OFFICE OF SUPERINTENDING ENGINEER 15 TH CIRCLE UTTAR PRADESH JAL NIGAM, JHANSI E-TENDER FOR Construction of 6 Nos 300x200mm T.Ws by DC Rig machine & SITC of 15HP to 25HP Submersible Pumping Plants-8 Nos., Chlorinating Plant-14 Nos., V.T. Pumping Plants-3 Nos., Servo Voltage Stabilizer-06 Nos. and other E/M Works complete in all repects for Re- organization w/s scheme in Nagar Palika Parishad Orai (Zone – 6) UNDER AMRUT PROGRAMME \ EARNEST MONEY: Rs. 1.96 lacs TENDER COST: Rs. 11,200.00 LAST DATE OF SUBMISSION OF E-TENDER : 09.07.2018 DATE OF OPENING OF TENDER: 10.07.2018 AT 03:00 PM SUPERINTENDING ENGINEER 15 TH CIRCLE, U.P. JAL NIGAM, JHANSI
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
OFFICE OF SUPERINTENDING ENGINEER
15TH CIRCLE
UTTAR PRADESH JAL NIGAM, JHANSI
E-TENDER FOR
Construction of 6 Nos 300x200mm T.Ws by DC Rig machine & SITC of 15HP to 25HP Submersible Pumping Plants-8 Nos., Chlorinating Plant-14 Nos., V.T. Pumping Plants-3 Nos., Servo Voltage Stabilizer-06 Nos. and other E/M Works complete in all repects for Re- organization w/s scheme in Nagar Palika Parishad
Orai (Zone – 6) UNDER AMRUT PROGRAMME
\
EARNEST MONEY: Rs. 1.96 lacs
TENDER COST: Rs. 11,200.00
LAST DATE OF SUBMISSION OF E-TENDER : 09.07.2018
DATE OF OPENING OF TENDER: 10.07.2018 AT 03:00 PM
SUPERINTENDING
ENGINEER
15TH CIRCLE,
U.P. JAL NIGAM,
JHANSI
INSTRUCTION TO THE TENDERERS
INSTRUCTION TO THE TENDERERS
1. The bid document is available online & digitally signed bids are to be submitted online
through e- procurement website http://etender.up.nic.in only. Bids submitted manually
will not be accepted. The bidders would be required to register in above website which is
free of cost. For submission of bids the bidders are required to have Digital Signature
Certificate from one of the authorized certifying agencies.
2. The cost of tender documents (non- refundable) Rs. 11,200.00 as applicable shall be
paid in the form of Demand Draft of any nationalized bank in favor of Executive
Engineer, Jhansi Division First, U.P Jal Nigam, Jhansi . Demand Draft should be
submitted in the office of E.E., Jhansi Division First , Jal Nigam Jhansi by 5.00 PM on day
before tender opening date i.e 09.07.2018. Copy of D.D shall be uploaded with tender.
3. The tender shall be accompanied with required earnest money duly pledged to The
Executive Engineer, Jhansi Division First, U.P Jal Nigam, Jhansi in the shape of
FDR/CDR of any nationalized bank only. FDR/CDR should be submitted in the office of
E.E., Jhansi Division First , Jal Nigam Jhansi by 5.00 PM on day before tender opening
date i.e 09.07.2018. Copy of EMD shall be uploaded with tender. The EMD shall be
valid for 180 days. Tenders without EMD or invalid EMD will be summarily rejected.
4. Tender is invited on two bid system i.e.
(i) Technical cum financial capability evaluation bid.
(ii) Financial bid.
5. The quantum of work may increase or decrease to any extent subject to availability of
funds. The date of pre-bid meeting shall be on 25-06-2018 at A.M. in the office of
Superintending Engineer ,15TH circle ,U.P. Jal Niagm, Jhansi. If the date of pre-bid meeting
becomes a holiday, the pre-bid meeting will be held on next working day.
6. The technical cum financial evaluation bids shall be opened on 10.07.2018 at 3.00 PM in
presence of bidders or their authorized representatives in the office of E.E., Jhansi Division
First , Jal Nigam Jhansi .
7. Financial bid of only those firms/ Contractors shall be opened who will be found eligible on
scrutiny of technical cum financial capacity evaluated bid. The date and time of opening of
financial bid shall be intimated separately. 8. If the date of opening of the tender documents becomes a holiday, the tender will be opened
on next working day.
9. U.P. Jal Nigam reserves the right to accept or reject any or all the bids without assigning any
reason thereof. So, further no any claim of applicant shall be considered in this regard. 10. The rates quoted in tender shall be valid for 120 days from the date of opening of financial
Bid. 11. The bidders are advised to inspect the site before quoting the rates.
12. For any queries bidders may connect Superintending Engineer,15TH Circle, U.P. Jal Nigam,
Jhansi on Mob. 9473942727 and Executive Engineer , Jhansi Division First ,U.P Jal
13. The bidders have to upload following documents along with tender without which tender will
not be considered.
(i) Copy of EMD
(ii) Demand Draft for payment towards tender document cost.
(iii) Copies of ITR of last Three years.
(iv) Copy of Latest/Valid solvency certificate issued by District Magistrate/Nationalized
Bank.
(v) Performance certificate for completed work and progress report of ongoing work
attributed at least satisfactory remarks for the tube well constructed / pumping plant
supplied & installed by firm in last 5 years.
(vi) CA attested summery of balance sheet and profit and loss account from financial year
2015-16 to 2017-18
(vii) Copy of valid registration certificate in U.P. Jal Nigam in appropriate class and
category
(viii) Copy of PAN
(ix) List of staff and T&P on prescribed format given in tender document.
(x) Copy of GST registration certificate.
(xi) Copy of Labour Cess registration certificate
2.3 Security Deposit
2.3.1 A contract security of contract performance security equal to an amount of 10% (ten percent) of the
contract amount shall be paid by the successful tenderer on the award of work. This amount is to guarantee the faithful performance of the contract and execute the works as per terms and conditions,
specifications, drawings and other requirements for completing the works to the complete satisfaction
of the department.
2.3.2 The security deposit can be paid in any one of the forms as described for the EMD in clause 2.2.1 2.3.4 The security deposit is to be submitted within seven (7) days from the date of letter accepting the
tender.
2.3.5 The security deposit shall be pledged to the Executive Engineer, Jhansi Division First ,U.P. Jal
Nigam, Jhansi. 2.3.6 IF the successful tender fails to deposit the security deposit and execute the contract agreement his
EMD will be forfeited. The tenderer may be disqualified from further tendering of work of this
department. 2.4 Method of tendering
Tender shall be signed by an individual if tender is made by an individual or by a person holding the
power of attorney if tender is by a limited company or by all partners if tender is made of firmed
partnership giving current correspondence address. A certified copy of the power of attorney with
evidence of its currency shall accompany the tender in case the tender is signed by a person holding
attorney for signing the tender. 2.5 Witnesses and Dates 2.5.1 All witnesses and sureties shall be persons of status and probity and their full names, and current
correspondence address shall be stated below their signature. All signature shall be dated below the
signatures in all the tender.
Preparation of Tenders
The tenderer is required to study carefully and well all the tender document and then only shall fill in
complete and submit the tender documents after obtaining all the clarification and clearing all doubts
if any in the tender documents.
Submission of tender shall be taken as evidence and confirmation that the tenderer has acknowledge
all the provision of the tender documents and has fully acquainted himself with conditions and all
factors which may influence the preparation, submission and satisfactory performance of the contract
agreement.
The tender shall be submitted in a complete form filling in all the information called for the prescribed
format only. All the blank formats included in the tender shall be filled in signed witnessed and dated
at the places provided for the same. Violation of the above requirement to submit all the required
information the tender may lead to disqualification of the tender.
No alteration shall be allowed in the tender anywhere in the tender documents once the tenders are
submitted.
It must be however clearly understood that the owner accept that the tenderer submit the tenders as
stated in the tender documents. Any deviation from the tender provisions are therefore discouraged
strongly. Such deviations particularly those involving financial implications, which make the
comparison of the various tenders difficult without further reference and correspondence with tenderer
is likely to be a cause of rejection of the tender. 2.6.6 Any tender containing vague and indefinite expression such as “subject to immediate acceptance” etc
shall not be considered. No condition shall be attached to the tender. Such conditional tenders will be
rejected.
2.6.7 Page shall be neither added not removed from the tender documents.
2.6.8 The quantities of the works indicated in the bill of quantities are not firm quantities but are only
approximate to give an idea to the tender about the various items of worked involved and their extent
of magnitude. However, the tenderer shall estimate his own quantities based on the drawing, and other
information given in the tender documents. Any changes in the quantities during actual execution
actually executed and indicated in the bill of quantities shall not entitle the contractor for any extra claims compensations etc. The tenderer has to complete the works as shown in the drawing issue
for the first time or subsequently revised/ordered/directed by the owner/engineer incharge during the
period of execution. Actual work will be measured and paid. 2.7 Validity period of Tender:
The tender shall be valid for a period of not less than 120 days after the date of opening of the tender.
There after the tenderer shall have an option of keeping his tender open if the owner request for such
extension.
2.8 Bidders must have Joint ventures for E/M works with E/M contractor & authorization Certificate
from Pump Manufactures/Distributor/Dealer and
2.9 An”Oath certificate” (against this tender) has to be produced on legal paper from the manufacturer/
Authorized Distributor/ Dealer of offered Pump to give an undertaking to provide complete technical support to the tenderer in supply, execution and maintenance to the authorized firm and also to
undertake that incase the firms fail to fulfil their commitment, manufacturer for Distributer/Dealer for
pump will own full responsibility to complete and maintain the project.
2.10 The Firm should submit characteristic curves & schedule ‘E’ of V.T./Submersible pump Individually
.
2.11 Offered make of all equipment should be as per approved U.P. Jal Nigam make list and the offered
make of pumping plant should be mentioned in tender document.
2.12 No complaint of any tenderer will be entertained after opening of financial bid.
2.13 If any certificate may be found fake in verification, registration of the contractor will be
cancelled or the firm may also be black listed, the firm will give and undertaking on
"Legal Paper" that all the certificates submitted are true.
PHYSICAL EXPERIENCE FOR E/M WORKS
1- One similar completed works of at least 05 No. Tubewells Construction, 09 Nos.
SITC of Pumping Plant of minimum 25 H.P. and above
Or
2- Two similar completed works of at least 03 No. Tubewells Construction, 06 Nos.
SITC of Pumping Plant of minimum 15 H.P. and above
Or
3- Three similar completed works of at least 02 Nos. Tubewells Construction, 4
Nos. SITC of Pumping Plant of minimum 12.5 H.P. and above
4- Tender Documents should be properly filled & Duly signed by the bidder. Without it
tender will not be accepted.
QUALIFIED APPLICANTS :
U.P. Jal Nigam will decide which applicants are qualified and will inform them by E-MAIL
confirming in writing by registered/ speed post letter. Qualified contractors will be given an
invitation to participate in opening of Financial Bid of the tender at the appropriate time.
GENERAL CONDITIONS OF CONTRACT
OFFICE OF SUPERINTENDING ENGINEER , 15TH
CIRCLE
UTTAR PRADESH JAL NIGAM, JHANSI
1. DEFINITIONS AND ABBREVIATIONS:
1.1 DEFINITIONS: In this contract as hereinafter defined, the following words and expressions shall have the
meanings hereby assigned to them (expect where the context requires otherwise).
1.1.1 ‘OWNER’ MEANS U.P. JAL NIGAM.
1.1.2 Contractor means the person(s), firm or companies whose tender has been accepted by the Engineer and who has concluded a contract with the Engineer to execute the works included in
the tender and contract agreement. This includes the contractor’s personal representatives,
successors and assignees. 1.1.3 ‘Sub-Contractor’ means any person, firm or company other than the contractor named in the
contract for any part of the work, or any person to whom any of the works part of the works
included in the contract has been sublet with the consent in writing of the Engineer, and the sub-Contractors legal personal representatives, successors and permitted assignees.
1.1.4 Engineer/Engineer-in-Charge means the Executive Engineer, who has called for the tenders and
in charge of execution of the works and administration of the contract. The Engineer may assign
his duties to his sub-ordinates who assist in execution of works and administration of the contract. His subordinates shall be termed as Assistant Engineer/Junior Engineer in Charge as the case may
be. These sub-ordinates shall be Engineer representatives at the site of works. The Engineer
representatives will carry out such duties of the Engineer, like issuing of instructions, certificates and orders as are required in the execution of the works. Engineer’s representation will watch and
supervise the works, test and examine the materials, equipments, plant and machinery and
workmanship employed in connection with the works under the contract. The Engineer’s representatives with the approval of the Engineer will have the authority to relieve the contractor
of any of his obligations under the contract and to order any extra work involving delay in
completion of the works and also requiring any extra payment to the contract.
1.1.5 ‘Department’ means the Uttar Pradesh Jal Nigam, the words departments and Executive Engineer and his representatives have been used interchangeable at place and means the same i.e. the
Engineer or his representatives.
1.1.6 Consultant means a person who have formulated and designed the scheme, prepared the drawings, drawn the specifications and who act as advisers to the owner in all technical matter
and operation and maintenance of the work.
1.1.7 Work means all items of work to be constructed by the contractor, provision of rig machine
compressor and o.p. unit of required capacity for construction and handing over the tube wells. 1.1.8 Contract means promise to execute the work in accordance with the conditions of contract,
specifications drawings schedules, tender document, the letter of acceptance and the contract
agreement. 1.1.9 Drawing means the drawing referred to in the list of drawing attached to the tender and any
modifications of such drawings approved/issued in writing by the Engineer and such other
drawings as may from time to time be furnished or approved in drawing by the Engineer. 1.1.10 The contract sum means the sum identified in the contract for completion of works as per
contract.
1.1.11 Contract price means a portion of the contract sum adjusted to give effect to such additions or
deductions as are provided for in the contract which is properly apportionable to the plant in question having regard to the state, conditions, locations of the plant, the amount of work done
and all over relevant circumstances in the cost of executing the works.
1.1.12 Contractor’s equipment means all appliances or things of whatsoever nature required for the purpose of completing the works.
1.1.13 ‘Plant; means machinery, apparatus, materials, articles of intends to be provided under the
contract other than the contractor’s equipment.
1.1.14 ‘Portion of the work’ means a part of the work or section of work.
1.1.15 ‘Section of the works’ means the sections into which the works are divided for the purposes described and set out in the specification.
1.1.16 ‘Specification’ and ‘Particular Specification’ means the relating guidelines contained in the
P.W.D. specification, Manual of Sewerage and Sewage Treatment, manual on water supply published by the Central Public Health and Environmental Engineering Organization (CPHEEO)
under the Ministry of Works and Housing, Indian standard specification and codes, all of latest
and those contained in the tender documents and also those on good Engineering practice. 1.1.17 ‘Month’ means 30 days.
1.1.18 ‘Day’ means calendar day.
1.1.19 Time for completion means the same time as stipulated for completion of the works or any
section or portion thereof as cited in the contract or as extended under clause and shall be calculated from the date specified in the contract. It will be the date when the contract is into
force of fulfillment of any obligation as per necessary legal financial or administrative
requirements.
1.1.20 ‘Defect liability Period’ means the period after actual completion of the work during which the
contractor will carry the liability to make good to the complete satisfaction of the Engineer, any
defects in the completed work or any bad work visible afterwards. 1.1.21 Cost means the amount which shall be deemed to include overhead costs incurred on or off the
sites, all taxes, excise duties royalties etc. as applicable on the materials, labour or any other item
is required to complete the works. 1.1.22 ABBREVIATIONS:
Abbreviations used in the tender documents or any other despondence will stand for the
Work or works where used in these conditions and specifications shall unless there be something either in the subject or context repugnant to such construction be constructed and taken to mean
work by virtue of the contract to be executed whether temporary or permanent and whether
original altered, substituted or additional.
2.3 WORKS NOT TO BE SUBLET WITHOUT SANCTION:
This contract or any part thereof shall not be assigned or sublet without the written approval of
the Engineer. If (1) the contractor shall assign or sublet his contract or attempt to do so or become insolvent or commence any insolvency proceeding or make any composition with his creditors, or
attempt to do so, or (2) if any bribe, gratuity, gift loan perquisite, reward of advantage, pecuniary
or otherwise, shall either directly or indirectly be given, promised or offered by the contractor or
any of his servants or agents to any public officer or person in the employee of U.P. Jal Nigam or in any way relating to such officer or person shall become in any way directly or indirectly
interested in the contract, the Engineer may notice in writing rescind the contract and the security
deposit shall thereupon stand forfeited and be absolutely at the disposal of the U.P. Jal Nigam, and the same consequence shall ensure as if the contract had been rescinded under clauses
4.1.5.3. thereof and in addition the contractor shall not be entitled to recover or be paid for any
work that has already been performed under this contract.
2.4 SITE FACILITIES: The contractor shall at his own cost construct a site office for his own use and shed for materials.
He shall also dismantle the same after the works are complete, and arrange for site cleaning
operations by removal of soil and debris. If the contractor fails to dismantle the temporary structure after the works are completed it shall be treated as unauthorized occupation of the
owners land and necessary action as deemed fit under such circumstances shall be initiated for the
vacation of the land.
2.5 TIME FOR COMPLETION:
2.6 Contract Time: 12 Months
The time allowed for carrying out the works shall be as stated in notice Inviting Tenders of the
tender documents and shall be strictly observed by the contractor and shall be reckoned from the
date of the receipt of the written order to commence the works.
Thereafter a defect liability period of 12 (twelve) months after successfully running of
tubewell of the works will follow. During which the contractor shall remove all the defects
in the works, if any pointed by the operating staff.
2.7 FORCE MAJEUR:
Neither party shall be liable to the other for any loss or damage occasioned by or arising out of
acts of God, and in particular, unprecedented flood, volcanic eruption, earthquake or other convulsion of nature and other acts such as but not restricted to invasion, the act of foreign
countries, hostilities or warlike operation before or after declaration of war, rebellion, military or
usurped power which prevent performance of the contract and which could not have been
foreseen or avoided by a prudent person.
2.1.1.4 EXTENSION OF TIME:
If the contractor shall desire an extension of time for completion of the work on the ground of
unavoidable hindrance in its execution, he shall apply in writing, giving details of hindrance to the Superintending Engineer through the Engineer in Charge, within 7 days of the date of
occurrence of hindrances on account of which he desires such extension as aforesaid and the
Engineer shall authorized such extension of time, as may be reasonable in his opinion. If the work is suspended due to necessary and unavoidable reasons, the contract period shall be
accordingly amended but no compensation on this ground shall be permissible. For all
suspensions exceeding fifteen days ordered by the Engineer no rent of T&P if any shall be payable but the contractor shall be responsible for the safe custody of Nigam’s material and
T&P. No claim shall be entertained for the maintenance of any staff during such idle period or
for the disuse of his own T&P.The department shall however not be responsible for any
suspension of work occasioned by the contractor on his own account.
2.8 ENGINEER’S CERTIFICATE OF COMPLETION:
On completion of the work, the contractor shall be furnished with a certificate of such
completion by the Engineer but no such certificate shall be given nor shall the works be considered to be completed until the work shall have been measured up by the Engineer whose
measurement shall be binding and conclusive against the contract. The contractor shall have to
remove all scaffolding, surplus materials and rubbish and cleaned of all dirt and debris in upon
or about the premises of which he may have possession for the purpose of executing the said work. If the contractor fails to comply with the requirement of this clause as to removal of
scaffolding, surplus materials and rubbish and dispose of the same as he thinks fit and clean off
such dirt and debris as aforesaid, the contractor shall forthwith pay the amount of all expenses so incurred for any sum actually released by the sale thereof after deducting the aforesaid
expenses.
2.9 The Engineer shall within seven days issue the completion certificate on completion of above- mentioned measurement and cleaning of site. The date of certificate shall be taken as date of
completion of work.
2.10 PAYMENTS:
i) Payment terms are given in schedule 'J' in mode and terms of payment. ii) Written guarantee shall also be submitted by the contractor regarding satisfactory
completion of work for a period of one year from the date of successful handing
over of work.
iii) The processing of payment may take minimum one month time from the date of
submission of bills for which no claim shall be admissible. 2.11 No compensation for the alteration in or reduction of work to be carried out shall be
permissible, if at any time after the commencement of the work the U.P. Jal Nigam, shall for
any reason whatsoever not require the whole thereof as specified in this contract to be carried out, the Engineer shall give notice in writing of the fact to the contractor and upon the receipt of
such notice in writing the works under this contract shall cease and the compensation
whatsoever on account of any profit of advantage, which he might have derived from the execution of the work in full, but which he did not derive in consequence of the full amount of
the works not having been carried out, neither shall he have any claim for compensation by
reason of any alternations having been made in the original specifications, drawings and
instructions which shall involve any curtailment of the work as originally contemplated.
2.12 ACTION AND COMPENSATION PAYABLE IN CASE OF BAD WORK
If it shall appear to the Engineer or his authorized representative that any work has been
executed with imperfect or unskilled workmanship or with materials of any inferior description or the material and equipment not new or that any materials or articles provided by the
contractor for the execution of the works are unsound or of inferior quality to that contracted
for or otherwise not in accordance with the contract, the contractor shall on demand in writing
from the Engineer, specifying the work, materials or the articles complained of forthwith rectify, remove and replace, demolish and reconstruct the work so specified in whole or in part
as the case may require, or as the case may be, remove the materials, or articles so specified and
provide other proper and suitable materials or articles at his own charge and cost. In the event of his failing to do so within a period to be specified by the Engineer, then the contractor shall
be liable to pay compensation at the rate of (1%) one percent on the amount of the estimated
cost of the whole work for every week not exceeding ten weeks while his failure to do so shall continue and in case of any such failure, the Engineer may rectify, remove, demolish and
reconstruct the works or remove and replace with others, the materials or articles complained
of, as the case may be, at risk and expense of the contractor in all respects and such expense
may be deducted from such sum as may be due to the contractor or may become due to him and from his security deposit. A certificate by the Engineer as to the amount of the expenses
incurred shall be final and binding upon the contractor.
In case the water of tube well is not found potable due to any reason than the
NO payment of drilling and development shall be done as per rules.
2.13 SUM PAYABLE BY WAY OF COMPENSATION:
All sums payable by way of compensation under any of these conditions shall be considered as reasonable compensation to be applied to the actual loss or damage sustained and whether or
not any damage shall have been sustained.
2.14 REVISION OF RATES:
No claim on account of revision of taxes, duties, labour and material rates, fuel, lubricants, plants/equipments or any other reason that can influence the rates quoted shall be entertained
when the contract is operative.
2.15 BILLS TO BE SUBMITTED ON PRESCRIBED FORM:
The contractor shall submit all bills on the prescribed forms to be had on application from the
office of the Engineer. The charges in the bill shall always be entered at the rates given in the
schedule of rates hereto attached or in the case of an extra work ordered in pursuance of these
condition and not mentioned or provided for in tender at the rates hereinafter to be agreed upon.
2.16 Payments shall be made at the quoted rates as far as items included in the price schedule. In
case of items not included in the price schedule agreed/approved rates shall be applicable.
2.17 The measurement as shown in the drawings/revised drawings, duly approved for construction by Engineer-In-Charge instruction given in this regard, shall be measured and paid. Any
measurement in excess of those shown in the drawings fully executed or otherwise shall not be
entitled for payment.
2.18 RECEIPT OF AND POWER TO ADJUST SECURITY MONEY:
The U.P. Jal Nigam has received from the contractor the sum of 10% (ten percent) of the
tendered cost the receipt of which is hereby acknowledged. This is sum together with the sum made of the percentage described in clause 4.1.4. of this contract shall be held as security and
stipulations of this contract. The Engineer is empowered to deduct from time to time such
security money, all or sum or sums which may become due from the contractor as
compensation for the breach any or all the covenants or provisions of this contract. If not confiscated above under the provisions of this contract the security money or such balance
thereof as may be left after paying the deduction or deductions above mentioned will be
returned to the contractor 12 (twelve) months after the final certificate of the completion of the work shall have been given by the Engineer and after the Examiner/Engineer shall have
satisfied himself that all the terms of the contractor have been faithfully carried out by the
contractor.
2.19 Each tender must be accompanied with the deposit receipt of the earnest money which shall be
deposited in the shape as description for EMD in clause 2.2.1. Earnest money in other shape
shall not be accepted and tender is likely to be rejected on this account.
2.20 CONTRACTOR’S LIABILITY:
The work shall throughout the stipulated period of the contract be proceeded with all the due
diligence (time being agreed to be the essence of the contract) and the contractor shall pay as
compensation an amount equal to (one percent) 1% per day on contract price that the works remain uncommenced, or finished after the proper dates. Provide that always the entire
compensation to be paid under the provisions of this clause shall not exceed ten (10) percent of
the contract value.
2.21 OBSERVANCE OF LAWS, LOCAL REGULATIONS NOTICES AND ATTACHMENTS:
Contractor shall confirm to all the laws of the land, the relations and by-laws of any local
authority and or of any other or lighting companies with those whose systems the works are
proposed to be connected. He shall before making any variations the drawing or specifications that may be necessitated for so indicating, give to the Engineer written notice, specifying the
alteration proposed to be made and the reasons for making them and for instructions thereon. In
case the contractor shall not give such instructions within 7 days proceed with the work confirming to the provisions, regulations or by-laws in question of any variations in the
drawings or specifications so necessitated shall be dealt with under clause 4.1.8.2. The
contractor shall give all notice required by the said, acts relations or by-laws and pay all fees in
connections therewith. He shall also ensure that no attachments are made against works related to the contract. In every case referred to this clause, the contractor shall protect and indemnify
U.P. Jal Nigam against any claim or liabilities arising from or based on the violation of such
law, ordinance, regular decree or attachment by his employees.
2.22 Contractor liable for damage done and imperfections the contractor or his work people or
servants shall break, injure or destroy any part of a building in which they may be working or
any building, road defense, enclosure or grassland or cultivated ground continuous to the
premises on which the work or the part of it is being executed, or if any damage shall happen to the work while in progress from any cause whatsoever or any imperfections become apparent
in it within 12 (Twelve) months after the final certificate of its completion shall have been
given by the Engineer as aforesaid, contractor shall make the same good at his own expense
within reasonable time.
If the same to be made good by other workman and the expanse (of which the certificate of the
Engineer shall be final) from any sum that may be then or at any time thereafter will become due to the contractor or from his security deposit. Such rectification shall be guaranteed for six
months from the date of completion of the said rectification, if the rectification is carried out
after six months of completion period. The security deposit if necessary shall be extended to
cover up such period.
