Top Banner
# Via Nordica 2012, reykjavik Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen, COWI A/S 1 Via Nordica 2012 - Fehmarnbelt Bridge
61

Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

Sep 17, 2018

Download

Documents

lenga
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Via Nordica 2012, reykjavik

Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design

Henrik Elgaard Jensen, COWI A/S

1 Via Nordica 2012 - Fehmarnbelt Bridge

Page 2: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

Content of the presentation

1. Situation at start of 2011

2. Concept Design October 2010

3. Approach Bridges

4. Main Bridge

5. Risk studies and safety aspects

6. Planning of construction

7. Main construction cost and manpower resources

8. Expected project development

2 Via Nordica 2012 - Fehmarnbelt Bridge

Page 3: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

1. Situation at start of 2011

Design started April 2009 with reference to treaty DK – D (09/2008)

Concept designs for tunnel und bridge completed

Environmental data collection (2 years) are concluded

Preliminary environmental evaluation available

Evaluation of all results leads to the recommendation by Femern A/S to Transport Minister: > Immersed Tunnel

Information meetings in Germany and Denmark during January

Transport Minister/Trafikudvalg to comment on recommendation at start of February

Recommendation Immersed Tunnel confirmed on 1st February

The preferred solution is now the Immersed Tunnel and the alternative solution the Cable Stayed Bridge

3 Via Nordica 2012 - Fehmarnbelt Bridge

Page 4: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

2. Concept Design October 2010

4 Via Nordica 2012 - Fehmarnbelt Bridge

The design was developed in the following steps:

1. Data collection and basis for design

2. Investigations of options

3. Preliminary concept designs

4. Concept Design March 2010

5. Revised Concept Design July 2010 (Variant 1) including options

6. Final Concept Design October 2010 (Variant 2)

7. Harmonisation between tunnel and bridge

8. Completion of Safety Concept development

9. Preliminary evaluation of environmental impacts

Page 5: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

Location and impor-tance of Fixed Link

Connection rated as important TEN-T project by EU

Main railway connection to Scandinavia (Sweden)

Railway capacity for heavy goods will reach limits soon (old Lillebælt bridge)

Railway link Helsingør-Helsingborg (HH) in future required

Bottle necks: DK: Storstrømsbroen D: Fehmarnsundbridge; B 207 widened (A1 only up to Heiligenhafen)

5 Via Nordica 2012 - Fehmarnbelt Bridge

HH

Page 6: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

6 Via Nordica 2012 - Fehmarnbelt Bridge

Peninsula Fehmarn 580 m Approach bridge Fehmarn 5,748 m Main bridge 2,414 m Approach bridge Lolland 9,412 m Peninsula Lolland 450 m

Page 7: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Preferred corridor for connection

Corridor as result of spatial resistance investigations and of connection between possible landing points on Fehmarn (4) and Lolland (4) Red connection is the chosen route for the bridge in the preferred corridor

7 Via Nordica 2012 - Fehmarnbelt Bridge

Page 8: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

Main challenges – besides Design Basis development, general risk studies and identification of optimal foundation concepts – were:

Investigation of corridor/route and alignment

Navigation in Fehmarnbelt - Safety of bridge structures - Size, number and arrangement of navigation channel(s)

Operational risk analysis (ORA)

Negligible changes to water flow in Fehmarnbelt

Optimization of approach bridges (girders and piers)

Concept development for cable stayed and suspension bridge

Erection concept for approach bridge and main bridge including time plan and cost estimate

8 Via Nordica 2012 - Fehmarnbelt Bridge

Main requirements to Concept Design

Page 9: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Foundation locations

Area of ground improvement: Approach bridge Fehmarn + Main bridge

9 Via Nordica 2012 - Fehmarnbelt Bridge

Improvement area

Page 10: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

Ground improvement alternatives

1. Deep Cement Mixing (Japanese method)

2. Steel pile inclusions a) driven or vibrated steel piles b) concrete pile inclusions (''bored pile type'')

10 Via Nordica 2012 - Fehmarnbelt Bridge

Steel piles Ø 2m

Page 11: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

Ground improvement with concrete pile inclusions

NEW IMAGE

11 Via Nordica 2012 - Fehmarnbelt Bridge

Typical caisson 24m x 30m

Concrete pile inclusion:

1. construction method similar to bored pile with casing of varying length depending on soil conditions, e.g. shorter in Palaeogene Clay and longer in other layers

