Florida Department of TRANSPORTATION 2015 FTBA ANNUAL CONVENTION August 6-9, 2015 NAPLES GRANDE BEACH RESORT WORK PROGRAM OVERVIEW 2016-2020 Jim Boxold Secretary, Florida Department of Transportation FLORIDA DEPARTMENT OF TRANSPORTATION 1
Dec 25, 2015
Florida Department ofTRANSPORTATION
2015 FTBA ANNUAL CONVENTION August 6-9, 2015
NAPLES GRANDE BEACH RESORT
WORK PROGRAM OVERVIEW2016-2020
Jim BoxoldSecretary, Florida Department of Transportation
FLORIDA DEPARTMENT OF TRANSPORTATION
1
Florida Department of Transportation
1915 - the State Road Department (SRD) was authorized by the Florida Legislature.
1920 - the SRD created five divisions which later became districts.
1969 - The State Road Board and State Road Department were merged into the Department of Transportation.
2
FLORIDA DEPARTMENT OF TRANSPORTATION100 YEARS OF SERVICE
Florida Department of Transportation
1915 HIGHWAY PROGRAM
REVENUE (FROM AUTO LICENSE) $3,647
DISBURSEMENTS 974
BALANCE $2,673
EARLY FEDERAL AID
FEDERAL AID IN 1917 LAW OF 1916 $55,976
AFTER FIRST DECADE - BY 1925-26
OCTOBER 1915-DECEMBER 1926 ROAD PROJECTS COMPLETED (SAND-CLAY/ASPHALT/BROKEN STONE BASE)
1,158 MILES@ COST OF $22,565,165
CONSTRUCTION COST AVG. $19,000/MILE
MAINTENANCE COST IN 1925 (ON 1270 MILES ) $585/MILE
PLANS COMPLETED IN 1925-26 1,006 MILES OF PLANS
1915 VEHICLE COST –AVERAGE WAS $500
WHAT WAS OUR PROGRAM LIKE IN 1915?
3
Florida Department of Transportation4
EARLY ROAD BUILDING RESOURCES
The MulesThe Department
added to the organization a
Veterinarian to care for the 514 mules.
CONVICTS LAYING BRICK PAVEMENT 1915 ROAD-BUILDING USING CONVICT LABOR
The MenConvict Labor
1,000 Convicts working at $1.06 per day.
1925-26 REPORT: STATE WORK FORCE
Florida Department of Transportation
DISTRICT SIX This 13 mile $481M project - tolled express lanes along the SR 826/Palmetto Expressway
WE’VE COME A LONG WAY IN 100 YEARS
5
1917 DIXIE HWY BEFORE 1917 DIXIE HWY AFTER
FROMEARLY
IMPROVED 2-LANES
TOMODERN MULTI-LEVEL
FREEWAYS
Florida Department of Transportation
TOTAL FUNDING FY 2016 - 2020
2-July-2015 16Adopt01 - Adopted Work ProgramTotals May Not Add Due To Rounding - Excludes Emergency Related Programming 1-July-2015
6
Florida Department of Transportation
TOTAL BUDGET FY 2016-2020
2-July-2015 16Adopt01 - Adopted Work ProgramTotals May Not Add Due To Rounding - Excludes Emergency Related Programming 1-July-2015
7
Florida Department of Transportation
TOTAL CONSTRUCTION FY 2016 - 2020
Total 5-Year Adopted Work Program $19,226M Note: In addition, $633M of Construction phases are included in the FLP Transit, Rail and Intermodal Access Programs. 2-July-2015 16Adopt01 - Adopted Work ProgramTotals May Not Add Due To Rounding - Excludes Emergency Related Programming 1-July-2015
