CON 4003 CON 4003 CVE 4073/5073 CVE 4073/5073 Construction Cost Construction Cost Estimating Estimating Class #2: The Estimating Class #2: The Estimating Process Process Prof. Ralph V. Locurcio, Prof. Ralph V. Locurcio, PE PE
Jan 03, 2016
CON 4003 CON 4003 CVE 4073/5073CVE 4073/5073Construction Cost EstimatingConstruction Cost Estimating
Class #2: The Estimating Class #2: The Estimating ProcessProcess
Prof. Ralph V. Locurcio, PEProf. Ralph V. Locurcio, PE
The Estimating Process-1The Estimating Process-1 Decision to bidDecision to bid Form the estimating teamForm the estimating team Estimate work planEstimate work plan
Type of estimateType of estimate ProceduresProcedures DocumentationDocumentation
Risk & contingency analysisRisk & contingency analysis Review & check the estimateReview & check the estimate Finalize the estimateFinalize the estimate
The Estimating ProcessThe Estimating Process
KickoffMeeting
WorkPlan
EstablishStandards
UpdateDatabase
PrepareEstimate
DocumentEstimate
ReviewEstimate
Adjust Estimate?
SubmitBid
ProjectExecution
ProjectCompletion
Yes
No
Revise
Lessons Learned
Feedback to improve data base
Re
ality Ch
eck
Estimate work planEstimate work plan Type of estimate required Deliverables by subcontractors Budget for the estimate Staffing Schedule Methodology Controls & reviews Presentation format & production
Prepare the estimatePrepare the estimate Conceptual estimateConceptual estimate
Decision on unitsDecision on units Adjustments for time & locationAdjustments for time & location
Detailed estimateDetailed estimate Material take-offMaterial take-off Equipment & cycle timeEquipment & cycle time Labor & productivityLabor & productivity Admin+overhead+logistics+profitAdmin+overhead+logistics+profit
Basic estimating Basic estimating procedureprocedure
Read the plans, specs & contractRead the plans, specs & contract Conduct a site investigationConduct a site investigation Decide on construction methodDecide on construction method Prepare schedulePrepare schedule Material quantity takeoffsMaterial quantity takeoffs Plan for equipmentPlan for equipment Plan for subcontractsPlan for subcontracts Estimate costs of labor & Estimate costs of labor &
materialsmaterials Assess risksAssess risks Determine contingencyDetermine contingency
Basic estimating Basic estimating procedureprocedure
Read the Plans, Specs & Contract
Conduct Site Visit
Decide Construction
MethodPrepare Schedule
Plan for Subcontracts
Plan for EquipmentMaterial Take-Offs
Estimate costs
Determine contingency
Analyze Risk Factors
Finalize Bid
Conduct thorough site Conduct thorough site visitvisit
Physical characteristicsPhysical characteristics Sub-surface conditionsSub-surface conditions Site logistics for construction Site logistics for construction
layoutlayout Condition of roads & bridgesCondition of roads & bridges Storage space for lay-downStorage space for lay-down Security requirementsSecurity requirements Operational requirementsOperational requirements
Read the plans, specs & Read the plans, specs & contractcontract
Contract terms & Contract terms & conditionsconditions
Payment & penaltiesPayment & penalties Scope and quantities Scope and quantities Complexity of constructionComplexity of construction Completeness of plansCompleteness of plans Quality of materials Quality of materials
requiredrequired
Decide construction Decide construction methodmethod
Basic approach & teamingBasic approach & teaming Work breakdown structureWork breakdown structure Skills of work crewsSkills of work crews Decision on work to be Decision on work to be
subcontractedsubcontracted Timing of individual activitiesTiming of individual activities Phasing of crews & subs on sitePhasing of crews & subs on site Procurement of equipmentProcurement of equipment Flow of materials & laydownFlow of materials & laydown Cash flow projectionCash flow projection
Conceptual work Conceptual work scheduleschedule
Based on contract provisionsBased on contract provisions Sequence of workSequence of work Operational constraintsOperational constraints Site constraintsSite constraints Weather & safety factorsWeather & safety factors Lead time for materialsLead time for materials Availability of subcontractorsAvailability of subcontractors
Material quantity takeoffMaterial quantity takeoff Systematic breakdown of unitsSystematic breakdown of units Study plans & specsStudy plans & specs Bid instructions, format & Bid instructions, format &
alternatesalternates Follow sequence of constructionFollow sequence of construction Categorize materials & laborCategorize materials & labor Check for duplicates & Check for duplicates &
omissionsomissions Document all workDocument all work Review & check for errorsReview & check for errors
Calculate direct costsCalculate direct costs
Materials, labor, equipmentMaterials, labor, equipment Subcontractor bidsSubcontractor bids Contact suppliersContact suppliers Market factors applyMarket factors apply Establish and update cost Establish and update cost
data basedata base
Calculate indirect costsCalculate indirect costs MobilizationMobilization Field officeField office InsuranceInsurance BondsBonds Taxes & permitsTaxes & permits CleanupCleanup DemobilizationDemobilization
Conduct risk analysisConduct risk analysis Complexity of plans & specsComplexity of plans & specs Terms of contract & penaltiesTerms of contract & penalties Experience with ownerExperience with owner Timing of projectTiming of project Market factors for labor & materialsMarket factors for labor & materials Weather & safety Weather & safety Other uncertainties effecting Other uncertainties effecting
executionexecution Probability of occurrence of eachProbability of occurrence of each
Determine contingencyDetermine contingency
Percentage of base estimatePercentage of base estimate Determine high cost risk Determine high cost risk
factorsfactors Expected net risk based on Expected net risk based on
probabilityprobability Aggregate total project riskAggregate total project risk
The Estimating ProcessThe Estimating Process
KickoffMeeting
WorkPlan
EstablishStandards
UpdateDatabase
PrepareEstimate
DocumentEstimate
ReviewEstimate
Adjust Estimate?
SubmitBid
ProjectExecution
ProjectCompletion
Yes
No
Revise
Lessons Learned
Feedback to improve data base
Re
ality Ch
eck
That’s all for today…That’s all for today…
Slides are on my web siteSlides are on my web site My web site:My web site:
www.my.fit.edu/~locurciowww.my.fit.edu/~locurcio