Draft
2015 Annual Land Use Control Monitoring Report, RVAAP-01
Ramsdell Quarry Landfill
and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna Joint Military Training Center
Former Ravenna Army Ammunition Plant Portage and Trumbull
Counties, Ohio
Contract No. W912QR-13-C-0031
Prepared for:
U.S. Army Corps of Engineers
Louisville District
Prepared by:
December 7, 2015
-
Draft 1 2015 Annual Land Use Control Monitoring Report, 2
RVAAP-01 Ramsdell Quarry Landfill 3 and 4
RVAAP-05 Winklepeck Burning Grounds 5 6
Camp Ravenna Joint Military Training Center 7 Former Ravenna
Army Ammunition Plant 8
Portage and Trumbull Counties, Ohio 9 10
Contract No. W912QR-13-C-0031 11 12 13 14
Prepared for: 15
16 U.S. Army Corps of Engineers 17
Louisville District 18 19
20
Prepared by: 21
22
23 24
December 7, 2015 25 26 27
28
-
Draft FY2015 Annual Land Use Control Monitoring Report, RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
DISCLAIMER STATEMENT 29 30
This document is a work prepared for the United States
Government by Vista Sciences 31 Corporation. In no event shall
either the United States Government or Vista Sciences Corporation
32 have any responsibility or liability for any consequences of any
use, misuse, inability to use, or 33 reliance on the information
contained herein, nor does either warrant or otherwise represent in
any 34 way the accuracy, adequacy, efficacy, or applicability of
the contents hereof. 35
36 37 38 39
40
-
Draft FY2015 Annual Land Use Control Monitoring Report, RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
41
Place Holder for 42
Ohio EPA Approval Letter 43
44 (Letter will be inserted upon approval) 45
46
47
48
49
50
51
52
53
54
55
56
57
58
-
Draft FY2015 Annual Land Use Control Monitoring Report, RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
DOCUMENT DISTRIBUTION 59 For the 60
Draft 2015 Annual Land Use Control Monitoring Report, 61
RVAAP-01 Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning
Grounds 62
63 Camp Ravenna Joint Military Training Center 64
Former Ravenna Army Ammunition Plant 65 Portage and Trumbull
Counties, Ohio 66
67
Name/Organization Number of Printed
Copies Number of
Electronic Copies
Mark Leeper, ARNG-ILE Clean Up 0 1
Kevin Sedlak, ARNG and Katie Tait, OHARNG 1 1
Andrew Kocher, Ohio EPA Project Manager – NEDO-DERR 1 3
Justin Burke, Ohio EPA – CDO-DERR 0 Email w/o attachments0
Quyet La, USACE - Louisville 1 1
Administrative Record – RVAAP Restoration Program 2 2
68 ARNG-ILE = Army National Guard Environmental Programs
Division 69 OHARNG = Ohio Army National Guard 70 Ohio EPA-NEDO-DERR
= Ohio Environmental Protection Agency-Northeast District Office
–Division of 71 Environmental Response and Revitalization 72 Ohio
EPA-CDO-DERR = Ohio Environmental Protection Agency-Central
District Office –Division of 73 Environmental Response and
Revitalization 74 USACE = United States Army Corps of Engineers 75
RVAAP = Ravenna Army Ammunition Plant 76
-
Draft FY2015 Annual Land Use Control Monitoring Report, RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page i
TABLE OF CONTENTS 77 SECTION 1.0 INTRODUCTION
...............................................................................................
1 78
1.1 Report Introduction
...............................................................................................................
1 79 1.2 Facility Location
...................................................................................................................
1 80
1.3 Facility History
......................................................................................................................
2 81
1.4 Land Use Controls, Monitoring, And Reporting Requirements
........................................... 3 82
1.5 Annual LUC Inspection and Monitoring Report Requirement
............................................. 3 83
SECTION 2.0 ANNUAL LUC MONITORING REPORT FOR RAMSDELL QUARRY 84
LANDFILL
...............................................................................................................................
5 85
2.1 Ramsdell Quarry
Landfill......................................................................................................
5 86
2.2 RQL Annual Inspection Form
...............................................................................................
6 87
SECTION 3.0 ANNUAL LUC MONITORING REPORT FOR WINKLEPECK 88
BURNING GROUNDS
...............................................................................................................
10 89
3.1 Winklepeck Burning Grounds
.............................................................................................
10 90 3.2 LUC Quarterly Inspection and Report Mechanisms for WBG
........................................... 10 91
3.3 Land Use Control Awareness Training
...............................................................................
12 92
3.4 Camp Ravenna Perimeter Fence
.........................................................................................
12 93
SECTION 4.0 CONCLUSION
..................................................................................................
14 94 4.1 General LUC Training
........................................................................................................
14 95
4.2 Land Use Consistency and Land Use Control Effectiveness at
RQL ................................. 14 96
4.3 Land Use Consistency and Land Use Control Effectiveness at
WBG ................................ 14 97
4.4 Land Use Control Deficiency Corrective Action at RQL and WBG
.................................. 15 98 4.5 Land Use Control
Effectiveness Certification
....................................................................
15 99
SECTION 5.0 REFERENCES
..................................................................................................
16 100
101
102
LIST OF APPENDICES 103
Appendix A Weekly RQL Inspection Reports 104 Appendix B RQL Soil
Repair Memo 105 Appendix C Quarterly RQL Inspection Reports 106
Appendix D RQL Access Logs 107 108
-
Draft FY2015 Annual Land Use Control Monitoring Report, RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page ii
LIST OF APPENDICES, continued 109 Appendix E RQL Annual
Inspection Photographs 110 Appendix F FY 2015 Quarterly Land Use
Control Index Maps 111 Appendix G Final FY 2015 First Quarter Land
Use Control Inspection, RVAAP-05 112
Winklepeck Burning Grounds 113 Appendix H Final FY 2015 Second
Quarter Land Use Control Inspection, RVAAP-05 114
Winklepeck Burning Grounds 115 Appendix I Final FY 2015 Third
Quarter Land Use Control Inspection, RVAAP-05 116
Winklepeck Burning Grounds 117 Appendix J Final FY 2015 Fourth
Quarter Land Use Control Inspection, RVAAP-05 118
Winklepeck Burning Grounds 119 Appendix K FY 2015 Perimeter
Fence Defect Call Outs Identified and Repaired 120 121
-
Draft FY2015 Annual Land Use Control Monitoring Report, RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page iii
LIST OF ACRONYMS AND ABBREVIATIONS 122
ACM Asbestos Containing Material 123 AOC Area of Concern 124 AR
Army Regulation 125 ARNG Army National Guard 126 bgs below ground
surface 127 Camp Ravenna Camp Ravenna Joint Military Training
Center 128 CERCLA Comprehensive Environmental Response,
Compensation, and Liability 129
Act 130 C.F.R. Code of Federal Regulations 131 DFFOs Director’s
Final Findings and Orders 132 FWSAP Facility-Wide Sampling and
Analysis Plan 133 FWGWMPP Facility-Wide Groundwater Monitoring
Program Plan 134 FY Fiscal Year 135 GIS Geographical Information
System 136 IRP Installation Restoration Program 137 LUC Land Use
Control 138 MK Mark 139 MEC Munitions and Explosives of Concern 140
MRS Munitions Response Site 141 NCP National Contingency Plan 142
NBC Nuclear, Biological, Chemical 143 Ohio EPA Ohio Environmental
Protection Agency 144 OHARNG Ohio Army National Guard 145 PMP
Property Management Plan 146 RD Remedial Design 147 RDX Research
Department Explosive 148 ROD Record of Decision 149 RQL Ramsdell
Quarry Landfill 150 RVAAP Ravenna Army Ammunition Plant 151 SOP
Standard Operating Procedure 152 TNT Trinitrotoluene 153 U.S.C.
United States Code 154 USP&FO United States Property and Fiscal
Officer 155 UXO Unexploded Ordnance 156 WBG Winklepeck Burning
Grounds 157
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page 1
SECTION 1.0 INTRODUCTION 158
1.1 Report Introduction 159 As of September 2015, two areas at
the former Ravenna Army Ammunition Plant (RVAAP), 160 now known as
the Camp Ravenna Joint Military Training Center (Camp Ravenna) have
161 designated Land Use Controls (LUCs); Ramsdell Quarry Landfill
(RQL) and Winklepeck 162 Burning Grounds (WBG). As explained in
greater detail in Sections 1.4 and 1.5, annual reports 163 are
required for the areas at Camp Ravenna that utilize LUCs to protect
the integrity of an 164 environmental remedy (if present), human
health, and the environment by limiting the activities 165 that may
occur at those areas. 166
The following sections present the 2015 Annual Report for Land
Use Controls Inspections, 167 RVAAP-01 Ramsdell Quarry Landfill and
RVAAP-05 Winklepeck Burning Grounds, Camp 168 Ravenna Joint
Military Training Facility, Former Ravenna Army Ammunition Plant,
Portage and 169 Trumbull Counties, Ohio. This annual report is laid
out as follows: 170
Section 1.0 – General introduction to the facility, and a
general description of Land Use 171 Controls, monitoring and annual
reporting requirements. 172 Section 2.0 – Annual Report for RQL.
