Top Banner
OFFICE OF SUPERINTENDING ENGINEER 15 TH CIRCLE UTTAR PRADESH JAL NIGAM, JHANSI E-TENDER FOR Construction of 6 Nos 300x200mm T.Ws by DC Rig machine & SITC of 15HP to 25HP Submersible Pumping Plants-8 Nos., Chlorinating Plant-14 Nos., V.T. Pumping Plants-3 Nos., Servo Voltage Stabilizer-06 Nos. and other E/M Works complete in all repects for Re- organization w/s scheme in Nagar Palika Parishad Orai (Zone 6) UNDER AMRUT PROGRAMME \ EARNEST MONEY: Rs. 1.96 lacs TENDER COST: Rs. 11,200.00 LAST DATE OF SUBMISSION OF E-TENDER : 09.07.2018 DATE OF OPENING OF TENDER: 10.07.2018 AT 03:00 PM SUPERINTENDING ENGINEER 15 TH CIRCLE, U.P. JAL NIGAM, JHANSI
109

E-TENDER FOR - AWS

May 03, 2023

Download

Documents

Khang Minh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: E-TENDER FOR - AWS

OFFICE OF SUPERINTENDING ENGINEER

15TH CIRCLE

UTTAR PRADESH JAL NIGAM, JHANSI

E-TENDER FOR

Construction of 6 Nos 300x200mm T.Ws by DC Rig machine & SITC of 15HP to 25HP Submersible Pumping Plants-8 Nos., Chlorinating Plant-14 Nos., V.T. Pumping Plants-3 Nos., Servo Voltage Stabilizer-06 Nos. and other E/M Works complete in all repects for Re- organization w/s scheme in Nagar Palika Parishad

Orai (Zone – 6) UNDER AMRUT PROGRAMME

\

EARNEST MONEY: Rs. 1.96 lacs

TENDER COST: Rs. 11,200.00

LAST DATE OF SUBMISSION OF E-TENDER : 09.07.2018

DATE OF OPENING OF TENDER: 10.07.2018 AT 03:00 PM

SUPERINTENDING

ENGINEER

15TH CIRCLE,

U.P. JAL NIGAM,

JHANSI

Page 2: E-TENDER FOR - AWS
Page 3: E-TENDER FOR - AWS
Page 4: E-TENDER FOR - AWS
Page 5: E-TENDER FOR - AWS

INSTRUCTION TO THE TENDERERS

Page 6: E-TENDER FOR - AWS

INSTRUCTION TO THE TENDERERS

1. The bid document is available online & digitally signed bids are to be submitted online

through e- procurement website http://etender.up.nic.in only. Bids submitted manually

will not be accepted. The bidders would be required to register in above website which is

free of cost. For submission of bids the bidders are required to have Digital Signature

Certificate from one of the authorized certifying agencies.

2. The cost of tender documents (non- refundable) Rs. 11,200.00 as applicable shall be

paid in the form of Demand Draft of any nationalized bank in favor of Executive

Engineer, Jhansi Division First, U.P Jal Nigam, Jhansi . Demand Draft should be

submitted in the office of E.E., Jhansi Division First , Jal Nigam Jhansi by 5.00 PM on day

before tender opening date i.e 09.07.2018. Copy of D.D shall be uploaded with tender.

3. The tender shall be accompanied with required earnest money duly pledged to The

Executive Engineer, Jhansi Division First, U.P Jal Nigam, Jhansi in the shape of

FDR/CDR of any nationalized bank only. FDR/CDR should be submitted in the office of

E.E., Jhansi Division First , Jal Nigam Jhansi by 5.00 PM on day before tender opening

date i.e 09.07.2018. Copy of EMD shall be uploaded with tender. The EMD shall be

valid for 180 days. Tenders without EMD or invalid EMD will be summarily rejected.

4. Tender is invited on two bid system i.e.

(i) Technical cum financial capability evaluation bid.

(ii) Financial bid.

5. The quantum of work may increase or decrease to any extent subject to availability of

funds. The date of pre-bid meeting shall be on 25-06-2018 at A.M. in the office of

Superintending Engineer ,15TH circle ,U.P. Jal Niagm, Jhansi. If the date of pre-bid meeting

becomes a holiday, the pre-bid meeting will be held on next working day.

6. The technical cum financial evaluation bids shall be opened on 10.07.2018 at 3.00 PM in

presence of bidders or their authorized representatives in the office of E.E., Jhansi Division

First , Jal Nigam Jhansi .

7. Financial bid of only those firms/ Contractors shall be opened who will be found eligible on

scrutiny of technical cum financial capacity evaluated bid. The date and time of opening of

financial bid shall be intimated separately. 8. If the date of opening of the tender documents becomes a holiday, the tender will be opened

on next working day.

9. U.P. Jal Nigam reserves the right to accept or reject any or all the bids without assigning any

reason thereof. So, further no any claim of applicant shall be considered in this regard. 10. The rates quoted in tender shall be valid for 120 days from the date of opening of financial

Bid. 11. The bidders are advised to inspect the site before quoting the rates.

12. For any queries bidders may connect Superintending Engineer,15TH Circle, U.P. Jal Nigam,

Jhansi on Mob. 9473942727 and Executive Engineer , Jhansi Division First ,U.P Jal

Nigam, Jhansi on Mob. 9473942728.

Page 7: E-TENDER FOR - AWS

13. The bidders have to upload following documents along with tender without which tender will

not be considered.

(i) Copy of EMD

(ii) Demand Draft for payment towards tender document cost.

(iii) Copies of ITR of last Three years.

(iv) Copy of Latest/Valid solvency certificate issued by District Magistrate/Nationalized

Bank.

(v) Performance certificate for completed work and progress report of ongoing work

attributed at least satisfactory remarks for the tube well constructed / pumping plant

supplied & installed by firm in last 5 years.

(vi) CA attested summery of balance sheet and profit and loss account from financial year

2015-16 to 2017-18

(vii) Copy of valid registration certificate in U.P. Jal Nigam in appropriate class and

category

(viii) Copy of PAN

(ix) List of staff and T&P on prescribed format given in tender document.

(x) Copy of GST registration certificate.

(xi) Copy of Labour Cess registration certificate

2.3 Security Deposit

2.3.1 A contract security of contract performance security equal to an amount of 10% (ten percent) of the

contract amount shall be paid by the successful tenderer on the award of work. This amount is to guarantee the faithful performance of the contract and execute the works as per terms and conditions,

specifications, drawings and other requirements for completing the works to the complete satisfaction

of the department.

2.3.2 The security deposit can be paid in any one of the forms as described for the EMD in clause 2.2.1 2.3.4 The security deposit is to be submitted within seven (7) days from the date of letter accepting the

tender.

2.3.5 The security deposit shall be pledged to the Executive Engineer, Jhansi Division First ,U.P. Jal

Nigam, Jhansi. 2.3.6 IF the successful tender fails to deposit the security deposit and execute the contract agreement his

EMD will be forfeited. The tenderer may be disqualified from further tendering of work of this

department. 2.4 Method of tendering

Tender shall be signed by an individual if tender is made by an individual or by a person holding the

power of attorney if tender is by a limited company or by all partners if tender is made of firmed

partnership giving current correspondence address. A certified copy of the power of attorney with

evidence of its currency shall accompany the tender in case the tender is signed by a person holding

attorney for signing the tender. 2.5 Witnesses and Dates 2.5.1 All witnesses and sureties shall be persons of status and probity and their full names, and current

correspondence address shall be stated below their signature. All signature shall be dated below the

signatures in all the tender.

Page 8: E-TENDER FOR - AWS

Preparation of Tenders

The tenderer is required to study carefully and well all the tender document and then only shall fill in

complete and submit the tender documents after obtaining all the clarification and clearing all doubts

if any in the tender documents.

Submission of tender shall be taken as evidence and confirmation that the tenderer has acknowledge

all the provision of the tender documents and has fully acquainted himself with conditions and all

factors which may influence the preparation, submission and satisfactory performance of the contract

agreement.

The tender shall be submitted in a complete form filling in all the information called for the prescribed

format only. All the blank formats included in the tender shall be filled in signed witnessed and dated

at the places provided for the same. Violation of the above requirement to submit all the required

information the tender may lead to disqualification of the tender.

No alteration shall be allowed in the tender anywhere in the tender documents once the tenders are

submitted.

It must be however clearly understood that the owner accept that the tenderer submit the tenders as

stated in the tender documents. Any deviation from the tender provisions are therefore discouraged

strongly. Such deviations particularly those involving financial implications, which make the

comparison of the various tenders difficult without further reference and correspondence with tenderer

is likely to be a cause of rejection of the tender. 2.6.6 Any tender containing vague and indefinite expression such as “subject to immediate acceptance” etc

shall not be considered. No condition shall be attached to the tender. Such conditional tenders will be

rejected.

2.6.7 Page shall be neither added not removed from the tender documents.

2.6.8 The quantities of the works indicated in the bill of quantities are not firm quantities but are only

approximate to give an idea to the tender about the various items of worked involved and their extent

of magnitude. However, the tenderer shall estimate his own quantities based on the drawing, and other

information given in the tender documents. Any changes in the quantities during actual execution

actually executed and indicated in the bill of quantities shall not entitle the contractor for any extra claims compensations etc. The tenderer has to complete the works as shown in the drawing issue

for the first time or subsequently revised/ordered/directed by the owner/engineer incharge during the

period of execution. Actual work will be measured and paid. 2.7 Validity period of Tender:

The tender shall be valid for a period of not less than 120 days after the date of opening of the tender.

There after the tenderer shall have an option of keeping his tender open if the owner request for such

extension.

2.8 Bidders must have Joint ventures for E/M works with E/M contractor & authorization Certificate

from Pump Manufactures/Distributor/Dealer and

2.9 An”Oath certificate” (against this tender) has to be produced on legal paper from the manufacturer/

Authorized Distributor/ Dealer of offered Pump to give an undertaking to provide complete technical support to the tenderer in supply, execution and maintenance to the authorized firm and also to

undertake that incase the firms fail to fulfil their commitment, manufacturer for Distributer/Dealer for

pump will own full responsibility to complete and maintain the project.

2.10 The Firm should submit characteristic curves & schedule ‘E’ of V.T./Submersible pump Individually

.

Page 9: E-TENDER FOR - AWS

2.11 Offered make of all equipment should be as per approved U.P. Jal Nigam make list and the offered

make of pumping plant should be mentioned in tender document.

2.12 No complaint of any tenderer will be entertained after opening of financial bid.

2.13 If any certificate may be found fake in verification, registration of the contractor will be

cancelled or the firm may also be black listed, the firm will give and undertaking on

"Legal Paper" that all the certificates submitted are true.

PHYSICAL EXPERIENCE FOR E/M WORKS

1- One similar completed works of at least 05 No. Tubewells Construction, 09 Nos.

SITC of Pumping Plant of minimum 25 H.P. and above

Or

2- Two similar completed works of at least 03 No. Tubewells Construction, 06 Nos.

SITC of Pumping Plant of minimum 15 H.P. and above

Or

3- Three similar completed works of at least 02 Nos. Tubewells Construction, 4

Nos. SITC of Pumping Plant of minimum 12.5 H.P. and above

4- Tender Documents should be properly filled & Duly signed by the bidder. Without it

tender will not be accepted.

QUALIFIED APPLICANTS :

U.P. Jal Nigam will decide which applicants are qualified and will inform them by E-MAIL

confirming in writing by registered/ speed post letter. Qualified contractors will be given an

invitation to participate in opening of Financial Bid of the tender at the appropriate time.

Page 10: E-TENDER FOR - AWS

GENERAL CONDITIONS OF CONTRACT

Page 11: E-TENDER FOR - AWS

OFFICE OF SUPERINTENDING ENGINEER , 15TH

CIRCLE

UTTAR PRADESH JAL NIGAM, JHANSI

1. DEFINITIONS AND ABBREVIATIONS:

1.1 DEFINITIONS: In this contract as hereinafter defined, the following words and expressions shall have the

meanings hereby assigned to them (expect where the context requires otherwise).

1.1.1 ‘OWNER’ MEANS U.P. JAL NIGAM.

1.1.2 Contractor means the person(s), firm or companies whose tender has been accepted by the Engineer and who has concluded a contract with the Engineer to execute the works included in

the tender and contract agreement. This includes the contractor’s personal representatives,

successors and assignees. 1.1.3 ‘Sub-Contractor’ means any person, firm or company other than the contractor named in the

contract for any part of the work, or any person to whom any of the works part of the works

included in the contract has been sublet with the consent in writing of the Engineer, and the sub-Contractors legal personal representatives, successors and permitted assignees.

1.1.4 Engineer/Engineer-in-Charge means the Executive Engineer, who has called for the tenders and

in charge of execution of the works and administration of the contract. The Engineer may assign

his duties to his sub-ordinates who assist in execution of works and administration of the contract. His subordinates shall be termed as Assistant Engineer/Junior Engineer in Charge as the case may

be. These sub-ordinates shall be Engineer representatives at the site of works. The Engineer

representatives will carry out such duties of the Engineer, like issuing of instructions, certificates and orders as are required in the execution of the works. Engineer’s representation will watch and

supervise the works, test and examine the materials, equipments, plant and machinery and

workmanship employed in connection with the works under the contract. The Engineer’s representatives with the approval of the Engineer will have the authority to relieve the contractor

of any of his obligations under the contract and to order any extra work involving delay in

completion of the works and also requiring any extra payment to the contract.

1.1.5 ‘Department’ means the Uttar Pradesh Jal Nigam, the words departments and Executive Engineer and his representatives have been used interchangeable at place and means the same i.e. the

Engineer or his representatives.

1.1.6 Consultant means a person who have formulated and designed the scheme, prepared the drawings, drawn the specifications and who act as advisers to the owner in all technical matter

and operation and maintenance of the work.

1.1.7 Work means all items of work to be constructed by the contractor, provision of rig machine

compressor and o.p. unit of required capacity for construction and handing over the tube wells. 1.1.8 Contract means promise to execute the work in accordance with the conditions of contract,

specifications drawings schedules, tender document, the letter of acceptance and the contract

agreement. 1.1.9 Drawing means the drawing referred to in the list of drawing attached to the tender and any

modifications of such drawings approved/issued in writing by the Engineer and such other

drawings as may from time to time be furnished or approved in drawing by the Engineer. 1.1.10 The contract sum means the sum identified in the contract for completion of works as per

contract.

1.1.11 Contract price means a portion of the contract sum adjusted to give effect to such additions or

deductions as are provided for in the contract which is properly apportionable to the plant in question having regard to the state, conditions, locations of the plant, the amount of work done

and all over relevant circumstances in the cost of executing the works.

1.1.12 Contractor’s equipment means all appliances or things of whatsoever nature required for the purpose of completing the works.

1.1.13 ‘Plant; means machinery, apparatus, materials, articles of intends to be provided under the

contract other than the contractor’s equipment.

1.1.14 ‘Portion of the work’ means a part of the work or section of work.

Page 12: E-TENDER FOR - AWS

1.1.15 ‘Section of the works’ means the sections into which the works are divided for the purposes described and set out in the specification.

1.1.16 ‘Specification’ and ‘Particular Specification’ means the relating guidelines contained in the

P.W.D. specification, Manual of Sewerage and Sewage Treatment, manual on water supply published by the Central Public Health and Environmental Engineering Organization (CPHEEO)

under the Ministry of Works and Housing, Indian standard specification and codes, all of latest

and those contained in the tender documents and also those on good Engineering practice. 1.1.17 ‘Month’ means 30 days.

1.1.18 ‘Day’ means calendar day.

1.1.19 Time for completion means the same time as stipulated for completion of the works or any

section or portion thereof as cited in the contract or as extended under clause and shall be calculated from the date specified in the contract. It will be the date when the contract is into

force of fulfillment of any obligation as per necessary legal financial or administrative

requirements.

1.1.20 ‘Defect liability Period’ means the period after actual completion of the work during which the

contractor will carry the liability to make good to the complete satisfaction of the Engineer, any

defects in the completed work or any bad work visible afterwards. 1.1.21 Cost means the amount which shall be deemed to include overhead costs incurred on or off the

sites, all taxes, excise duties royalties etc. as applicable on the materials, labour or any other item

is required to complete the works. 1.1.22 ABBREVIATIONS:

Abbreviations used in the tender documents or any other despondence will stand for the

full forms given as under:

Jal Nigam : Uttar Pradesh Jal Nigam

Level I : Chief Engineer, Level I

U.P. Jal Nigam, Lucknow

Chief Engineer : Chief Engineer,

U.P. Jal Nigam, Jhansi.

Superintending Engineer : Superintending Engineer,15TH Circle,

U.P. Jal Nigam, Jhansi.

Executive Engineer/Engineer. Incharge : Executive Engineer

Jhansi Division First

U.P. Jal Nigam, Jhansi

2 GENERAL CONDITIONS OF CONTRACT:

2.1 WORKS:

2.2 WORK OR WORKS:

Work or works where used in these conditions and specifications shall unless there be something either in the subject or context repugnant to such construction be constructed and taken to mean

work by virtue of the contract to be executed whether temporary or permanent and whether

original altered, substituted or additional.

2.3 WORKS NOT TO BE SUBLET WITHOUT SANCTION:

This contract or any part thereof shall not be assigned or sublet without the written approval of

the Engineer. If (1) the contractor shall assign or sublet his contract or attempt to do so or become insolvent or commence any insolvency proceeding or make any composition with his creditors, or

attempt to do so, or (2) if any bribe, gratuity, gift loan perquisite, reward of advantage, pecuniary

or otherwise, shall either directly or indirectly be given, promised or offered by the contractor or

any of his servants or agents to any public officer or person in the employee of U.P. Jal Nigam or in any way relating to such officer or person shall become in any way directly or indirectly

interested in the contract, the Engineer may notice in writing rescind the contract and the security

deposit shall thereupon stand forfeited and be absolutely at the disposal of the U.P. Jal Nigam, and the same consequence shall ensure as if the contract had been rescinded under clauses

Page 13: E-TENDER FOR - AWS

4.1.5.3. thereof and in addition the contractor shall not be entitled to recover or be paid for any

work that has already been performed under this contract.

2.4 SITE FACILITIES: The contractor shall at his own cost construct a site office for his own use and shed for materials.

He shall also dismantle the same after the works are complete, and arrange for site cleaning

operations by removal of soil and debris. If the contractor fails to dismantle the temporary structure after the works are completed it shall be treated as unauthorized occupation of the

owners land and necessary action as deemed fit under such circumstances shall be initiated for the

vacation of the land.

2.5 TIME FOR COMPLETION:

2.6 Contract Time: 12 Months

The time allowed for carrying out the works shall be as stated in notice Inviting Tenders of the

tender documents and shall be strictly observed by the contractor and shall be reckoned from the

date of the receipt of the written order to commence the works.

Thereafter a defect liability period of 12 (twelve) months after successfully running of

tubewell of the works will follow. During which the contractor shall remove all the defects

in the works, if any pointed by the operating staff.

2.7 FORCE MAJEUR:

Neither party shall be liable to the other for any loss or damage occasioned by or arising out of

acts of God, and in particular, unprecedented flood, volcanic eruption, earthquake or other convulsion of nature and other acts such as but not restricted to invasion, the act of foreign

countries, hostilities or warlike operation before or after declaration of war, rebellion, military or

usurped power which prevent performance of the contract and which could not have been

foreseen or avoided by a prudent person.

2.1.1.4 EXTENSION OF TIME:

If the contractor shall desire an extension of time for completion of the work on the ground of

unavoidable hindrance in its execution, he shall apply in writing, giving details of hindrance to the Superintending Engineer through the Engineer in Charge, within 7 days of the date of

occurrence of hindrances on account of which he desires such extension as aforesaid and the

Engineer shall authorized such extension of time, as may be reasonable in his opinion. If the work is suspended due to necessary and unavoidable reasons, the contract period shall be

accordingly amended but no compensation on this ground shall be permissible. For all

suspensions exceeding fifteen days ordered by the Engineer no rent of T&P if any shall be payable but the contractor shall be responsible for the safe custody of Nigam’s material and

T&P. No claim shall be entertained for the maintenance of any staff during such idle period or

for the disuse of his own T&P.The department shall however not be responsible for any

suspension of work occasioned by the contractor on his own account.

2.8 ENGINEER’S CERTIFICATE OF COMPLETION:

On completion of the work, the contractor shall be furnished with a certificate of such

completion by the Engineer but no such certificate shall be given nor shall the works be considered to be completed until the work shall have been measured up by the Engineer whose

measurement shall be binding and conclusive against the contract. The contractor shall have to

remove all scaffolding, surplus materials and rubbish and cleaned of all dirt and debris in upon

or about the premises of which he may have possession for the purpose of executing the said work. If the contractor fails to comply with the requirement of this clause as to removal of

scaffolding, surplus materials and rubbish and dispose of the same as he thinks fit and clean off

such dirt and debris as aforesaid, the contractor shall forthwith pay the amount of all expenses so incurred for any sum actually released by the sale thereof after deducting the aforesaid

expenses.

2.9 The Engineer shall within seven days issue the completion certificate on completion of above- mentioned measurement and cleaning of site. The date of certificate shall be taken as date of

completion of work.

Page 14: E-TENDER FOR - AWS

2.10 PAYMENTS:

i) Payment terms are given in schedule 'J' in mode and terms of payment. ii) Written guarantee shall also be submitted by the contractor regarding satisfactory

completion of work for a period of one year from the date of successful handing

over of work.

iii) The processing of payment may take minimum one month time from the date of

submission of bills for which no claim shall be admissible. 2.11 No compensation for the alteration in or reduction of work to be carried out shall be

permissible, if at any time after the commencement of the work the U.P. Jal Nigam, shall for

any reason whatsoever not require the whole thereof as specified in this contract to be carried out, the Engineer shall give notice in writing of the fact to the contractor and upon the receipt of

such notice in writing the works under this contract shall cease and the compensation

whatsoever on account of any profit of advantage, which he might have derived from the execution of the work in full, but which he did not derive in consequence of the full amount of

the works not having been carried out, neither shall he have any claim for compensation by

reason of any alternations having been made in the original specifications, drawings and

instructions which shall involve any curtailment of the work as originally contemplated.

2.12 ACTION AND COMPENSATION PAYABLE IN CASE OF BAD WORK

If it shall appear to the Engineer or his authorized representative that any work has been

executed with imperfect or unskilled workmanship or with materials of any inferior description or the material and equipment not new or that any materials or articles provided by the

contractor for the execution of the works are unsound or of inferior quality to that contracted

for or otherwise not in accordance with the contract, the contractor shall on demand in writing

from the Engineer, specifying the work, materials or the articles complained of forthwith rectify, remove and replace, demolish and reconstruct the work so specified in whole or in part

as the case may require, or as the case may be, remove the materials, or articles so specified and

provide other proper and suitable materials or articles at his own charge and cost. In the event of his failing to do so within a period to be specified by the Engineer, then the contractor shall

be liable to pay compensation at the rate of (1%) one percent on the amount of the estimated

cost of the whole work for every week not exceeding ten weeks while his failure to do so shall continue and in case of any such failure, the Engineer may rectify, remove, demolish and

reconstruct the works or remove and replace with others, the materials or articles complained

of, as the case may be, at risk and expense of the contractor in all respects and such expense

may be deducted from such sum as may be due to the contractor or may become due to him and from his security deposit. A certificate by the Engineer as to the amount of the expenses

incurred shall be final and binding upon the contractor.

In case the water of tube well is not found potable due to any reason than the

NO payment of drilling and development shall be done as per rules.

2.13 SUM PAYABLE BY WAY OF COMPENSATION:

All sums payable by way of compensation under any of these conditions shall be considered as reasonable compensation to be applied to the actual loss or damage sustained and whether or

not any damage shall have been sustained.

2.14 REVISION OF RATES:

No claim on account of revision of taxes, duties, labour and material rates, fuel, lubricants, plants/equipments or any other reason that can influence the rates quoted shall be entertained

when the contract is operative.

2.15 BILLS TO BE SUBMITTED ON PRESCRIBED FORM:

The contractor shall submit all bills on the prescribed forms to be had on application from the

office of the Engineer. The charges in the bill shall always be entered at the rates given in the

schedule of rates hereto attached or in the case of an extra work ordered in pursuance of these

condition and not mentioned or provided for in tender at the rates hereinafter to be agreed upon.

2.16 Payments shall be made at the quoted rates as far as items included in the price schedule. In

case of items not included in the price schedule agreed/approved rates shall be applicable.

Page 15: E-TENDER FOR - AWS

2.17 The measurement as shown in the drawings/revised drawings, duly approved for construction by Engineer-In-Charge instruction given in this regard, shall be measured and paid. Any

measurement in excess of those shown in the drawings fully executed or otherwise shall not be

entitled for payment.

2.18 RECEIPT OF AND POWER TO ADJUST SECURITY MONEY:

The U.P. Jal Nigam has received from the contractor the sum of 10% (ten percent) of the

tendered cost the receipt of which is hereby acknowledged. This is sum together with the sum made of the percentage described in clause 4.1.4. of this contract shall be held as security and

stipulations of this contract. The Engineer is empowered to deduct from time to time such

security money, all or sum or sums which may become due from the contractor as

compensation for the breach any or all the covenants or provisions of this contract. If not confiscated above under the provisions of this contract the security money or such balance

thereof as may be left after paying the deduction or deductions above mentioned will be

returned to the contractor 12 (twelve) months after the final certificate of the completion of the work shall have been given by the Engineer and after the Examiner/Engineer shall have

satisfied himself that all the terms of the contractor have been faithfully carried out by the

contractor.

2.19 Each tender must be accompanied with the deposit receipt of the earnest money which shall be

deposited in the shape as description for EMD in clause 2.2.1. Earnest money in other shape

shall not be accepted and tender is likely to be rejected on this account.

2.20 CONTRACTOR’S LIABILITY:

The work shall throughout the stipulated period of the contract be proceeded with all the due

diligence (time being agreed to be the essence of the contract) and the contractor shall pay as

compensation an amount equal to (one percent) 1% per day on contract price that the works remain uncommenced, or finished after the proper dates. Provide that always the entire

compensation to be paid under the provisions of this clause shall not exceed ten (10) percent of

the contract value.

2.21 OBSERVANCE OF LAWS, LOCAL REGULATIONS NOTICES AND ATTACHMENTS:

Contractor shall confirm to all the laws of the land, the relations and by-laws of any local

authority and or of any other or lighting companies with those whose systems the works are

proposed to be connected. He shall before making any variations the drawing or specifications that may be necessitated for so indicating, give to the Engineer written notice, specifying the

alteration proposed to be made and the reasons for making them and for instructions thereon. In

case the contractor shall not give such instructions within 7 days proceed with the work confirming to the provisions, regulations or by-laws in question of any variations in the

drawings or specifications so necessitated shall be dealt with under clause 4.1.8.2. The

contractor shall give all notice required by the said, acts relations or by-laws and pay all fees in

connections therewith. He shall also ensure that no attachments are made against works related to the contract. In every case referred to this clause, the contractor shall protect and indemnify

U.P. Jal Nigam against any claim or liabilities arising from or based on the violation of such

law, ordinance, regular decree or attachment by his employees.

2.22 Contractor liable for damage done and imperfections the contractor or his work people or

servants shall break, injure or destroy any part of a building in which they may be working or

any building, road defense, enclosure or grassland or cultivated ground continuous to the

premises on which the work or the part of it is being executed, or if any damage shall happen to the work while in progress from any cause whatsoever or any imperfections become apparent

in it within 12 (Twelve) months after the final certificate of its completion shall have been

given by the Engineer as aforesaid, contractor shall make the same good at his own expense

within reasonable time.

If the same to be made good by other workman and the expanse (of which the certificate of the

Engineer shall be final) from any sum that may be then or at any time thereafter will become due to the contractor or from his security deposit. Such rectification shall be guaranteed for six

months from the date of completion of the said rectification, if the rectification is carried out

after six months of completion period. The security deposit if necessary shall be extended to

cover up such period.

Page 16: E-TENDER FOR - AWS

2.23 BREACH OF CONTRACT: In any case in which under any clause or clause of these condition the contractor, shall have

rendered himself liable to any compensations amounting to the whole of the security deposit

whether deducted in one sum or deducted by installments the Engineer on behalf of the Department shall have power to adopt any of the following courses as he may deem just suited

to interest of Jal Nigam.

