Top Banner
This document sets out NBN Co’s proposals in respect of certain aspects of the National Broadband Network. The contents of this document represent NBN Co’s current position on the subject matter of this document. The contents of this document should not be relied upon by our stakeholders (or any other persons) as representing NBN Co’s final position on the subject matter of this document, except where stated otherwise. NBN Co’s position on the subject matter of this document may also be impacted by legislative and regulatory developments in respect of the National Broadband Network. All prices shown in this document are exclusive of GST. UNCLASSIFIED | © NBN Co 2013 Evolution of Network Implementation Finance Project Fox Planning & Design September 2013 to June 2014
122

Evolution of Network Implementation · SpatialNet Accelerated understanding of NDD’s provided by P&D Regional Network Designer to support SDP’s in completing DDD’s 4 Benefits:

Feb 13, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • This document sets out NBN Co’s proposals in respect of certain aspects of the National Broadband Network. The contents of this document represent NBN Co’s current position on the subject matter of this document. The contents of this document should not be relied upon by our stakeholders (or any other persons) as representing NBN Co’s final position on the subject matter of this document, except where stated otherwise. NBN Co’s position on the subject matter of this document may also be impacted by legislative and regulatory developments in respect of the National Broadband Network. All prices shown in this document are exclusive of GST.

    UNCLASSIFIED | © NBN Co 2013

    Evolution of Network Implementation Finance Project Fox

    Planning & Design September 2013 to June 2014

  • UNCLASSIFIED | © NBN Co 2013

    Plan to Evolve Network Implementation

    The combination of the changes to the Network Architecture, with the Telstra involvement in Duct proving and remediation specified in Step Change, and the direct management of Tier 2 Contractors with the Render application; all supported with the new technology introduction of Small Form Factor Multi‐ports, smaller diameter cables and the next generation Fibre Distribution Hubs will allow the cost forecast in the NBN Co Corporate Plan to not only be met, but even lower cost levels achieved! 

       Architecture 2.1 + Step Change + Render  

    New Technologies 

    Corporate Plan ($ & time) 

  • UNCLASSIFIED | © NBN Co 2013

    Architecture Type 2.1 Key Changes

    • Fibre Demand Point allocation changed to: • 1.5 fibres per Single Dwelling Unit • 1.5 fibres per Commercial Premises • 1.25 fibres per Multi Premises Site  

    • Increase FDH utilisation to ~400 GNAF.  

    • Reduction of feeder fibre allocation per FDH in DFN to 24 Fibres, 2 Ribbons. • Provision of point to point fibre allocation per FDH in DFN of 12 Fibres, 1 Ribbon • Removal of dual direction feed of DFN to each FDH, removal of patching restoration, change to 432 fibre cable. 

    • Increase in number of FDHs to be served via a spur to 8 (although DFN ring configuration will remain the preferred configuration). 

    • Fibre Demand Point allocation changed to: • 1.5 fibres per Single Dwelling Unit • 1.5 fibres per Commercial Premises • 1.25 fibres per Multi Premises Site  

    • Increase FDH utilisation to ~400 GNAF.  

    • Reduction of feeder fibre allocation per FDH in DFN to 24 Fibres, 2 Ribbons. • Provision of point to point fibre allocation per FDH in DFN of 12 Fibres, 1 Ribbon • Removal of dual direction feed of DFN to each FDH, removal of patching restoration, change to 432 fibre cable. 

    • Increase in number of FDHs to be served via a spur to 8 (although DFN ring configuration will remain the preferred configuration). 

  • UNCLASSIFIED | © NBN Co 2013 Page 4 14-Sep-14

    Summary of Architecture 2.1 Modelling Results

    Average savings of $315 achieved per Premises broken down by network component can be shown as:

  • UNCLASSIFIED | © NBN Co 2013 Page 5 14-Sep-14

    Benefits:  Reduce repetitive FIR walkouts by enforcing “Right First Time” approach  Reduce duration from 80+ days to maximum of 17 days 

     

    Design Field Support Services will conduct T‐FIRs and audit E‐FIR and AVRs 

    Benefits:  SDP improve capability  in using SpatialNet  Accelerated understanding of NDD’s provided by P&D     

    Regional Network Designer to support SDP’s in completing DDD’s  

    Benefits:  Faster issuance of Certificate of Accuracy  Better use of Arial Design Expertise  Consistent workflow to Aerial Design House  Removes requirement to constantly retrain SDP engaged ADH 

    National Arial Design within NBN Co control to provide consistency of Arial Design with direct Utility engagement 

    6 Eliminate Handover Points by streamlining the E2E NDD to DDD design process 

    Benefits:  Reduction of time spent on review and understanding  Reduction of multiple quality checks such as SpatialNet NCR  Reduced chance of error at handover  Improved Quality  

    Benefits:  Reduction of rework on BoQ  Accelerated throughput of DDD to construction 

    Providing  Regional Design Manager with authority to conduct in field design variations  

    Benefits:  NBN Co being accountable will drive the delivery of DDDs  Better training of resources at NBN Co in network design  More efficient utilisation of existing NBN Co design resources 

    Move Accountability for DDD from SDPs to  NBN Co Regional Design Teams 

    Field Support Services 

    NBN  Co DDD Support Capabilities 

    VIC/TAS  WA/SA  NT  QLD 

    NSW/ACT 

    Network Design 

    Construction Support 

    Field Support Services 

    Service Stream

     

    Transfield 

    Visio

    nstream 

    Synthe

    Silcar 

    Other 

    Gate 1 Gate2 

    Gate3 

    NDD  DDD 

    More than 10 Handover Points 

    Eliminated Handover Points within NBN Co with SDP 

    88+ Days 

    43+ Days 

    Service Delivery Partners 

    E‐FIR   

    AVR   

    T‐FIR   

    Service Delivery Partners 

    E‐FIR   

    AVR   

    T‐FIR   

    Design Field Support Services Audit  Execute 

    Service Delivery Partners 

    Service Delivery Partners 

    Regional Network Designers 

    NBN Co Regional Manager 

    NNR* NNR* 

    Multip

    ort 

    Multip

    ort 

    Ducts 

    Ducts 

    Pits 

    Pits 

    Remed

    iatio

    n Re

    med

    iatio

    Execute IFDV 

    In‐Field Design Variation 

    Service Delivery Partners 

    Telstra 

    NBN Co Design Cost Optimisation 

    Aerial Design House 

    Engage

     

    Design 

    Arial Design Expert 

    Arial Design Expert 

    ADH 

    NBN Co Arial Design Experts 

    Replace Arial with Underground 

    * NNR - Notification Not Required

    6 key improvements proposed to optimise the E2E design process

  • UNCLASSIFIED | © NBN Co 2013

    Aerial Included Step Change Process

    Network Design 

    Document 

    Field Inspection Report 

    Detailed Design 

    Document 

    Design & Civil Construction, Augment and New Build  

    (underground) 

    Remediation Works 

    Build, Splice & Test Fibre (aerial & underground) 

    Remediation Handover

    Handover to Network Operations

    10 days 17 days 5 days 3 months

    • Assess fitness (rod and rope activities) • Identify alternatives to maximise use • Identify required remediation works • Perform targeted Address walkout

    Design Optimisation 

    Serv

    ice

    Del

    iver

    y Pa

    rtne

    r

    NB

    N C

    o

    Tels

    tra

    (a

    s C

    ontr

    acto

    r)

    Confirmed Order Response and comment 

    Provisional Order Response and comment 

    3 month Default Remediation Period

    3 month Generic Completion Time

    Tels

    tra

    (u

    nder

    DA)

    Ae

    rial A

    SP

    Field Survey & Prelim Design 

    Design Optimisation 

    Design  Finalisation, Approval and Make Ready Works 

    3 month Generic Completion Time

    3 months

  • UNCLASSIFIED | © NBN Co 2013

    10 

    13 

    20 

    20 

    16 

    20 

    29 

    21 

    18 

    20 

    20 

    40 

    20 

    10 

    15 

    10 

    11 

    12 

    23 

    14 

    10 

    11 

    42 

    17 

    14 

    14 

    20 

    11 

    16 

    13 

    24 

    18 

    13 

    15 

    29 

    10 

    2GOS‐08

    4NDG‐05

    2CBT‐01

    4BDB‐04

    4KLG‐08

    4BDB‐03

    4AAR‐01

    3MLT‐10

    Target(To‐Be)

    As‐IsBaseline

    Today: 25th Nov

    Step Change: 7 out of 8 FSAMs have delivered net process time savings between 52-72 days (vs. 71 target)

    Delay 

    FIR Phase 

    DDD Phase 

    CN/CICA Phase 

    Forecast 

    20 

    20 

    16 

    20 

    29 

    21 

    18 

    20 

    23 

    20 

    40 

    10 

    11 

    23 

    14 

    10 

    11 

    17 

    42 

    14 

    20 

    11 

    16 

    13 

    24 

    18 

    13 

    10 

    15 

    29 

    10 

    2GOS‐08

    4NDG‐05

    2CBT‐01

    4BDB‐04

    4KLG‐08

    4BDB‐03

    4AAR‐01

    3MLT‐10

    Proven cycletime

    Target (To‐Be)

    As‐Is Baseline

    Target Duration

    Total elapsed time Net process time

    Ready for CICA 

    Ready for CICA 

    Ready for CICA 

    Ready for CICA* 

    Ready for CICA 

    Ready for CICA 

    Ready for CICA 

    Ready for CICA* 

    Ready for CICA 

    Ready for CICA* (Excl. Utility certified Aerial Design) 

    • Average CICA duration below 15days, as designs were reported “Ready for Issue” without LAANs 

    • Extended DDD duration due to resource availability and skill gaps. 

