PRODUCTION TECHNOLOGY GROUP PROJECT FIELD DEVELOPMENT OPTIONS - CURTIN OFFSHORE FIELD STUDENTS: AARON ANTHONY (14290345), YINGHSUAN HSIEH (15373438), MOHAK BHANDARI (15632906), DAWEI PAN (15350428), CHRIS RAYNER (4304246), MILENA RADIC (14059740) DUE DATE: 3RD OF NOVEMBER, 2014 UNDERGRADUATE PROJECT - 2014
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
PRODUCTION TECHNOLOGY GROUP PROJECT
FIELD DEVELOPMENT OPTIONS - CURTIN OFFSHORE FIELD
STUDENTS: AARON ANTHONY (14290345), YINGHSUAN HSIEH (15373438), MOHAK BHANDARI (15632906), DAWEI PAN (15350428), CHRIS RAYNER (4304246), MILENA RADIC (14059740)
Based on the mentioned issues and concerns that are presented above, the final selection of
equipment and completions strategy is as follows:
1. Vertical well drilled directly into the center of the J18. TD = 4370m
2. The hole will be Cased and Cemented with the top 35feet of J18 being perforated.
(see Figure 3)
3. A single tubing of size ID=3.068in and OD =3.5in will be used. (This choice will be
explained later in the report)
4. Further down hole equipment will be installed to monitor the well and give
options intervention and for EOR at later date. (see Figure 20 & 21)
Figure 5: Sketch of reservoir intervals
17 | P a g e
3.0 Perforation intervals and Location The sketch above shows that in J-16, the overlaying gas is 85ft thick on top and the oil layer has
a thickness of only 15ft at bottom. For this thin oil layer, it is quite difficult to consider economical
production. For instance, due to the oil layer being thin, the production rate would be very low.
So in order to increasing the production rate, the well needs to be deviated or even horizontally
inclined to increase the contact surface of the oil layer and well. As a result of this, gas coning is
likely to take place. The prevention or shut-off methods for gas coning should also be devised at
an early stage in order to reduce the need for expensive well intervention activities. As producing
oil from J-16 is deemed to be uneconomical, the decision was made to drill J-18 straight.
As the top of reservoir J-18 is 4330ft TVDSS, the mid depth of the perforations would be at 4345ft
TVDSS (15ft below top of J-18). To calculate the production index, the assumptions made for the
reservoir J-18 are as follows:
Perforation Height = 30ft Permeability = 100mD Oil Viscosity = 1.2cP Oil Formation Volume Factor = 1.3rb/stb Rw = 16/2 = 8in = 0.667ft (Production Casing) Area of J-18 is same as J-16 = 2200 Acres So, Re = 5523ft (assume radial flow) Skin = 0
As there is water support for the reservoir, the steady-state formula for calculating production
index is chosen,
𝑃𝐼 =0.007082𝑘ℎ
μ𝐵𝑜(ln𝑅𝑒
𝑅𝑤−12)
Therefore the calculated 𝑃𝐼 ≈ 1.6𝑠𝑡𝑏/𝑝𝑠𝑖.
By applying Vogel method, the data for IPR curve can be calculated. This was done assuming
the initial reservoir pressure is 2000psig and a bubble point pressure of 2000psig.
18 | P a g e
3.1 IPR curve for J18
Figure 6: IPR Curve for J18
The IPR curve above indicates the relationship between the inflow production rate and the
bottom hole flowing pressure based on the assumption currently made for the reservoir. From
the chart, the AOF for this reservoir is around 1780 stb/d.
But this curve also has its limits. As the bubble point pressure is not given, and has been assumed
to be 2000psig, there will be no straight- line section on this IPR curve acting as the oil reservoir
depletion performance does not exist above bubble point pressure. So, if the bubble point
pressure is assumed to be a different value, it will give a different IPR curve plotting.
19 | P a g e
3.2 Selection of Optimum Tubing Sizes
Selection of the optimum tubing inner Diameter (ID) is critical to the success of oil production.
The tubing selection is based on the Sensitivity analysis required through the concept of the
Nodal Analysis. The selected tubing should not only fit for the current situation but should also
be good enough to perform for a considerable period. The effect of Gas Oil Rate (GOR), Water
Cut (W-Cut) & Well Head Pressure (P-Out) have been assessed using the computer design
program Pipesim® to give the optimal selection of the tubing.
To complete the sensitivity studies, additional assumptions are required for the estimation.