8
Florida Department of Transportation
TOTAL CONSTRUCTION ENGINEERING INSPECTION (CEI)FY 2016-2020
Note: In-house Construction Engineering Inspection is now combined into Operations and Maintenance. In-house values are as programmed in WPA.2-July-2015 16Adopt01 - Adopted Work ProgramTotals May Not Add Due To Rounding - Excludes Emergency Related Programming 1-July-2015
Total 5-Year Adopted Work Program $2,019M
9
Florida Department of Transportation
FY 2016 PROJECT LETTINGS - BY MANAGING DISTRICT(JULY 31, 2015 LOCKDOWN PLAN)
FY 2016 PROJECT LETTINGS(OUR FY 2016 ADOPTED PLAN)
DISTRICT LETTINGS AMOUNT IN $MILLIONS
LETTINGSNUMBER OF PROJECTS
1 $312 80
2 $754 70
3 $248 73
4 $246 36
5 $335 52
6 $305 54
7 $176 40
TE $721 27
SW $3,097 432TARGETS & RESERVE BOXES NOT INCLUDED
10
Florida Department of Transportation
FY 2016 PROJECT LETTINGS - BY PROJECT TYPE(JULY 31, 2015 LOCKDOWN PLAN)
TYPE PROJECT AMOUNT IN $MILLIONS NUMBER OF PROJECTS
ROADWAY $2,235 170
BRIDGE
REPLACE $110 REPAIR $71
REPLACE 8 REPAIR 50
RESURFACING $559 135
SAFETY $79 49
TRAFFIC OPS $43 20
TOTAL SCHEDULED $3,097 432
11
Florida Department of Transportation
FY 2016 PROJECT LETTINGSPROJECT LETTINGS > $50M PLANNED
DESIGN BUILD
DIST FIN PRJ PROJECT DESCRIPTION EST $M MONTH
2 208001-4 SR 223/ALT. US 301 TRUCK ROUTE FROM SR 200 (US 301) TO SR 100 $50 MAY
2 210712-4 SR 200 (A1A) FROM WEST OF RUBIN RD TO EAST OF CR 107/SCOTT RD $59 OCT
2 213323-1 I-95 (SR 9) AT NORTH I-295 INTERCHANGE $171 APR
2 428865-1 I-10 (SR 8) / SR 200 (US 301) INTERCHANGE OPERATIONAL IMPROVEMENTS $77 SEP
2 433036-1 I-95 (SR 9) AT I-10 INTERCHANGE OPERATIONAL IMPROVEMENT $122 DEC
4 419013-1 SR-80/SOUTHERN BLVD BRIDGES 930097 & 930098 $77 APR
5 423446-9 CENTRAL FLORIDA COMMUTER RAIL $71 NOV
5 240196-1 SR 15/600 (US 17/92) FROM SHEPARD RD TO LAKE MARY BLVD $50 DEC
6 434922-1 SR 90/TAMIAMI TRAIL FROM MP 14.038 TO MP 17.230 $125 APR
8 405270-3 SUNCOAST PARKWAY 2 - HERNANDO/CITRUS COUNTY LINE TO CARDINAL ST. $65 JUN
8 405270-4 SUNCOAST PARKWAY 2 - CARDINAL ST. TO SR 44 $73 JUN
8 406110-1 I-75/TPK INTCHG MODIFICATION (NORTHERN TERMINUS) (MP 309) $50 NOV
8 411406-1 WIDEN TPK FROM OSCEOLA CNTY LINE TO BEACHLINE, MP 249.3-254 (4TO8 LNS) $124 JUN
8 415051-4 WIDEN HEFT, BIRD RD - SR836(MP23.8-26) (6 TO 10 LANES) INC. EXPRESS LAN $134 OCT
8 417545-1 WIDEN SEMINOLE XWAY FROM ALOMA AVE TO SR 434 (MP 38 - 44) (4TO6 LANES) $96 JUN
12
Florida Department of Transportation
STATEWIDE PROJECT LETTINGS IN $B FY 2016-2018
FISCAL YEAR SCHEDULED BOXED TARGETS & RESERVES
TOTAL IN $B
FY 2016 $3.1 $0.3 $3.4
FY 2017 $2.7 $0.4 $3.1
FY 2018 $1.8 $0.4 $2.2
Note: The outer fiscal years will increase as they move forward in the Work Program.
