DTS: What is the Dynamic Track Stabiliser?
• In use since the 1980s on the UK infrastructure
• Self propelled on track machine
• Applies vibration to the track to ‘fluidise’ ballast
• When combined with a vertical load, enables better
ballast interlocking and reduced voiding.
• Research suggests consolidation achieved by DTS
is similar to 100,000 tonnes of ordinary line traffic.
DTS: Why do we use it?
• Better ballast consolidation > better lateral and vertical track support.
• Opportunity for higher speed hand-back
• Ineffective track support > Emergency Speed Restrictions (ESRs)
• Increased track stability through increased ballast consolidation
DTS: NR/L2/TRK/018 – The DTS Standard
August 1997
Major Changes:
➢ Re-write of Standard in its entirety.
➢ Full consideration of both Plain Line (inc. High Output) and S&C
➢ Provision for use in maintenance as well as refurbs and renewals
➢ Using on-site testing to validate data models to more accurately predict the
Zone of Influence of DTS
➢ Introduction of new TEF forms to identify structures and determine suitability for
DTS
(RT/CE/P/018)
S&C 90 Asset damage HP fracture switch
Visible failure of switch during
works
Loss or reduced function and potential
reduction in safety protection DTS
Passengers,
Workforce,
MOP 1 4 5 COP Form B Systems Component Certificate TEF 3203 (Issue 5)
S&C Refurb
WG 1 4 5
A condition assessment of all components and assets must be carried out prior to specifying
the use of the DTS. The assets must meet a minimum condition requirement as specified in
Appendix A. (DTS - CONSTRUCTION) 1 2 3
S&C 91 Loss of support train guidance DTS run out into unscoped site
DTS works outside scope
mileage and damages track or
structures
Potential for Train Derailment with
potential harm to train occupants and
those adjacent to the railway DTS
Passengers,
Workforce,
MOP 5 4 9
Compliance with:
NR/GN/TRK/7001/TWIT020 - How to plan a Dynamic Track Stabiliser S&C Refurb
WG 5 4 9
The mileages over which the DTS should operate should be clearly specified and assessed
for suitability for use of DTS, including the lengths of track where the DTS will be ramping
in/out. (DTS SCOPING) 5 1 6
S&C 92 Loss of support train guidance Bullhead keys vibrate loose
Potential for Train Derailment with
potential harm to train occupants and
those adjacent to the railway DTS
Passengers,
Workforce,
MOP 5 4 9 COP Form B Systems Component Certificate TEF 3203 (Issue 5)
S&C Refurb
WG 5 4 9Certain layouts and track components are not suitable for use of DTS: Bullhead rail
(SCOPING DTS) 5 1 6
S&C 93 Asset damage E&P equipment damage
Loss or reduced function and potential
reduction in safety protection DTS
Passengers,
Workforce,
MOP 1 4 5 COP
Form E Electrification Certificate TEF 3203 (Issue 5)
NR/L1/NI/CP1010 Policy on working safely in the vicinity of buried services S&C Refurb
WG 1 4 5
Surface and buried cables are to be clearly marked up and removed, where possible, for the
duration of the excavation and re-ballasting works.
Points heating equipment should be removed.
1 2 3
S&C 94 Asset damage Switches that have been weld repaired
Loss or reduced function and potential
reduction in safety protection DTS
Passengers,
Workforce,
MOP 1 4 5 COP Form B Systems Component Certificate TEF 3203 (Issue 5)
S&C Refurb
WG 1 4 5
A condition assessment of all components and assets must be carried out prior to specifying
the use of the DTS. The assets must meet a minimum condition requirement as specified in
Appendix A. (DTS - CONSTRUCTION) 1 2 3
S&C 95 Asset damage Damage to handpoints
Loss or reduced function and potential
reduction in safety protection DTS
Passengers,
Workforce,
MOP 1 3 4 COP Form B Systems Component Certificate TEF 3203 (Issue 5)
S&C Refurb
WG 1 3 4Certain layouts, track and S&T components are not suitable for use of DTS:
• Hand points (DTS - SCOPING) 1 1 2
Track 96 Asset damage Damage to Plain Line components Force applied by DTS Fatigue/Equipment failure
Loss or reduced function and potential
reduction in safety protection DTS
Passengers,
Workforce,
MOP 3 4 7 COP
Existing RT/CE/P/018 Standard - Limited mention of specific components to be
controlled, also correspondance received from Pandrol and Vosslah that they
do not have any concerns surrounding the use of DTS and the effect that it
would have on their fastening systems.NR56/NR60 rail sections - evidence DTS WG 3 3 6
NR/L2/TRK/018/mod02 - Working Group discussed and approved -
Concrete sleepers (Cast-in housings, Converted F10 sleepers, with PR401A or e clips,
Converted F16 sleepers, with PR401A or e clips)
Wood sleepers (Screw-fastened Pandrol baseplates with approved pads and clips (e-clips
may be used in SG iron baseplates)) 3 1 4
Track 97 Asset damage Damage to asset by DTS working DTS zone not properly assessed
Damage to infrastructure (poor
track quality)
Loss or reduced function and potential
reduction in safety protection DTS
Passengers,
Workforce,
MOP 4 5 9 COP
Current limitations in RT/CE/P/018 set at 20m. To attempt to reduce numbers of
TSRs and improve handback speeds/ track quality, DTS scope is proposed
within closer parameters than 20m DTS WG 4 3 7
NR/L2/TRK/018/mod02 - Significant research done as part of DTS Standard to understand
the limit of zone of influence of DTS. Safety factor of 1.5 applied on top of existing limits in the
Standard. TEF 3274 to cover recording of where assets have/ have not been DTS'd, and
records category of asset being DTS'd. 4 2 6
Track 98 Asset damage
Asset deteriorates after initial
assessment but before DTS application Inspections out of date
Damage to infrastructure (poor
track quality)
Loss or reduced function and potential
reduction in safety protection DTS
Passengers,
Workforce,
MOP 4 4 8 COP
Existing RT/CE/P/018 Standard - Requires review prior to DTS use, but with no
specific time periods assigned. DTS WG 4 3 7
NR/L2/TRK/018/mod02 - In discussion with the WG, new DTS TEFs shall be signed off at
nominally 3 years and 12 months out from the date work is due to commence.
