Supporting European Aviation European ATM Master Plan Level 3 & Local Single Sky ImPlementation (LSSIP) reporting Awareness Presentation Module 1 – Introduction EUROCONTROL Edition: 12 October 2021
101

European ATM Master Plan Level 3 & Local Single Sky ...

Jun 20, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: European ATM Master Plan Level 3 & Local Single Sky ...

Supporting European

Aviation

European ATM Master Plan Level 3 & Local Single Sky ImPlementation (LSSIP) reporting

Awareness PresentationModule 1 – Introduction

EUROCONTROLEdition: 12 October 2021

Page 2: European ATM Master Plan Level 3 & Local Single Sky ...

Outline

• Module 1 – Introduction

• ATM Implementation Planning, Reporting and Monitoring Process:• Module 2 – Requirements• Module 3 – Deliverables• Module 4 – Process• Module 5 – Tools

• Module 6 – Summary

European ATM Master Plan Level 3 + the LSSIP reporting 2

European ATM Master Plan Level 3 +

the LSSIP reporting

Page 3: European ATM Master Plan Level 3 & Local Single Sky ...

IntroductionContent

European ATM Master Plan Level 3 + the LSSIP reporting 3

Scope and purpose of this presentation1Simplified framework2The broad picture3EUROCONTROL’s role4

Page 4: European ATM Master Plan Level 3 & Local Single Sky ...

Scope and purpose of this presentation

• Broad overview of the ATM Implementation planning and reporting mechanisms, at both(Pan-)European and local levels.

• Topics covered:

• The ATM Master Plan Level 3 (MP L3) Implementation view

• The Implementation Objectives• The Tools and Processes

• The criteria to determine implementation progress

• The Stakeholders and Users

• The Evolution

European ATM Master Plan Level 3 + the LSSIP reporting 4

Page 5: European ATM Master Plan Level 3 & Local Single Sky ...

Simplified framework

European ATM Master Plan Level 3 + the LSSIP reporting 5

Global Level

1 European/Regional Level

2

GANP

ICAO ASBU Monitoring

Reports per Region

European ATM Master

Plan

LSSIP Document(Local Single Sky Implementation)

State Performance

Plans

Stakeholder business plans and other local

plans

MP L3 / LSSIP planning and monitoring process ties together ATM planning and monitoring

3Local/State

Level

Page 6: European ATM Master Plan Level 3 & Local Single Sky ...

The broad picture

• Both European ATM Master Plan and ICAO Global Air Navigation Plan (GANP) needconcrete implementation plans and progress monitoring.

• Local and regional business plans (required by EU ATM legislation) are developed for allthe ATM Stakeholders.

European ATM Master Plan Level 3 + the LSSIP reporting 6

• Individual Stakeholders compile their ownimplementation progress reports.

• These are later consolidated at European level foroverall deployment planning and progress reportingpurposes.

Page 7: European ATM Master Plan Level 3 & Local Single Sky ...

EUROCONTROL’s role

• Coordination of the contributions to the annual European ATM Master PlanLevel 3 Plan (also sometimes called ESSIP - European Single SkyImPlementation).

• Facilitation of the development of national Stakeholders’ implementationprogress reports (i.e. LSSIP - Local Single Sky ImPlementation -documents).

• Production of consolidated reports on a European level:• ATM Master Plan (MP) Level 3 Progress Report;• ICAO GANP/ASBU monitoring report;• U-space services Implementation Monitoring Report

• Support to the decision-making by various steering bodies on any remedialaction needed to implement the plans.

• In addition, recently EUROCONTROL and SESAR Deployment Manager(SDM) have partnered up to ensure gathering of data, through the LSSIP, forthe production, by SDM, of the SDP Monitoring View

European ATM Master Plan Level 3 + the LSSIP reporting 7

Page 8: European ATM Master Plan Level 3 & Local Single Sky ...

Quiz on this module

European ATM Master Plan Level 3 + the LSSIP reporting 8

What do both European ATM Master Plan and ICAO Global Air Navigation Plan (GANP) need?

A Concrete implementation plans?

B Progress monitoring? Or,

C Both answers are correct?C

Page 9: European ATM Master Plan Level 3 & Local Single Sky ...

Supporting European

Aviation

European ATM Master Plan Level 3 & Local Single Sky ImPlementation (LSSIP) reporting

Awareness PresentationModule 2 – Process Requirements

EUROCONTROLEdition: 12 October 2021

Page 10: European ATM Master Plan Level 3 & Local Single Sky ...

ATM Implementation Planning, Reporting and MonitoringRequirements

European ATM Master Plan Level 3 + the LSSIP reporting 10

Why?1Master Plan Level 3 / LSSIP Mechanism2Link with other processes3

Page 11: European ATM Master Plan Level 3 & Local Single Sky ...

Why?

• Single European Sky (SES) and SESAR framework require Stakeholders to agree at European level on implementation actions prior to local deployment.

• Facilitate the achievement of endorsed implementation actions by all concerned ATM Stakeholdersas a major contribution to reach the expected benefits of SES and SESAR in particular against agreed performance targets.