These lettings include the Highway and Bridge Programs only. Includes Resurfacing, Bridges, Roadway, Safety, and Traffic Operations.
Only Contract Classes 1 (Central Office Let), 7 (District Office Let), and 9 (Design-Build) are included.
13
Florida Department of Transportation
FISCAL YR DIST FIN PRJ PROJECT DESCRIPTION EST $M
2016 02 213323-1 I-95 (SR 9) AT NORTH I-295 INTERCHANGE $171
2016 02 433036-1 I-95 (SR 9) AT I-10 INTERCHANGE OPERATIONAL IMPROVEMENT $122
2016 06 434922-1 SR 90/TAMIAMI TRAIL FROM MP 14.038 TO MP 17.230 $125
2016 08 411406-1 WIDEN TPK FROM OSCEOLA CNTY LINE TO BEACHLINE, MP 249.3-254 (4TO8 LNS) $124
2016 08 415051-4 WIDEN HEFT, BIRD RD - SR836(MP23.8-26) (6 TO 10 LANES) INC. EXPRESS LAN $134
2017 03 409334-1 SR 30 (US 98) PENSACOLA BAY BRIDGE NO. 480035 $459
2017 05 238275-7 SR429/46(WEKIVA PKW) FROM W OF OLD MCDONALD RD TO E OF WEKIVA RIVER RD $221
2017 06 251688-1 SR 836/I-395 FROM WEST OF I-95 TO MACARTHUR CSWY BRIDGE $600
2017 07 433880-1 GATEWAY EXPRESSWAY FM SR690 @ US19 & SR686 EXT @ CR611 TO W OF I-275 $321
2018 05 240200-2 SR429/46(WEKIVA PKWY)FROM E OF WEKIVA RIVER RD TO ORANGE BOULEVARD $176
2018 08 435542-1 WIDEN HEFT- NW 106TH ST TO I-75 (MP34 TO MP39) 6TO10 LANES W/EXP LANES $100
PROJECT LETTINGS > $100M FY 2016-2018
P3
14
MAJOR PROJECTS - PRELIMINARY SCHEDULE
DIST FIN PRJ PRJ DESC Industry Forum Short List Price Proposal Due Date
03 409334-1 Pensacola Bay Bridge Sep-15 Dec-15 Jul-16
06 251688-1 I-395 Oct-15 Nov-15 Aug-16
07 433880-1 Gateway Nov-15 May-15 Sep-16
Florida Department of Transportation
PROJECT LETTINGS - HISTORY/ESTIMATED
Note: These lettings include the Highway and Bridge Programs only, including Resurfacing, Bridges, Roadway, Safety, and Traffic Operations. 0nly Contract Classes 1 (Central Office Let), 7 (District Office Let), and 9 (Design-Build) are included.
Reserves are included for 2016-2018 . The $2.3B D5 I-4 DBFOM contract is shown in 2015; 2006-2015 ARE ACTUALS; 2016-2018 BASED ON DATA AS OF 7/31/15
Note: These lettings include the Highway and Bridge Programs only, including Resurfacing, Bridges, Roadway, Safety, and Traffic Operations. 0nly Contract Classes 1 (Central Office Let), 7 (District Office Let), and 9 (Design-Build) are included.
Reserves are included for 2016-2018 . The $2.3B D5 I-4 DBFOM contract is shown in 2015; 2006-2015 ARE ACTUALS; 2016-2018 BASED ON DATA AS OF 7/31/15
$2.2
$3.1
$3.4
15
Florida Department of Transportation
DESIGN BUILD HOW MUCH ARE WE DOING?