173 Section 3.0 – Summary of FY2015 Quarterly LUC Inspection
Reports for WBG. 174 Section 4.0 – Conclusions 175 Section 5.0 –
References 176
1.2 Facility Location 177 Camp Ravenna is located in
northeastern Ohio within Portage and Trumbull counties, and is 178
approximately three miles east/northeast of the City of Ravenna and
one mile north/northwest of 179 the City of Newton Falls. The
facility is approximately 11 miles long and 3.5 miles wide. The 180
facility is bounded by State Route 5, the Michael J. Kirwan
Reservoir, and the CSX System 181 Railroad to the south; Garret,
McCormick, and Berry Roads to the west; the Norfolk Southern 182
Railroad to the north; and State Route 534 to the east, as shown in
Figure 1. In addition, the 183 facility is surrounded by the
communities of Windham, Garrettsville, Charlestown, and 184
Wayland. 185
186
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page 2
187
Figure 1.0 Map of Camp Ravenna Joint Military Training Center
188 (Former Ravenna Army Ammunition Plant) 189
190
1.3 Facility History 191 RVAAP was a load, assemble, and pack
facility built to produce large-caliber artillery projectiles 192
and bombs. Although RVAAP downsized after World War II, plant
production lines were 193 reactivated during the Korean and Vietnam
Wars. Additionally, the plant conducted nearly 194 continuous
demilitarization of war stocks, refurbishment of inventoried
ammunition, and minor 195 research and development projects. By
1992, the installation's status changed from "inactive but 196
maintained" to that of "caretaker." 197
The Department of Defense established the Installation
Restoration Program (IRP) to provide 198 guidance and funding for
the investigation and cleanup of potential contamination and past
199 operations caused by historical activities at military
installations. The IRP began at RVAAP in 200 1989. Administrative
accountability for the initial acreage of the facility was
transferred to the 201 United States Property and Fiscal Officer
(USP&FO) for Ohio in May 1999 with subsequent 202 transfers to
follow. To date, administrative accountability for the entire
21,683-acre facility has 203 been transferred to the USP&FO for
Ohio and subsequently licensed to the Ohio Army National 204 Guard
(OHARNG) for use as a military training site, Camp Ravenna. The
RVAAP restoration 205 program involves cleanup of former
production/operational areas throughout the facility related 206 to
former activities conducted under the RVAAP. The restoration
program is currently managed 207 by the Army National Guard (ARNG)
with support from the OHARNG. 208
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page 3
1.4 Land Use Controls, Monitoring, And Reporting Requirements
209 All work, plans, and documentation for the RVAAP IRP at Camp
Ravenna must be in 210 conformance with the Comprehensive
Environmental Response, Compensation, and Liability 211 Act
(CERCLA) [42 United States Code (U.S.C.) §9601, et seq.], the
National Contingency Plan 212 (NCP) [40 Code of Federal Regulations
(C.F.R.) Part 300], and the Director's Final Findings and 213
Orders (DFFOs) [June 10, 2004]. If residual contamination is left
in place after the CERCLA 214 remediation process is complete and
the contamination still poses a potential for unacceptable 215
risks or exceeds cleanup standards, then the Record of Decision
(ROD) for the Areas of 216 Concern/Munitions Response Sites
(AOC/MRS) will require LUCs in accordance with the 217 approved
Remedial Design (RD). 218
LUCs include any physical, legal, or administrative mechanism
that places restrictions on the use 219 of, or limits access to,
real property to prevent exposure to contaminants at concentrations
greater 220 than permissible levels or other safety issues. The
intent of using these controls is to protect the 221 integrity of
the remedy (if present), human health, and the environment by
limiting the activities 222 that may occur at an AOC/MRS. When
implemented, these LUCs provide protection to 223 individuals using
or working at the AOC/MRS by limiting and/or preventing activities
which 224 could potentially result in risks to those individuals.
The Army is responsible for controlling 225 land use on active
installations such as Camp Ravenna and can internally restrict the
use of such 226 property. LUCs may include engineering controls
such as fences, Seibert markers and signs, or 227 administrative
controls such as awareness training and restrictions on use
including type of use 228 and duration. 229 The Property Management
Plan (PMP), dated August 2012, identifies LUCs and restrictions for
230 specific AOCs/MRSs at Camp Ravenna and provides mechanisms to
implement and manage 231 those LUCs. The PMP is required under Army
Regulation (AR) 210-20 and satisfies 232 requirements of the DFFOs.
The PMP lists general performance objectives of LUCs at Camp 233
Ravenna as well as AOC/MRS specific LUCs detailed to address the
concerns present on that 234 particular AOC/MRS. According to
Section 1.3 of the PMP, it is the responsibility of the Army 235 to
implement, inspect, maintain and enforce LUCs set forth under the
RVAAP Restoration 236 Program. 237
1.5 Annual LUC Inspection and Monitoring Report Requirement 238
The PMP requires that the Army conduct a minimum of an annual
inspection of the LUCs to 239 confirm that the LUCs remain
effective and still meet the LUC objectives, and also requires that
240 the results of the annual LUC inspection be included in an
Annual LUC Monitoring Report to be 241 submitted to the Ohio EPA
for review and approval. The Annual LUC Monitoring Report is 242
required to evaluate the status and effectiveness of LUCs with a
description of how LUC 243 deficiencies, including inconsistent
land uses, were addressed. The Annual LUC Monitoring 244 Reports
will be used in the preparation of the CERCLA 121(c) Five-Year
Review. This Annual 245 LUC Monitoring Report presents the
following: 246
• The FY 2015 Annual Report for the Ramsdell Quarry Landfill.
The LUCS were 247 instituted for RQL in December 2014. This is the
first annual LUC report for RQL. 248
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page 4
• A summary of the monitoring conducted during the Fiscal Year
(FY) 2015 Quarterly 249 LUC Inspection Reports for WBG. This is the
third annual report completed in 250 accordance with the Final PMP
dated August 2012. 251
Additionally, the PMP requires that a written certification will
be submitted with the Annual 252 Monitoring Report that states
whether or not the LUCs remain in place and are effective. The 253
written certifications for both the RQL and WBL LUCs are presented
in Section 4.4. 254
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page 5
SECTION 2.0 ANNUAL LUC MONITORING REPORT FOR RAMSDELL 255 QUARRY
LANDFILL 256
2.1 Ramsdell Quarry Landfill 257 RQL encompasses approximately
14 acres in the northeastern portion of Camp Ravenna. RQL 258 was
initially a stone quarry that was excavated 30 to 40 feet below
existing grade until ceasing 259 quarrying operations in 1941. From
1946 to the 1950s, the bottom of the quarry was used to 260 burn
waste explosives from Load Line 1. Between 1941 and 1989, the
western and southern 261 sections of the abandoned quarry were used
for landfill operations. No information is available 262 regarding
landfill disposal activities from 1941 to 1976, and no information
is available on other 263 activities at the quarry from the 1950s
to 1976. Only nonhazardous solid waste was deposited in 264 RQL
from 1976 until it was closed in 1989. In 1978, a portion of the
abandoned quarry was 265 permitted as a sanitary landfill by the
State of Ohio. The sanitary landfill closed in 1990 under 266 State
of Ohio solid waste regulations, and was covered by a clay cap
covering approximately 267 four acres. 268
Although post-closure requirements for RQL under State of Ohio
solid waste regulations only 269 require that a quarterly
inspection be conducted, weekly inspections have been conducted at
the 270 site as a best management practice. The weekly inspections
assess the condition of various 271 aspects of the RQL, including
(but not limited to) vehicular access, gate and fence condition,
272 landfill and cap integrity, and groundwater monitoring well
security. The weekly inspection 273 sheets from December 1, 2014
through October 15, 2015 are presented in Appendix A. 274
A large amount of construction and miscellaneous debris was
discovered during soil remediation 275 and removal activities in
the quarry bottom in June 2010. A portion of the debris was found
to 276 have asbestos-containing material (ACM) in them. After
removing and disposing of the soil and 277 construction debris (all
considered as ACM), the area was backfilled and graded to the
pre-278 excavation elevation. 279
RQL is managed as Restricted Access due to residual asbestos and
contamination and the closed 280 landfill. Permissible exposure
parameters have been established for personnel accessing the 281
RQL, and are defined as one hour/day for 250 days/year for 25
years. In order to enforce the 282 Restricted Access status of the
RQL, the following LUCs were established in December 2014: 283
• All digging or excavation within the quarry bottom is
prohibited. 284 • Digging and excavation on the landfill cap will
be regulated by the post-closure care plan 285
and the Ohio solid waste regulations. 286 • Permanent warning
signs will be installed and maintained around RQL on the gates and
287
on the chain-link and high tensile wire fence at 300 ft. centers
to warn of the ACM hazard 288 in the quarry bottom. The signs will
meet the requirements of OAC 3745-20-289 07(B)(1)(b). 290
• As no soil disturbing activities are allowed within the quarry
bottom, OSHA asbestos 291 training set forth at 29 CFR
1926.1101(k)(9)(vii) is not required. Any personnel entering 292
the quarry bottom will be briefed of the asbestos hazards. 293
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page 6
In order to track exposure, personnel entering the LUC area sign
an access log sheet each time 294 they enter and exit the LUC area.
295
2.2 RQL Annual Inspection Form 296
Camp Ravenna Joint Military Training Center (Camp Ravenna)/
Former Ravenna Army 297 Ammunition Plant (RVAAP) Land Use Control
(LUC) Inspection Form for RVAAP-01 298
Ramsdell Quarry Landfill AOC 299
In accordance with the Camp Ravenna/former RVAAP PMP (dated
August 2012) and Appendix 300 A-2 and the Final Remedial Design for
Soil and Dry Sediment at RVAAP-01 Ramsdell Quarry 301 Landfill
(RQL), a LUC inspection of RQL was conducted by Allan Brillinger
(Vista Sciences 302 Corporation) on behalf of Camp Ravenna on
October 15, 2015. 303 304 According to LUCs set forth in the Final
Remedial Design for Soil and Dry Sediment at 305 the RVAAP-01
Ramsdell Quarry Landfill, dated 9 April 2014, and memorialized in
the PMP, 306 periodic monitoring of LUCs, in the form of site
inspections, is required to be conducted by 307 the Army to confirm
that the LUCs remain effective and still meet LUC objectives for
308 continued remedy protectiveness. Site inspections are required
to be conducted on an 309 annual basis and inspections of the solid
waste landfill are conducted in accordance with State 310 of Ohio
solid waste regulations and the Ohio Environmental Protection
Agency (Ohio EPA) 311 Director’s Final Findings and Orders (Ohio
EPA 2004). Additional LUC inspections may 312 be conducted when
landfill inspections are conducted as needed. The required Annual
LUC 313 Report is to be submitted to the Ohio EPA for review and
approval. 314
315 The inspections shall include the following: 316
• Review of LUC training/inbriefs/maintenance and access logs
and other documentation 317 as applicable to RQL. 318
• Evaluation of activities at RQL to ensure that all activities
executed within RQL are 319 in compliance with the established
digging restrictions and established exposure limits 320 (Security
Guard/Maintenance Worker - one (1) hour/day for 250 days/year for
25 years). 321
o All digging or excavation within the quarry bottom is
prohibited due to residual 322 asbestos and contamination. 323
o Digging and excavation on the landfill cap will be regulated
by the post closure 324 care plan and the Ohio solid waste
regulations. 325
o Due to not meeting the industrial/commercial standard,
exposure monitoring 326 for the full-time facility employee must be
conducted to ensure and document 327 that exposure at the AOC is
not above the established exposure limit set 328 for the Security
Guard/Maintenance worker of one (1) hour/day for 250 329 days/year
for 25 years. 330
• Inspection of warning signs on gates and fencing. 331 •
Inspection of RQL fencing and gates. 332
333 LUC deficiencies or inconsistent land uses that are
identified must be reported and identified 334 on the inspection
form/report and must also be reported to the Army National Guard
335 (ARNG)/Ohio Army National Guard (OHARNG). 336
337
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
38 Review of LUCs – Management/Corrective Action
Activities and Land Use: a) This AOC is to be managed as
Restricted Access and is restricted from residential land
use. Has residential use occurred? Have other land uses or land
use changes occurred?
