• KAR Pipeline LTD, HKN RETM, Piping (from 28/Nov/2018 to 01-Dec-2019), ➢ Working as Mechanical Supervisor Engineer in piping construction, was in charge of pipe welding map mark, site construction quality check (delivery checklist of pipes, welding, sandblasting, coating, painting). ➢ Prepare hydro-test Package and relevant certificates (such as the mechanical complete certificates, Provisional Acceptance certificate, Commissioning Certificate, Ready to Start-up Certificate, Start-up Certificate, etc.) ➢ Material checking with certificate for piping in RETM HKN Materials. ➢ hydrostatic test of piping. • KAR Pipeline LTD, GKPI (PF1,RETM) and pipeline 16'' (from 01/Nov/2018 to 01-Dec-2019), ➢ Working as Mechanical engineer in Pipeline construction, was in charge of pipe welding map mark, site construction quality check (delivery checklist of pipes, stringing, bending, welding, coating, lowering) 12.850 Km. ➢ Material checking with certificate for piping in PF1. ➢ Torqueing the flanges and valves. Experiences FAWAZ MIRO Supervisor Mechanical Engineer at KAR GROUP Duhok, Iraq +964-7508359100 [email protected]LinkedIn: Fawaz Miro Personal Information Nationality: Syrian Sex: Male Family status: Married, I have two children Date of Birth: 20\12\1983 Scientific Certification University: Damascus University, the Faculty of Mechanical and Electrical Engineering. Department: Mechanical Engineering / Mechanical Power Department Graduation Project: Economic Survey of the Feasibility at Spinning and Textile factory in Damascus, Syria. Degree: Good Rate: (62, 43 %) 2011
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
• KAR Pipeline LTD, HKN RETM, Piping (from 28/Nov/2018 to 01-Dec-2019),
➢ Working as Mechanical Supervisor Engineer in piping construction, was in charge of pipe
welding map mark, site construction quality check (delivery checklist of pipes,
welding, sandblasting, coating, painting).
➢ Prepare hydro-test Package and relevant certificates (such as the mechanical
Ready to Start-up Certificate, Start-up Certificate, etc.)
➢ Construction coordination with Client for pre-commission and hand over working.
➢ Be familiar with sand blasting, Coating, And Welding.
➢ Install 3 pumps, alignment, hot commissioning.
• KAR Pipeline LTD, ATRUSH PIPELINE EXPORT SYSTEM oil and gas (March 2017- October 2017)- ATRUSH TO SHEKHAN, Kurdistan, Iraq
Main Duties:
➢ Working as Mechanical engineer in Pipeline construction, was in charge of pipe welding
map mark, site construction quality check.
➢ Punch list incorrect item of piping installation, close the punch list items.
➢ Be familiar with sand blasting, Coating, And Welding.
• KAR Group LTD, Khormala Power Plant (1000 MW) (January 2013- Febriwary-2017) - Erbil, Kurdistan, Iraq
Field Engineer
Main Duties:
➢ Supervising the installation of the 5000 CUBIC METERS Tank Farm (Erection,
hydrostatic test, commissioning).
➢ Supervising the installation of the 400 KV switchyard towers.
➢ Supervising the installation of the central air-conditioning HVAC in (Project administration building, social building, control building, reception building and firefighting building).
➢ Supervising the Welding processes and installing the pipes within the project (Erection,
Blowout, Hydrostatic test, flashing).
➢ Arranging the working sheets that satisfy the work demand of the contractor
(SIEMENS, ABB & ACCORU) and sub-contractor (SEC, Power China, and NYCO).
➢ Arranging the Notification Sheets that report the issues occur during work. ➢ QA/QC completion that related to the NDT Company (NYCO). ➢ Electrical ECC (Erection Clearance Certificate) & FQP (Field Quality Plan) for all power
plant units. ➢ Placing all KKS labels regarding the power plant elements according to P&ID diagrams.
➢ Work in commissioning of fuel gas supply system and fuel oil supply system. ➢ Embedded part (install anchor bolts, plats and H-beam) in the foundation in power
plant, phase one (four units) and phase three (two units).
➢ Supervising the installation of the power island, SIEMENS part (turbine, generator, air intake, exhaust stack, and auxiliary), phase three (two units).
➢ Cold commissioning and hot commissioning of the power plant with SIEMENS teams in Khormala power plant.
➢ Commissioning of Demin water System Capacity 10 m3 per day.
• Avro City (Duhok / Kurdistan / Iraq), (April 2012- December 2012).
Main Duties:
➢ Installation and maintenance of air conditioners individual, multilateral and central air conditioning with VRV system.
➢ Expertise in engineering drawing more than four years in Damascus. ➢ Installation, Welding, and insulation of the brass pipes. ➢ Work in Electricity car workshop for three Years. ➢ A member of Association of Engineers in Syria.
➢ Kurdish: Native Language.
➢ Arabic: Excellent Read and write.
➢ English: good Read and write.
Relative Skills:
Languages:
➢ Turkish: good conversation.
➢ Proficient in Microsoft Office, Data Base (ICDL) and Computer Maintenance in
Software and Hardware.
➢ Proficient in Mechanical Desktop and AutoCAD Desktop.
➢ Knowledgeable in operating Mechanical Desktop and AutoCAD for HVAC Planning