2.23 BREACH OF CONTRACT: In any case in which under any clause or clause of these condition the contractor, shall have
rendered himself liable to any compensations amounting to the whole of the security deposit
whether deducted in one sum or deducted by installments the Engineer on behalf of the Department shall have power to adopt any of the following courses as he may deem just suited
to interest of Jal Nigam.
(a) To rescind the contract (of which rescission notice in writing given to the contractor under the hand of the Engineer shall be inclusive evidence), in which case the security deposit of the
contractor together with such sum or sums due to him under the contract(s) shall stand
forfeited and be absolutely at the disposal of the department.
(b) Terminate the contract and call in another contractor or employ locally labour to dismantle bad work if necessary (the bad work to be certified by the Engineer whose decision shall be final)
and to renew and complete the said works and pay the cost of such contractor for daily labour
and price of materials required for such dismantling, renewing and completion out of the said security deposit or such sum or sums as may be due to the contractor under his contract. If such
cost be more then the amount made up of the security money and the sum or sums due to the
contractor under this contract, the difference between it and the sum made up by the security money and the balance due to the contractor as aforesaid will be a debt due from the said
contractor to the Department.
In the event of either of the above courses being adopted by the Engineer, the contractor shall
have no claim to compensation for heavy loss sustained by him by reason of his having purchased or produced any materials, or entered into any agreements or made any advances or
account of or with a view to the execution of the work for the performance of the contract. In
case the contract shall be rescind under the provision aforesaid the contractor shall not be entitled to recover or be paid any sum for any work therefore actually performed under this
contract unless and until the Engineer shall have certified in writing the performance of such
work and the value payable in respect thereof, and he shall only be entitled to be paid the value
so certified.
2.24 NON-EXERCISE OF CONTRACTORS LIABILITY TO PAY COMPENSATION:
In any case in which any of the powers conferred upon the Engineer in clause 4.1.5.4. thereof
shall have become exercisable and the same shall have not been exercised, the non-exercise thereof shall not constitute a waiver of any of the conditions hereof and such power shall not
withstanding earlier non-exercisable, be exercisable in the event of any future case of default by
the contractor for which by any clause or clauses hereof he is declared liable to pay compensation amounting to the whole of his security deposit and the liability of the contractor
for past and future compensation shall remain unaffected. In the event of the Engineer putting
in force either of the powers (a) or (b) vested in him under the preceding clause, he may, if he
so desires take possession of all or any tools, plant, materials and stores in or upon the works or the site thereof belonging to the contractor, or procured by him and intended to be used for the
execution of the work or any part thereof paying or allowing for the same in account at
prevailing market rates, such rates to be certified by the Engineer whose certificates thereof shall be final. Otherwise the Engineer may issue notice in writing to the contractor or his other
authorized agents require him to remove such tools, plants, materials or stores from the
premises (within a time to be specified in such notice). In the amount of the contractor failing
to comply with any such requisition, the Engineer may remove them at the contractors expense or sell them by auction or private sale on account of the contractor and at his cost and risk in all
respects, and the certificate of the Engineer as to the Expenses of any such removal, and the
amount of the proceeds and expenses of any such sale shall be final and conclusive against the
contractors.
2.25 COMPENSATION TO WORKMEN:
The contractor on occurrence of accident, arising out of the work which result in serious injurious to the person or property, shall within 24 hours of such occurrence, report to the
Engineer, stating clearly and in sufficient details the facts and circumstance of the accident and
the action taken by the contractor. In all cases the contractor shall indemnify U.P. Jal Nigam,
against all losses or damages including directly or indirectly from contractor’s failure to give
notice under the workman’s compensation Act or otherwise.
In every case in which by virtue of the provisions Jal Nigam be obliged to pay compensation to a workman employed by the contractor or by any sub-contractor from him in the execution of
the said work, Jal Nigam, will recover from the contractor the amount of the compensation so
paid. Without prejudice to the right of Jal Nigam, Jal Nigam shall be at liberty to recover such amount of any part thereof by deducting it either from the security deposit or his credit under
clause 3.4.9. of these conditions or from any other sum due by Jal Nigam to the contractor
whether under this contract or otherwise.
2.26 Jal Nigam shall not be bound to contest any claim made against it under section 12, sub-station
(1) of the workman’s compensation Act, except on the written request of the contractor and upon
his giving to Jal Nigam might become liable in consequence of consisting the claim.
2.27 CONTRACTOR DYING, BECOMING INSOLVENT OR IMPRISONED:
(a) In the event of the death, insanity or insolvency, imprisonment of the contractor or where
the contractor being a partnership of firm becomes dissolved or a corporation goes into
liquidation, the contractor may be terminated by notice in writing posted at the site of the works and advertised in one issue of the local newspaper and all acceptable, works shall be
paid for after recovering all the contractors dues to U.P. Jal Nigam there from at
appropriate rates to the person or person entitled to receive and give a discharge for the payment.
(b) If the contractor becomes bankrupt or has received order made against him or compound
with the creditor or being a corporation commence to be wound up not being a voluntary
winding up for the purpose only of amalgamation or reconstruction or carry on its business under a receiver for the benefit of the creditors or any of them, the U.P. Jal Nigam, shall be
at a liberty.
(c) To give such liquidation, receiver or other person, the option of carrying out the contract subject to his providing a guarantee for the due faithful performance of the contract upto
an amount to be determined by the U.P. Jal Nigam.
(d) To terminate the contract forthwith by notice in writing to the contractor or to the
liquidator or to any person in whom the contractor become vested and to act in the manner as provided in the clause Breach of contract.
2.9 CONTRACTOR TO SUPPLY LABOUR, PLANT, LADDER, SCAFFOLDING:
2.10 The contractor shall supply at his own cost all labour, (skilled and unskilled) and all things necessary (expect such specials things, if any, as in accordance with the specification supplied
from the Engineer’s stores) such as plants, tools appliances, implements, ladders, tackles, fuel,
oil, packing, derricks, boring tools etc. as well as all other apparatus and temporary works requisite for the proper execution of the work together original, altered or substituted and
whether included in the specifications or other document forming part of the contract or
referred to in these conditions or not which may be necessary for the purpose of satisfying or
complying, with the requirements of the Engineer as to any matter as to which under these conditions he is entitled to be satisfied, or which he is entitled to require, together with
carriage hereto for and from the work. The contractor shall also supply without charge the
requisite number of persons with the means and things necessary for those of setting out the works, and counting, weighing, and consisting in the measurement and examination at any
time and from time to time, of the works done, or materials supplied by him. The contractor
shall also provide at his own expenses all necessary fencing and lights required to protect the
public from accident and shall assume all the liability for and indemnify U.P. Jal Nigam against all actions or suits arising out of or connected neighboring owners or workman
employed on the works. While carrying the works, whether such actions are brought by
members of the public, the contractor shall carry out the works confirming to the statuary and other legal enactments applicable to them and give all notice and pay all fees payable to local
authorities and other in respect of them. The contractor shall be responsible for the adequacy,
strength and safety of all the working strutting, curbing, bonding, brickwork, masonry, contract permanent or temporary, appliances, matters and things furnished by him for the
purpose of this contract.
2.11 MATERIALS AND PLANT OF CONTRACTOR: All materials brought by the contractor upon the site of the works shall be deemed to be the
property of U.P. Jal Nigam and shall not on any account be removed from the site of the works
during the execution of the works and shall at all times be open to the inspection of the Engineer. The Engineer on the completion of the works or upon the stoppage of the works as
provided in clause 4.1.4.2. of this contract shall have an option of taking over any such unused
material at prevailing market rates, with the provision that the price allowed to the contractor shall not exceed the amount originally paid by him for the same, as he (the Engineer) shall
desire upon giving a notice in writing under his signature and within(15) fifteen days of the
completion of the works to that effect, and all materials not so taken over by the Engineer shall
cease to be the property of U.P. Jal Nigam and the contractor shall have no claim for compensation on account of any such material as aforesaid which are not so taken over by the
said Engineer unused by him ( the contractor) or for any wastage in or damage to any such
materials.
EMPLOYMENT OF AN EXPERIENCED SITE ENGINEER:
The contractor shall employ a site Engineer of the rank of a Resident Engineer who is well
experienced in the type of the works, he has to handle and shall be well acquainted with all latest Indian standards, codes of practice, local practice of construction and has good
managerial qualities, capable of handling labour force tactfully and extract good quality of
workmanship and plan execution of works efficiently. He shall be conversant with
specification, construction equipment use, testing, inspecting and supervising the works. He
shall have good ability to guide his subordinates and shall be time conscious.
The contractor shall employ work agents and such foreman as may be necessary for the
execution of the works to ensure proper and efficient control.
EXPERIENCE OF THE LABOUR FORCE:
The contractor shall employ in his pay-roll only such workers who are experienced in the trade
or job for which they have been employed. The Engineer shall have full powers to direct the
contractor to remove and engaging on work persons who do not have any experience in the trade and whose work is not satisfactory. If in the opinion of the Engineer a person is found to
be incompetent, such person shall be replaced by an experienced one to the satisfaction of the
Engineer.
Permission in writing should be taken from the Engineer in order to work on Sundays, holidays,
nights and to work after time. No women labour should be engaged on works during night.
CONDUCT OF LABOUR: The contractor is solely responsible for the peaceful and orderly conduct of labour in the
neighborhood of work site. The Engineer in charge shall have full powers to order the
contractor to prevent undesirable labour force from entering the work site. Further the Engineer
has full power to ask the contractor to remove from the site of works any person who
misconducts at site.
LABOUR WELFARE:
Facilities for welfare of the labour shall be provided by the contractor at his own cost as per the
existing labour laws.
The contractor shall make all arrangements for supply of a drinking, bathing and washing water
to the labour, at his own expenses.
Adequate first aid and medical facilities shall be provided. Proper, separate toilet facilities for men and women shall be provided.
Protective accessories like helmet, gumboots, gloves, goggles as found necessary, shall be
provided to the labourers.
CAUTION LIGHTS:
Contractor shall provide caution signs/lights near excavations, trenches, fencing etc. and
employ watchmen during night and off working days and hours.
SAFETY OF WORKERS:
Contractor shall ensure that all precautions are taken to avoid accidents by providing
scaffolding, platforms, etc. of adequate strengths, which can safely take the loads by properly
bracing, tying and storing as necessary. No extra costs shall be claimed for all above safety
works.
The contractor shall provide at his own cost, all safety equipments to the labours, children’s
and cattles like barbed wire fencing barricades, temporary crossing, etc. around the tube well site to prevent accidental slips, falls, injuries etc.
The contractor shall make his own arrangements for conveyance of materials and labour to the
work site by making, if necessary, any temporary paths, roads, access etc. at his own cost.
DRAWING AND SPECIFICATIONS:
WORKS TO BE EXECUTED IN ACCORDANCE WITH THE SPECIFICATION:
The contractor shall execute the whole and every part of the work in the most substantial and
workman like manner both as regards material and otherwise in every respect in strict accordance with the specification. The contractor shall also confirm exactly, fully and faithfully
to the drawings and instructions in writing relating to the work assigned by the Engineer.
ALTERATION IN SPECIFICATION OR DRAWINGS: The Engineer shall have powers, to make any alteration in or any additions to, the original
specifications, drawings and instructions that may appear to him to be necessary or advisable
during the progress of the works. The contractor shall be bound to carry out of the work in
accordance with any instructions which may be given to him in writing signed by the Engineer and such alteration shall not invalidate this contract. Any additional work, which the contractor
may be directed to do in the manner above specified, as part of the work shall be carried out by
the contractor on the same conditions in all respects on which he is awarded to do the main work. The time for the completion of the work shall be extended if applied for by the contractor
in writing in the proportion that the additional works as to the original contract work. The
certificate of the Engineer shall be conclusive as to such extension. And if the altered works
include any class of work for which no rate is provided in this contract then such class of work shall be corrected out at rates to be agreed upon in writing between the Engineer and the
contractor prior to the work being taken in hand.
Basis for fixing such rates shall ordinary be the current U.P. Jal Nigam schedule of rates for the district provided, if the contractor shall commence work or insure any expenditure in regard
there to, the rates shall have been remained as before mentioned. He shall only be entitled in
respect of the work carried out or expenditure incurred prior to the date of the determination of the rates as aforesaid according to such rate or rates as shall be fixed by the Engineer. In the
event a dispute, the decision of the General Manager shall be final.
In the additional or altered work for which no rates is entered in contract or in the U.P. Jal
Nigam schedule of the rates of the district, is ordered to be carried out before the rates are agreed upon, then the contractor shall, within seven days of the receipt of the order, carry out
such works as he may consider advisable. However the work is to be carried out according to
design, drawings and specification recommended by the contractor and alteration above
referred shall be within and specification appended to the tender.
ACTION WHERE NO SPECIFICATION:
In the case of any class of work of which there is no mention of specification, such work shall
be carried out in accordance with the instructions and requirements of the Engineer.
DEVIATIONS FROM DRAWINGS AND SPECIFICATIONS:
Deviations or changes shall not be made by the contractor himself without the prior approval of
the Engineer, from the dimension, sizes, material or workmanship, specifications of works
shown in the drawings, specifications, instructions issued on same by the Engineer or his
authorized representatives. All the sizes shall be executed strictly according to the drawings,
and specifications using best quality of raw and finished materials, best workmanship to the
complete satisfaction of the Engineer.
COPIES OF SUPPLY ORDERS AND OTHER LITERATURE OF ARTICLES
PRODUCED FROM THE TRADE:
Copies of supply orders and other literature of articles procured in the trade shall be furnished to the Engineer. The technical literature, dimensional and material specifications, guarantees of
materials procured from the trade along with operation, maintenance and installation manuals
also should be submitted to Engineer in triplicate.
DRAWINGS AND SCHEDULES:
Drawings showing workshop fabrications etc. shall be submitted in advance and approval shall
be obtained before commencement of orders from the Engineer or his authorized representatives. However, the approval shall not resolve the contractor from the responsibility
of the performance of the plant.
WORKMANSHIP:
Civil, electrical, and mechanical works included in the tender shall be properly coordinated so that work is completed in time in a complete manner, and handed over in a perfect
workmanship manner in good working condition and to the complete satisfaction of the
Engineer.
ENGINEER’S RIGHTS IN CASE OF USE OF INFERIOR MATERIALS,
WORKMANSHIP AND PLANT:
Engineer during the course of execution of the work shall have absolute powers hereunder to
order the following in writing from time to time regarding the quality of the work.
The discontinuance of the use of inferior quality of materials which do not confirm to the
specifications and removal of the rejected material from the site of works forthwith.
Stoppage of improper, inferior and unsuitable plant used for construction, stoppage of inferior workman-ship, improper construction methods, etc.
The re-execution of dismantled/rejected work(s) using fresh materials, labour, plant according
to the specification laid down in the contract shall be started by the contractor. In case the contractor fails to execute the orders, the Engineer shall have powers to get the defective work
rectified/re-constructed/replaced by another agency and all the expenses on account of same
shall be charged to the contractor and shall be recovered from payments due to him or from
payments to become due to him.
SETTING OUT OF WORKS:
The contractor is responsible for setting out the works as indicated in the drawings and
instructions given in this regard and to obtain the approval of the same from the Engineer or his authorized representative before commencing the works. The contractor shall provide, free of
cost, all facilities like labour, instruments, etc. and all cooperation to the Engineer to check all
dimensions, alignment level etc. This shall however not dissolve the contractor of his own
responsibility of maintaining the accuracy of work.
INSPECTION, TESTING AND MISCELLANEOUS:
ACCESS TO THE WORK:
The Engineer in charge or his authorized representative and consultants of the Engineer shall be provided with all facilities to access to the site of works, fabrication shops, stores of materials,
labour camps, testing shops and other premises connected with the execution of works in any
way all time, for inspection, supervision, examination of all related works.
GUARANTEES:
Not withstanding the detailed drawings supplied and specifications given in the tender, the
contractor can not claim any relief from his responsibility towards the performance of
mechanical and electrical equipment and the whole functioning of the works for which it is intended. The contractor is deemed to posses the above knowledge absolutely, before tendering
without any ambiguities or doubts which, if any, may be got clarified from the Engineer and
then only submit his tender.
POWER AND WATER REQUIRED FOR CONSTRUCTION/TESTING:
Contractor shall make their own arrangements for power and water required for execution and
testing of works at their own cost and the rates quoted shall be deemed to include all such expenditure. The above required for testing shall also be the contractor’s responsibility. If
possible, water and power shall be supplied only at one point by the department for which the
amount will be recovered at the prevailing rates.
DEWATERING AND EXTRA WORK IN FOUNDATIONS: Dewatering of foundation, trenches etc. shall not be paid extra over and above the rates quoted
and the rates quoted shall be deemed to be inclusive of the above items of work. Shoring and
strutting work required for excavation, excavation in difficult conditions of soil shall not be
paid extra except in case to be paid as indicated on the bill of quantities.
AS BUILT DRAWINGS:
On completion of the works, before issuing of the completion certificate by the Engineer, the
contractor shall submit 3 sets of drawings.
SITE CLEARANCE:
No extra money will be payable to the contractor for removal of stubs, debris, rubbish, moulds
of earth or any such unevenness in their ground levels before commencement of the works. Similarly, he will remove from site above said materials and spoil such surplus materials as
directed by the Engineer and leave the site in a condition that is acceptable to the Engineer as
far as cleanliness of work site is concerned without any additional payment. His rates shall be
deemed to include all expenditure.
Except with prior permission in writing of the Engineer, the contractor shall not divert his plant
labour, materials to any other work. In granting such permission the Engineer may impose any conditions as may be found necessary to ensure that no delays or interruption are caused in
execution of the works under the contract. The contractor shall not be entitled to any
compensation resulting from such delays. Granting such permission shall not resolve the
contractor from the responsibility of completing the works as per time schedule specified in the contract.
MAKING AVAILABLE DRAWINGS AND DOCUMENTS AT SITE:
One set of drawings and all other documents relating to the works under contract shall be kept in the site office and made readily available for discussion, examination of the Engineer or his
representatives.
WORKS TO BE OPEN TO INSPECTION:
All works under or in course of execution or executed in pursuance to this contract shall at all times be open to the inspection of the Engineer and his authorized representative. The
contractor shall at times during the usual working hours and at all other once of which
reasonable notice of the intention of the Engineer or his authorized representatives to visit the works shall have given to the contractor, either himself be present to receive instruction or have
a responsible agent present for that purpose. Orders given to the contractor’s agent shall be
considered to have the same force as they have been given to the contractor himself. Verbal orders shall not be considered as binding on either party until they are confirmed in writing and
signed by the Engineer.
NOTICE TO BE GIVEN WORK IS COVERED UP:
The contractor shall give not less than five days in advance notice in writing to the Engineer, or his duly authorized representatives of the work before covering up, or otherwise going beyond
the reach of measurement any work, in order that same may be measured, and correct
dimensions thereof be taken before the same is so covered up of placed beyond the reach the measurement any work without the consent in writing of the Engineer or his duly authorized
representative if any work shall be covered up or placed beyond the reach of measurement
without such notice having been given or consent detained, the same shall be uncovered at the
contractors expanses. In default thereof no payments or allowance shall be made for such work
or the materials with which the same was executed.
WORKS TO BE UNDER DIRECTION OF ENGINEER:
All works to be executed under the contract shall be executed under the direction and subject to the approval in all respect of Engineer who shall be entitled to direct at point or points and in
what manner they are to be commenced from time to time.
DECISION OF THE CHIEF ENGINEER: Except where otherwise specified on this contract, the decision of the Chief Engineer for the
time being shall be final conclusive and binding on parties to the contract upon all questions
relating to the meaning of the specifications drawings and instructions therein before mentioned
and to the quality of workmanship and materials used on the work or as to any other question,
claim, might matter of things, whatsoever in any way arising out of or relating to the contract drawings, specifications, estimates, instructions, orders or these conditions or otherwise
concerning the works or the execution or failure, to execute the same, whether arising during
the progress of the work or after the completion or the sooner determination thereof of the
contract.
TAKING OVER OF THE TUBEWELL:
Following final inspection and when the Engineer is satisfied that the entire works have been completely constructed, erected, tested, and only when all specified test certificates, are
supplied, the Engineer will issue a taking over certificate. Until such certificate is issued, the
contractor shall be responsible for making good any damage occasioned to the tubewell.
FACILITIES TO BE PROVIDED BY THE CONTRACTOR:
1) The contractor will make his own arrangement for all his communication needs such as
telephone; telex etc. at his office and his residential area. Owner will assist the contractor in
getting the above facilities, in case of difficulties.
2) The areas where equipment might drip oil and cause damage to the floor surface, a suitable
protective cover of a flame resistance, oil proof sheet shall be provided to protect the floor from
such damage.
CONSTRUCTION/MANAGEMENT
This is the essence of the contractor and the contractor shall be responsible for performance of
his works in accordance with the specified construction schedule. If at any time the contractor
is falling behind the schedule he shall take necessary action to make good for such delays by increasing his work force or by working over time. The contractor shall not be allowed any
extra compensation for such action.
CONTRACTOR’S CO-OPERATION WITH THE OWNER:
In case where the performance of the erection work by the contractor affects the operation of
the system facilities of the owner, such erection work of the contractor shall be scheduled to be
performance only in the manner stipulated by the purchaser and the same shall be acceptable at
all these to the contractor. The purchaser may impose such restrictions on the facilities provided to the contractor such as electrically, water etc. as he may think it in the interest of the owner
and the contractor shall strictly adhere to such restrictions and co-operate with the purchaser. It
will be the responsibility of the contractor to provide all necessary temporary instrumentation and other measuring devices required during start up and operation of the equipment system
which are erected by him. The contractor shall also be responsible for flushing and initial filling
of all the oil and lubricants required for the equipment furnished and erected by him so as to make such equipment ready for operation. The contractor shall be responsible for satisfactory
operation of the equipment.
The vendor attention is invited to the specific clause, about delay hold up due to other agencies
work affecting time to erection, testing, commissioning.
CO-OPERATION WITH OTHER CONTRACTORS AND CONSULTING PURCHASER: The contractor shall agree to co-operate with the owner’s other contractors and consulting
purchasers and freely exchange with them such technical information as is necessary to obtain
the most efficient and economical design and to avoid unnecessary duplication of efforts. The
contractor shall attend design coordination meetings at his own cost when ever required.
FIELD OFFICE RECORDS:
The contractor shall maintain at his site office upto date copies of all drawings, specifications longbooks and other contact documents and any supplementary data complete with all latest
revisions thereto.
DESIGN CO-ORDINATION:
The contractor shall be responsible for the selection and design of appropriate equipments to
provide the best coordinated performance of the entire system. All the rotating components
shall be so selected that the natural frequency of the complete unit is not critical or close to the
operating range of this unit.
QUALITY ASSURANCE PROGRAMME:
To ensure that the equipments and services under the scope of this contract whether manufactured or performed within the contractors works or at his sub-contractors premises or at
the owner’s site or at any other place of work are in accordance with the specifications. The
contractor shall adopt suitable quality assurance programme to control such activities at all
point necessary. Such programme shall be outlined by the contractor and shall be finally accepted by the purchaser after discussions before the award of contract, and such agreed
programme shall form a part of the contract.
DEFECTS IN WORKS OF OTHER CONTRACTORS: The purchaser shall be notified promptly by the contractor of any defects in the other
contractor’s work that could affect the contractors work.
The purchaser shall determined the corrective measures if any, required to rectify this situation after inspection of the works and such decisions by the purchaser shall be binding on the
contractor.
UNFAVORABLE WORKING CONDITIONS:
The contractor shall confine all the field operations to those works which can be performed without subjecting the equipment and materials to adverse effects, during inclement weather
conditions, like monsoon, storms, etc. and during other unfavorable construction conditions
will in no way relieve the contractor of his responsibility to perform the works as per the
schedule.
PROTECTIVE GUARDS:
Suitable guards shall be provided for protection of personal on all exposed rotating and/or
moving machine parts.
PROGRAMME OF WORKS:
As soon as the letter of indent is issued to the contractor, he will submit to the Engineer his
programme to complete the works by the time indicated in the contract, in the form of a bar chart for review of the Engineer and make suggested modifications before his approval of the
same. The approved bar chart shall be diligently and strictly followed with a view to complete,
the works as per schedule. The programme of work shall be reviewed from time to time by the Engineer and he may modify the same depending upon the exigencies of the work and stage of
the works.
INSURANCE:
The contractor, shall unless otherwise specified by the purchaser, insure the plant and shall keep it insured against destruction or damage by fire, earthquake, flood storm under exposure
to the weather or through riot , civil emotion, war or materials until the plant is taken over.
The insurance for the equipment shall cover the risks towards handling transit, storage at site, re transporting up to the place of erection, testing and commissioning of the equipment at site. The
contractor shall take the policy in the name of the consignee of the department. The insurance
policy then will be assigned to the contractor for further operation. The insurance shall be full
and shall cover any loss or damage in accordance with what is said above. The damage materials will be set right or replaced by the contractor, free of cost. The claims arising out of
the composite insurance policy shall be dealt with or handled by the contractor at his own cost
after receipt of preliminary damage/loss intimation given by the Engineer.
PATENTS, RIGHTS ETC.:
The contractor shall fully indemnity the purchaser against all actions, suits, claims demands,
costs, charges and expenses arising from, or incurred by reason from any infringement for any letters, patent designs, trademark or name, copyright or other protected rights in respect of any
machine of using, fixing, working or arrangement used or fixed or supplied by the contractor but his indemnity shall not extend or apply to any action, suit, claim demand cost charges or
expenses arising from or incurred by reason of the use of the works or any part thereof
otherwise than in the manner or for a purpose contemplated by the contract. All royalties and other similar payments which may have to be paid for the use of any such machine, plant,
work, material thing, system or method as aforesaid (whether payable in one sum or by
installments or otherwise) shall be covered by the contract price and payable by the contractor.
In the event of any claim or demand being made or action or suit through against the purchaser
in respect of any such matter or matters as aforesaid the contractor shall be duly notified
thereof, and he shall conduct all negotiations for the settlement of such claims or demands and
such action or suit shall also be conducted by him, if and as far as the owner shall think proper,
to the supervision and control of the owner through the officer duly authorized in his behalf.
OTHER CONTRACTORS:
When two or more contractors are engaged on work in the same vicinity, they shall work together in a spirit of cooperation and accommodation. The contractor shall not take or cause to
be taken any steps or actions that may cause disruptions, discontent or disturbance to the works,
labour and other arrangements of other contract in neighboring and the project localities. In case of any difficulty among the contractors, the Engineer shall direct the manner in which each
contractor shall conduct his work so for as it affect others.
DISCREPANCIES AND ADJUSTMENT OF ERRORS:
The several documents forming the contract are to be taken as mutually explanatory of one another, detailed drawings being followed in preference to small scale drawings and the figured
dimensions in preference to scale.