No residential land use has occurred at the RQL. There have been
no other land uses or land use changes over the past year.
b) What activities have occurred at RQL since last Inspection?
Has any maintenance been performed at the AOC?
This is the first annual inspection of the RQL since the LUCs
were instituted in December 201. The high tensile wire fence was
repaired due to single strand breaks in December 2014 and January
2015. In mid-January, three eroded areas within the LUC enclosure
(but off the landfill cap) were filled with clean soil, and were
seeded April 2015 once the snow cover melted (Appendix B). Annual
mowing was conducted for the RQL in early October. Additional minor
eroded/settled areas inside the LUC enclosure (but off the landfill
cap) were filled with clean soil and seeded in October 2015.
Weekly inspections were conducted in accordance with Ohio solid
waste regulations. The weekly inspection forms are presented in
Appendix A. Quarterly inspections were conducted by the Portage
County Health Department. The quarterly inspection letters are
presented in Appendix C.
Semi-annual groundwater monitoring activities were conducted at
the RQL in March 2015 and July 2015.
c) Are activities at RQL being conducted in compliance with
established digging restrictions and established exposure limits
(exposure for full-time employees who access RQL must be
tracked)?
The activities taking place at RQL are being conducted in
accordance with the established digging restrictions. The exposure
limits to personnel who must access the RQL LUC area are being
tracked with Log In sheets that every person entering the LUC area
must fill out when entering and exiting the LUC area. The completed
Access Log sheets for December 2014 through October 15, 2015 are
presented in Appendix D.
d) Are the warning signs in place and functional? Please note
condition and any deficiencies.
The warning signs are posted on the RQL LUC fence and gate as
required. Signs that read “DANGER – Unauthorized Personnel Keep
Out” and “Danger – Asbestos Waste Disposal Site – Do Not Create
Dust – Breathing Asbestos is Hazardous to Your Health” are posted
on the LUC fence and gate at 300 ft. centers.
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page 7
3
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page 8
e) Is the RQL fencing and gates intact and in good condition?
Please note condition and any deficiencies.
The RQL fencing and gate are intact and in good condition. There
are no deficiencies with the fence and gates.
Inspections and Reporting Inspections are required on an annual
basis. Periodic monitoring inspections may be conducted as needed.
Are annual inspections being conducted as required? Have any
additional inspections been completed?
The annual LUC inspection was conducted on October 15, 2015. As
per Ohio solid waste regulations, The RQL is inspected weekly. The
weekly RQL inspection forms are presented in Appendix A.
Additionally, the Portage County Health Department conducts a
quarterly inspection of the RQL. The Portage County Health
Department inspection letters are presented in Appendix D.
Photographs of the RQL LUC area taken during the annual inspection
are presented in Appendix E.
An Annual Report is required. Has the annual report been
completed and submitted to the Ohio EPA?
The RQL LUCs were instituted in December 2014. This is the first
annual inspection and report for the RQL LUCs.
Training/Inbriefs (as applicable to RQL): Are RQL LUC training
and/or inbriefs (for those who need to access RQL) being conducted
as applicable? Describe the training (content/who attended/who
provided/documentation of training).
LUC training is provided annually to all Camp Ravenna staff and
tenant units at Camp Ravenna, and was conducted on March 3rd and
5th, 2015. The LUC training is typically provided by Katie Tait
and/or Tim Morgan, Camp Ravenna-Environmental. The training
provides an overview of the history of the facility, the ongoing
cleanup work, the location of the cleanup sites, any land use
controls/restrictions on AOCs/Munitions Response Sites (MRS), and
specific LUC and other restrictions for RQL, as well as other areas
at Camp Ravenna. Training materials and rosters are on file in the
Camp Ravenna Environmental Office. Training will be conducted for
additional Camp Ravenna staff and contractors that missed the March
training dates as needed.
A “Land Use Control (LUC) Brief for Contractors/Personnel” was
conducted for all personnel that entered the RQL LUC area. The
training consisted of a review of the RQL site history, the
environmental hazards present at the RQL, the LUC s that have been
instituted, and the requirements of all personnel that enter the
LUC area. All personnel that have received the brief sign the
briefing form that states that they have been briefed and
understand the RQL
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page 9
LUC requirements, and that they will comply with all
requirements. The signed briefing forms are kept on file at the
Camp Ravenna Environmental office.
If training was not provided, explain why and what corrective
actions were initiated.
N/A
Is access to RQL for full-time employees of the facility being
logged in order to track exposure? Please review access logs to
ensure exposure is within the established exposure limits.
Access for all personnel entering the RQL LUC area are being
tracked with the Access Log. The established exposure limits are
one (1) hour/day for 250 days/year for 25 years. The most any one
worker was working inside the RQL area from December 1, 2014
through October 15, 2015 was 41 hours for a Maintenance Worker. The
Maintenance Worker that had the 41 hours within the LUC area spent
4.5 hours conducting soil repairs and 36.5 hours mowing.
LUC Violations (if any): Description of any observed/noted LUC
violation(s) as identified.
The top wire of the 5-wire fence was observed to be broken on
December 19, 2014 and again on January 30, 2015.
Date of Notification of LUC violations (if applicable) to
ARNG/OHARNG:
The above-noted fence wire breaks were reported to ARNG/OHARNG
on December 19, 2014 and January 30, 2015.
Description of any corrective actions taken to remedy observed
LUC violations or recommended corrective actions:
The fence was repaired on December 30, 2014 and again on March
13, 2015.
Additional Notes/Comments:
Original Inspection Completed by:
Signature:
Printed Name: Allan B. Brillinger Title: Program Manager
Organization: Vista Sciences Corporation Date: October 15, 2015
339
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page 10
SECTION 3.0 ANNUAL LUC MONITORING REPORT FOR WINKLEPECK 340
BURNING GROUNDS 341
3.1 Winklepeck Burning Grounds 342 As described in the Property
Management Plan (PMP), WBG encompasses 211.66 acres and is 343
located in the central portion of Camp Ravenna (see Appendix F
maps). The burning grounds 344 area has been in operation since
1941. Prior to 1980, burning was conducted on the bare ground 345
and the ash was abandoned at the site. Wastes treated in the area
included Research Department 346 Explosive (RDX), antimony sulfide,
Composition B, lead azide, trinitrotoluene (TNT), 347 propellants,
black powder, waste oil, sludge from the load lines, domestic
wastes, and small 348 amounts of laboratory chemicals. From 1980
until 1998, periodic burning of scrap explosives, 349 propellants,
and explosive-contaminated waste materials (e.g., wipe rags, paper,
and cardboard) 350 was conducted in raised refractory-lined metal
trays within a 1.5-acre area. A Part-B permit 351 covering the
active portion of the site was withdrawn in 1994. The burn trays
along the 90-day 352 storage unit of Building 1601 were closed in
accordance with Ohio Environmental Protection 353 Agency (Ohio EPA)
guidance in 1998. Munitions and Explosives of Concern (MEC) is
present 354 in the Area of Concern (AOC). The previously applied
remedy at the WBG AOC consisted of 355 excavation of contaminated
soil to preclude likely exposure through human contact. A portion
356 of that remedy resulted in hazardous substances, pollutants, or
contaminants remaining greater 357 than levels that allow unlimited
use and unrestricted exposure. Therefore, a component of the 358
remedial action at the WBG AOC includes LUCs which are detailed in
Section A-1.6 of the 359 PMP. 360
Per the PMP, the land use for the WBG is Small Arms Range
(including the existing Mark [MK] 361 19 Grenade Machinegun Range)
for the OHARNG Military Use and Training. The Department 362 of the
Army has classified the Small Arms Range as an Operational Range at
the WBG AOC. 363 The Small Arms Range Land Use, in terms of the
Risk Assessment, was created to assess 364 specific training
activities that would occur on a small arms range and was developed
to assess 365 risks to OHARNG personnel. In addition to the small
arms training, certain activities are 366 required to sustain and
maintain the area as a range, such routine maintenance and
activities are 367 permitted if conducted by authorized personnel.
More specific maintenance activities that are to 368 be performed
by the National Guard Range Maintenance Soldier and/or other
similar authorized 369 personnel on the WBG AOC can be found in the
PMP. 370
3.2 LUC Quarterly Inspection and Report Mechanisms for WBG 371
The PMP states that site inspections will be conducted on a
quarterly basis at WBG. The WBG 372 Inspectors Quarterly Inspection
Report Form completed for each quarter of FY 2015 states that 373
all quarterly inspections include evaluation of the following:
374
• Review of LUC training and documentation as applicable to WBG.