Based on the assumptions already made in the previous section, the extra assumption would be:
1. Oil Gravity = 35 API
2. Reservoir Temperature = 200F
3. Reservoir Water Salinity = 60000 ppm (S.G. 1.02)
4. H2S content = 10-20ppm
5. CO2 = 0.1%
6. Packer location: 4320ft TVDSS
7. Soil Temperature (surface temperature) = 25degC
8. Initial Well head Pressure = 200psig
9. Initial GOR = 400scf/stb
10. Initial Water Cut = 0%
11. For stimulation, Tubing size chosen are only based on catalogue of API. Tubing
size are as following.
20 | P a g e
12. Tubing Size
OD(in) ID(in) OD(in) ID(in)
1.05 0.824
2.875
2.195
1.315 1.049 2.259
1.66 1.38 2.323
1.41 2.441
1.9 1.61
3.5
2.75
1.65 2.922
2.375
1.703 2.992
1.867 3.068
1.995 4
3.476
2.041 3.548
4.5 3.958
Figure 7: Standard Tubing Sizes
21 | P a g e
4.0 Analysis of Tubing sizes
4.1 Nodal Analysis - Tubing Size The plot for varying tubing sizes are shown below:
Figure 8: Nodal Analysis Tubing Sizes 0.824” to 1.995’’ ID
22 | P a g e
From the analysis, it can be figured out that with the increasing of the tubing size, the operating production
rate increase, and the operating production pressure decrease, due to more fluid requires higher pressure
difference of bottom hole and well head to be lifted up. The minimum stable point is shifting to bottom
right with the tubing size increasing. As the tubing size be up to 3.958in ID, it becomes difficult to recognize
a minimum stable point on the VLP plotting. So if operating with this tubing size, the production will become
unstable and may cause serious problems.
Figure 9: Nodal Analysis Tubing 2.041’’ to 3.958’’
As for choosing the right tubing size for the production, it should not only fit the current situation, but
also need to give relative good production rates for a considerable period of time. Over a long-term period
of production, the reservoir conditions will change, such as a drop in the reservoir pressure; increase in
water cut and increase in gas oil ratio.
Sensitivity studies were carried out for different tubing sizes, different water cuts, GORs and wellhead
pressure conditions. The data and plotting provided are based on “system analysis” and “nodal analysis”
in the pipesim program. The overall analysis for the different tubing sizes was done first, and then 3
particular tubing sizes were chosen to do the nodal analysis. Only the recommend tubing size nodal
analysis will be shown here. The nodal analysis for the other two tubing size will be in included in the
appendix.
23 | P a g e
4.2 Overall Analysis
4.2.1 GOR analysis For GOR analysis, the water cut value is assumed to be 0% and wellhead pressure is assumed to
be 200psig.
Figure 10: Liquid production rate vs Tubing Size with changing GOR
In the plot above, the x-axis represents the different tubing sizes (inch for ID) and the y-axis
represents liquid production rate (stb/d). The different data curves represent different GOR
values (scf/bbl). The GOR values picked were from 400scf/bbl as the initial value, then increasing
by a factor of 2 each time until a value of 25600scf/bbl was reached. In this way, a large range of
GOR values can be covered in the estimation. It can be recognized that for most of the tubing
sizes, an increase in the GOR value results in an initial increase in the production rate then a
decrease. By the system calculations, as the GOR value increases up to 25600 scf/bbl, the
production is mostly gas under stock-tank condition. This is proved by the fact that 80.77713%
mass flow will be gas. So, this condition can be regarded as an extreme condition to be the upper
limit for GOR value that an oil production can handle. In order to handle a wide range of GOR
values with a relative high production rate, the Tubing size (ID) value is recommend to be over
2.992in. Larger tubing size provided more liquid production.
24 | P a g e
4.2.2 Wellhead Pressure Analysis
For wellhead pressure analysis, the GOR value is assumed to be 0scf/bbl and water cut value is
assumed to be 0%.
Figure 11: Liquid production rate vs Tubing Size with changing Wellhead Pressure
In this plot, the x-axis represents different tubing sizes (inch for ID) and the y-axis represents
changing liquid production rates (stb/d). The different data curves represent changing wellhead
pressures (psig). As the minimum allowable pressure is 200psig, the analyzed pressure range was
from 200psig to 650psig, with a step size of 50psig.