European ATM Master Plan Level 3 + the LSSIP reporting 11

SESAR’s performance ambitions

Page 12: European ATM Master Plan Level 3 & Local Single Sky ...

Master Plan Level 3 / LSSIP Mechanism

Cyclic process including three main components:

1) Implementation Planning – MPL3 Plan

2) Implementation Progress reporting and monitoring at local Level – LSSIP documents

3) Implementation Progress reporting and monitoring at European Level – MPL3 Report

European ATM Master Plan Level 3 + the LSSIP reporting 12

European ATM Master Plan

Level 1 and 2

European ATM Master

Plan Level 3

1

2

3

Page 13: European ATM Master Plan Level 3 & Local Single Sky ...

Enabling the monitoring of the Global Air Navigation Plan (GANP)

International Civil Aviation Organisation

Link with other processes

European ATM Master Plan Level 3 + the LSSIP reporting 13

Enabling monitoring of the military organisation’s infrastructure where and when needed

European Defence Agency

Links at planning level with European Plan for Aviation Safety (EPAS)

European Aviation Safety Agency

Airspace Architecture Study (AAS), U-Space (Drones), RP3 questionnaires

European Commission

Network Systems Coordination and Synchronisation (NETSYS) and On-Line Data Interchange (OLDI) monitoring

Network Manager

No more double reporting for implementing stakeholders

SESAR Deployment Manager

It is part of the ATM Master Plan

SESAR Joint Undertaking

Page 14: European ATM Master Plan Level 3 & Local Single Sky ...

Quiz on this module

European ATM Master Plan Level 3 + the LSSIP reporting 14

Why the ATM Master Plan and LSSIP processes were introduced?

A To report the implementations to ICAO?

B To introduce synchronised actions, in order to achieve by all ATM stakeholders the expected benefits of SES and SESAR? Or

C At the request of EDA for military purposes?

B

Page 15: European ATM Master Plan Level 3 & Local Single Sky ...

Supporting European

Aviation

European ATM Master Plan Level 3 & Local Single Sky ImPlementation (LSSIP) reporting

Awareness PresentationModule 3 – Deliverables

EUROCONTROLEdition: 12 October 2021

Page 16: European ATM Master Plan Level 3 & Local Single Sky ...

ATM Implementation Planning, Reporting and MonitoringDeliverables

European ATM Master Plan Level 3 + the LSSIP reporting 16

Introduction on the European ATM Master Plan1The ATM Master Plan Level 3 – Implementation Plan2LSSIP Documents3The ATM Master Plan Level 3 – Progress Report4ICAO ASBU Implementation Monitoring Report5

Page 17: European ATM Master Plan Level 3 & Local Single Sky ...

Introduction on the Master PlanFramework

European ATM Master Plan Level 3 + the LSSIP reporting 17

• Main planning tool for defining ATM modernisation priorities and ensuring theimplementation of the SESAR Target Concept by all operational stakeholders.

• Sets the framework for the development activities performed by the SJU.

• Consistency and alignment of the deployment of the regulated CP1 ensured bycoordination with SESAR Deployment Manager (SDM) through the SESAR DeploymentProgramme (SDP).

• Developed under the governance of SJU through a dedicated project led byEUROCONTROL.

Page 18: European ATM Master Plan Level 3 & Local Single Sky ...

Introduction on the Master PlanThe three levels of the Master Plan

European ATM Master Plan Level 3 + the LSSIP reporting 18

SESAR Vision, Performance View, Operational View, Deployment View, Business View, and Risk Management.

Detailed information supporting Levels 1 and 3; available through the European ATM Portal

Link: (http://www.atmmasterplan.eu/)

Basis for short-term common implementation planning.

Master Plan Level 3 – PlanSet of commonly agreed Implementation Objectives and actions

Master Plan Level 3 – Progress ReportProgress assessment for all Implementation Objectives at ECAC level

Page 19: European ATM Master Plan Level 3 & Local Single Sky ...

Introduction on the Master PlanLevel 1

European ATM Master Plan Level 3 + the LSSIP reporting 19

Table of contents of the Master Plan (Level 1) document

Our vision of how ATM, and to some extent aviation, will operate by 2040

Four phases of change to deliver the Digital European Sky

2The SESAR Vision

The 9 Essential Operational Changes to deliver the Vision

SESAR Solutions in deployment, approaching maturity and still requiring R&D

4Operational View

Our performance ambitions for all performance areas

3Performance View

Deployment scenarios for mature solutions and those approaching maturity

Stakeholder category specific roadmaps (e.g. ANSPs, AUs, Airports, NM) and CNS Roadmap

5Deployment View

Including mitigating actions

7Risk Management

Investment profile over the coming years Direct and indirect benefit analysis over the same

time period

6Business View

Page 20: European ATM Master Plan Level 3 & Local Single Sky ...

