EWEC 2007 Milan 7-10 May 2007 Policies and programmes Wind energy in Italy: national and regional policies, market development and future perspectives Luciano Pirazzi ENEA
Apr 01, 2015
EWEC 2007 Milan 7-10 May 2007
Policies and programmes
Wind energy in Italy: national and regional policies, market development
and future perspectives
Luciano Pirazzi
ENEA
National actions supporting electricity production from
renewable energy sources Capital cost subsidies
• Law No. 308 was issued in 1982
(limited to 3 MW with a contribution up to 30% of eligible cost)
• Laws No. 9 and 10 were issued in 1991
(contribution up to 30-40% of plant cost)
National actions supporting electricity production from renewable energy sources
Feed-in Tariff
Provision No. 6/92Issued by CIP (the Inter-ministerial Committee for Prices)
in 1992
Premium tariff composed of two items:
- avoided cost
- incentive, granted over the first 8 years of plant operation
CIP 6/92
2006 rates for the first 8 years of operation for different renewable sources
- hydropower plants with a reservoir, and run-of-river plants above 3 MW: from 20,87 €cent/kWh
(peak hours) to 6,07 €cent/kWh off-peak hours
- run-of-river hydropower plants up to 3 MW:
12,35 €cent/kWh
- wind and geothermal plants: 14,94 €cent/kWh
- PV, biomass and waste plants: 20,61 €cent/kWh
Mandatory quota and Tradable Green Certificate
Legislative decree No. 79/99
• Since 2001 a RES (Renewable Energy Sources) quota has been operating.
• Electricity producers or importers from non renewable sources exceeding 100 GWh must feed into the Italian grid, within the end of the subsequent year, an amount of RES electricity equalling a minimum quota of this non-renewable electricity.
• The RES electricity quota was originally 2%, but was subsequently raised by 0.35% a year: specifically, it was 2.35% in 2005 and 2.70% in 2006 and is 3.05 % in 2007). No quota has, as yet, been set for the following years.
Tradable Green Certificate
• To show compliance, obliged operators can either hand in TGC (Tradable Green Certificates) from their own RES plants, or buy TGC from other RES producers on the market.
• Qualified RES electricity producers get one TGC for each 50 MWh of their production over a term that was formerly 8 years, but has, since 2006, been extended to 12 years of plant operation.
• The sale of TGC brings them an additional income besides the proceeds from the sale of energy on the wholesale electricity market.
Green certificate Reference price
TGC relating to the 2006 RES production was set (VAT not including) at 125.28 €/MWh by GSE (Gestore Servizi Elettrici)
This value was calculated as the difference between:
• the average cost of CIP/6 electricity purchased by GSE in 2006 and produced from renewable plants
• The revenue resulting from the sale of the same electricity in 2006
Legislative Decree No. 387/03
(implementing EU Directive 2001/77/EC on RES promotion)
• Production of 76 TWh/y from RES by 2010 (corresponding to a share of 22% of gross electricity consumption)
• No specific target for any type of renewable technology
• Annual increase of the RES quota obligation
• Net-metering for renewable plants not exceeding 20 kW
• National targets are to be allocated among regions
• Permit for renewable plant construction has to be released by the region concerned, through a single authorisation involving all parties concerned, within 180 days
National targets
• 2,500 MW from wind by 2008-2012 (Italian white paper for the exploitation of RES)
• 25% of renewables into the electrical system by 2011 (new energy programme)
• Reduction in annual greenhouse emissions of 6.5% less than 1990 by 2008-2012
Regional policies
Legislative Decree No. 112/98
• Decentralization of administration
• Decision on RES plants must be taken at regional and local level
As a consequence:
Regions are in charge of evaluating wind projects in terms of environmental impact and all other relevant aspects, before authorizing the building of wind plants
Regional energy and environmental plan
• Wind energy has been included in many regional plans
• The Apulia, Sicily, Campania and Calabria regions are currently stimulating wind deployment
• Some regions have issued confusing rules in their wind guidelines as a consequence of the lack of:
- national guidelines- establishment of obligation on regional governments
to contribute in meeting national renewable energy commitments
Other regional support
• Financial support in capital cost to RES initiatives, through European structural funds, has been granted by some southern regions
• In particular, the Apulia, Campania and Sicily regions, have allocated financial resources towards various renewable projects at different percentage of eligible cost
Installed Capacity and Annual Energy Production
2340
3215
14041458
1837
232
402563
1179
1180
100200300400500600700800900
10001100120013001400150016001700180019002000210022002300
1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006
Year
Ins
talle
d C
ap
ac
ity
(M
W)
0
500
1000
1500
2000
2500
3000
3500
An
nu
al E
ne
rgy
Pro
du
cti
on
(G
Wh
)Annual MW
Cumulative MW
Annual EnergyProduction
Number of units and average capacity (kW)
84150
243
402
585
798
1346
65 94159 183 222
411
137 145
389 378 363
1209
1880
1491
2258
2575
260
368403
447482
521561
585607
673
761
823
1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006
Nu
mb
er o
f u
nit
s
0
100
200
300
400
500
600
700
800
900
Ave
rag
e ca
pac
ity
(kW
/un
it)
Number of units(cumulative)Number of units(annual)Average capacity
Market share of wind turbine manufacturers at the end of 2006
Repower 2%
Enercon 12%
Gamesa 20%Vestas Italia
57%
GE Wind 6%
Contribution by electricity producers from wind at the end of 2006
0
5
10
15
20
25
30
35
Market Shares (% rated power)
Wind Energy Producers
% 31 14 13 9 5 5 4 4 2
31 14 13 9 5 5 4 4 2
IVPC Enel Edens FRI-EL Moncada Endesa EnerTAD Sardeol.Sansever.