If the work has not been completed within 12 months of final sign off, re-approval shall be
required. 4 1 5
Track 99 Asset damage Failure of obsolete componentry
DTS used on obsolete
components
Damage to infrastructure (poor
track quality)
Loss or reduced function and potential
reduction in safety protection DTS
Passengers,
Workforce,
MOP 4 3 7 COP Not curently controlled in existing 018 Standard DTS WG 4 3 7
NR/L2/TRK/018 Standard - DTS shall not be used on track layouts with obsolete components.
Presence of obsolete fastenings should be recorded during scoping and plans to update
fastenings should be made. (SCOPE) 4 1 5
Track 100 Asset damage DTS used on asset which is unsuitable
Misunderstanding of 'Category'
in Standard Damage to infrastructure
Loss or reduced function and potential
reduction in safety protection DTS
Passengers,
Workforce,
MOP 4 4 8 COP
Existing RT/CE/P/018 Standard - Covers a broad understanding of the categories
and what to do in each case DTS WG 4 2 6
NR/L2/TRK/018 Standard - Further demonstrates the categories, plus the impact of TEF form
to accompany for proof of choise and recorded decision making. Structural assessment
reports Detailed structural examination reports shall be reviewed to confirm the
categorisation of each structure with respect to the operation of the DTS taking into account
the type of structure and defects present. 4 1 5
Structures 101 Asset damage Damage to asset by DTS working
DTS use on bridge/ culverts/
viaducts at natural frequencies Damage to infrastructure
Loss or reduced function and potential
reduction in safety protection DTS
Passengers,
Workforce,
MOP 3 4 7 COP DTS Standard (RTCE/018) prevents use at frequencies below 25Hz DTS WG 3 2 5New NR/L2/TRK/018 Standard includes this, plus guidance on standard working to use
frequencies above 33Hz 3 1 4
Track 102 Asset damage Damage to asset by DTS working
DTS causes baseplate shuffle in
S&C layout Damage to infrastructure
Loss or reduced function and potential
reduction in safety protection DTS
Passengers,
Workforce,
MOP 4 3 7 SRS
Currently best practise docuses on tamping standard and explores mitigation
by assessment of fastenings in line with TRK/001 but is not explicit with
requirement for DTS DTS WG 4 2 6
New NR/L2/TRK/018 Standard will require 'all track components are complete and in good
condition (including all bolted connections checked for security).
For guidance on condition, see NR/L2/TRK/001/mod05).
For specific guidance on condition of bearer ties, see (TRK/3406)' 4 1 5
DTS: NR/L2/TRK/018 – The DTS Standard
• HAZID Log connected to the Standard (over 85 hazards tracked to date,
still working through these…)
• Communication with existing DTS suppliers to ensure no duplication of
effort
• Discussion with key stakeholders to capture previous ‘Lessons Learned’
• Working Group sessions still ongoing to date
DTS: NR/L2/TRK/018 – Filling in the blanks
• Previous investigation has been done to understand the Zone of Influence
without the required conclusions.
• SETAN40 (Earthworks) – Focusses on the vertical effects (not lateral).
• High Marnham – Report considered inconclusive
• DTS of S&C – Purely S&C – Not ground effects.
• As a result, the Working Group agreed to conduct further testing of DTS,
with the intention to validate and calibrate a model with real-world testing,
which could then be used to simulate our requirements.
Work Scope
Literature review to understand the DTS
principles
Carry out site trials with using DTS and
measurement instrumentations
Develop and calibrate a 3D dynamic FEM to
using the trials data
Using the developed model, carry out a parametric study to understand the
effect of subgrade condition on the DTS influence zone
DTS: Testing (Site Selection)
• Predominantly driven by availability for both DTS machine and sidings.