375 • Evaluation of the facility perimeter fence to ensure that it
is maintained in a manner that is 376
protective and effective and deters trespassers. 377 •
Evaluation of activities at WBG to ensure that all activities
executed within WBG are in 378
compliance with OHARNG range safety regulations/standard
operating procedures (SOPs), 379 established digging restrictions,
and established exposure limits. All digging, intrusive 380
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page 11
activities, or excavation on the WBG AOC outside of the
Unexploded Ordnance (UXO)/ 381 MEC-cleared areas within the MK-19
Grenade Machinegun Range is prohibited with the 382 following
exceptions: 383
o Routine maintenance of roads, ditches, culverts and activities
listed in A-1.4 of the 384 PMP (maintenance of targetry and
associated lifting mechanisms, range maintenance 385 activities
including removal of practice rounds, vegetation management,
compatible 386 natural resource management activities, nuisance
wildlife control, drainage 387 maintenance, wetland delineation,
grassland management, scientific research and 388 sampling
activities); 389
o Ground surface repairs by authorized range personnel in
support of authorized range 390 activities; 391
o Digging along target array areas by authorized range personnel
to a depth of one (1) 392 foot below ground surface (bgs). 393
This shall also include evaluation of required range signage.
The range is required to be 394 marked with signage in conformance
with the requirements of the current Department of 395 Army
regulations. 396
• Evaluation of groundwater activities to ensure that any
groundwater activities are being 397 conducted in a manner
consistent with established LUCs. Groundwater use or extraction of
398 groundwater located at or underlying the WBG AOC or any portion
thereof is prohibited, 399 except for the following: 400
o The installation, development, purging, and sampling of new or
existing monitoring 401 wells in accordance with the most recent
Facility-Wide Sampling and Analysis Plan 402 (FWSAP) as part of the
AOC-specific IRP or Facility-Wide Ground Water 403 Monitoring
Program Plan (FWGWMPP). 404
o The abandonment and replacement of monitoring wells damaged by
activities 405 conducted on the Installation and wells no longer
utilized as part of IRP or 406 FWGWMPP activities, in accordance
with Ohio EPA guidance, the most recent 407 FWSAP, and applicable
Ohio Administrative Code requirements. 408
409 Four quarterly LUC inspection were conducted during FY 2015.
The LUC inspections generally 410 consisted of the following:
411
• An inspection of the Camp Ravenna perimeter fence. 412 • A
review of current land uses at WBG to determine if they are in
compliance with the 413
LUCs. 414 • A review of activities at WBG since the previous
inspection to determine if they are in 415
compliance with the LUCs. 416 • A review of required warning
signage. 417 • A review of training applicable to WBG LUCs. 418 • A
description of any noted LUC deficiencies, any corrective actions
taken to remedy the 419
LUC deficiencies, and/or any recommended corrective action. 420
The following WBG quarterly inspections were conducted in FY 2015
by Don Trocchio of Vista 421 Sciences Corporation: 422
• FY 2015 First Quarter Land Use Control Inspection, RVAAP-05
Winklepeck Burning 423 Grounds (report dated April 3, 2015,
inspection completed December 17, 2014). This 424 report is
included in Appendix G. 425
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page 12
• FY 2015 Second Quarter Land Use Control Inspection, RVAAP-05
Winklepeck Burning 426 Grounds (report dated July 23, 2015,
inspection completed March 31, 2015). This report 427 is included
in Appendix H. 428
• FY 2015 Third Quarter Land Use Control Inspection, RVAAP-05
Winklepeck Burning 429 Grounds (report dated October 30, 2015,
inspection completed June 15, 2015). This 430 report is included in
Appendix I. 431
• FY 2015 Fourth Quarter Land Use Control Inspection, RVAAP-05
Winklepeck Burning 432 Grounds (report dated TBD, inspection
completed August 13, 2015). This report is 433 included in Appendix
J. 434
3.3 Land Use Control Awareness Training 435 Section 4.2 of the
PMP, Land Use Control Awareness Training, describes requirements
and 436 guidelines for LUC awareness training at the facility. LUC
awareness training for Camp 437 Ravenna staff and tenant units was
conducted on March 3rd and 5th, and is provided annually to 438 all
Camp Ravenna staff and tenant units at Camp Ravenna. Formal LUC
training has been 439 conducted since 2006 and refresher training
is given annually to all personnel. The LUC training 440 is
typically provided by Katie Tait and/or Tim Morgan, Camp
Ravenna-Environmental. The 441 training provides an overview of the
history of the facility, the ongoing cleanup work, the 442 location
of the cleanup sites, any land use controls/restrictions on
AOCs/Munitions Response 443 Sites (MRS), and included specific
restrictions for WBG. Annual training is conducted 444 throughout
the year as needed for additional Camp Ravenna staff and
contractors that missed the 445 March training dates. 446
Using units also receive an in-brief prior to firing on the
range. Using units and tenant units at 447 Camp Ravenna are not
allowed down range. Environmental contractors who access WBG are
448 also provided with an in-brief which informs them of the
LUCs/restrictions at the AOC. They 449 must read and sign the
in-brief form. Training records are kept on file in the Camp
Ravenna 450 Environmental Office. 451
3.4 Camp Ravenna Perimeter Fence 452 Currently, the only
facility-wide engineering control for the AOCs/MRSs is the
perimeter fence, 453 as listed in Section 4.1.1 of the PMP. The
Camp Ravenna perimeter fence is situated mostly in 454 Portage
County, Ohio, with a small portion (see maps in Appendix F – FY
2015 Quarterly Land 455 Use Control Index Maps) extending easterly
into western Trumbull County, Ohio. The entire 456 perimeter fence
was inspected for each of the FY 2015 quarterly inspections.
457
The majority of the original Camp Ravenna perimeter fence is
approximately seventy years old. 458 Most, but not all, of the
perimeter fence situated within Trumbull County is less than 459
approximately ten years old. Typically, but not all, of the
perimeter fence consists of a six foot 460 high chain link fence
fabric with steel I-beam shaped posts set on 10 to 12 foot centers
set in 461 concrete footers. The top and bottom of the fence fabric
is reinforced with a horizontal pipe 462 running along the entire
length. On top of each post is a V bracket with six strands of
15-gauge 463 barb wire, three strands inward facing and three
strands outward facing. Twenty-six access gates 464 are scattered
throughout the approximate 30 miles of perimeter fencing evaluated
(see maps in 465
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page 13
Appendix F – FY 2015 Quarterly Land Use Control Index Maps).
Most of the former railroad 466 access gates have been welded shut
along with a few vehicle access gates that are no longer used.
467
In addition to documenting compliance with training, operation,
and maintenance requirement 468 set forth in the PMP, quarterly
inspections also identify, document, and map major defects along
469 the perimeter fence for future repair. In the inspector’s
judgment, a major defect was considered 470 a breach in the fence
through which an adult could gain unlawful access to the facility.
471 Additionally, during the evaluation, major defects noted in
previous inspections were visited and 472 repairs logged if
completed or ongoing. Geographical Information System (GIS) raw
field data 473 collected from the inspections were reduced and
compiled in ESRI Arc Map. Index Maps 474 depicting the call outs
along with Detail Maps and photographs of each call out were
prepared 475 and submitted along with the WBG Inspectors Quarterly
Inspection Report Form. Final 476 approved versions of each FY 2015
Quarterly LUC Inspection Report are included in 477 Appendices G,
H, I and J of this report. 478
The four quarterly inspections performed in FY 2015 reported a
total of 20 documented major 479 defects in the perimeter fence. A
total of 13 documented defects from the FY 2014 quarterly 480
inspections had not yet been repaired at end of the FY 2014
reporting period. Of this total, 29 481 repairs were performed and
documented in the subsequent (FY 2015) quarterly inspection 482
reports. See Appendix K for a table of all perimeter fence defect
call outs identified and repaired 483 in FY 2015. When a major
defect is noted during the LUC field inspection the Army is
notified 484 via email detailing the date and location. The date of
notification is included in the quarterly 485 LUC inspection report
under “Section 6. Date of notification of LUC violation (if
applicable).” 486
The Camp Ravenna maintenance crews are limited to making only
minor fence repairs. Repair 487 logs make reference to “contractor
needed” on some call out sections where more extensive 488 repairs
are required. An example would be storm washouts (i.e., SE2A) along
the perimeter road 489 that continue to damage the perimeter fence.
Culvert pipe inlets and outlets become clogged 490 with debris, old
corrugated metal culvert pipes have rusted and collapsed and some
pipe sizes are 491 unable to handle the storm runoff, all
contributing to the washouts along the perimeter road. 492
It should be noted that only repairs of defects called out and
included in previous LUC 493 Inspection Reports are conveyed in the
detail sheets of the subsequent LUC Inspection Reports. 494 These
repairs are documented in repair logs kept by the Camp Ravenna
Maintenance Crews and 495 are included with the quarterly reports
in Attachment 2 – Camp Ravenna Fence Repair Log 496 (Appendices G,
H, I and J of this report). Numerous minor repairs (consisting of
patching 497 smaller openings in the fence fabric, replacing
missing/broken barb wire, repairing frost heaved 498 posts,
removing fallen trees and branches resting on top of the fence)
that were not sited during 499 the LUC field inspection, were, and
continue to be, repaired by the Camp Ravenna 500 staff/maintenance
crew and are not documented in repair logs. Overall, the perimeter
fence at 501 Camp Ravenna is intact and in good condition, and is
an effective LUC for the WBG. 502
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page 14
SECTION 4.0 CONCLUSION 503
4.1 General LUC Training 504 The OHARNG provided training to all
Camp Ravenna staff and tenant units including an 505 overview of
the history of the facility, the ongoing cleanup work, the location
of the cleanup 506 sites, any land use controls/restrictions on
AOCs/MRSs, and specific restrictions for RQL and 507 WBG (See
Section 2.2 and 3.3). All training requirements presented in the
PMP were met by the 508 OHARNG in FY 2015. Training compliance is
demonstrated in the RQL Inspection Form 509 (Section 2.2) and in
the FY 2015 Quarterly LUC Inspection Reports for WBG that are
included 510 in Appendices G, H, I and J of this report. Training
materials and rosters are on file in the Camp 511 Ravenna
Environmental Office. 512
4.2 Land Use Consistency and Land Use Control Effectiveness at
RQL 513 The land use at RQL is Restricted Access due to residual
asbestos, contamination and the closed 514 landfill. Based on the
completed weekly, quarterly and annual inspections at RQL, there
are no 515 inconsistent uses or activities discovered or reported
at RQL during the time when the LUCs 516 were instituted in
December 2014 through when the annual inspection was conducted on
October 517 15, 2015. All activities conducted within the RQL LUC
area were performed in compliance with 518 established digging
restrictions, and established exposure limits as described in the
PMP. This 519 indicates current LUC objectives are being met to
ensure the remedy is effective and protective. 520
An in-brief was provided to all personnel entering the RQL LUC
area that included an overview 521 of the history of the RQL, the
land use controls/restrictions, and specific restrictions for RQL.
