Top Banner
0 10 20 Miles Introduction The Fish Passage Improvement Project at the Red Bluff Diversion Dam (RBDD) is a celebrated success, completed on schedule and under budget. It resolves a significant impediment to fish migration and provides a reliable water supply to over 150,000 acres of agricultural land in the Sacramento Valley. The project includes a pumping facility and state-of-the-art fish screen to replace operation of the dam. Total project cost is estimated at $200M. The project received wide-spread support from a variety of entities, including local, state, and federal agencies, environmentalists, and water users. The National Marine Fisheries Service’s 2009 Biological Opinion for operation of the Central Valley Project required the RBDD gates to be raised year-round after 2011. The project was “shovel-ready” in 2009 and eligible to receive funding from the American Recovery and Reinvestment Act (ARRA). The project received over $119M from ARRA, representing the largest Department of Interior economic recovery project in the nation. This investment created an estimated 1,200 jobs and protected an additional 6,000 existing jobs. Construction of the project commenced in the spring of 2010 and deliveries began in the spring of 2012. The cooperative effort of the Tehama Colusa Canal Authority, Reclamation, and the State of California was critical in securing adequate funding and achieving the mandated schedule. Successful completion of the project protected the ability to deliver irrigation to 150,000 acres of high-value crops in the Sacramento Valley. TCCA is a Joint Powers Authority comprised of 17 irrigation districts in Tehama, Glenn, Colusa, and Yolo Counties. TCCA operates and maintains the 140-mile Tehama-Colusa and Corning Canal agricultural water supply systems. TCCA provides irrigation to 150,000 acres of agricultural land, over half of which is permanent crops, such as almonds, olives, and grapes. Crops grown in the service area produce over $250 million in crops and contribute over $1 billion to the regional economy annually. September 2008 Who is the Tehama-Colusa Canal Authority? 0 20,000 40,000 60,000 80,000 Acres Crop Type in the TCCA Service Area 1992 1997 2002 2007 Permanent Annuals Fallow/Idle at the Red Bluff Diversion Dam Fish Passage Improvement Project September 2012
4

Fish Passage Improvement Project

Oct 01, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Fish Passage Improvement Project

0 10 20Miles

I n t r o d u c t i o n

The Fish Passage Improvement Project at the Red Bluff Diversion Dam (RBDD) is a celebrated success, completed on schedule and under budget. It resolves a significant impediment to fish migration and provides a reliable water supply to over 150,000 acres of agricultural land in the Sacramento Valley. The project includes a pumping facility and state-of-the-art fish screen to replace operation of the dam. Total project cost is estimated at $200M. The project received wide-spread support from a variety of entities, including local, state, and federal agencies, environmentalists, and water users.

The National Marine Fisheries Service’s 2009 Biological Opinion for operation of the Central Valley Project required the RBDD gates to be raised year-round after 2011. The project was “shovel-ready” in 2009 and eligible to receive funding from the American Recovery and Reinvestment Act (ARRA). The project received over $119M from ARRA, representing the largest Department of Interior economic recovery project in the nation. This investment created an estimated 1,200 jobs and protected an additional 6,000 existing jobs. Construction of the project commenced in the spring of 2010 and deliveries began in the spring of 2012. The cooperative effort of the Tehama Colusa Canal Authority, Reclamation, and the State of California was critical in securing adequate funding and achieving the mandated schedule. Successful completion of the project protected the ability to deliver irrigation to 150,000 acres of high-value crops in the Sacramento Valley.

TCCA is a Joint Powers Authority comprised of 17 irrigation districts in Tehama, Glenn, Colusa, and Yolo Counties.

TCCA operates and maintains the 140-mile Tehama-Colusa and Corning Canal agricultural water supply systems.

TCCA provides irrigation to 150,000 acres of agricultural land, over half of which is permanent crops, such as almonds, olives, and grapes.

Crops grown in the service area produce over $250 million in crops and contribute over $1 billion to the regional economy annually.

September 2008

W h o i s t h e T e h a m a - C o l u s a C a n a l A u t h o r i t y ?

0

20,000

40,000

60,000

80,000

Acr

es

Crop Type in the TCCA Service Area

1992 1997 2002 2007Permanent Annuals Fallow/Idle

at the Red Bluff Diversion Dam

F i s h P a s s a g e I m p r o v e m e n t P r o j e c t

September 2012

Page 2: Fish Passage Improvement Project

T h e P r o b l e m

The RBDD was completed in the mid-1960s. When the

operable gates were lowered, the dam raised the surface

level of the Sacramento River, enabling gravity diversion

into the canals. Fish ladders constructed to allow passage

during dam operation were unreliable and inefficient. As

a result, the RBDD was a significant impediment to adult

and juvenile fish migration. The main species of concern

are winter-and spring-run Chinook salmon, Central

Valley steelhead, and green sturgeon.

After the decline of winter-run Chinook salmon, the

duration of annual gate operations began to steadily

decrease from twelve months to two months. When the

dam gates were raised, the Tehama-Colusa Canal Authority

continued to deliver irrigation water through a series of

short-term fixes, including a Temporary Pumping Plant,

a Research Pumping Plant, seasonal pumps, and Stony

Creek. The diversion capacity from these sources was not

enough to meet year-round irrigation demand.