2. construction sequence changed to first dredging, then ground improvement

Page 12: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Environmental impact considerations

Main view points are:

1. Impact on water exchange with eastern Baltic Sea

2. Permanent loss of foundation areas (marine growth compensates ?)

3. Disturbance of harbour porpoise (marsvin) population in German FHH-Area

4. Impact on bird migration across bridge (barrier effect)

5. Increased danger of spill of oil or chemicals (collision of ships)

6. CO2 emission during construction and operation

Preliminary evaluation results:

>> Bridge acceptable seen environmental-technically

>> Bridge may be difficult seen environmental-legally

12 Via Nordica 2012 - Fehmarnbelt Bridge

Page 13: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Water exchange through Fehmarnbelt

Exchange between North Sea and Baltic Sea uses Lille Bælt (10%), Store Bælt (60%) and Øresund (30%)

Ingress of salty water important; acceptable are 0.1 to 0.2% reduction (changes due to climate changes ca. 10 times larger!)

13 Via Nordica 2012 - Fehmarnbelt Bridge 13

Darsser Schwelle

Page 14: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Impact areas in Fehmarnbelt (footprint)

14 14 Via Nordica 2012 - Fehmarnbelt Bridge

Impact at coast with temporary construction harbours

Impact in the Belt area of main bridge

Grey area = temporary

Red area = permanent

Page 15: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

15 Via Nordica 2012 - Fehmarnbelt Bridge

Possible compensation for permanent impacts

West Bridge, pier 52 East Bridge, western pylon Area for marine growth substantially larger than area covered by bridge ! > Marine growth on piers future feeding ground for harbour porpoises.

Page 16: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

16 Via Nordica 2012 - Fehmarnbelt Bridge

Protected areas in Fehmarnbelt neighbourhood

Eider duck

Marsvin

Page 17: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Risk for ship accidents per year (index figures)

0

10

20

30

40

50

60

70

80

90

100

Refe

ren

ce

sc

en

ari

o

Refe

ren

ce

wit

h V

TS

Bri

dg

e w

ith

VT

S

The Link structure

Grounding and wind parks

Ship - Ship

Source: Risk assessment results for variations in reference scenario, 7. January 2011

17 Via Nordica 2012 - Fehmarnbelt Bridge

VTS system reduces total risk substantially!

Page 18: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

18 Via Nordica 2012 - Fehmarnbelt Bridge

CO2 emission from bridge construction

0

500

1.000

1.500

2.000

2.500

B1 B2 B3 B4

CO2 emissions from construction - Bridge (1000 ton)

Concrete ( mix 110, 210 and 500) Steel Asphalt External transport Internal transport Machinery Electricity construction

Variation of specific material emissions

B1: steel low; cement low

B2: steel high; cement low

B3: steel high; cement high

B4: steel average; cement low

Page 19: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

3. Approach Bridges

19 Via Nordica 2012 - Fehmarnbelt Bridge

Approach bridge Fehmarn 5,748 m Approach bridge Lolland 9,412 m

Page 20: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Einfügen von ganzseitigen Bildern und Grafiken

(NICHT für Text geeignet)

Bridge section

4 lanes, 2 side lanes, 2 tracks Width roadway 22.1 m Width deck 23.1 m Depth of girder 12.9 m

20 Via Nordica 2012

- Fehmar

nbelt Bridge

Page 21: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Improvement of water flow

Joint moved to +4 m and shaft now continuous

Piers and pylons (1999) with section change to caissons at -2 m > local vortices developed!

21 Via Nordica 2012 - Fehmarnbelt Bridge

Page 22: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Pier arrangement (standard piers)

22 Via Nordica 2012 - Fehmarnbelt Bridge

• Pier type II; 185 MN collision load

• Caisson up to + 4m

• Pier shaft from + 4m

• Weights: Caisson max 8,200t Shaft max 4,400t

Page 23: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Girder cross section approach bridge

Concrete deck road 22.1m wide

Depth 12.9m

Diagonals at every 20.0m

Track area 12.2 m wide

Depth bottom chord 2.2 to 2.5m (accessible)

Dehumidification system incl. diagonals

Windshields

23 Via Nordica 2012 - Fehmarnbelt Bridge

Page 24: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Ship collision with approach bridge pier - model