522 All training and maintenance requirements specific to the RQL
LUC were met by the OHARNG 523 during this reporting period and is
documented in the pages of this report. 524
4.3 Land Use Consistency and Land Use Control Effectiveness at
WBG 525 Per the PMP, the land use for the WBG is Small Arms Range
(including the existing MK-19 526 Grenade Machinegun Range) for the
OHARNG Military Use and Training. Based on the 527 completed
inspections during FY 2015, there were no inconsistent uses or
activities discovered 528 or reported at WBG. All training and
activities conducted within the WBG AOC were 529 performed in
compliance with OHARNG range safety regulations/SOP, established
digging 530 restrictions, and established exposure limits as
described in the PMP. This indicates current 531 LUC objectives are
being met to ensure the remedy is effective and protective of human
health 532 and the environment. 533
The LUCs for the WBG AOC were evaluated quarterly in FY 2015 as
stated in the PMP using 534 the parameters listed in Section 3.1
LUC Quarterly Inspection and Reporting Mechanisms for 535 WBG.
These Quarterly LUC Inspections show all LUCs requirements
presented in the PMP for 536 WBG remained in place and were
effective through FY 2015. 537
Units that utilize the range at WBG also receive an in brief
prior to firing on the range and are 538 not allowed down range.
Environmental contractors who access WBG are also provided with an
539 in-brief which informs them of the LUCs/restrictions at the
AOC. All training, operation, and 540 maintenance requirements
specific to WBG presented in the PMP were met by the OHARNG in
541
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page 15
FY 2015 and is documented in the FY 2015 Quarterly LUC
Inspection Reports included in 542 Appendix G, H, I and J of this
report. 543
4.4 Land Use Control Deficiency Corrective Action at RQL and WBG
544 The main purpose of inspecting and monitoring LUCs is to
identify and correct LUC deficiencies 545 and violations. LUC
inspection reports allow the OHARNG to document consistent land
use, as 546 well as corrective action if deficiencies are
encountered. 547 548 For the RQL, inspections were conducted by
personnel familiar with the RQL so that changes (if 549 present)
were readily noted. Minor fence repairs and soil cover deficiencies
were noted and 550 corrected as weather conditions allowed. There
repairs were tracked throughout the year to 551 monitor their
effectiveness. 552
For the WBG, each quarterly inspection has been conducted using
the same parameters, resulting 553 in a uniform and concise system
of identification and repair of perimeter fence defect call outs.
554 Of the total number of perimeter fence defect call-outs
identified, approximately 80% were 555 repaired by the next
quarterly inspection. 556
4.5 Land Use Control Effectiveness Certification 557 This
certifies that to the best of my knowledge and belief all of the
information contained in this 558 Annual LUC Monitoring Report is
accurate, and that the Land Use Controls instituted for the 559
Ramsdell Quarry Landfill and the Winklepeck Burning Grounds are in
place and remain 560 effective. 561 562 563 / 564 (signature)
(date) 565 566 567 568 (printed name) 569 570 571 572 (Title).
573
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
Page 16
SECTION 5.0 REFERENCES 574 Final Property Management Plan for
the Designated Areas of Concern and Munitions Response 575 Sites,
Volume One – Version 1.0. U.S. Army Corps of Engineers. August
2012. 576 577 Ravenna Army Ammunition Plant Restoration Program
website: www.rvaap.org 578 Final Remedial Action Report for Soil
and Dry Sediment at RVAAP-01 Ramsdell Quarry 579 Landfill, Ravenna
Army Ammunition Plant, Portage and Trumbull Counties, Ohio. US Army
580 Corps of Engineers. January 30, 2015 581
582 583
http://www.rvaap/
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
584
585
586
587
588
589
Appendix A 590
Weekly RQL Inspection Reports 591
592
-
WEEKI..Y INSPECTION OF RAMS.DELL QUARRY LANDFILL
Weather Conditions I Recent P
Tune: Started ,o l '-' 0 . -- ..,.
Tvoe of:. ·-· / .. ,..,.....v,~
1. Vehicular Access
2.Entrance
a. Gate/Chain
3. Landfi11 Site/Cap
a. Vegetative Cover
b. Standing Water on Cap
c. Animal Distmbances
d. Woody Vegetation
e. Gully Erosion/Soil Cover
f. Runott: Siltation
g.Leacbate
14. Monitoring Wells (5) a. Locks inplace?
c. Well ID Legible
5.Commems:
J
. .. . -·
- ..u-' l- \\~00
SiteWalk Other
Statua/Condillon
\.j •
"'A A ,n y '
Ud2..C:... u-~ .
\J
' • ofD . - •. • Action needed:6. D
-
WE.EKLY INSPECTION OF RAMSDELL QUARRY LANDnLL
Date: Or 1 I.. -f \$. 1.-015
I. - . bv: A\ l:Sc;, \\Y')c..a..r. ......
Weather Conditions I Recent P. (.}
,: .$..,'{\(\'-'I... b2° ('a,; n ...§2 ~+~cJe.u.{ FvYi. u I
Tune: Started I: 'f S lamJdm) \;Of . ·" : 2.'.i-0 (am/Dffll
.Type or· 11: Wllldshield ,--Stte walk) Other
Inspected StatuslCondillo Commelds
1. Vehicular Access 400d v
2. Entrance
a. Gate/Chain ~d
. " .,_3. Landfill Site/Cao:
a Vegetative Cover qp~J "(".e. L.12...,1"\ \-\...., VVI-OweJ
...... v ' b. Standing Water on Cap 'Vl,..Oh/)
c. Animal Distw:baoces Y\OY\.Jl.. d. Woody Vegetation
\IL..O'(U/
e. Gully Erosion/Soil Cover ~oc) yv\..:1.(\C( (~(S (o+f c:.o.p)
Ar;~ . £ Runoff; Siltation ~oJ
g.Leachat.e ~
v 4. Monitoring Wells (5)
a Locks in place? wlS
b. Condi.tion ofC'.J11mna ~~ -c. Well ID Legible Ul2~
0
5. Comments:
'IC LUC. c,....J o-.Jl.A ov\
-
WEE.KLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: Oc.-h:::,\".la_f 2 ?-DIS
I, : bv: A-I 8',. ,·j/,'nt:.a/
(.J. . ..
Weather Conditions I Recent P. ,. 'iB" clove/q · YJt'J ,a..,,.'n
fi?,P v. 2 tf h,s - ' .... ' .,Tune: Started /0: l>U ·~ '-~!Iii
l .... 1':f\?o .= ~ _..JIIJ
.. -Type of i. 11: rW"llldsh~ C--SiteWalk'' Other
' -s,·fe wa.,fJ:. NW ~rnt?r CMl"I
v Inspected StatuslCondltlo Comme11ts
1. Vebicular Aca:ss 0r0cd (/
2.Entrance
a. Gate/Chain 9':0l)d ""u.J. ~c....,*e_ oee n for ~wil'lo, . v u
. u.3. Landfill Site/Cap- ..~
a. Vegetative Cover ~cJ - c..vrr-etrt fl '1.- lu, i n oi
WUJW-'1cf v u ll
b. Standing Water on Cap novi.P
c. Animal Distw:baoces ~ d. Woody Vegetation YU/vu?
e. Gully ErosionlSoil Cover ~d wuY\il, ~s 1u b P,· Ile) a.Fkr ~.
u ~
f. Runoff: Siltation ~
g.Leachate ~
4. Monitorinfl Wells (5)
a. Locks in place? u.os b. Condi.ti.on ofC'sunna ~rJ c. Well ID
Legiole ~>
LI
5. Comments:
C,cJrO:'wf/
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: .·~
1. Vehicular Acoess
2. Entrance
a. Gate/Chain
a. Vegetative C.over
b. Standing Water on Cap
c. Animal DistuibaDces
d. Woody Vegetation
e. Gully Erosion/Soil Cover
f. Runofl: Siltation
g.Leachate
a. Locks inplace?
b. Condltion of
c. Well ID Legtl>le
6. · "onof emedial Action needed:
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDffl..L
Date: .s~~+,.D.VV"'\.h D f \
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: 9-//-LS -I, bv: A-I Br; //,~c:;e.,- -w
. . ..J . -·Weather Conditions I Recent ; . s.., V'\ ~ oJ.- 7.3
0 IVO r@t'ort+ {'a..,c r"\ \J
• • _JTime: Started J/:o. ~ l 11:30 rz:i::'1- rl)
Tvoeofi. . ... Wmdshield SifeWalk) Other
'
lnapec:lad StatualConditlo Comments
1. Vehicular Access 6\oocJ
2.Entrance
a. Gate/Chain Gsn,,..\ .... _ .3. Landfill Site/Cao w
a Vegetative Cover ~ooeJ '1 '1 Cf. '~ +o '=, ' ~
-
- -
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: s~'rt""\k_, 3 2...c:)\S. .I, bv: A\ -e:,, ; \ h V')~
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date:~ - ~'b -d-._6\:)
Ins -!bv: \S ~t-~'\ 'Y\ ~\f\.4
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDn:LL
Date: 20,s.Av"l.cJor-S1 2.. I .. bv•I, - . vA-t Br; I/,' 11
-..12..r
u. . .. . ~00Weather Conditions I Recent :- Sv....,~ /,•a,
"1fr"a...in Pr-e v. 'Z. i k.,,,.~. \,J . .............. . . - I.-
I, .~Irrune: Started 3:35 _;,d •- 'S:Sv
-~-· -L
·--~ Type of:. . -, .. ·~n....,..,_ SiteWalk Other -
c) ru.Je ~ a.,rot.J~ th>-b.i' ~ cO f- LUC~~ Inspected
StatalSfCondltion Comments
1. Vehicular Access a~oJ u
2. Entrance
a. Gate/Chain ct.eocJ lo~cic.~':. c...t.o~ ..) ~ \.o::>~~J u
....,.3. Landfill Site/Cap " -.,
,...._a. Vegetati.ve Cover ....