Introduction on the Master PlanEssential Operational Changes

European ATM Master Plan Level 3 + the LSSIP reporting 20

9 Essential Operational Changes (EOCs)

CNS Infrastructure Services

ATM Interconnected Network

Digital AIM and MET Services

Airport and TMA performance

Fully Dynamic and Optimised Airspace Organisation

Trajectory Based Operations

Multimodal Mobility and integration of all airspace users

U-space Services

Virtualisation of Service Provision

Page 21: European ATM Master Plan Level 3 & Local Single Sky ...

Focus on the Master Plan Level 3 and its monitoringMPL3 Plan, MPL3 Report and LSSIP Documents

European ATM Master Plan Level 3 + the LSSIP reporting 21

European ATM Master Plan

Level 1 and 2

European ATM Master Plan

Level 3

The MP L3 consists of two strictly related parts: Plan and Progress Report

Complemented by the national Local Single Sky ImPlementation (LSSIP) documents.

Page 22: European ATM Master Plan Level 3 & Local Single Sky ...

Master Plan L3Implementation Plan

European ATM Master Plan Level 3 + the LSSIP reporting 22

Link: https://www.eurocontrol.int/publication/european-atm-master-plan-implementation-plan-level-3

MPL3Implementation

Plan

European ATM Master Plan Level 1 and 2

European ATM Master Plan

Level 3

Page 23: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 PlanMain features

European ATM Master Plan Level 3 + the LSSIP reporting 23

Updated every year, MPL3 Plan is a roadmap of commonly agreed activities to guide Stakeholders in the implementation of operationally and technically mature actions across the ECAC+ area.

Based on the ATM MP L1 and L2 (including SDM Deployment Programme (SDP) ATM Functionalities), the Network Strategy Plan, as well as SES Interoperability regulations.

Updated in light of the Airspace Architecture Study (AAS) and its Transition Plan (AAS-TP).

Under the governance of SJU (through the Master Planning Committee and the SESAR PJ20, a dedicated Project for its maintenance), and EUROCONTROL Provisional Council

Shows the deployment of SESAR prerequisites progress, as well as the progress in CP1 delivery until the target completion date.

Page 24: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 PlanTwo Deliverables

European ATM Master Plan Level 3 + the LSSIP reporting 24

Main document (Printed book)

Technical Annex – Engineering View (Soft Copy)

Delivered by mail

Also available online

High-level document

Only online PDF

Detailed information for LSSIP-related activities

Recommended to fill-in the LSSIP+ Database

Page 25: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 Plan 2021Contents

European ATM Master Plan Level 3 + the LSSIP reporting 25

1. Introduction• Context• Scope• How to read• What is new

2. Operational View• Organized by EOC• Stakeholders involved• Impacted KPAs• Performance stats

3. Deployment View• Organized by EOC• Objective descriptions

4. AAS Transition Plan• Scope of transition strategy• Mapping AAS vs MPL3 Plan

Annexes

1. Mappings of MPL3 Plan2. Applicability to Airports

3. L3 Implementation Roadmap4. Acronyms

Page 26: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 Plan 2021Dashboard

European ATM Master Plan Level 3 + the LSSIP reporting 26

MPL3 Plan Dashboard

2021

Intro page of the MPL3 Plan 2021 Overall statistics Geographical scope

CP1 statistics Objectives & Solutions grouped by EOC Stakeholders & Performance statistics

Page 27: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 Plan 2021Operational View

European ATM Master Plan Level 3 + the LSSIP reporting 27

Performance statistics

Synopsis of the EOC as per MPL1

The Operational View presents the main operational changes grouped by EOC and gives an overview of what is in the pipeline for deployment.

Objectives linked to a Solution in V5

3 groups for elements in V5

Objectives not linked to a Solution

Solutions in V5 not yet linked to an Objective

V4 Solutions

Elements in V4

Page 28: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 Plan 2021Deployment View

European ATM Master Plan Level 3 + the LSSIP reporting 28

MAIN ACTIONS by STAKEHOLDERS

The Deployment View gives a more detailed description of each Objective, including the link with the MPL2, the SDP, and the ICAO Aviation Systems Block Upgrades (ASBUs).

WHAT

WHEN

WHERE

LINKS

REGULATIONS & STANDARDS

BENEFITS

PROGRESS STATUS

INDUSTRIALISATION and STANDARDISATION

WHO

Page 29: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 Plan 2021Engineering View

European ATM Master Plan Level 3 + the LSSIP reporting 29

The Engineering View provides a complete description of each Implementation Objective with details of the Stakeholder Lines of Action (SLoAs) and reference to the necessary supporting material.

Page 30: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 Plan 2021Engineering View Example: SLOAs and Benefits

European ATM Master Plan Level 3 + the LSSIP reporting 30

CP1 / SESAR

STAKEHOLDERS INVOLVED

GEOGRAPHICAL APPLICABILITY

DESCRIPTION

Page 31: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 Plan 2021Engineering View Example: SLOAs and Benefits

European ATM Master Plan Level 3 + the LSSIP reporting 31

Page 32: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 Plan 2021Engineering View Example: SLOA Details

European ATM Master Plan Level 3 + the LSSIP reporting 32

Page 33: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 Plan AccessEngineering View access (I)

European ATM Master Plan Level 3 + the LSSIP reporting 33

Link: https://ost.eurocontrol.int/sites/lssip/SitePages/Home.aspx

Page 34: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 Plan AccessEngineering View access (II)

European ATM Master Plan Level 3 + the LSSIP reporting 34

Link: http://webprisme.cfmu.eurocontrol.int/elssip/lssip/index

Download Objective EV!