    • Net FIR duration aligns with target duration of 20 days 

    Ready for CICA 

    Ready for CICA 

    -71 -71

    -52 -52

    -64 -64

    -69 -69

    -61 -61

    -57 -57

    -72 -72

    Ready for CICA 

    Ready for CICA 

    -52 -52

  • UNCLASSIFIED | © NBN Co 2013

    3MLT-10 Deployment Trial Background

    8

    The Melton 10 (3MLT‐10) Deployment Trial was initiated by NBN Co to create an internal baseline/benchmark for programme, productivity and cost performance utilising: 

    1. The Render deployment management system; 

    2. Innovative specified equipment; 

    3. Innovative build methods and work practices; 

    4. Project governance initiatives; and 

    5. Build Drop installation during LN/DN build. 

    Telstra remediation works commenced in January 2014. NBN Co engaged Australian Broadband Company, Celemetrix, Comms Connect and Linktech directly to carry out the works with a uniform Schedule of rates. Specified equipment was free issued by NBN Co to the Contractors. 

    3MLT‐10 is a large residential FSAM with 2484 GNAF’s (2459 SDU, 25 MDU). It contains a mixture of old and new infrastructure and is a rocky area. There is also a relatively large number of 5 and 1 acre lots and standard residential blocks within the FSAM. 

    The 3MLT‐10 deployment was the first to utilise a Telstra FIR / NBN Co design. A separate Post Implementation analysis for Design is currently being completed by NBN Co’s Design group. 

     

  • UNCLASSIFIED | © NBN Co 2013

    A

    B

    C

    Completed FSAM's All FSAM's 3MLT-10

    LN/DN Cost per GNAF Comparison - 3BRA

    265 days

    344 days

    104 days

    Completed FSAM's All FSAM's 3MLT-10

    'Build Commenced to RFS' Comparison - 3BRA

    3MLT-10 Programme and Cost per GNAF Results

    3MLT‐10 was completed: 

    - 61% faster than FSAMs completed in 3BRA to date (161 business days faster) 

    - 70% faster that all FSAMs commenced in 3BRA to date (240 business days faster) 

    Programme 

    3MLT‐10 was completed: 

    - 50% cheaper than FSAMs completed in 3BRA to date 

    - 43% cheaper than all FSAMs commenced in 3BRA to date 

    Cost per GNAF 

  • UNCLASSIFIED | © NBN Co 2013

    3MLT-10 Build Timeline compared to 3BRA FSAMs to date

    This chart includes the ‘Build Commenced to RFS’ programme for all FSAMs commenced to date in Ballarat 2 CSA (3BRA). Dark green are RFS FSAMs and light green are Build Commenced FSAMs. 3MLT‐10 is RFS and is yellow. FSAMs are sorted by Build Commenced date. 

  • UNCLASSIFIED | © NBN Co 2013

    Small Footprint Multiports (SFM)

    • Underground use only • Directly replaces legacy larger

    MPT device • Can be used in smaller pits • Minimises Remediation • Available in 4 port, 8 port or 12

    port configurations • Still has 12F tether with HMFOC

    connector.

  • UNCLASSIFIED | © NBN Co 2013

    Smaller Diameter Cables - Overview

    05 Sept 13 | Rev 1.1 UNCLASSIFIED 12 

    Benefits   

     

     

     

     

     

     

     

     

    Assumptions • No change in equipment cost – reinforced by early discussions with vendors • No change in equipment technical standards for cable performance   • Local cable production change‐over costs would be absorbed by suppliers • Existing stock of cable would be deployed (no long term supply holding impact) 

      

  • UNCLASSIFIED | © NBN Co 2013

    Smaller Diameter Cables - Project Scope

    • Smaller Diameter Cables project is part of Passive Network Release 4 (PNR4)

    • Based on availability, the following selection of cables will be introduced as part of PNR4:

    dd MMM yy | Rev 0.1 UNCLASSIFIED 13 

    SUPPLIER  FIBRE COUNT 

    FILLER  CURRENT OUTER DIAMTER (mm) 

    REDUCED DIAMETER (mm) 

    REDUCTION %  USAGE PER FSAM BUILD * 

    AVAILABILITY FOR NBN Co VALIDATION 

    Corning  72  Gel free  12.7  12.0  5.5 %  18.6%  August 2013 

    Corning  288 (V1) 

    Gel  23.7  21.7  8.4 %  5.5 %  August 2013  

    Prysmian  144 (V1) 

    Gel  17.1  14.1  17.5%  48.4 %  August 2013  

    Prysmian  

    288  Gel  23.7  21.7  8.4 %  5.5 %  August 2013  

    Prysmian  

    576  Gel  26.7  23.9  10.5 %  27.5 %  August 2013  

    * Percentages are shown per cable type rather than discriminating per supplier 

  • UNCLASSIFIED | © NBN Co 2013

    Next Generation Fibre Distribution Hub

    Version 8 19 June 2013 Page 14

  • UNCLASSIFIED | © NBN Co 2013

    Details of the Major Projects

    •Architecture 2.1 • Step Change •Melton Project & Render •New Technology Introduction 

    • Small Form Factor Multiport • Smaller Diameter Cables • Next Generation FDH 

     

    •Architecture 2.1 • Step Change •Melton Project & Render •New Technology Introduction 

    • Small Form Factor Multiport • Smaller Diameter Cables • Next Generation FDH 

     

  • UNCLASSIFIED | © NBN Co 2013

    Why have we chosen Type 2.1 Architecture?

    Two main reasons: • To Reduce cost • To Reduce the time taken to build the network.

    Savings are made in:

    • Materials used • Civil works

    • Pit Upgrades • Duct Augmentation • Duct Build.

    Redesigns will: • Reduce the cost of the build • Get designs built faster, connecting more premises by target dates

    Architecture 2.1

    New 

  • UNCLASSIFIED | © NBN Co 2013

    Architecture Type 2.1 Key Changes

    • Allocated Fibres at each Demand Point reduced to: o 1.5 fibres per Single Dwelling Unit (SDU) - Type 2 was 3 fibres o 1.5 fibres per Commercial Premises - Type 2 was 2 fibres o 1.25 fibres per Multi Premises Site (MPS) - Type 2 was 1.5 fibres

    • Connected Fibres at each Demand Point has not changed: o 1 fibre per Single Dwelling Unit (SDU) - Type 2 was 1 fibre o 1 fibre per Commercial Premises - Type 2 was 1 fibre o 1 fibre per Multi Premises Site (MPS) - Type 2 was 1 fibre

    • Double the utilisation of each Fibre Distribution Hub (FDH) to approximately 400 addresses

    • Reduce feeder fibre allocation per FDH to 24 fibres (2 ribbons)

    • Reduce default Distribution feeder cable size from 576 fibre to 432 fibre

  • UNCLASSIFIED | © NBN Co 2013

    Architecture 2.1 Benefits

    Approved for implementation: • Reduction in the fibres allocated per premises at the Multiport • Reduction of DSS fibres allocated per FDH • Relaxation of the DSS protect path rules • Slight reduction of the Mandrel size • Introduction of Small Footprint Multiports (SFM)

    Reduction in fibres means: • Smaller cables, so they are more likely to fit into existing ducts • Fewer FDH cabinets, so better chances of finding good sites • Fewer splices, so they are more easily placed into existing pits or manholes • Still have plenty of capacity for growth (Typically four fibres spare in each Multiport tether cable)

    Mandrel size reduction is closer aligned to the real world and reduces augmentation.

    Small Footprint Multiports fit into most existing pits.

  • UNCLASSIFIED | © NBN Co 2013

    Fibre Structure—Underground Type 2 The configuration for underground local fibre is  a ‘Star’ local access joint used to provide the multiport tethers from a central pit, feeding pits located at the property boundary containing multiport terminals utilised to provide the same ‘plug and play’ connections. 

    Local Fibre Allocation 

    19 

    One Dwelling Unit Group of 24 Lots One Dwelling Unit Group of 

    12  1  2  3  4  5  6  7  8  9  10  11  12  1 

    12  1  2  3  4  5  6  7  8  9  10  11  12  1 

    Splitters are only patched to

    addresses when required. Pass-

    through connections

    provide point to point connectivity

    2 fibres allocated per 

    address 

    1 ribbon (12 fibres) allocated to each multiport 

    2  2 

    2  2 

    4 fibres allocated per NAP for addresses,    

    8 spare 

    12 

    Distribution fibre to next

    FDH

    Distribution fibre to FAN

    Underground Configuration, ducts down one side of the street, cross street bores for each dwelling pair.

    P100 conduit used for Local Cables and Distribution Cable  

    P50 conduit used for cross street 

    drops 

    Star Joint splices 10 multiport 

    tethers to Local Fibre Cable ribbons 

    DJL LJL

    FDH 

  • UNCLASSIFIED | © NBN Co 2013

    Fibre Distribution Area Structure— Underground 2 Local Fibre Design – approximately 200 Premises  

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    mmmm

    19003901002390

    Street lengthHorizontal at premisesVertical at premises

    IntersectionsTotal

    mmmPremise length = 39

    Road Width 14m + 2x3m verge = 20Premise width = 19

    Local Fibre

    Drop Fibre

    PitsStreet

    39 m

    190 m

    1 42 53 6 87 9 10

    190 m

    19 m

    FDH

    20 m

    Local Fibre ‐ undergroundDistribution Fibre ‐ underground

    20 

  • UNCLASSIFIED | © NBN Co 2013

    Fibre Structure—Underground Type 2.1 The configuration for underground local fibre is  a ‘Star’ local access joint used to provide the multiport tethers from a central pit, feeding pits located at the property boundary containing multiport terminals utilised to provide the same ‘plug and play’ connections. 