JUN JUL AUG SEP OCT NOV DECJAN FEB MAYMAR APR

JUN JUL AUG SEP OCT NOV DECJAN FEB MAYMAR APR

1966

1972

1988

1992

1993

1994 - 2008

2009 – 2011

2012

Gates Out

Gates In

PUMPING CAPACITY

Ten-Point Winter-Run Chinook Salmon Restoration Plan implemented

Federal Endangered Species Act

USBR operated RBDD for protection of winter-run Chinook salmon

USBR continued to operate RBDD for protection of winter-run Chinook salmon

1993 Biological Opinion for winter-run Chinook salmon

Gates InPumping Pumping

Agricultural Demand

2009 Biological Opinion for operation of the Central Valley Project

Completion of the Fish Passage Improvement Project

Gates initially lowered into the Sacramento River

A g r i c u l t u r a l D e m a n d C o m p a r e d t o G a t e O p e r a t i o n s a n d P u m p i n g C a p a c i t y a t R B D D

S e l e c t G a t e O p e r a t i o n s a t R e d B l u f f D i v e r s i o n D a m 1 9 6 6 T h r o u g h 2 0 1 2

Page 3: Fish Passage Improvement Project

Project Groundbreaking (March 23, 2010)

Overview of Fish Screen and Forebay Construction (November 2011)

T h e S o l u t i o nThe Fish Passage Improvement Project is the culmination

of over 40 years of efforts by various entities to find

a balanced solution that improves fish passage and

reliability of irrigation water deliveries. Highlights of the

project include:

• Selection of a Project: The selected project included

the construction of a pumping plant near the

existing canal headworks with an initial installed

capacity of 2,000 cfs and a footprint that will allow

expansion to 2,500 cfs.

• Completion of Environmental Review: TCCA

certified the Environmental Impact Report under

the California Environmental Quality Act (CEQA)

on June 4, 2008, and Reclamation signed the Record

of Decision under the National Environmental

Policy Act (NEPA) on July 16, 2008.

• Construction: Construction commenced in spring

2010. The groundbreaking event included, among

others, Secretary of Interior Ken Salazar and former

Governor Arnold Schwarzenegger.

• Operation: The project was completed on schedule

and under budget. The new facility was substantially

complete and began delivering water in May 2012.

Full operation began in summer 2012.

The project received wide-spread support, including letters from the following:• SenatorDianneFeinstein,• SenatorBarbaraBoxer,• CongressmanWallyHerger,• CongressmanMikeThompson,• CongressmanDanLungren,• CongressmanGeorgeMiller,• PacificCoastFederationofFisherman’sAssociations,• CaliforniaTrout,• NaturalResourcesDefenseCouncil,• MetropolitanWaterDistrictofSouthernCalifornia,• StateWaterContractors,• Tehama, Glenn, Colusa, Yolo County Farm Bureaus, and • Tehama, Glenn, Colusa, Yolo County Boards of Supervisors.

Site Plan for the Red Bluff Pumping Plant Forebay

Pumping Plant

Fish ScreenForebay

Red Bluff Diversion DamRed Bluff Diversion Dam

Sacramento RiverSacramento River

Mitigation Site (construction in progress)BridgeBridge

Red Bank CreekRed Bank Creek Pumping Plant

Fish Screen

Page 4: Fish Passage Improvement Project

H a b i t a t M i t i g a t i o nMitigation was required to compensate for unavoidable impacts to wetland and riparian habitats during construction of the fish screen and pumping plant. The mitigation site was selected and designed based on natural side channel habitats on nearby reaches of the Sacramento River. Side channel habitats are important because they increase instream and riparian habitat diversity by providing shaded cover and rearing areas for juvenile fish. Healthy rearing habitat may lead to higher juvenile growth rates, which in turn may improve juvenile fish survival. This is important for sensitive species, notably winter- and spring-run Chinook salmon, Central Valley steelhead, and green sturgeon.

The mitigation includes restoration of 32 acres of native, riparian habitat. Key features include an open-water channel and four native vegetation communities. The open-water channel is designed to maintain year-round connectivity to the Sacramento River. The native vegetation communities include emergent marsh, floodplain herbaceous, willow-riparian scrub, and mixed-riparian forest. Over time, these new communities will mature and connect with the existing habitat along the edges of the site.

The mitigation site is located directly across the river from the Red Bluff Pumping Plant in East Sand Slough (see Site Plan on page 3). Construction of the site commenced in 2012 and it is on-schedule to be complete in 2013.

F o r M o r e I n f o r m a t i o n :Jeff Sutton/TCCA P.O. Box 1025

Willows, CA 95988

530.934.2125

[email protected]

Mitch Butler/Natural Resource Results, LLC 1455 Pennsylvania Avenue, NW, Suite 400

Washington, DC 20004

202.280.6382

[email protected]

Mike Urkov/NewFields 2020LStreet,Suite110

Sacramento, CA 95811

916.265.6331

[email protected]

Project Background: Red Bluff Diversion Dam

was completed in 1964 as a part of the Sacramento

Canals Unit of the Central Valley Project (CVP).

The fish passage problem at RBDD was addressed

in the Central Valley Project Improvement Act of

1992 - Public Law 102-575, Title 32 (CVPIA).

Specifically, Section 3406(b)(10) authorizes and

directs the Secretary of the Interior to develop

and implement measures to minimize fish passage

problems for adult and juvenile anadromous fish

at the Red Bluff Diversion Dam. The Fish Passage

Improvement Project at the Red Bluff Diversion

Dam was developed to respond to this federal

directive. The RBDD is owned by the U.S. Bureau

of Reclamation and operated and maintained

by the TCCA.Overview of Construction at the Mitigation Site (June 2012)