FY OF LETTING
DOLLAR VOLUME IN $M NUMBER OF PROJECTS
DB LETTINGS INCLUDE THESE MAJOR PROJECTS:
Contract Lettings
(Class 1, 7, 9)
Design-Build(Class 9)
% of $M of Projects as DB
Contract Lettings
(Class 1, 7, 9)# of Contracts
# of DB Contracts
% of Number of
Projects as DB
2010ACTUAL
$2,270 $1,060 47% 622 131 21% $551M SR826/SR836; 91 ARRA @ $924M
2011ACTUAL
$1,894 $746 39% 512 70 14%
$72M I-95/SR-9; $84M I-95/EXPRESS/HOT LNS; $94M SR-A1A FLAGLER MEM BR.;
19 ARRA @ $99M
2012ACTUAL
$2,362 $1,091 46% 500 59 12%$215M I-275;
$135M I-4; $149M I-95;
$118M I-95/SR9;
2013 ACTUAL
$2,272 $792 35% 526 56 11%
$83M GANDY BLVD;$98M SR 79 PROJECTS;
$119M US331 CHOCT BAY; $77M SR23;
$96M SR9B PH III;
2014ACTUAL
$2,729 $1,591 58% 545 57 10%INCLUDES 13 PROJECTS >$50M;
$277M SR 826;$403M I-75 ML PROJECTS (6);
2015 ACTUAL
$2,917 $1,242 43% 489 33 7%
DOESN’T INCLUDE THE $2.3B I-4 PROJECT INCLUDES :
D2 - $140M I-295; D4 - $305M SR9/I-95 (3 PROJECTS);
D5 - $205M I-95
2016 PLANNED
$3,083 $808 26% 434 14 3%INCLUDES :
D2 - $295M I-95 (2 PROJECTS);D6 – $125M TAMIAMI TRLTPKE - $134M WDN HEFT
16
Florida Department of Transportation
DESIGN BUILD FOR FY 2016 (JULY 31, 2015 LOCKDOWN PLAN)
DST FIN PRJ PROJECT DESCRIPTION EST $M
1 427315-2 I-4 FROM EAST OF POLK PARKWAY TO OSCEOLA COUNTY LINE $3
1 437082-1 I-75 (SR 93) FROM I-275 INTERCHANGE TO CR 683 MOCASSIN WALLOW $6
2 213323-1 I-95 (SR 9) AT NORTH I-295 INTERCHANGE $170
2 433036-1 I-95 (SR 9) AT I-10 INTERCHANGE OPERATIONAL IMPROVEMENT $125
3 218605-6 SR 10 (US 90A) 9 MILE ROAD FROM CR 99 BEULAH ROAD TO SR 8 (I-10) $19
3 218605-7 SR 10 (US 90A) 9 MILE ROAD FROM SR 8 (I-10) TO SR 297 PINE FOREST RD $4
5 426904-3 I-95 INT @ ST JOHNS HERITAGE PKWY/PALM BAY PK WY N OF MICCO RD $31
5 434484-2 I-4 (SR 400) WEST BOUND REST AREA RECONSTRUCTION IN SEMINOLE COUNTY (NEW FM NUMBER) $7
5 423446-9 CENTRAL FLORIDA COMMUTER RAIL $71
6 434922-1 SR 90/TAMIAMI TRAIL FROM MP 14.038 TO MP 17.230 $125
8 406110-1 I-75/TPK INTCHG MODIFICATION (NORTHERN TERMINUS) (MP 309) $50
8 406110-2 I-75/TURNPIKE INTERCHANGE ( I-75 WIDENING 4 TO 6 LANES, MP 20.8-SR44) $18
8 415051-4 WIDEN HEFT, BIRD RD - SR836(MP23.8-26) (6 TO 10 LANES) INC. EXPRESS LAN $134
8 417545-1 WIDEN SEMINOLE XWAY FROM ALOMA AVE TO SR 434 (MP 38 - 44) (4TO6 LANES) $96
8 435462-1 CONSTRUCTION OF RAMPS FROM CAMPBELL DR TO NB HEFT(TPK SR821) (MP2) $21
17
Florida Department of Transportation
STATEWIDE LETTINGS - LOW BID HISTORY(COMPARISON OF LOW BIDS TO THE LOCKDOWN PLAN ESTIMATES)
SAVINGS IN $M
SAVINGS IN %
18
Florida Department of Transportation
CONSTRUCTION COST AND TIME MANAGEMENT
CONSTRUCTION PERFORMANCE: When projects reach a status of being conditionally, materially, and finally accepted (status 6, 7 or 8), the time and cost changes are determined. They are reported in two methods: 1) simply as what percentage time or cost increases have occurred over the life of the contract, or 2) what percentage contracts have had less than 20% time increases or what percentage contracts have had less than 10% cost increase.