    Local Fibre Allocation 

    21 

    One Dwelling Unit Group of 24 Lots One Dwelling Unit Group of 

    12  1  2  3  4  5  6  7  8  9  10  11  12  1 

    12  1  2  3  4  5  6  7  8  9  10  11  12  1 

    Splitters are only patched to

    addresses when required. Pass-

    through connections

    provide point to point connectivity

    1 fibre allocated per 

    address 

    1 ribbon (12 fibres) allocated to each multiport 

    1  1 

    1  1 

    8 fibres allocated per NAP for addresses,    

    4 spare 

    12 

    Distribution fibre to next

    FDH

    Distribution fibre to FAN

    Underground Configuration, ducts down one side of the street, cross street bores for each dwelling pair.

    P100 conduit used for Local Cables and Distribution Cable  

    P50 conduit used for cross street 

    drops 

    Star Joint splices 10 multiport 

    tethers to Local Fibre Cable ribbons 

    DJL LJL

    FDH 

    1  1 

    1  1 

  • UNCLASSIFIED | © NBN Co 2013

    Fibre Distribution Area Structure— Underground 2.1 Local Fibre Design ‐ approximately 400 Premises 

    22 

  • UNCLASSIFIED | © NBN Co 2013

    Fibre Structure—Aerial Type 2 Local Fibre Allocation 

    23 

    2  4  6  8  10  12  14  16  18  20  22  24 

    1  3  5  7  9  11  13  15  17  19  21  23 

    DJL

    Multiports Installed on the required Poles 

    Distribution fibre to next FDH 

    Distribution fibre to FAN  LJL

    FDH 

    Factory installed FlexNAP on cable 

    span 

    Larger Multiport terminals can be   ‘plugged’ in as additional capacity is required. 

    2 fibres allocated per 

    address 

    1ribbon (12 fibres) allocated to each 

    multiport 

    2  2 

    2  2 

    4 fibres allocated per NAP for addresses,     

    8 spare 

    12 

    Fibre Distribution Hubs (FDH) are planned for 1 fibre per address, plus associated splitter and distribution fibre. Additional pass‐through is provided for point to point services. 

    Splitters are only patched to addresses when required. Pass‐through connections provide point to point connectivity 

        

    FlexNAP access port – prefabricated with 4, 8 or 12 fibres per port

  • UNCLASSIFIED | © NBN Co 2013

    mmmm

    19003901002390

    Street lengthHorizontal at premisesVertical at premises

    IntersectionsTotal

    m m m m 6 

    Premise length =  39 Pole mount height = 

    Road Width 14m + 2x3m verge =  20 Premise width =  19 

    Fibre Distribution Area Structure—Aerial Type 2 Local Fibre Design – approximately 200 Premises 

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    24 

  • UNCLASSIFIED | © NBN Co 2013

    Fibre Structure—Aerial Type 2.1 Local Fibre Allocation 

    25 

    2  4  6  8  10  12  14  16  18  20  22  24 

    1  3  5  7  9  11  13  15  17  19  21  23 

    DJL

    Multiports Installed on the required Poles 

    Distribution fibre to next FDH 

    Distribution fibre to FAN  LJL

    FDH 

    Factory installed FlexNAP on cable 

    span 

    Larger Multiport terminals can be   ‘plugged’ in as additional capacity is required. 

    1 fibre allocated per 

    address 

    1ribbon (12 fibres) allocated across 2 

    multiports 

    1  1 

    1  1 

    4 fibres allocated per NAP for addresses,     4 spare every second 

    NAP 

    Fibre Distribution Hubs (FDH) are planned for 1 fibre per address, plus associated splitter and distribution fibre. Additional pass‐through is provided for point to point services. 

    Splitters are only patched to addresses when required. Pass‐through connections provide point to point connectivity 

          

    1  1 

    1  1 

        

    4  4 8  8 

    FlexNAP access port – prefabricated with 4, 8 or 12 fibres per port

  • UNCLASSIFIED | © NBN Co 2013

    Fibre Distribution Area Structure—Aerial Type 2.1 Local Fibre Design – approximately 400 Premises 

    26 

  • UNCLASSIFIED | © NBN Co 2013

    Fibre Serving Area Module Cables   

    27 

    16 Splitter Tubes (Both Directions) 4 Transit Tubes 432 Fibre Cable 

    8 Splitter Tubes (Both Directions) 2 Transit Tubes 216 Fibre Cable 

  • UNCLASSIFIED | © NBN Co 2013

    Summary of change impact

    Cells highlighted in green are values that have changed

    2x ODF DSS DJL HSD FDH HSL LJL LSS AJL MSS MPT SDS

    Capacity  2x576f FSAM 

     1x576 fibres 

     6xCables 

     1x72 fibres 

     576 premises 

     1x 576 fibres 

     10x cables 

     144f or 72f 

     6 or 12 MSS 

     12fibres 

     12ports 

    Premises Capacity      36,864       18,432            576            576            576   72 / 144   12   12 

    Max initial Utilisation 16% 33% 67% 67% 33% 33% 50% 83% 83% 33% 33%

    Physical Size  2Racks 

     560mm2 

     0.05m3 

     123mm2 

     0.24m3 

     603mm2 

     0.06m3 

     230mm2 

     0.03m3 

     28mm2 

     0.01m3 

    Max premises day 1        6,016         3,008            188            188            188              40   4   4 

    Capacity  3x432f FSAMs 

     432 fibres   6xCables 

     72 fibres   576 premises 

     1x 576 fibres 

     10x cables 

     144f or 72f 

     6 or 12 MSS 

     12 fibres   12 ports 

    Premises Capacity      82,944       27,648            576            576            576   144 or 72   12   12 

    Max initial Utilisation 22% 44% 67% 67% 65% 65% 50% 83% 83% 67% 67%

    Physical Size 2Racks

     377mm2 

     0.05m3 

     123mm2 

     0.24m3 

     603mm2 

     0.06m3 

     230mm2 

     0.03m3 

     28mm2 

     0.01m3 

    Max premises day 1      18,048         6,016            376            376            376              80   8   8 

    End User

    Today

    Future State

    100% SDU scenario

  • UNCLASSIFIED | © NBN Co 2013 Page 29 14-Sep-14

    To determine the impact of reducing the fibres allocated per premises. Specifically, the impact on Duct and Pit Augmentation required. To achieve this, four areas were selected to produce designs under different fibre allocation rules and compare the theoretical build requirements based on the BoQ. Areas were selected within the following constraints: -Two adjacent FSAMs (So they could be sensibly combined) -Combined less than 5000 premises (To be able to fit into 1x FSAM) -NDDs issued within the last 6 months (To improve the input data quality) -No aerial network (Subject of a different review) -Not outliers in terms of augmentation or new build quantities

    Appendix – Scope of evaluation study

  • UNCLASSIFIED | © NBN Co 2013 Page 30 14-Sep-14

    Test Areas

    Area  FSA  Type  Premises  Comparison type 

    Scenarios 

    Maitland NSW  2MAI 

    Regional town low density 

    4959 4889 

    Minimal manual intervention 

    Base Case (3f /SDU, 2f /CDU, 1.5f /MPS) Reduced Fibre Count (1.5f /SDU, 1.5f /CDU, 1.25f /MPS) 

    Victoria Park WA  6VIC 

    Metro area Medium density  3657 

    Minimal manual intervention 

    Base Case (3f /SDU, 2f /CDU, 1.5f /MPS) Reduced Fibre Count  (1.5f /SDU, 1.5f /CDU, 1.25f /MPS) 

    Toowoomba Qld  4TOB 

    Regional town low density  3500 

    Optimised Design 

    Base Case (3f /SDU, 2f /CDU, 1.5f /MPS) Reduced Fibre Count  (1.5f /SDU, 1.5f /CDU, 1.25f /MPS) 

    Penrith NSW  2PTH 

    Metro area Medium density  3500 

    Optimised Design 

    Base Case (3f /SDU, 2f /CDU, 1.5f /MPS) Reduced Fibre Count  (1.5f /SDU, 1.5f /CDU, 1.25f /MPS) 

  • UNCLASSIFIED | © NBN Co 2013 Page 31 14-Sep-14

    Summary of Results

    Cable / Duct  Connection points / Pits Duct Augmentation  All reduced  Pit Remediation  All reduced 

    New Duct  Mixed result  New Pits  All reduced 

    New + Augment duct  All reduced  New + Remediated pits  All reduced 

    DSS  All reduced  DJL  All reduced 

    LSS  All reduced  FDH  All reduced 

    MSS  All reduced  LJL  All reduced 

    SDS  Mixed result  AJL  All reduced 

    Total Cable length  All reduced  MPT  All reduced 

    Total Cable volume  All reduced  Total connection points  All reduced 

    Average cost saving = $315 per premises 

    Below is a summary of the results for the four areas comparing base case with a fibre allocation of 1.5 fibres per SDU, 1.5 fibres per commercial premises, 1.25 per MPS.