(a) To rescind the contract (of which rescission notice in writing given to the contractor under the hand of the Engineer shall be inclusive evidence), in which case the security deposit of the

contractor together with such sum or sums due to him under the contract(s) shall stand

forfeited and be absolutely at the disposal of the department.

(b) Terminate the contract and call in another contractor or employ locally labour to dismantle bad work if necessary (the bad work to be certified by the Engineer whose decision shall be final)

and to renew and complete the said works and pay the cost of such contractor for daily labour

and price of materials required for such dismantling, renewing and completion out of the said security deposit or such sum or sums as may be due to the contractor under his contract. If such

cost be more then the amount made up of the security money and the sum or sums due to the

contractor under this contract, the difference between it and the sum made up by the security money and the balance due to the contractor as aforesaid will be a debt due from the said

contractor to the Department.

In the event of either of the above courses being adopted by the Engineer, the contractor shall

have no claim to compensation for heavy loss sustained by him by reason of his having purchased or produced any materials, or entered into any agreements or made any advances or

account of or with a view to the execution of the work for the performance of the contract. In

case the contract shall be rescind under the provision aforesaid the contractor shall not be entitled to recover or be paid any sum for any work therefore actually performed under this

contract unless and until the Engineer shall have certified in writing the performance of such

work and the value payable in respect thereof, and he shall only be entitled to be paid the value

so certified.

2.24 NON-EXERCISE OF CONTRACTORS LIABILITY TO PAY COMPENSATION:

In any case in which any of the powers conferred upon the Engineer in clause 4.1.5.4. thereof

shall have become exercisable and the same shall have not been exercised, the non-exercise thereof shall not constitute a waiver of any of the conditions hereof and such power shall not

withstanding earlier non-exercisable, be exercisable in the event of any future case of default by

the contractor for which by any clause or clauses hereof he is declared liable to pay compensation amounting to the whole of his security deposit and the liability of the contractor

for past and future compensation shall remain unaffected. In the event of the Engineer putting

in force either of the powers (a) or (b) vested in him under the preceding clause, he may, if he

so desires take possession of all or any tools, plant, materials and stores in or upon the works or the site thereof belonging to the contractor, or procured by him and intended to be used for the

execution of the work or any part thereof paying or allowing for the same in account at

prevailing market rates, such rates to be certified by the Engineer whose certificates thereof shall be final. Otherwise the Engineer may issue notice in writing to the contractor or his other

authorized agents require him to remove such tools, plants, materials or stores from the

premises (within a time to be specified in such notice). In the amount of the contractor failing

to comply with any such requisition, the Engineer may remove them at the contractors expense or sell them by auction or private sale on account of the contractor and at his cost and risk in all

respects, and the certificate of the Engineer as to the Expenses of any such removal, and the

amount of the proceeds and expenses of any such sale shall be final and conclusive against the

contractors.

2.25 COMPENSATION TO WORKMEN:

The contractor on occurrence of accident, arising out of the work which result in serious injurious to the person or property, shall within 24 hours of such occurrence, report to the

Engineer, stating clearly and in sufficient details the facts and circumstance of the accident and

the action taken by the contractor. In all cases the contractor shall indemnify U.P. Jal Nigam,

against all losses or damages including directly or indirectly from contractor’s failure to give

notice under the workman’s compensation Act or otherwise.

Page 17: E-TENDER FOR - AWS

In every case in which by virtue of the provisions Jal Nigam be obliged to pay compensation to a workman employed by the contractor or by any sub-contractor from him in the execution of

the said work, Jal Nigam, will recover from the contractor the amount of the compensation so

paid. Without prejudice to the right of Jal Nigam, Jal Nigam shall be at liberty to recover such amount of any part thereof by deducting it either from the security deposit or his credit under

clause 3.4.9. of these conditions or from any other sum due by Jal Nigam to the contractor

whether under this contract or otherwise.

2.26 Jal Nigam shall not be bound to contest any claim made against it under section 12, sub-station

(1) of the workman’s compensation Act, except on the written request of the contractor and upon

his giving to Jal Nigam might become liable in consequence of consisting the claim.

2.27 CONTRACTOR DYING, BECOMING INSOLVENT OR IMPRISONED:

(a) In the event of the death, insanity or insolvency, imprisonment of the contractor or where

the contractor being a partnership of firm becomes dissolved or a corporation goes into

liquidation, the contractor may be terminated by notice in writing posted at the site of the works and advertised in one issue of the local newspaper and all acceptable, works shall be

paid for after recovering all the contractors dues to U.P. Jal Nigam there from at

appropriate rates to the person or person entitled to receive and give a discharge for the payment.

(b) If the contractor becomes bankrupt or has received order made against him or compound

with the creditor or being a corporation commence to be wound up not being a voluntary

winding up for the purpose only of amalgamation or reconstruction or carry on its business under a receiver for the benefit of the creditors or any of them, the U.P. Jal Nigam, shall be

at a liberty.

(c) To give such liquidation, receiver or other person, the option of carrying out the contract subject to his providing a guarantee for the due faithful performance of the contract upto

an amount to be determined by the U.P. Jal Nigam.

(d) To terminate the contract forthwith by notice in writing to the contractor or to the

liquidator or to any person in whom the contractor become vested and to act in the manner as provided in the clause Breach of contract.

2.9 CONTRACTOR TO SUPPLY LABOUR, PLANT, LADDER, SCAFFOLDING:

2.10 The contractor shall supply at his own cost all labour, (skilled and unskilled) and all things necessary (expect such specials things, if any, as in accordance with the specification supplied

from the Engineer’s stores) such as plants, tools appliances, implements, ladders, tackles, fuel,

oil, packing, derricks, boring tools etc. as well as all other apparatus and temporary works requisite for the proper execution of the work together original, altered or substituted and

whether included in the specifications or other document forming part of the contract or

referred to in these conditions or not which may be necessary for the purpose of satisfying or

complying, with the requirements of the Engineer as to any matter as to which under these conditions he is entitled to be satisfied, or which he is entitled to require, together with

carriage hereto for and from the work. The contractor shall also supply without charge the

requisite number of persons with the means and things necessary for those of setting out the works, and counting, weighing, and consisting in the measurement and examination at any

time and from time to time, of the works done, or materials supplied by him. The contractor

shall also provide at his own expenses all necessary fencing and lights required to protect the

public from accident and shall assume all the liability for and indemnify U.P. Jal Nigam against all actions or suits arising out of or connected neighboring owners or workman

employed on the works. While carrying the works, whether such actions are brought by

members of the public, the contractor shall carry out the works confirming to the statuary and other legal enactments applicable to them and give all notice and pay all fees payable to local

authorities and other in respect of them. The contractor shall be responsible for the adequacy,

strength and safety of all the working strutting, curbing, bonding, brickwork, masonry, contract permanent or temporary, appliances, matters and things furnished by him for the

purpose of this contract.

Page 18: E-TENDER FOR - AWS

2.11 MATERIALS AND PLANT OF CONTRACTOR: All materials brought by the contractor upon the site of the works shall be deemed to be the

property of U.P. Jal Nigam and shall not on any account be removed from the site of the works

during the execution of the works and shall at all times be open to the inspection of the Engineer. The Engineer on the completion of the works or upon the stoppage of the works as

provided in clause 4.1.4.2. of this contract shall have an option of taking over any such unused

material at prevailing market rates, with the provision that the price allowed to the contractor shall not exceed the amount originally paid by him for the same, as he (the Engineer) shall

desire upon giving a notice in writing under his signature and within(15) fifteen days of the

completion of the works to that effect, and all materials not so taken over by the Engineer shall

cease to be the property of U.P. Jal Nigam and the contractor shall have no claim for compensation on account of any such material as aforesaid which are not so taken over by the

said Engineer unused by him ( the contractor) or for any wastage in or damage to any such

materials.

EMPLOYMENT OF AN EXPERIENCED SITE ENGINEER:

The contractor shall employ a site Engineer of the rank of a Resident Engineer who is well

experienced in the type of the works, he has to handle and shall be well acquainted with all latest Indian standards, codes of practice, local practice of construction and has good

managerial qualities, capable of handling labour force tactfully and extract good quality of

workmanship and plan execution of works efficiently. He shall be conversant with

specification, construction equipment use, testing, inspecting and supervising the works. He

shall have good ability to guide his subordinates and shall be time conscious.

The contractor shall employ work agents and such foreman as may be necessary for the

execution of the works to ensure proper and efficient control.

EXPERIENCE OF THE LABOUR FORCE:

The contractor shall employ in his pay-roll only such workers who are experienced in the trade

or job for which they have been employed. The Engineer shall have full powers to direct the

contractor to remove and engaging on work persons who do not have any experience in the trade and whose work is not satisfactory. If in the opinion of the Engineer a person is found to

be incompetent, such person shall be replaced by an experienced one to the satisfaction of the

Engineer.

Permission in writing should be taken from the Engineer in order to work on Sundays, holidays,

nights and to work after time. No women labour should be engaged on works during night.

CONDUCT OF LABOUR: The contractor is solely responsible for the peaceful and orderly conduct of labour in the

neighborhood of work site. The Engineer in charge shall have full powers to order the

contractor to prevent undesirable labour force from entering the work site. Further the Engineer

has full power to ask the contractor to remove from the site of works any person who

misconducts at site.

LABOUR WELFARE:

Facilities for welfare of the labour shall be provided by the contractor at his own cost as per the

existing labour laws.

The contractor shall make all arrangements for supply of a drinking, bathing and washing water

to the labour, at his own expenses.

Adequate first aid and medical facilities shall be provided. Proper, separate toilet facilities for men and women shall be provided.

Protective accessories like helmet, gumboots, gloves, goggles as found necessary, shall be

provided to the labourers.

CAUTION LIGHTS:

Contractor shall provide caution signs/lights near excavations, trenches, fencing etc. and

employ watchmen during night and off working days and hours.

SAFETY OF WORKERS:

Contractor shall ensure that all precautions are taken to avoid accidents by providing

scaffolding, platforms, etc. of adequate strengths, which can safely take the loads by properly

Page 19: E-TENDER FOR - AWS

bracing, tying and storing as necessary. No extra costs shall be claimed for all above safety

works.

The contractor shall provide at his own cost, all safety equipments to the labours, children’s

and cattles like barbed wire fencing barricades, temporary crossing, etc. around the tube well site to prevent accidental slips, falls, injuries etc.

The contractor shall make his own arrangements for conveyance of materials and labour to the

work site by making, if necessary, any temporary paths, roads, access etc. at his own cost.

DRAWING AND SPECIFICATIONS:

WORKS TO BE EXECUTED IN ACCORDANCE WITH THE SPECIFICATION:

The contractor shall execute the whole and every part of the work in the most substantial and

workman like manner both as regards material and otherwise in every respect in strict accordance with the specification. The contractor shall also confirm exactly, fully and faithfully

to the drawings and instructions in writing relating to the work assigned by the Engineer.

ALTERATION IN SPECIFICATION OR DRAWINGS: The Engineer shall have powers, to make any alteration in or any additions to, the original

specifications, drawings and instructions that may appear to him to be necessary or advisable

during the progress of the works. The contractor shall be bound to carry out of the work in

accordance with any instructions which may be given to him in writing signed by the Engineer and such alteration shall not invalidate this contract. Any additional work, which the contractor

may be directed to do in the manner above specified, as part of the work shall be carried out by

the contractor on the same conditions in all respects on which he is awarded to do the main work. The time for the completion of the work shall be extended if applied for by the contractor

in writing in the proportion that the additional works as to the original contract work. The

certificate of the Engineer shall be conclusive as to such extension. And if the altered works

include any class of work for which no rate is provided in this contract then such class of work shall be corrected out at rates to be agreed upon in writing between the Engineer and the

contractor prior to the work being taken in hand.

Basis for fixing such rates shall ordinary be the current U.P. Jal Nigam schedule of rates for the district provided, if the contractor shall commence work or insure any expenditure in regard

there to, the rates shall have been remained as before mentioned. He shall only be entitled in

respect of the work carried out or expenditure incurred prior to the date of the determination of the rates as aforesaid according to such rate or rates as shall be fixed by the Engineer. In the

event a dispute, the decision of the General Manager shall be final.

In the additional or altered work for which no rates is entered in contract or in the U.P. Jal

Nigam schedule of the rates of the district, is ordered to be carried out before the rates are agreed upon, then the contractor shall, within seven days of the receipt of the order, carry out

such works as he may consider advisable. However the work is to be carried out according to

design, drawings and specification recommended by the contractor and alteration above

referred shall be within and specification appended to the tender.

ACTION WHERE NO SPECIFICATION:

In the case of any class of work of which there is no mention of specification, such work shall

be carried out in accordance with the instructions and requirements of the Engineer.

DEVIATIONS FROM DRAWINGS AND SPECIFICATIONS:

Deviations or changes shall not be made by the contractor himself without the prior approval of

the Engineer, from the dimension, sizes, material or workmanship, specifications of works

shown in the drawings, specifications, instructions issued on same by the Engineer or his

authorized representatives. All the sizes shall be executed strictly according to the drawings,

and specifications using best quality of raw and finished materials, best workmanship to the

complete satisfaction of the Engineer.

COPIES OF SUPPLY ORDERS AND OTHER LITERATURE OF ARTICLES

PRODUCED FROM THE TRADE:

Page 20: E-TENDER FOR - AWS

Copies of supply orders and other literature of articles procured in the trade shall be furnished to the Engineer. The technical literature, dimensional and material specifications, guarantees of

materials procured from the trade along with operation, maintenance and installation manuals

also should be submitted to Engineer in triplicate.

DRAWINGS AND SCHEDULES:

Drawings showing workshop fabrications etc. shall be submitted in advance and approval shall

be obtained before commencement of orders from the Engineer or his authorized representatives. However, the approval shall not resolve the contractor from the responsibility

of the performance of the plant.

WORKMANSHIP:

Civil, electrical, and mechanical works included in the tender shall be properly coordinated so that work is completed in time in a complete manner, and handed over in a perfect

workmanship manner in good working condition and to the complete satisfaction of the

Engineer.

ENGINEER’S RIGHTS IN CASE OF USE OF INFERIOR MATERIALS,

WORKMANSHIP AND PLANT:

Engineer during the course of execution of the work shall have absolute powers hereunder to

order the following in writing from time to time regarding the quality of the work.

The discontinuance of the use of inferior quality of materials which do not confirm to the

specifications and removal of the rejected material from the site of works forthwith.

Stoppage of improper, inferior and unsuitable plant used for construction, stoppage of inferior workman-ship, improper construction methods, etc.

The re-execution of dismantled/rejected work(s) using fresh materials, labour, plant according

to the specification laid down in the contract shall be started by the contractor. In case the contractor fails to execute the orders, the Engineer shall have powers to get the defective work

rectified/re-constructed/replaced by another agency and all the expenses on account of same

shall be charged to the contractor and shall be recovered from payments due to him or from

payments to become due to him.

SETTING OUT OF WORKS:

The contractor is responsible for setting out the works as indicated in the drawings and

instructions given in this regard and to obtain the approval of the same from the Engineer or his authorized representative before commencing the works. The contractor shall provide, free of

cost, all facilities like labour, instruments, etc. and all cooperation to the Engineer to check all

dimensions, alignment level etc. This shall however not dissolve the contractor of his own

responsibility of maintaining the accuracy of work.

INSPECTION, TESTING AND MISCELLANEOUS:

ACCESS TO THE WORK:

The Engineer in charge or his authorized representative and consultants of the Engineer shall be provided with all facilities to access to the site of works, fabrication shops, stores of materials,

labour camps, testing shops and other premises connected with the execution of works in any

way all time, for inspection, supervision, examination of all related works.

GUARANTEES:

Not withstanding the detailed drawings supplied and specifications given in the tender, the

contractor can not claim any relief from his responsibility towards the performance of

mechanical and electrical equipment and the whole functioning of the works for which it is intended. The contractor is deemed to posses the above knowledge absolutely, before tendering

without any ambiguities or doubts which, if any, may be got clarified from the Engineer and

then only submit his tender.

POWER AND WATER REQUIRED FOR CONSTRUCTION/TESTING:

Contractor shall make their own arrangements for power and water required for execution and

testing of works at their own cost and the rates quoted shall be deemed to include all such expenditure. The above required for testing shall also be the contractor’s responsibility. If

possible, water and power shall be supplied only at one point by the department for which the

amount will be recovered at the prevailing rates.

Page 21: E-TENDER FOR - AWS

DEWATERING AND EXTRA WORK IN FOUNDATIONS: Dewatering of foundation, trenches etc. shall not be paid extra over and above the rates quoted

and the rates quoted shall be deemed to be inclusive of the above items of work. Shoring and

strutting work required for excavation, excavation in difficult conditions of soil shall not be

paid extra except in case to be paid as indicated on the bill of quantities.

AS BUILT DRAWINGS:

On completion of the works, before issuing of the completion certificate by the Engineer, the

contractor shall submit 3 sets of drawings.

SITE CLEARANCE:

No extra money will be payable to the contractor for removal of stubs, debris, rubbish, moulds

of earth or any such unevenness in their ground levels before commencement of the works. Similarly, he will remove from site above said materials and spoil such surplus materials as

directed by the Engineer and leave the site in a condition that is acceptable to the Engineer as

far as cleanliness of work site is concerned without any additional payment. His rates shall be

deemed to include all expenditure.

Except with prior permission in writing of the Engineer, the contractor shall not divert his plant

labour, materials to any other work. In granting such permission the Engineer may impose any conditions as may be found necessary to ensure that no delays or interruption are caused in

execution of the works under the contract. The contractor shall not be entitled to any

compensation resulting from such delays. Granting such permission shall not resolve the

contractor from the responsibility of completing the works as per time schedule specified in the contract.

MAKING AVAILABLE DRAWINGS AND DOCUMENTS AT SITE:

One set of drawings and all other documents relating to the works under contract shall be kept in the site office and made readily available for discussion, examination of the Engineer or his

representatives.

WORKS TO BE OPEN TO INSPECTION:

All works under or in course of execution or executed in pursuance to this contract shall at all times be open to the inspection of the Engineer and his authorized representative. The

contractor shall at times during the usual working hours and at all other once of which

reasonable notice of the intention of the Engineer or his authorized representatives to visit the works shall have given to the contractor, either himself be present to receive instruction or have

a responsible agent present for that purpose. Orders given to the contractor’s agent shall be

considered to have the same force as they have been given to the contractor himself. Verbal orders shall not be considered as binding on either party until they are confirmed in writing and

signed by the Engineer.

NOTICE TO BE GIVEN WORK IS COVERED UP:

The contractor shall give not less than five days in advance notice in writing to the Engineer, or his duly authorized representatives of the work before covering up, or otherwise going beyond

the reach of measurement any work, in order that same may be measured, and correct

dimensions thereof be taken before the same is so covered up of placed beyond the reach the measurement any work without the consent in writing of the Engineer or his duly authorized

representative if any work shall be covered up or placed beyond the reach of measurement

without such notice having been given or consent detained, the same shall be uncovered at the

contractors expanses. In default thereof no payments or allowance shall be made for such work

or the materials with which the same was executed.

WORKS TO BE UNDER DIRECTION OF ENGINEER:

All works to be executed under the contract shall be executed under the direction and subject to the approval in all respect of Engineer who shall be entitled to direct at point or points and in

what manner they are to be commenced from time to time.

DECISION OF THE CHIEF ENGINEER: Except where otherwise specified on this contract, the decision of the Chief Engineer for the

time being shall be final conclusive and binding on parties to the contract upon all questions

relating to the meaning of the specifications drawings and instructions therein before mentioned

and to the quality of workmanship and materials used on the work or as to any other question,

Page 22: E-TENDER FOR - AWS

claim, might matter of things, whatsoever in any way arising out of or relating to the contract drawings, specifications, estimates, instructions, orders or these conditions or otherwise

concerning the works or the execution or failure, to execute the same, whether arising during

the progress of the work or after the completion or the sooner determination thereof of the

contract.

TAKING OVER OF THE TUBEWELL:

Following final inspection and when the Engineer is satisfied that the entire works have been completely constructed, erected, tested, and only when all specified test certificates, are

supplied, the Engineer will issue a taking over certificate. Until such certificate is issued, the

contractor shall be responsible for making good any damage occasioned to the tubewell.

FACILITIES TO BE PROVIDED BY THE CONTRACTOR:

1) The contractor will make his own arrangement for all his communication needs such as

telephone; telex etc. at his office and his residential area. Owner will assist the contractor in

getting the above facilities, in case of difficulties.

2) The areas where equipment might drip oil and cause damage to the floor surface, a suitable

protective cover of a flame resistance, oil proof sheet shall be provided to protect the floor from

such damage.

CONSTRUCTION/MANAGEMENT

This is the essence of the contractor and the contractor shall be responsible for performance of

his works in accordance with the specified construction schedule. If at any time the contractor

is falling behind the schedule he shall take necessary action to make good for such delays by increasing his work force or by working over time. The contractor shall not be allowed any

extra compensation for such action.

CONTRACTOR’S CO-OPERATION WITH THE OWNER:

In case where the performance of the erection work by the contractor affects the operation of

the system facilities of the owner, such erection work of the contractor shall be scheduled to be

performance only in the manner stipulated by the purchaser and the same shall be acceptable at

all these to the contractor. The purchaser may impose such restrictions on the facilities provided to the contractor such as electrically, water etc. as he may think it in the interest of the owner

and the contractor shall strictly adhere to such restrictions and co-operate with the purchaser. It

will be the responsibility of the contractor to provide all necessary temporary instrumentation and other measuring devices required during start up and operation of the equipment system

which are erected by him. The contractor shall also be responsible for flushing and initial filling

of all the oil and lubricants required for the equipment furnished and erected by him so as to make such equipment ready for operation. The contractor shall be responsible for satisfactory

operation of the equipment.

The vendor attention is invited to the specific clause, about delay hold up due to other agencies

work affecting time to erection, testing, commissioning.

CO-OPERATION WITH OTHER CONTRACTORS AND CONSULTING PURCHASER: The contractor shall agree to co-operate with the owner’s other contractors and consulting

purchasers and freely exchange with them such technical information as is necessary to obtain

the most efficient and economical design and to avoid unnecessary duplication of efforts. The

contractor shall attend design coordination meetings at his own cost when ever required.

FIELD OFFICE RECORDS:

The contractor shall maintain at his site office upto date copies of all drawings, specifications longbooks and other contact documents and any supplementary data complete with all latest

revisions thereto.

Page 23: E-TENDER FOR - AWS

DESIGN CO-ORDINATION:

The contractor shall be responsible for the selection and design of appropriate equipments to

provide the best coordinated performance of the entire system. All the rotating components

shall be so selected that the natural frequency of the complete unit is not critical or close to the

operating range of this unit.

QUALITY ASSURANCE PROGRAMME:

To ensure that the equipments and services under the scope of this contract whether manufactured or performed within the contractors works or at his sub-contractors premises or at

the owner’s site or at any other place of work are in accordance with the specifications. The

contractor shall adopt suitable quality assurance programme to control such activities at all

point necessary. Such programme shall be outlined by the contractor and shall be finally accepted by the purchaser after discussions before the award of contract, and such agreed

programme shall form a part of the contract.

DEFECTS IN WORKS OF OTHER CONTRACTORS: The purchaser shall be notified promptly by the contractor of any defects in the other

contractor’s work that could affect the contractors work.

The purchaser shall determined the corrective measures if any, required to rectify this situation after inspection of the works and such decisions by the purchaser shall be binding on the

contractor.

UNFAVORABLE WORKING CONDITIONS:

The contractor shall confine all the field operations to those works which can be performed without subjecting the equipment and materials to adverse effects, during inclement weather

conditions, like monsoon, storms, etc. and during other unfavorable construction conditions

will in no way relieve the contractor of his responsibility to perform the works as per the

schedule.

PROTECTIVE GUARDS:

Suitable guards shall be provided for protection of personal on all exposed rotating and/or

moving machine parts.

PROGRAMME OF WORKS:

As soon as the letter of indent is issued to the contractor, he will submit to the Engineer his

programme to complete the works by the time indicated in the contract, in the form of a bar chart for review of the Engineer and make suggested modifications before his approval of the

same. The approved bar chart shall be diligently and strictly followed with a view to complete,

the works as per schedule. The programme of work shall be reviewed from time to time by the Engineer and he may modify the same depending upon the exigencies of the work and stage of

the works.

INSURANCE:

The contractor, shall unless otherwise specified by the purchaser, insure the plant and shall keep it insured against destruction or damage by fire, earthquake, flood storm under exposure

to the weather or through riot , civil emotion, war or materials until the plant is taken over.

The insurance for the equipment shall cover the risks towards handling transit, storage at site, re transporting up to the place of erection, testing and commissioning of the equipment at site. The

contractor shall take the policy in the name of the consignee of the department. The insurance

policy then will be assigned to the contractor for further operation. The insurance shall be full

and shall cover any loss or damage in accordance with what is said above. The damage materials will be set right or replaced by the contractor, free of cost. The claims arising out of

the composite insurance policy shall be dealt with or handled by the contractor at his own cost

after receipt of preliminary damage/loss intimation given by the Engineer.

PATENTS, RIGHTS ETC.:

The contractor shall fully indemnity the purchaser against all actions, suits, claims demands,

costs, charges and expenses arising from, or incurred by reason from any infringement for any letters, patent designs, trademark or name, copyright or other protected rights in respect of any

Page 24: E-TENDER FOR - AWS

machine of using, fixing, working or arrangement used or fixed or supplied by the contractor but his indemnity shall not extend or apply to any action, suit, claim demand cost charges or

expenses arising from or incurred by reason of the use of the works or any part thereof

otherwise than in the manner or for a purpose contemplated by the contract. All royalties and other similar payments which may have to be paid for the use of any such machine, plant,

work, material thing, system or method as aforesaid (whether payable in one sum or by

installments or otherwise) shall be covered by the contract price and payable by the contractor.

In the event of any claim or demand being made or action or suit through against the purchaser

in respect of any such matter or matters as aforesaid the contractor shall be duly notified

thereof, and he shall conduct all negotiations for the settlement of such claims or demands and

such action or suit shall also be conducted by him, if and as far as the owner shall think proper,

to the supervision and control of the owner through the officer duly authorized in his behalf.

OTHER CONTRACTORS:

When two or more contractors are engaged on work in the same vicinity, they shall work together in a spirit of cooperation and accommodation. The contractor shall not take or cause to

be taken any steps or actions that may cause disruptions, discontent or disturbance to the works,

labour and other arrangements of other contract in neighboring and the project localities. In case of any difficulty among the contractors, the Engineer shall direct the manner in which each

contractor shall conduct his work so for as it affect others.

DISCREPANCIES AND ADJUSTMENT OF ERRORS:

The several documents forming the contract are to be taken as mutually explanatory of one another, detailed drawings being followed in preference to small scale drawings and the figured

dimensions in preference to scale.

If there are varying or conflicting provisions made in any document forming provisions made in any document forming part of the contractor the accepting officer i.e. the General Manager

shall be the sole deciding authority with regard to the intension of the document and his

decision in this respect shall be final and binding.

Any error in description in the bill of quantities of any omission therefore shall not vitiate the contract or release the contractor from the execution of the whole or any parts of the drawings

and specifications or from any of obligation under the contract.

If there are discrepancies found in the tender documents and the same have not been clarified before submission of the tender, the interpretation or clarification given by the Engineer is final

and conclusive.

Any disputes or differences whatsoever will shall at any time in between the parties hereto touching or concerning the works under the execution or maintenance thereof or this contract or the

construction, execution or maintenance thereof or the construction meaning operation or effect

thereof, or to the rights and liabilities of the parties or arising out of or in relation thereto whether

before or after determination, for closure or breach of the contract (other than those in respect of which, the decision of any person is by the contract expressed to be final and binding) shall after

written notice by either party to the contract to the other of them specify the nature of such dispute

and difference and call for the point or points at issue to be referred to the arbitration.

ARBITRATION SHALL BE EFFECTED:

By an arbitrator agreed upon by the parties or failing agreement upon such an arbitrator.

By an Arbitrator appointed by the President of the Institute of Engineers (India) or failing such

appointment.

By an arbitrator appointed by the Chief Engineer, U.P. Jal Nigam or failing such appointment.

By an arbitrator appointed in accordance, with the provisions of the Indian arbitration act,

which law governs the contract.

The arbitrator so appointed shall be a person presently connected with the organization for

which and by which the work is executed.