If there are varying or conflicting provisions made in any document forming provisions made in any document forming part of the contractor the accepting officer i.e. the General Manager
shall be the sole deciding authority with regard to the intension of the document and his
decision in this respect shall be final and binding.
Any error in description in the bill of quantities of any omission therefore shall not vitiate the contract or release the contractor from the execution of the whole or any parts of the drawings
and specifications or from any of obligation under the contract.
If there are discrepancies found in the tender documents and the same have not been clarified before submission of the tender, the interpretation or clarification given by the Engineer is final
and conclusive.
Any disputes or differences whatsoever will shall at any time in between the parties hereto touching or concerning the works under the execution or maintenance thereof or this contract or the
construction, execution or maintenance thereof or the construction meaning operation or effect
thereof, or to the rights and liabilities of the parties or arising out of or in relation thereto whether
before or after determination, for closure or breach of the contract (other than those in respect of which, the decision of any person is by the contract expressed to be final and binding) shall after
written notice by either party to the contract to the other of them specify the nature of such dispute
and difference and call for the point or points at issue to be referred to the arbitration.
ARBITRATION SHALL BE EFFECTED:
By an arbitrator agreed upon by the parties or failing agreement upon such an arbitrator.
By an Arbitrator appointed by the President of the Institute of Engineers (India) or failing such
appointment.
By an arbitrator appointed by the Chief Engineer, U.P. Jal Nigam or failing such appointment.
By an arbitrator appointed in accordance, with the provisions of the Indian arbitration act,
which law governs the contract.
The arbitrator so appointed shall be a person presently connected with the organization for
which and by which the work is executed.
Premises to arbitration shall be a deemed to be a submission to arbitration within the meaning
of the Indian arbitration act, which law governs the contract.
If the arbitrator so appointed is unable or unwilling to act or resigns his appointment or vacates his office due to any reason whatsoever another sole arbitrator shall be appointed as aforesaid.
Work under the contract shall, if reasonably be possible, true during the arbitration proceeding
and no payment due or payable to the contractor for other works than under arbitration will be
withheld on account of such proceeding.
Arbitration shall be deemed to have entered on the reference on date he issues notice to both the
parties fixing the date of first hearing.
Arbitration may, from time to time with the consent of the parties, enlarge the time for making
and publishing the award.
Arbitrator shall give a separate award in respect of each difference referred to him.
Place of arbitration shall be within the limits of Jhansi.
Fees, if any, of the arbitrator shall, if required to be paid are the award is made and published,
be paid half and half by both of the parties. The cost of the reference and of the award including
the fees, if any, of the arbitrator shall be in the discretion of the arbitrator who may direct to and by whom and in the manner, such cost or any part thereof be paid and may fix or title the
amount of cost to be paid.
Any disputes in the matter of the contract are subject to jurisdiction of appropriate court at
Jhansi.
--------------------------------
Witness Signature
Name----------------------------------------
Address-------------------------------------
-----------------------------------------------
------------------------------------------------
--------------------------------
Signature of Contractor
Name----------------------------------------
Address-------------------------------------
-----------------------------------------------
------------------------------------------------
FORM OF TENDERER
(To be filled and signed, witnessed and submitted by the tenderer)
From : ………………………..
………………………..
……………………….. ………………………..
To,
The Executive Engineer, Jhansi Division Ist,
U.P. Jal Nigam, Jhansi.
1. I/We ………………………..………………………..……………………….. have read the various
conditions governing the contract attached hereto, studied the specifications, possess the knowledge of site
conditions, availability of materials and labour. I/We offer to do the work of Tube well Construction As
per laid down specification/drawings and abide by the conditions. I/We also agree to keep this offer valid
up to 180 days from the date of receipt/opening of tenders whichever is later.
2. I/We agree to complete the works within 06 months from the date of issue of letter of intent.
3. A sum of Rs 1,96,000.00 towards Earnest Money in the form of ……………………
……………………….. drawn on ………………………….………..………………………..Bank
Bidder has to be prior to starting the work and should have comprehensible approach to
complete the work with his own arrangement for the T&P and other accessories required for
successful completion of the work. It is presumed that bidders have visited and examined the
site conditions to curb the difficulties / obstructions likely to be arisen while completing the
work. it is also presumed that rates quoted by the bidders have sufficient margin to overcome
the cost of unforeseen expenses and running errands in course of the work completion. The
rates in schedule ‘G’ will be inclusive of such expenses having no counts to asked for extra
payment or compensation and therefore, no claim for any compensation in any shape arisen
out of such difficulties shall be entertain. Time is the essence of this contract. No request for
extension of time will be entertained unless the Engineer finds the delay is not due to
procrastination.
SCHEDULE ‘B’
(List of plans accompanying the tender)
NIL
SCHEDULE ‘C’
(List of the drawings to be provided by the contractor to the Engineer during the course
of contract) 1. Boring charted as per format provide by Engineer. 2. Proposed Tube Well assembly chart for Engineer’s approval. 3. Manual of O&M for pumping plant, switch gear materials etc. are to be provided the
site in charge.
SCHEDULE ‘D’
(List of samples to be submitted by the contractor to the Engineer during the course of contract)
The contractor shall deliver following samples. Either at the site of work or at the office as
desired by the Engineer.
i. Sample of strata met with during boring. ii. Any other samples if required by the Engineer
SCHEDULE ‘E’ List of Test to be conducted
For Tubewell
1. Yield test and test for measurement of sand contents. 2. Any other test as decided by Engineer.
Note:- Yield test shall be conducted through V-Notch or circular orifice meter or any other
method approved by the Engineer.
For Pumping Plant
Schedule É’ has to be provided in terms of discharge (Q)- head (H) & efficiency of pump
and motor from the selected characteristic curve of model and make of the pumping plant.
Signature of Contractor
Dated : …….................
SCHEDULE ‘F’
(Completion Period)
Period for completion of the work as specified shall be taken up by the
bidders or their representatives under the guidance of the site in charge which
shall be carried out to the satisfaction of the site in charge in terms of quantity &
quality of the work and therefore, onus lies on the bidder to carry out the work
under the guidance and control of site in charge. However, responsibility shall not
ceases until the defect liability period is expired.
The Completion period shall be Scheduled as under:-
1 The Completion period for Total work included in
contract 12
Month
2 The Completion period for each Tube Well from the
availability of the Pin Point 45
DAY
SCHEDULE ‘J’
(Terms and Procedures of Payment) The following shall be the breakup for the running payments of Execution of
Reorganization of Water Supply Scheme on the basis of schedule “G”
S.No Description of item Performance level of works % of payment allowed
on the basis of
performance
1
Construction of deep
Tubwell of desired depth
and discharge, Drilling,
Supply and lowering of
Tubewell Assembly etc
complete, Development of
Tubewell by compressor
and O.P Unit
Supply & delivery of T/w
assembly with accesorries
complete in all respect
Completion of boring &
Lowering of Tubewell
Assembly complete with
housing, Plain/slotted pipe,
reducer, Bail plug, M.S
Clamp, well cap, M.S ring
etc
50%
Development of Tubewell
by compressor and O.P
Unit,
30%
Testing and commissioning
10%
Completion of 3 months
trial run
10%
2
Supply and installation of
submersible clear water
pumping
plant/Cholorinating
Plant/Voltage stabilizer/
Internal & External
electrification of Pump
house
On supply & delivery of
materials
50%
On installation Testing and
commissioning
30%
After successful completion
of 3 months trial run
10%
After successful completion
defect liability period of 18/
24 months
10%
I/We have read understood and accept for compliance, the above
mentioned instructions and conditions of this schedule and have taken factors in to
1.1 Supply & erection of all required tools plants (T&P,) for drilling of necessary bore of required size as
detailed in BOQ, lowering of well tubes together with all excavation, pumping, all temporary masonry
work, channels for samples, dressing & cleaning of site & reinstatement.
1.2 Supply & erection of all required T& P for development of Tube Well.
1.3 Supply & erection of all temporary and auxiliary plants such as derricks, hoists, etc. and other
appliance required for the work.
1.4 Supply of all lubricants and oils, cotton and other material required during the drilling,
developing and testing operations.
1.5 Supply of bentonite and sticky clay if required to line up the bore.
2. TRANSPORTATION:
This includes transportation of drilling and developing equipment like rig, compressor, O.P. unit
with all required auxiliary T&P and material to proposed site including carting loading,
unloading etc. complete work. 3. DRILLING:
3.1 This includes installation of rig machine, drilling of bore well, up to required Depth for
successful construction of tube well in full satisfaction of Engineer in charge, including supply
of all required material like bentonite, sticky clay and Ferrow speed electro rod/ ISI mark etc.
and also make provision for water arrangement for drilling at their own expenses.
4. LOGGING:
4.1 After completing the bore well, its logging will be within the scope of the contractor which shall
be done by the departmental/U.P. Jal Nigam approved loggers on their own cost.
4.2 No compensation shall be paid to the contractor on account of any delay in electric logging of
bore well.
4.3 The Contractor shall maintain the bore hole up to logging or lowering with shrouding is
complete in all respect.
5. TUBE WELL ASSEMBLY AND ITS LOWERING:
5.1 Tube well assembly will be supplied by the Contractor. MSERW Pipe to be used should strictly
Confirm to IS 4270:2001 after dispatch of MSERW Pipes contractor has to arrange inspection at
manufacture fection 5.2 All the associated accessories as mentioned in detailed specification, of tube well Assembly, will
be supplied by the contractor.
5.3 The contractor shall prepare the tube well assembly as approved by the Engineer in advance and shall arrange the same in proper sequence at site. He shall get the same checked and passed by the Engineer or his authorized representative. There after the assembly shall be painted with standard quality anti-corrosive paint.
5.4 Before lowering the tube well assembly the contractor shall ensure that the bore hole is clear up to the
required depth and shall get it checked by the Engineer or his authorized representative.
5.5 The lowering of tube well assembly carried out by contractor. 5.6 The welding Job Work of tube well Assembly parts to give sufficient strength to the assembly will be done
by the contractor at the time of lowering, in the presence of the Engineer or his authorized
Representative. The contractor shall ensure that lowering of assembly takes place smoothly, &
entire responsibility for that shall be on the contractor.
5.7 As soon as the lowering is complete, the contractor shall take the sounding of the lowered tube well
assembly to the Engineer or his authorized representative. In case the complete sounding of tube well
assembly is not found then it will be entire responsibility of the contractor. 6. PEA GRAVEL AND ITS SHROUNDING :
6.1 The gravel packing shall be done by a suitable method approved by the Engineer or his authorized representative.
6.2 The packing of gravel in the annular space between the well pipe and the bore shall start at the
bottom of the well and extend upwards to the ground level.
7. DEVELOPMENT:
7.1 The development of the tube well shall be done first by the proper size & capacity air
Compressor, after that it shall be done by O.P. Unit of Suitable capacity.
7.2 During development by air compressor as soon as the pea-gravel is not sinking during back
blowing in annular space between the bore and tube well assembly water becomes clears &
starting sand content are between 3000 To 4000 ppm it will be assumed that there is no need of
further development by air compressor provided that there is no bridging This shall be decided
by engineer In charge or his representative white testing.
7.3 The development of the tube well by O.P. Unit shall be done by suitable capacity O.P. Unit till
the water level and discharge becomes steady and sand content within tolerable limits.
7.4 The Engineer has sole right of deciding, development of T/W done by department unites also or
by other agencies in case of work getting delayed. If development of tube well will be done with
the help of departmental Units then it will be in supervision of contractor at their risk, the
responsibility for construction of successful tube well be on contractor.
8. LIMITS OF CONTRACT:
The work included in this contract shall be deemed to be complete finally when all the
specifications set up herein and conditions of contract attached have been completed with and
tube well having been successfully tested and handed over to the Nigam.
9. DESIGN, MATERIAL AND WORKMANSHIP:
The specification as set for the execution of the various parts are to be followed. Any
suggestions with a view to effect the economy or to increase reliability in operation which the
tender may wish to offer must be set forth in the schedule as addendum for consideration.
10. RESPONSIBILITIES OF CONTRACTOR:
10.1 The contractor shall maintain Chaukidar at his own cost to watch T&P and also provide
material for protection of work if necessary. He shall arrange for storing of T&P and materials
for accommodation of supervising staff engaged on the work by him. The contractor shall also
arrange his own supplies of water, fuel etc. for the use of his workman and also for the execution
of the work.
10.2 Until the test specified herein have been applied and the installation have been passed
and formally accepted by the Engineer the contractor shall be entirely responsible for the
working or performance, whether such working as for the propose of testing or in the service of
Nigam.
10.3 As each part of the construction of the tube well is completed, it shall be checked over
by the Engineer or his authorized representative. The representative of contractor shall ascertain
with the Engineer’s representative from time to time, what parts he wished to check over and
pass but such passing shall be no way relieve the contractor from his responsibility, until the
entire work has been completed according to the contract and taken over by the Engineer.
10.4 Contractor shall take all safety measures at site. He shall arrange first aid box at site. in
the event of any accident, he should make arrangement for primary & higher medical facilities
to labour engage by him. Jal Nigam shall not bear any liability about accident at site. The entire
liabilities about first aid, higher medical facilities and compensation if arises have to be borne by
the contractor.
10.5 The contractor shall submit daily report of the work done by him each day to the
Engineer on the prescribed format to be obtained from the Engineer. These reports shall be
handed over to the Engineer’s representative stationed at site or/also posted to the Engineer (in
case there is no representative stationed at site) every day after close of the day. Postage changes
for the same shall be borne by the contractor.
10.6 Work done of any kind to the designated site for the construction of Tube Well or any
other material such as fuel etc consumed by the contractor shall not be paid out in case of failure
of tube well however contractor can retrieve them. 11. TESTS:
During the progress of the work and after its completion the contractor shall carry out such tests, as
in the opinion of the Engineer are necessary to insure that the installation compile with the conditions
of these specification whether under test conditions or in ordinary working. All pipe connections and other apparatus required for the tests shall be provided by the
contractor at his own cost.
12. REINSTATEMENT:
After completion of work the contractor shall remove all surplus material and dresses the ground
disturbed during the operation of the excavation boring and construction of the well to the
satisfaction of the Engineer.
13. VERTICALITY: 13.1 The formal test is not required due to proposed Pumping Plant is of submersible type, although
constructed tube well should be vertical and having clear cylindrical space within the housing
pipe to accommodating the O.P. Unit for development of Tube Well and also submersible
Pumping Plant of requisite capacity with its proper installation and working. 13.2 If the housing pipe is so much non-vertical that it could not accommodate a submersible pumping
plant of requisite capacity with its proper working up to desired depth then the tube well will be
rejected outright, and all expenditure if any done by department on tube well should be recovered
from contractor. If there is any dispute in this regard the final decision authority will be chief
Engineer (E&M) and whose decision shall be binding to contractor.
14. YIELD TEST:
The official yield test shall be conducted by department as per departmental norms, but all
arrangements for that shall be provided by contractor on his own cost.
15. COMPLETION AND HANDING OVER OF TUBE WELL: 15.1 After giving the official test as above, the contractor shall give sounding of the tube well to the
Engineer or his authorized representative. In case the complete sounding is not found and it is
observed that sand is plugged more than half the length of the bail plug, than it will be
responsibility of the contractor to clear the tube well at his own cost and risk. 15.2 Just after giving the sounding and accepted by the Engineer or his authorized representative, the
contractor shall cap the tube well duly welded.
16. PRESERVATION OF EXCAVATED MATERIAL:
As the boring work of Tube Well proceeds, the contractor shall keep carefully notes of all changes of
strata after every 3 meters or earlier whenever the strata change and keep its measurement from
ground level and shall preserve a sample of soil taken from every strata, each sample must be atleast
200 c.c. by volume and must be carefully preserved and marked with the depth and range from which
it was taken in transparent packages. The contractor shall also maintain at the site, the boring chart
showing daily progress of the work, nature of soil passed through each day and the thickness of each
strata and others. The strata samples shall be handed over to the Engineer.
17. SITES FOR TUBE WELL: 17.1 The site of tube well shall be shown to the contractor or his authorized representative before
starting the work. 17.2 The contractor is strongly advised to consult strata chart of boring done in vicinity of the place.
The strata chart available in the office may be seen but these can be only taken as guide. No
claims shall be entertained differs from that shown on those charts.
18. FAILURE OF TUBE WELL:
If the tube well fails due to bad workman ship/accident or any other reason on account of
contractor, except that non availability of suitable strata, the department will not make any
payment to the contractor for that T/W and if any expenditure done by department on that tube
well will be recovered from the contractor’s Security Money Deposit/payments out standing in
this division or any other divisions in Jal Nigam.
Technical / Terms & Conditions for Construction of Tube well by DC Rig Machine in
Distt. Jalaun
1. Cost are to be quoted for Six Numbers Tube well’s as per BOQ.
2. Required Tube well assembly shall be supplied by contractor should confirm to IS-4270:2001. Technical
specification and other data of pipes shall be as per relevant IS or their latest revision. Bidden has to
submit QAP after quard of contract.
3. Quantities given in BOQ are approximate and average and may vary upto any extent as tube
wells are proposed to be constructed in the range up to 110 meter depth.
4. Contractor has to arrange adequate continuous clear water supply required during drilling and cost of the
same should be included in the rates tendered for construction of the tube well is must.
5. The rates shall include the collection and preservation of strata samples taken at every three meters
depth and where ever the strata changes, supplying the boring/strata chart immediately after
completion of drilling and supplying lowering chart to the deptt. and got approved before lowering
and the contactor shall submit finally tube well completion chart.
6. Pea gravel shall be supplied from LAL KUAN quarry (Haldwani, Uttranchal) which shall be
thoroughly washed, graded, screened and stacked properly at site, 5% of quantity shall be
deducted against bulk age/voids from measured quantity of pea gravel.
7. Yield test of tube well shall be carried out in accordance with IS-2800 (part II) and detailed
specifications given in tender form. In case of any deviation suitable action shall be taken as per
CB or decision taken by the competent authority regarding the acceptance of tube well which
shall be final and binding.
8. It is sole responsibility of the contractor to prepare lowering assembly based on the actual strata
encountered matching with logging report ant then get it duly approved by the Engineer In
charge there after the lowering work will be started by the contractor.
9. The income tax, work contract tax, labours cess. as applicable at the time of payment, shall be
deducted at source as per Govt. rules, hence rates should be quoted accordingly.
10. The contractor shall be paid 100% of quoted rates after construction, development and testing of
tube well. If required, approach path upto the pin point given would be constructed by the
contractor and if any hindrance encountered in making approach path the same will be resolved
by the contractor at his own cost. Any damage/loss to public or Govt. properties will be born by
the contractor.
11. Site clearance/leveling of site will be done by the contractor after completion of TW construction.
12. The contractor will have to take all preventive measures with the help support of site in charge to
ensure that Tube well construction site is not exposed to risk of accident to the passers by,
residents of the neighborhood or children etc. Until the Tube well construction is complete in all
respect. Failing which, contractor in person is liable for prosecution as per law of the land in
case of any accident or loss to life and property. After the successful completion of the tube well
all the activities pertinent to safety measures shall be carried forward by the Deptt.
13. Contractor or drilling agency shall be sole responsible for any injury or damage to Tube well
assembly while drilling lowering and development works caused by in proper handling of the
machine or any gadget or equipment or machine failure. In event of loss to property of the
Deptt. shall be recovered from the contractor.
14. Drilling agency shall be sole responsible for any accident due to their negligence, apathetic/
sluggish attitude and shall pay out compensation to the party inflicting any injury or loss to life
and property.
15. Engineer in charge is not responsible for acquiring and providing legal and physical possession
of the site other than the getting the construction of the tube well is complete at the pin points
according to the choice and selection of the concerning authority.
16. Argument or dis argument or spat with site in charge at site or in office with any officers shall be
treated as misconduct amounting to cancellation of the contract bond.
17. While transportation of the Rig Machine to the pin point, approach road shall be made by the
Deptt. if it is deemed necessary.
18. During development of tube well, disposal of discharged water in general specified by the site in
charge will be made by the contractor at their own cost. Unless otherwise unfavorable
circumstances
19. After completion of work all pits would be leveled and cleared, excess earth shall be removed
from the site by the contractor.
20. Carting of tube well assembly from divisional store to pin point of tube well will be done by
contractor on his own cost.
21. Contractor have to provide a vehicle for supervision purpose to the executing staff during the
completion period of tubewell construction as per the directions of the engineer, failing which
the department shall arrange for the same on the cost of contractor as per the approved
departmental rates.
22. The contractor must have experience of construction of such type of TWs & the certificate must
be attached along with other documents. The contractor has to arrange the following machine /
T&P in good running condition for construction of tube wells.
(i) Rig machine - D.C. Rig machine 675/600 or as required as per Schedule “G” above with
all its accessories, T&P, welding plant etc.
(ii) Compressor- 250 PSI compressor with all T&P & accessories
(iii) OP Unit- 3 cusec capacity with all T&P & accessories.
23. Flexibility of the contractors. 23.1 This contract provide a certain number of tube wells for construction as per NIT. But the contractor
may be called upon to construct further number of tube wells under this contract as it may be
necessary as per direction as directed by the competent authority.
24. From the date of availability of pin point the contractor has to complete the construction of
tubewell within 45 days otherwise penalty will be imposed as per directions of engineer in
charge if it deems that the delay is from the part of contractor.
Construction of Tubewells Detailed Specification
1. Tube well assembly:
300 mm dia housing pipe , 200mm dia plain/slotted pipe of Tubewell assembly will be supplied
by the contractor. Should confirm to IS 4270:2001
1. Tubewell Accessories : (Supplied by the contractor)
(a) Well Cap :- Well cap made out from 100x10 mm M.S. flat, 5mm thick top sheet with a
handle on top suitable for M.S. Housing pipe 300 mm dia.
(b) Housing Pipe Clamp :- Housing pipe clamp made out from 100x16 mm M.S. flat with
500 mm long arm on both ends having drilled hole and fastened by means of 4 Nos. ½”
dia 6” long, nut bolt & washer suitable for clamp 300 mm dia M.S. pipe.
(c) M.S. Ring 300 mm dia :- Ring made up of 150x12 mm M.S. flat suitable for M.S. Pipe the
ring has to be tapered with ‘V’ groove at both ends and seat in between, suitable for 300 mm
dia.
(d) M.S. Ring 200 mm dia :- Ring made up of 150x12 mm M.S. flat suitable for M.S. Pipe
The ring has to be tapered with ‘V’ groove at both ends and seat in between, suitable for
200 mm dia.
(e) M.S. Reducer: - Reducer made up of 12 mm thick M.S. flat having total length of 350
mm and upper & lower ring of 100 mm wide suitable for 300x200 mm. Size.
(f) Bail Plug: - Bail plug made out from 100x12 mm flat with ‘U’ Hook of 20 mm dia M.S.
rod 300 mm high, bolted at bottom of bail plug suitable for 200 mm dia M.S. pipe.
(g) Centre Guide: - Centre guide made out from 25x5 mm M.S. flat 300 mm long suitable
for 200 mm dia pipe.
(h) MS Fabricated Tubewell support:- Tubewell support made up of 200x100 mm size MS
girder having 2.5m long and in H shape as per departmental design.
2. Gravel Packing:
Gravel packing shall be done by suitable method approved by the Engineer or his authorized
representative. The placing of the gravel in the annular space between the well pipe and the hole
shall start at the bottom of the well and extend upward to ground level. The construction of the gravel
filter once started will be continuous operation until it is finished.
The following specifications are to be followed for supply of Pea Gravel for Tubewell.
1. The Gravel has to be supplied from Lalkuan, Query Haldwani and conforming to IS 4097-1967
and as latest amendments.
2. The average particle size of Gravel shall be 1.6 to 4.8mm. 3. The Gravel shall consist of hard quartz (about 96% SiO2) or other suitable material, with an average
specific gravity of not less than 2.5. Not more than 10% by weight of the material shall
have a specific gravity of less than 2.25. The Gravel shall contain not more than 2% by weight
of thin flat or elongated
pieces. In case of such pieces, the larger dimensions shall not be more than 3 times the smallest
dimensions. The quartz shall be of sub rounded to rounded grains with minimum angular features.
4. The Gravel shall be free from impurities, such as shale, mica, feldspar, clay, sand, dirt, loam
hematite and organic materials.
5. The particle size distribution of Gravel may be Determine by screening through standard sieve
accordance with IS: 460. 6. The gravel shall have a hardness of not less than 5 in Moh’s scale.
7. Voids @ 5% shall be deducted from quantities measured at site.
8. Any tax, Royalty shall be included in the offered rates.
3. Development by Air Compressor:
The tube well shall be developed either by surging, including washing and agitation by air compressor or by over pumping and back washing with or without an air lift. The development of tube well by air compressor process shall be continued until The tubewell ceases to absorb further gravel. The depression ceases to improve. The discharge ceases to improve. The water is reasonably sand free.
The analysis of sand content will be carried out by the contractor as per written instruction by the Engineer. The sounding of T/W will be taken after development by air compressor and OP unit.
The contractor shall over develop so as to yield a discharge 20% in excess of the rated
discharge or to depress the well to 50% higher than the nominal depression at which the tube well
is pumped on continuous duty which ever may be more.
The discharge during development shall be measured at minimum intervals of 6 hours over
a V-Notch weir or by other suitable method may be accepted and record kept as previously
provided. The development will continue till no further feeding of gravel is found necessary and
the discharge is free of sand within the requirement of specifications.
The discharge shall be sand free i.e. sand contents will be less than 10 ppm in the
final
discharge of the tube well obtained after 05 minutes of starting and clear/traces within 10 minutes.
The discharge of tubewell shall be measured by means of water meter or orifice meter or
rectangular V-notch chamber constructed according to ISS such that the full size discharge from
the outlet pipe the plumb will fall into the first compartment of V-notch chamber. In order enable
the collection of water in a bucket for measuring the sand contents of water a bib cock shall be
provided in the delivery pipe away from the discharge outlet. The contractor will also provide
necessary measuring jars.
The yield of the tube well will be carried out as under:-
Firstly, the discharge of the tube well will be increased in stages at an interval of one
hour and relevant readings at each stage will be recorded by checking these readings. The most
suitable discharge will be selected and the tube well will be run for about 6 hours and the
readings of depression and discharge will taken after every half an hour for ensuring the figure
of discharge and depression remain steady during the entire period of test. The specified
discharge of the tube-well shall be obtained at a depression not exceeding 20 ft. Thereafter the
recoupment test of the tubewell will be conducted by noting the readings of recumbent of water
level in the housing pipe by noting the depth of water level from the top of the housing pipe after
suitable intervals/ Cleaning of water after stopping pumping.