.\ V~ · V(). ..\-a b' ~
-
WEEKI.Y INSPECTION OF RAMSDELL QUARRY LANDnLL
Date: 1-tJa..u&"t \~ '2.o I '4-. _. / bv:I, A' o,\ \'~
"'c:J.._' \..J. . .
Weather Condition& I Recent ;-- ,: ""') 0 !=,•t\ './
S,u"lt'\
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: /lu °lv.5 f 7 70 J.5 -. ~bv:I, A, Br,· I J; 11 c. cv,
Weather Conditiona I Recent ; . ·· .. ,:
CJ P"~ tl...i vlo vcJ ~ 73° nn reu:,,rz f ,rc...i rt
.u ' . . . ITime: Started 12:00 (aml.offl) /~:Zc) (amlaml
.. -n-Tvoe of i. .. ·--~ SiteWalk Other ' -
lnspect8d 8tatuelCondltio Commetll:s
1. Vehicular Access oA3od 0
2.Entrance
a. Gate/Chain °!
-
----
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: ..L; \\I\--- 3, Z.ol.5 '-' . -" bv:I, A\ -Sr;\ \,V)o.
~
....J . . Weather Conditions I Recent ;-. ,: 5-:,nlf').c,1_ ~c;
0 1'1:n fa.An orev. 2'/ h,s. .- .. I I I' , . ~ I •. --=-,.Time:
Started 12:w ·~-~ 12:'-lo IUJ - .. • ..,,.c" ••• '),.Type of it ,.:
/W'l'HftMR.-.J SiteWalk other
\...
lnspedad .....ISICondltlon Commelds
1. Vehicular Access o...Dod v
2. Entrance
a Gate/Chain ...... _,....,,.~ Eo..e:.\ Q,. c..:le.. \a..t-c."'-
c.d \u~tee) s.o +"-..d . v ~ loc..~ "\"" •'tS. '""' ,~~ \i.:,c.l:.
l"T. 3. umdfill Site/Cap ... ..
_, a Vegetative Cover ci.ood \Jee,.. . \JD ~ k.;x~~
u u '-J b. Standing Water on Cap Yl..DY\.() c. Animal
Disturbaoces ~ d. Woody Vegetation YUN,()
e. Gully ErosioolSoil Cover \/\..Ov\.Q.
f. RlDlOff: Siltation vw-Q
g.Leachatc ~
f4. Monitorin2 Wells (5) a Locks in place? .J2.S.
b. ~onofC'-ino ~ ......
c. Well ID Legible v\)2.S
\J
5. Comments:
. . . 6. n of- •. • Adion needed:
-
I
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: J0 \'""'- '2.t..\ '2. 01S
! bv: \j A\ "13r\ \ \\Yl~.12....r
CJ. . ...Weather Conditions I Recent ; I : ,POA:i\* $..,Y\n...._
'o~0 .'}'1.Zl ('e.LJ.l Yl-~ '"°>1P ,. • !"\ \j ' ' ~. ~ . ITime:
Started z:..oo (am/; I z:2..0 ·-·~,
. ....-..-,~--Twe ot· ,.: / .,... SiteWalk Other ~ -
lnspectad ~ Commelds
1. Vehicular Access ~~d
2. Entrance '--'
a. Gate/Chain .eo.s.+ ~~('!_ - ..... "\' °"-~rt --Car ~ ~~ W£S.t
ca c.&e ot ..._ " v 3. Landfill Site/Cao ... _,
a. Vegetative Cover o.ooJ \J Q Q/\ • v ,p --\a .."J h..A';:\h. v
u " b. Standing Water on Cap vv:::, v-.Q
c. Animal Disturbances ~ (\A " {)d. Woody Vegetation .
e. Gully Erosioa/Soil Covec ~ f. RlDlOtf, Siltation ~
g.Leacbate . . ~
~.M .... Wells(S)
a. Loeb in place? w:s b. Condi.ti.on of• ....,;.,.•• ~d
0
c. Well ID l..egt"ble t.-\.9'.S>
\J
s. Comments:
. ~· .• Acuon needed: 6. D ·• ··- of .... & £a.::,t ~o.:1-e.
n.ud5 chc,.;_ ~ !'.;...,.. /a~l... Jo·d::.. ~.p ........ -4- +'.4 .
, -In \a-\-c.~
http:Condi.ti.on
-
WEEKI..Y INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: j \) \"4 11 2015 I, - _. bv: \\ A- ( r3r,· t J,· t1 c..
(LA
u. ·Weather Conditions I Recent ;-- ,. ClflrJ~rA I i'i ht
,a..,in 72 ° . v . v .____1••Time: Started 10:00 (am/pm) -
/0:u)~--· ; L
. .. -;-,') .., w n
'-
ITwe ot:. . . / ---...,._,. ...._.... SiteWalk Other-
........... Stat11slCondNloi1 Comme11ts 1. Vehicular Access
CW06
u 2.Entrance
a. Gate/Chain q,ooJ a,cJ: '2!, l O C Ke J v u
3. umdfilJ Site/Cap"" . ·
a. Vegetative Cover q,eroJ Vfl-~. UP +o ~ J-f, fu'e:d, u u I u
b. Standing Water on Cap V1...0 Ylf2
c. Animal Disturbances MnO d. Woody Vegetation yt f7YC£)
e. Gully ErosioalSoil Cover Vltn-10 f. Runoff, Siltation
Vt..()n0
g.Leacbate ~
f4. Monitoring Wells (5) a. Locks in place? () ,JL.~
b. Condiµon of f"-.ina y~ c. Well ID Legal>J.e ~
u
5. Comments: J t) (' _.\! .() V} f (} I \'"\+-c....l';f-
\/~.'::>~l.loIA!~ 0 .
. . . .....6. n of ..... ~· .~ Aedon needed·
;
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: J0\" \0 '2;015 .l....l
I, bv: At 'Br ; I I;Yl ""...e...r ~
Weather Conditions I Recent ;--• ,. c lovrlu t,b°F t"-t!. '24 f-
,a-,; '7 ~- . V. .. ...,_ ,.Tme: Started 10:10 _mJ I 10: 2 s ..
~-JIJ
.. ·--~ •• ""lr..Tweot;. ... , ......... ...,... SiteWalk Other
.....' lnapectecl StablSICondltlun Comments
___ _.l 1. Vehicular Access • 1'.J
v 2. Entrance
a. Gate/Chain ,?l,F)DJ a...r.. -1:-e..5 l O c),corJ u u
3. I.andtiJJ Site/Cao. . ·a. Vegetative Cover - -..- _) \Jee,..
uP "t"O 4' ~St,~. '-' b. Standing Water on Cap
IJ u '\A • -..,.(')
c. Animal Disturbances \\J""° d. Woody Vegetation ~
e. Oully Erosion/Soil Cover ~
f. Runoff, Siltation ~
g.Leacbate . - ()
14. Monitorin2 Wells (5)
a. Locks in place? ""\.A5
b. Condi.tion of
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDffl...L
I, · by: \l A-I 'Br ; I J,· n~
Weather Conditions/ Recent;-._ .:. .. --~,: {o(o O / J ,.,
,AcL-- ,,, .1, rr. ·.i"'I 0(-e.d. '2 '-{ h{~
. __ _..-_ -~)~Tvoe or;. ,. .,...._. SiteWalk Other
\-------lnspectltd 8tatuslConditto
1. Vehicular Access evood u
2.Entrance
a. Gate/Chain - -- / . v u3. LandfiU Site/Can T
a. Vegetative Cover ~---cJ uu u
b. Standing Water on Cap 'A O "'-- ()
c. Animal Disturbaoces "'- ~ ,-,.(?
d. WoodyV . .. ~ e. Gully Erosioa/Soil Cover ~
~
f. Runoft Siltation .__ ~..- n
g.Leacbate ·"'--'~ .4. Monitoring Wells (5)
a. Locks in place? "'\,t.S,
b. Condnion Of ('A
-
WEEKLY INSPECTION OJi' RAMSDELL QUARRY LANDFILL
Date: 20,sJ0n-e.. '1...lo .I, • bv: A\ 'Br:\\,v)~
. . .uWeather Conditions I Recent ; . ,. .'.:,-,0Y'W''\'-"- 11
OF (C.\.r. .Po.n\~pr '"n ,_, •n\
I • & -~ r L """'-'12:55 .-~:,o
-ITune: Started .....a I I
. -~ Twe or;. ... ..,.,.,...... ·-.....--..-.~ SleWalk other
(_
lnapecllld StaluelColMliOD Comments
1. Vehicular Access qeVc) u
2.Entrance
a. Gate/Chain loc...6r\
3.1.andfiU Site/Cap hi"- . .., a. Vegetative Cover a.cod '\.k?~
.( 1J'J p .A \ )() +.o 4'
' hJ."""1...,1 u
b. Standing Water on Cap ~
c. Animal Disturbances ~ .
d. WoodyV 'wl..1.~
e. Gully ErosioolSoil Cover ~
f. Runoff, Siltation ~
g.Leacbate
... Wells(S)~-" . . ~
a. Locks in place? llv(..S b. Condnion ofC'.A.ana ~
u
c. Well ID Lem"ble l..AL-11.. \J
5. Comments: fe"'r() \" -- __,~+l(.AI'\ QC>:::, ol.;,~"eJ
\-rf).,.,. Q~~ e.J.