Premises to arbitration shall be a deemed to be a submission to arbitration within the meaning

of the Indian arbitration act, which law governs the contract.

Page 25: E-TENDER FOR - AWS

If the arbitrator so appointed is unable or unwilling to act or resigns his appointment or vacates his office due to any reason whatsoever another sole arbitrator shall be appointed as aforesaid.

Work under the contract shall, if reasonably be possible, true during the arbitration proceeding

and no payment due or payable to the contractor for other works than under arbitration will be

withheld on account of such proceeding.

Arbitration shall be deemed to have entered on the reference on date he issues notice to both the

parties fixing the date of first hearing.

Arbitration may, from time to time with the consent of the parties, enlarge the time for making

and publishing the award.

Arbitrator shall give a separate award in respect of each difference referred to him.

Place of arbitration shall be within the limits of Jhansi.

Fees, if any, of the arbitrator shall, if required to be paid are the award is made and published,

be paid half and half by both of the parties. The cost of the reference and of the award including

the fees, if any, of the arbitrator shall be in the discretion of the arbitrator who may direct to and by whom and in the manner, such cost or any part thereof be paid and may fix or title the

amount of cost to be paid.

Any disputes in the matter of the contract are subject to jurisdiction of appropriate court at

Jhansi.

--------------------------------

Witness Signature

Name----------------------------------------

Address-------------------------------------

-----------------------------------------------

------------------------------------------------

--------------------------------

Signature of Contractor

Name----------------------------------------

Address-------------------------------------

-----------------------------------------------

------------------------------------------------

Page 26: E-TENDER FOR - AWS
Page 27: E-TENDER FOR - AWS
Page 28: E-TENDER FOR - AWS

FORM OF TENDERER

(To be filled and signed, witnessed and submitted by the tenderer)

From : ………………………..

………………………..

……………………….. ………………………..

To,

The Executive Engineer, Jhansi Division Ist,

U.P. Jal Nigam, Jhansi.

1. I/We ………………………..………………………..……………………….. have read the various

conditions governing the contract attached hereto, studied the specifications, possess the knowledge of site

conditions, availability of materials and labour. I/We offer to do the work of Tube well Construction As

per laid down specification/drawings and abide by the conditions. I/We also agree to keep this offer valid

up to 180 days from the date of receipt/opening of tenders whichever is later.

2. I/We agree to complete the works within 06 months from the date of issue of letter of intent.

3. A sum of Rs 1,96,000.00 towards Earnest Money in the form of ……………………

……………………….. drawn on ………………………….………..………………………..Bank

…………………………………..dated………………………..………………………...……………………

…..pledged in the name of ………………………..…………………valid for …….. days.

4. The full value of earnest money shall stand forfeited without prejudice to any other rights or remedies if.

a) I/We do not execute the contract documents within Fifteen (15) days from the date of issue of letter of

intent.

b) I/We do not complete the work within 18 months after receipt of order as to that effect.

5. Until a formal agreement is prepared and executed acceptance of this tender shall constitute a binding

contract between us subject to modifications, as may be mutually agreed to between us and as indicated in

the letter of acceptance of my/our offer for this work.

6. All tender documents/drawings duly signed are returned herewith along with a declaration as specified.

Yours Faithfully

Date Name ……………………….…..

Address…………………………

………………………………….. …………………………………..

…………………………………..

1. ……………………………….. 2. ………………………………..

(Signature of Witness) (Signature of Witness)

Address ………………………… Address.………………………… …………………………………...

…………………………………... …………………………………...

…………………………………... …………………………………... …………………………………... …………………………………...

Page 29: E-TENDER FOR - AWS

MANUFACTURERS AUTHORIZATION FORM

No.___________________________________ Date: _______________________

To,

_________________________

_________________________

_________________________

Dear Sir,

We ________________________________ who are established and reputable manufacturers of

________________________having factories at ______________________ do hereby authorize M/s

contract with you against NIT No……………………………………………………….for the above

goods manufactured by us.

We hereby extend our full guarantee and warranty as per clause of the General

Conditions of Contract for the goods offered for supply against this invitation for bid by the above

firm.

Yours faithfully,

(Name)

For and Behalf of M/s

(Name of Manufacturers)

Note: This letter of authority should be on the letter head of the manufacturing concern and should be

signed by a person competent and having the power of attorney to bind the manufacturer.

Page 30: E-TENDER FOR - AWS

ANNEXURE – F

LIST OF TOOL AND PLANT AND EQUIPMENT HELD AND PROPOSED

TO BE USED ON THE WORKS.

Sl. No. Name and Capacity of the plant No. Held No. to be used at site Remarks

Place……………………………………

Date……………………………………

Signature……………………………

Name………………………………..

Address……………………………..

………………………………………

Page 31: E-TENDER FOR - AWS

ANNEXURE – G

LIST OF WORKS IN HAND AND THEIR POSITION PRESENTLY REGARDING

TIME OF THEIR COMPLETION

Sl. No. Name of work Client Amount of work Rs.

(Lacs)

Anticipated date of

completion

Place……………………………………

Date……………………………………

Signature……………………………

Name………………………………..

Address……………………………..

………………………………………

Page 32: E-TENDER FOR - AWS

ANNEXURE – H

STATEMENT SHOWING WORKS OF SIMILAR NATURE EXECUTED

BY THE TENDERER

Sl. No. Name and work For whom

executed

Amount of work Year of

execution

Remarks

Note: Performance certificate of the executed works of government engineering department are to be

submitted. The certificate should have been issued by an official of the rank not less than

Executive Engineer.

Place……………………………………

Date……………………………………

Signature……………………………

Name………………………………..

Address……………………………..

………………………………………

Page 33: E-TENDER FOR - AWS

ANNEXURE – I

DETAILS OF REGISTRATION

Departments Particulars

Reg. No. Date of Reg. Class of Reg. Reg. Valid upto

1. CPWD

2. Railways

3. MES

4. UP PWD

5. UP Jal Nigam

6. Others

Place……………………………………

Date……………………………………

Signature……………………………

Name………………………………..

Address……………………………..

………………………………………

Page 34: E-TENDER FOR - AWS

ANNEXURE – J

FINANCIAL STATUS

Sl. No. Particulars Remarks

1. Name………………………….

2. Adress…………………………

………………………………...

3. Total Liabilities Rs…………………………

4. Total Assets Rs…………………………

5. Current Liabilities Rs…………………………

6. Bank over draft Rs…………………………

7. Net work Rs…………………………

8. Liquid assets Rs…………………………

9. Outstanding Stock Rs…………………………

10. Current assets Rs…………………………

11. Bank reference Attach Separately

12. Solvency amount Rs…………………………

13. Annual turnover for last three years

(Give separately for each year supported

by balance sheet)

Rs…………………………

14. Bonding capacity Rs…………………………

15. Bondable Capacity Rs…………………………

16. Value of contracts for which firm would tender Rs…………………………

Note: All the above data shall be as of 30 days prior to the date of submission.

Place……………………………………

Date……………………………………

Signature……………………………

Name………………………………..

Address……………………………..

………………………………………

Seal of Company

Page 35: E-TENDER FOR - AWS

ANNEXURE – K

STATEMENT OF TECHNICAL PERSONNEL AND TRADESMEN HELD ON ROLL

(As On Date of Submission Of Application)

Name of Contractor……………………….

Address …………………………………..

……………………………………………

……………………………………………

S.No.

Particulars

Post No. Experience

Years

Remarks

Graduate Engineers

Engineer (Diploma holders)

Junior Engineers

Supervision/Forman

Fitters

Electrician

Skilled Labour

Unskilled Labour

Place……………………………………

Date……………………………………

Signature……………………………

Name………………………………..

Address……………………………..

………………………………………

Page 36: E-TENDER FOR - AWS

SCHEDULE ‘A’

(Purpose)

These Tube Wells are to be constructed at the sites under Zone-6 Orai Reorganization W/S

Scheme, Distt Jalaun. The site of Tube Well or Tube wells shall be shown to contractor or his agent before

starting the work. The advantage of maximum yield from the strata met will be taken

consequently as soon as the boring is completed the contractor shall submit drawing as

per schedule ‘C’ together with samples of strata for approval and the tube well shall not

be put in until the approval of the Engineer or his representative has been obtained and

officially communicated to the contractor.

The contractor should clearly understand that he will have to make his own

arrangements for the T&P and other accessories that may be required for boring purposes.

The contractor shall be deemed to have carefully inspected the site to find what

obstructions are there in the way of rapid progress as to include in his rates sufficient

margin cover the cost of removing them. The rates in schedule ‘G’ will be all inclusive.

No claim for any compensation in any shape arising out of such difficulties shall be

entertained.

The contractor so strongly advises to consult strata chart of boring done in the

vicinity of the place. A few strata chart may available in the office of the Engineer. But

those can only be taken as guide and no claim shall be entertained on the ground that

strata actually met differs from the show on these charts.

Time is the essence of this contract. No request for extension of time will be

entertained unless the Engineer finds the delay was unavoidable

SITC of pumping plants is to be done at different Tubewells and ZPS constructed under

Zone-6 Orai Reorganization W/S Scheme, Distt Jalaun.

Bidder has to be prior to starting the work and should have comprehensible approach to

complete the work with his own arrangement for the T&P and other accessories required for

successful completion of the work. It is presumed that bidders have visited and examined the

site conditions to curb the difficulties / obstructions likely to be arisen while completing the

work. it is also presumed that rates quoted by the bidders have sufficient margin to overcome

the cost of unforeseen expenses and running errands in course of the work completion. The

rates in schedule ‘G’ will be inclusive of such expenses having no counts to asked for extra

payment or compensation and therefore, no claim for any compensation in any shape arisen

out of such difficulties shall be entertain. Time is the essence of this contract. No request for

extension of time will be entertained unless the Engineer finds the delay is not due to

procrastination.

Page 37: E-TENDER FOR - AWS

SCHEDULE ‘B’

(List of plans accompanying the tender)

NIL

SCHEDULE ‘C’

(List of the drawings to be provided by the contractor to the Engineer during the course

of contract) 1. Boring charted as per format provide by Engineer. 2. Proposed Tube Well assembly chart for Engineer’s approval. 3. Manual of O&M for pumping plant, switch gear materials etc. are to be provided the

site in charge.

SCHEDULE ‘D’

(List of samples to be submitted by the contractor to the Engineer during the course of contract)

The contractor shall deliver following samples. Either at the site of work or at the office as

desired by the Engineer.

i. Sample of strata met with during boring. ii. Any other samples if required by the Engineer

SCHEDULE ‘E’ List of Test to be conducted

For Tubewell

1. Yield test and test for measurement of sand contents. 2. Any other test as decided by Engineer.

Note:- Yield test shall be conducted through V-Notch or circular orifice meter or any other

method approved by the Engineer.

For Pumping Plant

Schedule É’ has to be provided in terms of discharge (Q)- head (H) & efficiency of pump

and motor from the selected characteristic curve of model and make of the pumping plant.

Signature of Contractor

Dated : …….................

Page 38: E-TENDER FOR - AWS

SCHEDULE ‘F’

(Completion Period)

Period for completion of the work as specified shall be taken up by the

bidders or their representatives under the guidance of the site in charge which

shall be carried out to the satisfaction of the site in charge in terms of quantity &

quality of the work and therefore, onus lies on the bidder to carry out the work

under the guidance and control of site in charge. However, responsibility shall not

ceases until the defect liability period is expired.

The Completion period shall be Scheduled as under:-

1 The Completion period for Total work included in

contract 12

Month

2 The Completion period for each Tube Well from the

availability of the Pin Point 45

DAY

Page 39: E-TENDER FOR - AWS

SCHEDULE ‘J’

(Terms and Procedures of Payment) The following shall be the breakup for the running payments of Execution of

Reorganization of Water Supply Scheme on the basis of schedule “G”

S.No Description of item Performance level of works % of payment allowed

on the basis of

performance

1

Construction of deep

Tubwell of desired depth

and discharge, Drilling,

Supply and lowering of

Tubewell Assembly etc

complete, Development of

Tubewell by compressor

and O.P Unit

Supply & delivery of T/w

assembly with accesorries

complete in all respect

Completion of boring &

Lowering of Tubewell

Assembly complete with

housing, Plain/slotted pipe,

reducer, Bail plug, M.S

Clamp, well cap, M.S ring

etc

50%

Development of Tubewell

by compressor and O.P

Unit,

30%

Testing and commissioning

10%

Completion of 3 months

trial run

10%

2

Supply and installation of

submersible clear water

pumping

plant/Cholorinating

Plant/Voltage stabilizer/

Internal & External

electrification of Pump

house

On supply & delivery of

materials

50%

On installation Testing and

commissioning

30%

After successful completion

of 3 months trial run

10%

After successful completion

defect liability period of 18/

24 months

10%

Page 40: E-TENDER FOR - AWS

I/We have read understood and accept for compliance, the above

mentioned instructions and conditions of this schedule and have taken factors in to

account while quoting rates in schedule 'G'.

Signature .................................................

Name of Contractor ...............................

Address...................................................

3

Supply installation testing and

commissioning of 100 KVA

Sub-Station

On supply & delivery of

materials

50%

On installation Testing and

commissioning

30%

After successful completion of

3 months trial run

10%

After successful completion

defect liability period of 24

months

10%

Page 41: E-TENDER FOR - AWS

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR

TUBEWELL CONSTRUCTION 1. CONTRACT INCLUDES:

1.1 Supply & erection of all required tools plants (T&P,) for drilling of necessary bore of required size as

detailed in BOQ, lowering of well tubes together with all excavation, pumping, all temporary masonry

work, channels for samples, dressing & cleaning of site & reinstatement.

1.2 Supply & erection of all required T& P for development of Tube Well.

1.3 Supply & erection of all temporary and auxiliary plants such as derricks, hoists, etc. and other

appliance required for the work.

1.4 Supply of all lubricants and oils, cotton and other material required during the drilling,

developing and testing operations.

1.5 Supply of bentonite and sticky clay if required to line up the bore.

2. TRANSPORTATION:

This includes transportation of drilling and developing equipment like rig, compressor, O.P. unit

with all required auxiliary T&P and material to proposed site including carting loading,

unloading etc. complete work. 3. DRILLING:

3.1 This includes installation of rig machine, drilling of bore well, up to required Depth for

successful construction of tube well in full satisfaction of Engineer in charge, including supply

of all required material like bentonite, sticky clay and Ferrow speed electro rod/ ISI mark etc.

and also make provision for water arrangement for drilling at their own expenses.

4. LOGGING:

4.1 After completing the bore well, its logging will be within the scope of the contractor which shall

be done by the departmental/U.P. Jal Nigam approved loggers on their own cost.

4.2 No compensation shall be paid to the contractor on account of any delay in electric logging of

bore well.

4.3 The Contractor shall maintain the bore hole up to logging or lowering with shrouding is

complete in all respect.

5. TUBE WELL ASSEMBLY AND ITS LOWERING:

5.1 Tube well assembly will be supplied by the Contractor. MSERW Pipe to be used should strictly

Confirm to IS 4270:2001 after dispatch of MSERW Pipes contractor has to arrange inspection at

manufacture fection 5.2 All the associated accessories as mentioned in detailed specification, of tube well Assembly, will

be supplied by the contractor.

5.3 The contractor shall prepare the tube well assembly as approved by the Engineer in advance and shall arrange the same in proper sequence at site. He shall get the same checked and passed by the Engineer or his authorized representative. There after the assembly shall be painted with standard quality anti-corrosive paint.

5.4 Before lowering the tube well assembly the contractor shall ensure that the bore hole is clear up to the

required depth and shall get it checked by the Engineer or his authorized representative.

5.5 The lowering of tube well assembly carried out by contractor. 5.6 The welding Job Work of tube well Assembly parts to give sufficient strength to the assembly will be done

by the contractor at the time of lowering, in the presence of the Engineer or his authorized

Page 42: E-TENDER FOR - AWS

Representative. The contractor shall ensure that lowering of assembly takes place smoothly, &

entire responsibility for that shall be on the contractor.

5.7 As soon as the lowering is complete, the contractor shall take the sounding of the lowered tube well

assembly to the Engineer or his authorized representative. In case the complete sounding of tube well

assembly is not found then it will be entire responsibility of the contractor. 6. PEA GRAVEL AND ITS SHROUNDING :

6.1 The gravel packing shall be done by a suitable method approved by the Engineer or his authorized representative.

6.2 The packing of gravel in the annular space between the well pipe and the bore shall start at the

bottom of the well and extend upwards to the ground level.

7. DEVELOPMENT:

7.1 The development of the tube well shall be done first by the proper size & capacity air

Compressor, after that it shall be done by O.P. Unit of Suitable capacity.

7.2 During development by air compressor as soon as the pea-gravel is not sinking during back

blowing in annular space between the bore and tube well assembly water becomes clears &

starting sand content are between 3000 To 4000 ppm it will be assumed that there is no need of

further development by air compressor provided that there is no bridging This shall be decided

by engineer In charge or his representative white testing.

7.3 The development of the tube well by O.P. Unit shall be done by suitable capacity O.P. Unit till

the water level and discharge becomes steady and sand content within tolerable limits.

7.4 The Engineer has sole right of deciding, development of T/W done by department unites also or

by other agencies in case of work getting delayed. If development of tube well will be done with

the help of departmental Units then it will be in supervision of contractor at their risk, the

responsibility for construction of successful tube well be on contractor.

8. LIMITS OF CONTRACT:

The work included in this contract shall be deemed to be complete finally when all the

specifications set up herein and conditions of contract attached have been completed with and

tube well having been successfully tested and handed over to the Nigam.

9. DESIGN, MATERIAL AND WORKMANSHIP:

The specification as set for the execution of the various parts are to be followed. Any

suggestions with a view to effect the economy or to increase reliability in operation which the

tender may wish to offer must be set forth in the schedule as addendum for consideration.

10. RESPONSIBILITIES OF CONTRACTOR:

10.1 The contractor shall maintain Chaukidar at his own cost to watch T&P and also provide

material for protection of work if necessary. He shall arrange for storing of T&P and materials

for accommodation of supervising staff engaged on the work by him. The contractor shall also

arrange his own supplies of water, fuel etc. for the use of his workman and also for the execution

of the work.

10.2 Until the test specified herein have been applied and the installation have been passed

and formally accepted by the Engineer the contractor shall be entirely responsible for the

working or performance, whether such working as for the propose of testing or in the service of

Nigam.

Page 43: E-TENDER FOR - AWS

10.3 As each part of the construction of the tube well is completed, it shall be checked over

by the Engineer or his authorized representative. The representative of contractor shall ascertain

with the Engineer’s representative from time to time, what parts he wished to check over and

pass but such passing shall be no way relieve the contractor from his responsibility, until the

entire work has been completed according to the contract and taken over by the Engineer.

10.4 Contractor shall take all safety measures at site. He shall arrange first aid box at site. in

the event of any accident, he should make arrangement for primary & higher medical facilities

to labour engage by him. Jal Nigam shall not bear any liability about accident at site. The entire

liabilities about first aid, higher medical facilities and compensation if arises have to be borne by

the contractor.

10.5 The contractor shall submit daily report of the work done by him each day to the

Engineer on the prescribed format to be obtained from the Engineer. These reports shall be

handed over to the Engineer’s representative stationed at site or/also posted to the Engineer (in

case there is no representative stationed at site) every day after close of the day. Postage changes

for the same shall be borne by the contractor.

10.6 Work done of any kind to the designated site for the construction of Tube Well or any

other material such as fuel etc consumed by the contractor shall not be paid out in case of failure

of tube well however contractor can retrieve them. 11. TESTS:

During the progress of the work and after its completion the contractor shall carry out such tests, as

in the opinion of the Engineer are necessary to insure that the installation compile with the conditions

of these specification whether under test conditions or in ordinary working. All pipe connections and other apparatus required for the tests shall be provided by the

contractor at his own cost.

12. REINSTATEMENT:

After completion of work the contractor shall remove all surplus material and dresses the ground

disturbed during the operation of the excavation boring and construction of the well to the

satisfaction of the Engineer.

13. VERTICALITY: 13.1 The formal test is not required due to proposed Pumping Plant is of submersible type, although

constructed tube well should be vertical and having clear cylindrical space within the housing

pipe to accommodating the O.P. Unit for development of Tube Well and also submersible

Pumping Plant of requisite capacity with its proper installation and working. 13.2 If the housing pipe is so much non-vertical that it could not accommodate a submersible pumping

plant of requisite capacity with its proper working up to desired depth then the tube well will be

rejected outright, and all expenditure if any done by department on tube well should be recovered

from contractor. If there is any dispute in this regard the final decision authority will be chief

Engineer (E&M) and whose decision shall be binding to contractor.

14. YIELD TEST:

The official yield test shall be conducted by department as per departmental norms, but all

arrangements for that shall be provided by contractor on his own cost.

Page 44: E-TENDER FOR - AWS

15. COMPLETION AND HANDING OVER OF TUBE WELL: 15.1 After giving the official test as above, the contractor shall give sounding of the tube well to the

Engineer or his authorized representative. In case the complete sounding is not found and it is

observed that sand is plugged more than half the length of the bail plug, than it will be

responsibility of the contractor to clear the tube well at his own cost and risk. 15.2 Just after giving the sounding and accepted by the Engineer or his authorized representative, the

contractor shall cap the tube well duly welded.

16. PRESERVATION OF EXCAVATED MATERIAL:

As the boring work of Tube Well proceeds, the contractor shall keep carefully notes of all changes of

strata after every 3 meters or earlier whenever the strata change and keep its measurement from

ground level and shall preserve a sample of soil taken from every strata, each sample must be atleast

200 c.c. by volume and must be carefully preserved and marked with the depth and range from which

it was taken in transparent packages. The contractor shall also maintain at the site, the boring chart

showing daily progress of the work, nature of soil passed through each day and the thickness of each

strata and others. The strata samples shall be handed over to the Engineer.

17. SITES FOR TUBE WELL: 17.1 The site of tube well shall be shown to the contractor or his authorized representative before

starting the work. 17.2 The contractor is strongly advised to consult strata chart of boring done in vicinity of the place.

The strata chart available in the office may be seen but these can be only taken as guide. No

claims shall be entertained differs from that shown on those charts.

18. FAILURE OF TUBE WELL:

If the tube well fails due to bad workman ship/accident or any other reason on account of

contractor, except that non availability of suitable strata, the department will not make any

payment to the contractor for that T/W and if any expenditure done by department on that tube

well will be recovered from the contractor’s Security Money Deposit/payments out standing in

this division or any other divisions in Jal Nigam.

Page 45: E-TENDER FOR - AWS

Technical / Terms & Conditions for Construction of Tube well by DC Rig Machine in

Distt. Jalaun

1. Cost are to be quoted for Six Numbers Tube well’s as per BOQ.

2. Required Tube well assembly shall be supplied by contractor should confirm to IS-4270:2001. Technical

specification and other data of pipes shall be as per relevant IS or their latest revision. Bidden has to

submit QAP after quard of contract.

3. Quantities given in BOQ are approximate and average and may vary upto any extent as tube

wells are proposed to be constructed in the range up to 110 meter depth.

4. Contractor has to arrange adequate continuous clear water supply required during drilling and cost of the

same should be included in the rates tendered for construction of the tube well is must.

5. The rates shall include the collection and preservation of strata samples taken at every three meters

depth and where ever the strata changes, supplying the boring/strata chart immediately after

completion of drilling and supplying lowering chart to the deptt. and got approved before lowering

and the contactor shall submit finally tube well completion chart.

6. Pea gravel shall be supplied from LAL KUAN quarry (Haldwani, Uttranchal) which shall be

thoroughly washed, graded, screened and stacked properly at site, 5% of quantity shall be

deducted against bulk age/voids from measured quantity of pea gravel.

7. Yield test of tube well shall be carried out in accordance with IS-2800 (part II) and detailed

specifications given in tender form. In case of any deviation suitable action shall be taken as per

CB or decision taken by the competent authority regarding the acceptance of tube well which

shall be final and binding.

8. It is sole responsibility of the contractor to prepare lowering assembly based on the actual strata

encountered matching with logging report ant then get it duly approved by the Engineer In

charge there after the lowering work will be started by the contractor.

9. The income tax, work contract tax, labours cess. as applicable at the time of payment, shall be

deducted at source as per Govt. rules, hence rates should be quoted accordingly.

10. The contractor shall be paid 100% of quoted rates after construction, development and testing of

tube well. If required, approach path upto the pin point given would be constructed by the

contractor and if any hindrance encountered in making approach path the same will be resolved

by the contractor at his own cost. Any damage/loss to public or Govt. properties will be born by

the contractor.

11. Site clearance/leveling of site will be done by the contractor after completion of TW construction.

12. The contractor will have to take all preventive measures with the help support of site in charge to

ensure that Tube well construction site is not exposed to risk of accident to the passers by,

residents of the neighborhood or children etc. Until the Tube well construction is complete in all

respect. Failing which, contractor in person is liable for prosecution as per law of the land in

case of any accident or loss to life and property. After the successful completion of the tube well

all the activities pertinent to safety measures shall be carried forward by the Deptt.

13. Contractor or drilling agency shall be sole responsible for any injury or damage to Tube well

assembly while drilling lowering and development works caused by in proper handling of the

machine or any gadget or equipment or machine failure. In event of loss to property of the

Deptt. shall be recovered from the contractor.

Page 46: E-TENDER FOR - AWS

14. Drilling agency shall be sole responsible for any accident due to their negligence, apathetic/

sluggish attitude and shall pay out compensation to the party inflicting any injury or loss to life

and property.

15. Engineer in charge is not responsible for acquiring and providing legal and physical possession

of the site other than the getting the construction of the tube well is complete at the pin points

according to the choice and selection of the concerning authority.

16. Argument or dis argument or spat with site in charge at site or in office with any officers shall be

treated as misconduct amounting to cancellation of the contract bond.

17. While transportation of the Rig Machine to the pin point, approach road shall be made by the

Deptt. if it is deemed necessary.

18. During development of tube well, disposal of discharged water in general specified by the site in

charge will be made by the contractor at their own cost. Unless otherwise unfavorable

circumstances

19. After completion of work all pits would be leveled and cleared, excess earth shall be removed

from the site by the contractor.

20. Carting of tube well assembly from divisional store to pin point of tube well will be done by

contractor on his own cost.

21. Contractor have to provide a vehicle for supervision purpose to the executing staff during the

completion period of tubewell construction as per the directions of the engineer, failing which

the department shall arrange for the same on the cost of contractor as per the approved

departmental rates.

22. The contractor must have experience of construction of such type of TWs & the certificate must

be attached along with other documents. The contractor has to arrange the following machine /

T&P in good running condition for construction of tube wells.

(i) Rig machine - D.C. Rig machine 675/600 or as required as per Schedule “G” above with

all its accessories, T&P, welding plant etc.

(ii) Compressor- 250 PSI compressor with all T&P & accessories

(iii) OP Unit- 3 cusec capacity with all T&P & accessories.

23. Flexibility of the contractors. 23.1 This contract provide a certain number of tube wells for construction as per NIT. But the contractor

may be called upon to construct further number of tube wells under this contract as it may be

necessary as per direction as directed by the competent authority.

24. From the date of availability of pin point the contractor has to complete the construction of

tubewell within 45 days otherwise penalty will be imposed as per directions of engineer in

charge if it deems that the delay is from the part of contractor.

Page 47: E-TENDER FOR - AWS

Construction of Tubewells Detailed Specification

1. Tube well assembly:

300 mm dia housing pipe , 200mm dia plain/slotted pipe of Tubewell assembly will be supplied

by the contractor. Should confirm to IS 4270:2001

1. Tubewell Accessories : (Supplied by the contractor)

(a) Well Cap :- Well cap made out from 100x10 mm M.S. flat, 5mm thick top sheet with a

handle on top suitable for M.S. Housing pipe 300 mm dia.

(b) Housing Pipe Clamp :- Housing pipe clamp made out from 100x16 mm M.S. flat with

500 mm long arm on both ends having drilled hole and fastened by means of 4 Nos. ½”

dia 6” long, nut bolt & washer suitable for clamp 300 mm dia M.S. pipe.

(c) M.S. Ring 300 mm dia :- Ring made up of 150x12 mm M.S. flat suitable for M.S. Pipe the

ring has to be tapered with ‘V’ groove at both ends and seat in between, suitable for 300 mm

dia.