4. Abandonment of Tubewell:
During construction it may be required to abandon the tubewell due to negligence of the working
staff of the contractor, in such case no payment of the executed work will be made to the contractor.
If during drilling very hard rock or boulders or uncontrollable caving strata is met and also if due to
any natural reason i.e. connecting the well with any nearby natural well and it is not possible to drill
further or no strata is met, payment of the actual depth drilled will be made. However the contractor
for at least 48 hours in case of hard rock, try to penetrate it in presence of the Engineer in-charge for
24 hours and if the progress is less than 1 feet in 24 hours and sufficient strata has not been met to
yield required discharge, the bore may be declared as abandoned and payment of actual work
executed will be made.
5. Quality of Water:
In the construction of the tubewell, due precautions shall be taken by the drilling agency to
maintain the premises in a sanitary condition and to avoid as much as practical, the entrance of
contaminated water into the safe water bearing formations, any water or materials used shall be
free of contamination and, if their nature permits, should be adequately disinfected with chlorine
before use. The slush pit should be constructed so that no material there from will enter the well,
except mud reused when the construction is by rotary method. In such cases the slush pit and
mud return channels should be protected against contamination from surface water or any other
sources.
The well shall be disinfected after completion of test for yield. All the exterior parts of
the pump coming in contract with the water shall be thoroughly cleaned and dusted with
powdered chlorine compound.
SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR SITC
OF TUBEWELL PUMPING PLANT 1. SUBMERSIBLE PUMP SET: (Should confirm to IS 8034:2002)
Submersible pumping set suitable for 300 mm dia or 200 mm dia T/W Bore fitted with dynamically
balance bronze or SS impellers mounted on a stainless steel pump shaft with shaft protection sleeves
having stage bowls of closed grained cast iron. The pump will be fitted with built in non-return valve
and shall be suitable for direct coupling to the squirrel cage electric induction, water cooled type
submersible motor suitable to operate on 400 ± 10% V, 3 phase, 50 cycles/sec. A.C. Power Supply
and 2900 rpm (nominal) speed and capable to give a discharge and head as is mentioned in NIT.
Other specifications shall be as per following:
1.1.1 PUMP SET: 1.1.2 A Standard hydrostatic test on all pressure containing parts shall be made at 1.5 times the
maximum discharge pressure. 1.1.3 The bowls shall be equipped with replaceable casing bearing. 1.1.4 The bowl assembly shall bear a name plate preferably embossed information as per following:
a) Name of the manufacturer or trade mark. b) Serial number of the pump set. c) Pump type. d) Number of stages. e) Total head. f) Shut off head. g) Capacity.
Note: Shut off head must be above 25% of the total head required. 1.1.5 The impeller shall be of enclosed type equipped with seal rings on their hubs. Seal rings shall be
provided either with impeller or in the bowl. 1.1.6 The pump shaft shall be guided by bearing provided in each bowl of above and below the impeller shaft
assembly. The shaft without sleeves shall have a surface finish 0.75 micron Ra Max.
1.1.7 The opening in the suction case for the entrance of water shall be of proper size and shape to
avoid eddy currents. 1.1.8 The suction case shall be fitted with a strainer made of corrosion resistant material. 1.1.9 Suitable sand guard shall be provided just above the suction case bearing to prevent the entry of
foreign matter into the suction case. 1.1.10 Non return valve shall be provided above the pump discharge case.
1.2 SUBMERSIBLE MOTOR: (Should confirm to IS 9283:1995) 1.2.1 The submersible motor shall be squirrel cage induction motor. 1.2.2 The winding of motor shall be wet type. 1.2.3 The motor shall be suitable for operation voltages and frequency confirming to IS 585-1962
(revised) “Voltages and frequency for A.C. transmission and distribution system” 1.2.4 The earthing of the motor shall comply with IS: 3043-1966 code of practice for earthing.
1.2.5 The Thrust bearing shall be of adequate size to withstand the weight of all rotating parts as well
as the imposed hydraulic thrust. These shall be lubricated suitably. 1.2.6 The Motor winding and nearing bushes of the rotor shaft shall be cooled/lubricated by pure
water filled in the motor before erecting the pump set. 1.2.7 The motor shall be protected by means of cable glands, rubber seals etc. from ingress of tubewell
water, sand and other foreign matter. 1.2.8 The thrust bearing housing shall be provided with a drain plug to empty the pure water filled into
the thrust bearing housing/Motor. 1.2.9 The rotor shaft in copper strip shall be provided with shaft protecting sleeves having a surface
finish of 0.75 micron Ra max. 1.2.10 The Motor shall be provided with a breathing attachment like bellows, diaphragm etc. to
compensate the Volumetric variations due to change in temperature. 1.2.11 The motor shall be made of corrosion resistant materials or suitably treated materials to resist
corrosion. 1.2.12 The motor shall have a name plate preferably embossed on body of motor giving the following
information :
a) Induction Motor;
b) Name of Manufacturer;
c) Manufacturer’s number and frame reference;
d) Type of duty;
e) Frequency in Hz;
f) Number of Phases;
g) Rated output in HP/KW;
h) Rated voltage and winding connections;
i) Current in amperes at rated output.
j) Speed in RPM at rated output.
1.3 DATA OF PUMP SET:
a) Model of motor.
b) Model of pump.
c) Discharge in LPM.
d) Total head.
e) Nett effective head.
f) Number of stages.
g) Pump outlet size in mm.
h) O.D. of pump in mm.
h) MOC of each and every component of the pump set.
i) Speed of pump set.
j) Method of starting.
The performance details as per enclosed schedule ‘E’ are to be submitted as per enclosed sheet
separately.
1.5 TESTING OF PLANT:
The contractor shall do preliminary testing at manufacture’s works which Shall be witnessed by
department and at site and through testing of the plant during the course of erection and when it is
completed as specified and for official testing of the same in accordance with schedule ‘E’. The electric
motor and pump may be type tested at the manufacturer’s works. Pump sets will be tested at manufacturer
works or at site of the SICT as per schedule ‘E’ uploaded by the contractor and as per IS:8034. Other
material/accessories will be checked as per relevant ISS. Test certificate of the pump set concluded at
works of the manufacturer is obligatory to be furnished with characteristic curve stipulating the discharge,
head or pump efficiency etc that it could ensure duties of the pump set is well suited to need of the
pumping system.
1.5.1 TEST DUTIES AND EFFICIENCIES:
The contractor shall state in the tables attached with tender documents the efficiencies and duties of
the pumping plants when working at specified conditions of the pumping and the guaranteed
performance in K.W. hour input per water horse power output under various conditions of working.
The guaranteed performances are also to be specified under following conditions i.e. variation in
head discharge and power consumption in the following cases:
a) When available voltage decreases from 415 volts to 380 volts or increases from 415 volts to 440
volts.
b) When there is fluctuation of ±3% in the frequency of the AC power supply from 50 C/S.
c) When there is above change in voltage and frequency of the AC power supply simultaneously. The
official tests shall be conducted in two stages. Preliminary tests may be conducted at the
manufacturer’s works. The final tests shall be conducted at site. Pumps shall be run so as to obtain
the range of heads specified in the performance tables by means of throttling or opening valves of the
pumping mains and tests results will be compared with those guaranteed by averaging the units
consumption per water horse power hour.
The guaranteed figures stated above shall be subjected to no tolerance and the average results
shall be obtained during official test of plant. If the results lack average guaranteed figures the
contractor shall forfeit followings ascertained damages relating to each set installed.
If BOT unit (KWI) per WHP, the consumption is above the average guaranteed figure under the
specified Q and H, the liquidated damages will be recovered as the capitalized cost of the Extra
Energy Consumption during the useful life span 15 years of the pumping set. The liquidated
damages shall be calculated as below :-
Cost of extra power consumption
to be recovered shall be equal to =Cost of extra power per annum × capitalization factor for 15
years at an interest rate of 9%.
No damage will however, be recovered if the consumption is less than 0.05 BOT units per WHP
above the guaranteed.
If on testing the discharge of pumps is found to be within the permissible limit of ±4% then the
pumping plant will be accepted without imposing any penalty. If discharge is less by 5% to 10% then
pro rate deduction @ 1% of the cost of pump and motor for less percentage of discharge shall be
made and further if the discharge is less than 10%, plant will be rejected.
It may be noted carefully that no privilege shall be given to any offer for evaluation purposes
considering the efficiency of the pump and Motor. Better efficiency pump and motor however
shall be preferred. For evaluation purposes the maximum efficiency of pump and motor shall be
considered as 72% & 84% respectively but these will be tested on the efficiency quoted by the
firm in schedule-E of their tender
The pump efficiency offered below the efficiency quoted shall be considered for evaluation as
follows:
(i) Electric charges shall be based on 16 hours of operation per day for 15 years at the prevailing
rate of Electric Charges and interest of the rates of 9% per annum for cumulative cost difference
in 15 years. day.
(ii) All future costs of yearly power consumption will be capitalized to present value at
capitalization factor @ 9% interest.
The tenderers shall have to consider the condition of pumps being run at shut off head under the
pump duty variation condition as narrated above. The tenderer should ensure selection of pumps
considering shut off head at least 25% more than the duty head. However the motor should be
selected as per tender specification and scope of work defined. The possibilities of change of duty
point of each pump in parallel operation cannot be ruled out under such condition tenderer should
select the pump carefully. Penalty for delay in supply and installation-0.25% per day of the total
tendered cost subject to a maximum of 10%. 2. SWITCH GEAR MATERIAL:
Complete switch gear with all equipment, accessories shall be supplied and erected by the
contractor with the provision for connecting to the 415 +6%, 10%-v, 3 phase 50 Hz A.C. supply
system at tubewell pump house. Under the item construction features as follow: Rating of the
switch gear shall be as per Data sheet. 2.1 CONSTRUCTIONAL FEATURES 2.1.1 The control panel shall be completely metal enclosed and shall be dust, moisture and vermin
proof. The enclosures shall provide a degree of protection not less than IP-54 in accordance with
IS:2147.
2.1.2 Panels shall be wall mounting type and shall comprise rigid welded selected, smooth finished, hot
rolled sheet steel of thickness not less than 3 mm for front and rear portions and 2.5 mm for sides top
and bottom portions. There shall be sufficient reinforcement to ensure a plain surface to limit
vibration and to provide rigidity during installation and when panel put in service. 2.1.3 The control panel shall be assembled on channel/angle base plates with anti-vibration mountings. The
vertical panel shall be wall mounting type with removable covers at front. All bolts, nuts, and screw
etc., appearing on panel shall be so arranged as to present a neat appearance. Lifting hooks shall be
provided such that no openings are left when hooks are removed. All hooks, bolts and nuts exposed
to external atmosphere shall be chromium plated or zinc plated. 2.1.4 Operating handles of the doors shall have locking arrangement. There shall be no sharp door
covers to avoid injury to personnel. 2.1.5 The switch gear panel shall be provided with hinged door on the front and removable access
cover on the front. The door of the panels shall be gasketed all around with neoprene gaskets.
Ventilating covers if provided shall have screens, fittings and due collecting devices. The
screens shall be made or either brass or G.I. wire mesh if required. 2.1.6 Design, material selection and workmanship shall be such as to result in neat appearance inside
and outside with no welds and reverts apparent from outside, will all exterior surfaces free and
smooth. 2.1.7 Switch Gear Panel shall be suitable for wall mounting control cubicles as specified in data sheets
in the form of metal channels property drilled shall be furnished alongwith anchor bolts and
necessary hardware for mounting the panels. These shall be dispatched in advance so that they
may be installed and leveled.
2.1.8 Switch gear panel shall be liberally sized so as to provide spacious layout of equipment and
devices with sufficient working space in between.
2.1.9 The maximum and minimum height of the operating equipment on the panel shall be 2100mm and
900mm respectively from the floor level. If the panel height is small then it should be mounted on
separate support so that the operating height of the equipment comes within the above limit. The
proper supporting arrangement shall be provided by the tenderer. The following features are also required:-
(i) MCCB, bus bar, instrumentation and protection equipment and cables shall be inbuilt within
cubical panel.
(ii) The panels shall be so constructed that failure of one equipment does not effect that adjacent units.
Suitable vent shall be provided to release gas pressure developed due to short circuits or any burn. (iii) Bus bar connections, joints and taps shall be silver plated; connections shall be as short as
possible.
(iv) Each cubical shall be provided with HRC fuse and plug sockets. (v) Wiring for instrumentation, protection relay and lead indicating lamps in each switch gear panel
shall be grasped and brought out to easily accessible terminals for external connections. Note: Switch gear control panel shall be provided built within Automatic star delta starter as a single unit.
2.2 SOFT STARTER APPLICABLE AS PER ACTUAL REQUIREMENT:
The soft- starter shall be developed and qualified in accordance with international standards,
particularly with the standard dedicated to soft-starter EN / IEC 60947-4-2. The starter must be
CE marked under the harmonized standard EN / IEC 60947-4-2.
Description
The operating principle of the Soft-starter should not simply take ground on a limitation of motor current
during the transitional phases or on a voltage ramp but on a torque control motor. The
Soft-starter should provide a torque ramp during the acceleration phase. Thus, it can control the torque
during the starting period and if necessary provide a motor torque constant throughout the acceleration
phase. For pumping applications, the deceleration will be on torque a ramp.
All Soft-starter sizes will have the same control board. That control board must be identical
for all applications.
All Soft-starters shall be equipped with means for measuring motor current to ensure protection.
The measurements of the current will be active when the Soft-starter is by-passed (embedded
by-pass for all sizes).
The Soft-starter should have a separate power control.
The terminals of the board control shall be of plug type for easy maintenance.
Soft Starter should control 3-phase output with Programmable display.
The Soft-starter will handle the by-pass itself: manage the closure of the by-pass at end of
acceleration time and open that by-pass at end of stop sequence. That function must be
compatible with the types of stop: freewheel, ramp
The access to the settings can be locked by code. The monitoring parameters should
remain accessible.
Environment
The maximum relative humidity will be 95% without condensation or dripping water according
to standards IEC60947-4-2.
The storage temperature can be between -25 ° C to + 70 °
Electrical characteristics of the Soft-starter
The Soft-starter will automatically adapt itself to the frequency of the mains 50 or 60 Hz
with a tolerance of + / -10%.
Outputs: the Soft-starter must have at least 2 relays with a NO/NC contact Maximum switching
capacity on inductive load: 2 A at 250 Vac and 30 Vdc.
Protections
· The starter will include the management of Motor PTC probe. · The starter will calculate continuously the motor overheating from the real current value
(the current must be measured and not estimated). Several classes of thermal protection
will be proposed following the standard EN/IEC60947-4-2: Classes 10, 20, 30.The
calculation of the thermal protection must be active even when the Soft-starter is not power
energized.
· The starter shall be protected against thermal overload, over & under voltage.
· Dry run protection for pump motor.
· Protection against reverse-phase network, the loss of phases on mains or on motor.
· The protections will always be maintained even the Soft-starter is by-passed internal or self.
Communication
· The starter will include a multipoint serial link to be connected directly to a Modbus network.
The starter shall be able to be connected to Ethernet and other networks and communication bus
option.
· The communication shall provide access to the control, adjustment and monitoring of the
Soft-starter.
Display
· The starter shall have a display and programming push buttons. · The following information must be accessible on the display
- Motor current (by phase) - Motor state - Current status (acceleration, deceleration, Running). - Operating time. - The last fault occurred - Fault history - I/O status
2.2.1 THERMAL OVERLOAD RELAYS 01 No. APPLICABLE FOR STARTER, UNLESS
OTHERWISE SPECIFIED BY ENGINEER IN CHARGE:
Thermal overload relays 03 pole type shall be hand reset. The hand reset device and ‘STOP’ push
button of starter shall be separate from each other. Starter shall be complete with three element
positive acting, ambient temperature compensated, time lagged thermal overload relay with
adjustable setting. Overload reset push button shall be brought out on front of door cover. Overload
relays shall be provided with 02 NO / and NC auxiliary contact. 2.2.2 CT OPERATED RESIN CAST MAGNETIC OVERLOAD RELAY 01 No. APPLICABLE
or DIGITAL OVER CURRENT RELAY:
CT operated resin cast thermal over current relay or Electro Magnetic overload relays with CTs 03
pole type shall be hand reset. It can be managed with the combination of thermal time lagged relays
with CT operated magnetic overload relays. Adjustment of both time setting & current setting shall
be provided with easily accessible. Over current relays with CTs shall be procured with switch gear
panel in built Star delta starter separately or cumulatively. Over current relay shall be mounted
within switch gear panel. Over current range shall be suitable to HP of the motor at full load and over
load as per Data sheet.
2.2.3 SINGLE PHASING PREVENTER:
Single phasing preventer relay shall be provided with current operated type. The relay shall not operate
for supply unbalance; of 5%, but shall positively operate for unbalance more than 5%. The relay shall
operate in the event of single phase fuse blowing even though motor emf in the concerned phase is order
of the 85%. After sensing a single phasing, the delay shall operate with a time delay of 02 or 03 seconds.
The relay shall not operate for 03 phase power supply failure. The
relay shall be hand reset of push button. Resetting shall be instantaneous and independent of the
adjusted time delay in the tripping of the unit. Visual indication for the relay shall be provided
such as for 03 Nos. Pots at input for power supply, 02 Nos pots for auxiliary supply and 03 Nos
pots for common, NO and NC
The relay shall be suitable for application to protect reversible and non reversible motors. The relay
operation shall be independent of HP rating and RPM of the motor. The relay shall be of fail-safe type
and shall operate to trip the motor when the relay internal wiring is accidently open circuit. Reference
voltage for the supply shall be available even when supply has lost one phase.
2.2.4` ELECTRO MAGNET TYPE CONTACTS:
The motor starter contactor shall be of the electromagnet type, rated for uninterrupted duty as defined
in IS 2959, class applicable is I or II unless otherwise specified by the Engineer in charge, class I is
up to 30 operations per hour and class II is up to 150 operations per hours. It shall be decided by the
Engineer in charge as per site conditions after the award of contract.
Contactors shall be of double break, non gravity type. Each contact shall be provided with 02 NO, 02 NC
auxiliary contact. Insulation class of opening coil shall be E or better. Uninterrupted duty draws the
inference that duty in which main contacts remain closed without interruption while carrying a steady
current for a period of more than 08 hrs. This type of duty is taken care by a de-rating factor as the
accumulation of dirt and oxides have adverse affect on the performance of the contactor. It is closed by an
electromagnet. It opens under the action of gravity or spring when the
coil is de-energized. The principal component of magnetic contactor are as below: (a) Magnetic frame. (b) Magnetic or holding coil. (c) Moving armature which is attracted by the electromagnet frame and moving armature are of
laminated steel in the AC contactor for preferred rating 415V±6% for the main circuit. (d) Stationary contacts. (e) Moving contacts and spring mounted on the armature frame. (f) Are chute or arc snuffers for extinguishing the arc. (g) Flexible shunts for electrical connection to the moving contacts. (h) Auxiliary or inter locking contacts.
There shall be the circuits associated with electromagnet. The main circuit and the control
circuit. The contacts shall be copper alloy silver coated to the main contacts in addition to the
main contacts. There are auxiliary & arcing contacts close Ist, then the auxiliary contacts and last
of all the main contacts while opening. The order of operation is reverse, arcing contacts
prevents the concentration of arc on small area and results in increased life for the main contacts
and arc boxes. The arcing contacts are replaced with when they are too worn to make contact
ahead of main contacts.
2.2.5 CAPACITORS:
Motor shall be provided with separate capacitors to correct the power factor of the machines to 0.9
lagging or close to upf. The capacitor shall be of scaled unit pattern comprising paper, foil or plastic,
impregnated with oil or synthetic electrolyte. Capacitors shall comprising assemble of units mounted
on frame with suitable trucking, screening, interconnections or shall be housed in ventilated sheet
steel, enclosures. If either cases capacitors shall be complete with all necessary interconnections,
discharge devices, protective fuses and terminals for the connections of a 3 core supply cable. A
removable un-drilled cable gland shall be provided. Its rating shall be in the range of 1/3 to 1/4 KVAr
of HP of the motor unless otherwise specified by the Engineer in charge to improve power factor 0.9
lagging.
2.3 SUBMERSIBLE CABLE FOR PUMPING PLANTS:
Conforming to IS 694:1990 Tested at 1100 V, PVC flat submersible cable for pumping plant shall be
in three core working as power cable suitable for voltage and current rating of the motor at inrush
current of the motor starting. The size of conductor close section of the cable shall be in copper only
sufficient enough to withstand rigors of motor starting or short circuit fault taking in to account the
type of starters used for starting the motor. The cable shall be laid down from control panel/ starter to
the pump sets and therefore, length of cable should be sufficient considering the loops of suitable
length at certain points in the route of cabling. Cable joint with motor shall be done with IP-68 water
sheath in order to make water type joint as prescribe in IER. The cable must be checked for
continuity of the jointing and no. of copper stands and its gauge must be conforming to IS or
manufacturer’s code of practice failing which, cable shall be rejected. Note: The entire length of the
cable must be adequately enough to connect pump set and panel, starter etc. and margin in loop shall
be given to recover the need of future. It will have to be extended by the contractor in the event of
length of cable fall short in course of SICT. Size of the submersible cable 1x3x…..sq. mm around 35
mtr. long. 2.3.1 CABLE ENTRY:
The panels shall have provisions of cable entry from bottom. The removable cable gland
plate shall be provided to make entry dust tight and vermin proof.
The panels shall have provisions inside for fixing the multicore cable glands. The cable
glands support plate shall be 4 mm thick.
Cable entries to the panel shall be from the bottom unless otherwise specified. When called
for, necessary number of cable glands of sizes to suit purchaser's internal cables to the
panels shall be supplied. Cable glands shall be screwed type and made of brass. 2.4 MOUNTING: 2.4.1 All equipment in front of panel shall be of flush mounting type. 2.4.2 All equipment shall be so mounted that the removal and replacement may be accomplished
individually without interruption of services to others.
2.4.3 All equipment inside the panel shall be so located that their terminals and adjustments are readily
accessible for inspection or maintenance. 2.4.4 No equipment shall be mounted on the doors without prior approval Engineer in charge. 2.4.5 Wherever applicable Auxiliary bus bars for AC and P.T. circuits and other common service shall
be provided near the top of the panels running through the entire length of the panels, shall be
suitably insulated and along their run. 2.4.6 Fuses and links shall be provided for isolation of individual circuit from bus wires/bars without
disturbing other circuits. 2.4.7 Wherever practicable, wiring shall be accommodated on the sides of the panel. Sharp bends shall
be avoided. 2.4.8 Wiring shall be neatly bunched in groups by non-metallic cleats or bands. Each shall adequately
supported along its run to prevent sagging and strain on the termination. 2.4.9 Wire termination shall be made with solder less compression type of tinned copper lugs which
grip the conductor and insulation. Insulated sleeves shall be provided at all the wire
terminations. Wire shall not be spliced between terminal points. 2.4.10 Tenderer shall be solely responsible for the completeness and correctness of the internal wiring
and for the proper functioning of the connection equipment. 2.5 WIRING:
Panel shall be supplied completely wired indicating to equipment devices and terminal blocks and
relays for external cable connections at the terminal blocks all the internal wiring shall be furnished
by contacts / MCB/ MCCB. Panel wiring shall be securely supported neatly arranged readily
accessible and connected to equipment’s terminals and terminal blocks. Spare contact of auxiliary
relays and switches shall be wired upto the terminal blocks and wiring shall be carried out with 650
volts grade PVC. Insulated single core, standard copper conductor shall be 1.5mm for potential
circuit and 2.5mm for current and control circuit. The minimum number of strands per conductor
shall be three, flexible wires shall be used for wiring devices mounted on moving parts as swing
panel door. Auxiliary bus bars fo AC supply shall be provided inside the panel near the top of the
panel running through the entire width of panel to accommodate 03 Nos rings CTs for
instrumentation/ protection- fuses and links shall be provided for isolation of individual circuit from
bus bars without disturbing other circuits. Wherever practicable wiring shall be accommodated on
the sides of panel. Wiring shall be neatly bunched in groups by not Metallic cleats or bands, each
shall be adequately supported along its running to prevent sagging and strain on the termination.
Wiring termination shall be made with solderless compression type of tind copper lugs which grips the
conductor and insulation. Insulation sleeve shall be provided at all the wire terminations. Wire shall not
be spliced between terminal points. Each wire shall be identified by both ends by plastic ferrules with
wire designation in accordance with wiring diagram fitted inside the panel.
2.6 Instruments: 2.6.1 Indicating Instruments (a) All electrical indicating instruments shall be circular 270° scale, 96 mm square electro- magnate coil
instruments suitable for semi-flush mounting with only flange projecting on vertical panels.
(b) Instrument dials shall be white with black numerals and lettering knife edge painters and
parallex feedials shall be preferred. (c) Instrument shall conform to IS:1248 and shall have an accuracy class of 2.0 or better. (d) The number of digits provided shall be adequate to cover 1000 hours of operation. (e) Current coils of meters shall have a continuous over load capacity of 200% for both accuracy as
well as thermal limits. Also the coil shall withstand at least 10 times rated current for 0.5
seconds without loss of accuracy. 2.7 RELAYS : 2.7.1 All relays shall conform to IS:3231 or equivalent. They shall be suitable for semi-flush mounting
with only flanges projecting on the front with connections from the rear. 2.7.2 Relays shall be rectangular in shape and shall have dust tight, transparent covers removable from
the front. 2.7.3 All protective relays shall be in drawout cases with built in test facilities. Test block and
switches shall be located just below each relay for testing unless otherwise specified. All
auxiliary relay and timers shall be supplied in non-draw-out cases. 2.7.4 All relays shall be suitable for operation at 50 Hz, 415V A.C. voltage operated relays and current operated
relays shall be suitable for operation. A.C. auxiliary relays and timers shall be designed for the A.C.
voltage and shall operate satisfactorily between 70% and 110% of rated voltage. Voltage operated relays
shall have adequate thermal capacity for continuous operation. 2.7.5 All protective relays shall be provided with atleast two pair of potential free output contacts.
Relays case shall have adequate number of terminals for making potential free connections, to
the relay coils and spare contacts. Paralleling of contacts if any shall be done at the terminals on
the casing of the relay. 2.7.6 All protective relays shall be provided with externally hand reset positive action operation
indicator. 2.7.7 Timers shall be electromagnetic or thermal of latest improved type only. Short time delays in
millisecond may be obtained by shading with copper lugs on auxiliary relays. This shall not
affect the continuous rating of the relays. 2.7.8 All relays shall be self next type unless otherwise specified. 2.7.9 Each relay shall have provision for easy isolation of trip circuit for the purpose of testing and
maintenance. 2.7.10 All relays shall with stand a test as per relevant I.S.IO. code and standard. 2.7.11 Auxiliary seal in units provided on the protective relay shall be shunt reinforcement type.