. . .6. D of'ft - •. • Action needed:
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: j vne.. \ 9 '2..01'S
Tme: 11:,0 -~. IJ Corr .. __. I }!z5 -~_;....,,i
Type of;. SiteWalk Other
1. Vehicular A~
2.Entrance \.)
a. Gate/Chain u u
3. Landfil1 Site/Cap T
a. Vegetative Cover u \,.J
b. Standing Water on Cap
c. Animal Distmbances
d. Woody Ve1_~·on
e. Oully ErosioolSoil Cover
£ Runoff: Siltation
g.Leacbate
4. Monitorill2 Wells (5)
a. Locks in place?
b. Condiµ,on ofr .....ina
c. Well ID Leaal>le
s. Comments:
6. n • • ofD . - ,.•.• Action needed·
I
-
WEEKI.Y INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: Jvt\ e. \1- '2015 .I, _. bv: A, Be ; \ \ ,
..,,q,...c.r
1....1 Weather Conditions I Recent :--I
........ ,: -p~,- ..Ll .. 1 d"\udc,\.. ~20 I,~ ""1 \-
,c.....1."' or~". ·v-t \-u' r:l -
Tame: Started 11·.oo . - ·I \,OI' •\..l . \J
JI :c/S · . flJ Twe or. . ,: Windshield rSiteWali> other
lnllpeclld 8tautlCondillon Commelds
1.·Vehicular Access - .) l..)
2.Entrance
a. Gate/Chain c.-cJh~~ loc.te.d 3. I.andfilJ Site/Cap! ... ..
u
a. Vegetative Cover ~oJ \J
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: JJf\JL 5 20,s
- •bv:I, Al "Br~\\ 'Vl a.J2.f
. •. IJ... ,. -,30Weather Conditions I Recent :-. Sv VI "'
-
---
I
WUKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: MOM 2.g ?.l'J ,; \
_. bv: (-\\ 13, i \, in c...er
.l.! .
Weather Conditions I Recent ;--I . 5'-.lv,V, V\_ 12. 0
Y\Jl.o..\/'-'L- (CM.'('\ D.cd-e.:> lock J 3. I.andfill s~~- ~
'.,.,. v
a. Vegetative Cover o.,,.e-,oc) l".l/'\r. c.,_s \ I
"> ~~ ~ \..)
b. Standing Water on Cap ~N o~\Jed
c. Animal Distumaoces novui. ob~\Ja.J
d. WoodyV . on ~
e. Oully F..rosionlSoil Cover ~
f. Runoff: Siltation ~-o\o~"J
g.Leacbate ~ olo~veJ...
14. Monitorina Wells (5)
a. Locks in place? \A.fl..> b, Condijion OfC'Aana ~J
u c. Well ID I .ea1nle Vi.QC:.,.
!j
5. Comments:
. . . - •. • Action needed·6. D -, or'
-
WEEKLY INSPECTION OP RAMSDELL QUARRY LAND.FILL
Date: tv\ Glv! 2J z..o,s. . .I, _. bv: A, ~; \ \ \ Y\CO_r
9 ·- .Weather Conditions I Recent ;--. ,: too"' c:....lo
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: 1"10
-
WEEKI,Y INSPECTION OP RAMSDELL QUARRY LANDFILL
Date: tv1 c......, 8 20 ,.s I .I, bv: A1 Be ~ \ \ , Y\ c r12
. ~ .. -· ,BoWeather Conditions I Recent :--. . s ... V'\""-"" :
V\...D .fee n y'\.± D(€c_',D . I. . .!Tune: Started \O;~ ~
\0:£0
Tweofit .. :~~· SiteWalk Other
lnepectad StatualCondillo Camme11ta
1. Vehicular Access Qf"")od
u
2.Entrance
a. Gate/Chain ~oc) q.cu\e_"> \ oc...\:.or)
v u.3.l.andfiHSite/CapT ,y
a. Vegetative Cover ~c:J v
b. Standing Water on Cap "'\It~ c. ADuna, Disturbances ~ d.
Woody Vegetation ~
e. Gully Erosion/Soil Cover ~
f. Runoff: Siltation ~
g.Leachate ~
14. Monitorin2 Wells (5) a. Locks in place? '11-> b. Condiµon
ofC'.JLuno ~ .., c. Well ID' .-hie '-Vl- ...
.....
s. Comments:
. .. . .... ~- n of..... •. • Action nmled:
'
-
WEEKI..Y INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: Mo-t \ . 2Dl5
I, . bv: Al t3r;l /,v,~r u .. ..Weather Conditions I Recent ;-.
,:
Tune: Started 11:1...s -~ ,\ _..... I &,2 0 • ::,vnn
-
- -
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: '~Ot'"i I 23 2015 lnsoected bv: (-JI ,3, ,· !J,·n <
o.,,, Weather Conditions I Recent Preci~ion: J,~ 1-? f ::>vz-ow
/ TG...-\ n- c)..ovc/1,1 37
11
Time: Started 10:35 '0-m) Com Dieted J0.'$0 ~·-ft .....
~.,..,.n) Type of;. ··on: ,,,-Wtndsh~ Site Walk Other
d. Woody Vegetation . ·- "-e. Gully Erosion/Soil Cover
a,.o-od
u
f. Runoff, Siltation ~,(")-f')J g. Leachate ~-
u - -J
l)
4. Monitorin.2 Wells (5)
a. Locks in place? 1-" c....
b. Condition ofCasing ~c) u
c. Well ID Legible vULC... u
5. Comments:
& •6. Description ofO '!lemedial Action needed:
~ (\ "nr.
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: Aor,. l 17 zo,s. Ins "bv: Al Mr; JJi' Y?c. 0/7
u.Weather Conditions I Recent P, _ . . ••• ~a·F vlovd'A. r
c..... i Y? A ~ .f./1 i rt.~ /2ttJj v. Z '1 '\.A.A -. -· (am/pm) u
ITime: Started //.'~ ....~..,..., Completed ' u
Type of ins- - ~· n: (Windshield Site Walk Other vev-..-t,J
.!>; +c. Lc..)a.J ..
ovh.;~ ~.e..,,, c..J;) I
Inspected Status/Condition Comments
1. Vehicular Access ~ad u
2. Entrance
a. Gate/Chain \o~J.. c.-Ood ' v
3. Landfil1 Site/Cap Integrity
a. Vegetative Cover ~od u
b. Standing Water on Cap "' -'""' (') 0 k,~"e. J
c. Animal Disturbances 'V\.~O DY?~v-e.lJ t":l. -- ___,d. Woody
Vegetation
...... " e. Gully Erosion/Soil Cover ""-.,.e,-vJ
u f. Runoff, Siltation a..,-0oc)
u g. Leachate (1,afir)
u 4. Monitoring Wells (5)
a. Locks in place? (..{ ..Q_ ~
b. Condition ofCasing 0 Ct .-.}-f)d 0
c. Well ID Legible c,t Cl
-
WEEKI,Y INSPECTION O.F RAMSDELL QUARRY LAND.FILL
Date: Al')(",·/ JO 20/S,I _. bv:I
. . . It.Weather Conditions I Recent -;-• 57° /?Ge.Av,
(h..ee..11"" J +;~) {.),-evicJv.S z da.......5
v II ./"""\, . . ... ITune: Started II! 10 ._ __JJJ
,
,,:as le 1..1..Jl.~ u
s. Comments: .... "'t
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: Aa,J 2 I . 20,s
Ins:: - _. bv•- . At ?5r,·1Iin 1?it2, Weather Conditions I
Recent Precioiti'tion: 00 ° o
-
WEEKI.Y INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: Mn f\r.V\ 21 Z.01$ '
I, ·bv: Al 1:fr,· / /in ero r zqoWeather Conditions I Recent
P,(} ;.. · ,: I,., h + :5YUJw' .,
,.:::::.',__ ,,,.....--...,,Time: Started 11:20 U3111f .... ll/
Completed I t:'{o ·-IJll f,11 /1J-.Type of ins -,: (Windshield~
Site Watk Other
__,,........
Inspected Status/Condition Comments
1. Vehicular Access 6\-0C'.>d u
2. Entrance G\-06d
a. Gate/Chain \:>Jt.i GI_,. +es l C)c...6 ) u
3. Landfill Site/Cap lnte2J'ity
a. Vegetative Cover ~J u
b. Standing Water on Cap q.-Qod
c. Animal Distmbances ~od u
d. Woody Vegetation C\Oad u •
e. Gully Erosion/Soil Cover 0~ Jr (" v
f. Runoff, Siltation C>ifY')r_
g. Leachate ~o~J v
4. Monitoring Wells (5)
a. Locks in place? v\Q.S,
b. Condition ofCasing ~~j c. Well ID Legi'ble ~"
\J
5. Comments:
.6. Description of n ""' •. ~ Action needed: 3 Areas f'.RJ}C
-
- -
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: Mo./\c.,\n 20 'Z-o1.S
Inspected by: A I !3,r"i°/ J.-.,,.,,M (.)
Weather Conditions I Recent Precipitation: Cl oud'1 / , c,
J,..if yvt....-iS f 37° u v
Time: Started I/! ID (@Dllpm) Completed 1/:30 ~/pm)
Type of insoection: r'Windshi~ Site Walk Other '
Inspected Status/Condition Comments
1. Vehicular Access C\oad
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: Md.l)c...,\,,.. 13 '2-015 .
l,~edbv: A/ S,,· J/iY'}o,,L.f'
u ... -Weather Conditions I Recent P on: C) OtJd "L ~i) " u
I
Time: Started IZ: 1S Cam/mffl ComDieted /2:35 (am/tin)
Tvce of i, .. ,windshield) Site Walk Other \.