• Grange Sidings, Stoke-on-Trent selected
• Previous DTS testing conducted here
• Well consolidated track (simulates ‘worst-case’
transmission path)
• Both F27 (MTCE) and G44 (REN) sleepers available
• DTS availability on site (thanks to Colas Rail)
• Good choice of roads in siding to choose from
DTS: Testing (Testing Protocol)
Vertical
Longitudinal
Lateral
DTS: Testing (Site Walkout)
• Identification of good testing locations
• Not near existing structures (to avoid interference)
• Preferable 1 x G44 and 1 x F27 (spot discrepancies)
• Good overall track condition, good ballast depth, good condition track
fastenings (replaced if poor/worn/missing)
DTS: Testing (Testing Protocol)
DTS: Testing
DTS: Modelling
DTS modelling
DTS inputs
Track Bed inputs
Compare vibration results with field data
DTS: Modelling
DTS: Modelling – model design
DTS: Modelling – model design
DTS: Modelling – model design
DTS: Modelling – simulation scope
DTS: Modelling – simulation runs
Simulation video
DTS: Modelling – results interpretation
n
m
DTS Unite
Stress
influence zone
m: Longitudinal distance
from the DTS centreline
to the position at which
the stress level equal to
the threshold
n: Lateral distance from
the DTS centreline to the
position at which the
stress level equal to the
threshold
DTS: Modelling – results vertical stress
-6
-4
-2
0
2
4
6
-10 -8 -6 -4 -2 0 2 4 6 8 10n(m
)
m (m)
DTS 5-soft DTS 5-stiff DTS 4-soft DTS 4-stiff DTS 3-soft
DTS 3-stiff DTS 2-soft DTS 2-stiff DTS 1-soft DTS 1-stiff
Vertical stress
DTS mode DTS loading Subgrade modulus (MPa) m (m) n (m) Area of influence zone (m2)
DTS 5Vertical load = 70bar
Frequency = 38Hz
6 8.5 4.6124
50 4.6 4.769
DTS 4Vertical load = 20bar
Frequency = 38Hz
6 5.3 4.066
50 4.2 4.458
DTS 3Vertical load = 45bar
Frequency = 33Hz
6 6.5 5.4111
50 4.7 4.363
DTS 2Vertical load = 70bar
Frequency = 28Hz
6 6.4 4.795
50 4.7 4.770
DTS 1Vertical load = 20bar
Frequency = 28Hz
6 5.2 3.964
50 3.9 4.252
DTS: Modelling – results vertical stress
DTS: Modelling – results vertical stress - soft soil
-20
-15
-10
-5
0
5
10
15
20
-20 -15 -10 -5 0 5 10 15 20n (
m)
m (m)
Max DTS vertical Light train vertical Heavy train vertical
DTS: Modelling – results vertical stress – stiff soil
-20
-15
-10
-5
0
5
10
15
20
-20 -15 -10 -5 0 5 10 15 20n (
m)
m (m)
Max DTS verticle Light train vertical Heavy train vertical
DTS: Modelling – results lateral stress - soft soil
-25
-20
-15
-10
-5
0
5
10
15
20
25
-20 -15 -10 -5 0 5 10 15 20n (
m)
m (m)
Max DTS lateral light train lateral Heavy train lateral
DTS: Modelling – results lateral stress - stiff soil
-25
-20
-15
-10
-5
0
5
10
15
20
25
-20 -15 -10 -5 0 5 10 15 20n (
m)
m (m)
Max DTS lateral light train lateral Heavy train lateral
DTS: Interpretation of the results
• Every DTS mode generates a different zone of influence
• The vertical stress influence can reach of up to 9m longitudinally and 5m
laterally (based on ‘worst case’ + 0.5kPa boundary conditions).
• The lateral stress influence can reach of up to 8m longitudinally and 19m
laterally (based on ‘worst case’ + 0.5kPa boundary conditions).
• In the longitudinal direction, the DTS stress influence is very similar to the
influence of running trains. However, this is not the case in the lateral
direction.
• The maximum influence is governed by the lateral stress from the DTS
DTS: Lessons learned
• The DTS ‘Zone of Influence’ appears larger than we originally anticipated
when referenced against the current limiting requirements from Structures
(STE).
• The research has given us useful information on stress vs. distance for the
DTS which we have never previously had.
• Structures may be more easily reviewed using these modelled stress
tables which will be found in the Standard. This should decrease
assessment time on required structures if DTS is planned.
• This research will be used to inform the requirements of the Standard (to
be published in 2020).
DTS: Next Steps
• Consultation with technical asset leads to further identify risk to structures
inside the ‘Zone of Influence’ currently defined.
• Micro-study - Management of low vs. high risk assets when using DTS
• Validation at DTS Working Group (early 2020)
• Standard publication using this modelling and feedback from the above
(NR/L2/TRK/018).
THANK YOU FOR LISTENINGQuestions?