  • UNCLASSIFIED | © NBN Co 2013 Page 32 14-Sep-14

    Summary of Results

  • UNCLASSIFIED | © NBN Co 2013 Page 33 14-Sep-14

    Summary of Results Average savings achieved per Premises broken down by network component

  • UNCLASSIFIED | © NBN Co 2013

    Results per Site

  • UNCLASSIFIED | © NBN Co 2013 Page 35 14-Sep-14

    2MAI – Maitland Background info

    Country town north of Sydney Growing town so mixture of old and new homes 4900 premises 2130 sqm per premises 16.5 m of street per premises

  • UNCLASSIFIED | © NBN Co 2013 Page 36 14-Sep-14

    2MAI – Maitland Quantity results

    Base Case (Max 200m SDS)

    Compromise fibre allocation

    Minimum fibre allocation (Max 

    250m SDS)

    2x FSAMs, 3f/SDU, 2f/CDU, 1.5f/MPS

    1x FSAM, 1.5f/SDU, 1.5f/CDU, 1.25f/MPS

    1x FSAM, 1.25f/SDU, 1.25f/CDU, 1f/MPS

    Area (sqkm) 10.6 10.4 10.7Streetlength (km) 81.9 80.0 83.1SDUs/CDUs sites 3779 3799 3794MPS sites 291 282 287Total Premises 4959 4889 5035

    Distribution cable length within FSAM (km) 27.5 14.9 14.5Distribution cable length Outside FSAM (km) 3 0 0Distribution cable length total (km) 30.5 14.9 14.5FDHs 27 16 16PDHs 0 0 0Local + MSS cable length (km) 264 191 161.3Multiports 1158 709 648SDS cable length (km) 337.9 328.2 318.9

    Duct Augmentation (km) 25.2 17.4 15.6New Duct (km) 6.1 5 6.3Pit Remediation (Qty) 686 496 486New Pits (Qty) 19 11 7

  • UNCLASSIFIED | © NBN Co 2013 Page 37 14-Sep-14

    2MAI – Maitland Unit Cost results

    Base Case (Max 200m SDS)

    Compromise fibre allocation

    Minimum fibre allocation (Max 

    250m SDS)

    2x FSAMs, 3f/SDU, 2f/CDU, 1.5f/MPS

    1x FSAM, 1.5f/SDU, 1.5f/CDU, 1.25f/MPS

    1x FSAM, 1.25f/SDU, 1.25f/CDU, 1f/MPS

    Distribution cable 197$                                $                                 98  $                                 92 FDHs 125$                                $                                 75  $                                 73 

    ‐$                                 $                                  ‐    $                                  ‐   Local + MSS cable 426$                                $                              313  $                              256 Multiports 68$                                  $                                 42  $                                 37 SDS cable 477$                                $                              470  $                              443 

    ‐$                                 $                                  ‐    $                                  ‐   Duct Augmentation 422$                                $                              295  $                              257 New Duct 123$                                $                              102  $                              125 Pit Remediation ‐$                                 $                                  ‐    $                                  ‐   New Pits 7$                                     $                                   4  $                                   3 

    ‐$                                 $                                  ‐     $                                  ‐   Total 1,844$                           1,399$                           1,287$                          Saving relative to base case 24% 30%

  • UNCLASSIFIED | © NBN Co 2013 Page 38 14-Sep-14

    6VIC – Victoria Park Background info

    Southern part of Perth Mixture of old and new homes Some industrial 3657 premises 1100 sqm per premises 13.1 m of street per premises

  • UNCLASSIFIED | © NBN Co 2013 Page 39 14-Sep-14

    6VIC – Victoria Park Quantity results

    Base Case (Max 200m SDS)

    Compromise fibre allocation

    Minimum fibre allocation (Max 

    250m SDS)

    2x FSAMs, 3f/SDU, 2f/CDU, 1.5f/MPS

    1x FSAM, 1.5f/SDU, 1.5f/CDU, 1.25f/MPS

    1x FSAM, 1.25f/SDU, 1.25f/CDU, 1f/MPS

    Area (sqkm) 4.0 4.0 4.0Streetlength (km) 47.9 47.9 47.9SDUs/CDUs sites 1678 1678 1678MPS sites 391 391 391Total Premises 3657 3657 3657

    Distribution cable length within FSAM (km) 12.6 9.7 7.5Distribution cable length Outside FSAM (km) 12 7 7Distribution cable length total (km) 24.6 16.7 14.5FDHs 19 12 10PDHs 4 4 4Local + MSS cable length (km) 141.5 124.6 115.9Multiports 620 427 391SDS cable length (km) 130.7 153.3 155.1

    Duct Augmentation (km) 6.5 7.1 5.2New Duct (km) 5.4 5.3 5.3Pit Remediation (Qty) 287 243 217New Pits (Qty) 0 0 0

  • UNCLASSIFIED | © NBN Co 2013 Page 40 14-Sep-14

    6VIC – Victoria Park Unit Cost results

    Base Case (Max 200m SDS)

    Compromise fibre allocation

    Minimum fibre allocation (Max 

    250m SDS)

    2x FSAMs, 3f/SDU, 2f/CDU, 1.5f/MPS

    1x FSAM, 1.5f/SDU, 1.5f/CDU, 1.25f/MPS

    1x FSAM, 1.25f/SDU, 1.25f/CDU, 1f/MPS

    Distribution cable 215$                                $                              146  127$                             FDHs 119$                                $                                 75  63$                               

    ‐$                                 $                                  ‐    ‐$                              Local + MSS cable 310$                                $                              273  254$                             Multiports 49$                                  $                                 34  31$                               SDS cable 250$                                $                              293  297$                             

    ‐$                                 $                                  ‐    ‐$                              Duct Augmentation 148$                                $                              161  118$                             New Duct 148$                                $                              145  145$                             Pit Remediation ‐$                                 $                                  ‐    ‐$                              New Pits ‐$                                 $                                  ‐    ‐$                              

    ‐$                                ‐$                                ‐$                               Total 1,239$                           1,128$                           1,034$                          Saving relative to base case 9% 17%

  • UNCLASSIFIED | © NBN Co 2013 Page 41 14-Sep-14

    4TOB – Toowoomba Background info

    Large Regional town West of Brisbane, Qld Mostly new homes 3625 premises 2519 sqm per premises 19.3 m of street per premises

  • UNCLASSIFIED | © NBN Co 2013 Page 42 14-Sep-14

    4TOB – Toowoomba Quantity results

    Base Case(Issued NDDs)

    First RunRun 2 (Tighter MPT 

    packing)

    2x FSAMs, 3f/SDU, 2f/CDU, 1.5f/MPS

    1x FSAM, 1.5f/SDU, 1.5f/CDU, 1.25f/MPS

    1x FSAM, 1.5f/SDU, 1.5f/CDU, 1.25f/MPS

    Area (sqkm) 9.0 9.0 9.0Streetlength (km) 68.8 68.8 68.8SDUs/CDUs sites 2921 2877 2877MPS sites 112 121 121Total Premises 3560 3625 3625

    Distribution cable length within FSAM (km) 25.42 19.6 15.3Distribution cable length Outside FSAM (km) 19 9.5 9.5Distribution cable length total (km) 44.42 29.1 24.8FDHs 24 15 13PDHs 0 1 1Local + MSS cable length (km) 196 163.3 147.2Multiports 869 534 418SDS cable length (km) 145.3 167 202.5

    Duct Augmentation (km) 8.2 6.3 4.5New Duct (km) 7.5 7.4 7.6Pit Remediation (Qty) 124 119 87New Pits (Qty) 45 0 0

  • UNCLASSIFIED | © NBN Co 2013 Page 43 14-Sep-14

    4TOB – Toowoomba Unit Cost results

    Base Case(Issued NDDs)

    First RunRun 2 (Tighter MPT 

    packing)

    2x FSAMs, 3f/SDU, 2f/CDU, 1.5f/MPS

    1x FSAM, 1.5f/SDU, 1.5f/CDU, 1.25f/MPS

    1x FSAM, 1.5f/SDU, 1.5f/CDU, 1.25f/MPS

    Distribution cable 399$                                $                              257  $                              219 FDHs 155$                                $                                 95  $                                 82 

    ‐$                                 $                                  ‐    $                                  ‐   Local + MSS cable 440$                                $                              360  $                              325 Multiports 71$                                  $                                 43  $                                 33 SDS cable 286$                                $                              322  $                              391 

    ‐$                                 $                                  ‐    $                                  ‐   Duct Augmentation 191$                                $                              144  $                              103 New Duct 211$                                $                              204  $                              210 Pit Remediation ‐$                                 $                                  ‐    $                                  ‐   New Pits 23$                                  $                                  ‐    $                                  ‐   

    ‐$                                 $                                  ‐     $                                  ‐   Total 1,776$                           1,426$                           1,363$                          Saving relative to base case 20% 23%

  • UNCLASSIFIED | © NBN Co 2013 Page 44 14-Sep-14

    2PTH – Penrith Background info

    Metro area in western Sydney Mostly new homes 4689 premises 1098 sqm per premises 13.6 m of street per premises

  • UNCLASSIFIED | © NBN Co 2013 Page 45 14-Sep-14

    2PTH – Penrith Quantity results

    Base Case(Issued NDDs)

    First Run (Min. Manual work)

    Second Run (FDH placement optimised)