2.8 CONTROL SWITCHES:
Control and instrument switches shall be rotary type suitable for semi flush mounting with
access to connection from the back by the removal of the cover. It should not be possible to
close the switch gear / MCCB with the door of it is when open and it should be possible to open
the door of it only when the switch is in the off position. Mechanical position indicator on/off
shall be provided.
MCCB shall be provided with facility for locking the panel with visible indication to show that
panel is in operation.
Neutral link shall be disconnected type. All connection shall be preferably be done with spring
washers and accessible for inspection. 2.9 MOULDED CASE CIRCUIT BREAKER –MCCB
MCCB should automatically isolate the electrical circuit under sustained overloads or short
circuits. The constructional features shall be as per details given below: Operating mechanism shall be quick make, quick break and trip free, independent of manual
operation contacts. Housing shall be made of resistance insulating material having all parts of it
enclosed in moulded housing. Terminal should be accessible for external connections. Magnetic thermal release should have three bimetals given thermal overload protection and
electromagnetic for short circuit protection. All releases should operate on common trip bar so
that all the phases gate disconnected even when faults occur on only one of them. Silver alloy
contacts should have long electric life. The mechanism should be so designed that they should be
no arcing on the current carrying part of the contact system. There should be strong wipe action
of the contact system for keeping the contacts surface clear of site films. It terminal should have
large sufficient dimension to accept links or cable lugs. Adjacent phase terminals should be
separate by insulating various with adequate clearances. Terminal configuration should permit
straight through cabling.
2.9 BUS BARS:
03 Nos. Bus bars of adequate preferably 1.0 amp. for aluminum and 1.6 for copper Per squire mm at
inrush current of motor starting shall be located in air insulated encloser. Direct or accidental contact
should not be possible with bus bars and primary connections. Bus bars shall be silver / tinned faced.
Spring washer shall be provided to ensure good contacts. In case aluminum connection are required,
suitable bimetallic connections or all bus bars joints shall be silver faced. Bus bar shall be adequately
supported on cast resin insulators to withstand dynamic stresses due to short circuit. The bus bars
support insulator shall conform to IS 2544. Bus bar shall be insulated with external PVC sleeves or
other insulating material. The PVC used shall be of high temperature grade, 50-0 and shall possess
good die electric properties- high tensile strength and good finish. The joints shall be covered with
insulating tap’s covering able to withstand temperature 85 degree size of bus bars shall be selected
making them suitable to withstand high large current for 30 second.
Note: Miniature circuit breaker (MCB) is denied in place of MCCB MCB is meant for lighting
purpose whereas isolator switch is forbidden.
3. MAIN PIPING AND VALVES:
Quantity of the main piping & valves are given below (for each T/W):
Sl. Particular Oty. Unit
No
1. MSDF Column pipe available in 03mtr. long 15 Nos.
2. MSDF Pipe 1.5mtr. long 2 Nos.
3. MSDF Pipe 1.0mtr. long 1 No.
4. CI DF bend (ISI mark) 1 No.
5. CI AF Tee (ISI mark) 1 No.
6. CI DF sluice valve (ISI Mark) 2 Nos.
7- CI DF Reflux valve (ISI Mark)) 1 No.
8. MS Fabricated DUMDUM 1 No.
9. Nut Bolts & Packing. 1 Set
10. SI column pipe clamp 2 Pairs
Note : size of the main piping & valves must be corresponding to the velocity range from
0.90m/s to 2.0m/s and valves shall be IVC / Kirloskar make.
3.1 M.S. COLUMN PIPE: 3.1.1 This shall be 100 MM dia 5.4 MM thick 3M long threaded and welded double flanged M.S.
column pipe. 3.1.2 The flange shall be made up of 12 MM thick M.S. flat respectively for 100 MM sizes.
3.1.3 The flange shall have OD as 165 MM respectively for 100 MM sizes with cable
grove. 3.1.4 The flange shall have 6 holes respectively suitable to 12MM bolt.
3.2 M.S. D/F PIPE:
3.2.1 This shall be 100 MM M.S. Double flanged (D.F.) Pipe having thickness 5.4 MM
respectively.
3.2.2 The flange size shall be standard having standard numbers of holes.
3.2.3 The length of D/F pipe shall be 1.5/1.0M.
3.2.4 The thickness of flange shall be 16 MM respectively for 150/100/80MM size.
3.3 D/F BEND:
This shall be 100MM Size 90 D/F ISI marked CI/DI bend.
3.4. A/F TEE:
This shall be 100 MM size A/F (all flanged) ISI marked CI/DI Tee.
3.5. SLUICE VALVE: This shall be 100MM size CI D/F Jal Nigam approved make ISI marked clockwise closing, non-
rising stem type, and sluice valve with hand wheel. Rating of the valve PN1.0
3.6. REFLUX VALVE: This shall be 100MM size CI D/F Jal Nigam Approved make ISI marked reflux valve. Rating of the
valve PN1.0 3.7. DUM DUM:
This shall be 350X200MM or 350X150MM or 300x150MM or 200x100MM & 200x80MM size
M.S. fabricated adjustable height, twist & lock Dumdum having 5.4 mm pipe thickness, 10mm
thick cover plate, 10mm thick 100mm wide ring, lower flange same as item No- 2 and upper
flange same as in item No-3, also having provision for pressure gauge, depth gauge, double
earthing & cable suitable to 300MM housing pipe. 3.9 NUT BOLT AND PACKING:
H.T. Rust resistant quality 12 MM size nut bolt for column pipe, Standard quality 5/8” size nut bolt
for other flanges and 5mm thick Standard quality suitable size rubber picking for fitting item No.
2 to 8. 3.10 COLUMN PIPE CLAMP:
This shall be 100 MM size S.I. column pipe clamp made up of 12mmx100mm flat having 4 holes
suitable to 5/8'' bolt and 600mm total length including suitable length bolt. 4. SERVO VOLTAGE STABILIZER FOR CONTINEOUS VOLTAGE SUPPLY AND
REGULATION AT VARIATION ±1% :
Copper wound operated at input 250–500V & output 400–440V servo stabilizer at each Tube
well shall be provided as per details attached sheet at each Tube well filled with transformer oil
conforming to relevant IS including PVC copper conductor cable in 3.0 core of suitable size
conforming to relevant IS 1554 Part-1 heavy duty voltage grade 230V to 1100V from stabilizer
to control panel/ starter as directed by Engineer in charge.
GENERAL SPECIFICATION
1. Mode of operation : Manually operated
2. Input supply voltage : 250 Volt-460 Volt
3. Output voltage : 415 Volt
4. Type : Unbalance type, suitable for submersible motor,
to be filled : Oil level die electric filled as per IS 335 16. The stabilizer should be guaranteed against manufacturing defect due to bad material faulty
design and workmanship for a period of one year from the date of commissioning. Any item or
part found defective during the shall be replace free of cost.
17. Rating of stabilizer shall be 2 KVA per H.P. of the induction motor at 80% reduced voltage Starting
in case of ATS induction motor & 1.5 KVA per H.P. of the induction motor in case of star delta
starting and 03 KVA per H.P. of the induction motor in case of DOL starting.
18. Main line at : 3 Steps Step up : 5.0 Parts
Step down 19. No of Volt meter of suitable
range No. of Toggle switch
No. of Rotary switch
5. PRESSURE AND DEPTH GAUGE:
: 2.0 Parts : 3 Nos.
: 3 Nos.
: 3 Nos.
The contractor shall provide a pressure gauge of 100 mm dia suitable to read the delivery head of water in
‘Meters head of water’ and one pneumatic type of depth gauge which should be capable to read the depth
of water in Meters directly. The make of gauges shall be Feibig or H-Guru.
5.2 AIR LINE:
The contractor shall provide GI/Fibre Airline of 6mm dia or PVC nylone 12mm is preferred
alternatively in required length to lower below the floor of pump house. The air line pipes should
be ERW type and confirming to ‘C’ class specification of IS:239 (part-I) i.e. having thickness of
2.65 mm duly threaded and sockets of heavy type.
5.2.1 ACCESSORIES AND SPECIALS:
I. Both the gauges are to be mounted on a common teakwood board with white sunmica top of suitable
size on wall at a height of 1.5 meters from the floor of pump house and to be connected
with air line.
II. The pressure gauge is to be supplied with control cock of brass.
III. The depth gauge is to be supplied with following accessories.
(a) 1 No. foot operated air pump of reputed make and strong flexible piping.
(b) Schrader valve, M.S. Tee, Coupler, elbows etc. of suitable sizes for fixing in the
air line.
NOTE :- The contractor has to supply all M.S. Clamps etc. to be grouted in the wall for fixing
airlines to the gauges in proper way and parallel to each other and other required fittings
for proper installation.
6. TOOLS:
This shall be a set of tools comprising of following items:
(i) D-spanner set (6-17 mm) 1 No. (v) Hand air pump 1 No.
(ii) Ring spanner 4/8" & 5/8" , 2 Nos. (vi) Insulated cut Plier 1 No.
This shall be 2 Tone capacity (tested at 3 tone) 4.5 mtr. lift INDEF/MORRIS make spur-gear chain
pulley block.
The chain pulley block shall be operated on the lower flange of the bridge girder and load chain shall be of
alloy steel as per IS 2429 part-II. It shall be heat treated to give the ductility and toughness it shall be
welded construction with a factor of safety not less than 5. The lifting hook shall be forged steel, he
treated alloy or carbon steel. It shall be of single hook type provide with standard depress
type safety latch. Hook shall be conforming to IS 3815. The brake for the lifting gear shall be
screw and friction disc type and shall offer no resistance during hoisting. Overload test at 150%
of raises load for chain pulley block and trolley, overload test of 125% of rated load and
defection test with 100% of rated load. Test certificate of the manufacturer has to be submitted
by the contractor.
8. POWER WIRING AND EARTHING
PVC insulated 3.5 core round aluminum power cable of required size, 1100 V grade confirming
to IS 1554 part I heavy duty voltage grade 230V to 1100V accessible to earthing shall be
supplied to connect UPPCL energy meter and 02 meter leads shall be left in spare for making
connections. The size of cable shall be adequate to bear the brunt of in rush current at 45 degree
ambient temperature. It shall also include 12mm thick sunmica top board size of board 3̍x 1.5
and 4 Nos porcelien cutout of required capacity duly grouted on the wall is of paramount
importance as per IER.
8.1 EARTHING:
Double plate earthingas of the entire electrical system shall be carried out and connected to
permanent earthing plates buried in ground and surrounded with coke salt upto adequate depth
where earth is encountered. It shall be consisting of the following: ii) GI Earth plates of 600 X 600 X 6 mm size as per latest relevant ISS/IER. iii) GI water pipes of required length and 40mm dia. As per latest relevant ISS/IER. iv) Aluminium Earth strip of adequate size as per relevant ISS/IER and in required quantities to cover
complete installation in double run. The strip shall be without kinks and without any joints.
v) Necessary quantities of lugs and clamps etc. for proper earthing. vi) Necessary quantities of salt and coal shall be supplied at the time of erection. vii) Earth chamber CI box 300 X 300 mm as per ISS/IER.
i) The digging of pits for earthing and construction of suitable size earth chambers shall be done
by the tenderer. ii) The whole of the above work of power wiring and earthing shall be carried out to the entire
satisfaction of Engineer Incharge and subject to the approval of UPPCL and also be accordance
with IER and other Govt. regulations prescribed/amended upto date. iii) The power wiring shall be done properly on MS clamps to be grouted on the wall. The
submersible cable/copper lead will run through MS conduits on wall and floor through entire
route.
8.1.2 TESTING OF EARTHING SYSTEM 8.1.3 Purchaser may ask to carry-out earth continuity tests earth resistance measurements and other
tests in presence of him which in his opinion are necessary to prove that the system is in
accordance with design and specifications. Contractor shall bear cost of all such tests.
8.1.4` EARTHING SYSTEM (APPLICABLE AS PER ACTUAL REQUIREMENT)
8.1.5 Sizes and number of earth leads for earthing various items and other technical particulars shall
be as specified.
8.1.6 Earthing conductors are shown diagrammatically. Exact location of earthing conductors, earth electrodes
and test pits, and earthing connections may be changed to suit the site conditions.
8.1.7 Earthing conductors in the building, running parallel to walls and columns shall not be less than
1500 mm away from the wall/column.
8.1.8 Suitable earth risers shall be provided if the equipment is not available while carrying out
earthing connection.
8.1.9 Wherever earthing conductor passes through walls, galvanized iron sleeves shall be provided
for the passage of earthing conductor. Water stop sleeves shall be provided, wherever earthing
conductor enters the building from outside.
8.1.10 Wherever the conductors are to be buried, contractor shall coordinate with other civil
contractors to ensure that the conductors are installed before concreting.
8.1.11 All connections shall be of low resistance. Contact resistance shall be minimum.
8.1.12 Steel conductors, above ground level shall be galvanized. All conductors shall be free from
any defect. Earthing conductors shall not run in direct contact with control and other cables.
Single core cable amounting shall be earthed at one end. The cable trays shall be earthed to main
grid at least at two points and every 25 mt interval.
9. PAINTING:
All sheet metal work shall be phosphated in accordance with the following procedure and in
accordance with I.S. Code of Practice for Phosphating Iron and Steel after application of the
primer, two coats of finishing synthetic enamel paint shall be applied, each coat followed by
stoking. The color of the finishing coat shall be as per purchaser approval. Finished painted
appearance of panels shall present an aesthetically pleasing appearance free from dents and un-
even surface. A small quantity of finishing paint shall be supplied for minor touching up
required at site after the installation of panels. Main piping & valves and what’s not, existing
within pump house are also covered.
10. ERECTION:
The contractor shall undertake complete installation of the pumping plant along with associated
works such as switch gear, power wiring & earthing, main piping and valves, pressure & depth
gauge with air line and other things of the same types whatsoever, are required for proper
completion of the installation, commission & testing in the presence of at least one approved
senior English or Hindi speaking working erector to supervise the erection of the plant in the
capacity of contractor representative. The contractor shall also provide sufficient Erectors skilled
and good at mechanical, electrical and instrumental Engineering, such skilled, semiskilled, and
unskilled laborer are necessary to ensure
completion of the various sections of the installation works well in time. The contractor shall not
remove any supervisory staff or laborer from site without prior approval of the Engineer’s
representatives. Installation work also make necessary petty civil works such as cutting of wall
and brick work/ concrete work dismantling and repairing with restoration works satisfaction of
the Engineer in charge including watch and ward of the pumping plant until the commissioning
and handing over proceedings are complete. Such works are to be completed without making the
claim of extra payment.
11. TESTING:
The contractor shall carry out the final tests on the pumping plant to ensure power consumption
is as per schedule “E” furnished and all requirements as mentioned in respective specification if
any. The contractor shall also carry out all other tests required either by himself and/or the
Engineer to complete the plant etc. to supply systems and delivery of all works. The contractor
shall maintain on the log book in English/Hindi of all test carried out and will handover certified
copy of the same to the Engineer at the time of completion of the works.
12. COMMISSIONING & TRIAL RUN :
After being intimated by the office, contractor will commission the pumping plant within 10 days
time and just after that trial run will be taken up and started. During the trial run, the contractor shall
depute his skilled staff ( 3 nos operator in three shift on each TW and each ZPS also one electrician
in general shift in each ZPS ) for trial run (As and when required and as per availability of Power
Supply) during this period except for Power, all consumables shall be provided by the contractor free
of cost including watch & ward of pumping plant. Data sheet for Electrical Items Part-I
(Recommended rating of Contactor, MCCB, Stabilizer & Cable)
Starter Type of the Capacity of Capacity of Rating of Submersible cable capacity starter the main switch stabilizer size
contactor (MCCB)
Type, AC-3,
Making cap
5 HP DOL 9 A 20A, 10 KA 10 KVA 1x3x2.5 sq.mm.
6 HP DOL 12 A 20A, 10 KA 10 KVA 1x3x2.5 sq.mm.
7.5 HP Star delta 12 A 25A, 10 KA 15 KVA 2x3x2.5 sq.mm.
10 HP Star delta 18 A 25A, 10 KA 15 KVA 2x3x2.5 sq.mm.
12.5 HP Star delta 22 A 32A, 15 KA 20 KVA 2x3x4 sq.mm.
15 HP Star delta 32 A 32A, 20 KA 25 KVA 2x3x4 sq.mm.
20 HP Star delta 40 A 100A, 25 KA 30 KVA 2x3x6 sq.mm.
25 HP Star delta 50 A 125A, 25 KA 40 KVA 2x3x6 sq.mm.
30 HP Star delta 70 A 150A, 35 KA 50 KVA 2x3x10 sq.mm.
33 HP Star delta 70 A 150A, 35 KA 60 KVA 2x3x10 sq.mm.
Note: Rating of star- main & delta electromechanical contactors type AC-3 shall be the same and identical.
Since range of contactors vary manufacturer / vendor to vendor, range of contactors has to be chosen the
same as cited above or the next higher commercial range of the above cited range in the event of the range
not matching with above cited range.
Data sheet for Electrical Items Part-II
(Recommended Rating of Electrical Starters and Cables Items)
Full load Relay Recommended cable size for
HP Rating of current, A (IL)) range, A connection, sq mm. Recommended HRC
the pump set
(Ip))
Fuse rating, A Al Cu
5 7.5 4-6.5 4 2.5 15
7.5 11 6-10 6 2.5 25
10 14 6-10 10 4 28
12.5 18 9-14 10 4 40
15 21 12-10 16 6 50
20 28 18-30 25 10 50
25 34 24-40 25 10 63
30 39 36-60 35 16 63
40 55 36-60 50 25 80
50 66 48-80 70 35 100
60 80 60-100 70 35 125
75 95 60-100 95 70 160
100 135 90-150 95 120 200
125 165 120-200 120 185 250
150 200 120-200 120 185 250
HP Full load Electro Electro Electro CT ratio/ burden/
Rating of current, A Mechanical Mechanical Mechanical Accuracy class
the pump (IL)) contact contact contact
set (IL)) at DOL (IL)) at star delta (IL)) at ATS
starter starter starter
HP
1.5XHP
5XFIL
2X FIL 3X FIL 1.5 X FIL/5A,
6/10/15VA, CL1.0
Note:
1. Ampere ratings to main, delta and star/ taping contacts shall be the same as per ampere calculated for starters.
2. Thermal timer delay relay or digital timer delay relay shall be adjustable between 3-12/15 second
3.
for changeover to full voltage.
Starter must be suitable for 15 start stop per hours
Data sheet for Electrical Items Part-III
(Recommend Rating of 3 core flat cables conforming to IS 694:1990) Conductor Insulation Sheath Overall Dimension Conductor Current
resistance carrying Area No. Dia Thickness Thickness(Nom) Width Height
@ capacity
sq. of
(Nom)
mm
(Approx)'W'
(Approx)'H' 20c(max) @ 40C mm. strands mm mm mm
ohms/km. Amps mm
1.5 22/0.30 0.6 0.9 10.3 4.9 12.10 14
2.5 36/0.30 0.7 0.7 12.6 5.8 7.41 18
4.0 56/0.30 0.8 0.8 14.8 6.6 4.95 26
6 84/0.30 1 1.15 18.7 7.9 3.3 31
10 140/0.30 1 1.4 23.7 9.9 1.91 42
16 226/0.30 1 1.4 28 11.4 1.21 57
25 354/0.30 1.2 2 35.5 14.7 0.78 72
35 495/0.30 1.2 2 39.5 16.2 0.554 90
50 703/0.30 1.4 2.2 45.5 18.3 0.386 115
70 360/0.50 1.4 2.2 51 20 0.272 143
95 475/0.50 1.6 2.4 60 23.5 0.206 165
H.P. 5 7.5 10 12.5 15.5 17.5 20
Amp 7.5 11 14.9 18.9 22.5 25.2 28.4
H.P. 25 30 35 40 45 50 55
Amp 35.6 42.3 50.4 58.1 62.1 67.5 73.8
H.P. 60 65 70 75 80
Amp 81 87.3 93.6 100.8 108
SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR
SITC OF CWR PUMPING PLANT
This tender includes (A) Supply, Installation, Testing and Commissioning (SITC) and (B) Trial run of Vertical Turbine clear water pumping plants, substation, and other appurtenant work at
Zonal CWR. All electrical and mechanical works shall be under scope of this tender even it has been left
out in narratives of this works shall have to be completed in strict compliance of the relevant ISS/IER.
The capacities and general specifications of the equipments are given here as under.
1. VERTICAL TURBINE PUMP SET WITH 4.5 METER COLUMN ASSEMBLY:
Clear Water Vertical Turbine pumping set suitable for CWR fitted with dynamically balance bronze
impellers mounted on a stainless steel pump shaft with shaft protection sleeves having stage bowls of
closed grained cast iron. The pump will be fitted with built in non-return valve and shall be suitable
for direct coupling to the squirrel cage electric induction, water cooled type submersible motor
suitable to operate on 400 ± 10% V, 3 phase, 50 cycles/sec. A.C. Power Supply and capable to give a
desire discharge and head as mentioned in schedule G.
PARALLEL OPERATION OF PUMPS
The tenderer shall have to study and to submit the parallel operation curve of the pumps to be
operated in parallel. The system resistance curve should be drawn and should be superimposed with the
parallel operation curve to ensure the proper running of the pumps in parallel
At ZPS out of 3 pumps, 1 pump will be stand by and 2 pumps shall run in parallel for
which curve is to be drawn.
The head calculation data are to be provided by the tenderer to draw the system resistance
curve and parallel operation curves. The possibilities of change of duty point of each pump in
parallel operation cannot be ruled out, under such conditions tenderer shall have to submit their offer
with design and its analysis and curves justifying the change of duty.
(A) Design Requirements
a) The pumps shall be capable of developing the required total head at rated capacity. The pumps
should almost operate satisfactory at any point on the HQ characteristics curve over a range of
75% to 110% capacity.
b) The power rating of the pumps motor shall be larger of the following:- i) The maximum power required by the pump from zero discharge to full value of discharge. ii) 115% of the power required at the duty point if power consumed at duty point by pump comes
out to be up to 75 HP. If it is more than 75 HP than it will be 110% of the power consumed at
duty point.
(B) PUMP SET: 1.3.1 A Standard hydrostatic test on all pressure containing parts shall be made at 1.5 times the
maximum discharge pressure.
1.3.2 The bowls shall be equipped with replaceable casing bearing.
1.3.3 The bowl assembly shall bear a name plate preferably embossed information as per following:
a) Name of the manufacturer or trade mark. b) Serial number of the pump set. c) Pump type. d) Number of stages.
e) Total head.
f) Shut off head. g) Capacity.
Note: Shut off head must be above 25% of the total head required. 1.3.4 The impeller shall be of enclosed type equipped with seal rings on their hubs. Seal rings shall be
provided either with impeller or in the bowl.
1.3.5 The pump shaft shall be guided by bearing provided in each bowl of above and below the impeller shaft
assembly. The shaft without sleeves shall have a surface finish 0.75 micron Ra Max. 1.3.6 The opening in the suction case for the entrance of water shall be of proper size and shape to
avoid eddy currents.
1.3.7 The suction case shall be fitted with a strainer made of corrosion resistant material. 1.3.8 Suitable sand guard shall be provided just above the suction case bearing to prevent the entry of
foreign matter into the suction case.
1.3.9 Non return valve shall be provided above the pump discharge case. Note: The Pump should not be more than two stage
C. SUBMERSIBLE MOTOR:
9. The submersible motor shall be squirrel cage induction motor. 10. The winding of motor shall be wet type. 11. The motor shall be suitable for operation voltages and frequency confirming to IS 585-1962
(revised) “Voltages and frequency for A.C. transmission and distribution system” 12. The earthing of the motor shall comply with IS: 3043-1966 code of practice for earthing. 13. The Thrust bearing shall be of adequate size to withstand the weight of all rotating parts as well
as the imposed hydraulic thrust. These shall be lubricated suitably. 14. The Motor winding and nearing bushes of the rotor shaft shall be cooled/lubricated by pure
water filled in the motor before erecting the pump set. 15. The motor shall be protected by means of cable glands, rubber seals etc. from ingress of
tubewell water, sand and other foreign matter. 16. The thrust bearing housing shall be provided with a drain plug to empty the pure water filled into
the thrust bearing housing/Motor. 17. The rotor shaft shall be provided with shaft protecting sleeves having a surface finish of 0.75
micron Ra max. 18. The Motor shall be provided with a breathing attachment like bellows, diaphragm etc. to
compensate the Volumetric variations due to change in temperature. 19. The motor shall be made of corrosion resistant materials or suitably treated materials to resist
corrosion. 20. The motor shall have a name plate preferably embossed on body of motor giving the following
information :
a) Induction Motor; b) Name of Manufacturer;
c) Manufacturer’s number and frame reference; d) Type of duty; e) Frequency in Hz; f) Number of Phases; g) Rated output in HP/KW; h) Rated voltage and winding connections; i) Current in amperes at rated output.
j) Speed in RPM at rated output. (a) DATA OF PUMP SET:
These shall be furnished in the following manner’s
a) Model of motor. b) Model of pump. c) Discharge in LPM.
d) Total head.
e) Nett effective head. f) Number of stages.
g) Pump outlet size in mm. h) O.D. of pump in mm.
h) MOC of each and every component of the pump set. i) Speed of pump set.
j) Method of starting. The performance details as per enclosed schedule ‘E’ are to be submitted as per enclosed sheet separately.
E. M.S. COLUMN PIPE
(i) M.S. Column pipe shall be 7.1mm thick 1.5 meter long threaded and welded double flanged
(ii) The flange shall be made up of 16mm thick M.S. flat respectively.
F. SHOP TESTING
The following shop tests shall be witnessed by Engineer incharge of the project.
Standard Running test as per relevant IS at rated speed in Manufacturer’s works to measure capacity,
total head, efficiency and power. These tests will form the basis for acceptance of pumping plant.
The pumping plant shall be tested over the range covering from shut off head to the maximum flow.
The duration of the test shall be minimum one hour. Minimum five readings approximately
equidistant shall be taken for plotting the performance curves.
2.0 SOFT STARTER The soft- starter shall be developed and qualified in accordance with international standards,
particularly with the standard dedicated to soft-starter EN / IEC 60947-4-2. The starter must be
CE marked under the harmonized standard EN / IEC 60947-4-2.
Description
The operating principle of the Soft-starter should not simply take ground on a limitation of motor
current during the transitional phases or on a voltage ramp but on a torque control motor. The Soft-
starter should provide a torque ramp during the acceleration phase. Thus, it can control the torque
during the starting period and if necessary provide a motor torque constant throughout the
acceleration phase. For pumping applications, the deceleration will be on torque a ramp.