24 Via Nordica 2012 - Fehmarnbelt Bridge 24

Global IBDAS model for bridge

Local ABAQUS model for pier

HOB collision 20,000 DWT ship v= 5.1 m/sec (185 MN)

Page 25: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Peninsula and landing on Fehmarn

25 Via Nordica 2012 - Fehmarnbelt Bridge 25

Page 26: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Peninsula and landing on Lolland

26 Via Nordica 2012 - Fehmarnbelt Bridge 26

Page 27: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

4. Main Bridge (Cable stayed bridge)

Spans: 201 – 282 – 724 – 724 – 282 – 201m Total length: 2,414m

27 Via Nordica 2012 - Fehmarnbelt Bridge 27

Page 28: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

28 Via Nordica 2012 - Fehmarnbelt Bridge

Overview of Main Bridge

Vertical navigation clearance 65.0m plus 1.2m reserve for climate change

HOB collision forces: pylons 790 MN, piers 540 MN

Rectangular crossing of T-route (axis centre pylon = T-route)

High point roadway +82.2 m, railway +72.3m

Page 29: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

29 Via Nordica 2012 - Fehmarnbelt Bridge

Overview of pylons

Centre pylon Outer pylon

Page 30: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

30 Via Nordica 2012 - Fehmarnbelt Bridge

Pylon caissons

Centre pylon

cylindrical shape, diameter 74m

water filled

Outer pylon

elliptical shape, axis 94m/54m

sand filling

Page 31: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Einfügen von ganzseitigen Bildern und Grafiken

(NICHT für Text geeignet)

Cable stayed bridge Main spans 724 m Pylon height 272 m

31 Via Nordica 2012

- Fehmar

nbelt Bridge

Page 32: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Girder cross section main bridge

- Top and bottom chord accessible - Dehumidification arrangement for whole section incl. diagonals - Diagonals to introduce cable forces - Wind shields

32 Via Nordica 2012 - Fehmarnbelt Bridge

Lower joint

Diagonal

Uper joint Roadway deckUpper chord

Railway deck

Page 33: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

Deformation criteria for girder

Crit 1: Maximal deformation and inclination of main bridge

Crit 4: Maximal vertical movement at joints

Crit 7: Maximal rotation at joints (vertical plane)

Crit 8: Maximal rotation at joints (horizontal plane)

Crit 9: Maximal transverse slope for tracks and roadway

Crit 10: Maximal gradient of change of slope

Criteria 2, 3, 5 and 6 are not governing for the main bridge.

> All criteria are fulfilled.

33 Via Nordica 2012 - Fehmarnbelt Bridge

Page 34: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

Collision protection for piers close to T-route

34 Via Nordica 2012 - Fehmarnbelt Bridge

Anchor- and transition piers of main bridge; totally 4 piers; 540 MN impact

Page 35: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

Details of protection structure

35 Via Nordica 2012 - Fehmarnbelt Bridge

Page 36: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

36 36 Via Nordica 2012 - Fehmarnbelt Bridge

Study of impact load capacity

ABAQUS model for basic shear strength of 100 kPa

Steel piles for ground improvement required: pattern 5.0m and 7.5m

Requirement: 540 MN impact load Result: 250 kPa needed

Page 37: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Options for Suspension Bridges

37 Via Nordica 2012 - Fehmarnbelt Bridge

Suspension bridge with two spans of 1,104 m; Length 3,240 m

Suspension bridge with one span of 1,632 m; Length 3,096 m

Cons: Deformation of suspension bridge at limits (> 7m) Resistance to water exchange not known yet Longer construction time and higher costs for main bridge

Page 38: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Animation of Suspension Bridge

38 Via Nordica 2012 - Fehmarnbelt Bridge

Suspension bridge with 1,632m span

Page 39: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

5. Risk Studies and Safety Aspects

39 Via Nordica 2012 - Fehmarnbelt Bridge 39

ALARP approach to be applied with precedents principle Varying benchmarks for roadway and fixed benchmark for railway

High risk

The acceptability of risk to users and disruption of the link shall be guided risk associated with comparable infrastructure (precedents principle).

ALARP region

The risk can only be tolerated if cost of risk reduction would exceed the improvements gained. This implies that risk mitigation/alleviating measures complying with a marginal increase in total expected

societal benefit shall be introduced.

Broadly acceptable region Negligible risk

Evidently negligible risks will be evaluated based on qualitative assessment.

