Estimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, Construction Management Program Florida Institute of Technology
101

Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Feb 01, 2018

Download

Documents

trinhlien
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Estimating

in

Disaster Recovery

Prof. Ralph V. Locurcio, PE

Director, Construction Management Program

Florida Institute of Technology

Page 2: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 3: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

The 1991 Gulf War had just ended…

Page 4: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Debris was everywhere…

Page 5: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

750 Oil Fires blackened the skies…

Page 6: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

The Scope of Work…

Page 7: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Key Facilities…

3 Major Power Plants partially destroyed…

Page 8: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 9: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 10: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Electrical systems…

750 Oil Fires blackened the skies…

5000km of 300KV Power Lines…

Page 11: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 12: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Water systems…

2 Water Pumping stations & distribution lines…

Page 13: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 14: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Debris…

Roads & Bridges to be cleared…

Page 15: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Roads & Bridges…

Repave a major hiway…

Page 16: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 17: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Ports & Harbors…

2 Harbors mined & destroyed…

Page 18: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Fire damage…

Major facilities were torched…

Page 19: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Terrorist actions…

International Airport bombed & burned…

Page 20: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

300 Schools were severely damaged…

Unknowns…

Page 21: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 22: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 23: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 24: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 25: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 26: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 27: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 28: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 29: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 30: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 31: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 32: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 33: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 34: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 35: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 36: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 37: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Construction Methodology…

• Hired 11 Contractors

� Based on conceptual estimates

• Used Cost Plus Contracts

� No time for design

� Pre-qualified Contractors

� Made selection based on quals

� Mobilized with contingency

Page 38: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

The Estimating Process…

• 1200 Damage Survey Reports

� Prep Govt Estimate

� Excel Data Base

� Prioritize DSRs

• Issue Work Order to Contractor

� Compare estimates

� Negotiate differences

• Issue NTP

� Inspect labor & materials

� Difinitize at 50%

Page 39: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 40: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 41: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 42: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 43: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 44: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 45: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 46: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 47: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 48: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 49: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 50: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 51: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 52: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 53: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 54: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage
Page 55: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

55 January 20, 2010

Estimating Class at FIT

Page 56: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

My Background

� Corps of Engineers – 30yrs• Hurricane Eloise - PA 1975

• Hurricane Hugo - SC 1989

• Kuwait Reconstruction - 1992

• Hurricane Iniki - HI 1993

• Pinatubo Recovery - 1993

• Atlantic Hurricanes – 1994 to 1996

� Private sector engineering 1996-2004

� Florida Tech 2004 (4 Hurricanes)

Page 57: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Estimating defined…

� A complex process involving the collection of available information on the scope of a project, the expected resource consumption, and future changes in resource costs.

� This information is synthesized in a visualizationof the construction process and translated into an approximation of the final cost.

Page 58: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Qualifications of an estimator…

� Extensive knowledge of:� Construction processes & methods

� Materials & methods

� Contracts & work practices

� Construction documents & details

� Background business factors

� Design & code requirements

� Verbal & written communications

� Good common sense & judgment

Page 59: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Estimating & Bidding

Kickoff

MeetingWork

Plan

Establish

Standards

Update

Database

Prepare

Estimate

Document

Estimate

Review

Estimate

Adjust

Estimate?Submit

Bid

Project

Execution

Project

Completion

Yes

No

Revise

Lessons Learned

Feedback to improve data base

Reality Check Yes

No

Page 60: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Key Estimating Activities

Read the Plans,

Specs & Contract

Conduct

Site Visit

Decide

Construction

Method

Prepare Schedule

Plan for

SubcontractsPlan for EquipmentMaterial Take-Offs

Estimate costs

Determine

contingency

Analyze Risk

Factors

Finalize Bid

Page 61: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Components of an estimate…

� Project components

� Equipment needed

� Construction methods

� Temporary work items

� Support activities

� Externalities

Page 62: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Two broad types of estimates…

� Conceptual� Used for early decisions & feasibility

� Rough estimate using minimal data

� Relies heavily on past data

� Level of accuracy about 70%

� Detailed� Used for major decisions; i.e. bids & budgets

� Based on final design documents

� Level of accuracy up to 95%

Page 63: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Accuracy increases over time…

% Accuracy

% D

esign

0 25 50 90 100

100

90

60

30

Page 64: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Conceptual types:

� Based on prior experience:

� Weight check… weight of equipment

� Cost-capacity factor- ratio of Q/$

� Comparative cost of structure – $/unit

� Feasibility estimates

� Appropriations estimates

� Time & location adjustments

Page 65: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Comparative cost of structure…

� Basis is cost per unit based on past experience with similar units.

� Compare structures of like construction, (e.g. school: steel, concrete, quality, local labor, weather)

� Develop cost per unit, e.g.