All Soft-starter sizes will have the same control board. That control board must be identical
for all applications.
All Soft-starters shall be equipped with means for measuring motor current to ensure protection.
The measurements of the current will be active when the Soft-starter is by-passed (embedded
by-pass for all sizes).
The Soft-starter should have a separate power control.
The terminals of the board control shall be of plug type for easy maintenance.
Soft Starter should control 3-phase output with Programmable display.
The Soft-starter will handle the by-pass itself: manage the closure of the by-pass at end of
acceleration time and open that by-pass at end of stop sequence. That function must be
compatible with the types of stop: freewheel, ramp
The access to the settings can be locked by code. The monitoring parameters should
remain accessible.
Environment
The maximum relative humidity will be 95% without condensation or dripping water according
to standards IEC60947-4-2.
The storage temperature can be between -25 ° C to + 70 °
Electrical characteristics of the Soft-starter
The Soft-starter will automatically adapt itself to the frequency of the mains 50 or 60 Hz with
a tolerance of + / -10%.
Outputs: the Soft-starter must have at least 2 relays with a NO/NC contact Maximum switching
capacity on inductive load: 2 A at 250 Vac and 30 Vdc.
Protections
· The starter will include the management of Motor PTC probe. · The starter will calculate continuously the motor overheating from the real current value (the
current must be measured and not estimated). Several classes of thermal protection will be
proposed following the standard EN/IEC60947-4-2: Classes 10, 20, 30.The calculation of the
thermal protection must be active even when the Soft-starter is not power energized.
· The starter shall be protected against thermal overload, over & under voltage. · Dry run protection for pump motor. · Protection against reverse-phase network, the loss of phases on mains or on motor. · The protections will always be maintained even the Soft-starter is by-passed internal or self.
Display
· The starter shall have a display and programming push buttons. · The following information must be accessible on the display - Motor current (by phase) - Motor state - Current status (acceleration, deceleration, Running). - Operating time. - The last fault occurred - Fault history - I/O status
Contacts A. The motor starter contractors shall be of the electromagnetic type of uninterrupted duty as
defined in IS 2959 unless otherwise specified.
B. Contact shall be of the double break non gravity type. C. Main contacts of contact shall be of silver plated copper. D. Each contact shall be provided with 2 No. auxiliary contacts. E. Insulation classes of operating coils shall be of class ’E’ or better.
Epoxy Resin Cast Thermal Overload Relays (of suitable range & capacity) (a) Thermal overload relays shall be hand reset. This hand reset, device and ‘STOP’ push button of
starter shall be separate from each other.
(b) The starter shall be complete with three elements positive acting ambient temperature
compensated time lagged thermal overload relay with adjustable settings.
(c) Overload rest push button shall be brought out on the front of the compartment door. (d) Overload relay shall be provided with 1NO. AND INC
contact. Thermal Time Delay Relay
(a) It shall be hand reset to fix time for low voltage starting and full load
starting. Single Phasing preventers
(a) Single phasing preventers relay shall be provided.
(b) The single phasing preventor shall be of the current operated type. The relay shall not operate
for supply voltage unbalance of 5% but shall positively operate for unbalance more than 5%.
The relay shall operate in the event of single-phase fuse blowing. (c) After sensing a single phasing, the relay shall operate with a time delay of 2X3 seconds. The relay
shall not operate for a 3-phase power supply failure. The relay shall be of the hand-reset push
button. Resetting shall be instantaneous and independent of the adjusted time delay in the tripping of
the unit. Visual indication for the operation of the relay shall be provided. (d) The relay shall be suitable for application to protect reversible and non-reversible motors. The
relay operation shall be independent of H.P. rating and the R.P.M. of the motor. The relay shall
be of failsafe type and shall operate to trip the motor when the relay internal wiring is
accidentally open circuited. 3. LT CONTROL PANEL:
The control panel shall be compartmentalized cubical type, dust and vermin proof 2.4mm
thickness steel sheet fabricated, floor mounting type having aluminum bus bars. All operative control
should be above waist height (Around 4’) and metering around eye level AND IT SHOULD BE
COMPATIBLE FROM AUTOMATION POINT OF VIEW IN FUTURE
The control panel should consist of one incomer and 3 outgoing feeders for each pump
starter, also separate feeder for light & fan and other miscellaneous works in spare having
separate power terminals and control terminals along with APFC panel as follows:-
a) Incoming feeder:-
The incoming feeder should generally comprise of the following: - i) 1 No. required capacity MCCB with overloaded and earth fault protection and all other
protections provided by the manufacturer.
ii) 96 mm. sq. dial CT operated voltmeter with a range from 0-500 V with voltage selector switch-1 No.
iii) 96 mm. sq. dial CT operated ampere meter of suitable capacity with ampere selector switch-1 No. iv) 96 mm. sq. dial CT operated Power factor meter – 1 No. v) 96 mm. sq. dial CT operated frequency meter – 1 No.
vi) Indicating lamps, toggle switches and instrument fuses – 1 No. vii) KW meter of suitable capacity CT operated – 1 No.
viii) Switch fuse unit of suitable capacity - 1 No.
ix) Control MCB -1 No.
c) Outgoing feeders:- (A) Outgoing feeders five nos. each comprising of the following:-
i) Required capacity, MCCB, manually draw out in built overloaded and earth fault protection and
all other protections provided by the manufacturer – 1 No.
ii) 96 mm. sq. dial CT operated ampere meter with selector switch – 1 No. iii)
iv) Power contactor with 2 NO/NC – 1 No.
Single phase preventor – 1 No.
v) OV/UV Relay – 1 No.
(B) Spare feeders 3 Nos. each comprising of the following: - i) MCB of suitable capacity – 1 No. ii) 96 mm. sq. dial CT operated ampere meter with selector switch – 1 No.
(Note: The tenderer has to quote the capacity of MCCB's of rating 50KA and its make and CT’s
should be resin cast type & dual core, also auxiliary contactors to be provided for automation in
future)
All or part of control panel, metering, protection and other necessary equipment specified
in the following clauses of the specification shall be provided as and when called for in the
accompanied specification.
Codes and Standards:
The design, manufacture and performance of equipment shall comply with all currently
applicable regulation and safety codes in the locality where the equipment will be installed.
Unless otherwise specified, equipment shall conform to the latest applicable Indian,
British or USA standards.
Some of the standards are given below:-
a) IS 375 Auxiliary wiring and bus bar marking
b) IS 722 Energy meter
c) IS 1248 Indicating instrument
d) IS 2147 Degree of protection provided by enclosure
e) IS 2208 HRC fuses
f) IS 2705 Auxiliary current transformer
g) IS 3156 Auxiliary Voltage transformer
h) IS 3231 Electrical relays for power system protection
i) IS 4047 Air break switches
j) IS 2516 AC Circuit Breaker
k) IS 5124 AC induction motor starter
l) IS 3427 Metal indoor switch gear and control gear for voltage Above
100 V but not exceeding 11000 V
Extent of Work
The extent of the work included in the specification is as follow:
Design, fabrication of complete panels, provision for all associated equipment and wiring,
design and selection of all the components shall be made liberally with a good margin of safety
factor and considering the following points in mind.
Procurement (except specifically noted as supplied by purchaser) and mounting of all
equipment specified in the accompanied equipment list, data sheet, drawings and specification
together with such auxiliary equipment and materials as may be adjacent or complementary to
those specified.
All internal wiring to equipment and terminal block and wiring between adjacent panels.
Electrical and instrumentation detailing outlined in this specification and the accompanied
specification.
Preparation and furnishing of all drawings as required including schematic wiring, internal
wiring and external cable connection drawings.
Testing of panels and associated equipment accessories and furnishing of test
certificates. Preparation and furnishing of instruction, operating and maintenance
manuals.
Constructional Feature
The control panel shall be completely metal enclosed and shall be dust, moisture and
vermin proof. the enclosure shall provide a degree of protection and specified in data sheets but
not less than IP 54 in accordance with IS: 2147
Panels/desks shall be free standing, floor mounting type and shall comprise rigid welded
structural frames enclosed completely with specially selected, smooth finished, hot rolled sheets
steel of thickness not less than 3 mm for front and rear portions and 2.5 mm for sides top and
bottom portions. There shall be sufficient reinforcement to ensure a plain surface to limit
vibration and provide rigidity during shipment and installation.
The control panel/desk shall be assembled with channel/angle base plates
with anti-vibration mountings. The vertical panel shall be freestanding type with removable
covers at back. All bolts nuts and screw etc. appearing on panel shall be arranged as to present a
neat appearance, lifting hooks shall be provided such that no openings are left when hooks are
removed. All hooks, bolts and just exposed to external atmosphere shall be chromium plated or
zinc plated.
Operating handles of the doors shall have locking arrangement, There shall be no
sharp door covers to avoid injury to personnel.
The control desk shall be provided with hinged door on the rear and
removable access cover on the front. All doors, removable covers and panels shall be gasketed
all around with neoprene gaskets. Ventilating covers if provided shall have screens. Fittings and
due collecting devices shall be made of either brass of GI wire mesh.
Design, Material selection and workmanship shall be such as to result in neat appearance
inside and outside with no welds and reverts apparent from outside, with all exterior surfaces
free and smooth.
Panels desk shall be suitable for floor mounting. Metal stills in the form of metal channels properly
drilled shall be furnished along with anchor bolts and necessary hard ware for mounting the panels. These
shall be dispatched in advance so that they may be installed and leveled, when concrete foundations are
poured. The foundation and supporting frames, anti-vibration strips and fixing bolts, nuts, washers etc.
shall be supplied to suit the requirements.
The panels/desk shall be liberally sized so as to provide spacious layout of equipment
and devices with sufficient working space in between.
If a control panel consists of a number of panels, each panel shall be mounted side/by side
and bolted together to from a compact unit. Where two panels meet, the joints shall be smooth,
close fitting and unconstructive.
The maximum and minimum height of the operating equipment on the panel shall be 2100 mm and 900 mm respectively from the floor level, stands height of the equipment comes within the
above limit. The proper supporting arrangement shall be provided by the bidder.
The following features are also required: 9. The circuit breakers, bus bar, instrument transformer’s and cables shall be installed in separate
compartment within the cubical.
10. The panels shall be so designed that it may be possible to extend on either side if required at
future date.
11. The panels shall be so constructed that failure of one equipment does not effect the adjacent
units. Suitable vent shall be provided to release gas pressure developed due to the operation of
breaker or breaker or due to live are at the bus or short due to shot circuits. 12. All bus connections, joints and taps shall be silver plated, connections shall be as short as possible. 13. Each cubical shall be provided with space heater with switch fuse and plug socket with switch
for connection of heat lamps rated 240 V single phase 50 C/S. Space heater shall be provided
with thermostats of approved make and type. 14. Wiring for space heater and lamps in each switch gears shall be grasped and brought out to
easily accessible terminals for external connection.
All sheet metal work shall be phosphated in accordance with the following procedure and in
accordance with IS “code of practice for phosphating iron and steel” after application of the primer,
two coats of finishing synthetic enamel paint shall be applied, each coat followed by stoving. The
colour of the finishing coat shall be as specified in data sheet ‘A’.
Finished painted appearance of panels shall present an esthetically pleasing appearance
free from dents and uneven surface.
A small quantity of finishing paint shall be supplied for minor touching up required at
site after the installation of panels/desks. The type of anti-vibration strips shall be subject to
purchaser approval.
Cable Entry: 1. The panels shall have provisions of cable entry from bottom. The removable cable gland plate
shall be provided to make entry dust tight and vermin proof. 2. The panels shall have provisions inside for fixing the multi-core cable glands. The cable glands
support plate shall be 4 mm thick. 3 Cable entries to the panels/desks shall be from the bottom. When called for in data sheet.
Necessary number of cable glands of sizes to suit purchaser’s internal cables to the panels shall
be supplied. Cable glands shall be screwed type and made of brass.
Mounting:
All equipment in front of panel/desks shall be flush mounting type.
All equipment shall be so mounted that the removal and replacement may be accomplished
individually without interruption of service to others.
All equipment inside the panel/desk shall be so located that their terminals and adjustments
are rapidly accessible for inspection or maintenance.
No equipment shall be mounted on the doors without prior approval of purchaser.
Where applicable Auxiliary bus bars for AC and DC suppliers, Pt circuits and other common
service shall be provided near the top of the panels running through the entire length of he panels.
These buses shall have nominal cross section equivalent to a copper of 6mm2 and permit two
independent supply points.
Fuses and links shall be provided for isolation of individual circuit from bus wire/bars
without disturbing other circuits.
Wherever practicable wiring shall be accommodated on the sides of the panel/desk, sharp
bends shall be avoided.
Wiring shall be adequately supported along its run to prevent sagging and strain on the
termination.
Wire termination shall be made with solder less compression type of tinned copper lugs
which grip the conductor and insulation. Insulated sleeves shall be provided at all the wire
termination. Wire shall not be spliced between terminal points. Each wire shall be identified at
both ends by engrave, Core identification, plastic ferrules with wires designation in accordance
with contractor wiring diagram fitted inside the panel.
Vendor shall be solely responsible for the completeness and correctness of the internal
wiring and for the proper functioning of the connected equipment.
Terminal Block:
Multi- way terminal blocks complete with necessary binding screws and markers for wire
connections and terminal strips for terminal identifications shall be furnished for terminating the
wiring and outgoing cables.
Terminal blocks shall be 650 V grade, 15 amp, rated with marking on terminal strips shall
correspond to wire numbers on the wiring diagram.
Terminal block of CT and PT secondary leads shall be provided with test links and isolating
facilities. Also CT secondary leads shall be provided with test links and isolating facilities.
The terminal block shall be grouped according to circuit functions and shall have at least
20% spare terminate. For different voltage, the terminal blocks shall be segregated.
Bottom of the terminal blocks shall be least 2.00 mm above the cable crutch of incoming
multi core cables.
The terminals shall be open clamp/stud type suitable for connection of at least two (2) 2.5 mm copper wire, per terminal from each side. Terminals with tightening screws sitting directly
on the conductor shall be accepted.
No more than two wires shall be connected to any terminal. If necessary a number of
terminal shall be jumpered together to provide wiring point.
The center lines of switches, push buttons and indicating lamps shall be matched to give a
neat and uniform appearance. Likewise the top lines of all meters relays and recorders etc. shall
be matched.
Wherever required, panels/desks shall be matched with other panels/desks in control room in
respect of dimension, colour appearance and arrangement of equipment on the front.
Cable Terminations:
The purchasers external cable connection will be terminated on the terminal blocks
provided in the control panel. All necessary cable terminating, such as gland plaster, packing
glands, crimp type termed copper lugs and brackets, wiring troughs and gutters etc. for
purchaser’s cable shall be included in Vender’s scope of supply.
Electrical Instruments:
Indicating instrument
All electrical indicating instruments shall be circular 270 scale, 96mm. square moving coil
instruments suitable for semi-flush mounting with only flange projecting on vertical panels.
Instrument dials shall be white with black numerals and lettering, knife-edge pointers and
parallax free-dials shall be preferred.
Instrument shall conform to IS: 1248 and shall have an accuracy class of to 1.0 or better.
The number of digits provided shall be adequate to cover 1000 hours of operation.
Current coils of meters shall have a continuous over load capacity of 200% for both
accuracy as well as thermal limits. Also the coil shall withstand at least 10 times rated current
for 0.5 seconds without loss of accuracy.
Relays
All relay shall conform to IS 3231 or equivalent. They shall be suitable for semi-flush
mounting with only flanges projecting on the front with connection from the rear.
Relays shall be rectangular in shape and shall have dust tight, transparent from the rear.
All protective relays shall be in draw cases with built in test facilities. Test block and
switches shall be located just below each relay for testing unless otherwise specified. All
auxiliary relay and timers shall be supplied in non draw out cases.
All relays shall be suitable for operation at 50 Hz AC voltage operated relays and current
and times shall be designed for the DC voltage specified in data sheet and shall operate
satisfactorily between 70% and 110% of rated voltage.
Voltage operated relays shall have adequate thermal capacity for continuous operation.
All protective relays shall be provided with at least two pair of potential free output
contracts. For auxiliary relays and timer it shall be as specified in data sheet. Relay cases shall
have adequate number of terminals for making potential free connections, to the relay coils and
spare contracts. Paralleling of contacts, if any shall be done at the terminals on the casing of the
relay.
All protective relays shall be provided with externally hand reset positive action
operation indicator.
All timers shall be electromagnetic type only. Short time delays in milli- second may be
obtained by shading with copper lugs on auxiliary relays. This shall not affect the continuous
rating of the relay.
All relay shall be self next type unless other wise specified in respective data sheet.
Each relay shall have provision for easy isolation of trip circuit for the purpose of testing
and maintenance.
All relays shall with stand a test as per relevant IS code and standard.
Auxiliary seal in units provided on the protective relay shall be shunt reinforcement type.
Control Switches
Control and instrument switches shall be rotary type suitable for semi-flush mounting with access to
connection from the back by the removal of the cover.
The following shall be operating handles employed for the different type of switches.
a) Breaker control switches Pistol grip or knob type discrepancy control switch with built in lamps b) Selector switches c) Oval knob (black)
Circuit breaker control switches shall be 3 positions, spring return to neutral type and shall have external
red and green indicating lamps. Red lamps shall be wired for continuous supervision of trip circuit with a
serials resistor. Alternatively, discrepancy type control switches with built in pilot lamps may be
provided. In addition to the pilot lamps, each discrepancy switch shall be supplied with a non lamp wired
to supervise the trip circuit when the circuit is in closed position.
The switches shall have spring return from close and trip position to after close and trip position respectively.
Also it shall be required to press the switch before turning to close or trip command position.
Instrument transformers shall be of the maintained type. Ammeter selector switches shall be of break type
contacts.
Contacts of the switches shall be of pure silver and the rating shall be suitable for their duty.
Push Buttons
Push buttons shall be of momentary contact type with rear terminal connection. Where specified in the
data sheet, the push buttons shall be so designed to prevent in advertent operation.
All push buttons shall have contacts of pure make with two normally open and two normally closed
contacts.
Indicating Lamps
Indicating lamps shall be of the panel mounting type with built in series connected resistor.
The wattage and resistance of the lamps shall be as follows:
Neon indicating shall be provided when specified in data sheet.
Bulbs and lenses shall be easily replaceable and inter- changeable. Tools if any required for this shall be
included in the scope of supply. L.T. Circuit Breaker:
L.T. Circuit Breakers shall be of following type:-
1. Moulded case circuit breaker. 2. Air circuit breaker
The provided circuit breaker shall confirm to relevant I.S. specification Moulded Case Circuit Breakers (M.C.C.B.):
M.C.C.B. should automatically isolate the electrical circuit under sustained over load short
circuit. The other construction feature shall be as per details given below: -
1. Operating mechanism shall be quick make, quick-break and trip free. It should be independent
of manual operation.
2. Housing should be made of heat resistant insulating material. All parts of circuit breaker should be
enclosed in moulded housing. Terminals should be accessible for external connections.
3. Operating handle should give clear tip indication i.e. ‘ON’ ‘OFF’ and ripping position should be
clearly visible.
4. M.C.C.B. shall consist of bimetallic element providing an inverse time current tripping
characteristic.
5. Magneto thermal release shall have three bi-metals giving thermal over load protection and
electromagnets which offer short circuit protection. This shall be direct acting. Electro-magnets
shall offer short circuit protection.
6. All releases should operate on a common trip bar, so that all the phases get disconnected even
when fault occurs on only one of them.
7. Silver alloy contacts should have long electric life. The mechanism should be so designed that there
should be no arcing on the current carrying part of the contact. There should be strong wipe action of
the contact system for keeping the contact surface clear of oxide films. 8. Terminal should have large and sufficient dimensions to accept links or cable lugs, adjacent
phase terminal should be separated by insulated barriers with adequate clearances. Terminals
configuration should permit straight through cabling.
9. Back up fuse be provided. Specification of Air-Circuit Breaker (A.C.B.)
1. Triple pole draw-out A.C.B. suitable to operation 415 ± 6% 50 C/S A.C. supply shall be fully
interlocked horizontal withdraw-out type version with Hinged door. It shall be provided of
positively automatic safety shutters with pad locking facility, mechanical ON/OFF indication,
mechanical Service/Test/Isolated position indication, silver faced moving contacts and arcing
contact.
2. All contact subjected to arching should tipped with are resistance materials, Inter phase barriers
should also be incorporated.
3. Isolating contact of silver plated, multi-finger, spring loaded type should be provided. 4. Magnetic over current, release should be provided to offer protection against overload and short circuit. It
should be direct operated type or C.T. operated depending upon the ratings/load requirement. Release
should beset to trip the breaker between 75% to 15% or rated current.
5. The breakers should be interlocked to prevent access to live parts unless the circuit is dead. 6. The breaker should not be disconnected from the isolating contacts or re-engaged with the
contacts unless breaker is in the open position.
7. The breaker must be tripped before the door can be opened to gain access to the racking door is
open until ‘ISOLATED’ position is reached.
8. Main contacts should be shrouded automatically by a safety shutter preventing in advertent
contact with isolating contact in with-drawn position.
9. A.C.B. shall comply to IS-2516, I.E.C. –157-1 & B.S.4752 10. All rating of ACBS shall be tested as per I.S.
516. Main Bus Bars
Main bus bars shall be of aluminum alloy conforming to relevant I.S unless otherwise
mentioned in Data Sheet.
Bus bar shall be located in air insulated enclosure and segregated from all other
compartments of the cubical. Direct contact or accidental contacts shall not be possible with
the bus bars and primary connections.
All bus bar joints shall be silver faced. Spring washers shall be provided to ensure
good contacts. In case aluminum to copper connections are required, suitable bimetallic
connection or all bus bar joints shall be silver faced.
Bus bar shall be adequately supported on insulators to withstand dynamic stresses due
to short circuits. The bus bar support insulator shall conform to IS 2544.
Bus bar shall be insulated with extended PVC sleeves or other insulating material.
The PVC used shall be of high temperature grade (850C) and shall posses good dielectric
properties, high tensile strength and good finish. The joints and tops shall be covered within
insulating tapes covering which withstands a temperature of 850C. The size of bus bar shall be
selected making them suitable for future loads also.
Automatic Power Factor Correction Panel
APFC Panel shall have intelligent Microprocessor based relay, 12 steps based on the
requirement. The relay shall have auto manual selection feature and shall adapt the direction of
CT besides, it shall possess salient features like –
1. Auto self adjustment to any capacitor step value
2. Multiple LCD data indication of Power factor at each phase(lead/lag), KW, KVA, KVAR,
Voltage, Load Current at each phase, Capacitor current at each phase, Injected KVAR to reach
target power factor, Frequency, etc. incl. of all preset
parameters & specified installation data
3. Automatic Self-adjustment for C/K value.
4. Three phase sensing suitable for three phase-unbalanced loads.
5. Operation time delay facility for 10-240 sec.
6. Memory back up to save the data in the event of power failure.
7. Alarm output for Capacitor or Contact failure, abnormal values of voltage,
current, KVAR, Power factor, Temperature, Frequency, etc.
8. No-volt relay features to immediately disconnect all capacitors in the event of
power failure.
9. Various protections i.e. over temperature, over harmonics, overload, etc.
10. Remote fault alarm indicator.
11. Power factor correction fault.
12. Facility to connect computer.
13. RS 232 serial port.
Tests
Relays and control panels shall be subjected to the following tests at Manufacturer’s works
1. Mechanical operation test. 2. Certificate of test previously conducted on these items or on similar equipments of similar
capacities and specification verification of degree of protection shall be submitted.
3. Electrical control, interlock and sequential operation. 4. Verification of wiring. 5. Type tests and routine test shall be carried out on all associated equipment as per relevant Indian
standard.
6. Certified copies of all test reports shall be submitted to the purchaser before dispatch of the
equipment. 4.0 CABLES
The scope of this tender includes power wiring with 3.5 core Al. cable of suitable capacity from
power transformer to LT panel and 3.5 core copper cable of suitable capacity from each out going feeder
to starter of each pump and from starter to motor. The cabling shall have to be done properly providing
necessary loop at end termination duly clipped and mounted on the
sump wall of the pump house. Power wiring shall have to be carried out as per the latest relevant
IS/IER End termination should be lugged and then connected. The tenderer is required to quote
the size of the cable.
LT cables shall be rated for continuous operation and HT cables shall be rated for its short circuit. The sizes of cables shall be fixed after taking into consideration the derating factors applicable.
All cables shall be steel flat strip armored unless specified. Cable end box for HT cable shall be
furnished complete with heat shrinkable type termination, tabular tinned copper lugs, armour
clamps, gland plate etc.
MS CHEQUERED PLATES, 8 MM. THICK AND PAINTED WITH BLACK ENAMEL
PAINT FOR COVERING THE CABLE TRENCHES WHEREVER
REQUIRED/DIRECTED BY THE ENGINEER SHALL BE PROVIDED UNDER ALL
SUB HEADS. THE WEIGHT OF THE CHEQUERED PLATES SHALL BE AS PER
STANDARD TABLES AND IN DIAMOND PATTERN.
Wherever parallel double cables are to be laid, the capacity of individual cable should be
sufficient to take full load current required for ultimate load and other cable work as standby up
to ultimate stage.
Codes and Standards
The design, manufacturer and performance of the cables shall comply with all currently applicable
statues, regulations and safety codes in the locality where the equipment will be installed.
Unless otherwise specified, the equipment shall conform to the latest applicable Indian Standards.
a) IS: 1554 (Part – I) PVC insulated (Heavy duty) electric cables,
Part-I for working voltage up to and including 1100V
b) IS: 1554 (Part-II) PVC insulated (Heavy duty) electric cables.
Part-I for working voltage from 3.3 KV up to and
including 11 KV.
c) IS: 3961 (Part-I) Paper insulated (Heavy duty) electric cables.
Part – I for working voltage up to 3.3 KV.
d) IS:694 PVC insulated (Light duty) electric cables for
working voltage up to 1100V. e) IS:3961 (Part-II & V)Recommended current ratings for cables.
Part- duty
II-PVC
cables
insulated
Part –
and
V-PVC
PVC sheathed
insulated light
heavy
duty
cables. f)
IS-692-1965 (with latest
Paper Insulated Power Cables amendments)
g)
IS-7098
Specification for XLPE Cable
Cables shall be supplied on non-returnable drums made of seasoned wood.
For the following voltage grade, the cable length on each drum shall be subject to
purchaser’s approval.
