PRESENTATION TO: THE HON’BLE PRINCIPAL SECRETARY / COMMISSIONER, CHENNAI CITY, TAMILNADU Link Road Connecting Kaliamman Street to Poonamalle Road via Nerkundram Road Presented By: Naveen Jaiswal-Highway Engineer Date: 26.08.2014 C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r s VKS INFRATECH MANAGEMENT PVT. LTD.
27

Feasibility of a Link Road

Jul 18, 2016

Download

Documents

naveen jaiswal

It is the feasibility study of a link road Discuss various alternatives with merit and demerits with the best alternative.
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Feasibility of a Link Road

PRESENTATION TO:

THE HON’BLE PRINCIPAL SECRETARY / COMMISSIONER,

CHENNAI CITY, TAMILNADU

Link Road Connecting Kaliamman Street to Poonamalle Road via Nerkundram Road

Presented By:Naveen Jaiswal-Highway Engineer

Date: 26.08.2014

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Page 2: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Snapshot

Tender Accepted : 11.10.2013Negotiation Meeting : 15.10.2013Letter of Intent : 01.11.2013Kick off Meeting : 14.11.2013Time Period : 6 MonthsInception Report : SubmittedTraffic Report : SubmittedFeasibility Report : SubmittedRevised Feasibility Report : Submitted

Page 3: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Snapshot (Previous Reporting)Report Progress

Inception report Submitted & Approved

Traffic surveys

Submitted & Approved. It is observed that the project Corridor has reached it maximum capacity and additional lanes are required immediately.As there is a restriction in the available ROW, a full length elevated corridor, to increase the no. of lanes, is the solution.

Feasibility Report

Submitted on 26.03.2014.Project feasible subject to availability of landMinutes of Meeting received on 21.07.2014 instructing to submit revised feasibility report

Revised Feasibility Report

Submitted on 05.082014 incorporating the comments of the Minutes of Meeting of Feasibility Report

Page 4: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Sequence of Presentation1.Project Location & Existing Alignment2.Background3.Issues in the Project Corridor4.Objectives5.Most Feasible Alignments6.Proposal7.Comments of Feasibility Report & Response8.Conclusion & Recommendations

Page 5: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Project Location

Proj

ect R

oad

Poonamalle Road

Kaliamman Street

Chennai City -TAMILNADU State

Study Corridor

1. Link Road Connecting Kaliamman Street to Poonamalle Road via Nerkundram Road in Chennai.

Page 6: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Existing Alignment

Project Road: Starting at Kaliamman Koil Street and Ends at Poonamalle Highway

Page 7: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Background1. Lack of uniform corridor width, 2. Road encroachments.3. Road side Parking/halting/stopping.4. IPT Mode Prevalent.5. Lack of Designated and regulated

Parking6. Lack of pedestrian facilities and city

drainage.7. Lack of comprehensive Management

Schemes.

Page 8: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Issues in the Project Corridor

1. Large number of commercial establishments and substantial number of residential building.

2. There are a number of sharp curves needed to be improved.

3. There are public amenities like Children Park, Hospitals, Cremation Ground and Religious structures

4. Road width is insufficient to the cater the traffic

5. Connectivity of the Link Road

Page 9: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Objectives

1. Improving operational efficiency2. Remove Bottlenecks3. No/min Disturbance to road side

properties4. Mobility for all – Pedestrian, NMT and

2 wheeler.5. Lane space Utilization – Flyover Vs. At

Grade6. Assurance of traffic flow during

construction.7. Economy & Aesthetics

Page 10: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

MOST FEASIBILE ALIGNMENTS

Page 11: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Alignment: 1AThis alignment is proposed on the existing alignment with minor changes in the existing curves and with following realignments:• Realignment from ch.740 to ch.1080 (to avoid the

serpentine stretch) and • After Ch. 1870 of project roadThe total length of the Proposal is 2045 m

1870

Page 12: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Alignment: 1BThis alignment starts at the Kaliamman koil Street-Project Road junction and follows the existing alignment upto Chainage 1170 and then passes through open land along the Metro Depot and finally meets the Poonamalle High Road.The total length of the proposal is about 1770 m

Page 13: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Alignment: 2AThis alignment takes off from Kaliamman koil Street-market Road Junction and follows the Market Road upto chainage 1375 and then realigns at the project road upto chainage 1870 and the follows the Alternative 1A upto Poonamalle. Steep curves and serpentine stretch have been avoided.