TARGET IS < 20% TIME INCREASE
TARGET IS < 10% COST INCREASE
19
Florida Department of Transportation
CONSTRUCTION PERFORMANCE: When projects reach a status of being conditionally, materially, and finally accepted (status 6, 7 or 8), the time and cost changes are determined. They are reported in two methods: 1) simply as what percentage time or cost increases have occurred over the life of the contract, or 2) what percentage contracts have had less than 20% time increases or what percentage contracts have had less than 10% cost increase.
TARGET IS > 90% OF ALL CONTRACTS WITH < 10% COST INCREASE
TARGET IS > 80% OF ALL CONTRACTS WITH < 20% TIME INCREASE
CONSTRUCTION COST AND TIME MANAGEMENT
20
Florida Department of Transportation
SUMMARY OF PUBLIC-PRIVATE PARTNERSHIP PROJECTS(P3) AS OF APRIL 2015
DISTRICT TYPE PROJECT NUMBER DESCRIPTION EXECUTED TARGET COMPLETION
ESTIMATE$M
UNDER CONTRACT:
D5 DBFOM 432193-1 I-4 ULTIMATE IN ORANGE & SEMINOLE COUNTIES – 21 MILES SEP 14 2021 2300
D3 DBF 220773-9-5D SR 79 (20 MILE) JAN 13 AUG 17 98
D1 DBF 413066-1-5D I-75 NORTH OF SR 80 TO SOUTH OF SR78 (1.6 MILE) SEP 12 FALL 15 72
D2 DBF 209294-9-5D SR 9B EXTENDING FROM US 1 TO I-95 IN DUVAL COUNTY SEP 12 OCT 15 95
D5 DBF 406869-8-5D-01 I-95 FROM SOUTH OF SR 406 TO NORTH OF SR 44 (30 MILE) AUG 12 APR 16 130
D4 DBF 249581-1-52/56 PALMETTO SECTION 5 - SR 826/836 INTERCHANGE NOV 09 JAN 16 566
D1 BF 256881-1-52/82 US 19 FROM WHITNEY ROAD TO S.R. 60 OCT 09 SUMMER 15 120
IN OPERATIONS:
D6 DBFOM 251156-3-52/82 PORT OF MIAMI TUNNEL OCT 09 OPEN NOV 14 667
D4 DBFOM 420809-3-5A/52/8242809-8-52 I-595 IMPROVEMENTS MAR 09 OPEN SEPT 14 1.2B
CONSTRUCTION COMPLETE:
D7 BF 258415-1-5A/52/56 I-4 CONNECTOR BETWEEN I-4 AND THE SR 618 (SELMON EXPWY) JAN 10 OCT 14 429
D6 DBF 249856-4-5A/52/56 US 1 IMPROVEMENTS IN THE “18-MILE STRETCH” FEB 08 FEB 11 114
CONTRACT COMPLETE:
D1 DBF420655-1-5A/52/72420655-2-58421490-7-52
I-75 IN LEE AND COLLIER COUNTIES MAY 07 OCT 11 458
D6 DBF 249035-1-5A/52/56 PALMETTO WIDENING/INTCHG SECTION 2 SEP 08 MAR 12 190
D4 DBF 405506-8-5A/52 I-95 WIDENING/PINEDA CAUSEWAY INTERCHANGE MAR 08 FEB 12 200
D6 DBF 415456-1-5A/52 I-95 EXPRESS LANES PHASE I JAN 08 APR 10 139
21
Florida Department of Transportation
HAVE A GREAT CONVENTION
AND BE SAFE OUT THERE!
PARTNERS IN TRANSPORTATION
22