Annual growth rate
050
100150200250300350400450500
1997 1998 1999 2000 2001 2002 2003 2004 2005 2006
years
MW
0%10%20%30%40%50%60%70%80%90%100%
Growth rate MW
Growth rate %
Wind farms ready to be connected to the grid or just connected
• 1 in the Salerno province (Campania) operated by FRI-EL 36 MW composed of 3 MW turbines• 1 in the Lecce province (Apulia) operated by Inergia 36 MW composed of 2 MW turbines• 1 in the Foggia province (Apulia) operated by IVPC 30 MW composed of 2 MW turbines• 1 in the Foggia province (Apulia) operated by Fortore Energia 12 MW composed of 2 MW turbines• 1 in the Foggia province (Apulia) operated by Fortore Energia 20 MW composed of 2 MW turbines
TOTAL 134 MW
Trend
• Installation of large sized turbine
from 1,5 MW to 3 MW
• Large variability of wind farms
from a few MW to 84 MW
• New investors (also foreigners)
• Offshore initiatives
Infancy stage
Future perspectives
• Quite good in the short time (the main developers have ordered aerogenerators for many MW)
• Some uncertainties and constraints still present in many regions have to be solved shortly in order to comply with European commitment
• Many developers have planned important investment in the medium term
• Repowering (replacement of old, small turbines with new and larger ones) will increase power capacity
Regions: Sardinia , Toscana, Marche, Umbria, Lazio, Abruzzo e MoliseRegions: Sardinia , Toscana, Marche, Umbria, Lazio, Abruzzo e Molise
é
#
#
#
#
#
#
#
#
#
#
#
#
##
#
#
# #
SA RL U X
LA R N O
A U R E L A
S LU C I A
S U V E R E T O
RU M IA NC A
ROMA SUD
MO N TA L T O
RO M A ES T
SE L AR G I US
RO M A N O R D
VI LL A N O V A
PR ES E NZ AN O
ROSARA
VA L M O N T O N E
CE PR A N O
CA G L A R I SU D
M O N T A L TO C . L E
T O R R EV AL D A LI G A
FIUME SANTO
PIOMBINO
T O R R EV A L D A L G A N O R D
CODROGIANOS
S G IA C O M O
LATINA
LUCCIANA EDF
#
#
#
##
#TAVARNUZZE
CALENZANOPOGGIO A CAIANO
S. BARBARA
ACCIAIOLO
LA SPEZIA
ROSEN
BARGI
ROMA OVEST
CANDIA
LIVORNO
ENERGIA MOLISE
120 -> 132 kV
SAPEI – Sardinia – Mainland dc 500 kV link
SAPEI – Sardinia – Mainland dc 500 kV link
Substation 380/132 kV in Abbadia (MC)
Substation 380/132 kV in Abbadia (MC)
Grid development
Regions: Campania, Puglia e BasilicataRegions: Campania, Puglia e Basilicata
380 kV single circuit line Foggia - Benevento
380 kV single circuit line Foggia - Benevento
é
#
#
BARI OVEST
LAINO
MONTECORVINO
LARINO
GALATINA
TARANTO NORD
BRINDISIPATRIA
PRESENZANO
GARIGLIANO
S.M. CAPUA V.
BRINDISI NORD
BRINDISI SUD
ANDRIA
MIRANT S. SEVERO 400 MW
ENERGIA TERMOLI 800 MW
ENIPOWER BRINDISI 1170 MW
FOGGIA
BENEVENTO
MATERA
CANDELA
380 kV single circuit line Matera – S.Sofia
380 kV single circuit line Matera – S.Sofia
Substation near BariSubstation near Bari
Substation near Vesuvio (NA)
Substation near Vesuvio (NA)
380 kV double circuit line Montecorvino - Benevento380 kV double circuit line
Montecorvino - Benevento
S. SOFIA
Grid development
Possible new substation 380/150 kV
near Candela
CASALVECCHIOPIETRACATELLA
VOLTURARA
ALBERONA
ROSETO
MONTEFALCONE
COLLE SANNITA
FOIANO
CERCEMAGGIORE
CAMPOBASSO
PRESENZANO
S.SOFIA BENEVENTO 2
BENEVENTO N.
BENEVENTO IND.
APICE FS
ARIANO IRPINO
SAVIGNANO FS
FLUMERI
ACCADIA
LACEDONIA
BISACCIA
ASCOLI SATRIANO
MELFI IND.