(d) M.S. Ring 200 mm dia :- Ring made up of 150x12 mm M.S. flat suitable for M.S. Pipe

The ring has to be tapered with ‘V’ groove at both ends and seat in between, suitable for

200 mm dia.

(e) M.S. Reducer: - Reducer made up of 12 mm thick M.S. flat having total length of 350

mm and upper & lower ring of 100 mm wide suitable for 300x200 mm. Size.

(f) Bail Plug: - Bail plug made out from 100x12 mm flat with ‘U’ Hook of 20 mm dia M.S.

rod 300 mm high, bolted at bottom of bail plug suitable for 200 mm dia M.S. pipe.

(g) Centre Guide: - Centre guide made out from 25x5 mm M.S. flat 300 mm long suitable

for 200 mm dia pipe.

(h) MS Fabricated Tubewell support:- Tubewell support made up of 200x100 mm size MS

girder having 2.5m long and in H shape as per departmental design.

2. Gravel Packing:

Gravel packing shall be done by suitable method approved by the Engineer or his authorized

representative. The placing of the gravel in the annular space between the well pipe and the hole

shall start at the bottom of the well and extend upward to ground level. The construction of the gravel

filter once started will be continuous operation until it is finished.

The following specifications are to be followed for supply of Pea Gravel for Tubewell.

1. The Gravel has to be supplied from Lalkuan, Query Haldwani and conforming to IS 4097-1967

and as latest amendments.

2. The average particle size of Gravel shall be 1.6 to 4.8mm. 3. The Gravel shall consist of hard quartz (about 96% SiO2) or other suitable material, with an average

specific gravity of not less than 2.5. Not more than 10% by weight of the material shall

Page 48: E-TENDER FOR - AWS

have a specific gravity of less than 2.25. The Gravel shall contain not more than 2% by weight

of thin flat or elongated

pieces. In case of such pieces, the larger dimensions shall not be more than 3 times the smallest

dimensions. The quartz shall be of sub rounded to rounded grains with minimum angular features.

4. The Gravel shall be free from impurities, such as shale, mica, feldspar, clay, sand, dirt, loam

hematite and organic materials.

5. The particle size distribution of Gravel may be Determine by screening through standard sieve

accordance with IS: 460. 6. The gravel shall have a hardness of not less than 5 in Moh’s scale.

7. Voids @ 5% shall be deducted from quantities measured at site.

8. Any tax, Royalty shall be included in the offered rates.

3. Development by Air Compressor:

The tube well shall be developed either by surging, including washing and agitation by air compressor or by over pumping and back washing with or without an air lift. The development of tube well by air compressor process shall be continued until The tubewell ceases to absorb further gravel. The depression ceases to improve. The discharge ceases to improve. The water is reasonably sand free.

The analysis of sand content will be carried out by the contractor as per written instruction by the Engineer. The sounding of T/W will be taken after development by air compressor and OP unit.

The contractor shall over develop so as to yield a discharge 20% in excess of the rated

discharge or to depress the well to 50% higher than the nominal depression at which the tube well

is pumped on continuous duty which ever may be more.

The discharge during development shall be measured at minimum intervals of 6 hours over

a V-Notch weir or by other suitable method may be accepted and record kept as previously

provided. The development will continue till no further feeding of gravel is found necessary and

the discharge is free of sand within the requirement of specifications.

The discharge shall be sand free i.e. sand contents will be less than 10 ppm in the

final

discharge of the tube well obtained after 05 minutes of starting and clear/traces within 10 minutes.

The discharge of tubewell shall be measured by means of water meter or orifice meter or

rectangular V-notch chamber constructed according to ISS such that the full size discharge from

the outlet pipe the plumb will fall into the first compartment of V-notch chamber. In order enable

Page 49: E-TENDER FOR - AWS

the collection of water in a bucket for measuring the sand contents of water a bib cock shall be

provided in the delivery pipe away from the discharge outlet. The contractor will also provide

necessary measuring jars.

The yield of the tube well will be carried out as under:-

Firstly, the discharge of the tube well will be increased in stages at an interval of one

hour and relevant readings at each stage will be recorded by checking these readings. The most

suitable discharge will be selected and the tube well will be run for about 6 hours and the

readings of depression and discharge will taken after every half an hour for ensuring the figure

of discharge and depression remain steady during the entire period of test. The specified

discharge of the tube-well shall be obtained at a depression not exceeding 20 ft. Thereafter the

recoupment test of the tubewell will be conducted by noting the readings of recumbent of water

level in the housing pipe by noting the depth of water level from the top of the housing pipe after

suitable intervals/ Cleaning of water after stopping pumping.

4. Abandonment of Tubewell:

During construction it may be required to abandon the tubewell due to negligence of the working

staff of the contractor, in such case no payment of the executed work will be made to the contractor.

If during drilling very hard rock or boulders or uncontrollable caving strata is met and also if due to

any natural reason i.e. connecting the well with any nearby natural well and it is not possible to drill

further or no strata is met, payment of the actual depth drilled will be made. However the contractor

for at least 48 hours in case of hard rock, try to penetrate it in presence of the Engineer in-charge for

24 hours and if the progress is less than 1 feet in 24 hours and sufficient strata has not been met to

yield required discharge, the bore may be declared as abandoned and payment of actual work

executed will be made.

5. Quality of Water:

In the construction of the tubewell, due precautions shall be taken by the drilling agency to

maintain the premises in a sanitary condition and to avoid as much as practical, the entrance of

contaminated water into the safe water bearing formations, any water or materials used shall be

free of contamination and, if their nature permits, should be adequately disinfected with chlorine

before use. The slush pit should be constructed so that no material there from will enter the well,

except mud reused when the construction is by rotary method. In such cases the slush pit and

mud return channels should be protected against contamination from surface water or any other

sources.

The well shall be disinfected after completion of test for yield. All the exterior parts of

the pump coming in contract with the water shall be thoroughly cleaned and dusted with

powdered chlorine compound.

Page 50: E-TENDER FOR - AWS

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR SITC

OF TUBEWELL PUMPING PLANT 1. SUBMERSIBLE PUMP SET: (Should confirm to IS 8034:2002)

Submersible pumping set suitable for 300 mm dia or 200 mm dia T/W Bore fitted with dynamically

balance bronze or SS impellers mounted on a stainless steel pump shaft with shaft protection sleeves

having stage bowls of closed grained cast iron. The pump will be fitted with built in non-return valve

and shall be suitable for direct coupling to the squirrel cage electric induction, water cooled type

submersible motor suitable to operate on 400 ± 10% V, 3 phase, 50 cycles/sec. A.C. Power Supply

and 2900 rpm (nominal) speed and capable to give a discharge and head as is mentioned in NIT.

Other specifications shall be as per following:

1.1.1 PUMP SET: 1.1.2 A Standard hydrostatic test on all pressure containing parts shall be made at 1.5 times the

maximum discharge pressure. 1.1.3 The bowls shall be equipped with replaceable casing bearing. 1.1.4 The bowl assembly shall bear a name plate preferably embossed information as per following:

a) Name of the manufacturer or trade mark. b) Serial number of the pump set. c) Pump type. d) Number of stages. e) Total head. f) Shut off head. g) Capacity.

Note: Shut off head must be above 25% of the total head required. 1.1.5 The impeller shall be of enclosed type equipped with seal rings on their hubs. Seal rings shall be

provided either with impeller or in the bowl. 1.1.6 The pump shaft shall be guided by bearing provided in each bowl of above and below the impeller shaft

assembly. The shaft without sleeves shall have a surface finish 0.75 micron Ra Max.

1.1.7 The opening in the suction case for the entrance of water shall be of proper size and shape to

avoid eddy currents. 1.1.8 The suction case shall be fitted with a strainer made of corrosion resistant material. 1.1.9 Suitable sand guard shall be provided just above the suction case bearing to prevent the entry of

foreign matter into the suction case. 1.1.10 Non return valve shall be provided above the pump discharge case.

1.2 SUBMERSIBLE MOTOR: (Should confirm to IS 9283:1995) 1.2.1 The submersible motor shall be squirrel cage induction motor. 1.2.2 The winding of motor shall be wet type. 1.2.3 The motor shall be suitable for operation voltages and frequency confirming to IS 585-1962

(revised) “Voltages and frequency for A.C. transmission and distribution system” 1.2.4 The earthing of the motor shall comply with IS: 3043-1966 code of practice for earthing.

Page 51: E-TENDER FOR - AWS

1.2.5 The Thrust bearing shall be of adequate size to withstand the weight of all rotating parts as well

as the imposed hydraulic thrust. These shall be lubricated suitably. 1.2.6 The Motor winding and nearing bushes of the rotor shaft shall be cooled/lubricated by pure

water filled in the motor before erecting the pump set. 1.2.7 The motor shall be protected by means of cable glands, rubber seals etc. from ingress of tubewell

water, sand and other foreign matter. 1.2.8 The thrust bearing housing shall be provided with a drain plug to empty the pure water filled into

the thrust bearing housing/Motor. 1.2.9 The rotor shaft in copper strip shall be provided with shaft protecting sleeves having a surface

finish of 0.75 micron Ra max. 1.2.10 The Motor shall be provided with a breathing attachment like bellows, diaphragm etc. to

compensate the Volumetric variations due to change in temperature. 1.2.11 The motor shall be made of corrosion resistant materials or suitably treated materials to resist

corrosion. 1.2.12 The motor shall have a name plate preferably embossed on body of motor giving the following

information :

a) Induction Motor;

b) Name of Manufacturer;

c) Manufacturer’s number and frame reference;

d) Type of duty;

e) Frequency in Hz;

f) Number of Phases;

g) Rated output in HP/KW;

h) Rated voltage and winding connections;

i) Current in amperes at rated output.

j) Speed in RPM at rated output.

1.3 DATA OF PUMP SET:

a) Model of motor.

b) Model of pump.

c) Discharge in LPM.

d) Total head.

e) Nett effective head.

f) Number of stages.

g) Pump outlet size in mm.

h) O.D. of pump in mm.

h) MOC of each and every component of the pump set.

i) Speed of pump set.

Page 52: E-TENDER FOR - AWS

j) Method of starting.

The performance details as per enclosed schedule ‘E’ are to be submitted as per enclosed sheet

separately.

1.5 TESTING OF PLANT:

The contractor shall do preliminary testing at manufacture’s works which Shall be witnessed by

department and at site and through testing of the plant during the course of erection and when it is

completed as specified and for official testing of the same in accordance with schedule ‘E’. The electric

motor and pump may be type tested at the manufacturer’s works. Pump sets will be tested at manufacturer

works or at site of the SICT as per schedule ‘E’ uploaded by the contractor and as per IS:8034. Other

material/accessories will be checked as per relevant ISS. Test certificate of the pump set concluded at

works of the manufacturer is obligatory to be furnished with characteristic curve stipulating the discharge,

head or pump efficiency etc that it could ensure duties of the pump set is well suited to need of the

pumping system.

1.5.1 TEST DUTIES AND EFFICIENCIES:

The contractor shall state in the tables attached with tender documents the efficiencies and duties of

the pumping plants when working at specified conditions of the pumping and the guaranteed

performance in K.W. hour input per water horse power output under various conditions of working.

The guaranteed performances are also to be specified under following conditions i.e. variation in

head discharge and power consumption in the following cases:

a) When available voltage decreases from 415 volts to 380 volts or increases from 415 volts to 440

volts.

b) When there is fluctuation of ±3% in the frequency of the AC power supply from 50 C/S.

c) When there is above change in voltage and frequency of the AC power supply simultaneously. The

official tests shall be conducted in two stages. Preliminary tests may be conducted at the

manufacturer’s works. The final tests shall be conducted at site. Pumps shall be run so as to obtain

the range of heads specified in the performance tables by means of throttling or opening valves of the

pumping mains and tests results will be compared with those guaranteed by averaging the units

consumption per water horse power hour.

The guaranteed figures stated above shall be subjected to no tolerance and the average results

shall be obtained during official test of plant. If the results lack average guaranteed figures the

contractor shall forfeit followings ascertained damages relating to each set installed.

If BOT unit (KWI) per WHP, the consumption is above the average guaranteed figure under the

specified Q and H, the liquidated damages will be recovered as the capitalized cost of the Extra

Energy Consumption during the useful life span 15 years of the pumping set. The liquidated

damages shall be calculated as below :-

Page 53: E-TENDER FOR - AWS

Cost of extra power consumption

to be recovered shall be equal to =Cost of extra power per annum × capitalization factor for 15

years at an interest rate of 9%.

No damage will however, be recovered if the consumption is less than 0.05 BOT units per WHP

above the guaranteed.

If on testing the discharge of pumps is found to be within the permissible limit of ±4% then the

pumping plant will be accepted without imposing any penalty. If discharge is less by 5% to 10% then

pro rate deduction @ 1% of the cost of pump and motor for less percentage of discharge shall be

made and further if the discharge is less than 10%, plant will be rejected.

It may be noted carefully that no privilege shall be given to any offer for evaluation purposes

considering the efficiency of the pump and Motor. Better efficiency pump and motor however

shall be preferred. For evaluation purposes the maximum efficiency of pump and motor shall be

considered as 72% & 84% respectively but these will be tested on the efficiency quoted by the

firm in schedule-E of their tender

The pump efficiency offered below the efficiency quoted shall be considered for evaluation as

follows:

(i) Electric charges shall be based on 16 hours of operation per day for 15 years at the prevailing

rate of Electric Charges and interest of the rates of 9% per annum for cumulative cost difference

in 15 years. day.

(ii) All future costs of yearly power consumption will be capitalized to present value at

capitalization factor @ 9% interest.

The tenderers shall have to consider the condition of pumps being run at shut off head under the

pump duty variation condition as narrated above. The tenderer should ensure selection of pumps

considering shut off head at least 25% more than the duty head. However the motor should be

selected as per tender specification and scope of work defined. The possibilities of change of duty

point of each pump in parallel operation cannot be ruled out under such condition tenderer should

select the pump carefully. Penalty for delay in supply and installation-0.25% per day of the total

tendered cost subject to a maximum of 10%. 2. SWITCH GEAR MATERIAL:

Complete switch gear with all equipment, accessories shall be supplied and erected by the

contractor with the provision for connecting to the 415 +6%, 10%-v, 3 phase 50 Hz A.C. supply

system at tubewell pump house. Under the item construction features as follow: Rating of the

switch gear shall be as per Data sheet. 2.1 CONSTRUCTIONAL FEATURES 2.1.1 The control panel shall be completely metal enclosed and shall be dust, moisture and vermin

proof. The enclosures shall provide a degree of protection not less than IP-54 in accordance with

IS:2147.

Page 54: E-TENDER FOR - AWS

2.1.2 Panels shall be wall mounting type and shall comprise rigid welded selected, smooth finished, hot

rolled sheet steel of thickness not less than 3 mm for front and rear portions and 2.5 mm for sides top

and bottom portions. There shall be sufficient reinforcement to ensure a plain surface to limit

vibration and to provide rigidity during installation and when panel put in service. 2.1.3 The control panel shall be assembled on channel/angle base plates with anti-vibration mountings. The

vertical panel shall be wall mounting type with removable covers at front. All bolts, nuts, and screw

etc., appearing on panel shall be so arranged as to present a neat appearance. Lifting hooks shall be

provided such that no openings are left when hooks are removed. All hooks, bolts and nuts exposed

to external atmosphere shall be chromium plated or zinc plated. 2.1.4 Operating handles of the doors shall have locking arrangement. There shall be no sharp door

covers to avoid injury to personnel. 2.1.5 The switch gear panel shall be provided with hinged door on the front and removable access

cover on the front. The door of the panels shall be gasketed all around with neoprene gaskets.

Ventilating covers if provided shall have screens, fittings and due collecting devices. The

screens shall be made or either brass or G.I. wire mesh if required. 2.1.6 Design, material selection and workmanship shall be such as to result in neat appearance inside

and outside with no welds and reverts apparent from outside, will all exterior surfaces free and

smooth. 2.1.7 Switch Gear Panel shall be suitable for wall mounting control cubicles as specified in data sheets

in the form of metal channels property drilled shall be furnished alongwith anchor bolts and

necessary hardware for mounting the panels. These shall be dispatched in advance so that they

may be installed and leveled.

2.1.8 Switch gear panel shall be liberally sized so as to provide spacious layout of equipment and

devices with sufficient working space in between.

2.1.9 The maximum and minimum height of the operating equipment on the panel shall be 2100mm and

900mm respectively from the floor level. If the panel height is small then it should be mounted on

separate support so that the operating height of the equipment comes within the above limit. The

proper supporting arrangement shall be provided by the tenderer. The following features are also required:-

(i) MCCB, bus bar, instrumentation and protection equipment and cables shall be inbuilt within

cubical panel.

(ii) The panels shall be so constructed that failure of one equipment does not effect that adjacent units.

Suitable vent shall be provided to release gas pressure developed due to short circuits or any burn. (iii) Bus bar connections, joints and taps shall be silver plated; connections shall be as short as

possible.

(iv) Each cubical shall be provided with HRC fuse and plug sockets. (v) Wiring for instrumentation, protection relay and lead indicating lamps in each switch gear panel

shall be grasped and brought out to easily accessible terminals for external connections. Note: Switch gear control panel shall be provided built within Automatic star delta starter as a single unit.

2.2 SOFT STARTER APPLICABLE AS PER ACTUAL REQUIREMENT:

The soft- starter shall be developed and qualified in accordance with international standards,

particularly with the standard dedicated to soft-starter EN / IEC 60947-4-2. The starter must be

CE marked under the harmonized standard EN / IEC 60947-4-2.

Description

The operating principle of the Soft-starter should not simply take ground on a limitation of motor current

during the transitional phases or on a voltage ramp but on a torque control motor. The

Page 55: E-TENDER FOR - AWS

Soft-starter should provide a torque ramp during the acceleration phase. Thus, it can control the torque

during the starting period and if necessary provide a motor torque constant throughout the acceleration

phase. For pumping applications, the deceleration will be on torque a ramp.

All Soft-starter sizes will have the same control board. That control board must be identical

for all applications.

All Soft-starters shall be equipped with means for measuring motor current to ensure protection.

The measurements of the current will be active when the Soft-starter is by-passed (embedded

by-pass for all sizes).

The Soft-starter should have a separate power control.

The terminals of the board control shall be of plug type for easy maintenance.

Soft Starter should control 3-phase output with Programmable display.

The Soft-starter will handle the by-pass itself: manage the closure of the by-pass at end of

acceleration time and open that by-pass at end of stop sequence. That function must be

compatible with the types of stop: freewheel, ramp

The access to the settings can be locked by code. The monitoring parameters should

remain accessible.

Environment

The maximum relative humidity will be 95% without condensation or dripping water according

to standards IEC60947-4-2.

The storage temperature can be between -25 ° C to + 70 °

Electrical characteristics of the Soft-starter

The Soft-starter will automatically adapt itself to the frequency of the mains 50 or 60 Hz

with a tolerance of + / -10%.

Outputs: the Soft-starter must have at least 2 relays with a NO/NC contact Maximum switching

capacity on inductive load: 2 A at 250 Vac and 30 Vdc.

Protections

· The starter will include the management of Motor PTC probe. · The starter will calculate continuously the motor overheating from the real current value

(the current must be measured and not estimated). Several classes of thermal protection

will be proposed following the standard EN/IEC60947-4-2: Classes 10, 20, 30.The

calculation of the thermal protection must be active even when the Soft-starter is not power

energized.

· The starter shall be protected against thermal overload, over & under voltage.

· Dry run protection for pump motor.

· Protection against reverse-phase network, the loss of phases on mains or on motor.

· The protections will always be maintained even the Soft-starter is by-passed internal or self.

Page 56: E-TENDER FOR - AWS

Communication

· The starter will include a multipoint serial link to be connected directly to a Modbus network.

The starter shall be able to be connected to Ethernet and other networks and communication bus

option.

· The communication shall provide access to the control, adjustment and monitoring of the

Soft-starter.

Display

· The starter shall have a display and programming push buttons. · The following information must be accessible on the display

- Motor current (by phase) - Motor state - Current status (acceleration, deceleration, Running). - Operating time. - The last fault occurred - Fault history - I/O status

2.2.1 THERMAL OVERLOAD RELAYS 01 No. APPLICABLE FOR STARTER, UNLESS

OTHERWISE SPECIFIED BY ENGINEER IN CHARGE:

Thermal overload relays 03 pole type shall be hand reset. The hand reset device and ‘STOP’ push

button of starter shall be separate from each other. Starter shall be complete with three element

positive acting, ambient temperature compensated, time lagged thermal overload relay with

adjustable setting. Overload reset push button shall be brought out on front of door cover. Overload

relays shall be provided with 02 NO / and NC auxiliary contact. 2.2.2 CT OPERATED RESIN CAST MAGNETIC OVERLOAD RELAY 01 No. APPLICABLE

or DIGITAL OVER CURRENT RELAY:

CT operated resin cast thermal over current relay or Electro Magnetic overload relays with CTs 03

pole type shall be hand reset. It can be managed with the combination of thermal time lagged relays

with CT operated magnetic overload relays. Adjustment of both time setting & current setting shall

be provided with easily accessible. Over current relays with CTs shall be procured with switch gear

panel in built Star delta starter separately or cumulatively. Over current relay shall be mounted

within switch gear panel. Over current range shall be suitable to HP of the motor at full load and over

load as per Data sheet.

2.2.3 SINGLE PHASING PREVENTER:

Single phasing preventer relay shall be provided with current operated type. The relay shall not operate

for supply unbalance; of 5%, but shall positively operate for unbalance more than 5%. The relay shall

operate in the event of single phase fuse blowing even though motor emf in the concerned phase is order

of the 85%. After sensing a single phasing, the delay shall operate with a time delay of 02 or 03 seconds.

The relay shall not operate for 03 phase power supply failure. The

Page 57: E-TENDER FOR - AWS

relay shall be hand reset of push button. Resetting shall be instantaneous and independent of the

adjusted time delay in the tripping of the unit. Visual indication for the relay shall be provided

such as for 03 Nos. Pots at input for power supply, 02 Nos pots for auxiliary supply and 03 Nos

pots for common, NO and NC

The relay shall be suitable for application to protect reversible and non reversible motors. The relay

operation shall be independent of HP rating and RPM of the motor. The relay shall be of fail-safe type

and shall operate to trip the motor when the relay internal wiring is accidently open circuit. Reference

voltage for the supply shall be available even when supply has lost one phase.

2.2.4` ELECTRO MAGNET TYPE CONTACTS:

The motor starter contactor shall be of the electromagnet type, rated for uninterrupted duty as defined

in IS 2959, class applicable is I or II unless otherwise specified by the Engineer in charge, class I is

up to 30 operations per hour and class II is up to 150 operations per hours. It shall be decided by the

Engineer in charge as per site conditions after the award of contract.

Contactors shall be of double break, non gravity type. Each contact shall be provided with 02 NO, 02 NC

auxiliary contact. Insulation class of opening coil shall be E or better. Uninterrupted duty draws the

inference that duty in which main contacts remain closed without interruption while carrying a steady

current for a period of more than 08 hrs. This type of duty is taken care by a de-rating factor as the

accumulation of dirt and oxides have adverse affect on the performance of the contactor. It is closed by an

electromagnet. It opens under the action of gravity or spring when the

coil is de-energized. The principal component of magnetic contactor are as below: (a) Magnetic frame. (b) Magnetic or holding coil. (c) Moving armature which is attracted by the electromagnet frame and moving armature are of

laminated steel in the AC contactor for preferred rating 415V±6% for the main circuit. (d) Stationary contacts. (e) Moving contacts and spring mounted on the armature frame. (f) Are chute or arc snuffers for extinguishing the arc. (g) Flexible shunts for electrical connection to the moving contacts. (h) Auxiliary or inter locking contacts.

There shall be the circuits associated with electromagnet. The main circuit and the control

circuit. The contacts shall be copper alloy silver coated to the main contacts in addition to the

main contacts. There are auxiliary & arcing contacts close Ist, then the auxiliary contacts and last

of all the main contacts while opening. The order of operation is reverse, arcing contacts

prevents the concentration of arc on small area and results in increased life for the main contacts

and arc boxes. The arcing contacts are replaced with when they are too worn to make contact

ahead of main contacts.

Page 58: E-TENDER FOR - AWS

2.2.5 CAPACITORS:

Motor shall be provided with separate capacitors to correct the power factor of the machines to 0.9

lagging or close to upf. The capacitor shall be of scaled unit pattern comprising paper, foil or plastic,

impregnated with oil or synthetic electrolyte. Capacitors shall comprising assemble of units mounted

on frame with suitable trucking, screening, interconnections or shall be housed in ventilated sheet

steel, enclosures. If either cases capacitors shall be complete with all necessary interconnections,

discharge devices, protective fuses and terminals for the connections of a 3 core supply cable. A

removable un-drilled cable gland shall be provided. Its rating shall be in the range of 1/3 to 1/4 KVAr

of HP of the motor unless otherwise specified by the Engineer in charge to improve power factor 0.9

lagging.

2.3 SUBMERSIBLE CABLE FOR PUMPING PLANTS:

Conforming to IS 694:1990 Tested at 1100 V, PVC flat submersible cable for pumping plant shall be

in three core working as power cable suitable for voltage and current rating of the motor at inrush

current of the motor starting. The size of conductor close section of the cable shall be in copper only

sufficient enough to withstand rigors of motor starting or short circuit fault taking in to account the

type of starters used for starting the motor. The cable shall be laid down from control panel/ starter to

the pump sets and therefore, length of cable should be sufficient considering the loops of suitable

length at certain points in the route of cabling. Cable joint with motor shall be done with IP-68 water

sheath in order to make water type joint as prescribe in IER. The cable must be checked for

continuity of the jointing and no. of copper stands and its gauge must be conforming to IS or

manufacturer’s code of practice failing which, cable shall be rejected. Note: The entire length of the

cable must be adequately enough to connect pump set and panel, starter etc. and margin in loop shall

be given to recover the need of future. It will have to be extended by the contractor in the event of

length of cable fall short in course of SICT. Size of the submersible cable 1x3x…..sq. mm around 35

mtr. long. 2.3.1 CABLE ENTRY:

The panels shall have provisions of cable entry from bottom. The removable cable gland

plate shall be provided to make entry dust tight and vermin proof.

The panels shall have provisions inside for fixing the multicore cable glands. The cable

glands support plate shall be 4 mm thick.

Cable entries to the panel shall be from the bottom unless otherwise specified. When called

for, necessary number of cable glands of sizes to suit purchaser's internal cables to the

panels shall be supplied. Cable glands shall be screwed type and made of brass. 2.4 MOUNTING: 2.4.1 All equipment in front of panel shall be of flush mounting type. 2.4.2 All equipment shall be so mounted that the removal and replacement may be accomplished

individually without interruption of services to others.

Page 59: E-TENDER FOR - AWS

2.4.3 All equipment inside the panel shall be so located that their terminals and adjustments are readily

accessible for inspection or maintenance. 2.4.4 No equipment shall be mounted on the doors without prior approval Engineer in charge. 2.4.5 Wherever applicable Auxiliary bus bars for AC and P.T. circuits and other common service shall

be provided near the top of the panels running through the entire length of the panels, shall be

suitably insulated and along their run. 2.4.6 Fuses and links shall be provided for isolation of individual circuit from bus wires/bars without

disturbing other circuits. 2.4.7 Wherever practicable, wiring shall be accommodated on the sides of the panel. Sharp bends shall

be avoided. 2.4.8 Wiring shall be neatly bunched in groups by non-metallic cleats or bands. Each shall adequately

supported along its run to prevent sagging and strain on the termination. 2.4.9 Wire termination shall be made with solder less compression type of tinned copper lugs which

grip the conductor and insulation. Insulated sleeves shall be provided at all the wire

terminations. Wire shall not be spliced between terminal points. 2.4.10 Tenderer shall be solely responsible for the completeness and correctness of the internal wiring

and for the proper functioning of the connection equipment. 2.5 WIRING:

Panel shall be supplied completely wired indicating to equipment devices and terminal blocks and

relays for external cable connections at the terminal blocks all the internal wiring shall be furnished

by contacts / MCB/ MCCB. Panel wiring shall be securely supported neatly arranged readily

accessible and connected to equipment’s terminals and terminal blocks. Spare contact of auxiliary

relays and switches shall be wired upto the terminal blocks and wiring shall be carried out with 650

volts grade PVC. Insulated single core, standard copper conductor shall be 1.5mm for potential

circuit and 2.5mm for current and control circuit. The minimum number of strands per conductor

shall be three, flexible wires shall be used for wiring devices mounted on moving parts as swing

panel door. Auxiliary bus bars fo AC supply shall be provided inside the panel near the top of the

panel running through the entire width of panel to accommodate 03 Nos rings CTs for

instrumentation/ protection- fuses and links shall be provided for isolation of individual circuit from

bus bars without disturbing other circuits. Wherever practicable wiring shall be accommodated on

the sides of panel. Wiring shall be neatly bunched in groups by not Metallic cleats or bands, each

shall be adequately supported along its running to prevent sagging and strain on the termination.