S.No. Voltage Grade Conductor Size
1. 1100 V Above 95mm2
2. Below 1100V All sizes
Installation of Cables 1 Contractor’s scope of work includes unloading, laying, fixing, jointing, bending and termination of
cables. Contractor shall supply all the necessary hard wares for jointing and termination of cables. Cables
shall be laid directly buried in earth, on cable trays and supports in conduits and duct or bars on walls
ceiling etc. Contractor shall route the cables as directed by purchaser.
All cable work and the allied apparatus shall be designed and arranged to reduce the risk of fire
and any damage that may cause in the event of fire wherever cables pass through any floor or
wall opening suitable bushes shall be supplied if required by the purchaser. The bushes shall be
seated using fire resisting materials to prevent fire spreading. 2 Standard cable installation tools shall be utilized for cable pulling. Maximum pull tension shall not
exceed the manufacture’s recommended value. Cable grips reels or pulleys used shall be properly
lubricated. The lubricant shall not injure the overall covering and shall not set up undesirable
conditions of electrostatic stress. Cable pulling shall permit performance collateral work without
obstruction. Shear bending and kindling of cables shall be avoided. The bending radius for various
types of cables shall be more than those specified by manufacturer. 3 Power and control cables shall be laid in separate cable trays. The order of laying of various
cable in trenches and overhead trays shall be as specified below.
Cables of highest system voltage at the top most tier with second highest voltage on the second
tier from top, third highest voltage on the third tier from top etc. with control instrumentation
and other service cable in bottom most cable tier. 4 Where groups of HV and LV and control cable are to be laid along the same route, suitable
barriers to segregate them physically shall be employed. Where cables cross roads and water, oil,
gas or sewage pipes, the cables shall be laid in reinforced spun concrete pipes of 150 mm
minimum diameter. Also 50% space shall be kept as space for future if more than one cable are
to be laid through pipe. For road crossing, the pipe for the cable shall be buried at not less than
one meter depth. Cable shall be protected at all times from mechanical injury and from
absorption of moisture. 5 Some extra length shall be kept in each cable run at a suitable point to enable or two straight through
joints to be made at a later date, if any fault occurs. To facilitate visual tracing, cables in trays shall be laid
only in single layers where design permits. Cable splices shall not be permitted. 6 Cable jointing shall be in accordance with relevant Indian standard codes of practice and manufacturer’s
special instructions. Materials and tools required for cable jointing work shall be supplied by contractor.
Cables shall be firmly clamped on either sides or a straight through joint at not more than 300mm. away
from the joints. Identification tags shall be provided at each joint and at all cable terminations. Single core
cable joints shall be marked so that phase identification at each joint can be determined easily. The joints
shall be located at most suitable places. When two or more cables are laid together, joints shall be
arranged to be staggered at about three meters. Before jointing, insulating resistance of both sections of
cables to be jointed shall be checked. 7 Contractor shall install and connect the power, control and heater supply cables for motors.
Contractor shall be responsible for correct phasing of the motor power connecting and shall
interchange connection at the motor terminal box if necessary after each motor is test run. 8 Metal sheath and Armour of the cable shall be bonded to the earthing systems of the station. 9 Cable clamps shall be minimum 3 mm thick and 25 mm. wide galvanized M.S. flat spaced at
every 1.0 m interval.
Conduits & Pipe 1. Contractor shall supply and install conduits, pipes as specified. All accessories/fittings required
for making installation complete shall be supplied by the contractor. Conduits and pipes shall be
GI and of heavy duty type. Flexible metallic conduits shall be used for termination of
connections to equipment to be disconnected at periodic intervals. Conduits or pipes shall run
along walls floors and ceilings on steel supports embedded in soil, floor, wall or foundation in
accordance with relevant layout drawings.
2. Exposed conduit shall be adequately supported by racks clamps, straps or by other approved means.
Each conduit run shall be marked with its designation as indicated on the drawings.
3. When one or more cables are drawn through a conduit cable. Cable shall fill not more than 50%
of the internal cross sectional area of the conduit.
4. Entire system of conduit after installation shall be tested for mechanical and electrical continuity
throughout and permanently connected to earth by means of special approved type earthing
clamp efficiently fastened to the conduit
5.0 EOT CRANE
03 Tonne suitable for pump house alongwith all girders as per design & site conditions.
A. CRANE
a) The crane bride shall consist of a single bridge girder carrying two wheels at each end of the span
and 2 Nos. long travel girders for entire pump house as per drawing/site conditions.
b) The long travel bridge wheels shall be rim toughened, head treated carbon steel. They shall be
double flanged type. The wheels shall have antifriction bearings. The wheels shall be machined
on their treads to match the runway rail section. The bridge shall have a geared shaft and pulley,
connecting to opposite wheels of the span to manpower the long travel motion of the bridges by
means of a chain supplied with the crane. The runway rails of adequate strength and rigidity¸ rail
clamps and other accessories for mounting the rails on the structure and suitable end stops for the
bridge shall be provided.
B. TROLLEY AND CHAIN PULLEY BLOCK
a) The chain pulley block shall be operated on the lower flange of the bridge girder. b) The load chain shall be made of SS-410. It shall be heat treated to give ductility and toughness.
It shall be welded construction with a factor of safety not less than 5.
c) The load wheel, main arm holding upper hook and the B block holding bottom hook shall be
made of heavy duty malleable casting.
d) The hand chains for the hoisting and traverse mechanism shall hang well clear of the hook and
both the chain shall be on the same side. The hand chain wheel shall be made from pressed sheet
steel and shall be provided with roller type guarding. e) All the gearing shall be totally encased. Gears shall be out from solid cast of forged steel blanks. Pinions
shall be of forged carbon or heat treated alloy steel. Gears shall be as per IS 436.
f) The trolley track wheel shall be rim toughened, head treated carbon steel or lows alloy steel or
graded CI and shall be single flanged and shall have antifriction bearings.
g) The travelling trolley frame shall be made of rolled steel. The side plates of trolley frame shall
extend beyond wheel flanges. The two side plates shall be connected by means of an equalizing
pin.
h) Axles and shafts shall be made of carbon steel. i) The lifting hooks shall be forged, heat treated alloy or carbon steel. They shall be of single hook type
provided with a standard depress type safety latch. They shall swivel and operate on hardened races.
Locks to prevent hooks from swivelling shall be provided. Hook shall be as per IS 3815.
j) The brake for the lifting gear shall be screw and friction disc type and shall offer no resistance
during hoisting. Over load test at 150% of rated load for chain pulley block and trolley,
overloaded test of 125% of rated load and deflection test with 100% of rated load for the crane.
Test certificate has to be given by the fabricator/manufacture. 6 & 7 SLUICE VALVE
(A) DESIGN REQUIREMENTS
a) Sluice valves shall generally confirm to IS:780 and IS:2906. Additionally they should also meet
specific requirements mentioned in the following paragraphs.
b) Valves shall close with clockwise rotation of hand-wheel. The direction of closing shall be cast
on hand wheel.
c) Valves shall be designed for 10 bar rating. (B) FEATURES OF CONSTRUCTION
a) Valves shall have non-rising spindle. b) Valves shall be with bushing for replacement of packing without leakage. c) Valves of size 350mm and below shall be with renewable channel and shoe arrangement. d) Valves of size 350mm and above shall be supplied with worm/bevel gear arrangement so that
the valve can be operated with an effort not more than 7 kg-m on the hand wheel.
e) Nominal size of the valve shall be cast on the body of the valve. (C) MATERIAL OF CONSTRUCTION
Body - Cast iron IS 210 Gr FG 200
Wedge - Cast iron IS 210 Gr FG 200
Spindle - Stainless Steel AISI 410
Seat rings - Gun metal
Shoe - Gun metal
Channel - Gun metal lined
(D) SHOP TESTING
To be witnessed by engineer Incharge of project (if necessary) - Seat leakage test at 10 bar. - Backseat leakage test at 5 bar. - Body hydrostatic test at 15 bar.
8 & 9. NON-RETURN VALVES
(A) DESIGN REQUIREMENTS
a) Valves shall be with non-slam characteristics. b) Valves shall be suitable for mounting on horizontal pipe line. c) Hydraulic passages shall be designed to avoid cavitations. d) The internal parts shall be accessible through inspection hole. e) Valves shall be designed for 10 bar rating.
(B) FEATURES OF CONSTRUCTION
a) The non-slam characteristics shall be achieved either providing suitable combination of door and
hydraulic passage or by a dashpot arrangement.
b) Valves of size 500mm and above shall be provided with supporting foot. c) No by pass is required for the valves. d) Nominal size of the valve shall be cast on the body of the valve.
(C) MATERIALS OF CONSTRUCTION
Body - Cast iron IS 210 Gr. FG 200
Door - Cast iron IS 210 Gr. FG 200
Body Ring - Gun Metal
Door Ring - Gun Metal
Hinge Pin - AISI 410
(D) SHOP TESTING – To be witnessed by engineer incharge (If necessary) - Seat leakage test at 10 bar. - Body hydrostatic test at 15 bar.
10. M.S. /CI DF DELIVERY PIPING
A. GENERAL
a) The pipes shall be of uniform bore and straight in axis. Length of the straight double flanged pipes
shall be within a tolerance of ± 1.5mm. The thickness of fittings shall be 8 mm.
b) The flanges of the straight pipes shall be square to the axis of the pipes. The faces of the flanges shall
be parallel. The bolt hole circle shall be concentric with the bore and bolt holes equally spaced. In
straight pipes the bolt holes in one flange shall be located in line with those in other. c) The faces of the flanges of the fittings shall be square of the directional exes. The bolt holes shall
be located symmetrically off the centre line. The intersecting axes of the toes shall be
perpendicular to each other.
d) The bolt holes on flanges pipes and fittings shall be drilled with the help of drilling jig. B. MILD STEEL/CI PIPES AND FITTINGS
a) Materials of steel pipes and fittings shall confirm to IS:22 flanges to IS:2062 and IS: 1538. b) Fabricating and testing shall be in accordance with IS: 3589. c) Hydrostatic test pressure shall be 15 bar. d) Pipe surface shall be cleaned thoroughly by shot or sand blasting process, so that it is completely
free from rust and dirt. The cleaning shall be so carried out that it shall be free from mill scale,
rust, oil, welding scale and other foreign materials. At field, however, the surface may be cleaned
by wire brushing.
e) The primer paint shall be of material recommended by the manufacturer for the grace of enamel
used and shall be applied as recommended by the manufacturer. Freshly primed pipe shall be
handled carefully before applying enamel. f) Enamel shall be moisture and dirt free at all times prior to and at time of heating and application. The
primed surface shall be dry and clean at all times and the enamel shall be applied not later than 3 days
after application of primer. Along with first flood coat of enamel single spiral wrap of fibre glass inner
wrap shall be applied overlapping at least 20 mm on pipe upto 250mm diameter and 25mm on larger dia
pipe. The total thickness of the coating shall not be less than 2.5mm.
g) Each end of the pipes left bare for welding purpose shall be hand coated and wrapped after field
welding is completed and hydro tested. 11. PRESSURE GAUGES
a) Each main pump shall be provided with pressure gauge of the range (0-7 Kg/cm2 ) and
depth gauge. b) The gauges shall be of bourdon type. c) The error in pressure indication with either increasing or decreasing pressure shall not exceed
1.5 % of the maximum scale value.
d) The dial size of gauge shall not be less than 150 mm. e) Gauges shall generally confirm to IS:3624.
12. GALVANISED NUTS, BOLTS, STUDS AND WASHERS AND RUBBER PACKING
a) Nuts and bolts shall be of the best quality bright steel, machined on the shank under the head and
nuts. Studs, bolts and nuts shall be electro-galvanized. Bolts shall be of acreage length so that
only one thread shall show through the nut in the fully tightened conditions. b) Washers, locking devices and anti-vibration arrangements shall be provided where necessary. c) Where there is a risk of corrosion, bolts and studs shall be designed so that the maximum stress
does not exceed half the yield stress of the material under any conditions. All bolts nuts and
screws which are subject to frequent adjustment or removal in the course of the maintenance and
repair be made of nickel bearing stainless steel.
d) The contractor shall supply all holding down, alignment and leveling bolts complete with
anchorages, nuts washers and packing required to fix the plant to its foundations, bed plates,
frames and other structural parts.
e) The contractor shall procure and keep at site reasonable excess quantities to cover wastage of
those materials, which will be normally subject to waste during erection, commissioning and
setting to work.
f) Rubber packing shall be as per IS. Make of nut, bolt, washers etc. should be mentioned in the
offer.
13. INTERNAL ELECTRIFICATION OF ZONAL PUMPING STATION: -
It will be done in copper concealed PVC wiring along with tube light and bulkhead etc. as per
UPPWD electric work specifications as direction of engineer in charge.
14. FIRE EXTINGUISHER
The contractor shall provide adequate supply of approved fire extinguishers and refills for the works.
In this regard he shall consult the engineer as to the suitability of the appliances which he proposes to
supply. A combination of chemical type and sand buckets 15 Ltr. have to be provided.
A. Chemical type 5 kg 2 Nos.
1 Set B. Sand buckets 5 Nos.
First Aid Facilities
The contractor shall provide complete first aid facilities for his staff (and other) till the date of
the handling over of the works. The facilities shall be fully available on the day of the
commencement of the plant. 15. EARTHING SYSTEM (CONFORMING TO IS 3034 & IER)
Two separate and distinct earth leads shall be used for earthing each equipment/structures enclosing
the power conductor and one earth lead for metallic structure adjacent or electrical installation metallic
frames of all electrical equipment rated above 250 volts, must be earthed by two distinct connection with
earth system. Earthing cables crossing other metallic structures such as conduits, pipe lines etc. shall be
minimum 300 mm away from such structures. All underground
connections and joints in earthing system shall brazed welded. Connections with equipments/structures shall be bolted type. Conducting petroleum jelly shall be applied to
contact surfaces of all bolted joints and joints shall be covered with bituminous compound and
tapped. When GI. conductors are connected to aluminum conductors the contact surfaces of G.I. shall be tinned to prevent bimetallic corrosion. Neutral connection shall never be used for the
equipment earthing. Earthing conductors shall be protected against mechanical damage. Earthing
conductors running along the structures, well etc. shall be cleared at every 750 mm interval. Minimum size of earth conductor shall be in accordance with IS:3043. however, sizes of earth
conductors for equipment shall be at least half the size of power conductor, limited to maximum of 120 mm of aluminum. All earth lead connection shall be as short and direct as possible and
shall be without kink. Earth Pits and Main Grip
Adequate number of earthing pits and electrodes shall be used in conjunction with earthing grid.
Minimum spacing between two adjacent earth pits shall not be less than six (6) meter and shall be
kept sufficiently away from structures to clear footings. Main grid loop for a building shall be
installed outside boundary of the building buried to backfill. It shall be installed at a minimum depth
of 600mmoutsidethe building wall. The main earth loops in plant areas shall be generally routed
along cables when equipment is located away. Suitable sub-loops may be run up to them for deriving
connections for individual equipment. Indoor Equipment Earthing
Ear thing grid embedded in the floor slab shall have a minimum concrete cover of 50mm. Every
alternate column (steel or R.C.C.) of the building, housing, electrical equipment shall be connected to
main earthing grid. Earthing conductor shall be welded at interval of 1000 mm along their run of
steel structure and shall be at interval of 750mm along the wall.
16. ELECTRO- MAGNETIC FLOW METER
Direct on line Full Bore electro-magnetic Flow meter of suitable size for clear water
application. The flow meter shall be suitable for bi directional flow measurement. This shall be
having protection category of the sensor shall be IP68 and protection category for the transmitter
shall be IP- 65. Accuracy shall be of +/- 5% of measured value without being affected by variation in the line pressure. Equipment should be complete with converter, transmitting device
and should be fully programmable with digital flow indicator & integrator etc. The sensor
housing and junction box should be of SS.
Electrical Power Supply Power consumption
Output
Accuracy Repeatability Time constant Minimum conductivity Display
Data Entry
Flow data
Diagnostics
: 24 VDC OR 90 V AC to 265 V AC, 50/60 Hz : 35 W (max.) : a) 4-20 mA Isolated (Max. Load 800 Ohms). b) 2 SPDT Relay. Programmable relay function Max. rating 2A at 230 Vac for non-inductive Load. c) Pulse output: 24 VDC Pulse Isolated (min. Load 150 Ohms)
Option Frequency output of 0 to 1KHz full scale : ± 1% of flow rate
: ± 0.1 % of F.S.D : 0.8 to 8 seconds adjustable
: 5 μS/cm (Micro Siemens/centimetre) : 16 x 2 Alphanumeric LCD, in multiple -Engg. units
: 2 Hall Effect Switches : Bi-directional Flow with separate totalizers
for forward and reverse flow : Empty Pipe Detection with Low Flow Cut off
: Built in with Data retention in case of power failure.
Password protection
Enclosure Housing material : Cast Aluminium
Paint : Polyurethane
Cable entry : M 16 (3 No.) suitable for cable diameter from
4.5 mm to 10mm
Controller mounting : Integral with sensor or Wall mounted
Ambient Temperature : - 20 deg. C to + 60 deg. C Protection : IP 67 Sensor
Certification : CE certified, RoHS from DNV & FM approval
FM Certified
17. PAINTING OF ALL EQUIPMENTS
All items of metal work shall be thoroughly washed, dried, cleaned, degreased before
application of any paint.
Normally, the initial coat shall be applied in the manufacturer’s shop. After arrival of the
equipment on site, the same shall be inspected and damaged portions shall be cleaned and given
the primer and under coat of similar paint.
After erection, metal works shall be painted as follows:
a) Surface painted with red oxide or primer or with oil based under coat shall receive two under
coats and one finishing coat of approved oil based paint.
a) Bituminous painted surfaces shall receive two coats of approved bituminous paint.
b) Galvanized surfaces shall be primed with chromate prime followed by two under coats and one
finishing coat of approved oil based paint. c) All indoor parts, instruments and electrical equipment shall be chromium or copper nickel-
plated. The following tables gives the nature of surface and paints to be used. The contractor
shall study and follow this properly.
S.No. Surface
1. All railings, mild steel
Ladders, pipes for
water Supply
2. Submerged metallic parts
and their projections above water level.
Treatment
Galvanization & two coats
of approved oil paints of
Approved Shades.
Anti corrosive paints suitable for sewage water.
3. Metal parts above water level 4. All indoor fixtures, parts
instruments, equipment, panels etc.
Approved oil paint of approved shades. Chromium or nickel plating.
The contractor shall clearly indicate the surface treatment for all metallic parts of the
plants in the schedule of particulars in details
SUBSTATION OF ZPS
NOTE: The drawing & installation of substation works has to be approved by Director Electrical safety
government of U.P. by the contractor and the rates for the same has to be inclusive in substation
works.
ISOLATOR VERTICAL BEAK TYPE WITHIN CAMPUS OF CWR WITH MESH
WIRE FENCING.
Electrical substation is to be provided with isolator and earthing switch for disconnecting the
circuit under no load conditions to ensure visual isolation. It is to be erected in such a way that a
party of 11 KV power supply to indoor contact breakers can be isolated visually from the HT
outdoor power supply for the purpose of easy and comfortable maintenance. Isolator shall be
vertical break type as per norms of IER and code of practice prevailing. It shall be incorporated
with earthing switch also between the outdoor heat shrink box and earth to make it sure that
capacity discharge is no more there. Earthing switches one or two shall be mounted on the frame
of isolator.
21. 11/.44 KV TRANSFORMERS (Should Confirm to IS 2026 & IS 1180)
The transformers shall be complete with all accessories and auxiliary equipment in accessories
with this specification in the following annexure:
Fittings and accessories: Off Circuit tap changer externally hand operated.
Oil conservator with filling hole and cap.
Plain oil level gauge with minimum level marking.
Thermometer pocket.
Silica- Gel Breather.
Drain cum filter valve.
Two earthing terminals
Lifting arrangements.
Explosion vent.
Air release plug.
HT and LT cable box.
OTI with alarm & trip.
WTI with alarm & trip.
Marshalling box for OTI & WTI
First filling of transformer oil.
Special tools and tackles for erection and maintenance of the transformers & other requirements.
All relevant final drawings, data and instruction Manual for operation & maintenance of the
transformers and other equipment in triplicate.
At the option of the Engineer, the successful tenderer shall provide the services of a Senior
Engineer for following:-
a) Supervision of the erection, testing, commissioning and putting into successful commercial
operation of all equipments furnished under this specifications.
b) Supervision of power cable, control cable and bus duct connections at the terminals of the equipment for
interconnections with the equipment supplied by others and under this specification. This supervision
shall include coordination of controlling system with the equipment supplied by others and related to the
operation of the equipment under this specification.
DESIGN CRITERIA (as per is 2026 and 1180 as referred to guideline of apex court)
The estimated fault levels of different system with which the transformers will be connected are
given above.
The transformer shall be suitable for outdoor services in hot humid and topical climate. All
equipment, accessories and wiring shall therefore be provided with tropical finish to prevent
fungus growth.
The design shall be made to suit the site condition stated above of this technical specification.
Running load shoule be around 50 to 60% of transformer capacity and starting load not more
than 75% of transformer capacity has to be compiled with.
TYPE OF COOLING:
The transformers shall be oil immersed ONAN cooling and designed for cooling as
specified ahead: -
TEMPERATURE RISE:
The transformers shall be capable of continuous operation at its rated output without exceeding
the limit of temperature rise as follows: -
a) Winding by resistance: 300C above ambient temp0C
The derating of the transformer shall be done by taking 500C as an ambient temperature.
VOLTAGE FLUCTUATION WITHSTANDING CAPACITY:
The transformers shall be appreciably free from noise and vibration and shall be capable of
continuous operation at the rated output under the following conditions:-
i) The voltage varying by +5 to -5% of rated voltage in 5 steps, 2.5% in each step and impedence
4.5%
ii) Frequency varying by ± 3% of the nominal value of 50 Hz.
iii) The transformers shall be able to withstand for 5 seconds without damage a short circuit between phase
and between phases and ground at one side, maintaining rated voltage on the other side. The under
frequency condition will not occur simultaneously with the over voltage condition.
SPECIFIC DESIGN REQUIREMENTS:
Tanks:
a) Tanks shall be of welded construction and fabricated from good commercial grade low carbon
steel of adequate thickness. All beams shall be properly welded to withstand requesting impact
without distortion. All welding joints shall preferably be stress relieved.
b) The tank wall shall be reinforced by stiffener for rigidity so that it can withstand any deformation.
i) Mechanical shock during transportation, and
ii) In full vacuum during filling of all.
c) The tank cover shall be bolted on to the tank with weather proof, hot oil resistant, resilient gasket
in between for complete oil tightness. If gasket is compressible, metallic stops shall be provided
to prevent over compression. Bushings, currents, cover of all access holes and other devices
shall be designed to prevent any leakage of water into or oil from the tank.
d) Each transformer tank shall be provided with one set of bi-directional rollers for rolling the
transformer parallel to either central line of the transformer.
e) Jacking pads, lifting eyes and pulling lugs shall be provide to facilitate movement of the
transformer. All heavy removable parts shall be provided with eyebolt for ease.
f) Manholes/Handholes of sufficient size shall be provided for access to leads, windings, bottom
terminals of bushing and taps if provided.
g) Oil sampling trap with valves shall be provided to collect samples of oil for testing from
different levels of the tank.
h) To facilities the oil filtration by streamline filters, suitable inlet and outlet taps with valves at
bottom and at the top of the tank on diagonally opposite corners shall be provided. The valve at
the bottom may be used as drain valve.
i) Thermometer – pocket for noting top oil temperature by liquid thermometer shall be provided.
j) The transformer tank shall be fitted with a diaphragm type of explosion relief vent at the top.
CORE AND COILS:
a) The transformer may be of core type. The core shall be built up with high grade, non-aging, low loss,
high permeability silicon steel laminations specially suitable for core material.
b) The coils shall be manufactured from electrolytic copper conductor and shall be fully insulated.
c) All insulating material shall be of proven design. Coils shall be so insulated that impulse and
power frequency voltage stress are minimum. Insulation level of graded insulation shall confirm
to the relevant standard.
d) Coil assembly shall be suitably supported between adjacent sections by insulating spaces and
barriers. Bracing and other insulations used in assembly of the winding shall be arranged to
ensure a free circulation of the oil and to reduce the hot spot of the winding.
e) All leads from the windings to the terminals boards and bushing shall be rigidly supported to prevent
injury from vibration or short circuit stresses. Guide tube shall be used where practicable.
f) The core and coil assembly shall be securely fixed in position so that no shifting or deformation
occurs during movement of Transformer or under short circuit stresses.
TAPPINGS:
a) Off - load taps as specified shall be provided on the high voltage, winding. If tappings are
provided on the low voltage winding, the tenderer shall clearly indicate the same stating reasons
thereof.
b) The transformers shall be capable of operation at required capacity at any tap position provided the
voltage does not vary by more than ± 2.5% of the voltage corresponding to the tap.
c) The winding including the tapping arrangement shall be designed to preserve the
electromagnetic balance between HV and LV windings at all voltage ratios.
OFF-LOAD TAP CHARGES:
a) The off-load tap changing shall be effected by a 3 phase hand operated tap changing switch. The
operating shaft shall be brought out of the tank and provided with a hand wheel so that it can be
operated at standing height from ground level.
b) A visual tap position indicator for the tapping in use shall be provided at the external operating handle and
provision shall be made to padlock the handle in each tap position. The arrangement shall be such that
padlock cannot be inserted unless the contacts are correctly engaged.
c) All contacts of the tapping shall be silver plated and held on a position under strong contact
pressure so as to avoid contact pitting of any type whatsoever.
INSULATING LIQUID:
a) The insulating liquid shall confirm to the latest revision of IS:335 or BS: 148.
b) The transformers shall be dispatched with leak proof, first filling of oil.
c) The tenderer shall indicate clearly the following aspects of the design.
i) Composition and properties of the insulating Liquids.
ii) Liquid preservation system adopted and method of sealing.
CONSERVATOR TANK:
a) Oil preservation shall be by means of conservator tank. The tank shall be suitably mounted on a
rigid foundation. The conservator tank shall be connected with the main tank by the pipes with
stop valves at both sides.
b) The conservator tank shall be provided with level indicator visible from the ground level, oil
filing plug & cap and oil drain valve.
c) The conservator tank shall be provided with dehydrating breather.
TEMPERATURE INDICATOR:
Oil & winding temperature indicators shall be provided. The local temperature indicator where provided
shall be so mounted that the same becomes readable at a standing height from the ground level. Alarm
and trip contact where called for shall be provided for suitable termination.
TERMINALS MARKING:
The physical position of the terminals and their markings shall be as per latest revision of IS:2026.
