Dubai Maritime City | Ship Lifts With execution time being the crucial criterium, a sheet pile wall with AZ 50 was proposed as an alternative solution. Finally the main wall is made of AZ 50, whereas the anchor wall is made of AZ 18 sheet piles. For the local high vertical loads that will occur during the operation of the ship lift single AZ 50 box piles, called CAZ 50, were driven. This cost-efficient solution is the result of intense optimizing efforts carried by the technical department of BESIX in cooperation with the design department of ArcelorMittal Commercial Rails, Piles & Special Sections. The design The Dubai Maritime City project is located close to the Rashid port in Dubai and consists of a 2km² man-made peninsula providing different areas of business, housing and marinas as well as Ship Repair facilities which are equipped with two ship lifts of a capacity of 3000 t and 6000 t loads. The retaining walls of the ship lifts were built exclusively with hot rolled steel sheet piling. The main reason was that with the time line for the execution being on a tight schedule the sheet piling offered the opportunity to have a prefabricated product and thus minimize execution time. In the end all the sheet piling were installed within only 6 weeks. The project
2

Dubai Maritime City |Ship Lifts - ArcelorMittalpalancole.arcelormittal.com/uploads/files/64d76a78f41249...Dubai Maritime City |Ship Lifts With execution time being the crucial criterium,

Jun 26, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Dubai Maritime City |Ship Lifts - ArcelorMittalpalancole.arcelormittal.com/uploads/files/64d76a78f41249...Dubai Maritime City |Ship Lifts With execution time being the crucial criterium,

Dubai Maritime City | Ship Lifts

With execution time being the crucialcriterium, a sheet pile wall with AZ 50 wasproposed as an alternative solution. Finallythe main wall is made of AZ 50, whereasthe anchor wall is made of AZ 18 sheetpiles. For the local high vertical loads thatwill occur during the operation of the shiplift single AZ 50 box piles, called CAZ 50,were driven.

This cost-efficient solution is the resultof intense optimizing efforts carried bythe technical department of BESIX incooperation with the design departmentof ArcelorMittal Commercial Rails,Piles & Special Sections.

The design

The Dubai Maritime City project is locatedclose to the Rashid port in Dubai andconsists of a 2km² man-made peninsulaproviding different areas of business,housing and marinas as well as Ship Repairfacilities which are equipped with two shiplifts of a capacity of 3000 t and 6000 tloads.

The retaining walls of the ship lifts werebuilt exclusively with hot rolled steel sheetpiling. The main reason was that withthe time line for the execution being ona tight schedule the sheet piling offeredthe opportunity to have a prefabricatedproduct and thus minimize execution time.

In the end all the sheet piling wereinstalled within only 6 weeks.

The project

Page 2: Dubai Maritime City |Ship Lifts - ArcelorMittalpalancole.arcelormittal.com/uploads/files/64d76a78f41249...Dubai Maritime City |Ship Lifts With execution time being the crucial criterium,

05

.20

08

-C

S0

01

Dub

aiM

ariti

me

The installation

Anchor material

Conclusion

Being aware of the significant influence offreight rate for the building material on thetotal cost, the box piles were fabricatedon site so that all sheet piling could bedelivered stacked with a minimum ofrequired space. The assembly of theCAZ 50 box piles was eased by deliveringAZ 50 piles with already cut flanges.

A characteristic of the soil conditions in theDubai area is the cap rock. At this location,cap rock is found at a depth of about-19.00 m thus leading to hard drivingconditions. The installation was carried outwith vibratory hammers (ICE 815C andICE 1412) as well as a hydraulic impacthammer (IHC S90) without any furtherdriving assistance. A two level template wasused to guide the sheet piling during drivingwith free hanging driving equipment.The tolerances for the positioning of thebox piles were very strict, as these pilesrepresent the connection point betweenthe mechanical part of the ship lift, theretaining wall and the transfer rail.

Due to the high vertical loads during theoperation of the ship lift, the box pileshave to provide a high bearing capacity.The analysis of the driving records fromthe installation did allow a first estimationof the bearing capacity. These values spanfrom 3.2MN to 6.5MN.

To prove the bearing capacity of theCAZ 50 box piles, statical vertical loadtest was carried out which confirmed the

Dubai Maritime City | Ship lifts

Owner Nakheel

Contractor Belhasa Six Construct L.L.C.

Designer Halcrow International Partnership

Sheet piles AZ 50 / AZ 18

Length 23.0 m - 24.5 m / 8.50 m

Steel grade S460 AP / S430 GP

Total Quantity 3 580 metric tons

ArcelorMittal Commercial RPS S.à r.l.Sheet Piling66, rue de LuxembourgL-4221 Esch-sur-Alzette (Luxembourg)

t (+352) 5313 3105f (+352) 5313 3290e [email protected]/sheetpiling

ArcelorMittal International DubaiHoliday Centre # 1405P.O. Box 53608Dubai, UAE

t +971 (0)4 3310435f +971 (0)4 3314520e [email protected]/projects/foundations

calculated values and finally did verifythe values estimated during the designcalculations.

As an integrated part of the design of thestructure the specific anchoring layout wasdeveloped as a tailor made pre-fabricatedsystem of tie rods and waling which wasprovided by Anker Schroeder, Germany.All required materials such as tie rods,waling, bolts, nuts and plates were deliveredto the site and simply had to be assembledwith a minimum of work to be carriedout on the field. Even the connections ofthe waling beams were already preparedwith drilled holes. Bearing in mind that thesite is located on a reclaimed area righton the shoreline and the anchor level ofthe sheet piling is lower than the high tidelevel, the waling and the tie rods could onlybe installed at low tide under dewateringconditions. Therefore the choice ofprefabricated anchor material was the onlyway to carry out these works in acost–effective way.

The installation of the sheet piling forthe ship lifts in Dubai Maritime City wascompleted within the time frame as initiallyplanned. The excellent preparation ofthis project from the design phase to theexecution of the structure took advantageof a high degree of prefabrication and leadto a successful completion.