Top Banner
E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey
29

E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Dec 22, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

E4014 Construction Surveying

Route Location SurveysReconnaissance SurveyInvestigation SurveyWorking SurveyConstruction Survey

Page 2: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Reconnaissance Survey

Gather sufficient information to select one or more bands of country for the possible route

• Assemble basic information– Topographic maps– Cadastral maps / GIS– Aerial photos– Orthophotos

Page 3: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Reconnaissance Survey

• Evaluate

– General topography – Geology– Meteorological statistics– Flood records– Unsuitable terrain– Land use and ownership / Local

Authority’s GIS– Existing services– Existing communications

Page 4: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Reconnaissance Survey

• Field reconnaissance to confirm assembled data

• Choose possible routes

• NOTIFY RELEVANT AUTHORITIES

Page 5: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Investigation Survey• Collect sufficient information to

design the horizontal and vertical alignment and thus:– Likely earthwork quantities– Intersection details– Bridge and culvert sites– Stream diversions– Land resumptions– Water catchments– Flood levels– Road building material– Total cost

Page 6: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Investigation Survey• Survey methodology

– Place traverse stations along proposed route

– Establish basic horizontal and vertical control

– Preferably MGA coordinates (plane) and AHD heights

– Control traverse between traverse stations for horizontal coordinates

– Spirit level vertical control (if necessary)

Page 7: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Investigation Survey• Survey methodology, cont

– Create a DTM either by cross sections or point pickup• level & staff• total station• GPS

– 200m band (100m ether side of proposed centreline) or as requested

Page 8: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Investigation Survey• Survey methodology, cont

– include• railway / tramway• road and bridge details• culverts• overhead cables, transmission lines,

heights• underground services• cadastral boundaries and fences• property improvements• geological features and soil types• vegetation• watercourses and swamps

Page 9: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Investigation Survey• Survey methodology, cont

– Accuracy• Horizontal 1 : 5000

• Vertical ( 0.012 K) metres– where K is the distance levelled in kilometres

Page 10: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Investigation Survey• Survey methodology, cont

– Catchment Areas• Necessary for bridge and culvert design

• Aerial photos

• Compass and clinometer traverses

Page 11: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Investigation Survey• Survey methodology, cont

– Aerial Surveys• May be utilised in lieu of other methods

• Photographed data becomes a reasonably permanent record, unbiased and complete

• Heights are not necessarily accurate

Page 12: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Working Survey• A working survey must provide

data of sufficient accuracy and extent for the satisfactory detailed design of the road and the later setting-out for construction.

Page 13: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Working Survey• Survey Marks

– Pegs (75mm * 50mm) are placed along the centre line (straight and curves) at 20 / 50 metre intervals

– Offsets (75mm * 50mm pegs, short star pickets driven flush) placed left and right of centre line • 200 metre intervals• beginning, centre and end of curves

– level and check level all centre line and offset pegs

Page 14: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Working Survey• Survey Marks, cont

– establish benchmarks • at 1km intervals• at bridge and culvert sites

Page 15: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Working Survey• DTM is established at the following

widths

– Secondary roads 15 metres left and right

– Main roads 25 metres left and right

– Developmental roads and highways30 metres left and

right

Page 16: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Working Survey• Detail (horizontal and vertical)

– located within 100 metres of the centre line

– All public and private improvements

– Existing road and rail formations

– Drainage

– Underground and overhead services

Page 17: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Working Survey• Bridge and culvert sites

– Require sufficient information to plot 0.25 metre contours for 100 metres up and down stream of the centre line

– Grid may be used• Lines parallel and at 3 metres intervals from the

centre line• Each line is levelled from high bank to high bank• Any intermediate section where the profile

changes is also levelled

– Bed levels for 500 metres up and down stream

– Sections taken at the end and at any profile changes

Page 18: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

Working Survey• Watershed traverses

– as per Investigation Survey

• Working drawings– Plan

– Long-section

– Cross-sections

Page 19: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

CONSTRUCTION SURVEY

urban equivalent to the Working Survey

• route is pre-determined by the presence of existing road reserves

• general survey requirements are the same as for Working Surveys

• density of detail is such that the procedures of observation and recording may have to be varied

Page 20: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

CONSTRUCTION SURVEY• Separate field and level books

should be used– Detail Files / Field Notes

• (i) Main centreline pegging and adjacent detail

• (ii) Subsidiary centreline pegging and detail

• (iii) Fence traverses to locate dividing fences and property improvements

• (iv) Side street centreline traverses

Page 21: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

CONSTRUCTION SURVEY• Separate field and level books

should be used– Level Notes

• (i) Main centreline levels and normal cross section

• (ii) Subsidiary centreline levels• (iii) Check levels• (iv) Drainage levels, both

underground and surface• (v) Subsidiary levels - accesses• (vi) Side street levels and cross-

sections• (vii) Side street check levels

Page 22: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

CONSTRUCTION SURVEY• With respect to field books, cross

referencing of information and explanations of abbreviations used require utmost care and attention

• same code table used by all surveyors

• planning with the aid of maps should ensure that no area remains unsurveyed

Page 23: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

CONSTRUCTION SURVEY• Centre Line

– unable to safely mark the centreline of roads already carrying high loads of traffic

– centreline pegged along one footpath parallel to road centreline where possible

– subsidiary line along opposite footpath, if necessary

– offset pegs placed in "safe positions" eg against fences

Page 24: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

CONSTRUCTION SURVEY• Centre Line, cont

– fences

– detail may be located chainage & offset as well as radiations

– houses, dividing fences, points of vehicular access, etc. may be located by "chainage & offset" along previously located fence lines

Page 25: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

CONSTRUCTION SURVEY• Cross Sections

– based on main centre line – normally extend 5 metres into adjacent

properties– if resumptions are anticipated then cross

sections may have to be extended– be aware of abrupt changes in level

between footpath and adjacent properties

– must illustrate the true cross section shape of the road (ie crown, changes of cross fall, edges, channel lips, channels, kerbs and footpath)

Page 26: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

CONSTRUCTION SURVEY• Subsidiary Cross Sections

– required at all vehicular accesses to adjacent properties

– extend 5 metres into adjacent property

Page 27: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

CONSTRUCTION SURVEY• Drainage Detail

– both open and underground

– underground • position and level of manhole or pit

• size and direction of all pipes, leading in and out

• invert levels on all pipes

Page 28: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

CONSTRUCTION SURVEY• Drainage Detail, cont

– open drainage• channels and natural watercourses as per

culverts sites in Working Survey

– watershed• difficult to determine in urban situation

• attention must be paid to the position and direction of flow in stormwater pipes near the natural watershed boundary

Page 29: E4014 Construction Surveying Route Location Surveys Reconnaissance Survey Investigation Survey Working Survey Construction Survey.

CONSTRUCTION SURVEY• side streets

– extend minimum of 50 metres