Page 35: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 Plan AccessEngineering View access (III)

European ATM Master Plan Level 3 + the LSSIP reporting 35

Link: https://www.atmmasterplan.eu/depl/essip_objectives

Page 36: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP Documents

European ATM Master Plan Level 3 + the LSSIP reporting 36

Link: https://www.eurocontrol.int/service/local-single-sky-implementation-monitoring

European ATM Master Plan Level 1 and 2

European ATM Master Plan

Level 3

National Local Single Sky ImPlementation (LSSIP)

documents

Page 37: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP DocumentsContext

European ATM Master Plan Level 3 + the LSSIP reporting 37

• A ”Reality check” on the MPL3 Plan, as reported by National Stakeholders, who sign and commit to the report documents.

• For each ECAC State (+ MUAC, Israel, and Morocco), one printed document containing the local implementation plan and progress report.

• A review of the situation at the end of the calendar year, the evolution over the past year, and the plans for next years until achievement of each individual Implementation Objective.

• LSSIP process is also extended to the whole ICAO EUR region: • directly used for ECAC States;• with questionnaire for other ICAO EUR States.

Page 38: European ATM Master Plan Level 3 & Local Single Sky ...

Local Single Sky

ImPlementation (LSSIP)

State

ToolsTemplateWorking

Instructions

LSSIP DocumentsElaboration process

European ATM Master Plan Level 3 + the LSSIP reporting 38

Support of dedicated Contact Person per State

Online LSSIP Database

National Focal Point + stakeholder Focal Points

National LSSIP Documents

Page 39: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP DocumentsTables of contents

The LSSIP documents are structured into 5 Chapters:

European ATM Master Plan Level 3 + the LSSIP reporting 39

Link: https://www.eurocontrol.int/service/local-single-sky-implementation-monitoring

Chapter 1 National ATM EnvironmentAn overview of the ATM institutional arrangements within the State (including an overview of the airspace organization and classification, the ATC Units, the ATM systems operated by the main ANSP(s)).

Chapter 2 Traffic and CapacityA comprehensive picture of the situation of Air Traffic, Capacity and ATFM Delay per each ACC in the State.

Chapter 3 Implementation ProjectsA set of the main implementation projects (at national and multinational level) which contribute directly to the implementation of the ATM MP related elements.

Chapter 4 Cooperation ActivitiesThis section deals with the other cooperation activities beyond the projects. It provides an overview of the all multinational initiatives.

Chapter 5 Implementation Objectives ProgressHigh-level information on progress and plans of each Implementation Objective.

Page 40: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP DocumentsDownload the LSSIP Documents

European ATM Master Plan Level 3 + the LSSIP reporting 40

Link: https://www.eurocontrol.int/service/local-single-sky-implementation-monitoring

Page 41: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP Reporting CycleImplementation status: the concept of progress status

European ATM Master Plan Level 3 + the LSSIP reporting 41

NB – this colour scheme applies to the LSSIP+ 2021 cycle

Completed

Ongoing

Planned

Not yet Planned

Not Applicable

Function in operational use

Implementation started but is not yet fully completed. The planned implementation date is within the SLoA / SDP DM end date or later (delays are properly detailed).

A planned schedule and proper (approved and committed budgeted) actions are specified within the SLoA / SDP DM end date for completion.

No plan yet: feasibility phase, no budget allocated, risk identification, etc.

Objective is not relevant for the State

100%

1% - 99%

0%

0%

-

Page 42: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ Reporting CycleImplementation status: completed

European ATM Master Plan Level 3 + the LSSIP reporting 42

2020 2021 2022 2023 2024 2025

State Decision on the Objective Completed In operational use

All applicable Checkpoints answered YESComputed percentage = 100%

No further reporting (unless requirements change)

FOC

LSSIP Cycle n

Page 43: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ Reporting CycleImplementation status: not applicable

European ATM Master Plan Level 3 + the LSSIP reporting 43

2020 2021 2022 2023 2024 2025

State Decision on the Objective Not Applicable • Outside of the Applicability Area / alternative solutions in place

• All Checkpoints answered N/A• No computed percentage

No further reporting (unless requirements change)

FOC

LSSIP Cycle n

Page 44: European ATM Master Plan Level 3 & Local Single Sky ...