A$/pupil = A Cost/A pupils

� Apply to new construction:

B Cost = B pupils x A$/pupil

Page 66: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Examples:

� Schools: $/pupil

� Bridges: $/feet of span

� Stadium: $/seat

� Hospital: $/beds

� Offices: $/ft2

� Warehouses: $/ft3

Page 67: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Variations of comparative cost…

� Plant cost ratio… process plant ratio

differentiates machine ft2 from admin ft2

� Floor area… cost/ft2 … but

� Total horizontal area… all floors equal

� Finished floor area… $ based on type finish

� Cubic foot of volume… floor height varies

Page 68: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Parametric estimates…

� Used for capital budgeting

� Expect 80-90% accuracy

� Based on historical data base

� Methods:

� Panel… hist data on “typical” panels

� Bay… hist data on “typical” bays

� Plant component… equip cost + other

TPC = ET/(1-PT)

Where ET=tot equip cost/(1-% all other cost items)

ET = $$$ equip/(1-70%)

Page 69: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Time & Location adjustments…

� Cost indexing

� Based on similar “group” of key items

� Compare “group” over time or location

� Final cost based on ratio x calculated cost:

Est Cost = T2/T1 x Calc Cost

Est Cost = (T2/T1)(L2/L1) x Calc Cost

Page 70: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Cost forecasting…

� “The future ain’t what it used to be”…

Yogi Berra

� Need to project costs to mid-point of the

construction year for budgeting

� Generally average past 3-5 years cost data & project

forward

Page 71: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Detailed estimates…

� Based on three primary factors:

A. Scope… quantities

B. Constructability… methods

C. Risk… externalities

Page 72: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

A. Scope factors…

� Technology in project - complexity

� Milestone deadlines for work - timing

� Material & equipment - availability

� Staffing needed – skill & availability

� Contract terms – allocation of risk

� Amount of competition - markets

Page 73: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

B. Constructability factors…

� Construction quality – skill required

� Allowable tolerances – productivity

� Complexity of design – learning curve

� Flexibility of methods – special terms

Page 74: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

C. Risk factors…

� Unspecified material or workmanship

� Differing site conditions

� Error in bidding

� Changes in cost over time

� Subcontractor error or failures

� Weather & environmental issues

� Strikes & labor issues

� Utilities & support issues

Page 75: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Estimating process…

1. Determine project characteristics:

Scope, constructability, risk

2. Examine the project design & site

3. Structure the estimate

4. Determine elements of cost

5. Calculate estimate

Page 76: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Examine Project Design…

� Technical specifications

� Referenced standards

� Project drawings

� Testing and performance

� Special methods or procedures

� Physical elements & site characteristics

� Errors & omissions

Page 77: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Structure the estimate…

� Structure often follows specification template

� Ensure nothing left out

� Need a plan for completing the project

� Logical flow of resources & materials

� Productivity factors

Page 78: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Determine elements of cost…

� Labor- craft & skill resources; sub-contractors; union

labor; wage rates; training; “effective” labor rates;

productivity factors (weather, complexity, experience,

management)

� Material- price, shipping, availability, storage, relation

to specifications

� Equipment- purchase vs. lease, single use, down time,

cost of maintenance

� Capital- interest rates, payment flow, retainage

� Time- overhead costs, required completion date,

Page 79: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Calculate the estimate…� Material take-off from plans

1. Quantities of all construction materials

2. Compare with specifications

� Labor cost for construction or installation

1. Effective labor rates

2. Team composition & duration

� Construction equipment schedule

1. On hand vs. lease or purchase

2. Time on job

� Follow elements of cost

1. Ensure all items are covered

Page 80: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Some Example Problems

� Calculate the estimated cost

� Solution in class

Page 81: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Conceptual Estimates

� Based on historical data

� Accuracy = +30%

� Used for planning purposes when no design exists

� Used to check validity of detailed estimate

Page 82: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Cost of equipment method…

� Assumes cost of equipment is dominant factor in plant cost

� Estimate based on % of cost allocated to equipment relative to total cost of facility

� Estimated cost is proportional to known cost

� Must adjust for time & location

Page 83: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Example 1… 5 min.

� Assume that the equipment portion of a chemical processing

plant constructed in 2006 cost $1.2M and the total plant cost was

$2.5M. Therefore the equipment portion of the total cost was

46%. Estimate the cost of a new plant with the same processes if

the equipment for the new plant has been determined to cost

$2.7M. Assume time and location factors are negligible in this

case.

� Solution:

Page 84: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Example 2…

� Assume that the equipment portion of a chemical processing plant constructed in 2006 cost $1.2M and the total plant cost was $2.5M. Therefore the equipment portion of the total cost was 46%. Estimate the cost of a new plant with the same process if the equipment for the new plant has been determined to cost $2.4M. Assume time and location factors are negligible in this case.