    2x FSAMs, 3f/SDU, 2f/CDU, 1.5f/MPS

    1x FSAM, 1.5f/SDU, 1.5f/CDU, 1.25f/MPS

    1x FSAM, 1.5f/SDU, 1.5f/CDU, 1.25f/MPS

    Area (sqkm) 5.2 5.2 5.2Streetlength (km) 63.6 63.6 63.6SDUs/CDUs sites 4228 4228 4228MPS sites 120 120 120Total Premises 4689 4689 4689

    Distribution cable length within FSAM (km) 15.9 18.4 10.5Distribution cable length Outside FSAM (km) 8 4 4Distribution cable length total (km) 23.9 22.4 14.5FDHs 29 15 15PDHs 0 1 1Local + MSS cable length (km) 237.7 171.1 167.5Multiports 1163 607 607SDS cable length (km) 202.3 276.5 276.5

    Duct Augmentation (km) 8 5.6 4.9New Duct (km) 9.4 7.04 6.64Pit Remediation (Qty) 296 137 107New Pits (Qty) 138 136 135

  • UNCLASSIFIED | © NBN Co 2013 Page 46 14-Sep-14

    2PTH – Penrith Unit Cost results

    Base Case(Issued NDDs)

    First Run (Min. Manual work)

    Second Run (FDH placement optimised)

    2x FSAMs, 3f/SDU, 2f/CDU, 1.5f/MPS

    1x FSAM, 1.5f/SDU, 1.5f/CDU, 1.25f/MPS

    1x FSAM, 1.5f/SDU, 1.5f/CDU, 1.25f/MPS

    Distribution cable 163$                                $                              153  $                                 99 FDHs 142$                                $                                 74  $                                 74 

    ‐$                                 $                                  ‐    $                                  ‐   Local + MSS cable 406$                                $                              292  $                              286 Multiports 72$                                  $                                 38  $                                 38 SDS cable 302$                                $                              413  $                              413 

    ‐$                                 $                                  ‐    $                                  ‐   Duct Augmentation 142$                                $                                 99  $                                 87 New Duct 200$                                $                              150  $                              142 Pit Remediation ‐$                                 $                                  ‐    $                                  ‐   New Pits 53$                                  $                                 52  $                                 52 

    ‐$                                 $                                  ‐     $                                  ‐   Total 1,480$                           1,270$                           1,189$                          Saving relative to base case 14% 20%

  • UNCLASSIFIED | © NBN Co 2013

    Fibre Design Changes: Update 1. Step Change Project 2. Backlog Progress

    Planning & Design July, 2013

  • UNCLASSIFIED | © NBN Co 2013 Page 48 14-Sep-14

    Executive Summary – Step Change Up till now... 

    The Issues... 

    What are we proposing...  So that in the future... 

    Planning and Design completes NDDs, releases these to Construction Detailed Design, and then these are released to Service Delivery Partners to complete walkout activities and then develop Detailed Designs, co‐ordinated by Construction Regional Project Directors.  

    • Bottlenecks will reduce, throughput will increase and the SDP’s can focus on building the Network. 

    • From issuing a CI to current Gate 1, the expected cycle times will go from the current  average of 86 days to 

  • UNCLASSIFIED | © NBN Co 2013 Page 49 14-Sep-14

    Telstra FIR & DD (as per Step Change) only goes part way to address the 2014 850k GNAF target

    Page 49

    June  July  August  September  October  November  December 

    • Step change improvements deliver only part of 2014 850k GNAFs target • In addition to implementing step change recommendations, improvement / process changes must also address current 

    inefficiencies in “NDD to DDD delivery model”. • A number of different delivery models for detailed design during transition, each with different accountabilities across the 

    “NDD to DDD process”. Much greater coordination  across functional areas needed to achieve the corporate targets. •  Staged rollout of these models will add additional complexity that could be more effectively managed with Single NBN Co 

    functional  Accountability for all Design work.  

    Contrib

    ution to 1M GNAF

     Target 

    80 FSAMS 

    Brownfields BAU  445 CI’s Issued 

    Step Change ∆  

    NT Model 

    Silcar ∆ 

    Greenfields BAU  

    Vision Stream ∆ 

  • UNCLASSIFIED | © NBN Co 2013 Page 50 14-Sep-14

    Benefits:  Reduce repetitive FIR walkouts by enforcing “Right First Time” approach  Reduce duration from 80+ days to maximum of 17 days 

     

    Design Field Support Services will conduct T‐FIRs and audit E‐FIR and AVRs 

    Benefits:  SDP improve capability  in using SpatialNet  Accelerated understanding of NDD’s provided by P&D     

    Regional Network Designer to support SDP’s in completing DDD’s  

    Benefits:  Faster issuance of Certificate of Accuracy  Better use of Arial Design Expertise  Consistent workflow to Aerial Design House  Removes requirement to constantly retrain SDP engaged ADH 

    National Arial Design within NBN Co control to provide consistency of Arial Design with direct Utility engagement 

    6 Eliminate Handover Points by streamlining the E2E NDD to DDD design process 

    Benefits:  Reduction of time spent on review and understanding  Reduction of multiple quality checks such as SpatialNet NCR  Reduced chance of error at handover  Improved Quality  

    Benefits:  Reduction of rework on BoQ  Accelerated throughput of DDD to construction 

    Providing  Regional Design Manager with authority to conduct in field design variations  

    Benefits:  NBN Co being accountable will drive the delivery of DDDs  Better training of resources at NBN Co in network design  More efficient utilisation of existing NBN Co design resources 

    Move Accountability for DDD from SDPs to  NBN Co Regional Design Teams 

    Field Support Services 

    NBN  Co DDD Support Capabilities 

    VIC/TAS  WA/SA  NT  QLD 

    NSW/ACT 

    Network Design 

    Construction Support 

    Field Support Services 

    Service Stream

     

    Transfield 

    Visio

    nstream 

    Synthe

    Silcar 

    Other 

    Gate 1 Gate2 

    Gate3 

    NDD  DDD 

    More than 10 Handover Points 

    Eliminated Handover Points within NBN Co with SDP 

    88+ Days 

    43+ Days 

    Service Delivery Partners 

    E‐FIR   

    AVR   

    T‐FIR   

    Service Delivery Partners 

    E‐FIR   

    AVR   

    T‐FIR   

    Design Field Support Services Audit  Execute 

    Service Delivery Partners 

    Service Delivery Partners 

    Regional Network Designers 

    NBN Co Regional Manager 

    NNR* NNR* 

    Multip

    ort 

    Multip

    ort 

    Ducts 

    Ducts 

    Pits 

    Pits 

    Remed

    iatio

    n Re

    med

    iatio

    Execute IFDV 

    In‐Field Design Variation 

    Service Delivery Partners 

    Telstra 

    NBN Co Design Cost Optimisation 

    Aerial Design House 

    Engage

     

    Design 

    Arial Design Expert 

    Arial Design Expert 

    ADH 

    NBN Co Arial Design Experts 

    Replace Arial with Underground 

    * NNR - Notification Not Required

    6 key improvements proposed to optimise the E2E design process

  • UNCLASSIFIED | © NBN Co 2013

    Reminder: Guiding principles will help limit number of variations, ensure constructability and efficiency

    Page 51

    • 1 master E2E process will be defined • Various contract models will have separate processes (if required), but they will be

    based on the master process

    • New process will have to ensure (via accountabilities, KPIs, feedback loops, etc.) - Schedule of FSAM designs to be aligned to POW, including prioritised

    programme of FSAMs over next 12 months (planned to be 18 months) - Deliverables meet all reasonable and agreed technical expectations of

    Construction. The new process will not aspire to over-deliver / over-engineer any outputs

    - Clear handover accountability from Design to Construction - Efficient design correction mechanisms and feedback loops in case of design

    errors (from the constructability point of view)

    • Clear end-to-end FSAM ownership along the entire design process • Process cycle time targets will be based on the 80-20% rule

    - Target durations will be realistic to meet in case of “business as usual” situations and exceptions

    • (When we set target durations) we assume that the all required contracts/relationships will be in place to facilitate To-Be

    - E.g. we won’t lose significant time in Electrical Design phase due to lack of proper cooperation with Utilities

    Limit # of Process

    Variations

    Ensure Constructability

    Ensure Efficiency

    New 

    New 

  • UNCLASSIFIED | © NBN Co 2013

    Fast Track CI Process results in significant Delivery Partner delays and design rework

    Flowthrough process supports multiple contract models, improves design quality and reduces rework Aerial MRW CI for Construction Activities 

    Remediation Commencement Notice DDD FIR NDD Prerequisite 

    Aerial MRW CI for Construction Activities 

    Remediation Commencement Notice DDD FIR NDD Prerequisite 

    Appr. 20 Bus. Days 10 Bus. Days 20 Bus. Days 5 Bus. Days 15 Bus. Days 60 Bus. Days

    5 Bus. Days 12 Bus. Days 40 Bus. Days 42 Bus. Days 29 Bus. Days 60 Bus. Days

    Review DDD Telstra Response - Part A - Part B

    Review

    Targeted Address Walkout (by exception)

    Pole Survey

    NDD

    FIR Draft (submit FDA by FDA)

    Remediation Handover

    Telstra LAANs

    CI for Field Walkout

    Commencement Notice

    Define FSAM Boundaries

    Address Walkout (MPS)

    Create Network Design

    Planning Assessment (incl. FDH location)

    FIR

    BoQ

    NBN LAAN

    Construction Documentation

    Electrical Design

    Gate 1Review DDD Telstra Response - Part A - Part B

    Gate 3 Review

    FIR

    NDD

    Address Walkout

    Remediation Handover

    Telstra LAANs

    CI for Field Walkout

    Commencement Notice

    Define FSAM Boundaries

    Create Network Design FIR

    BoQ

    NBN LAAN

    Construction Documentation

    Electrical Design

    Planning Assessment

    Gate 2 Review

    DDD

    Rework

    NBN DP Telstra

    ASP Tier 2/3

    Key Process Change

    Pain Point

    Pole Survey

    CICA

    CICA

    To-Be design process expected to deliver (CICA) FSAMs in 98 days. Current pain points have been addressed

    Electrical Design Documentation

    Aerial MRW

    Target duration 98 calendar daysTarget duration 98 calendar days

  • UNCLASSIFIED | © NBN Co 2013

    Seven strategic focus areas to elaborate the most critical elements of the new process

    Version 8 Page 53

    Strategic focus areas Required details / key questions Proposed

    representatives

    Define P&D-C handover

    Re-define support requirements

    Define handling of in-field variations /

    issues

    Re-define KPIs

    Re-define accountabilities

    • P&D and C have to define a mechanism ensuring that designs meet required quality levels and include details required for constructability.