Wiring termination shall be made with solderless compression type of tind copper lugs which grips the

conductor and insulation. Insulation sleeve shall be provided at all the wire terminations. Wire shall not

be spliced between terminal points. Each wire shall be identified by both ends by plastic ferrules with

wire designation in accordance with wiring diagram fitted inside the panel.

Page 60: E-TENDER FOR - AWS

2.6 Instruments: 2.6.1 Indicating Instruments (a) All electrical indicating instruments shall be circular 270° scale, 96 mm square electro- magnate coil

instruments suitable for semi-flush mounting with only flange projecting on vertical panels.

(b) Instrument dials shall be white with black numerals and lettering knife edge painters and

parallex feedials shall be preferred. (c) Instrument shall conform to IS:1248 and shall have an accuracy class of 2.0 or better. (d) The number of digits provided shall be adequate to cover 1000 hours of operation. (e) Current coils of meters shall have a continuous over load capacity of 200% for both accuracy as

well as thermal limits. Also the coil shall withstand at least 10 times rated current for 0.5

seconds without loss of accuracy. 2.7 RELAYS : 2.7.1 All relays shall conform to IS:3231 or equivalent. They shall be suitable for semi-flush mounting

with only flanges projecting on the front with connections from the rear. 2.7.2 Relays shall be rectangular in shape and shall have dust tight, transparent covers removable from

the front. 2.7.3 All protective relays shall be in drawout cases with built in test facilities. Test block and

switches shall be located just below each relay for testing unless otherwise specified. All

auxiliary relay and timers shall be supplied in non-draw-out cases. 2.7.4 All relays shall be suitable for operation at 50 Hz, 415V A.C. voltage operated relays and current operated

relays shall be suitable for operation. A.C. auxiliary relays and timers shall be designed for the A.C.

voltage and shall operate satisfactorily between 70% and 110% of rated voltage. Voltage operated relays

shall have adequate thermal capacity for continuous operation. 2.7.5 All protective relays shall be provided with atleast two pair of potential free output contacts.

Relays case shall have adequate number of terminals for making potential free connections, to

the relay coils and spare contacts. Paralleling of contacts if any shall be done at the terminals on

the casing of the relay. 2.7.6 All protective relays shall be provided with externally hand reset positive action operation

indicator. 2.7.7 Timers shall be electromagnetic or thermal of latest improved type only. Short time delays in

millisecond may be obtained by shading with copper lugs on auxiliary relays. This shall not

affect the continuous rating of the relays. 2.7.8 All relays shall be self next type unless otherwise specified. 2.7.9 Each relay shall have provision for easy isolation of trip circuit for the purpose of testing and

maintenance. 2.7.10 All relays shall with stand a test as per relevant I.S.IO. code and standard. 2.7.11 Auxiliary seal in units provided on the protective relay shall be shunt reinforcement type.

Page 61: E-TENDER FOR - AWS

2.8 CONTROL SWITCHES:

Control and instrument switches shall be rotary type suitable for semi flush mounting with

access to connection from the back by the removal of the cover. It should not be possible to

close the switch gear / MCCB with the door of it is when open and it should be possible to open

the door of it only when the switch is in the off position. Mechanical position indicator on/off

shall be provided.

MCCB shall be provided with facility for locking the panel with visible indication to show that

panel is in operation.

Neutral link shall be disconnected type. All connection shall be preferably be done with spring

washers and accessible for inspection. 2.9 MOULDED CASE CIRCUIT BREAKER –MCCB

MCCB should automatically isolate the electrical circuit under sustained overloads or short

circuits. The constructional features shall be as per details given below: Operating mechanism shall be quick make, quick break and trip free, independent of manual

operation contacts. Housing shall be made of resistance insulating material having all parts of it

enclosed in moulded housing. Terminal should be accessible for external connections. Magnetic thermal release should have three bimetals given thermal overload protection and

electromagnetic for short circuit protection. All releases should operate on common trip bar so

that all the phases gate disconnected even when faults occur on only one of them. Silver alloy

contacts should have long electric life. The mechanism should be so designed that they should be

no arcing on the current carrying part of the contact system. There should be strong wipe action

of the contact system for keeping the contacts surface clear of site films. It terminal should have

large sufficient dimension to accept links or cable lugs. Adjacent phase terminals should be

separate by insulating various with adequate clearances. Terminal configuration should permit

straight through cabling.

2.9 BUS BARS:

03 Nos. Bus bars of adequate preferably 1.0 amp. for aluminum and 1.6 for copper Per squire mm at

inrush current of motor starting shall be located in air insulated encloser. Direct or accidental contact

should not be possible with bus bars and primary connections. Bus bars shall be silver / tinned faced.

Spring washer shall be provided to ensure good contacts. In case aluminum connection are required,

suitable bimetallic connections or all bus bars joints shall be silver faced. Bus bar shall be adequately

supported on cast resin insulators to withstand dynamic stresses due to short circuit. The bus bars

support insulator shall conform to IS 2544. Bus bar shall be insulated with external PVC sleeves or

other insulating material. The PVC used shall be of high temperature grade, 50-0 and shall possess

good die electric properties- high tensile strength and good finish. The joints shall be covered with

insulating tap’s covering able to withstand temperature 85 degree size of bus bars shall be selected

making them suitable to withstand high large current for 30 second.

Note: Miniature circuit breaker (MCB) is denied in place of MCCB MCB is meant for lighting

purpose whereas isolator switch is forbidden.

Page 62: E-TENDER FOR - AWS

3. MAIN PIPING AND VALVES:

Quantity of the main piping & valves are given below (for each T/W):

Sl. Particular Oty. Unit

No

1. MSDF Column pipe available in 03mtr. long 15 Nos.

2. MSDF Pipe 1.5mtr. long 2 Nos.

3. MSDF Pipe 1.0mtr. long 1 No.

4. CI DF bend (ISI mark) 1 No.

5. CI AF Tee (ISI mark) 1 No.

6. CI DF sluice valve (ISI Mark) 2 Nos.

7- CI DF Reflux valve (ISI Mark)) 1 No.

8. MS Fabricated DUMDUM 1 No.

9. Nut Bolts & Packing. 1 Set

10. SI column pipe clamp 2 Pairs

Note : size of the main piping & valves must be corresponding to the velocity range from

0.90m/s to 2.0m/s and valves shall be IVC / Kirloskar make.

3.1 M.S. COLUMN PIPE: 3.1.1 This shall be 100 MM dia 5.4 MM thick 3M long threaded and welded double flanged M.S.

column pipe. 3.1.2 The flange shall be made up of 12 MM thick M.S. flat respectively for 100 MM sizes.

3.1.3 The flange shall have OD as 165 MM respectively for 100 MM sizes with cable

grove. 3.1.4 The flange shall have 6 holes respectively suitable to 12MM bolt.

3.2 M.S. D/F PIPE:

3.2.1 This shall be 100 MM M.S. Double flanged (D.F.) Pipe having thickness 5.4 MM

respectively.

3.2.2 The flange size shall be standard having standard numbers of holes.

3.2.3 The length of D/F pipe shall be 1.5/1.0M.

3.2.4 The thickness of flange shall be 16 MM respectively for 150/100/80MM size.

3.3 D/F BEND:

This shall be 100MM Size 90 D/F ISI marked CI/DI bend.

3.4. A/F TEE:

This shall be 100 MM size A/F (all flanged) ISI marked CI/DI Tee.

3.5. SLUICE VALVE: This shall be 100MM size CI D/F Jal Nigam approved make ISI marked clockwise closing, non-

rising stem type, and sluice valve with hand wheel. Rating of the valve PN1.0

Page 63: E-TENDER FOR - AWS

3.6. REFLUX VALVE: This shall be 100MM size CI D/F Jal Nigam Approved make ISI marked reflux valve. Rating of the

valve PN1.0 3.7. DUM DUM:

This shall be 350X200MM or 350X150MM or 300x150MM or 200x100MM & 200x80MM size

M.S. fabricated adjustable height, twist & lock Dumdum having 5.4 mm pipe thickness, 10mm

thick cover plate, 10mm thick 100mm wide ring, lower flange same as item No- 2 and upper

flange same as in item No-3, also having provision for pressure gauge, depth gauge, double

earthing & cable suitable to 300MM housing pipe. 3.9 NUT BOLT AND PACKING:

H.T. Rust resistant quality 12 MM size nut bolt for column pipe, Standard quality 5/8” size nut bolt

for other flanges and 5mm thick Standard quality suitable size rubber picking for fitting item No.

2 to 8. 3.10 COLUMN PIPE CLAMP:

This shall be 100 MM size S.I. column pipe clamp made up of 12mmx100mm flat having 4 holes

suitable to 5/8'' bolt and 600mm total length including suitable length bolt. 4. SERVO VOLTAGE STABILIZER FOR CONTINEOUS VOLTAGE SUPPLY AND

REGULATION AT VARIATION ±1% :

Copper wound operated at input 250–500V & output 400–440V servo stabilizer at each Tube

well shall be provided as per details attached sheet at each Tube well filled with transformer oil

conforming to relevant IS including PVC copper conductor cable in 3.0 core of suitable size

conforming to relevant IS 1554 Part-1 heavy duty voltage grade 230V to 1100V from stabilizer

to control panel/ starter as directed by Engineer in charge.

GENERAL SPECIFICATION

1. Mode of operation : Manually operated

2. Input supply voltage : 250 Volt-460 Volt

3. Output voltage : 415 Volt

4. Type : Unbalance type, suitable for submersible motor,

Industrial voltage stabilizer.

5. IP : 45

6. Material of whole winding : Copper

7. Material of core : Silicon 92 grade/ CRGO

8. Material of body : 2mm thick M.S. sheet

9. Base : C.I. wheel mounted (detachable)

10. Cooling : Oil immersed

11. Cooling/ Insulation : Transformer oil cooled

12. Voltage control arrangement : In each phase

13. Votmeter with Indicator : In each phase

14. Painting : Double coat spray painting 15. Quantity of transformer oil

to be filled : Oil level die electric filled as per IS 335 16. The stabilizer should be guaranteed against manufacturing defect due to bad material faulty

design and workmanship for a period of one year from the date of commissioning. Any item or

part found defective during the shall be replace free of cost.

17. Rating of stabilizer shall be 2 KVA per H.P. of the induction motor at 80% reduced voltage Starting

in case of ATS induction motor & 1.5 KVA per H.P. of the induction motor in case of star delta

starting and 03 KVA per H.P. of the induction motor in case of DOL starting.

18. Main line at : 3 Steps Step up : 5.0 Parts

Page 64: E-TENDER FOR - AWS

Step down 19. No of Volt meter of suitable

range No. of Toggle switch

No. of Rotary switch

5. PRESSURE AND DEPTH GAUGE:

: 2.0 Parts : 3 Nos.

: 3 Nos.

: 3 Nos.

The contractor shall provide a pressure gauge of 100 mm dia suitable to read the delivery head of water in

‘Meters head of water’ and one pneumatic type of depth gauge which should be capable to read the depth

of water in Meters directly. The make of gauges shall be Feibig or H-Guru.

5.2 AIR LINE:

The contractor shall provide GI/Fibre Airline of 6mm dia or PVC nylone 12mm is preferred

alternatively in required length to lower below the floor of pump house. The air line pipes should

be ERW type and confirming to ‘C’ class specification of IS:239 (part-I) i.e. having thickness of

2.65 mm duly threaded and sockets of heavy type.

5.2.1 ACCESSORIES AND SPECIALS:

I. Both the gauges are to be mounted on a common teakwood board with white sunmica top of suitable

size on wall at a height of 1.5 meters from the floor of pump house and to be connected

with air line.

II. The pressure gauge is to be supplied with control cock of brass.

III. The depth gauge is to be supplied with following accessories.

(a) 1 No. foot operated air pump of reputed make and strong flexible piping.

(b) Schrader valve, M.S. Tee, Coupler, elbows etc. of suitable sizes for fixing in the

air line.

NOTE :- The contractor has to supply all M.S. Clamps etc. to be grouted in the wall for fixing

airlines to the gauges in proper way and parallel to each other and other required fittings

for proper installation.

6. TOOLS:

This shall be a set of tools comprising of following items:

(i) D-spanner set (6-17 mm) 1 No. (v) Hand air pump 1 No.

(ii) Ring spanner 4/8" & 5/8" , 2 Nos. (vi) Insulated cut Plier 1 No.

(iii)Pipe wrench 12" 2 Nos. (vii) Screw driver 12” 1 No.

(iv) Hammer (500gm) with handle 1 No. (viii) screw driver 8” 1 No. 7. LIFTING TACKLE:

This shall be 2 Tone capacity (tested at 3 tone) 4.5 mtr. lift INDEF/MORRIS make spur-gear chain

pulley block.

The chain pulley block shall be operated on the lower flange of the bridge girder and load chain shall be of

alloy steel as per IS 2429 part-II. It shall be heat treated to give the ductility and toughness it shall be

welded construction with a factor of safety not less than 5. The lifting hook shall be forged steel, he

treated alloy or carbon steel. It shall be of single hook type provide with standard depress

Page 65: E-TENDER FOR - AWS

type safety latch. Hook shall be conforming to IS 3815. The brake for the lifting gear shall be

screw and friction disc type and shall offer no resistance during hoisting. Overload test at 150%

of raises load for chain pulley block and trolley, overload test of 125% of rated load and

defection test with 100% of rated load. Test certificate of the manufacturer has to be submitted

by the contractor.

8. POWER WIRING AND EARTHING

PVC insulated 3.5 core round aluminum power cable of required size, 1100 V grade confirming

to IS 1554 part I heavy duty voltage grade 230V to 1100V accessible to earthing shall be

supplied to connect UPPCL energy meter and 02 meter leads shall be left in spare for making

connections. The size of cable shall be adequate to bear the brunt of in rush current at 45 degree

ambient temperature. It shall also include 12mm thick sunmica top board size of board 3̍x 1.5

and 4 Nos porcelien cutout of required capacity duly grouted on the wall is of paramount

importance as per IER.

8.1 EARTHING:

Double plate earthingas of the entire electrical system shall be carried out and connected to

permanent earthing plates buried in ground and surrounded with coke salt upto adequate depth

where earth is encountered. It shall be consisting of the following: ii) GI Earth plates of 600 X 600 X 6 mm size as per latest relevant ISS/IER. iii) GI water pipes of required length and 40mm dia. As per latest relevant ISS/IER. iv) Aluminium Earth strip of adequate size as per relevant ISS/IER and in required quantities to cover

complete installation in double run. The strip shall be without kinks and without any joints.

v) Necessary quantities of lugs and clamps etc. for proper earthing. vi) Necessary quantities of salt and coal shall be supplied at the time of erection. vii) Earth chamber CI box 300 X 300 mm as per ISS/IER.

i) The digging of pits for earthing and construction of suitable size earth chambers shall be done

by the tenderer. ii) The whole of the above work of power wiring and earthing shall be carried out to the entire

satisfaction of Engineer Incharge and subject to the approval of UPPCL and also be accordance

with IER and other Govt. regulations prescribed/amended upto date. iii) The power wiring shall be done properly on MS clamps to be grouted on the wall. The

submersible cable/copper lead will run through MS conduits on wall and floor through entire

route.

8.1.2 TESTING OF EARTHING SYSTEM 8.1.3 Purchaser may ask to carry-out earth continuity tests earth resistance measurements and other

tests in presence of him which in his opinion are necessary to prove that the system is in

accordance with design and specifications. Contractor shall bear cost of all such tests.

Page 66: E-TENDER FOR - AWS

8.1.4` EARTHING SYSTEM (APPLICABLE AS PER ACTUAL REQUIREMENT)

8.1.5 Sizes and number of earth leads for earthing various items and other technical particulars shall

be as specified.

8.1.6 Earthing conductors are shown diagrammatically. Exact location of earthing conductors, earth electrodes

and test pits, and earthing connections may be changed to suit the site conditions.

8.1.7 Earthing conductors in the building, running parallel to walls and columns shall not be less than

1500 mm away from the wall/column.

8.1.8 Suitable earth risers shall be provided if the equipment is not available while carrying out

earthing connection.

8.1.9 Wherever earthing conductor passes through walls, galvanized iron sleeves shall be provided

for the passage of earthing conductor. Water stop sleeves shall be provided, wherever earthing

conductor enters the building from outside.

8.1.10 Wherever the conductors are to be buried, contractor shall coordinate with other civil

contractors to ensure that the conductors are installed before concreting.

8.1.11 All connections shall be of low resistance. Contact resistance shall be minimum.

8.1.12 Steel conductors, above ground level shall be galvanized. All conductors shall be free from

any defect. Earthing conductors shall not run in direct contact with control and other cables.

Single core cable amounting shall be earthed at one end. The cable trays shall be earthed to main

grid at least at two points and every 25 mt interval.

9. PAINTING:

All sheet metal work shall be phosphated in accordance with the following procedure and in

accordance with I.S. Code of Practice for Phosphating Iron and Steel after application of the

primer, two coats of finishing synthetic enamel paint shall be applied, each coat followed by

stoking. The color of the finishing coat shall be as per purchaser approval. Finished painted

appearance of panels shall present an aesthetically pleasing appearance free from dents and un-

even surface. A small quantity of finishing paint shall be supplied for minor touching up

required at site after the installation of panels. Main piping & valves and what’s not, existing

within pump house are also covered.

10. ERECTION:

The contractor shall undertake complete installation of the pumping plant along with associated

works such as switch gear, power wiring & earthing, main piping and valves, pressure & depth

gauge with air line and other things of the same types whatsoever, are required for proper

completion of the installation, commission & testing in the presence of at least one approved

senior English or Hindi speaking working erector to supervise the erection of the plant in the

capacity of contractor representative. The contractor shall also provide sufficient Erectors skilled

and good at mechanical, electrical and instrumental Engineering, such skilled, semiskilled, and

unskilled laborer are necessary to ensure

Page 67: E-TENDER FOR - AWS

completion of the various sections of the installation works well in time. The contractor shall not

remove any supervisory staff or laborer from site without prior approval of the Engineer’s

representatives. Installation work also make necessary petty civil works such as cutting of wall

and brick work/ concrete work dismantling and repairing with restoration works satisfaction of

the Engineer in charge including watch and ward of the pumping plant until the commissioning

and handing over proceedings are complete. Such works are to be completed without making the

claim of extra payment.

11. TESTING:

The contractor shall carry out the final tests on the pumping plant to ensure power consumption

is as per schedule “E” furnished and all requirements as mentioned in respective specification if

any. The contractor shall also carry out all other tests required either by himself and/or the

Engineer to complete the plant etc. to supply systems and delivery of all works. The contractor

shall maintain on the log book in English/Hindi of all test carried out and will handover certified

copy of the same to the Engineer at the time of completion of the works.

12. COMMISSIONING & TRIAL RUN :

After being intimated by the office, contractor will commission the pumping plant within 10 days

time and just after that trial run will be taken up and started. During the trial run, the contractor shall

depute his skilled staff ( 3 nos operator in three shift on each TW and each ZPS also one electrician

in general shift in each ZPS ) for trial run (As and when required and as per availability of Power

Supply) during this period except for Power, all consumables shall be provided by the contractor free

of cost including watch & ward of pumping plant. Data sheet for Electrical Items Part-I

(Recommended rating of Contactor, MCCB, Stabilizer & Cable)

Starter Type of the Capacity of Capacity of Rating of Submersible cable capacity starter the main switch stabilizer size

contactor (MCCB)

Type, AC-3,

Making cap

5 HP DOL 9 A 20A, 10 KA 10 KVA 1x3x2.5 sq.mm.

6 HP DOL 12 A 20A, 10 KA 10 KVA 1x3x2.5 sq.mm.

7.5 HP Star delta 12 A 25A, 10 KA 15 KVA 2x3x2.5 sq.mm.

10 HP Star delta 18 A 25A, 10 KA 15 KVA 2x3x2.5 sq.mm.

12.5 HP Star delta 22 A 32A, 15 KA 20 KVA 2x3x4 sq.mm.

15 HP Star delta 32 A 32A, 20 KA 25 KVA 2x3x4 sq.mm.

20 HP Star delta 40 A 100A, 25 KA 30 KVA 2x3x6 sq.mm.

25 HP Star delta 50 A 125A, 25 KA 40 KVA 2x3x6 sq.mm.

30 HP Star delta 70 A 150A, 35 KA 50 KVA 2x3x10 sq.mm.

33 HP Star delta 70 A 150A, 35 KA 60 KVA 2x3x10 sq.mm.

Page 68: E-TENDER FOR - AWS

Note: Rating of star- main & delta electromechanical contactors type AC-3 shall be the same and identical.

Since range of contactors vary manufacturer / vendor to vendor, range of contactors has to be chosen the

same as cited above or the next higher commercial range of the above cited range in the event of the range

not matching with above cited range.

Data sheet for Electrical Items Part-II

(Recommended Rating of Electrical Starters and Cables Items)

Full load Relay Recommended cable size for

HP Rating of current, A (IL)) range, A connection, sq mm. Recommended HRC

the pump set

(Ip))

Fuse rating, A Al Cu

5 7.5 4-6.5 4 2.5 15

7.5 11 6-10 6 2.5 25

10 14 6-10 10 4 28

12.5 18 9-14 10 4 40

15 21 12-10 16 6 50

20 28 18-30 25 10 50

25 34 24-40 25 10 63

30 39 36-60 35 16 63

40 55 36-60 50 25 80

50 66 48-80 70 35 100

60 80 60-100 70 35 125

75 95 60-100 95 70 160

100 135 90-150 95 120 200

125 165 120-200 120 185 250

150 200 120-200 120 185 250

HP Full load Electro Electro Electro CT ratio/ burden/

Rating of current, A Mechanical Mechanical Mechanical Accuracy class

the pump (IL)) contact contact contact

set (IL)) at DOL (IL)) at star delta (IL)) at ATS

starter starter starter

HP

1.5XHP

5XFIL

2X FIL 3X FIL 1.5 X FIL/5A,

6/10/15VA, CL1.0

Note:

1. Ampere ratings to main, delta and star/ taping contacts shall be the same as per ampere calculated for starters.

2. Thermal timer delay relay or digital timer delay relay shall be adjustable between 3-12/15 second

3.

for changeover to full voltage.

Starter must be suitable for 15 start stop per hours

Page 69: E-TENDER FOR - AWS

Data sheet for Electrical Items Part-III

(Recommend Rating of 3 core flat cables conforming to IS 694:1990) Conductor Insulation Sheath Overall Dimension Conductor Current

resistance carrying Area No. Dia Thickness Thickness(Nom) Width Height

@ capacity

sq. of

(Nom)

mm

(Approx)'W'

(Approx)'H' 20c(max) @ 40C mm. strands mm mm mm

ohms/km. Amps mm

1.5 22/0.30 0.6 0.9 10.3 4.9 12.10 14

2.5 36/0.30 0.7 0.7 12.6 5.8 7.41 18

4.0 56/0.30 0.8 0.8 14.8 6.6 4.95 26

6 84/0.30 1 1.15 18.7 7.9 3.3 31

10 140/0.30 1 1.4 23.7 9.9 1.91 42

16 226/0.30 1 1.4 28 11.4 1.21 57

25 354/0.30 1.2 2 35.5 14.7 0.78 72

35 495/0.30 1.2 2 39.5 16.2 0.554 90

50 703/0.30 1.4 2.2 45.5 18.3 0.386 115

70 360/0.50 1.4 2.2 51 20 0.272 143

95 475/0.50 1.6 2.4 60 23.5 0.206 165

H.P. 5 7.5 10 12.5 15.5 17.5 20

Amp 7.5 11 14.9 18.9 22.5 25.2 28.4

H.P. 25 30 35 40 45 50 55

Amp 35.6 42.3 50.4 58.1 62.1 67.5 73.8

H.P. 60 65 70 75 80

Amp 81 87.3 93.6 100.8 108

Page 70: E-TENDER FOR - AWS

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR

SITC OF CWR PUMPING PLANT

This tender includes (A) Supply, Installation, Testing and Commissioning (SITC) and (B) Trial run of Vertical Turbine clear water pumping plants, substation, and other appurtenant work at

Zonal CWR. All electrical and mechanical works shall be under scope of this tender even it has been left

out in narratives of this works shall have to be completed in strict compliance of the relevant ISS/IER.

The capacities and general specifications of the equipments are given here as under.

1. VERTICAL TURBINE PUMP SET WITH 4.5 METER COLUMN ASSEMBLY:

Clear Water Vertical Turbine pumping set suitable for CWR fitted with dynamically balance bronze

impellers mounted on a stainless steel pump shaft with shaft protection sleeves having stage bowls of

closed grained cast iron. The pump will be fitted with built in non-return valve and shall be suitable

for direct coupling to the squirrel cage electric induction, water cooled type submersible motor

suitable to operate on 400 ± 10% V, 3 phase, 50 cycles/sec. A.C. Power Supply and capable to give a

desire discharge and head as mentioned in schedule G.

PARALLEL OPERATION OF PUMPS

The tenderer shall have to study and to submit the parallel operation curve of the pumps to be

operated in parallel. The system resistance curve should be drawn and should be superimposed with the

parallel operation curve to ensure the proper running of the pumps in parallel

At ZPS out of 3 pumps, 1 pump will be stand by and 2 pumps shall run in parallel for

which curve is to be drawn.

The head calculation data are to be provided by the tenderer to draw the system resistance

curve and parallel operation curves. The possibilities of change of duty point of each pump in

parallel operation cannot be ruled out, under such conditions tenderer shall have to submit their offer

with design and its analysis and curves justifying the change of duty.

(A) Design Requirements

a) The pumps shall be capable of developing the required total head at rated capacity. The pumps

should almost operate satisfactory at any point on the HQ characteristics curve over a range of

75% to 110% capacity.

b) The power rating of the pumps motor shall be larger of the following:- i) The maximum power required by the pump from zero discharge to full value of discharge. ii) 115% of the power required at the duty point if power consumed at duty point by pump comes

out to be up to 75 HP. If it is more than 75 HP than it will be 110% of the power consumed at

duty point.

(B) PUMP SET: 1.3.1 A Standard hydrostatic test on all pressure containing parts shall be made at 1.5 times the

maximum discharge pressure.

1.3.2 The bowls shall be equipped with replaceable casing bearing.

1.3.3 The bowl assembly shall bear a name plate preferably embossed information as per following:

a) Name of the manufacturer or trade mark. b) Serial number of the pump set. c) Pump type. d) Number of stages.

e) Total head.

Page 71: E-TENDER FOR - AWS

f) Shut off head. g) Capacity.

Note: Shut off head must be above 25% of the total head required. 1.3.4 The impeller shall be of enclosed type equipped with seal rings on their hubs. Seal rings shall be

provided either with impeller or in the bowl.

1.3.5 The pump shaft shall be guided by bearing provided in each bowl of above and below the impeller shaft

assembly. The shaft without sleeves shall have a surface finish 0.75 micron Ra Max. 1.3.6 The opening in the suction case for the entrance of water shall be of proper size and shape to

avoid eddy currents.

1.3.7 The suction case shall be fitted with a strainer made of corrosion resistant material. 1.3.8 Suitable sand guard shall be provided just above the suction case bearing to prevent the entry of

foreign matter into the suction case.