� Solution: C2/E2 = C1/E1 … solve for C2

C2 = [C1/E1] x E2

C2 = [$2.5M/$1.2M] x $2.4M

C2 = [2.08] x $2.7 = $5,625,000M

Page 85: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Volumetric unit measure…

� Similar to comparison of $/sf unit measure

� Used when facility has differing ceiling heights

� Calculate the $/cf of known facility

� Determine $/cf of known facility

� Calculate total cf of new facility

� Using known $/cf calculate cost of new facility

� Adjust for time and location

Page 86: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Example 2… 10 min.

� Determine the cost of a new warehouse which will have 3 distinct storage areas with differing ceiling heights. Area 1 = 12’; Area 2=14’ and Area 3 = 10’. The floor area of all three areas is 4000sf. A similar warehouse was constructed earlier this year for $2.4M. In that building the floor area was 8000sf and the ceiling height was a uniform 14’. Assume time and location factors are negligible in this case.

� Solution:

Page 87: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Example 2… � Determine the cost of a new warehouse which will have 3 distinct storage

areas with differing ceiling heights. Area 1 = 12’; Area 2=14’ and Area 3 = 10’. The floor area of each area is 4000sf. A similar warehouse was constructed earlier this year for $2.4M. In that building the floor area was 8000sf and the ceiling height was a uniform 14’. Assume time and location factors are negligible in this case.

� Solution: Existing Building A = 8000sf x 14’ = 112,000 cfCost/cf = $2,400,000 / 112,000 cf = $21.43/cfNew BuildingA1 = 4000sf x 12’ = 48,000 cfA2 = 4000sf x 14’ = 56,000 cfA3 = 4000sf x 10’ = 40,000 cfTotal = 144,000 cfCost = 144,000 cf x $21.43/cf = $3,085,714

Page 88: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Adjusting for time…

� Prices “escalate” over time due to inflation

� Must adjust estimated cost to “mid-point” of construction.

� Determine period of construction

� Determine start date of construction

� Determine mid-point of construction = average cost

� Determine “escalation rate” = given index

� Multiply estimated cost by “escalation rate”

� Note: escalation is compounded, ie. increase is cumulative over

number of years of escalation

Page 89: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Adjusting for location…

� Prices differ by region of the country

� Must consult a reliable index to determine “relative” cost of

construction between regions

� RS Means Cost Data or Engineering News Record are examples

� Adjustment is a simple ratio multiplied times the estimated

construction cost.

� So… C2/C1 = L2/L1 X Estimated Construction Cost

and C2 = C1 x L2/L1

Page 90: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Example 3… 15 min.

� You have been asked to prepare a conceptual cost estimate for the construction of a new university dormitory at Florida Tech to open in 2010. You have 2005 RS Means data that provides a cost of $30,000/bed for similar dormitories in the northeast of the US, and a construction period of 2 years. The Means data states that construction costs escalate at 10% per year in the southeast. If the dorm is to house 200 students at Florida Tech and the Means Cost Comparison Index between the northeast and southeast is 0.80, what is the estimated cost for the new library at Florida Tech at the mid-point of construction?

� Estimated Florida Tech cost:______________________

Page 91: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Solution to pop quiz…

1. $30,000 per bed x 200 beds =

$6,000,000… in the northeast in 2005

2. In the southeast in 2005…

$6,000,000 x 0.80 = $4,800,000

3. Construction start is…

Occupancy – 2 years = 2010 – 2 = 2008

4. Mid-point of construction is =

2008 + 1 = 2009

5. Years of escalation…

2009 – 2005 = 4 yrs

Page 92: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Solution to pop quiz…

6. Escalation:

$4,800,000 x 1.10 = $5,280,000 (2005-06)

$5,280,000 x 1.10 = $5,808,000 (2006-07)

$5,808,000 x 1.10 = $6,388,800 (2007-08)

$6,388,800 x 1.10 = $7,027,680 (2008-09)

Page 93: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Solution…

Therefore… the estimated cost of the new dormitory for

Florida Tech at the mid-point of construction in 2009 is:

$7,027,680

Page 94: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Cost Engineering Class

� Intro problem… garden shed

� Processes covered

� Conceptual estimating… 3 classes

� Detailed Estimating… 25 classes

� Materials covered… steel, masonry, wood

� Topics… foundations, walls, floors, roofing

� Industry professionals… 4 classes

Page 95: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

Semester Project

� Groups bid on actual project

� Lite commercial office = 3000sf

� Typical Residence = 2400sf

� Bids presented to panel of professional judges

� Mystery guest invited

Page 96: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

96 January 20, 2010

Industry Participation at FIT

Page 97: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

97 January 21, 2011

Harry Johnson explains BRPH estimating…

Page 98: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

98 January 21, 2011

Phillip Jarvis explains how estimating is done

at Burgoon-Berger

Page 99: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

The class bids on real projects

99 January 21, 2011

Page 100: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage

100 January 21, 2011

We appreciate industry support!

Page 101: Estimating in Disaster · PDF fileEstimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, ... Determine the cost of a new warehouse which will have 3 distinct storage