    • Checks to focus on comprehensiveness /quality of high impact parts

    • New design process and org setup will require different level of support from the corporate functions (HR, OHS&E, stakeholder management). Required forms and volume of support to be defined

    • P&D and C to define how variations will be handled efficiently • Issues will require systematic tracking to get fixed within reasonable

    time and initiate continuous improvement measures within P&D

    • KPIs will track quality (constructability),cycle times and costs • KPIs will have to reflect the new org and accountability structure • KPIs will have to be aligned with the overall E2E reporting concept

    g p

    • Design and P&D-C handover RACI has to be aligned with new org setup and new design process(es)

    • Level of accountability has to be defined concretely • Change control processes and accountabilities to be defined

    pp

    • P&D: Peter Zordan • C: Adam Hatch • PIP, P&D/C, Quality to

    support

    • P&D: Peter Zordan • PIP MvB team

    • P&D: Peter Zordan • PIP P&D, C and E2E

    reporting teams

    y

    • P&D: Peter Zordan • C: Adam Hatch,

    Caroline Heinze • PIP, P&D/C, Quality

    pp

    • P&D: Peter Zordan • C: Adam Hatch • PIP, P&D/C, Quality to

    support

    Define contract model selection mechanism

    • P&D and C have to define a mechanism how they will agree on the construction model to be applied for the different FSAMs based on contractor capabilities, workload, etc. pp

    • P&D: Peter Zordan • C: Adam Hatch • PIP, P&D/C, Quality to

    support

    Resourcing • Updated resourcing requirements for new processes and approach to

    be defined

    • P&D: Peter Zordan • PIP, P&D/C, Quality to

    support

  • UNCLASSIFIED | © NBN Co 2013

    Current “NDD to CICA” process suffers from several Pain Points

    Version # Page 54

    Delivery Partner 

    Construction 

    Business Operations 

    Planning & Design – Fibre Access Designer 

    DA Document Administrator  PN Designer Passive Network (Regional)  EU Design Electrical Utility 

    COA Cost Optimisation Analyst 

    PRM Production Regional Manager 

    CA Contract Administrator CM Contract Manager 

    PM Project Manager 

    RS Project Regional Scheduler LASA LASA

    Land Access & Stat. Approvals Officer 

    Plan   Design   Accept Design    Contract Instruction  PDS Program Field 

    Inspections Design 

    Review G1  Detailed Design V1  DD V1 Review 

    TLS Duct Reservation/Optimisation 

     Detailed Design V2  DD V2 Review 

    TLS Duct Reservation/Optimisation 

    Commence‐ment Notice  CICA 

    DA Register NDD 

    EU

    Calculate Contract Sum‐FSAM 

    Submit CSPO Estimates – Issue CI Pack to 

    Contract Commercial 

    Review & Approve CSPO 

    Create CI Pack 

    Release CI Pack to SDP 

    Receive CI Pack 

    Review CI Pack 

    Provide Feedback to NBN Co 

    Create PDS Program 

    PDS Review by PM 

    Upload and Update PDS 

    Submission (P6) 

    Initiate Field Inspection 

    Inspect GNAF (Output: AVR) 

    Inspect Electrical 

    Inspect Pit&Pipe, Poles & Ducts 

    (Output: Telstra FIR) 

    Submit to Construction  (Sharepoint) 

    Prepare PAAR 

    Update FACT Schedule 

    Issue Design Review Documentation (PAAR, 

    FIR, E‐FIR, AVR) 

    Review PAR, AVR, Telstra FIR 

    Review E‐FIR 

    Review & Approve Service 

    Program 

    Gate1 PAAR Review Complete 

    Review Contract Sum 

    Issue Transmittal Summary to SDP 

    Receive Design Docs from SDP (DDD Package, Approvals, BoQ, BoM, Construction Program) 

    Review Handover Date and Augmentation 

    Requirement 

    Review Electrical Design 

    Review DDD 

    Review LAAN’s LIF, Statutory Applications 

    Issue Feedback Electrical Design 

    Issue Feedback DDD, LAAN, LIF, Statutory 

    Apps 

    Issue Review Documentation 

    Review Contract Sum 

    Issue Feedback on Contract Sum 

    Issue Feedback on Contract Sum 

    High Level Review of DDD  Submit to DDD to Telstra 

    Telstra confirm duct reservations 

    (Part A) 

    Telstra Review DDD for optimisation 

    (Part B) 

    Update Telstra LAAN Commencement 

    Notice 

    Assess Telstra Remediation 

    Commencement 

    Receive updated DDD from SDP 

    Review/Issue Construction Program 

    File 

     Review of DDD V2  Submit to DDD to Telstra 

    Telstra confirm duct reservations 

    (Part A) 

    Submit Access Agreement Schedule 

    Review LAAN’s LIF, Statutory Applications 

    Review Issue Feedback 

    Electrical Design 

    Review/Issue Feedback DDD, LAAN, LIF, Statutory Apps 

    Issue Review Documentation 

    Review Contract Sum 

    Issue Feedback on Contract Sum 

    Notify Design Gate Completion 

    Update FACT Schedule 

    Notify Electrical Design Gate Completion 

    PN

    Review ND‐Passive Network 

    Review ND‐Electrical 

    PRM

    Accept ND‐ Regional 

    COA

    PN

    COA

    CA

    PMO

    Review & Refine Fibre Serving Area 

    Define FSAM Boundary 

    Request & Update Telstra Duct Information  

    Perform Address Processing 

    Update FSA / FSAM Boundary 

    Create and Optimise Network Design 

    Perform Post FOND Design Remediation 

    Perform Network Design Quality 

    Review 

    Import Network Design & Extract  Duct Reservation 

    Rework Network Design 

    Create NDD 

    Release NDD to Telstra 

    Process Telstra Response Feedback 

    Release NDD to Construction 

    Modify Detailed Design 

    Validate Address & Cable Paths 

    Reconnect Fibre Cables 

    Perform DSS / TSS Review 

    Perform Design Validation 

    Prepare DDD for Submission 

    Validate Element Assoc. & 

    Optimisation 

    Assess & Resolve Design Non‐Conformities 

    Modify Detailed Design 

    Validate Address & Cable Paths 

    Reconnect Fibre Cables 

    Perform DSS / TSS Review 

    Perform Design Validation 

    Prepare DDD for Submission 

    Validate Element Assoc. & 

    Optimisation 

    Assess & Resolve Design Non‐Conformities 

    Prepare Contract Instruction Support 

    Pack 

    CM

    CA

    DA

    PN

    EU

    PRM

    PN

    COA

    PN

    PN

    RS DA

    PM PM

    PM

    EU

    PN

    LASA LASA

    EU

    PN

    DA

    COA

    PN

    DA

    PN

    PM

    PN

    PN

    DA

    PN

    PM

    PN

    RS

    PN

    PN

    PN

    PN

    LASA LASA

    EU

    DA

    COA

    EU

    PN

    DA

    Telstra Review DDD for optimisation 

    (Part B) 

    COA 

    Create Commencement Notice 

    PN

    PM

    Issue Commencement 

    Notice 

    Create CICA Pack 

    PN

    PM

    Issue CICA Pack to Contracts 

    Receive COA from SDP 

    Check COA against 

    Objections 

    Issue COA Feedback to SDP 

    PN

    CA

    PN PN

    Prepare & Package up PO to SDP 

    Pain Points 

    1.  Poor data quality leads to NDD inaccuracies and downstream rework  6. Design guidelines and rules are constantly changing so DPs struggle to benefit from experience based efficiency 

    2.  Utility providers are not engaging with DPs for aerial designs, resulting in delays and changes to underground  7. Construction drawings frequently don't match BOQ/BOM  

    3.  FIR is not completed on time or to required quality  8.  NBN designers spent most of their time solving ad‐hoc problems, not completing design reviews 

    4.  Relaxed gate standards encourage DPs to continue with bad practices  9. Design optimisation is delivering results, however it causes significant re‐work 

    5.  Constructability not sufficiently considered during DDD phase 10. 

    Fast tracking FSAMs and accountability gaps contribute to delays in obtaining CoA acceptance 

    4  4 

    10 

  • UNCLASSIFIED | © NBN Co 2013

    Therefore, without changing the design process, P&D would soon become a bottleneck

    Page 55

    ...as current process duration significantly deviates from model duration

    Source: P6 milestones at 27 May 2013

    0

    500

    1,000

    1,500

    01‐Jul‐12 01‐Aug‐12 01‐Sep‐12 01‐Oct‐12 01‐Nov‐12 01‐Dec‐12 01‐Jan‐13 01‐Feb‐13 01‐Mar‐13 01‐Apr‐13 01‐May‐13 01‐Jun‐13 01‐Jul‐13 01‐Aug‐13 01‐Sep‐13 01‐Oct‐13 01‐Nov‐13 01‐Dec‐13

    Forecast bsaed on current GNAF Design Rate

    PO for build issued FSAMS

    Baseline GNAF construction commenced

    At current design rate, P&D will not be able to feed Construction...