2020

LSSIP+ Reporting CycleImplementation status: not yet planned

European ATM Master Plan Level 3 + the LSSIP reporting 44

2021 2022 2023 2024 2025

State Decision on the Objective Not yet Planned Activity not yet planned

• No final decision, no budget allocated, no plan to implement (not included in business plan)

• No implementation date

FOC

LSSIP Cycle n

Page 45: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ Reporting CycleImplementation status: planned

European ATM Master Plan Level 3 + the LSSIP reporting 45

2020 2021 2022 2023 2024 2025

State Decision on the Objective Planned Covered by Business Plan but activity not yet started

• All applicable Checkpoints answered NO• Computed percentage = 0%

LSSIP Cycle n

FOC

Page 46: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ Reporting CycleImplementation status: ongoing

European ATM Master Plan Level 3 + the LSSIP reporting 46

2020 2021 2022 2023 2024 2025

State Decision on the Objective Ongoing Implementation started

• At least one Checkpoint answered YES• Computed percentage = 1% - 99%

LSSIP Cycle n

FOC

Page 47: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ Reporting CycleExample #1: activity completion before FOC date

European ATM Master Plan Level 3 + the LSSIP reporting 47

2020 2021 2022 2023 2024 2025

State Decision on the Objective

LSSIP Cycle n

Ongoing 50% progress

FOC

Page 48: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ Reporting CycleExample #1: activity completion before FOC date

European ATM Master Plan Level 3 + the LSSIP reporting 48

2020 2021 2022 2023 2024 2025

State Decision on the Objective

LSSIP Cycle n+1

Ongoing 85% progress

FOC

Page 49: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ Reporting CycleExample #1: activity completion before FOC date

European ATM Master Plan Level 3 + the LSSIP reporting 49

2020 2021 2022 2023 2024 2025

State Decision on the Objective Completed 100% progress

LSSIP Cycle n+2

Actual implementation date FOC

Page 50: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ Reporting CycleExample #2: activity completion beyond FOC date

European ATM Master Plan Level 3 + the LSSIP reporting 50

2020 2021 2022 2023 2024 2025

State Decision on the Objective

LSSIP Cycle n

Ongoing 50% progress

FOC

Page 51: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ Reporting CycleExample #2: activity completion beyond FOC date

European ATM Master Plan Level 3 + the LSSIP reporting 51

2020 2021 2022 2023 2024 2025

State Decision on the Objective

LSSIP Cycle n+1

Ongoing 60% progress

FOC

Page 52: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ Reporting CycleExample #2: activity completion beyond FOC date

European ATM Master Plan Level 3 + the LSSIP reporting 52

2020 2021 2022 2023 2024 2025

State Decision on the Objective

LSSIP Cycle n+2

Ongoing 70% progress

FOC=

Planned implementation date

+1 year

Page 53: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ Reporting CycleExample #2: activity completion beyond FOC date

European ATM Master Plan Level 3 + the LSSIP reporting 53

2020 2021 2022 2023 2024 2025

State Decision on the Objective Ongoing 80% progress

LSSIP Cycle n+3

=FOC

Planned implementation date

Page 54: European ATM Master Plan Level 3 & Local Single Sky ...

FOC

LSSIP+ Reporting CycleExample #2: activity completion beyond FOC date

European ATM Master Plan Level 3 + the LSSIP reporting 54

2020 2021 2022 2023 2024 2025

State Decision on the Objective Completed

LSSIP Cycle n+4

<Actual

implementation date

100% progressNo “Late” status anymoreIn case implementation is completed beyond the FOC date, any delay will have to be properly detailed

Page 55: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ Reporting CycleCalculation example (only meant for illustrative purposes)

55

AOP4.2 A-SMGCS Runway Monitoring and RMCA (former Level 2)

European ATM Master Plan Level 3 + the LSSIP reporting

AOP04.2-APO01 Install required A-SMGCS RMCA function equipment 1 Activity started (e.g. Project kicked-off) 10%

2 Required A-SMGCS Level 2 control function system procured 30%

3 Required A-SMGCS Level 2 control function system installed 60%

Y -

Y 30/06/2019

Y 31/12/2020

AOP04.2-ASP01 Install required A-SMGCS RMCA function equipment

1 Activity started (e.g. Project kicked-off) 10%

2 Required A-SMGCS Level 2 control function system procured 30%

3 Required A-SMGCS Level 2 control function system installed 60%

Y -

Y -

N 31/12/2021

AOP04.2-ASP02 Train aerodrome control staff in the use of A-SMGCS RMCA

1 Activity started (e.g. Project kicked-off) 10%

2 Training ongoing 40%

3 Training completed 50%

N 30/11/2021

N -

N 31/03/2022

AOP04.2-ASP03 Implement approved A-SMGCS RMCA operational procedures

1 Activity started (e.g. Project kicked-off) 10%

2 Local A-SMGCS Level 2 operational procedures drafted 30%

3 Local A-SMGCS Level 2 operational procedures agreed, tested & validated 35%

4 Local A-SMGCS Level 2 operational procedures implemented, i.e. in operational use 25%

N -

N -

N -

N 30/06/2022

100%

40%

0%

0%

Completed

Ongoing (by:31/12/2021)

Planned (by: 31/03/2022)

Planned (by: 30/06/2022)

35%* Ongoing (by:30/06/2022)

Overall Implementation ASP

Overall Implementation APO 100%

13%

Completed

Ongoing (by:31/12/2021)

Airport completed all checkpoints.