It is easy to observe that with the increasing of the wellhead pressure, the production rate for
each tubing size decreases. The curve for each wellhead pressure indicates that, with the
increasing of the tubing size, the production rate first increases fast, and then the increasing rate
gradually declines. Each curves has a sharp increase at the start before achieving a constant rate.
The end points for the curves of well head pressure 550psig, 600psig and 650psig means that
there will be no stable production at that particular well head pressure with larger tubing ID sizes.
Therefore the recommended range of tubing sizes suitable for long-term production would be
above 2.195in for ID. Larger tubing size gives higher production rate but is not compatible with
high wellhead pressure.
25 | P a g e
4.2.3 Water Cut analysis For water cut analysis, the GOR value is assumed to be 0scf/bbl and wellhead pressure is
assumed to be 200psig.
Figure 12: Liquid production rate vs Tubing Size with changing Water Cut
In this plot, the x-axis represents different tubing sizes (inch for ID) and the y-axis represents different liquid
production rates (stb/d). The different data curves represent different WC values (%). The water cut range
is from 0% to 80%. As shown in the plot, with the increase in water cut, the liquid production rate decreases
for each tubing size. When the water cut reaches up to 80%, the system cannot gives a estimated
production value for tubing size over ID 2.75in, which means there is no stable production rate obtainable.
As the data curve for each WC value sharply increases at start and becomes more and more flat, the
recommended tubing size would be between 2.441in to 3.548in ID. Larger tubing sizes generally gives
higher production rate at low water cut, but this advantage gradually disappears and the production rate
even decreases with increasing tubing size at higher water cuts. Larger tubing sizes also cannot handle high
WC.
26 | P a g e
For the overall analysis above, the recommendation will be:
Figure 13: Summary of optimum tubing size ranges for changing GOR, Wellhead Pressure and
Water Cut
The chosen tubing sizes for nodal analysis are 2.992in 3.068in and 3.476in ID.
On comparison of the tubing sizes of 2.992in and 3.068in for changing GOR, well head pressure and water cuts, the 3.068in tubing will provides slightly higher production rate in all conditions.
When comparing a tubing size of 3.068in and 3.548in, 3.548in tubing can provide higher production rate compared to 3.068in tubing when in good condition at the start of production life for the well.
Though, for the changing GOR plots, the 3.548in tubing has a better capacity for handling high GOR value, but J-18 does not have gas cap and the aquifer influx is strong hence the GOR value is not expected to be that high.
For the changing water cut and wellhead pressure plots, the production advantage gradually disappears as the wellhead pressure increases or the water cut increases.
For well head pressure plot, the curve for 600psig well head pressure ends at tubing size of 3.068in, which means the 3.548in tubing will not have a stable production rate at the well head pressure of 600pisg.
For the water cut plot, the production rate for 3.548in tubing eventually becomes less than the production rate for 3.068in tubing. This relates to a required long production period, which means the production period turns into a relative undesired situation, leading to water cut increasing and reservoir pressure decreasing over time.
The 3.086in tubing will be sufficient to handle the production flow and provide a relatively good production rate compared to using 3.548in tubing in completion strategy. In regards to planning for long-term production, 3.068in tubing is more suitable than 3.548in tubing.
The recommended tubing size for completion is therefore 3.068in ID with 3.5in OD.
Recommendation
Analysis Tubing size (ID)
GOR 2.992in - 3.548in
W-head P 2.195in - 3.548in
WC 2.441in - 3.548in
27 | P a g e
4.3 Nodal Analysis For Tubing Size 3.068inch ID
4.3.1 Well Head Pressure Analysis
Figure 14: Nodal Analysis for 3.068 in tubing size
28 | P a g e
The nodal analysis for varying wellhead pressures can be used to indicate how much the reservoir
pressure drop can be tolerated under the assumption made before. As the wellhead pressure
increases, the VLP plot shifts up for the same amount each time (50psig). For reservoir pressure
of 2000psig, the maximum wellhead pressure that is able to give stable production is 600psig for
this size of production tubing. So, this means a minimum pressure difference of 2000 − 600 =
1400𝑝𝑠𝑖𝑔 required to give a stable production. Therefore, if the well head pressure is the
minimum allowable value of 200psig, the minimum reservoir pressure required to give stable
production is 1600psig. So, the allowable reservoir pressure drop for this tubing size is
2000 − 1600 = 400𝑝𝑠𝑖
So, if the reservoir pressure drop becomes more than 400psi, there will be a loss of stable
production and a smaller ID production tubing size is required.