  • UNCLASSIFIED | © NBN Co 2013 Page 56 14-Sep-14

    Network Design 

    Document 

    Field Inspection Reports 

    Detailed Design 

    Document 

    Design & Civil Construction, Augment and New Build  

    (underground) 

    Remediation Works 

    Build, Splice & Test Fibre (aerial & underground) 

    Remediation Handover

    Handover to Network Operations

    10 days 17 days 5 days 3 months

    Design Optimisation 

    Con

    stru

    ctio

    n D

    eliv

    ery

    Part

    ner

    NB

    N

    Tels

    tra

    (a

    s C

    ontr

    acto

    r)

    or o

    ther

    Des

    ign

    Del

    iver

    y Pa

    rtne

    r

    Confirmed Order Response and comment 

    Provisional Order Response and comment 

    3 month Default Remediation Period

    3 month Generic Completion Time

    Tels

    tra

    (u

    nder

    DA)

    Ae

    rial A

    SP Field Survey Field Survey 

    & Prelim Design 

    Design Optimisation 

    Design  Finalisation, Approval and Make Ready Works 

    3 month Generic Completion Time

    3 months

    • Assess fitness (rod and rope activities) • Identify alternatives to maximise use • Identify required remediation works • Perform targeted Address walkout • Remediation Authorisations

    Contract Instructions

    Commencement Notice

    Proposed step change process

  • UNCLASSIFIED | © NBN Co 2013

    Aerial Included NBN Co Design Managed Process (Half Step)

    Network Design 

    Document 

    Field Inspection Report 

    Detailed Design 

    Document 

    Design & Civil Construction, Augment and New Build  

    (underground) 

    Remediation Works 

    Build, Splice & Test Fibre (aerial & underground) 

    Remediation Handover

    Handover to Network Operations

    10 days 17 days 5 days 3 months

    • Assess fitness (rod and rope activities) • Identify alternatives to maximise use • Identify required remediation works • Perform targeted Address walkout

    Design Optimisation 

    Serv

    ice

    Del

    iver

    y Pa

    rtne

    r

    NB

    N C

    o

    Tier

    2/3

    C

    ontr

    acto

    r

    Confirmed Order Response and comment 

    Provisional Order Response and comment 

    3 month Default Remediation Period

    3 month Generic Completion Time

    Tels

    tra

    (u

    nder

    DA)

    Aeria

    l ASP

    Field Survey & Prelim Design 

    Design Optimisation 

    Design  Finalisation, Approval and Make Ready Works 

    3 month Generic Completion Time

    3 months

  • UNCLASSIFIED | © NBN Co 2013 Page 58 14-Sep-14

    Backlog & Flow Through

    FSAM Activity  Pre July 2013  2013 Q3 

     013 Q4 

    2014 Q1 

    2014 Q2  

    2014 Q3 

    2014 Q4  

    2015 Q1 

    2015 Q2 

    BACKLOG 

    FSAMs Completed  36 

    FSAMs In‐Flight – Builds to complete  207 

    FSAMs for 850K – CICAs to be issued  116 

    FSAMs for 850K – Builds yet to start  116 

    FLOW THROUGH  

    New NDD Release Throughput  135  135  135  135  135  135  135  135 

    New CICA Release Throughput  90  135  135  135  135  135  135  135 

    Telstra Remediation Throughput  0  90  135  135  135  135  135  135 

    New Build Throughput  0  0  90  135  135  135  135 

    New Build In‐Flight  0  90  225  270  270  270 

    850k GNAFS 

    359 FSAMs  

    2.2M GNAFS 

  • UNCLASSIFIED | © NBN Co 2013

    2  2 

    19 

    1  1 

    0  0 

    0  0 

    0  0 

    NDD inHand

    PDS CI Gate 1(FIR)

    Gate 2(DDD)

    TelstraCommNoticeIssued

    Gate 3 CICA CoA

    4 weeks ago 3 weeks ago 2 weeks ago 1 week ago

    375  365 

    293 244  229 

    191 238 

    109 

    10 

    72 

    49 15 

    38 

    129 

    8  8  18 

    90 139  154  145  145 

    383 

    50

    100

    150

    200

    250

    300

    350

    400

    450

    NDD inHand

    PDS CI Gate 1(FIR)

    Gate 2(DDD)

    TelstraCommNoticeIssued

    Gate 3 CICA CoA

    Complete WIP Remainder

    Target 850k GNAF shows 145 designs requiring CICA; No FSAMs passed CICA in the last three weeks

    13 FSAMs are ready to issue CICA, however there is no DP to issue  to 24 FSAMs have achieved CICA, however were not requested by construction 3Target provided on 22 July 2013 

    Source: P6, extract taken 25-7-2013

    Data extracted: 25 July 2013 

    There are 1452 CICAs to be issued prior to 31 Oct 2013

    No new CICAs have been issued in the last 3 weeks

  • UNCLASSIFIED | © NBN Co 2013 Page 60 14-Sep-14

    Backlog of CNs to be Issued

    0

    10

    20

    30

    40

    50

    60

    Monthly FSAM NDDs & CNs Issued

    NIP 3.1.1 NDD(mth) Actual NDD(mth) CN Issued to Telstra

  • UNCLASSIFIED | © NBN Co 2013

    Notional FOND NDD Design – per FSAM

    Version # DD MMM YYYY Page 61

    Dwelling 

    A J L 

    MPT 

    MPT 

    Dwelling 

    Dwelling 

    Dwelling 

    Dwelling 

    Dwelling 

    Dwelling 

    Dwelling 

    L J L  FDH  D J L 

    A J L 

    D J L 

    D J L 

    D J L 

    A J L 

    FDH 

    D J L 

    D J L 

    D J L 

    D J L 

    FDH 

    MPT 

    Dwelling 

    Dwelling 

    Pits Duct

    17 Cables

    100 Cables 650 Cables 3000 Cables

    B D C E Fond Solve Order: # Zone B, D, C, E

    A

    Zone A: # Field optimisation for SDS

    paths, LICs, and Addresses.

    Zone B: # MPT location determined by

    pit size and SDS cable length.

    Zone C: # LJL located with FDH. # AJL location determined by

    pit size and an even distribution along MSS route.

    Zone D: # FDH location determined by

    MPT distribution.

    Zone E: # DJL location determined by

    FDH placement, available P100 duct, and185m limit on DJL to FDH.

    16 FDAs

    FAN 

  • UNCLASSIFIED | © NBN Co 2013 Page 62 14-Sep-14

    NDD - DDD Design Optimisation NBN

     Telstra 

    (Con

    tractor) 

    5d 

    Prepare Notional NDD 

    FOND  

    Telstra FIR 

    Targeted Address  Validation 

    15d to 20d 

    3d 

    DDD v1  Released 

    Telstra LAAN 

    CN  Review and approve Underground Design Changes  

    Planning Assessment 

    TLS10.1.3 

    Rod & Rope 

    10d 

    Contract Instruction Issued 

    10d 

    Commencement Notice 

    2d 

    35d to 40d 

    TLS10.1.2 TLS10.1.1 

    Telstra 

    (DA)  Part A Response 

    Part B Response 

    SpatialNet (NDD) 

    Address Processing 

    Recommended design changes Permitted design changes 

    Part A Response Part B Response 

    SpatialNet Updates 

    FDA 1  FDA 16 

    MapInfo GML Cable / Conduit CSV GNAF File with Targets 

    Bulk IFDV spreadsheet FIR Response spreadsheet Design change recommendations GNAF Assessment & Updates 

    FIR Completed 

    SpatialNet  (DDD v1) 

    PDS 

    TLS10.1.3 

    Remediation 

    Design Complete Notification 

    Critical Design Issue? 

    3d ??  12d to 17d 

    NBN P&D change review 

    NBN Field Services change review Telstra Design Evaluation review 

    Address 

  • This document sets out NBN Co’s proposals in respect of certain aspects of the National Broadband Network. The contents of this document represent NBN Co’s current position on the subject matter of this document. The contents of this document should not be relied upon by our stakeholders (or any other persons) as representing NBN Co’s final position on the subject matter of this document, except where stated otherwise. NBN Co’s position on the subject matter of this document may also be impacted by legislative and regulatory developments in respect of the National Broadband Network. All prices shown in this document are exclusive of GST.

    FOUO: Commercial | © NBN Co 2013

    This document sets out NBN Co’s proposals in respect of certain aspects of the National Broadband Network. The contents of this document represent NBN Co’s current position on the subject matter of this document. The contents of this document should not be relied upon by our stakeholders (or any other persons) as representing NBN Co’s final position on the subject matter of this document, except where stated otherwise. NBN Co’s position on the subject matter of this document may also be impacted by legislative and regulatory developments in respect of the National Broadband Network. All prices shown in this document are exclusive of GST.