AOP status is completed 100%

ANSP partially completed SLoA#1Status is ongoing

ANSP did not complete any checkpoint, but a date is foreseen. Status is planned

Same as for SLoA #2Status is planned

ASP status is ongoing 13% (40%÷3)

SloA status is completed 100%

SloA status is ongoing 40%

SloA status is planned

* This method to calculate the progress percentage is applicable only to non-CP1 Objectives

Page 56: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP DocumentsEUROCONTROL Engagement

European ATM Master Plan Level 3 + the LSSIP reporting 56

In 2021, 44 LSSIP documents were issued,i.e. 41 ECAC States, MUAC, Israel andMorocco.

EUROCONTROL has the commitment ofthe ECAC States since almost 30 years.

Page 57: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 Progress Report

European ATM Master Plan Level 3 + the LSSIP reporting 57

European ATM Master Plan Level 1 and 2

European ATM Master Plan

Level 3

Link: https://www.eurocontrol.int/publication/european-atm-master-plan-implementation-report-level-3

MPL3Progress Report

Page 58: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 Progress ReportContext

• Provides a Synoptic View, as well as a Deployment View at Implementation Objective level.• ECAC-wide implementation Progress Assessment.• Under the aegis of SESAR – more than 30 contributors from ATM industry.• MP L3 Progress Report is based mainly on LSSIP data but also on other sources (PRISME,

NM, Stakeholders).• Fully driven by EOCs and aligned to MP Levels 1 & 2.

European ATM Master Plan Level 3 + the LSSIP reporting 58

Link: https://www.eurocontrol.int/publication/european-atm-master-plan-implementation-report-level-3-2019

Page 59: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 Progress ReportContents

European ATM Master Plan Level 3 + the LSSIP reporting 59

Page 60: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 Progress ReportExample of ATC17

European ATM Master Plan Level 3 + the LSSIP reporting 60

Page 61: European ATM Master Plan Level 3 & Local Single Sky ...

MPL3 Progress ReportThe Map Tool

European ATM Master Plan Level 3 + the LSSIP reporting 61

EATM Portal: https://www.eatmportal.eu/working/depl/essip_objectives/map

Page 62: European ATM Master Plan Level 3 & Local Single Sky ...

ICAO ASBU Implementation Monitoring Report

European ATM Master Plan Level 3 + the LSSIP reporting 62

European ATM Master Plan

Level 1 and 2

European ATM Master Plan

Level 3

Link: https://www.eurocontrol.int/publication/aviation-system-block-upgrade-asbu-implementation-monitoring-report-2019

Page 63: European ATM Master Plan Level 3 & Local Single Sky ...

ICAO ASBU Implementation Monitoring ReportContext

The ASBU (Aviation System Block Upgrades) Implementation Monitoring Report is a keydocument for the EASPG (European Aviation System Planning Group) to monitor and analyse theASBU implementation within the EUR Region.

Developed by EUROCONTROL in cooperation with ICAO EUR/NAT Office.

First report prepared in 2015 for the reporting/reference period 2014.

Reference year 2019 - Last report based on GANP 5th edition (2016)

European ATM Master Plan Level 3 + the LSSIP reporting 63

GANP 5th Edition(reports with

ASBU Modules)

GANP 6th EditionFirst report due by December 2021

(with ASBU Elements)

Page 64: European ATM Master Plan Level 3 & Local Single Sky ...

ICAO ASBU Implementation Monitoring ReportData sources and geographical scope

Two main data sources:

LSSIP mechanism (43 States) - ECAC States and the 2 States with a comprehensive Agreement with EUROCONTROL (IL + MA); no double reporting to comply with ICAO monitoring requirements;

Dedicated questionnaire (9 States) - remaining non-ECAC States within ICAO EUR Region; reportingburden limited to a minimum with specific guidanceprovided by EUROCONTROL.

European ATM Master Plan Level 3 + the LSSIP reporting 64

Geographical scope of the report

Page 65: European ATM Master Plan Level 3 & Local Single Sky ...

ICAO ASBU Implementation Monitoring ReportGlobal Air Navigation Plan

Endorsed at 40th ICAO Assembly in October 2019

New GANP web portal: https://www4.icao.int/ganpportal/

ASBU Elements to be monitored from now on in EUR Region:

European ATM Master Plan Level 3 + the LSSIP reporting 65

Page 66: European ATM Master Plan Level 3 & Local Single Sky ...

Quiz on this module

European ATM Master Plan Level 3 + the LSSIP reporting 66

How many LSSIP Documents are published on the EUROCONTROL website each year?

A 5?

B 44? Or

C 92?

B

Page 67: European ATM Master Plan Level 3 & Local Single Sky ...

Quiz on this module

European ATM Master Plan Level 3 + the LSSIP reporting 67

How often is the Master Plan Progress Report produced?

A Every year?

B Every 2 years? Or

C Every month?