1.3.9 Non return valve shall be provided above the pump discharge case. Note: The Pump should not be more than two stage

C. SUBMERSIBLE MOTOR:

9. The submersible motor shall be squirrel cage induction motor. 10. The winding of motor shall be wet type. 11. The motor shall be suitable for operation voltages and frequency confirming to IS 585-1962

(revised) “Voltages and frequency for A.C. transmission and distribution system” 12. The earthing of the motor shall comply with IS: 3043-1966 code of practice for earthing. 13. The Thrust bearing shall be of adequate size to withstand the weight of all rotating parts as well

as the imposed hydraulic thrust. These shall be lubricated suitably. 14. The Motor winding and nearing bushes of the rotor shaft shall be cooled/lubricated by pure

water filled in the motor before erecting the pump set. 15. The motor shall be protected by means of cable glands, rubber seals etc. from ingress of

tubewell water, sand and other foreign matter. 16. The thrust bearing housing shall be provided with a drain plug to empty the pure water filled into

the thrust bearing housing/Motor. 17. The rotor shaft shall be provided with shaft protecting sleeves having a surface finish of 0.75

micron Ra max. 18. The Motor shall be provided with a breathing attachment like bellows, diaphragm etc. to

compensate the Volumetric variations due to change in temperature. 19. The motor shall be made of corrosion resistant materials or suitably treated materials to resist

corrosion. 20. The motor shall have a name plate preferably embossed on body of motor giving the following

information :

a) Induction Motor; b) Name of Manufacturer;

c) Manufacturer’s number and frame reference; d) Type of duty; e) Frequency in Hz; f) Number of Phases; g) Rated output in HP/KW; h) Rated voltage and winding connections; i) Current in amperes at rated output.

j) Speed in RPM at rated output. (a) DATA OF PUMP SET:

These shall be furnished in the following manner’s

a) Model of motor. b) Model of pump. c) Discharge in LPM.

d) Total head.

Page 72: E-TENDER FOR - AWS

e) Nett effective head. f) Number of stages.

g) Pump outlet size in mm. h) O.D. of pump in mm.

h) MOC of each and every component of the pump set. i) Speed of pump set.

j) Method of starting. The performance details as per enclosed schedule ‘E’ are to be submitted as per enclosed sheet separately.

E. M.S. COLUMN PIPE

(i) M.S. Column pipe shall be 7.1mm thick 1.5 meter long threaded and welded double flanged

(ii) The flange shall be made up of 16mm thick M.S. flat respectively.

F. SHOP TESTING

The following shop tests shall be witnessed by Engineer incharge of the project.

Standard Running test as per relevant IS at rated speed in Manufacturer’s works to measure capacity,

total head, efficiency and power. These tests will form the basis for acceptance of pumping plant.

The pumping plant shall be tested over the range covering from shut off head to the maximum flow.

The duration of the test shall be minimum one hour. Minimum five readings approximately

equidistant shall be taken for plotting the performance curves.

2.0 SOFT STARTER The soft- starter shall be developed and qualified in accordance with international standards,

particularly with the standard dedicated to soft-starter EN / IEC 60947-4-2. The starter must be

CE marked under the harmonized standard EN / IEC 60947-4-2.

Description

The operating principle of the Soft-starter should not simply take ground on a limitation of motor

current during the transitional phases or on a voltage ramp but on a torque control motor. The Soft-

starter should provide a torque ramp during the acceleration phase. Thus, it can control the torque

during the starting period and if necessary provide a motor torque constant throughout the

acceleration phase. For pumping applications, the deceleration will be on torque a ramp.

All Soft-starter sizes will have the same control board. That control board must be identical

for all applications.

All Soft-starters shall be equipped with means for measuring motor current to ensure protection.

The measurements of the current will be active when the Soft-starter is by-passed (embedded

by-pass for all sizes).

The Soft-starter should have a separate power control.

The terminals of the board control shall be of plug type for easy maintenance.

Soft Starter should control 3-phase output with Programmable display.

The Soft-starter will handle the by-pass itself: manage the closure of the by-pass at end of

acceleration time and open that by-pass at end of stop sequence. That function must be

compatible with the types of stop: freewheel, ramp

The access to the settings can be locked by code. The monitoring parameters should

remain accessible.

Page 73: E-TENDER FOR - AWS

Environment

The maximum relative humidity will be 95% without condensation or dripping water according

to standards IEC60947-4-2.

The storage temperature can be between -25 ° C to + 70 °

Electrical characteristics of the Soft-starter

The Soft-starter will automatically adapt itself to the frequency of the mains 50 or 60 Hz with

a tolerance of + / -10%.

Outputs: the Soft-starter must have at least 2 relays with a NO/NC contact Maximum switching

capacity on inductive load: 2 A at 250 Vac and 30 Vdc.

Protections

· The starter will include the management of Motor PTC probe. · The starter will calculate continuously the motor overheating from the real current value (the

current must be measured and not estimated). Several classes of thermal protection will be

proposed following the standard EN/IEC60947-4-2: Classes 10, 20, 30.The calculation of the

thermal protection must be active even when the Soft-starter is not power energized.

· The starter shall be protected against thermal overload, over & under voltage. · Dry run protection for pump motor. · Protection against reverse-phase network, the loss of phases on mains or on motor. · The protections will always be maintained even the Soft-starter is by-passed internal or self.

Display

· The starter shall have a display and programming push buttons. · The following information must be accessible on the display - Motor current (by phase) - Motor state - Current status (acceleration, deceleration, Running). - Operating time. - The last fault occurred - Fault history - I/O status

Contacts A. The motor starter contractors shall be of the electromagnetic type of uninterrupted duty as

defined in IS 2959 unless otherwise specified.

B. Contact shall be of the double break non gravity type. C. Main contacts of contact shall be of silver plated copper. D. Each contact shall be provided with 2 No. auxiliary contacts. E. Insulation classes of operating coils shall be of class ’E’ or better.

Epoxy Resin Cast Thermal Overload Relays (of suitable range & capacity) (a) Thermal overload relays shall be hand reset. This hand reset, device and ‘STOP’ push button of

starter shall be separate from each other.

(b) The starter shall be complete with three elements positive acting ambient temperature

compensated time lagged thermal overload relay with adjustable settings.

(c) Overload rest push button shall be brought out on the front of the compartment door. (d) Overload relay shall be provided with 1NO. AND INC

contact. Thermal Time Delay Relay

(a) It shall be hand reset to fix time for low voltage starting and full load

starting. Single Phasing preventers

Page 74: E-TENDER FOR - AWS

(a) Single phasing preventers relay shall be provided.

(b) The single phasing preventor shall be of the current operated type. The relay shall not operate

for supply voltage unbalance of 5% but shall positively operate for unbalance more than 5%.

The relay shall operate in the event of single-phase fuse blowing. (c) After sensing a single phasing, the relay shall operate with a time delay of 2X3 seconds. The relay

shall not operate for a 3-phase power supply failure. The relay shall be of the hand-reset push

button. Resetting shall be instantaneous and independent of the adjusted time delay in the tripping of

the unit. Visual indication for the operation of the relay shall be provided. (d) The relay shall be suitable for application to protect reversible and non-reversible motors. The

relay operation shall be independent of H.P. rating and the R.P.M. of the motor. The relay shall

be of failsafe type and shall operate to trip the motor when the relay internal wiring is

accidentally open circuited. 3. LT CONTROL PANEL:

The control panel shall be compartmentalized cubical type, dust and vermin proof 2.4mm

thickness steel sheet fabricated, floor mounting type having aluminum bus bars. All operative control

should be above waist height (Around 4’) and metering around eye level AND IT SHOULD BE

COMPATIBLE FROM AUTOMATION POINT OF VIEW IN FUTURE

The control panel should consist of one incomer and 3 outgoing feeders for each pump

starter, also separate feeder for light & fan and other miscellaneous works in spare having

separate power terminals and control terminals along with APFC panel as follows:-

a) Incoming feeder:-

The incoming feeder should generally comprise of the following: - i) 1 No. required capacity MCCB with overloaded and earth fault protection and all other

protections provided by the manufacturer.

ii) 96 mm. sq. dial CT operated voltmeter with a range from 0-500 V with voltage selector switch-1 No.

iii) 96 mm. sq. dial CT operated ampere meter of suitable capacity with ampere selector switch-1 No. iv) 96 mm. sq. dial CT operated Power factor meter – 1 No. v) 96 mm. sq. dial CT operated frequency meter – 1 No.

vi) Indicating lamps, toggle switches and instrument fuses – 1 No. vii) KW meter of suitable capacity CT operated – 1 No.

viii) Switch fuse unit of suitable capacity - 1 No.

ix) Control MCB -1 No.

c) Outgoing feeders:- (A) Outgoing feeders five nos. each comprising of the following:-

i) Required capacity, MCCB, manually draw out in built overloaded and earth fault protection and

all other protections provided by the manufacturer – 1 No.

ii) 96 mm. sq. dial CT operated ampere meter with selector switch – 1 No. iii)

iv) Power contactor with 2 NO/NC – 1 No.

Single phase preventor – 1 No.

Page 75: E-TENDER FOR - AWS

v) OV/UV Relay – 1 No.

(B) Spare feeders 3 Nos. each comprising of the following: - i) MCB of suitable capacity – 1 No. ii) 96 mm. sq. dial CT operated ampere meter with selector switch – 1 No.

(Note: The tenderer has to quote the capacity of MCCB's of rating 50KA and its make and CT’s

should be resin cast type & dual core, also auxiliary contactors to be provided for automation in

future)

All or part of control panel, metering, protection and other necessary equipment specified

in the following clauses of the specification shall be provided as and when called for in the

accompanied specification.

Codes and Standards:

The design, manufacture and performance of equipment shall comply with all currently

applicable regulation and safety codes in the locality where the equipment will be installed.

Unless otherwise specified, equipment shall conform to the latest applicable Indian,

British or USA standards.

Some of the standards are given below:-

a) IS 375 Auxiliary wiring and bus bar marking

b) IS 722 Energy meter

c) IS 1248 Indicating instrument

d) IS 2147 Degree of protection provided by enclosure

e) IS 2208 HRC fuses

f) IS 2705 Auxiliary current transformer

g) IS 3156 Auxiliary Voltage transformer

h) IS 3231 Electrical relays for power system protection

i) IS 4047 Air break switches

j) IS 2516 AC Circuit Breaker

k) IS 5124 AC induction motor starter

l) IS 3427 Metal indoor switch gear and control gear for voltage Above

100 V but not exceeding 11000 V

Extent of Work

The extent of the work included in the specification is as follow:

Design, fabrication of complete panels, provision for all associated equipment and wiring,

design and selection of all the components shall be made liberally with a good margin of safety

factor and considering the following points in mind.

Procurement (except specifically noted as supplied by purchaser) and mounting of all

equipment specified in the accompanied equipment list, data sheet, drawings and specification

together with such auxiliary equipment and materials as may be adjacent or complementary to

those specified.

Page 76: E-TENDER FOR - AWS

All internal wiring to equipment and terminal block and wiring between adjacent panels.

Electrical and instrumentation detailing outlined in this specification and the accompanied

specification.

Preparation and furnishing of all drawings as required including schematic wiring, internal

wiring and external cable connection drawings.

Testing of panels and associated equipment accessories and furnishing of test

certificates. Preparation and furnishing of instruction, operating and maintenance

manuals.

Constructional Feature

The control panel shall be completely metal enclosed and shall be dust, moisture and

vermin proof. the enclosure shall provide a degree of protection and specified in data sheets but

not less than IP 54 in accordance with IS: 2147

Panels/desks shall be free standing, floor mounting type and shall comprise rigid welded

structural frames enclosed completely with specially selected, smooth finished, hot rolled sheets

steel of thickness not less than 3 mm for front and rear portions and 2.5 mm for sides top and

bottom portions. There shall be sufficient reinforcement to ensure a plain surface to limit

vibration and provide rigidity during shipment and installation.

The control panel/desk shall be assembled with channel/angle base plates

with anti-vibration mountings. The vertical panel shall be freestanding type with removable

covers at back. All bolts nuts and screw etc. appearing on panel shall be arranged as to present a

neat appearance, lifting hooks shall be provided such that no openings are left when hooks are

removed. All hooks, bolts and just exposed to external atmosphere shall be chromium plated or

zinc plated.

Operating handles of the doors shall have locking arrangement, There shall be no

sharp door covers to avoid injury to personnel.

The control desk shall be provided with hinged door on the rear and

removable access cover on the front. All doors, removable covers and panels shall be gasketed

all around with neoprene gaskets. Ventilating covers if provided shall have screens. Fittings and

due collecting devices shall be made of either brass of GI wire mesh.

Design, Material selection and workmanship shall be such as to result in neat appearance

inside and outside with no welds and reverts apparent from outside, with all exterior surfaces

free and smooth.

Panels desk shall be suitable for floor mounting. Metal stills in the form of metal channels properly

drilled shall be furnished along with anchor bolts and necessary hard ware for mounting the panels. These

shall be dispatched in advance so that they may be installed and leveled, when concrete foundations are

poured. The foundation and supporting frames, anti-vibration strips and fixing bolts, nuts, washers etc.

shall be supplied to suit the requirements.

The panels/desk shall be liberally sized so as to provide spacious layout of equipment

and devices with sufficient working space in between.

If a control panel consists of a number of panels, each panel shall be mounted side/by side

and bolted together to from a compact unit. Where two panels meet, the joints shall be smooth,

close fitting and unconstructive.

Page 77: E-TENDER FOR - AWS

The maximum and minimum height of the operating equipment on the panel shall be 2100 mm and 900 mm respectively from the floor level, stands height of the equipment comes within the

above limit. The proper supporting arrangement shall be provided by the bidder.

The following features are also required: 9. The circuit breakers, bus bar, instrument transformer’s and cables shall be installed in separate

compartment within the cubical.

10. The panels shall be so designed that it may be possible to extend on either side if required at

future date.

11. The panels shall be so constructed that failure of one equipment does not effect the adjacent

units. Suitable vent shall be provided to release gas pressure developed due to the operation of

breaker or breaker or due to live are at the bus or short due to shot circuits. 12. All bus connections, joints and taps shall be silver plated, connections shall be as short as possible. 13. Each cubical shall be provided with space heater with switch fuse and plug socket with switch

for connection of heat lamps rated 240 V single phase 50 C/S. Space heater shall be provided

with thermostats of approved make and type. 14. Wiring for space heater and lamps in each switch gears shall be grasped and brought out to

easily accessible terminals for external connection.

All sheet metal work shall be phosphated in accordance with the following procedure and in

accordance with IS “code of practice for phosphating iron and steel” after application of the primer,

two coats of finishing synthetic enamel paint shall be applied, each coat followed by stoving. The

colour of the finishing coat shall be as specified in data sheet ‘A’.

Finished painted appearance of panels shall present an esthetically pleasing appearance

free from dents and uneven surface.

A small quantity of finishing paint shall be supplied for minor touching up required at

site after the installation of panels/desks. The type of anti-vibration strips shall be subject to

purchaser approval.

Cable Entry: 1. The panels shall have provisions of cable entry from bottom. The removable cable gland plate

shall be provided to make entry dust tight and vermin proof. 2. The panels shall have provisions inside for fixing the multi-core cable glands. The cable glands

support plate shall be 4 mm thick. 3 Cable entries to the panels/desks shall be from the bottom. When called for in data sheet.

Necessary number of cable glands of sizes to suit purchaser’s internal cables to the panels shall

be supplied. Cable glands shall be screwed type and made of brass.

Mounting:

All equipment in front of panel/desks shall be flush mounting type.

All equipment shall be so mounted that the removal and replacement may be accomplished

individually without interruption of service to others.

All equipment inside the panel/desk shall be so located that their terminals and adjustments

are rapidly accessible for inspection or maintenance.

No equipment shall be mounted on the doors without prior approval of purchaser.

Where applicable Auxiliary bus bars for AC and DC suppliers, Pt circuits and other common

service shall be provided near the top of the panels running through the entire length of he panels.

Page 78: E-TENDER FOR - AWS

These buses shall have nominal cross section equivalent to a copper of 6mm2 and permit two

independent supply points.

Fuses and links shall be provided for isolation of individual circuit from bus wire/bars

without disturbing other circuits.

Wherever practicable wiring shall be accommodated on the sides of the panel/desk, sharp

bends shall be avoided.

Wiring shall be adequately supported along its run to prevent sagging and strain on the

termination.

Wire termination shall be made with solder less compression type of tinned copper lugs

which grip the conductor and insulation. Insulated sleeves shall be provided at all the wire

termination. Wire shall not be spliced between terminal points. Each wire shall be identified at

both ends by engrave, Core identification, plastic ferrules with wires designation in accordance

with contractor wiring diagram fitted inside the panel.

Vendor shall be solely responsible for the completeness and correctness of the internal

wiring and for the proper functioning of the connected equipment.

Terminal Block:

Multi- way terminal blocks complete with necessary binding screws and markers for wire

connections and terminal strips for terminal identifications shall be furnished for terminating the

wiring and outgoing cables.

Terminal blocks shall be 650 V grade, 15 amp, rated with marking on terminal strips shall

correspond to wire numbers on the wiring diagram.

Terminal block of CT and PT secondary leads shall be provided with test links and isolating

facilities. Also CT secondary leads shall be provided with test links and isolating facilities.

The terminal block shall be grouped according to circuit functions and shall have at least

20% spare terminate. For different voltage, the terminal blocks shall be segregated.

Bottom of the terminal blocks shall be least 2.00 mm above the cable crutch of incoming

multi core cables.

The terminals shall be open clamp/stud type suitable for connection of at least two (2) 2.5 mm copper wire, per terminal from each side. Terminals with tightening screws sitting directly

on the conductor shall be accepted.

No more than two wires shall be connected to any terminal. If necessary a number of

terminal shall be jumpered together to provide wiring point.

The center lines of switches, push buttons and indicating lamps shall be matched to give a

neat and uniform appearance. Likewise the top lines of all meters relays and recorders etc. shall

be matched.

Wherever required, panels/desks shall be matched with other panels/desks in control room in

respect of dimension, colour appearance and arrangement of equipment on the front.

Cable Terminations:

The purchasers external cable connection will be terminated on the terminal blocks

provided in the control panel. All necessary cable terminating, such as gland plaster, packing

glands, crimp type termed copper lugs and brackets, wiring troughs and gutters etc. for

purchaser’s cable shall be included in Vender’s scope of supply.

Page 79: E-TENDER FOR - AWS

Electrical Instruments:

Indicating instrument

All electrical indicating instruments shall be circular 270 scale, 96mm. square moving coil

instruments suitable for semi-flush mounting with only flange projecting on vertical panels.

Instrument dials shall be white with black numerals and lettering, knife-edge pointers and

parallax free-dials shall be preferred.

Instrument shall conform to IS: 1248 and shall have an accuracy class of to 1.0 or better.

The number of digits provided shall be adequate to cover 1000 hours of operation.

Current coils of meters shall have a continuous over load capacity of 200% for both

accuracy as well as thermal limits. Also the coil shall withstand at least 10 times rated current

for 0.5 seconds without loss of accuracy.

Relays

All relay shall conform to IS 3231 or equivalent. They shall be suitable for semi-flush

mounting with only flanges projecting on the front with connection from the rear.

Relays shall be rectangular in shape and shall have dust tight, transparent from the rear.

All protective relays shall be in draw cases with built in test facilities. Test block and

switches shall be located just below each relay for testing unless otherwise specified. All

auxiliary relay and timers shall be supplied in non draw out cases.

All relays shall be suitable for operation at 50 Hz AC voltage operated relays and current

and times shall be designed for the DC voltage specified in data sheet and shall operate

satisfactorily between 70% and 110% of rated voltage.

Voltage operated relays shall have adequate thermal capacity for continuous operation.

All protective relays shall be provided with at least two pair of potential free output

contracts. For auxiliary relays and timer it shall be as specified in data sheet. Relay cases shall

have adequate number of terminals for making potential free connections, to the relay coils and

spare contracts. Paralleling of contacts, if any shall be done at the terminals on the casing of the

relay.

All protective relays shall be provided with externally hand reset positive action

operation indicator.

All timers shall be electromagnetic type only. Short time delays in milli- second may be

obtained by shading with copper lugs on auxiliary relays. This shall not affect the continuous

rating of the relay.

All relay shall be self next type unless other wise specified in respective data sheet.

Each relay shall have provision for easy isolation of trip circuit for the purpose of testing

and maintenance.

All relays shall with stand a test as per relevant IS code and standard.

Auxiliary seal in units provided on the protective relay shall be shunt reinforcement type.

Control Switches

Control and instrument switches shall be rotary type suitable for semi-flush mounting with access to

connection from the back by the removal of the cover.

Page 80: E-TENDER FOR - AWS

The following shall be operating handles employed for the different type of switches.

a) Breaker control switches Pistol grip or knob type discrepancy control switch with built in lamps b) Selector switches c) Oval knob (black)

Circuit breaker control switches shall be 3 positions, spring return to neutral type and shall have external

red and green indicating lamps. Red lamps shall be wired for continuous supervision of trip circuit with a

serials resistor. Alternatively, discrepancy type control switches with built in pilot lamps may be

provided. In addition to the pilot lamps, each discrepancy switch shall be supplied with a non lamp wired

to supervise the trip circuit when the circuit is in closed position.

The switches shall have spring return from close and trip position to after close and trip position respectively.

Also it shall be required to press the switch before turning to close or trip command position.

Instrument transformers shall be of the maintained type. Ammeter selector switches shall be of break type

contacts.

Contacts of the switches shall be of pure silver and the rating shall be suitable for their duty.

Push Buttons

Push buttons shall be of momentary contact type with rear terminal connection. Where specified in the

data sheet, the push buttons shall be so designed to prevent in advertent operation.

All push buttons shall have contacts of pure make with two normally open and two normally closed

contacts.

Indicating Lamps

Indicating lamps shall be of the panel mounting type with built in series connected resistor.

The wattage and resistance of the lamps shall be as follows:

Neon indicating shall be provided when specified in data sheet.

Bulbs and lenses shall be easily replaceable and inter- changeable. Tools if any required for this shall be

included in the scope of supply. L.T. Circuit Breaker:

L.T. Circuit Breakers shall be of following type:-

1. Moulded case circuit breaker. 2. Air circuit breaker

The provided circuit breaker shall confirm to relevant I.S. specification Moulded Case Circuit Breakers (M.C.C.B.):

M.C.C.B. should automatically isolate the electrical circuit under sustained over load short

circuit. The other construction feature shall be as per details given below: -

1. Operating mechanism shall be quick make, quick-break and trip free. It should be independent

of manual operation.

2. Housing should be made of heat resistant insulating material. All parts of circuit breaker should be

enclosed in moulded housing. Terminals should be accessible for external connections.

3. Operating handle should give clear tip indication i.e. ‘ON’ ‘OFF’ and ripping position should be

clearly visible.

4. M.C.C.B. shall consist of bimetallic element providing an inverse time current tripping

characteristic.

5. Magneto thermal release shall have three bi-metals giving thermal over load protection and

electromagnets which offer short circuit protection. This shall be direct acting. Electro-magnets

shall offer short circuit protection.

Page 81: E-TENDER FOR - AWS

6. All releases should operate on a common trip bar, so that all the phases get disconnected even

when fault occurs on only one of them.

7. Silver alloy contacts should have long electric life. The mechanism should be so designed that there

should be no arcing on the current carrying part of the contact. There should be strong wipe action of

the contact system for keeping the contact surface clear of oxide films. 8. Terminal should have large and sufficient dimensions to accept links or cable lugs, adjacent

phase terminal should be separated by insulated barriers with adequate clearances. Terminals

configuration should permit straight through cabling.

9. Back up fuse be provided. Specification of Air-Circuit Breaker (A.C.B.)

1. Triple pole draw-out A.C.B. suitable to operation 415 ± 6% 50 C/S A.C. supply shall be fully

interlocked horizontal withdraw-out type version with Hinged door. It shall be provided of

positively automatic safety shutters with pad locking facility, mechanical ON/OFF indication,

mechanical Service/Test/Isolated position indication, silver faced moving contacts and arcing

contact.

2. All contact subjected to arching should tipped with are resistance materials, Inter phase barriers

should also be incorporated.

3. Isolating contact of silver plated, multi-finger, spring loaded type should be provided. 4. Magnetic over current, release should be provided to offer protection against overload and short circuit. It

should be direct operated type or C.T. operated depending upon the ratings/load requirement. Release

should beset to trip the breaker between 75% to 15% or rated current.

5. The breakers should be interlocked to prevent access to live parts unless the circuit is dead. 6. The breaker should not be disconnected from the isolating contacts or re-engaged with the

contacts unless breaker is in the open position.

7. The breaker must be tripped before the door can be opened to gain access to the racking door is

open until ‘ISOLATED’ position is reached.

8. Main contacts should be shrouded automatically by a safety shutter preventing in advertent

contact with isolating contact in with-drawn position.

9. A.C.B. shall comply to IS-2516, I.E.C. –157-1 & B.S.4752 10. All rating of ACBS shall be tested as per I.S.

516. Main Bus Bars

Main bus bars shall be of aluminum alloy conforming to relevant I.S unless otherwise

mentioned in Data Sheet.

Bus bar shall be located in air insulated enclosure and segregated from all other

compartments of the cubical. Direct contact or accidental contacts shall not be possible with

the bus bars and primary connections.

All bus bar joints shall be silver faced. Spring washers shall be provided to ensure

good contacts. In case aluminum to copper connections are required, suitable bimetallic

connection or all bus bar joints shall be silver faced.

Bus bar shall be adequately supported on insulators to withstand dynamic stresses due

to short circuits. The bus bar support insulator shall conform to IS 2544.

Bus bar shall be insulated with extended PVC sleeves or other insulating material.

The PVC used shall be of high temperature grade (850C) and shall posses good dielectric

properties, high tensile strength and good finish. The joints and tops shall be covered within

insulating tapes covering which withstands a temperature of 850C. The size of bus bar shall be

selected making them suitable for future loads also.

Page 82: E-TENDER FOR - AWS

Automatic Power Factor Correction Panel

APFC Panel shall have intelligent Microprocessor based relay, 12 steps based on the

requirement. The relay shall have auto manual selection feature and shall adapt the direction of

CT besides, it shall possess salient features like –

1. Auto self adjustment to any capacitor step value

2. Multiple LCD data indication of Power factor at each phase(lead/lag), KW, KVA, KVAR,

Voltage, Load Current at each phase, Capacitor current at each phase, Injected KVAR to reach

target power factor, Frequency, etc. incl. of all preset

parameters & specified installation data

3. Automatic Self-adjustment for C/K value.

4. Three phase sensing suitable for three phase-unbalanced loads.

5. Operation time delay facility for 10-240 sec.

6. Memory back up to save the data in the event of power failure.

7. Alarm output for Capacitor or Contact failure, abnormal values of voltage,

current, KVAR, Power factor, Temperature, Frequency, etc.

8. No-volt relay features to immediately disconnect all capacitors in the event of

power failure.

9. Various protections i.e. over temperature, over harmonics, overload, etc.

10. Remote fault alarm indicator.

11. Power factor correction fault.

12. Facility to connect computer.

13. RS 232 serial port.

Tests

Relays and control panels shall be subjected to the following tests at Manufacturer’s works

1. Mechanical operation test. 2. Certificate of test previously conducted on these items or on similar equipments of similar

capacities and specification verification of degree of protection shall be submitted.

3. Electrical control, interlock and sequential operation. 4. Verification of wiring. 5. Type tests and routine test shall be carried out on all associated equipment as per relevant Indian

standard.

6. Certified copies of all test reports shall be submitted to the purchaser before dispatch of the

equipment. 4.0 CABLES

The scope of this tender includes power wiring with 3.5 core Al. cable of suitable capacity from

power transformer to LT panel and 3.5 core copper cable of suitable capacity from each out going feeder

to starter of each pump and from starter to motor. The cabling shall have to be done properly providing

necessary loop at end termination duly clipped and mounted on the

Page 83: E-TENDER FOR - AWS

sump wall of the pump house. Power wiring shall have to be carried out as per the latest relevant

IS/IER End termination should be lugged and then connected. The tenderer is required to quote

the size of the cable.

LT cables shall be rated for continuous operation and HT cables shall be rated for its short circuit. The sizes of cables shall be fixed after taking into consideration the derating factors applicable.

All cables shall be steel flat strip armored unless specified. Cable end box for HT cable shall be

furnished complete with heat shrinkable type termination, tabular tinned copper lugs, armour

clamps, gland plate etc.

MS CHEQUERED PLATES, 8 MM. THICK AND PAINTED WITH BLACK ENAMEL

PAINT FOR COVERING THE CABLE TRENCHES WHEREVER

REQUIRED/DIRECTED BY THE ENGINEER SHALL BE PROVIDED UNDER ALL

SUB HEADS. THE WEIGHT OF THE CHEQUERED PLATES SHALL BE AS PER

STANDARD TABLES AND IN DIAMOND PATTERN.