Page 40: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Basis for Operational Risk Analysis (ORA)

40 Via Nordica 2012 - Fehmarnbelt Bridge 40

Operational risk assessment covers: Coast-to-coast section Landside sections coast Denmark to toll station coast Germany to neutral section

• Personal risk to the users of the Link, i.e.

– Railway users

– Road users

• Personal risk to third party, primarily on ship traffic passing the bridge

• Personal risk to operation and maintenance personnel

• Risk of damage to Link and user property

• Risk of traffic disruption and disturbance

• Risk of economic loss to third party, primarily the ship traffic passing the bridge

• Risk to the environment from accidents during operation

Page 41: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Risk categories and main hazards

41 Via Nordica 2012 - Fehmarnbelt Bridge 41

Hazard types to be considered are:

Train accidents Road accidents Aircraft accidents Ship accidents Fires Explosions Dangerous releases Natural hazards Malicious damage Operation & Maintenance

Risk Category Risk Measure

1 Individual risk road, user Fatalities/passage

2 Individual risk rail, user Fatalities/passage

3 Third party risk Fatalities/Year

4 Societal risk (composed of 1+2+3) Fatalities/Year, F-N representation

5 Maintenance/Inspection personnel Qualitative assessment

6 Risk of disruption, road-rail Days/Year, F-N representation

7 Environmental risk EUR/year

Page 42: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

42 Via Nordica 2012 - Fehmarnbelt Bridge

Route Name 2018 2038

H eg 6,689 10,609

T eg 1,418 2,303

K-O eg 23,491 36,392

Coastal eg 613 847

Coastal wg 474 638

T wg 35,044 53,833

Rødby 279 317

Puttgarden 159 180

Grand Total 66,168 105,118

Presently in addition 38,000 ferry passages per year

Ship traffic through Fehmarnbelt

Page 43: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

Risk of disruption due to ship collision

43 Via Nordica 2012 - Fehmarnbelt Bridge

• Disruption risk

2038:

Risk comparable to

Øresund Bridge

• Design for larger

ship collision loads:

- Pylons 790 MN

- Piers 540 (I), 185

(II, III) and 120

(IV) MN

- Girder 44 MN

Frequency scale 1/10,000 a

Length scale 5 km

Pier

Girder

54,42

54,47

54,52

54,57

54,62

11,17 11,22 11,27 11,32 11,37 11,42 11,47 11,52 11,57 11,62

Pier: 11,8 per 10,000 years

Girder: 2,6 per 10,000 years

Total: 14,4 per 10,000 years

Disruptions (>100 days)

Page 44: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Simulations of passages at FORCE Institute

44 44 Via Nordica 2012 - Fehmarnbelt Bridge

- Simulation of passages underneath

the bridge under conditions representing reality (varying sea state, wind, visibility, traffic etc.) as much as possible - Performed by pilots and captains from the merchant marine - Concluding evaluation

Cable stayed bridge

Suspension bridge

Page 45: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Safety Concept

The Safety Concept is developed in collaboration with the organisations involved in emergency situations in Denmark and Germany

The involved organisations are: Police Fire brigade Emergency doctors Ambulance service Special forces for handling accidents with dangerous goods

Several discussion rounds have taken place and a final version of the Safety Concept (document in 3 languages) is expected to be available in Mai 2011

Space requirements for emergency case handling are combined and coordinated with the toll station in Denmark (custom and border control) and the border control area in Germany

45 45 Via Nordica 2012 - Fehmarnbelt Bridge

Page 46: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

Main safety feature for operation

External staircase every 400m at both sides including elevator

46 Via Nordica 2012 - Fehmarnbelt Bridge

Page 47: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Preparations for operation and self-rescue

47 47 Via Nordica 2012 - Fehmarnbelt Bridge

Page 48: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Scenario: train catches fire – rescue steps

48 48 Via Nordica 2012 - Fehmarnbelt Bridge

Page 49: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Provisions for operation, maintenance and rescue

49 49 Via Nordica 2012 - Fehmarnbelt Bridge

Page 50: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

6. Planning of Construction

Major assumptions for the construction planning:

5 main contracts Landworks Fehmarn + Peninsula [< 2·109 USD] Substructure of approach bridges Superstructure of approach bridges Main bridge (cable stayed bridge) Landworks Lolland + Peninsula

Further contracts will cover railway structures, technical installations, toll station (Lolland), visitor centre, etc.