TERMINAL ARRANGEMENT:
i) Cable Connection:
a) High and low voltage terminals of transformers, which have been specified to be suitable for
cable termination shall be brought out through sidewall bushing to a weatherproof cable end box
with self-supporting disconnecting chamber. b) The cable end box shall be of plate steel construction, self supporting weather proof type having
suitable bus extension, if required, rigidly mounted on porcelain insulators.
COOLING UNITS:
The radiators of the transformer shall be designed for same pressure and vacuum conditions
as those for the main tank.
WIRING:
All controls, alarm indicators and relaying devices provided with the transformers shall be
wired upto the terminal blocks housed in a suited marshalling box and the terminal blocks shall be
suitable for termination of 7/0.737 mm copper conductor cable (1100 volt grade PVC insulated,
PVC sheathed armoured and overall PVC served cable as per IS. No two wires shall be connected to
one terminal. 10% spare terminals shall be provided.
PAINTING:
a) All steal surfaces shall be thoroughly cleaned by sand ballasting surface free of scales, rust and
grease.
b) All paints shall be carefully selected to withstand tropical heat, rain etc. The paint shall not scale
off or crinkle or be removed by abrasion due to normal handling.
c) All steel surface in contact with insulating oil shall be painted with heat resistant insulated
varnish which shall not react with and be soluble in the insulating liquid used.
d) After cleaning, the external surfaces shall be given a coat of high quality red oxide or yellow
chromate primer followed by filter coats.
e) The transformer shall be finished with two coats of battle ship gray synthetic enamel paint.
f) If it is considered necessary, the transformer may be given a further coating at site. The tenderer
shall indicate the type and quantity of the paint required with full specification for this purpose.
All external surfaces including that of radiators shall be so arranged that no point becomes
inaccessible in painting during maintenance work.
AUXILIARY POWER SUPPLY:
All indicators, alarms and trip contacts provided shall be suitable for operation on nominal
24V D.C. System.
EXPLOSION VENT:
These shall be suitable for rotation in any direction and shall be provided with sight gauge
and equalization connection.
TESTS
Routine Tests
During manufacture and on completion, all transformers shall be subjected to the routine tests as
per IS. In addition, the following tests shall be performed on each transformer.
a) After fabrication, each tank fitted with all valves, covers etc. shall be tested for leaks at the
normal head of oil 0.352 kg/cm.sq. for a period of 12 hours if any leaks occurs the test shall be
conducted again after all tanks have been repaired.
b) The tank shall be subjected to full vacuum for 12 hours.
c) After assembly each core shall be pressure tested for one minute at 2 KV AC between all bolts,
side plates, structural steel works and the core.
d) Excitation loss and current measurements shall be made at 90%, 100% and 110% of rated voltage.
e) Open circuit and short circuit test.
f) BDV test of die electric strength of oil upto 45 KV.
TYPE TESTS
Following type tests shall be performed on the transformers in accordance with relevant standards.
a) Impulse withstand test.
b) Temperature rise test.
Copies of such tests shall be given separately by the tenderer at the time of presenting the bill.
TEST ON MISCELLANEOUS EQUIPMENTS:
All component parts such as oil, bushings etc. auxiliary equipments shall be tested in
accordance with the respective Indian Standards.
WITNESSING OF TEST:
a) Equipment (Panel and transformers) may be finally tested at site after commissioning as per ISS
or BS.
b) Transformers shall be tested on load by the department before supply. This testing will be done at
manufacturer works or at U.P. State Electricity board approved Laboratory or authorised service
center of the concerned manufacturer. The contractor shall intimate the department (when this
equipment will be ready) at least 30 days before the expected date of these tests.
TEST CERTIFICATES:
a) Test certificate of Mfrs. shall be submitted in six copies.
b) Four (4) copies of each routine and type test certificates of the transformers shall be furnished to
the owner for prior approval before dispatch of any equipment.
c) The reports shall furnish complete identification of data including serial number of the
transformer.
22. 11 KV ARMOURED XLPE CABLE
Suitable size cable which shall be conforming to relevant IS specification. HT cables shall be
rated for its short circuit. The sizes of cables shall be fixed after taking into consideration the derating
factors applicable. All cables shall be steel flat strip armored unless specified.
MS CHEQUERED PLATES, 8 MM. THICK AND PAINTED WITH BLACK ENAMEL
PAINT FOR COVERING THE CABLE TRENCHES WHEREVER
REQUIRED/DIRECTED BY THE ENGINEER SHALL BE PROVIDED UNDER ALL
SUB HEADS. THE WEIGHT OF THE CHEQUERED PLATES SHALL BE AS PER
STANDARD TABLES AND IN DIAMOND PATTERN.
Wherever parallel double cables are to be laid, the capacity of individual cable should be
sufficient to take full load current required for ultimate load and other cable work as standby up
to ultimate stage.
Codes and Standards
The design, manufacturer and performance of the cables shall comply with all currently applicable
statues, regulations and safety codes in the locality where the equipment will be installed.
Unless otherwise specified, the equipment shall conform to the latest applicable Indian Standards.
a) IS-7098 Specification for XLPE Cable
23. HT CABLE AND TERMINATION BOX
Cable end box for HT cable shall be furnished complete with heat shrinkable type termination,
tabular tinned copper lugs, armour clamps, gland plate etc as per the relevant IS.
24. CONTROL CABLES
Control cables of suitable capacity running from HV panel to Power Transformer conforming to
relevant IS.
25. 24 VDC BATTERY BANK
02 Nos. lead acid battery each of 180A, 12V for control system alongwith electric charger of
30V with inbuilt protection to up keep 24 VDC Battery Bank.
26. EARTHING OF TRANSFORMER
Double plate earthing separately for both body and neutral, rest specification same as given in Sl. No. 15.
27. FIRE EXTINGUISHER
Same as given in Sl. No. 14
28. EXHAUST FAN
14″ Dia of reputed make totally enclosed and ruggedly built. The motor has prelubricated double
ball bearing and is provided with Class "A" and "E" insulation.
29. INSTALLATION, COMMISSIONING & TESTING OF PUMPING PLANT AND
SUBSTATION EQUIPMENTS :-
Scope of this tender includes installation of all equipments i.e. pump, starter, panel etc. required
for smooth and perfect functioning of pumping plants. The installation should be vibration less
(subject to tolerance as per IS) and fitting should not be in tension i.e. alignment should be perfect and sizes should be dimensionally correct. All the equipments shall have got to be tested
at works before supply and at site after installation for the guaranteed parameters. During the
course of commissioning any defect or shortcoming observed shall have to be rectified by the
contractor free of cost.
Also covers receiving of various pump sets at site, site handling, storing, maintenance
during storing, erection, testing and commissioning of the same.
Receiving, storing & maintenance of pump sets and all other equipment 1. Contractor shall usually check all the pump sets, electric motors and all other equipment received at
site for any physical damage and to see that all the accessories as indicated in vendors
drawings/purchase order have been received at site. After visual inspections, he shall make a report
stating his findings and submit the same to the purchaser. Upon submission of such report and
necessary action on the same by purchaser, if any, contractor shall be fully responsible for the pump
sets till it is installed, commissioned and handed over. 2. Pump sets received at site after contractor has opened his site office, if necessary shall be
unloaded and handled at site by the contractor. Any damaged to the equipment during handling
shall be on contractors account. 3. After taking over the pump sets, these should be properly stored and maintained as per the
manufactures instruction manual. Necessary consumables required for the purpose shall be
supplied by the contractors at no extra cost to purchaser. 4. All materials from one manufacturer must come in one lot. Erection of pump sets 1. As soon as pump house area is released for pump erection, contactor shall arrange to depute
sufficient number of skilled and unskilled labour and erector. The skilled erector shall be deemed to
be the contractor’s representative. Should there be more than one erector at site, the contractor shall
give in writing which erector is designated as his representative. 2. The contractors representative shall arrange to inspect the foundation requirements for erection of
pumping plants and all connected equipment for their suitability. The contractor will supply foundation
drawing and get the foundations constructed in presence of his representative. 3. Erection of pump sets and other equipments shall be carried out in presence of contractor’s
representative as per the instruction given by purchasers/pump manufacturer’s representative and/or
as per instruction given in the pump manufacturer’s manual. The contractor shall be responsible for
setting up and erecting the plant to the line and level required. 4. When the works are associated with or in physical contract with plan supplied by others the
contractor shall satisfy himself that work carried out by other contractor is consistent with physical
requirement of pump sets being erected. In case the contractor feels that the work carried out by other
agencies is not as per the design and would effect the erection/operation of pump set, he shall bring
the matter to the notice of purchaser’s site representative in writing.
Leveling and Grouting of Machinery
The purchaser’s representative shall be informed at all times to the progress of this work and
when any checks on alignment and level are to be carried out so that he may witness the checks
if he so requires. The approval of purchaser ’s representative or intimation that alignment or
level of pump sets is to his satisfaction shall in no way relieve the contractor of his obligation
under the contract to properly install and align the pump set and carry out rectification of any
installation work later found to be improperly carried out.
Final Connection
For other services such as electrical cables (power control), pump suction and discharge piping
etc. final connection for connecting these services to the respective terminal point on pump sets,
shall be done by the contractor.
Setting to Work
1. On completion of erection, the work erected by the contractor including final connection subjected to
hydraulic pressure shall be tested for 1.5 times maximum pressure whichever is higher to prove the
soundness of joint. The duration of test shall be of less than 10 minutes. 2. Prior to setting the plant to work the contractor shall check all items of electrical plant and shall
dry out the electrical motor insulation as stipulated in the electrical specification,
3. Only after above checks have been carried out and proved satisfactory, the contractor shall obtain
written permission from the purchaser’s representative for starting the pump set and shall continue to
operate the plant for the period desired by the purchase’s representative. Detailed Requirement of Installation
1. Switch gear, control panel etc.
All alignment, leveling, grouting, anchoring, adjustments shall be carried on in accordance with
manufacturer’s instructions and or as directed by the purchaser.
All modules shall be taken out and internal shall be cleaned preferable with vacuum cleaner.
All connections and fixing of equipments in switch gear control panels etc. shall be completed,
checked and adjusted to ensure safely and satisfactory operation of the equipment.
In some cases, minor modifications may have to be carried out at site in the wiring and mounting
of the equipment to meet the requirement of the desired control scheme and the contractor shall
have to do the same at no extra cost.
2. Motors
The installation of motors shall be carried out in accordance with manufacture’s instructions
and/or directed by the purchaser.
Checking and cleaning of bearing and charging/filling of lubricants wherever necessary.
Cleaning of core and winding, varnishing and drying gout the winding and measurement of air
gap for motor assembly at site if demanded.
Motors shall be run in uncoupled condition for few hours before coupling them with be drive
equipment.
Cable Termination
1) Cable termination shall include the following: a) Making necessary holes in bottom/top plates for fixing cable gland box.
b) Fixing cable gland box, connecting Armour clamp to cable Armour. c) Dressing cable, pouring compound etc. where ever necessary to make termination
complete.
d) Putting cable lugs, crimping them on the cores of cables, tapping bare conductors up
to lugs, wherever necessary.
e) Terminating to equipment terminals f) Supply and fixing of cable and core identification ferrules.
Where ever purchaser has not provided M.S. plates for fixing cable tray supports, contractor
shall install approved concrete fasteners for fixing cable tray support.
. Inspection
After completion of the erection/installation, each equipment shall be thoroughly inspected in presence of purchaser for correctness and completeness of installation. A checklist may be
furnished by the purchaser wherein all details to be checked and necessary instructions shall be
listed. The inspection and checking shall strictly follow the checklist. On completion of the
inspection two copies of the check list duly filled in shall be jointly signed by contractor and the
purchaser. Such endorsement however shall not relieve the contractor of his obligation under the
contract.
Testing and Commissioning
After completion of erection work, test shall be conducted by the contractor on each piece of the
equipment as per list to be supplied by the purchaser or his authorized representative. The contractor
shall provide all tools, instruments, material, labour and supervisory personnel for carrying out test
on the equipment and material under his scope of work.
The contractor shall record the test result on approved Performa and furnish four copies of the
result to the purchaser for his approval within a week from the data of test completed before
commissioning of the equipment. The contractor shall set the relays to their recommended
values. On successful testing the equipment shall be commissioned and put on trial run along
with other equipment in a manner mutually agreed upon.
The contractor provide preliminary testing at manufacture’s works and at site and
through testing of the plant during the course of erection and when it is completed as specified
and for official testing of the same in accordance with schedule ‘E’ . The electric motor and
pump be type tested at the manufacturer’s works. Pump sets will be tested at manufacturer
works as per schedule ‘E’ given by the contractor and as per IS:8034. Other material/accessories
will be checked as per relevant ISS.
After the plant has been put in continuous operation for the period desired by the purchaser’s
representative the plant shall be tested and commissioned as stipulated hereunder. 1. At least six weeks prior to start of testing and commissioning of the plant, the contractor shall
prepare a programme in consultation with the purchasers representative for the period of
commissioning and tests. 2. During commissioning the contractors shall supply all labour to supervise, operate test and do all
things necessary to keep the plant running. 3. Manual Commissioning Test These shall be such preliminary trails, test and run on individual items of plant as required by
purchaser’s representative.
4. Manual Operation Test These shall demonstrate the correct operating of the whole plant at all design flow and pressure with
minimum automatic control and monitoring equipments. The test shall be of at least seven consecutive
days duration reduced if necessary at the discretion of purchaser’s representative.
5. Automatic Commissioning Tests These shall demonstrate correct automatic operation of plant. Conditions shall be stimulated to
demonstrate the operating of safety and operation control. The tests shall be carried out for such
number of times, the purchasers representative considers necessary to demonstrate consistent
automatic operating of plant.
6. Test on Completion On completion of above noted tests, the tests on completion shall be carried out during which the
guaranteed duties must be performed continuously by each pumping unit for a period of at least 6
hours or as the purchaser’s representative may determine. The contractor shall provide all the
necessary instrument and gauges required for these tests. The instruments shall be celebrated prior to
their use. Contractor shall furnish necessary certificates of approved testing authority to this effect.
The test shall be carried out in line with B.S 5316 part-II.
If any test shows noticeable deterioration in the performance of the plant or any particular item
compared with the test results obtained during the test at manufactures work, the contractor shall
The contractor shall state in the tables attached with tender documents the efficiencies and duties of
the pumping plants when working at specified conditions of the pumping and the guaranteed
performance in K.W. hour input per water horse power output under various conditions of working.
The guaranteed performances are also to be specified under following conditions i.e. variation in
head discharge and power consumption in the following cases:
d) When available voltage decreases from 415 volts to 380 volts or increases from 415 volts to 440
volts.
e) When there is fluctuation of ±3% in the frequency of the AC power supply from 50 C/S. f) When there is above change in voltage and frequency of the AC power supply simultaneously.
The official tests shall be conducted in two stages. Preliminary tests may be conducted at the
manufacturer’s works. The final tests shall be conducted at site. Pumps shall be run so as to
obtain the range of heads specified in the performance tables by means of throttling or opening
valves of the pumping mains and tests results will be compared with those guaranteed by
averaging the units consumption per water horse power hour.
The guaranteed figures stated above shall be subjected to no tolerance and the average results shall
be obtained during official test of plant. If the results lack average guaranteed figures the contractor
shall forfeit followings ascertained damages relating to each set installed.
If BOT unit (KWI) per WHP, the consumption is above the average guaranteed figure under the
specified Q and H, the liquidated damages will be recovered as the capitalized cost of the Extra
Energy Consumption during the useful life span 15 years of the pumping set. The liquidated
damages shall be calculated as below:
Cost of extra power consumption
to be recovered shall be equal to =Cost of extra power per annum X capitalization factor for 15
years at an interest rate of 9%.
No damage will however, be recovered if the consumption is less than 0.05 BOT units per WHP
above the guaranteed.
If on testing the discharge of pumps is found to be within the permissible limit of ±4% then the
pumping plant will be accepted without imposing any penalty. If discharge is less by 5% to 10% then
pro rate deduction @ 1% of the cost of pump and motor for less percentage of discharge shall be
made and further if the discharge is less than 10%, plant will be rejected.
It may be noted very carefully that no privilege shall be given to any offer for evaluation
purposes considering the efficiency of the pump. Better efficiency pump however shall be
preferred. For evaluation purpose pump efficiency shall be considered as 75 % but the pump will
be tested on the efficiency quoted by the firm.
The pump efficiency offered below the efficiency quoted shall be considered for evaluation as
follows:
(i) Electric charges shall be based on 16 hours of operation per day for 15 years at the prevailing
rate of Electric Charges. (ii) All future costs of yearly power consumption will be capitalized to present value at
capitalization factor @ 9% interest.
The tenders shall have to consider the condition of pumps being run at shut off head under the
pump duty variation condition as narrated above. The tenderer should ensure selection of pumps
considering shut off head at least 25% more than the duty head. However the motor should be
selected as per tender specification and scope of work defined. The possibilities of change of
duty point of each pump in parallel operation can not be ruled out under such condition tenderer
should select the pump carefully.
Penalty for delay in supply and installation-0.25% per day of the total tendered cost subject to a
maximum of 10%.
Rectification and Taking Over
The contractor shall carry out all rectifications, repairs or adjustment work found necessary
during testing, commissioning and trial run. On successful commissioning and trial run and on
carrying out the rectification work, the purchaser will take over the installation either wholly or
in parts as the case may be.
30. DRAWINGS:
The tenderers shall have to submit the following drawings & QAP and to get it approved by the
deptt. before start of execution/dispatch from works :-
1. Layout plan of equipments and pipe and specials
2. Drawing of foundation blocks.
3. Manufacturer’s catalogue of pump set and transformer with cross sectional dimensional details.
4. Line diagram of power wiring of control panel.
5. Parallel operation curve (when two pumps running in parallel)
6. Characteristic curves of diesel engine and alternator showing their performance under
varying condition.
7. Control Panel Drawing.
31. INTERNAL AND EXTERNAL ELECTRIFICATION
TUBULAR POLES AND LIGHTING
09mtr. high single or double pole lighting shall be provided over the area spread over MPS
campus and STP with Illumination as required standards given below:
ILLUMINATION:
All internal and external areas shall be provided with lighting. The illumination levels to be
achieved shall be as follows for which contractor must submit the drawing and after getting
approved carry out the work as follows:
AREA LUX
Office and labs 300 Lux Switchgear Room 200 Lux
Control Room 300 Lux Pump House 200 Lux DG set room 200 Lux Chemical and general store 150 Lux Chemical Plant room 200 Lux Other indoor areas 100 Lux Outdoor plant from and 50 Lux Building entrance 100 Lux Indoor Plant Area 200 Lux Outdoor Plant Area 50 Lux Transformer Area 100 Lux
Roads 10 Lux
31.1 LED luminaries shall be used primarily for internal lighting. High pressure vapour or metal halide type
luminaries shall not be used in indoor application anywhere. All other internal areas shall be lit with
LED luminaries. Where specific recommendations of lux level are not covered above, illumination level
in such areas shall be finalized in consultation with Owner. Owner shall be required to measure levels of
illumination after completion of lighting installation work and short fall in illumination level shall be
made good by the Contractor. Complete set of calculations showing, room, index, copy MF shall be
given during detailed engineering. 31.2 Switches / sockets of piano type shall be used in general and in offices of staff, control room, MMI room,
decorative modular switches shall be used. Suitable fans shall be provided in rooms/ plant areas as per
standards. For exhaust fans it must be provided in process room, panel rooms, pump rooms, chemical
rooms, stores, toilets and at least 20 air changes per hour must be maintained.
31.3 The following type of lighting fixtures shall be proposed:
a) Decorative type fixtures for LED luminaries inside office/ administrative buildings and control rooms.
b) Corrosion resistant fixture with canopy made of FRP for LED luminaries for corrosive areas like chlorine handling or chemical store or area with corrosive smell/gases etc.
c) Industrial type vitreous enameled fixture for LED luminaries inside 415V switchgear, MCC room and pump house.
d) In outdoor process areas, lighting fixtures shall be LED type subjected to minimum of IP protection class.
e) All outside lights as plant field lights, building outside lights, flood lights etc. which are to be switched on only during night hours should be controlled through photo cell/ clock switch installed at a central place. All lights shall have minimum IP65 protection class. f) Street lighting wiring shall be through buried underground. g) All bulb fittings (except fluorescent lamps) will have screw type caps.
h) For outdoor lighting, the lighting feeder shall be operated through a contactor, controlled by photocell/ clock switch and shall also have a manual by pass switch.
31.4 Luminaries shall be installed to permit ease of maintenance i.e. it shall not be necessary to shut down
plant in order to carryout maintenance or to access luminaries located over areas of water etc. The
Contractor shall provide all equipment necessary to carryout maintenance on the lighting installation
and demonstrate its operation to the satisfaction of Owner.
31.5 Indoor lighting circuit will be arranged in such a way that 50% lighting can be put off in each room
through switches. All lighting circuits will be wired with 2.5sq.mm. Stranded copper wire or through 2.5
sq. mm. armoured cable laid in cable trays. Sub circuit from switch to fixture could be wired with1.5
sq.mm. stranded copper wire in MS conduits or armoured copper cable of similar size provided total
voltage drop in any lighting distribution board to last lighting point shall not
exceed 2%. All lighting circuits will have separate neutral, separate earth from Lighting Distribution
Board. For illumination of roads, outdoors areas where operation of equipment or units required and
sub-station area, lighting fixtures of appropriate type (such as street lighting type, flood lighting type,
post top lanterns etc.) incorporating high pressure sodium vapour lamps shall be proposed. Street
light poles shall not have less than 7500 mm height above the finished road level and the arm shall
not project more than 1200 mm along the road width. Poles of bigger heights may also be used if
some outdoor areas are to be illuminated. Poles of 4 / 4.5 Mtrs using post top lantern may be used in
gate office walk way or in front of office area. Complete area, streets, lanes, boundary shall be
covered with street lighting. Receptacles (Lighting & Small Power) :
a) Decorative and industrial type units of above shall be proposed in all plant areas, offices, stores, workshop, plant room and they shall be located at least two numbers in each room. Distance between two receptacles shall not be more than 8 – 10 mtr. All small 5 amps 5 pin lighting & small power sockets shall be wired by multi stranded copper wire of 2.5 sq. mm laid in rigid MS conduits along with earth wire of1.5 sq.mm flexible copper wire or equivalent size armoured cables. All wiring shall be coded with Red, Yellow, Blue & Black as per the phase used. If required, wiring can be done alternatively through armoured copper cables of similar size laid in MS perforated trays of minimum 2.0 mm thick.
b) Three phase power receptacles (convenience outlets) suitable for operation of 415V,3Phase 4 wire,
50 Hz power supply shall be proposed. In indoor areas one such unit shall be provided to cover areas
of 20 meter radius (or at least one in each room housing plant items ) and in outdoors areas on such
unit shall be provided at 50 meter interval. Actual requirement of such units shall be finalized by
MMC during detailed engineering. One three phase receptacle shall be provided near entrance of
each building for utilities like welding. c) Single phase 15 Amp 5 Pin / 6 Pin receptacles will be provided in each room and in halls they will be
provided in such a way that with 15 meter cord we should reach every place in building. These shall be
wired with 4 sq. mm copper earth wire in MS rigid conduits along with 2.5 sq. mm earth wire. Not more than two sockets shall be looped in one circuit. Alternatively they can also be connected through armoured cable of 4 sq. mm running in appropriate cable trays.
31.6 Separate lighting panels and lighting distribution boards shall be installed and they shall not take tapping for power from motor control centers or power distribution boards.
INTERNAL & EXTERNAL LIGHTING OF THE BUILDING All the building construction will have internal and external lighting as above mentioned
specifications and lighting panel MCB distribution board as per specifications given below.
SPECIFICATIONS FOR LIGHTING PANELS (MCB DISTRIBUTION BOARDS) SPECIFICATIONS
Relevant Indian Standard Specifications and Codes shall apply for Lighting Panel Boards and
their components wherever such Standard Specifications exist. The panel shall be approved by
the Fire Insurance Association. Lighting Panels shall be generally comprised of Isolators, MCBs, ELCBs, ELMCBs and HRC fuses (if asked for in BOQ), Potential Indicating lamps, set of separate phase terminal strips, Neutral terminal strip and Earthing terminal strip and any other components as indicated in the
Bill of quantities
2 GENERAL REQUIREMENTS i) Lighting panels shall be made of 14SWG sheet steel and painted with powder spray to prevent
corrosion. ii) Lighting panels shall have properly hinged cover of min. 2 mm thick CRCA sheet on its front so
that all the Electrical components and accessories can be accessed only after opening of the front cover. After opening of the front cover, the panel shall have another hinged door made of min. 2 mm
thick CRCA sheet with necessary cut-outs for mounting the all Electrical components with
adequate clearances.
The Panel shall be suitable for Top / Bottom entries for incoming and outgoing Cables/Circuits. The
incoming Switchgear component shall have suitable provision for terminating a looping cable (of
max. 50 sq.mm size) for feeding to another Panel in the zone.
All the Panel wiring shall be carried out using 660/1100V grade FRLS insulated, flexible, multicore Copper conductors of reputed make and of rating considering the respective Isolator / MCB/ ELCB rating with all derating factors. (iii) The Switchgear components such as MCB, ELCBs, etc. shall be of 10KA breaking capacity with mid trip position for easy identification of the fault conditions. The components shall have shock proof and safe finger touch
terminals. The components shall have lower watt losses and shall have provision for mounting the additional accessories such as auxiliary blocks, shunt trip, etc.
iii) Lighting panels shall be suitable for 3 Phase, 4 Wire, 415/240 Volts as per the distribution schemes indicated in the relevant drawings.
iv) The lighting panels shall be completely dust and vermin proof, double door type and provided with neoprene gaskets and free of mechanical and electrical defects. The degree of protection for the panel enclosure shall be minimum IP 54.
v) Knockouts for branch circuit conduits or cables shall be provided on the top and bottom as required. vii) Tinned copper sockets shall be provided for the main connections to the panel.
vi) All panels shall be self-supporting, wall / steel structure mounting type unless otherwise specified in the schedule of quantities
vii) All the lighting panels shall be provided with two external Earthing terminals and suitable tinned copper lugs for connection to the Earthing system
viii) The neutral terminal block shall have sufficient number of terminals for all single-phase outgoing branch circuits.
ix) Means for easy identification of each and every branch circuit shall be provided. A Circuit Distribution diagram shall be pasted on the rear side of the front door of the panel for the easy reference.
x) Vendor shall furnish the GA drawings with supporting and connection arrangement and wiring diagrams
with the detailed bill of quantities, for the approval of Owner / Consultant, before
32. TRAIL RUN
Staff to be deployed by the contractor as follows On each tubewell – 3 no’s operator in three shift On each ZPS – 3 no’s operator in three shift and one electrician in general shift
Except electricity all other consumables have to be arranged and supplied by the contractor.