1870

Page 14: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Alignment: 2BThis alignment takes off from Kaliamman koil Street-market Road Junction and then follows alternative 1B as it passes through open land along the Metro Depot and finally meets at Poonamalle.The total length of the alignment is 1753m

Page 15: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

PROPOSAL

Page 16: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Proposal: 4 lane Elevated Flyover over Alignment

1870 Proposed

Cross section

Page 17: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

1. In this proposal 4-lane elevated corridor takes off from Kaliamman koil Street-market Road Junction and then follows alternative 2B as it passes through open land along the Metro Depot and finally meets at Poonamalle.

2. Total estimated cost of construction for 4-lane flyover is Rs. 1,72,39,58,544.

3. The total length of the alignment is 1753m

Silent Features of the Proposal

Page 18: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

1870

SL.NO PARAMETERS

1 Technical Parameters  i Total Length 1753 m  ii Design Speed (Posted Speed) 50 kmph

  iii Total no. of curves 4

  iv

No. of curves compliant to IRC standards 4

2 Social and Cultural Parameters

  i No. of hotspots (religious structures) affected 1

3 Environmental Parameters  i Proposed Right of Way 20 m  ii Area of Land to be acquired 17500 sqm

  iii No. of trees to be shifted 76

  iv No. of utilities to be shifted 33

Parameters Governing the Proposal

Page 19: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Merits & Demerits

Merits1. It is smaller in Length as compared to other

proposals.2. Land Acquisition will be least.3. 4-lane elevated corridor to ease the traffic

congestion4. Market road will be utilized.

Demerits5. Cost of the proposal is highest6. Integration with existing alignment is not possible

Page 20: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Comments of Feasibility Report

Page 21: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Points to be addressed as per Minutes of Meeting1. The consultants were requested to study both at-

grade and elevated proposal for the selected option.

2. The consultants were requested to segregate the area details of land acquisition and structures to be affected due to L.A.

3. The consultant was requested to study the proposal of Highways Department in the Kalliamman Street in conjunction with the proposed proposal.

Page 22: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Points 1: At-grade vs Elevated proposal

• The alignment passes through boundary of church and if we go at grade it will require larger area at ground and demolition of structures in the church area will become unavoidable. Whereas if we go elevated, demolition may be avoided by options various pier position.

• The alignment passes through the built up area and hence at grade may increase the demolition which may be avoided in case of elevated proposal.

Page 23: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Points 2: Land acquisition & Structures affected

• ROW proposed: 20 m• Total Area Required: 17500 sqm (Lump sump)• Total no. of structures affected: 19

Page 24: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

Points 3: Proposal of Highways Department in conjunction with the proposed proposal.

As per the data collected and information obtained no such proposal are in conjunction with the proposed proposal.

Page 25: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

• Proposal though being highest on cost requires least land acquisition and solves the problem of traffic congestion to the maximum

• Based on economic benefits in terms of savings in VOC and savings in travel time cost for passenger and goods vehicles of all the alternatives Proposal 5 is recommendate.

• An economic internal rate of return of 27.17% (more than 12% of discounted rate) and positive value of INR 19,777.30 Lacs as NPV of net benefits indicates the economic viability of project road for the proposed improvement of proposal 5 i.e. 4 lane elevated corridor.

Conclusion & Recommendation

Page 26: Feasibility of a Link Road

C o n s u l t i n g E n g i n e e r s P l a n n e r s & M a n a g e r sVKS INFRATECH MANAGEMENT PVT. LTD.

THANK YOU