    FOUO: Commercial | © NBN Co 2013

    3MLT-10 Deployment Trial Post Implementation Results and Recommendations - Industry Pack

    NBN Co Construction Services Group August 2014

  • FOUO: Commercial | © NBN Co 2013 FOUO: Commercial | © NBN Co 2013 64

    3MLT-10 Deployment Trial Background

    64

    The Melton 10 (3MLT-10) Deployment Trial was initiated by NBN Co to create an internal baseline/benchmark for programme, productivity and cost performance utilising:

    1. The Render deployment management system;

    2. Innovative specified equipment;

    3. Innovative build methods and work practices;

    4. Project governance initiatives; and

    5. Build Drop installation during LN/DN build.

    Telstra remediation works commenced in January 2014. NBN Co engaged Australian Broadband Company, Celemetrix, Comms Connect and Linktech directly to carry out the works with a uniform Schedule of rates. Specified equipment was free issued by NBN Co to the Contractors.

    3MLT-10 is a large residential FSAM with 2484 GNAF’s (2459 SDU, 25 MDU). It contains a mixture of old and new infrastructure and is a rocky area. There is also a relatively large number of 5 and 1 acre lots and standard residential blocks within the FSAM.

    The 3MLT-10 deployment was the first to utilise a Telstra FIR / NBN Co design. A separate Post Implementation analysis for Design is currently being completed by NBN Co’s Design group.

  • FOUO: Commercial | © NBN Co 2013 FOUO: Commercial | © NBN Co 2013 65

    3MLT-10 Scorecard for Comparison

    65

    Deployment data for all FSAMs ‘Ready for Service’ or ‘Build Commenced’ in the Ballarat 2 CSA (3BRA) has been used as the basis for comparison. This results in a group of 20 FSAMs for comparison.

    The scorecard items below was prepared and agreed by all of the NBN Co Stakeholders prior to commencement of the trial, and was to be the basis for comparison at the end of the trial period.

  • FOUO: Commercial | © NBN Co 2013 FOUO: Commercial | © NBN Co 2013 66

    A

    B

    C

    Completed FSAM's All FSAM's 3MLT-10

    LN/DN Cost per GNAF Comparison - 3BRA

    265 days

    344 days

    104 days

    Completed FSAM's All FSAM's 3MLT-10

    'Build Commenced to RFS' Comparison - 3BRA

    3MLT-10 Programme and Cost per GNAF Results

    3MLT-10 was completed:

    - 61% faster than FSAMs completed in 3BRA to date (161 business days faster)

    - 70% faster that all FSAMs commenced in 3BRA to date (240 business days faster)

    Programme

    3MLT-10 was completed:

    - 50% cheaper than FSAMs completed in 3BRA to date

    - 43% cheaper than all FSAMs commenced in 3BRA to date

    Cost per GNAF

  • FOUO: Commercial | © NBN Co 2013 FOUO: Commercial | © NBN Co 2013 67

    3MLT-10 Build Timeline

    Build drops:

    Distribution Network (FDA-00) – 7 clear weeks

    Telstra Remediation – 9 weeks

    NBN Co Deployment – 16 weeks

    Local Network – 11 clear weeks

    90% SC2 threshold is forecast to be achieved 29 August (131 business days)

    LN/DN:

  • FOUO: Commercial | © NBN Co 2013 FOUO: Commercial | © NBN Co 2013 68

    3MLT-10 Build Timeline compared to 3BRA FSAMs to date

    This chart includes the ‘Build Commenced to RFS’ programme for all FSAMs commenced to date in Ballarat 2 CSA (3BRA). Dark green are RFS FSAMs and light green are Build Commenced FSAMs. 3MLT-10 is RFS and is yellow. FSAMs are sorted by Build Commenced date.

  • FOUO: Commercial | © NBN Co 2013 FOUO: Commercial | © NBN Co 2013 69

    Source: P6

    3MLT-10 Productivity Results compared to Vic Averages

  • FOUO: Commercial | © NBN Co 2013 FOUO: Commercial | © NBN Co 2013 70

    3MLT-10 Customer Complaints Results

    Jan 14 – May 14 average complaints per premises passed

    % complaints/GNAFS

    0.00%

    0.50%

    1.00%

    1.50%

    2.00%

    2.50%

    WA TAS SA NSW VIC QLD NT ACT 3MLT10

    Despite having a lower level of overheads and carrying out Build Drops in parallel with the LN/DN deployment, the 3MLT-10 team received a very low level of complaints from the Public.

  • FOUO: Commercial | © NBN Co 2013 FOUO: Commercial | © NBN Co 2013 71

    3MLT-10 Scorecard at Completion

    71

    This 3MLT-10 Deployment Trial scorecard is included below.

    Note: HSE, Cost, Quality, Stakeholder Management data is updated to 30 June, excluding average cost per drop which is February data. Build data is updated to 30 July.

  • FOUO: Commercial | © NBN Co 2013 FOUO: Commercial | © NBN Co 2013 72

    3MLT-10 Render Deployment Management Results

    Following a technical Proof of Concept, the Render deployment management methodology was trialled in 3MLT-10. Render was used to:

    1. Automatically create the work scope, material BOQ directly from the DDD, including the asset data and construction sequence.

    2. Allocate work to Contractors in advance using the work scope information created.

    3. Automatically create the work schedule based on committed allocated resources.

    4. Release 4 days worth of work to crews each day(top up) to ensure continuity & visibility of work.

    5. Only release jobs that were ready to be done, i.e. all preceding tasks had been completed.

    6. Status completed work daily then optimally reschedule the remaining work.

    7. Capture as-built information at the task level on the day it was completed wherever possible, taking advantage of the detail extracted from the DDD in the task data.

    8. Automatically update progress status and view scope/resource/asset/location/cost/programme data centrally, visible on Google maps.

    9. Build the network as it was designed, eliminating “air gaps” and red-line mark ups.

    10. Sequence and manage build drops concurrently with the LN/DN build.

    The task based approach created by the Render tools took some time to become familiar to the teams after which time it was used to deploy and manage the work. There is still some work to be done on the functionality of the system however it performed well.

  • FOUO: Commercial | © NBN Co 2013 FOUO: Commercial | © NBN Co 2013 73

    3MLT-10 Deployment Management Results

    Reduced administration and simplify the following for NBN Co and Contractors:

    Work Scope – defining scope at the task/asset/address level

    Work Visibility - viewing all elements of the deployment on Google maps, from high level to task level to address level

    Variation Management – measure design and in-field variations at the task/asset/resource level

    Work Allocation – commit work volumes at the task level to Contractors

    Progress reporting – automated, accurate and updated on a daily basis (Report 004)

    Jeopardy management – manage issues at the task/asset/address/resource level

    HSE & Quality management – integrated at the task/resource/asset level

    Improve productivity, resource utilisation and forecast accuracy:

    Schedule optimisation – automated daily schedule optimisation, accurate forecasts

    Contractor productivity – ability to monitor productivity at the task/crew level

    Crew utilisation – maximised productivity of resources each day

    As-built management – updated as-built data accurately at the task/asset level daily

  • FOUO: Commercial | © NBN Co 2013 FOUO: Commercial | © NBN Co 2013 74

    3MLT-10 Innovative Specified Equipment Results

    SMALL DIAMETER CABLE

    Overall indications are that SDC is 10-20% faster to deploy

    Lighter and more flexible making the cable easier to handle and transport

    Easy to coil (smaller layout area required) for cable directional changes during haul, greater utilisation of Telstra infrastructure

    Less physical strain on crew – HSE benefit + reduction in crew number required for hauling

    Significantly increased installation efficiency – 5 mins install vs. 15 minute install for traditional multiport No requirement to mount the multiport Can be used in smaller pits, reducing the need for Telstra pit

    remediation which significantly reduces HSE risk associated with Asbestos Containing Material (ACM)

    Quality issue with connection waterproofing is under investigation by the CTO group.

    SMALL FOOTPRINT MULTIPORT

  • FOUO: Commercial | © NBN Co 2013 FOUO: Commercial | © NBN Co 2013 75

    3MLT-10 Innovative Build Methods and Work Practices Results

    Intelligent Optical Loss Measurement (IOLM) Testing Provided a 66% reduction in testing time Automated test result capture and upload Enabled real time defect rectification and

    smoother handover when FSAM complete/less defects

    Removed subjectivity regarding test results

    HSE initiatives:

    Safety barricading in lieu of bunting

    Waste water harvesting and re-use

    Distribution pipe straightener removed memory of the 100mm pipes minimising HS&E incidents

    In Line Jointing:

    Significantly reduces the number of splices required.

    100% Asset Locating

    Investment in asset locating resulted in zero asset strikes.

    Non destructive potholing/Hydro Vacuum:

    Ground Penetrating Radar was trialled and had mixed results impacted by the soil conditions

    Use of the Sub Surface Instruments All Material Locator (AML) was an effective method of identifying buried assets

    Design walkout/Constructability Review:

    Joint NBN Co/Contractor constructability walkout prior to completion of the design would have eliminated many of the design variations encountered.

    Purpose stocked Trailer for drops:

    Engaged Kennards to trial.

    Proven initial success.

  • FOUO: Commercial | © NBN Co 2013 FOUO: Commercial | © NBN Co 2013 76

    3MLT-10 Project Governance Initiatives Results

    Project Governance Meetings (twice a week)

    Provided a forum to jointly address schedule, resourcing and jeopardy issues

    Progress and earned value analysis by Contractor, CPA Report 004.

    Focus on Culture and Work Environment

    Established site office and warehouse and ran daily site (toolbox) meetings

    Less administration and simpler processes

    Focus on