Construction of Peña Bridge - March 2013 East Rail Line Update FasTracks Citizens Advisory Committee Dec. 11, 2013 Courtesy of HDR, Inc, © 2013, Keith Philpott Courtesy of HDR, Inc, © 2013, Keith Philpott
30

East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

Nov 01, 2018

Download

Documents

truonghanh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

Construction of Peña Bridge - March 2013

East Rail Line Update FasTracks Citizens Advisory Committee

Dec. 11, 2013

Courtesy of HDR, Inc, © 2013, Keith Philpott

Courtesy of HDR, Inc, © 2013, Keith Philpott

Page 2: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

2

Kevin Flynn RTD Eagle Project Public Information Manager

East Rail Line Update

Page 3: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

3

Eagle P3 Project

• East Rail Line offers 35-minute travel time to DIA

• Northwest Rail Westminster Segment offers 11-minute travel time to

Westminster

• Gold Line offers 25-minute travel time to Ward Road

• Project capital budget $2.2 billion

Page 4: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

4

RTD Board Eagle Project Directors

Eagle Project Area

Bill James

District A – central Denver

Barbara Deadwyler

District B – east-northeast

Denver, DIA, north Aurora

Angie Malpiede

District C – northwest

Denver, DUS, Globeville

Larry Hoy

District J – Westminster

Lorraine Anderson

District L – southwest

Adams County, Arvada

Natalie Menten

District M – Wheat Ridge

Page 5: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

5

Eagle P3 Progress • 50 percent complete

• 28 of 32 bridges

under construction

(18 on East)

• 9 of 15 stations under

way (6 on East)

• Nearly 26 of 36 miles

under construction

• All 50 commuter rail

car body shells

complete, first 20 in

Philadelphia for

assembly and testing

Commuter rail vehicle at Hyundai Rotem plant in Philadelphia – October 2013

Page 6: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

6

Eagle P3 Progress

Unloading commuter

rail car body shell at

Port of Philadelphia,

Sept. 23, 2013

Page 7: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

7

Eagle P3 Progress

Design DBE Design SBE Construction DBE Construction SBE

Actual $18.0 $7.1 $96.8 $22.7

Commitments $19.1 $7.3 $164.7 $41.2

Goal $17.1 $3.0 $172.5 $43.2

111% of goal 239% of goal

95% of goal

96% of goal

$0.0

$20.0

$40.0

$60.0

$80.0

$100.0

$120.0

$140.0

$160.0

$180.0

$200.0

$ m

illio

ns

DBE/SBE Goals

Local/Disadvantaged/Small Business Participation

• $840 million dollars to 390 Colorado businesses

• $232 million to 160 D/SBE businesses

• WIN hiring: 43 local trainees hired on Eagle Project

Page 8: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

8

Upcoming Construction

East Rail Line – Work Areas

Josephine St. railroad crossing

Monaco Parkway at Smith Road

Quebec frontage at Smith Road

Smith Rd./Havana St. railroad

I-70 Flyover Bridge at Airport Blvd.

East Rail Upcoming Construction

Page 9: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

9

Proposed Station Names

38th & Blake

40th & Colorado

Central Park

Peoria

40th & Airport • Gateway Park (change)

Denver Airport (change)

Page 10: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

10

Concurrent Projects

Peoria Crossing

• Bridge piers and

abutments up

• Approach walls

underway

• Frontage Road

connections from

33rd and 39th

avenues

• Demolition along

the northbound

Peoria lanes

Aerial rendering of Peoria Street grade separation

Page 11: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

11

Concurrent Projects

DIA Hotel and Transit Center

• New detours on Terminal East public

roads in place until late 2014

• Terminal West detour closures to be

lifted this weekend

• Train platform canopy steel complete,

ironworkers now installing steel for

public plaza canopy

• Concrete work complete to Level 5

including public plaza

• Installation of exterior walls to begin

this month

Train platform plaza, hotel above

Page 12: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

12

Construction Progress

Commuter rail maintenance facility, November 2013

RTD commuter rail

maintenance facility

• 230,000-square foot,

four-level building will

house a staff of 240

• Yard storage for up to 80

vehicles

• When completed in 2014,

it will be a LEED Silver

Certified building

• Located at 5151 Fox St.,

in the Globeville

neighborhood of Denver

Page 13: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

13

Construction Progress

Union Station CRT

Platform

Page 14: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

14

Construction Progress

Smith Road

reconstruction,

Colorado Boulevard

to Kearney Street

Page 15: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

15

Construction Progress

Overhead power pole

installation, Smith

Road

Page 16: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

16

Construction Progress

Sandown Substation

transformer

installation

Page 17: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

17

Construction Progress

Central Park Station

platform construction

Page 18: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

18

Construction Progress

Track hardening

along Smith Road at

I-225

Page 19: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

19

Construction Progress

Girder installation on

Interstate 70 Flyover

bridge, the longest

bridge on the project

at nearly 5,000 feet

Page 20: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

20

Construction Progress

Airport/40th Station

platform construction

Page 21: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

21

Construction Progress

Track installation and

joint welding, East Rail

Line at 64th Avenue

Page 22: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

22

Construction Progress

Courtesy of HDR, Inc, © 2013, Keith Philpott

East Rail Line track

along Peña

Transportation

Corridor curve

Page 23: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

23

Construction Progress

E-470 Bridge, wide

enough for future

double-track, uses

direct-fixation track

over the highway for

a lighter structure

Page 24: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

24

Construction Progress

Construction on 1,953-

foot Peña Boulevard

Bridge, East Rail Line

Page 25: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

25

Construction Progress

Gantry used for direct

fixation track on Peña

Bridge

Page 26: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

26

Construction Progress

Track installation along

78th Avenue, parallel to

Runway 7/25

Page 27: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

27

Construction Progress

Rail underpass

beneath DIA east and

west terminal under

access roadway “X”

crossover

Page 28: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

28

Construction Progress

DIA Station approach

and platform, looking

south

Page 29: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

29

Canopy construction

over the passenger

platform at DIA

Construction Progress

Page 30: East Rail Line Update - FasTracks Home · 2 Kevin Flynn RTD Eagle Project Public Information Manager East Rail Line Update

30

Construction of DIA Station Canopy, September 2013

Questions?