A

Page 68: European ATM Master Plan Level 3 & Local Single Sky ...

Quiz on this module

European ATM Master Plan Level 3 + the LSSIP reporting 68

Where can I access the Technical Annex – Engineering View ?

A In the LSSIP DB and SP?

B In the eATM Portal? Or

All platforms mentioned above?C

Page 69: European ATM Master Plan Level 3 & Local Single Sky ...

Supporting European

Aviation

European ATM Master Plan Level 3 & Local Single Sky ImPlementation (LSSIP) reporting

Awareness PresentationModule 4 – Process

EUROCONTROLEdition: 12 October 2021

Page 70: European ATM Master Plan Level 3 & Local Single Sky ...

ATM Implementation Planning, Reporting and MonitoringProcess

European ATM Master Plan Level 3 + the LSSIP reporting 70

Overall timeline1Supporting documents for LSSIP2LSSIP timeline3LSSIP Expert Group4

Page 71: European ATM Master Plan Level 3 & Local Single Sky ...

Overall TimelineAnnual cycle of MPL3 / LSSIP

European ATM Master Plan Level 3 + the LSSIP reporting 71

2020 2021 2022

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecNov Dec

LSSIP Event

Coversto be

slightly different

Coverto be slightly different

Page 72: European ATM Master Plan Level 3 & Local Single Sky ...

Regular update after each cycle

Supporting documents for LSSIP

European ATM Master Plan Level 3 + the LSSIP reporting 72

2021

LSS

IP+

Wor

king

Inst

ruct

ions LSSIP roles and responsibilities

Production of LSSIP document

Progress determination

LSSIP Database User Guide

LSSIP SharePoint User Guide

LSSIP Template / LSSIP Initial Draft

Page 73: European ATM Master Plan Level 3 & Local Single Sky ...

Focus on the timeline for LSSIPDetailed timeline for LSSIP + 2021

European ATM Master Plan Level 3 + the LSSIP reporting

Page 74: European ATM Master Plan Level 3 & Local Single Sky ...

Focus on the timeline for LSSIPRoles & Responsibilities

European ATM Master Plan Level 3 + the LSSIP reporting

National Focal Point Agency LSSIP Contact Person SDM Monitoring TeamF C

• Coordinator of national Stakeholders for LSSIP cycle

• Coordinator of data gathering for LSSIP document elaboration process

• Nominated by the State among the staff of the NSA / Regulatory Authority or ANSP

• Mediator between EUROCONTROL and the State during LSSIP cycle

• Works in coordination with the National Focal Point or other relevant State Stakeholders

• Provides support, instructions and guidance to the State

• Reference team for CP1 related contents and EU States

• Works in collaboration with LSSIP Contact Persons during the LSSIP Cycle

• Provides support, instructions and guidance to the CP1 Stakeholders directly and through the SDM Liaison Officers

Page 75: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP Expert GroupParticipants

European ATM Master Plan Level 3 + the LSSIP reporting 75

LSSIP EG is the sounding board for all LSSIP related items.

The Terms of Reference of the Group are published on LSSIP SharePoint

Page 76: European ATM Master Plan Level 3 & Local Single Sky ...

Quiz on this module

European ATM Master Plan Level 3 + the LSSIP reporting 76

When is the LSSIP Database frozen every year?

A In December?

B In January? Or

C In February?C

Page 77: European ATM Master Plan Level 3 & Local Single Sky ...

Supporting European

Aviation

European ATM Master Plan Level 3 & Local Single Sky ImPlementation (LSSIP) reporting

Awareness PresentationModule 5 – Tools

EUROCONTROLEdition: 12 October 2021

Page 78: European ATM Master Plan Level 3 & Local Single Sky ...

ATM Implementation Planning, Reporting and Monitoring Process Tools

European ATM Master Plan Level 3 + the LSSIP reporting 78

LSSIP+ Database1LSSIP SharePoint2European ATM Portal (Working)3EUROCONTROL Website4

Page 79: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ DatabasePersonalised Landing Page

European ATM Master Plan Level 3 + the LSSIP reporting 79

Page 80: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ DatabaseImplementation Objectives/ SDP Families – CP1/ SDP Monitoring

European ATM Master Plan Level 3 + the LSSIP reporting 80

By selecting the CP1/SDP button, the Stakeholder can access the CP1 / SDP monitoring items under the frame of the SDM.

Page 81: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ DatabaseView at Deployment Milestone Level

European ATM Master Plan Level 3 + the LSSIP reporting 81

AOP11.1-ASP01SDP 2.2.1 ASP DM1

AOP11.1-ASP02SDP 2.2.1 ASP DM2

Page 82: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ DatabaseHow to report the progress for each Objective

European ATM Master Plan Level 3 + the LSSIP reporting 82

Step 1: Checkpoints

1. Select the Objective

2. Select the relevant Stakeholder

3. Select the SLoA / DM

4. Fill-in the checkpoints (Y/N answer)

Step 2: Status for SLoA / DM

Step 3: Consolidated progress per Stakeholder

Step 4: Consolidated progress per Objective

1. Select a status for each SLoA (Completed, Ongoing, Planned, Not yet planned, Not applicable)

1. The progress of each Stakeholder is calculated based on weights assigned to each SLoA / DM level

1. The progress of each Objective is calculated by applying a weight on each Stakeholder contributing to the implementation of the relevant CP1 Objective

This methodology applies to CP1 Objectives regardless the CP1 Applicability Area. For all other Objectives, the simple average applies.