Wherever parallel double cables are to be laid, the capacity of individual cable should be

sufficient to take full load current required for ultimate load and other cable work as standby up

to ultimate stage.

Codes and Standards

The design, manufacturer and performance of the cables shall comply with all currently applicable

statues, regulations and safety codes in the locality where the equipment will be installed.

Unless otherwise specified, the equipment shall conform to the latest applicable Indian Standards.

a) IS: 1554 (Part – I) PVC insulated (Heavy duty) electric cables,

Part-I for working voltage up to and including 1100V

b) IS: 1554 (Part-II) PVC insulated (Heavy duty) electric cables.

Part-I for working voltage from 3.3 KV up to and

including 11 KV.

c) IS: 3961 (Part-I) Paper insulated (Heavy duty) electric cables.

Part – I for working voltage up to 3.3 KV.

d) IS:694 PVC insulated (Light duty) electric cables for

working voltage up to 1100V. e) IS:3961 (Part-II & V)Recommended current ratings for cables.

Part- duty

II-PVC

cables

insulated

Part –

and

V-PVC

PVC sheathed

insulated light

heavy

duty

cables. f)

IS-692-1965 (with latest

Paper Insulated Power Cables amendments)

g)

IS-7098

Specification for XLPE Cable

Cables shall be supplied on non-returnable drums made of seasoned wood.

For the following voltage grade, the cable length on each drum shall be subject to

purchaser’s approval.

S.No. Voltage Grade Conductor Size

1. 1100 V Above 95mm2

2. Below 1100V All sizes

Page 84: E-TENDER FOR - AWS

Installation of Cables 1 Contractor’s scope of work includes unloading, laying, fixing, jointing, bending and termination of

cables. Contractor shall supply all the necessary hard wares for jointing and termination of cables. Cables

shall be laid directly buried in earth, on cable trays and supports in conduits and duct or bars on walls

ceiling etc. Contractor shall route the cables as directed by purchaser.

All cable work and the allied apparatus shall be designed and arranged to reduce the risk of fire

and any damage that may cause in the event of fire wherever cables pass through any floor or

wall opening suitable bushes shall be supplied if required by the purchaser. The bushes shall be

seated using fire resisting materials to prevent fire spreading. 2 Standard cable installation tools shall be utilized for cable pulling. Maximum pull tension shall not

exceed the manufacture’s recommended value. Cable grips reels or pulleys used shall be properly

lubricated. The lubricant shall not injure the overall covering and shall not set up undesirable

conditions of electrostatic stress. Cable pulling shall permit performance collateral work without

obstruction. Shear bending and kindling of cables shall be avoided. The bending radius for various

types of cables shall be more than those specified by manufacturer. 3 Power and control cables shall be laid in separate cable trays. The order of laying of various

cable in trenches and overhead trays shall be as specified below.

Cables of highest system voltage at the top most tier with second highest voltage on the second

tier from top, third highest voltage on the third tier from top etc. with control instrumentation

and other service cable in bottom most cable tier. 4 Where groups of HV and LV and control cable are to be laid along the same route, suitable

barriers to segregate them physically shall be employed. Where cables cross roads and water, oil,

gas or sewage pipes, the cables shall be laid in reinforced spun concrete pipes of 150 mm

minimum diameter. Also 50% space shall be kept as space for future if more than one cable are

to be laid through pipe. For road crossing, the pipe for the cable shall be buried at not less than

one meter depth. Cable shall be protected at all times from mechanical injury and from

absorption of moisture. 5 Some extra length shall be kept in each cable run at a suitable point to enable or two straight through

joints to be made at a later date, if any fault occurs. To facilitate visual tracing, cables in trays shall be laid

only in single layers where design permits. Cable splices shall not be permitted. 6 Cable jointing shall be in accordance with relevant Indian standard codes of practice and manufacturer’s

special instructions. Materials and tools required for cable jointing work shall be supplied by contractor.

Cables shall be firmly clamped on either sides or a straight through joint at not more than 300mm. away

from the joints. Identification tags shall be provided at each joint and at all cable terminations. Single core

cable joints shall be marked so that phase identification at each joint can be determined easily. The joints

shall be located at most suitable places. When two or more cables are laid together, joints shall be

arranged to be staggered at about three meters. Before jointing, insulating resistance of both sections of

cables to be jointed shall be checked. 7 Contractor shall install and connect the power, control and heater supply cables for motors.

Contractor shall be responsible for correct phasing of the motor power connecting and shall

interchange connection at the motor terminal box if necessary after each motor is test run. 8 Metal sheath and Armour of the cable shall be bonded to the earthing systems of the station. 9 Cable clamps shall be minimum 3 mm thick and 25 mm. wide galvanized M.S. flat spaced at

every 1.0 m interval.

Page 85: E-TENDER FOR - AWS

Conduits & Pipe 1. Contractor shall supply and install conduits, pipes as specified. All accessories/fittings required

for making installation complete shall be supplied by the contractor. Conduits and pipes shall be

GI and of heavy duty type. Flexible metallic conduits shall be used for termination of

connections to equipment to be disconnected at periodic intervals. Conduits or pipes shall run

along walls floors and ceilings on steel supports embedded in soil, floor, wall or foundation in

accordance with relevant layout drawings.

2. Exposed conduit shall be adequately supported by racks clamps, straps or by other approved means.

Each conduit run shall be marked with its designation as indicated on the drawings.

3. When one or more cables are drawn through a conduit cable. Cable shall fill not more than 50%

of the internal cross sectional area of the conduit.

4. Entire system of conduit after installation shall be tested for mechanical and electrical continuity

throughout and permanently connected to earth by means of special approved type earthing

clamp efficiently fastened to the conduit

5.0 EOT CRANE

03 Tonne suitable for pump house alongwith all girders as per design & site conditions.

A. CRANE

a) The crane bride shall consist of a single bridge girder carrying two wheels at each end of the span

and 2 Nos. long travel girders for entire pump house as per drawing/site conditions.

b) The long travel bridge wheels shall be rim toughened, head treated carbon steel. They shall be

double flanged type. The wheels shall have antifriction bearings. The wheels shall be machined

on their treads to match the runway rail section. The bridge shall have a geared shaft and pulley,

connecting to opposite wheels of the span to manpower the long travel motion of the bridges by

means of a chain supplied with the crane. The runway rails of adequate strength and rigidity¸ rail

clamps and other accessories for mounting the rails on the structure and suitable end stops for the

bridge shall be provided.

B. TROLLEY AND CHAIN PULLEY BLOCK

a) The chain pulley block shall be operated on the lower flange of the bridge girder. b) The load chain shall be made of SS-410. It shall be heat treated to give ductility and toughness.

It shall be welded construction with a factor of safety not less than 5.

c) The load wheel, main arm holding upper hook and the B block holding bottom hook shall be

made of heavy duty malleable casting.

d) The hand chains for the hoisting and traverse mechanism shall hang well clear of the hook and

both the chain shall be on the same side. The hand chain wheel shall be made from pressed sheet

steel and shall be provided with roller type guarding. e) All the gearing shall be totally encased. Gears shall be out from solid cast of forged steel blanks. Pinions

shall be of forged carbon or heat treated alloy steel. Gears shall be as per IS 436.

f) The trolley track wheel shall be rim toughened, head treated carbon steel or lows alloy steel or

graded CI and shall be single flanged and shall have antifriction bearings.

g) The travelling trolley frame shall be made of rolled steel. The side plates of trolley frame shall

extend beyond wheel flanges. The two side plates shall be connected by means of an equalizing

pin.

Page 86: E-TENDER FOR - AWS

h) Axles and shafts shall be made of carbon steel. i) The lifting hooks shall be forged, heat treated alloy or carbon steel. They shall be of single hook type

provided with a standard depress type safety latch. They shall swivel and operate on hardened races.

Locks to prevent hooks from swivelling shall be provided. Hook shall be as per IS 3815.

j) The brake for the lifting gear shall be screw and friction disc type and shall offer no resistance

during hoisting. Over load test at 150% of rated load for chain pulley block and trolley,

overloaded test of 125% of rated load and deflection test with 100% of rated load for the crane.

Test certificate has to be given by the fabricator/manufacture. 6 & 7 SLUICE VALVE

(A) DESIGN REQUIREMENTS

a) Sluice valves shall generally confirm to IS:780 and IS:2906. Additionally they should also meet

specific requirements mentioned in the following paragraphs.

b) Valves shall close with clockwise rotation of hand-wheel. The direction of closing shall be cast

on hand wheel.

c) Valves shall be designed for 10 bar rating. (B) FEATURES OF CONSTRUCTION

a) Valves shall have non-rising spindle. b) Valves shall be with bushing for replacement of packing without leakage. c) Valves of size 350mm and below shall be with renewable channel and shoe arrangement. d) Valves of size 350mm and above shall be supplied with worm/bevel gear arrangement so that

the valve can be operated with an effort not more than 7 kg-m on the hand wheel.

e) Nominal size of the valve shall be cast on the body of the valve. (C) MATERIAL OF CONSTRUCTION

Body - Cast iron IS 210 Gr FG 200

Wedge - Cast iron IS 210 Gr FG 200

Spindle - Stainless Steel AISI 410

Seat rings - Gun metal

Shoe - Gun metal

Channel - Gun metal lined

(D) SHOP TESTING

To be witnessed by engineer Incharge of project (if necessary) - Seat leakage test at 10 bar. - Backseat leakage test at 5 bar. - Body hydrostatic test at 15 bar.

8 & 9. NON-RETURN VALVES

(A) DESIGN REQUIREMENTS

a) Valves shall be with non-slam characteristics. b) Valves shall be suitable for mounting on horizontal pipe line. c) Hydraulic passages shall be designed to avoid cavitations. d) The internal parts shall be accessible through inspection hole. e) Valves shall be designed for 10 bar rating.

Page 87: E-TENDER FOR - AWS

(B) FEATURES OF CONSTRUCTION

a) The non-slam characteristics shall be achieved either providing suitable combination of door and

hydraulic passage or by a dashpot arrangement.

b) Valves of size 500mm and above shall be provided with supporting foot. c) No by pass is required for the valves. d) Nominal size of the valve shall be cast on the body of the valve.

(C) MATERIALS OF CONSTRUCTION

Body - Cast iron IS 210 Gr. FG 200

Door - Cast iron IS 210 Gr. FG 200

Body Ring - Gun Metal

Door Ring - Gun Metal

Hinge Pin - AISI 410

(D) SHOP TESTING – To be witnessed by engineer incharge (If necessary) - Seat leakage test at 10 bar. - Body hydrostatic test at 15 bar.

10. M.S. /CI DF DELIVERY PIPING

A. GENERAL

a) The pipes shall be of uniform bore and straight in axis. Length of the straight double flanged pipes

shall be within a tolerance of ± 1.5mm. The thickness of fittings shall be 8 mm.

b) The flanges of the straight pipes shall be square to the axis of the pipes. The faces of the flanges shall

be parallel. The bolt hole circle shall be concentric with the bore and bolt holes equally spaced. In

straight pipes the bolt holes in one flange shall be located in line with those in other. c) The faces of the flanges of the fittings shall be square of the directional exes. The bolt holes shall

be located symmetrically off the centre line. The intersecting axes of the toes shall be

perpendicular to each other.

d) The bolt holes on flanges pipes and fittings shall be drilled with the help of drilling jig. B. MILD STEEL/CI PIPES AND FITTINGS

a) Materials of steel pipes and fittings shall confirm to IS:22 flanges to IS:2062 and IS: 1538. b) Fabricating and testing shall be in accordance with IS: 3589. c) Hydrostatic test pressure shall be 15 bar. d) Pipe surface shall be cleaned thoroughly by shot or sand blasting process, so that it is completely

free from rust and dirt. The cleaning shall be so carried out that it shall be free from mill scale,

rust, oil, welding scale and other foreign materials. At field, however, the surface may be cleaned

by wire brushing.

e) The primer paint shall be of material recommended by the manufacturer for the grace of enamel

used and shall be applied as recommended by the manufacturer. Freshly primed pipe shall be

handled carefully before applying enamel. f) Enamel shall be moisture and dirt free at all times prior to and at time of heating and application. The

primed surface shall be dry and clean at all times and the enamel shall be applied not later than 3 days

after application of primer. Along with first flood coat of enamel single spiral wrap of fibre glass inner

wrap shall be applied overlapping at least 20 mm on pipe upto 250mm diameter and 25mm on larger dia

pipe. The total thickness of the coating shall not be less than 2.5mm.

Page 88: E-TENDER FOR - AWS

g) Each end of the pipes left bare for welding purpose shall be hand coated and wrapped after field

welding is completed and hydro tested. 11. PRESSURE GAUGES

a) Each main pump shall be provided with pressure gauge of the range (0-7 Kg/cm2 ) and

depth gauge. b) The gauges shall be of bourdon type. c) The error in pressure indication with either increasing or decreasing pressure shall not exceed

1.5 % of the maximum scale value.

d) The dial size of gauge shall not be less than 150 mm. e) Gauges shall generally confirm to IS:3624.

12. GALVANISED NUTS, BOLTS, STUDS AND WASHERS AND RUBBER PACKING

a) Nuts and bolts shall be of the best quality bright steel, machined on the shank under the head and

nuts. Studs, bolts and nuts shall be electro-galvanized. Bolts shall be of acreage length so that

only one thread shall show through the nut in the fully tightened conditions. b) Washers, locking devices and anti-vibration arrangements shall be provided where necessary. c) Where there is a risk of corrosion, bolts and studs shall be designed so that the maximum stress

does not exceed half the yield stress of the material under any conditions. All bolts nuts and

screws which are subject to frequent adjustment or removal in the course of the maintenance and

repair be made of nickel bearing stainless steel.

d) The contractor shall supply all holding down, alignment and leveling bolts complete with

anchorages, nuts washers and packing required to fix the plant to its foundations, bed plates,

frames and other structural parts.

e) The contractor shall procure and keep at site reasonable excess quantities to cover wastage of

those materials, which will be normally subject to waste during erection, commissioning and

setting to work.

f) Rubber packing shall be as per IS. Make of nut, bolt, washers etc. should be mentioned in the

offer.

13. INTERNAL ELECTRIFICATION OF ZONAL PUMPING STATION: -

It will be done in copper concealed PVC wiring along with tube light and bulkhead etc. as per

UPPWD electric work specifications as direction of engineer in charge.

14. FIRE EXTINGUISHER

The contractor shall provide adequate supply of approved fire extinguishers and refills for the works.

In this regard he shall consult the engineer as to the suitability of the appliances which he proposes to

supply. A combination of chemical type and sand buckets 15 Ltr. have to be provided.

A. Chemical type 5 kg 2 Nos.

1 Set B. Sand buckets 5 Nos.

First Aid Facilities

The contractor shall provide complete first aid facilities for his staff (and other) till the date of

the handling over of the works. The facilities shall be fully available on the day of the

commencement of the plant. 15. EARTHING SYSTEM (CONFORMING TO IS 3034 & IER)

Two separate and distinct earth leads shall be used for earthing each equipment/structures enclosing

the power conductor and one earth lead for metallic structure adjacent or electrical installation metallic

frames of all electrical equipment rated above 250 volts, must be earthed by two distinct connection with

earth system. Earthing cables crossing other metallic structures such as conduits, pipe lines etc. shall be

minimum 300 mm away from such structures. All underground

Page 89: E-TENDER FOR - AWS

connections and joints in earthing system shall brazed welded. Connections with equipments/structures shall be bolted type. Conducting petroleum jelly shall be applied to

contact surfaces of all bolted joints and joints shall be covered with bituminous compound and

tapped. When GI. conductors are connected to aluminum conductors the contact surfaces of G.I. shall be tinned to prevent bimetallic corrosion. Neutral connection shall never be used for the

equipment earthing. Earthing conductors shall be protected against mechanical damage. Earthing

conductors running along the structures, well etc. shall be cleared at every 750 mm interval. Minimum size of earth conductor shall be in accordance with IS:3043. however, sizes of earth

conductors for equipment shall be at least half the size of power conductor, limited to maximum of 120 mm of aluminum. All earth lead connection shall be as short and direct as possible and

shall be without kink. Earth Pits and Main Grip

Adequate number of earthing pits and electrodes shall be used in conjunction with earthing grid.

Minimum spacing between two adjacent earth pits shall not be less than six (6) meter and shall be

kept sufficiently away from structures to clear footings. Main grid loop for a building shall be

installed outside boundary of the building buried to backfill. It shall be installed at a minimum depth

of 600mmoutsidethe building wall. The main earth loops in plant areas shall be generally routed

along cables when equipment is located away. Suitable sub-loops may be run up to them for deriving

connections for individual equipment. Indoor Equipment Earthing

Ear thing grid embedded in the floor slab shall have a minimum concrete cover of 50mm. Every

alternate column (steel or R.C.C.) of the building, housing, electrical equipment shall be connected to

main earthing grid. Earthing conductor shall be welded at interval of 1000 mm along their run of

steel structure and shall be at interval of 750mm along the wall.

16. ELECTRO- MAGNETIC FLOW METER

Direct on line Full Bore electro-magnetic Flow meter of suitable size for clear water

application. The flow meter shall be suitable for bi directional flow measurement. This shall be

having protection category of the sensor shall be IP68 and protection category for the transmitter

shall be IP- 65. Accuracy shall be of +/- 5% of measured value without being affected by variation in the line pressure. Equipment should be complete with converter, transmitting device

and should be fully programmable with digital flow indicator & integrator etc. The sensor

housing and junction box should be of SS.

Electrical Power Supply Power consumption

Output

Accuracy Repeatability Time constant Minimum conductivity Display

Data Entry

Flow data

Diagnostics

: 24 VDC OR 90 V AC to 265 V AC, 50/60 Hz : 35 W (max.) : a) 4-20 mA Isolated (Max. Load 800 Ohms). b) 2 SPDT Relay. Programmable relay function Max. rating 2A at 230 Vac for non-inductive Load. c) Pulse output: 24 VDC Pulse Isolated (min. Load 150 Ohms)

Option Frequency output of 0 to 1KHz full scale : ± 1% of flow rate

: ± 0.1 % of F.S.D : 0.8 to 8 seconds adjustable

: 5 μS/cm (Micro Siemens/centimetre) : 16 x 2 Alphanumeric LCD, in multiple -Engg. units

: 2 Hall Effect Switches : Bi-directional Flow with separate totalizers

for forward and reverse flow : Empty Pipe Detection with Low Flow Cut off

: Built in with Data retention in case of power failure.

Password protection

Page 90: E-TENDER FOR - AWS

Enclosure Housing material : Cast Aluminium

Paint : Polyurethane

Cable entry : M 16 (3 No.) suitable for cable diameter from

4.5 mm to 10mm

Controller mounting : Integral with sensor or Wall mounted

Ambient Temperature : - 20 deg. C to + 60 deg. C Protection : IP 67 Sensor

Nominal Bore : 10 NB to 600 NB

Meter Lining : Rubber

Electrode Material : SS 316

Metering pipe Flanges : Low carbon steel, ASA 150 # flanges

Metering Pipe Material : SS 304

Sensor Body Material : Sheet Steel

Protection : IP 68

Process Temperature : + 80 deg. C

Process Pressure : Up to Size 200 NB: 16 bars

Sizes above 200 NB:10 bar

Certification : CE certified, RoHS from DNV & FM approval

FM Certified

17. PAINTING OF ALL EQUIPMENTS

All items of metal work shall be thoroughly washed, dried, cleaned, degreased before

application of any paint.

Normally, the initial coat shall be applied in the manufacturer’s shop. After arrival of the

equipment on site, the same shall be inspected and damaged portions shall be cleaned and given

the primer and under coat of similar paint.

After erection, metal works shall be painted as follows:

a) Surface painted with red oxide or primer or with oil based under coat shall receive two under

coats and one finishing coat of approved oil based paint.

a) Bituminous painted surfaces shall receive two coats of approved bituminous paint.

b) Galvanized surfaces shall be primed with chromate prime followed by two under coats and one

finishing coat of approved oil based paint. c) All indoor parts, instruments and electrical equipment shall be chromium or copper nickel-

plated. The following tables gives the nature of surface and paints to be used. The contractor

shall study and follow this properly.

S.No. Surface

1. All railings, mild steel

Ladders, pipes for

water Supply

2. Submerged metallic parts

and their projections above water level.

Treatment

Galvanization & two coats

of approved oil paints of

Approved Shades.

Anti corrosive paints suitable for sewage water.

Page 91: E-TENDER FOR - AWS

3. Metal parts above water level 4. All indoor fixtures, parts

instruments, equipment, panels etc.

Approved oil paint of approved shades. Chromium or nickel plating.

Page 92: E-TENDER FOR - AWS

The contractor shall clearly indicate the surface treatment for all metallic parts of the

plants in the schedule of particulars in details

SUBSTATION OF ZPS

NOTE: The drawing & installation of substation works has to be approved by Director Electrical safety

government of U.P. by the contractor and the rates for the same has to be inclusive in substation

works.

ISOLATOR VERTICAL BEAK TYPE WITHIN CAMPUS OF CWR WITH MESH

WIRE FENCING.

Electrical substation is to be provided with isolator and earthing switch for disconnecting the

circuit under no load conditions to ensure visual isolation. It is to be erected in such a way that a

party of 11 KV power supply to indoor contact breakers can be isolated visually from the HT

outdoor power supply for the purpose of easy and comfortable maintenance. Isolator shall be

vertical break type as per norms of IER and code of practice prevailing. It shall be incorporated

with earthing switch also between the outdoor heat shrink box and earth to make it sure that

capacity discharge is no more there. Earthing switches one or two shall be mounted on the frame

of isolator.

21. 11/.44 KV TRANSFORMERS (Should Confirm to IS 2026 & IS 1180)

The transformers shall be complete with all accessories and auxiliary equipment in accessories

with this specification in the following annexure:

Fittings and accessories: Off Circuit tap changer externally hand operated.

Oil conservator with filling hole and cap.

Plain oil level gauge with minimum level marking.

Thermometer pocket.

Silica- Gel Breather.

Drain cum filter valve.

Two earthing terminals

Lifting arrangements.

Explosion vent.

Air release plug.

HT and LT cable box.

OTI with alarm & trip.

Page 93: E-TENDER FOR - AWS

WTI with alarm & trip.

Marshalling box for OTI & WTI

First filling of transformer oil.

Special tools and tackles for erection and maintenance of the transformers & other requirements.

All relevant final drawings, data and instruction Manual for operation & maintenance of the

transformers and other equipment in triplicate.

At the option of the Engineer, the successful tenderer shall provide the services of a Senior

Engineer for following:-

a) Supervision of the erection, testing, commissioning and putting into successful commercial

operation of all equipments furnished under this specifications.

b) Supervision of power cable, control cable and bus duct connections at the terminals of the equipment for

interconnections with the equipment supplied by others and under this specification. This supervision

shall include coordination of controlling system with the equipment supplied by others and related to the

operation of the equipment under this specification.

DESIGN CRITERIA (as per is 2026 and 1180 as referred to guideline of apex court)

The estimated fault levels of different system with which the transformers will be connected are

given above.

The transformer shall be suitable for outdoor services in hot humid and topical climate. All

equipment, accessories and wiring shall therefore be provided with tropical finish to prevent

fungus growth.

The design shall be made to suit the site condition stated above of this technical specification.

Running load shoule be around 50 to 60% of transformer capacity and starting load not more

than 75% of transformer capacity has to be compiled with.

TYPE OF COOLING:

The transformers shall be oil immersed ONAN cooling and designed for cooling as

specified ahead: -

TEMPERATURE RISE:

The transformers shall be capable of continuous operation at its rated output without exceeding

the limit of temperature rise as follows: -

a) Winding by resistance: 300C above ambient temp0C

The derating of the transformer shall be done by taking 500C as an ambient temperature.

Page 94: E-TENDER FOR - AWS

VOLTAGE FLUCTUATION WITHSTANDING CAPACITY:

The transformers shall be appreciably free from noise and vibration and shall be capable of

continuous operation at the rated output under the following conditions:-

i) The voltage varying by +5 to -5% of rated voltage in 5 steps, 2.5% in each step and impedence

4.5%

ii) Frequency varying by ± 3% of the nominal value of 50 Hz.

iii) The transformers shall be able to withstand for 5 seconds without damage a short circuit between phase

and between phases and ground at one side, maintaining rated voltage on the other side. The under

frequency condition will not occur simultaneously with the over voltage condition.

SPECIFIC DESIGN REQUIREMENTS:

Tanks:

a) Tanks shall be of welded construction and fabricated from good commercial grade low carbon

steel of adequate thickness. All beams shall be properly welded to withstand requesting impact

without distortion. All welding joints shall preferably be stress relieved.

b) The tank wall shall be reinforced by stiffener for rigidity so that it can withstand any deformation.

i) Mechanical shock during transportation, and

ii) In full vacuum during filling of all.

c) The tank cover shall be bolted on to the tank with weather proof, hot oil resistant, resilient gasket

in between for complete oil tightness. If gasket is compressible, metallic stops shall be provided

to prevent over compression. Bushings, currents, cover of all access holes and other devices

shall be designed to prevent any leakage of water into or oil from the tank.

d) Each transformer tank shall be provided with one set of bi-directional rollers for rolling the

transformer parallel to either central line of the transformer.

e) Jacking pads, lifting eyes and pulling lugs shall be provide to facilitate movement of the

transformer. All heavy removable parts shall be provided with eyebolt for ease.

f) Manholes/Handholes of sufficient size shall be provided for access to leads, windings, bottom

terminals of bushing and taps if provided.

g) Oil sampling trap with valves shall be provided to collect samples of oil for testing from

different levels of the tank.

h) To facilities the oil filtration by streamline filters, suitable inlet and outlet taps with valves at

bottom and at the top of the tank on diagonally opposite corners shall be provided. The valve at

the bottom may be used as drain valve.

i) Thermometer – pocket for noting top oil temperature by liquid thermometer shall be provided.

j) The transformer tank shall be fitted with a diaphragm type of explosion relief vent at the top.

CORE AND COILS:

a) The transformer may be of core type. The core shall be built up with high grade, non-aging, low loss,

high permeability silicon steel laminations specially suitable for core material.

Page 95: E-TENDER FOR - AWS

b) The coils shall be manufactured from electrolytic copper conductor and shall be fully insulated.

c) All insulating material shall be of proven design. Coils shall be so insulated that impulse and

power frequency voltage stress are minimum. Insulation level of graded insulation shall confirm

to the relevant standard.

d) Coil assembly shall be suitably supported between adjacent sections by insulating spaces and

barriers. Bracing and other insulations used in assembly of the winding shall be arranged to

ensure a free circulation of the oil and to reduce the hot spot of the winding.

e) All leads from the windings to the terminals boards and bushing shall be rigidly supported to prevent

injury from vibration or short circuit stresses. Guide tube shall be used where practicable.

f) The core and coil assembly shall be securely fixed in position so that no shifting or deformation

occurs during movement of Transformer or under short circuit stresses.

TAPPINGS:

a) Off - load taps as specified shall be provided on the high voltage, winding. If tappings are

provided on the low voltage winding, the tenderer shall clearly indicate the same stating reasons

thereof.

b) The transformers shall be capable of operation at required capacity at any tap position provided the

voltage does not vary by more than ± 2.5% of the voltage corresponding to the tap.

c) The winding including the tapping arrangement shall be designed to preserve the

electromagnetic balance between HV and LV windings at all voltage ratios.

OFF-LOAD TAP CHARGES:

a) The off-load tap changing shall be effected by a 3 phase hand operated tap changing switch. The

operating shaft shall be brought out of the tank and provided with a hand wheel so that it can be

operated at standing height from ground level.

b) A visual tap position indicator for the tapping in use shall be provided at the external operating handle and

provision shall be made to padlock the handle in each tap position. The arrangement shall be such that

padlock cannot be inserted unless the contacts are correctly engaged.

c) All contacts of the tapping shall be silver plated and held on a position under strong contact

pressure so as to avoid contact pitting of any type whatsoever.

INSULATING LIQUID:

a) The insulating liquid shall confirm to the latest revision of IS:335 or BS: 148.

b) The transformers shall be dispatched with leak proof, first filling of oil.

c) The tenderer shall indicate clearly the following aspects of the design.

i) Composition and properties of the insulating Liquids.

ii) Liquid preservation system adopted and method of sealing.

