx xx S/N xxxxxx Do NOT perform installation inside a building. S/N xxxxxx Locate the unit as shown for optimal signal conditions. 7001.0080 v1.3 06-07-2015 ©Trackunit 2015
2

General Trackunit 401 DualID installation

Oct 16, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: General Trackunit 401 DualID installation

Placement instructions

Practical advice

General Trackunit 401 DualID installation

Do NOT install the GPS/GSM unit directly under a layer of metal or next to wires.

Make sure that water can run off the unit.

1. Mount the bracket on the machine using 3 screws.

Ø11 mm 3. Click the DualID into the bracket starting at the top. A click is felt when pressing the bottom part of the DualID firmly in place.

2. Drill a hole in the back panel for the unit cable and drag the cable through the hole. The hole must be big enough for the plug!

Serial number located on the back of the GPS/GSM unit.

GSM number and unit serial number is located on the box. Label can be peeled off and placed on page 4 of this guide.

+xx xx xx xx xx S/N xxxxxx

Do NOT perform installation inside a building.

S/N xxxxxx

Locate the unit as shown for optimal signal conditions.

7001.0080 v1.3 06-07-2015

©Trackunit 2015

Page 2: General Trackunit 401 DualID installation

Trackunit 401 DualID installation

General wiring

Guidelines for correct wiring: Disconnect the power supply during installation.

©Trackunit 2015

Wire colour Connection Description

Blue Ground Ground

White Digital input 1 Operating hours counter input

Brown Digital input 2 Ignition signal input

Grey Digital Input 3 Not available. Used for DualID Power.

Pink Digital input 4

In case the main switch breaks the ground wire, the inputs may register a voltage level when off. To avoid this, the pink wire should be connected to the chassis of the machine and activate input filter by setting filtering ‘on’ via the Verify tool. (See page 3)

Yellow Digital output 1 Output activates ground for relay (85)

Red Power Connect to permanent 12 / 24 / 48V supply (Absolut max. range 9-65V)

Example showing general installation

Hourmeter

Alternator

7001.0080 v1.3 06-07-2015