Cost estimate to be prepared as contractor will do, e.g. identify optimal sequence of activities and find efficient, low cost production facilities

Temporary construction harbours and pre-fabrication yards to be included

50 Via Nordica 2012 - Fehmarnbelt Bridge

Page 51: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

Consequences of major assumptions

Prefabrication of bridge elements to largest possible extent results in: Approach bridge - Prefabricate piers comprising shaft and caisson as 1 piece or 2 elements - Assemble composite girder in full length, float it in on barge and erect it Main bridge - Prefabricate pylon caissons and float them in - Construction of pylons on top of caisson in-situ - Assembly of 20m long segments and erection in free cantilevering method

Prefabrication of elements is deemed to be cost/risk/time optimal for: Approach bridge - Caisson and pier shaft in Poland - Steel structure 1. step in China + sea transport; assembly and deck concreting in Poland Main bridge - Caissons in dry dock and in Fehmarn Belt - Steel structure 1. step in China + sea transport; assembly for erection in Poland

51 Via Nordica 2012 - Fehmarnbelt Bridge

Page 52: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

Prefabrication of approach bridge elements

Caissons and pier shafts Transport of steel parts

Temporary harbour at coast Assembly of superstructures

52 Via Nordica 2012 - Fehmarnbelt Bridge

Page 53: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

HLV 'Svanen'

53 Via Nordica 2012 - Fehmarnbelt Bridge

• Self-propelled double-pontoon

floating crane for transport and

erection of bridge elements

• Lifting capacity 8,700 t

• Length 102.8 m

• Width 71.8 m

• Lifting height 74.5 m

• Draft 4.5 m

• Centric loading point

• Previous jobs: West Bridge,

Confederation Bridge, Øresund

Bridge, Offshore operations

> 'Svanen' is one example; several floating cranes available, new ones are coming

Page 54: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Construction sequence for piers

Standard erection of caisson and pier shaft

Shallow water piers will be prefabricated and erected in one piece

54 54 Via Nordica 2012 - Fehmarnbelt Bridge

Page 55: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

Erection of superstructure approach bridge

55 Via Nordica 2012 - Fehmarnbelt Bridge

Joint 40m in span: better fit at bearing, welding easier, bending moment at pier location

Page 56: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

Prefabrication for main bridge

Caissons in dry dock up to 10 m

Extension of caissons to full height Caisson ready for submerging

Assembly for steel erection

56 Via Nordica 2012 - Fehmarnbelt Bridge

Page 57: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

In-situ construction of main bridge in Fehmarnbelt

Construction of pylon (climbing form) and start of steel girder erection

Free cantilevering of bridge girder

Via Nordica 2012 - Fehmarnbelt Bridge 57

Page 58: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

7. Main Construction Cost and Manpower Resources

58 Via Nordica 2012 - Fehmarnbelt Bridge

Result of cost estimate

NPV value for O&M costs 669.7 Mio Euro (120 years)

Project part

[Mio Euro] [Mia DKK]

Fehmarn Landworks + Peninsula 164.2

Substructures approach bridges 601.0

Superstructures approach bridges 1,185.2

Cable stayed main bridge 782.7

Lolland Landworks + Peninsula 178.3

Construction costs (1) 2,911.4

Selected options 90.8

Railway tracks and installations 133.6

Mechanical + electrical installations 148.8

Construction costs (2) 3,284.6

Construction risk add-on 294.9

Total construction costs 3,579.5 26.7

Cost

Page 59: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Time schedule: Status January 2011

- Time planning assumes today construction start in 2014

- Construction period 5½ years with reserve for climbing of pylon legs and testing of technical installations

59 Via Nordica 2012 - Fehmarnbelt Bridge

Design

Investigations

Approval procedures

Tendering

Construction

2009 2010 2011 2012 2013 2014 2020

Page 60: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

60 Via Nordica 2012 - Fehmarnbelt Bridge Animation of Bridge Solution

Page 61: Fehmarnbelt Fixed Link Bridge Design Presentation … Henrik Elgaard Jensen_3712209.pdf · Fehmarnbelt Fixed Link – Bridge Design Presentation of Concept Design Henrik Elgaard Jensen,

#

Symposium Leipzig 2010

Sunset at Fehmarnbelt

61 Via Nordica 2012 - Fehmarnbelt Bridge

Thank you very much for your attention