CONSERVATOR TANK:

a) Oil preservation shall be by means of conservator tank. The tank shall be suitably mounted on a

rigid foundation. The conservator tank shall be connected with the main tank by the pipes with

stop valves at both sides.

Page 96: E-TENDER FOR - AWS

b) The conservator tank shall be provided with level indicator visible from the ground level, oil

filing plug & cap and oil drain valve.

c) The conservator tank shall be provided with dehydrating breather.

TEMPERATURE INDICATOR:

Oil & winding temperature indicators shall be provided. The local temperature indicator where provided

shall be so mounted that the same becomes readable at a standing height from the ground level. Alarm

and trip contact where called for shall be provided for suitable termination.

TERMINALS MARKING:

The physical position of the terminals and their markings shall be as per latest revision of IS:2026.

TERMINAL ARRANGEMENT:

i) Cable Connection:

a) High and low voltage terminals of transformers, which have been specified to be suitable for

cable termination shall be brought out through sidewall bushing to a weatherproof cable end box

with self-supporting disconnecting chamber. b) The cable end box shall be of plate steel construction, self supporting weather proof type having

suitable bus extension, if required, rigidly mounted on porcelain insulators.

COOLING UNITS:

The radiators of the transformer shall be designed for same pressure and vacuum conditions

as those for the main tank.

WIRING:

All controls, alarm indicators and relaying devices provided with the transformers shall be

wired upto the terminal blocks housed in a suited marshalling box and the terminal blocks shall be

suitable for termination of 7/0.737 mm copper conductor cable (1100 volt grade PVC insulated,

PVC sheathed armoured and overall PVC served cable as per IS. No two wires shall be connected to

one terminal. 10% spare terminals shall be provided.

PAINTING:

a) All steal surfaces shall be thoroughly cleaned by sand ballasting surface free of scales, rust and

grease.

b) All paints shall be carefully selected to withstand tropical heat, rain etc. The paint shall not scale

off or crinkle or be removed by abrasion due to normal handling.

c) All steel surface in contact with insulating oil shall be painted with heat resistant insulated

varnish which shall not react with and be soluble in the insulating liquid used.

d) After cleaning, the external surfaces shall be given a coat of high quality red oxide or yellow

chromate primer followed by filter coats.

e) The transformer shall be finished with two coats of battle ship gray synthetic enamel paint.

f) If it is considered necessary, the transformer may be given a further coating at site. The tenderer

shall indicate the type and quantity of the paint required with full specification for this purpose.

All external surfaces including that of radiators shall be so arranged that no point becomes

inaccessible in painting during maintenance work.

Page 97: E-TENDER FOR - AWS

AUXILIARY POWER SUPPLY:

All indicators, alarms and trip contacts provided shall be suitable for operation on nominal

24V D.C. System.

EXPLOSION VENT:

These shall be suitable for rotation in any direction and shall be provided with sight gauge

and equalization connection.

TESTS

Routine Tests

During manufacture and on completion, all transformers shall be subjected to the routine tests as

per IS. In addition, the following tests shall be performed on each transformer.

a) After fabrication, each tank fitted with all valves, covers etc. shall be tested for leaks at the

normal head of oil 0.352 kg/cm.sq. for a period of 12 hours if any leaks occurs the test shall be

conducted again after all tanks have been repaired.

b) The tank shall be subjected to full vacuum for 12 hours.

c) After assembly each core shall be pressure tested for one minute at 2 KV AC between all bolts,

side plates, structural steel works and the core.

d) Excitation loss and current measurements shall be made at 90%, 100% and 110% of rated voltage.

e) Open circuit and short circuit test.

f) BDV test of die electric strength of oil upto 45 KV.

TYPE TESTS

Following type tests shall be performed on the transformers in accordance with relevant standards.

a) Impulse withstand test.

b) Temperature rise test.

Copies of such tests shall be given separately by the tenderer at the time of presenting the bill.

TEST ON MISCELLANEOUS EQUIPMENTS:

All component parts such as oil, bushings etc. auxiliary equipments shall be tested in

accordance with the respective Indian Standards.

WITNESSING OF TEST:

a) Equipment (Panel and transformers) may be finally tested at site after commissioning as per ISS

or BS.

b) Transformers shall be tested on load by the department before supply. This testing will be done at

manufacturer works or at U.P. State Electricity board approved Laboratory or authorised service

center of the concerned manufacturer. The contractor shall intimate the department (when this

equipment will be ready) at least 30 days before the expected date of these tests.

TEST CERTIFICATES:

a) Test certificate of Mfrs. shall be submitted in six copies.

Page 98: E-TENDER FOR - AWS

b) Four (4) copies of each routine and type test certificates of the transformers shall be furnished to

the owner for prior approval before dispatch of any equipment.

c) The reports shall furnish complete identification of data including serial number of the

transformer.

22. 11 KV ARMOURED XLPE CABLE

Suitable size cable which shall be conforming to relevant IS specification. HT cables shall be

rated for its short circuit. The sizes of cables shall be fixed after taking into consideration the derating

factors applicable. All cables shall be steel flat strip armored unless specified.

MS CHEQUERED PLATES, 8 MM. THICK AND PAINTED WITH BLACK ENAMEL

PAINT FOR COVERING THE CABLE TRENCHES WHEREVER

REQUIRED/DIRECTED BY THE ENGINEER SHALL BE PROVIDED UNDER ALL

SUB HEADS. THE WEIGHT OF THE CHEQUERED PLATES SHALL BE AS PER

STANDARD TABLES AND IN DIAMOND PATTERN.

Wherever parallel double cables are to be laid, the capacity of individual cable should be

sufficient to take full load current required for ultimate load and other cable work as standby up

to ultimate stage.

Codes and Standards

The design, manufacturer and performance of the cables shall comply with all currently applicable

statues, regulations and safety codes in the locality where the equipment will be installed.

Unless otherwise specified, the equipment shall conform to the latest applicable Indian Standards.

a) IS-7098 Specification for XLPE Cable

23. HT CABLE AND TERMINATION BOX

Cable end box for HT cable shall be furnished complete with heat shrinkable type termination,

tabular tinned copper lugs, armour clamps, gland plate etc as per the relevant IS.

24. CONTROL CABLES

Control cables of suitable capacity running from HV panel to Power Transformer conforming to

relevant IS.

25. 24 VDC BATTERY BANK

02 Nos. lead acid battery each of 180A, 12V for control system alongwith electric charger of

30V with inbuilt protection to up keep 24 VDC Battery Bank.

26. EARTHING OF TRANSFORMER

Double plate earthing separately for both body and neutral, rest specification same as given in Sl. No. 15.

27. FIRE EXTINGUISHER

Same as given in Sl. No. 14

28. EXHAUST FAN

14″ Dia of reputed make totally enclosed and ruggedly built. The motor has prelubricated double

ball bearing and is provided with Class "A" and "E" insulation.

Page 99: E-TENDER FOR - AWS

29. INSTALLATION, COMMISSIONING & TESTING OF PUMPING PLANT AND

SUBSTATION EQUIPMENTS :-

Scope of this tender includes installation of all equipments i.e. pump, starter, panel etc. required

for smooth and perfect functioning of pumping plants. The installation should be vibration less

(subject to tolerance as per IS) and fitting should not be in tension i.e. alignment should be perfect and sizes should be dimensionally correct. All the equipments shall have got to be tested

at works before supply and at site after installation for the guaranteed parameters. During the

course of commissioning any defect or shortcoming observed shall have to be rectified by the

contractor free of cost.

Also covers receiving of various pump sets at site, site handling, storing, maintenance

during storing, erection, testing and commissioning of the same.

Receiving, storing & maintenance of pump sets and all other equipment 1. Contractor shall usually check all the pump sets, electric motors and all other equipment received at

site for any physical damage and to see that all the accessories as indicated in vendors

drawings/purchase order have been received at site. After visual inspections, he shall make a report

stating his findings and submit the same to the purchaser. Upon submission of such report and

necessary action on the same by purchaser, if any, contractor shall be fully responsible for the pump

sets till it is installed, commissioned and handed over. 2. Pump sets received at site after contractor has opened his site office, if necessary shall be

unloaded and handled at site by the contractor. Any damaged to the equipment during handling

shall be on contractors account. 3. After taking over the pump sets, these should be properly stored and maintained as per the

manufactures instruction manual. Necessary consumables required for the purpose shall be

supplied by the contractors at no extra cost to purchaser. 4. All materials from one manufacturer must come in one lot. Erection of pump sets 1. As soon as pump house area is released for pump erection, contactor shall arrange to depute

sufficient number of skilled and unskilled labour and erector. The skilled erector shall be deemed to

be the contractor’s representative. Should there be more than one erector at site, the contractor shall

give in writing which erector is designated as his representative. 2. The contractors representative shall arrange to inspect the foundation requirements for erection of

pumping plants and all connected equipment for their suitability. The contractor will supply foundation

drawing and get the foundations constructed in presence of his representative. 3. Erection of pump sets and other equipments shall be carried out in presence of contractor’s

representative as per the instruction given by purchasers/pump manufacturer’s representative and/or

as per instruction given in the pump manufacturer’s manual. The contractor shall be responsible for

setting up and erecting the plant to the line and level required. 4. When the works are associated with or in physical contract with plan supplied by others the

contractor shall satisfy himself that work carried out by other contractor is consistent with physical

requirement of pump sets being erected. In case the contractor feels that the work carried out by other

agencies is not as per the design and would effect the erection/operation of pump set, he shall bring

the matter to the notice of purchaser’s site representative in writing.

Page 100: E-TENDER FOR - AWS

Leveling and Grouting of Machinery

The purchaser’s representative shall be informed at all times to the progress of this work and

when any checks on alignment and level are to be carried out so that he may witness the checks

if he so requires. The approval of purchaser ’s representative or intimation that alignment or

level of pump sets is to his satisfaction shall in no way relieve the contractor of his obligation

under the contract to properly install and align the pump set and carry out rectification of any

installation work later found to be improperly carried out.

Final Connection

For other services such as electrical cables (power control), pump suction and discharge piping

etc. final connection for connecting these services to the respective terminal point on pump sets,

shall be done by the contractor.

Setting to Work

1. On completion of erection, the work erected by the contractor including final connection subjected to

hydraulic pressure shall be tested for 1.5 times maximum pressure whichever is higher to prove the

soundness of joint. The duration of test shall be of less than 10 minutes. 2. Prior to setting the plant to work the contractor shall check all items of electrical plant and shall

dry out the electrical motor insulation as stipulated in the electrical specification,

3. Only after above checks have been carried out and proved satisfactory, the contractor shall obtain

written permission from the purchaser’s representative for starting the pump set and shall continue to

operate the plant for the period desired by the purchase’s representative. Detailed Requirement of Installation

1. Switch gear, control panel etc.

All alignment, leveling, grouting, anchoring, adjustments shall be carried on in accordance with

manufacturer’s instructions and or as directed by the purchaser.

All modules shall be taken out and internal shall be cleaned preferable with vacuum cleaner.

All connections and fixing of equipments in switch gear control panels etc. shall be completed,

checked and adjusted to ensure safely and satisfactory operation of the equipment.

In some cases, minor modifications may have to be carried out at site in the wiring and mounting

of the equipment to meet the requirement of the desired control scheme and the contractor shall

have to do the same at no extra cost.

2. Motors

The installation of motors shall be carried out in accordance with manufacture’s instructions

and/or directed by the purchaser.

Checking and cleaning of bearing and charging/filling of lubricants wherever necessary.

Cleaning of core and winding, varnishing and drying gout the winding and measurement of air

gap for motor assembly at site if demanded.

Motors shall be run in uncoupled condition for few hours before coupling them with be drive

equipment.

Cable Termination

1) Cable termination shall include the following: a) Making necessary holes in bottom/top plates for fixing cable gland box.

Page 101: E-TENDER FOR - AWS

b) Fixing cable gland box, connecting Armour clamp to cable Armour. c) Dressing cable, pouring compound etc. where ever necessary to make termination

complete.

d) Putting cable lugs, crimping them on the cores of cables, tapping bare conductors up

to lugs, wherever necessary.

e) Terminating to equipment terminals f) Supply and fixing of cable and core identification ferrules.

Where ever purchaser has not provided M.S. plates for fixing cable tray supports, contractor

shall install approved concrete fasteners for fixing cable tray support.

. Inspection

After completion of the erection/installation, each equipment shall be thoroughly inspected in presence of purchaser for correctness and completeness of installation. A checklist may be

furnished by the purchaser wherein all details to be checked and necessary instructions shall be

listed. The inspection and checking shall strictly follow the checklist. On completion of the

inspection two copies of the check list duly filled in shall be jointly signed by contractor and the

purchaser. Such endorsement however shall not relieve the contractor of his obligation under the

contract.

Testing and Commissioning

After completion of erection work, test shall be conducted by the contractor on each piece of the

equipment as per list to be supplied by the purchaser or his authorized representative. The contractor

shall provide all tools, instruments, material, labour and supervisory personnel for carrying out test

on the equipment and material under his scope of work.

The contractor shall record the test result on approved Performa and furnish four copies of the

result to the purchaser for his approval within a week from the data of test completed before

commissioning of the equipment. The contractor shall set the relays to their recommended

values. On successful testing the equipment shall be commissioned and put on trial run along

with other equipment in a manner mutually agreed upon.

The contractor provide preliminary testing at manufacture’s works and at site and

through testing of the plant during the course of erection and when it is completed as specified

and for official testing of the same in accordance with schedule ‘E’ . The electric motor and

pump be type tested at the manufacturer’s works. Pump sets will be tested at manufacturer

works as per schedule ‘E’ given by the contractor and as per IS:8034. Other material/accessories

will be checked as per relevant ISS.

After the plant has been put in continuous operation for the period desired by the purchaser’s

representative the plant shall be tested and commissioned as stipulated hereunder. 1. At least six weeks prior to start of testing and commissioning of the plant, the contractor shall

prepare a programme in consultation with the purchasers representative for the period of

commissioning and tests. 2. During commissioning the contractors shall supply all labour to supervise, operate test and do all

things necessary to keep the plant running. 3. Manual Commissioning Test These shall be such preliminary trails, test and run on individual items of plant as required by

purchaser’s representative.

4. Manual Operation Test These shall demonstrate the correct operating of the whole plant at all design flow and pressure with

minimum automatic control and monitoring equipments. The test shall be of at least seven consecutive

days duration reduced if necessary at the discretion of purchaser’s representative.

Page 102: E-TENDER FOR - AWS

5. Automatic Commissioning Tests These shall demonstrate correct automatic operation of plant. Conditions shall be stimulated to

demonstrate the operating of safety and operation control. The tests shall be carried out for such

number of times, the purchasers representative considers necessary to demonstrate consistent

automatic operating of plant.

6. Test on Completion On completion of above noted tests, the tests on completion shall be carried out during which the

guaranteed duties must be performed continuously by each pumping unit for a period of at least 6

hours or as the purchaser’s representative may determine. The contractor shall provide all the

necessary instrument and gauges required for these tests. The instruments shall be celebrated prior to

their use. Contractor shall furnish necessary certificates of approved testing authority to this effect.

The test shall be carried out in line with B.S 5316 part-II.

If any test shows noticeable deterioration in the performance of the plant or any particular item

compared with the test results obtained during the test at manufactures work, the contractor shall

immediately inform purchaser’s representative accordingly.

TEST DUTIES AND EFFICIENCIES:

The contractor shall state in the tables attached with tender documents the efficiencies and duties of

the pumping plants when working at specified conditions of the pumping and the guaranteed

performance in K.W. hour input per water horse power output under various conditions of working.

The guaranteed performances are also to be specified under following conditions i.e. variation in

head discharge and power consumption in the following cases:

d) When available voltage decreases from 415 volts to 380 volts or increases from 415 volts to 440

volts.

e) When there is fluctuation of ±3% in the frequency of the AC power supply from 50 C/S. f) When there is above change in voltage and frequency of the AC power supply simultaneously.

The official tests shall be conducted in two stages. Preliminary tests may be conducted at the

manufacturer’s works. The final tests shall be conducted at site. Pumps shall be run so as to

obtain the range of heads specified in the performance tables by means of throttling or opening

valves of the pumping mains and tests results will be compared with those guaranteed by

averaging the units consumption per water horse power hour.

The guaranteed figures stated above shall be subjected to no tolerance and the average results shall

be obtained during official test of plant. If the results lack average guaranteed figures the contractor

shall forfeit followings ascertained damages relating to each set installed.

If BOT unit (KWI) per WHP, the consumption is above the average guaranteed figure under the

specified Q and H, the liquidated damages will be recovered as the capitalized cost of the Extra

Energy Consumption during the useful life span 15 years of the pumping set. The liquidated

damages shall be calculated as below:

Cost of extra power consumption

to be recovered shall be equal to =Cost of extra power per annum X capitalization factor for 15

years at an interest rate of 9%.

No damage will however, be recovered if the consumption is less than 0.05 BOT units per WHP

above the guaranteed.

If on testing the discharge of pumps is found to be within the permissible limit of ±4% then the

pumping plant will be accepted without imposing any penalty. If discharge is less by 5% to 10% then

pro rate deduction @ 1% of the cost of pump and motor for less percentage of discharge shall be

made and further if the discharge is less than 10%, plant will be rejected.

Page 103: E-TENDER FOR - AWS

It may be noted very carefully that no privilege shall be given to any offer for evaluation

purposes considering the efficiency of the pump. Better efficiency pump however shall be

preferred. For evaluation purpose pump efficiency shall be considered as 75 % but the pump will

be tested on the efficiency quoted by the firm.

The pump efficiency offered below the efficiency quoted shall be considered for evaluation as

follows:

(i) Electric charges shall be based on 16 hours of operation per day for 15 years at the prevailing

rate of Electric Charges. (ii) All future costs of yearly power consumption will be capitalized to present value at

capitalization factor @ 9% interest.

The tenders shall have to consider the condition of pumps being run at shut off head under the

pump duty variation condition as narrated above. The tenderer should ensure selection of pumps

considering shut off head at least 25% more than the duty head. However the motor should be

selected as per tender specification and scope of work defined. The possibilities of change of

duty point of each pump in parallel operation can not be ruled out under such condition tenderer

should select the pump carefully.

Penalty for delay in supply and installation-0.25% per day of the total tendered cost subject to a

maximum of 10%.

Rectification and Taking Over

The contractor shall carry out all rectifications, repairs or adjustment work found necessary

during testing, commissioning and trial run. On successful commissioning and trial run and on

carrying out the rectification work, the purchaser will take over the installation either wholly or

in parts as the case may be.

30. DRAWINGS:

The tenderers shall have to submit the following drawings & QAP and to get it approved by the

deptt. before start of execution/dispatch from works :-

1. Layout plan of equipments and pipe and specials

2. Drawing of foundation blocks.

3. Manufacturer’s catalogue of pump set and transformer with cross sectional dimensional details.

4. Line diagram of power wiring of control panel.

5. Parallel operation curve (when two pumps running in parallel)

6. Characteristic curves of diesel engine and alternator showing their performance under

varying condition.

7. Control Panel Drawing.

31. INTERNAL AND EXTERNAL ELECTRIFICATION

TUBULAR POLES AND LIGHTING

09mtr. high single or double pole lighting shall be provided over the area spread over MPS

campus and STP with Illumination as required standards given below:

Page 104: E-TENDER FOR - AWS

ILLUMINATION:

All internal and external areas shall be provided with lighting. The illumination levels to be

achieved shall be as follows for which contractor must submit the drawing and after getting

approved carry out the work as follows:

AREA LUX

Office and labs 300 Lux Switchgear Room 200 Lux

Control Room 300 Lux Pump House 200 Lux DG set room 200 Lux Chemical and general store 150 Lux Chemical Plant room 200 Lux Other indoor areas 100 Lux Outdoor plant from and 50 Lux Building entrance 100 Lux Indoor Plant Area 200 Lux Outdoor Plant Area 50 Lux Transformer Area 100 Lux

Roads 10 Lux

31.1 LED luminaries shall be used primarily for internal lighting. High pressure vapour or metal halide type

luminaries shall not be used in indoor application anywhere. All other internal areas shall be lit with

LED luminaries. Where specific recommendations of lux level are not covered above, illumination level

in such areas shall be finalized in consultation with Owner. Owner shall be required to measure levels of

illumination after completion of lighting installation work and short fall in illumination level shall be

made good by the Contractor. Complete set of calculations showing, room, index, copy MF shall be

given during detailed engineering. 31.2 Switches / sockets of piano type shall be used in general and in offices of staff, control room, MMI room,

decorative modular switches shall be used. Suitable fans shall be provided in rooms/ plant areas as per

standards. For exhaust fans it must be provided in process room, panel rooms, pump rooms, chemical

rooms, stores, toilets and at least 20 air changes per hour must be maintained.

31.3 The following type of lighting fixtures shall be proposed:

a) Decorative type fixtures for LED luminaries inside office/ administrative buildings and control rooms.

b) Corrosion resistant fixture with canopy made of FRP for LED luminaries for corrosive areas like chlorine handling or chemical store or area with corrosive smell/gases etc.

c) Industrial type vitreous enameled fixture for LED luminaries inside 415V switchgear, MCC room and pump house.

d) In outdoor process areas, lighting fixtures shall be LED type subjected to minimum of IP protection class.

e) All outside lights as plant field lights, building outside lights, flood lights etc. which are to be switched on only during night hours should be controlled through photo cell/ clock switch installed at a central place. All lights shall have minimum IP65 protection class. f) Street lighting wiring shall be through buried underground. g) All bulb fittings (except fluorescent lamps) will have screw type caps.

h) For outdoor lighting, the lighting feeder shall be operated through a contactor, controlled by photocell/ clock switch and shall also have a manual by pass switch.

31.4 Luminaries shall be installed to permit ease of maintenance i.e. it shall not be necessary to shut down

plant in order to carryout maintenance or to access luminaries located over areas of water etc. The

Contractor shall provide all equipment necessary to carryout maintenance on the lighting installation

and demonstrate its operation to the satisfaction of Owner.

31.5 Indoor lighting circuit will be arranged in such a way that 50% lighting can be put off in each room

through switches. All lighting circuits will be wired with 2.5sq.mm. Stranded copper wire or through 2.5

sq. mm. armoured cable laid in cable trays. Sub circuit from switch to fixture could be wired with1.5

sq.mm. stranded copper wire in MS conduits or armoured copper cable of similar size provided total

voltage drop in any lighting distribution board to last lighting point shall not

Page 105: E-TENDER FOR - AWS

exceed 2%. All lighting circuits will have separate neutral, separate earth from Lighting Distribution

Board. For illumination of roads, outdoors areas where operation of equipment or units required and

sub-station area, lighting fixtures of appropriate type (such as street lighting type, flood lighting type,

post top lanterns etc.) incorporating high pressure sodium vapour lamps shall be proposed. Street

light poles shall not have less than 7500 mm height above the finished road level and the arm shall

not project more than 1200 mm along the road width. Poles of bigger heights may also be used if

some outdoor areas are to be illuminated. Poles of 4 / 4.5 Mtrs using post top lantern may be used in

gate office walk way or in front of office area. Complete area, streets, lanes, boundary shall be

covered with street lighting. Receptacles (Lighting & Small Power) :

a) Decorative and industrial type units of above shall be proposed in all plant areas, offices, stores, workshop, plant room and they shall be located at least two numbers in each room. Distance between two receptacles shall not be more than 8 – 10 mtr. All small 5 amps 5 pin lighting & small power sockets shall be wired by multi stranded copper wire of 2.5 sq. mm laid in rigid MS conduits along with earth wire of1.5 sq.mm flexible copper wire or equivalent size armoured cables. All wiring shall be coded with Red, Yellow, Blue & Black as per the phase used. If required, wiring can be done alternatively through armoured copper cables of similar size laid in MS perforated trays of minimum 2.0 mm thick.

b) Three phase power receptacles (convenience outlets) suitable for operation of 415V,3Phase 4 wire,

50 Hz power supply shall be proposed. In indoor areas one such unit shall be provided to cover areas

of 20 meter radius (or at least one in each room housing plant items ) and in outdoors areas on such

unit shall be provided at 50 meter interval. Actual requirement of such units shall be finalized by

MMC during detailed engineering. One three phase receptacle shall be provided near entrance of

each building for utilities like welding. c) Single phase 15 Amp 5 Pin / 6 Pin receptacles will be provided in each room and in halls they will be

provided in such a way that with 15 meter cord we should reach every place in building. These shall be

wired with 4 sq. mm copper earth wire in MS rigid conduits along with 2.5 sq. mm earth wire. Not more than two sockets shall be looped in one circuit. Alternatively they can also be connected through armoured cable of 4 sq. mm running in appropriate cable trays.

31.6 Separate lighting panels and lighting distribution boards shall be installed and they shall not take tapping for power from motor control centers or power distribution boards.

INTERNAL & EXTERNAL LIGHTING OF THE BUILDING All the building construction will have internal and external lighting as above mentioned

specifications and lighting panel MCB distribution board as per specifications given below.

SPECIFICATIONS FOR LIGHTING PANELS (MCB DISTRIBUTION BOARDS) SPECIFICATIONS

Relevant Indian Standard Specifications and Codes shall apply for Lighting Panel Boards and

their components wherever such Standard Specifications exist. The panel shall be approved by

the Fire Insurance Association. Lighting Panels shall be generally comprised of Isolators, MCBs, ELCBs, ELMCBs and HRC fuses (if asked for in BOQ), Potential Indicating lamps, set of separate phase terminal strips, Neutral terminal strip and Earthing terminal strip and any other components as indicated in the

Bill of quantities

2 GENERAL REQUIREMENTS i) Lighting panels shall be made of 14SWG sheet steel and painted with powder spray to prevent

corrosion. ii) Lighting panels shall have properly hinged cover of min. 2 mm thick CRCA sheet on its front so

that all the Electrical components and accessories can be accessed only after opening of the front cover. After opening of the front cover, the panel shall have another hinged door made of min. 2 mm

thick CRCA sheet with necessary cut-outs for mounting the all Electrical components with

adequate clearances.

Page 106: E-TENDER FOR - AWS

The Panel shall be suitable for Top / Bottom entries for incoming and outgoing Cables/Circuits. The

incoming Switchgear component shall have suitable provision for terminating a looping cable (of

max. 50 sq.mm size) for feeding to another Panel in the zone.

All the Panel wiring shall be carried out using 660/1100V grade FRLS insulated, flexible, multicore Copper conductors of reputed make and of rating considering the respective Isolator / MCB/ ELCB rating with all derating factors. (iii) The Switchgear components such as MCB, ELCBs, etc. shall be of 10KA breaking capacity with mid trip position for easy identification of the fault conditions. The components shall have shock proof and safe finger touch

terminals. The components shall have lower watt losses and shall have provision for mounting the additional accessories such as auxiliary blocks, shunt trip, etc.

iii) Lighting panels shall be suitable for 3 Phase, 4 Wire, 415/240 Volts as per the distribution schemes indicated in the relevant drawings.

iv) The lighting panels shall be completely dust and vermin proof, double door type and provided with neoprene gaskets and free of mechanical and electrical defects. The degree of protection for the panel enclosure shall be minimum IP 54.

v) Knockouts for branch circuit conduits or cables shall be provided on the top and bottom as required. vii) Tinned copper sockets shall be provided for the main connections to the panel.

vi) All panels shall be self-supporting, wall / steel structure mounting type unless otherwise specified in the schedule of quantities

vii) All the lighting panels shall be provided with two external Earthing terminals and suitable tinned copper lugs for connection to the Earthing system

viii) The neutral terminal block shall have sufficient number of terminals for all single-phase outgoing branch circuits.

ix) Means for easy identification of each and every branch circuit shall be provided. A Circuit Distribution diagram shall be pasted on the rear side of the front door of the panel for the easy reference.

x) Vendor shall furnish the GA drawings with supporting and connection arrangement and wiring diagrams

with the detailed bill of quantities, for the approval of Owner / Consultant, before

32. TRAIL RUN

Staff to be deployed by the contractor as follows On each tubewell – 3 no’s operator in three shift On each ZPS – 3 no’s operator in three shift and one electrician in general shift

Except electricity all other consumables have to be arranged and supplied by the contractor.

Page 107: E-TENDER FOR - AWS
Page 108: E-TENDER FOR - AWS
Page 109: E-TENDER FOR - AWS

109