Page 83: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ DatabaseImplementation Projects

European ATM Master Plan Level 3 + the LSSIP reporting 83

Page 84: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ DatabaseSurveillance Questionnaire

European ATM Master Plan Level 3 + the LSSIP reporting 84

Page 85: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ DatabaseSESAR Solutions

European ATM Master Plan Level 3 + the LSSIP reporting 85

Page 86: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ DatabaseDLS Questionnaire – CP1/SDP Monitoring

European ATM Master Plan Level 3 + the LSSIP reporting 86

Page 87: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ DatabaseReports

European ATM Master Plan Level 3 + the LSSIP reporting 87

Page 88: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ DatabaseAnalytics

European ATM Master Plan Level 3 + the LSSIP reporting 88

Page 89: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP+ DatabaseMapping MPL3 Objectives – NETSYS ATM System Functionalities

European ATM Master Plan Level 3 + the LSSIP reporting 89

Page 90: European ATM Master Plan Level 3 & Local Single Sky ...

LSSIP Sharepoint

European ATM Master Plan Level 3 + the LSSIP reporting 90

Useful Links

Link: https://ost.eurocontrol.int/sites/lssip/SitePages/Home.aspx

Page 91: European ATM Master Plan Level 3 & Local Single Sky ...

European ATM PortalDeployment View

European ATM Master Plan Level 3 + the LSSIP reporting 91

Link: https://www.eatmportal.eu/working/

Page 92: European ATM Master Plan Level 3 & Local Single Sky ...

European ATM PortalImplementation Objectives Planning site

European ATM Master Plan Level 3 + the LSSIP reporting 92

Page 93: European ATM Master Plan Level 3 & Local Single Sky ...

European ATM PortalImplementation Objectives Monitoring Site

European ATM Master Plan Level 3 + the LSSIP reporting 93

Page 94: European ATM Master Plan Level 3 & Local Single Sky ...

EUROCONTROL Internet Website

European ATM Master Plan Level 3 + the LSSIP reporting 94

Link: https://www.eurocontrol.int

Page 95: European ATM Master Plan Level 3 & Local Single Sky ...

EUROCONTROL Internet WebsiteMaster Plan Architecture and Monitoring

European ATM Master Plan Level 3 + the LSSIP reporting 95

Link: https://www.eurocontrol.int/master-plan-architecture-and-monitoring

Page 96: European ATM Master Plan Level 3 & Local Single Sky ...

Quiz on this module

European ATM Master Plan Level 3 + the LSSIP reporting 96

What are the main 2 Tools to be used for the production of the LSSIP Document?

A The LSSIP+ Database and the LSSIP SharePoint site?

B The LSSIP Database and the EUROCONTROL website? Or

C The LSSIP SharePoint and the EUROCONTROL website?

A

Page 97: European ATM Master Plan Level 3 & Local Single Sky ...

Supporting European

Aviation

European ATM Master Plan Level 3 & Local Single Sky ImPlementation (LSSIP) reporting

Awareness PresentationModule 6 – Summary

EUROCONTROLEdition: 12 October 2021

Page 98: European ATM Master Plan Level 3 & Local Single Sky ...

SummaryContent

European ATM Master Plan Level 3 + the LSSIP reporting 98

MPL3 and LSSIP+ in a nutshell1Need more info?2Useful Links3

Page 99: European ATM Master Plan Level 3 & Local Single Sky ...

ATM Implementation Planning, Reporting and Monitoring:• Requirements• Deliverables• Process• Tools

European ATM Master Plan Level 3 + the LSSIP reporting 99

In a nutshell

Page 100: European ATM Master Plan Level 3 & Local Single Sky ...

Need more info?

• But what if you need more information?

European ATM Master Plan Level 3 + the LSSIP reporting 100

Update on current situation – 21st Oct 2021 Annual Event

Then bilateral meeting CP-FP

And consult the eATM Portal

And through your FP ask access to the LSSIP Database

And more info on SDP/CP1 through SDM Liaison OfficersAnd also at the 16 Nov dedicated SDM Monitoring Webinar

Page 101: European ATM Master Plan Level 3 & Local Single Sky ...

Supporting European

Aviation

Thank you for your attention!

Useful links

European ATM Master Plan https://www.eatmportal.eu/working/

All MP L3 https://www.eurocontrol.int/master-plan-architecture-and-monitoring

LSSIP Information https://www.eurocontrol.int/service/local-single-sky-implementation-monitoring

Contact [email protected]

https://www.sesardeploymentmanager.eu/publications/deployment-programme/SESAR Deployment Programme