EOS 1 TROIA
TROIAORSARA
LUCERA
AVELLINO
AGIP DELICETO
FOGGIA
FOGGIA 380 KV
FOGGIAFS
FOGGIA IND.
ANDRIA
BARI O.
TRINITAPOLI
ALENIA
ORTANOVA
CERIGNOLA FS
S.SEVERO FS
S.SEVERO
S.GIOVANNI ROTONDO
MANFREDONIA
P.D.R. CELLE S.VITO
C.LE EDISON CANDELA
MONTESARCHIO
AIROLA
BOVINO
BOVINO FS
CALITRI
VALLESACCARDA
To streghten
remove transmission
constraint
FOGGIA O.
Grid development in Campania and Puglia
NEW 380 SUBSTATION
Regions Calabria and SicilyRegions Calabria and Sicily
380 kV double circuit line Sorgente-Rizziconi
380 kV double circuit line Sorgente-Rizziconi
380 kV single circuit line Chiaramonte - Ciminna380 kV single circuit line Chiaramonte - Ciminna
PARTANNA
BELLOLAMPO
PARTINICOTERMINI I.
CARACOLI
AGRIGENTO FAVARA
PATERNO’
ANAPO
CORRIOLO
MISTERBIANCO
CATANIA
PRIOLO
SIRACUSA
MELILLI
RAGUSA
PALERMO
TRAPANI
TRAPANI
RAGUSA
S.FILIPPODEL MELA
ENNA
POLIMERI
CALTANISSETTA
DUFERDOFIN
ISAB
CIMINNA
CHIAROMONTE G.
MESSINA
CROTONE
EDISONSimeri Crichi (CZ) – 800 MW
EDISON Altomonte (CS) – 800 MW
MONTECORVINO
da declassare a 150 kV
PISTICCI
tratto da demolire
SCANDALE
FEROLETO 380 kV
MUCONE 1 2
COSENZA
CATANZAROVIBOVALENTIA
REGGIOCALABRIA
MATERA
ROTONDA
ROSSANO – 1600 MW
MERCURE
LAINO
RIZZICONI
EDISON Pianopoli (CZ) – 800 MW
SORGENTE
Grid development
Network development process
The Development Plan is worked yearly out according
to the planning scenarios, on the basis of:
Demand growth per each area
Development of new production units (Thermal + Wind)
Location of new generation on the territory
Signals from the power exchange
New transformersNew transformers (MVA)(MVA) 14.85014.850 2.840 2.840 0 0 17.690 17.690
Short-medium term Short-medium term 10.850 2.430 0
13.280
Medium-long term Medium-long term 4.000 410 0
4.410
Lines (km) Lines (km) 3.2403.240 - 990 1.080 - 990 1.080 3.330 3.330
Short-medium term Short-medium term 2.320 - 260 890
2.950
Medium-long term Medium-long term 920 - 730 190
380
380 kV380 kV 220 kV 120-150 kV 220 kV 120-150 kV Total Total
2006-2015 Network Development Plan in ItalyCharacterization of new investments
Difficulties in building new high voltage lines due to authorisation problemsDifficulties in building new high voltage lines due to authorisation problems
Authorization problems
People opposition linked to increased (excessive) environmental sensitivity
Difficulties in identifying new feasible routes due to intense human territorial penetration
Lack of integration between electrical and territorial/environmental planning
Unsatisfactory results and uncertain timetable of present authorization procedures (EIA)
Main issues related to wind farm development
Mainly distributed in major Islands Sardinia is linked with Italy with a dc 200 kV line
Limited transport capability (300 MW) and operational flexibility (few fast
reversal/Year) and modulation range
Conventional power plant: few units, large size with high technical minimum
difficulty in managing load ramping in case of wind decrease
Big amount “Cip 6/92” Power Plant, with priority dispatching
Wind power plant located in region of low power demand
Wind energy to be transmitted over long distances to the load
centres
Necessity of grid extension
Wind capacity at regional level at the end of 2006 in MW. Wind capacity added in 2006 is indicated in bracket
346 (12)
451 (137)
153 (68) 421 (11) 468 (126)
70 (21)155 (8)
9
Wind capacity added in 2006 = 417 MW
3.5
28 (26)
2.5 (1.3)
6.5 (1.7)
1.5
Total wind capacity2.123 MW
6 (6)
36
326
1.516
1.126
North
Centre
South
Islands
FRANCEFRANCE
SWITZERLANDSWITZERLAND AUSTRIAAUSTRIA
168
158
400
593
533
303
197
616
36
TOTAL (MW) 3.004TOTAL (MW) 3.004
Wind generation capacity in 2008
640
2.547
13.342
8.652
North
Centre
South
Islands
TOTAL (MW) 25.181 TOTAL (MW) 25.181
SLOVENIASLOVENIA
FRANCEFRANCE
SWITZERLANDSWITZERLAND AUSTRIAAUSTRIA
288
377
849
3.0281862
2.828
2.044
5.442
147
201
109
1011
44
70
91
6.790
Total Wind connection applications to transmission grid: 25.181 MW (update December 2006)