W-head P
(psig)
Stock-tank liquid
at nodal point
(STB/d)
Pressure at nodal
analysis point (psi)
200 1443.781 750.9319
250 1373.937 844.67
300 1293.566 943.46
350 1201.696 1047.2
400 1096.339 1156.786
450 983.4195 1265.465
500 868.4639 1368.625
550 745.0333 1472.525
600 620.9713 1570.994
Figure 15: Values used in Nodal Analysis
29 | P a g e
4.3.2 GOR Analysis
Figure 16: Values used in Nodal Analysis with changing GOR
30 | P a g e
From the plot and the table below, it can be seen that the production rate will increase initially
then start decreasing with an increase in GOR. In this analysis it can be seen that the initial GOR
of 400scf/bbl results in a production rate of 1443.781stb/d, but a GOR of 3200scf/bbl can give a
production rate of 1557.381stb/d, an increase of more than 100stb. So, in order to increase the
production rate, gas lift is recommended.
The thick black line in Fig 16 is drawn to estimate the change of the IPR curve due to the maximum
reservoir pressure drop (400psi) during production. The operation point with maximum
production rate is still with a GOR value of 3200scf/bbl. So, the gas lift is recommended to
maintain the GOR value to be around 3200scf/bbl to obtain the maximum production rate.
Figure 17: Data from Nodal analysis with changing GOR
GOR
(scf/bbl)
Stock-tank liquid at
nodal point (STB/d)
Pressure at nodal
analysis point (psi)
400 1443.781 750.9319
800 1525.334 628.9187
1600 1551.445 586.0987
3200 1557.381 576.0551
6400 1528.732 623.4655
12800 1434.908 763.3221
25600 1199.437 1049.647
31 | P a g e
4.3.3 Water Cut Analysis
Figure 18: Plot of Nodal analysis with changing Water Cut
32 | P a g e
WC (%)
Stock-tank liquid
at nodal point
(STB/d)
Pressure at nodal
analysis point (psi)
Oil Production
Rate (STB/d)
0 1443.781 750.9319 1443.781
10 1407.372 800.8413 1266.6348
20 1360.852 861.352 1088.6816
30 1301.122 934.5234 910.7854
40 1221.548 1025.499 732.9288
50 1114.037 1138.982 557.0185
60 963.1363 1284.171 385.25452
70 762.4047 1458.285 228.72141
Figure 19: Data from Nodal analysis with changing Water Cut
For the water cut analysis, it can be seen from Fig 18 that the production rate decreases as the
water cut increases. This is due to the difference in densities between water and oil. An increase
in water cut, corresponds with an increase in production fluid density. So, the denser the fluid,
the greater the required pressure difference needed to lift up the fluids to the surface. This then
corresponds with a decrease in production rate. Another potential issue caused by increasing
water cut is liquid hold up where the lighter phase is unable to push past the much denser fluid.
The black line is used to indicate the new IPR curve corresponding to a maximum reservoir
pressure drop (400psi) as a result of production. From Fig 18, it can be seen that this curve does
not intercept with the VLP curves corresponding to Water Cuts of 60%, 70% and 80%. The original
IPR curve however intercepts all the VLP curves except the one corresponding to 80% WC. This
means that the capacity of handling water cut is decreasing with a decrease in reservoir pressure
during production. So, in order to make it safe, the water shut off method should to be executed
at a water cut of 50%.
33 | P a g e
4.4 Nodal Analysis Conclusion Based on the assumptions and analysis above,
The recommended production tubing size is 3.068in ID and 3.5in OD. The maximum allowable reservoir pressure drop is 400psi. As the initial GOR value is 400scf/bbl, gas lift equipment should be used to increase the
GOR to around 3200scf/bbl in order to achieve maximum production rate. The water shut off method needs to be executed at a water cut of 50%.
34 | P a g e
5.0 Final Completion Design
The final Design is as follows:
Cased Cement well bore drilled to a depth of 4400 ft SS
Single Tubing of size 3.5 “ OD run to a depth of 4265 ft SS
Sub surface completions equipment of Packers and Mandrels, SSSV
Figure 20: Final Completion Design
Equipment Piece Function Justification Approx. Depth (SSft)
Casing – API sizes Provide Well integrity, and isolation from non-producing formations.
Requirement to provide safety and ensure hole integrity
4330
Completion Tubing Provide Pathway for HC
Needed to connect BH to surface equipment.
4370
Permeant Packer Isolate production Zone
Protect upper Casing, Direct flow to tubing, Isolate pressure