Inspected Status/Condition Comments
I. Vehicular Access ~o6d 2.Entrance
a. Gate/Chain (;rood
3. Landfill Site/Cao Integrity
a. Vegetative Cover no+ v'i~; blR WU>.sf /'( ( "J' 'lo ·Jo )
!:>Jtto,..) ui v~f b. Standing Water on Cap 'IL()t ,1,:Sil::,/p
/ c. Animal Disturbances K.i> f- v.,-S ; b (o d. Woody
Vegetation 111.-0 + v' ,':,; b l_p
I
I e. Gully Erosion/Soil Cover .-u>+ ilj$, t,"' f. Runoff,
Siltation 'V\..D t- vi!,; b ~ g. Leachate .........., +- v,.s; b4'
~
4. Monitorill2 Wells (5)
a. Locks in place? 0\,,0 oJ I i..µ.s u
b. Condition ofCasing "'v~. u
· c. Well ID Legible t.'1~S
v
5. Comments:
6. Description ofR • _/D ~· ·' Action needed:
',¥ Ea.:~h~.,"" S-w-,
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: l'I\ CULJ"l h , '2.D 15'
IJ~edbv: Al 13r~ \ h""'lc:..oJ-Weather Conditions I
Recent;-;-_:. . .,,: /C}D F '> l ' s h-0 c..J c...D .., IV)
Time: Started IZ: OC> lam/Dffl) Com · · ~ 12:zo ,--,J6m)
Type of;, ·on: ,,.--W1ndshleld Site Walk Other
'
Inspected Status/Condition Comments
1. Vehicular Access roa.cl ,.s o\ov.:ieJ 11n!es
a...e..~,olav»J~' ,,," 2. Entrance
a. Gate/Chain \oc.uJ acJ:e ..,, sn:uwe.J '"' 3~ Landfi11
Site/Cap Integrity
a. Vegetative Cover t\.J\-- Vis: ~lp lo...vid-+\ \l is
Si.t...0w-c:.vvQNIJ ~ +'..-a"'9"' I\ " ""b. Standing Water on Cap
VLO-\: \J i s,l I:,.lo
c. Animal Disturbances l,U)+ ",s-.1.;.la • \\ ,, .,
d. Woody Vegetation
e. Gully Erosion/Soil Cover
u:.)°t
Y\Oi"
v ; s ', l.;,le
'llj5',l.:.lo
,.
.. ,,
.. " ..
"
..
f. Runoff, Siltation
g. Leachate
ltt.l't"
rto-l.
.Jis,b~
Iii 51 l:,lo
,,
. ,,
IA
,,
.. ~
.
4. Monito~ Wells (5)
a. Locks in place? ~':, v
b. Condition ofCasinR ~ odJ ......
c. Well ID Legible l.1t.-.$ u
5. Comments:
. ID6. Description of'""~- _.. • Action needed: Eo..?-\-e. r
..r'\ +-e. VJ u:, +on wirCL o.f S·wi '"'~-- ~ .....Ii\ +e."'c..:
le
./
1.C.e..v1rn b
-
___
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: FrtJnu F~h. 21 2.,ot~•
Inspected by: A\ :Br;\\ ,-nc;e.r-Weather Conditions I Recent
Preci · ,--,. "(!) ,ece.'ll'l.t Sl'\.OW~ Q O (sVt.Ot.,.J covett )
,0. Time: Started ,o~4o (GmJ/pm) Com .. ~ ,,:ou
((ab,.......'--n)
-Type of n ·:n: JNindshieJ(I Site Walk Other
....
Inspected Status/Condition Comments
1. Vehicular Access f~c- R.c..wis.At0\l ~~) ~ J1ln..ueJ'
\.\·w\.atd Jr\..tc:_c;~ '
2. Entrance
a. Gate/Chain - ..1 u
3. Landfill Site/Cap Integrity \a..-J~\\ cov~J w\ -svwv.J (">
\') a. Vegetative Cover ~i\e. ObS,av~ ~ -\-,re~
-b. Standing Water on Cap \M.)-v,
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: Fr; Jl1...J F-e.Jo
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: ~v~'1- /3. z..o,s l1~edbv: wed e:.~ a.c:c.~is."-Ci '....
2. Entrance
a. Gate/Chain '°'ood-3. Landfill Site/Cao Integrity
a. Vegetative Cover Y'\-bt- ";:,'\\;,\.e_ ~\-\-e.. \!, :,.~-
(.()v eAad b. Standing Water on Cap ""'-a\- '1 ,~·, \,U2 ... .. c.
Animal Distmbances vu,\ ",~··l;:.Lcz..
,.. I d. Woody Vegetation G:t.-.oJ-e. Gully Erosion/Soil Cover
~-\- -.J,5~ \p\o .s:..\....::. ,s. C:..IAJ::,w c..oJQ,,Qrl
. f. Runoff, Siltation ""o-\ '1;S,~.P \ ... ,_
" g. Leachate nn-\- '1i5\'d..P ...
,._ .. 4. Monitoring Wells (5)
a. Locks in place? I ).A C...,
b. Condition ofCasing 0 - ~ - ":l. c. Well ID Legible
u~, \.l
5. Comments:
,...6. Descri.Dtion of~ -- •• •1 Action needed;
.. I 1 (.J J W, (4!? o+- e..a. !:>-h;,
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: F..p 1,,. '? 201
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: Ja. ..00..,"f 3o, 2.DIS
Inspected by: A1 'Br, I\ ,Y'l-=i 2-C
-~
Weather Conditions I Recent Precipitation: ,·1 u. \ i"l \,\-\: s
~"" (""' 2·3 Sl'Ulw \~ \c.., \,,le,
d. Woody Vegetation ~
e. Gully Erosion/Soil Cover ~ vi~,b~
f. Runoff, Siltation ~ v-.5,61(;,
g. Leachate ~ visib~
4. Monitoring Wells (5)
a. Locks in place? ua_~
b. Condition ofCasing ad u
c. Well ID Legible t.J\9-S ..
5. Comments: RQL '\ 5 Sl'U>v..> c..av ~d a...v,.ttY +
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: _j (~ .(\ IIn tu-..- 2.'3 2c)15 Inspected by: A\ Br~\ t
nc..n.r
0 2..-C> ,., 3 q ,(21Weather Conditions I Recent
Precipitation: 'o ' G,L.o v j "\ .s )'\..() w OV"\ IJ_ I-,psTime:
Started 10\~ _(~m) Completed Jim/pm)
Type of inspection: ,,-Wincfshield/ Site Walk Other -···
Inspected Status/Condition Comments
1. Vehicular Access a..-ind J
2. Entrance
a. Gate/Chain qood
3. Landfill Site/Cap Integrity 5~ C...CNQI\Q~
a. Vegetative Cover II
b. Standing Water on Cap l I
c. Animal Disturbances 'I
d. Woody Vegetation \\
e. Gully Erosion/Soil Cover s ee w-m~ ho,(o..J f. Runoff,
Siltation - {
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date:
leted ~·. 33 Other
Inspected Status/Condition Comments
1. Vehicular Access
2. Entrance
a. Gate/Chain
3. Landfill Site/Cap Integrity
a. Vegetative Cover
b. Standing Water on Cap
c. Animal Disturbances
d. Woody Vegetation
e. Gully Erosion/Soil Cover ~
t,,-.--~~~~~~~~~~-f-;i.....,;~..........~~~1L41,-.q..u..~-.\-~~~~~~~~~~~~--1
f. Runoff, Siltation
g. Leachate
4. Monitoring Wells (5)
a. Locks in place?
b. Condition of Casing
c. Well ID Legible
5. Comments:
6. Description ofRepairs/Remedial Action needed:
-
WEEKI.. Y INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: Je1.-r, \,) ClJv:I., " 1.o\,S Inspected by: A.Br~\
\,Y)c.a,
" Weather Conditions I Recent Precipitation: \t, 0
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: So P.ec.e""" ba, 20\ L/ lnsoected bv: A\ lSr~\ h"'-~or .
\Sm~ t\1'1ld (ol-\A12..JcJ
u
Weather Conditions I Recent Precipitation: On.-.k-lu
C::.1-v,.ntA 2no II
Time: Started l'.IS
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: I)e (.'l IO\\-;;,.£!./ ·2 "-\ . '2.o 1l(
Inspected by: At fr;\\,Y1C..O/" u
Weather Conditions I Recent Precipitation: 52° \\',; ""'+
~.$+-Time: Started q:oo cc. .a.~-\
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: 1:::e c...e VT')b.e , \ 9 , '2.o , '-( 4lnsoected by: A\
'i:!:,,c--, \ '''°'~V ~~ec:.c..c... \-\.c....V'\4~
- '-J Weather Conditions I Recent Precipitation: c..\o~a~
a.o·
'2. 1 1-:o \)
z:YsTime: Started V'\tl ob~ved
c. Animal Disturbances ~ do':::f2A.,JeJ d. Woody Vegetation
o...ood \'Le""2. o hSa.a.,1e,l ~ C:.CJ';J,- . e. Gully Erosion/Soil
Cover AA.,-oJ .... r>re.'1 tc..:>s.\~. \,t,,.4,o A'
e...od..Dd f. Runoff, Siltation vt.o\d'00""2 g. Leachate
Y\-C>v-.e c~"ed
4. Monitoring Wells (5)
a Locks in place? \Al!,':::,
b. Condition of Casing ~d ... c. Well ID Legible ~::,-
-~ 5. Comments: ~:11< +e...... ,. 0 \Vl+c...c...\- .&1
_,, .. a+ c._., \:,rob "' -\oo '-Al~~ e_ ( l \oc..._.t.:IN\)
oc..~-\- e:.1 J...a o+- ~e.vi CJ2 ,.\ Cl.A.ao...,
6. Description ofRepairs/Remedial Action needed:
~ -ce.,o,.\,,,J ,.. - -- a.. (3,) -tc> be +:, \\e J WhQ"'
c..nDrnJeJ ..C:i\\ J'ir-\- ,s o.va.ll.cd..lo .
.
·~
http:o.va.ll.cdhttp:o+-~e.vi
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: D.e.c e )'>"\\,.Q.r I Z... • Zzn '-f
lnsoected bv: Al 'Br;\"""~I .., Weather Conditions I Recent
Precipitation: 308 c..\o.JJ~ Y\.C f-e.Cef\+ nre.c...Xo.
\J 10·.~ l('.o 5Time: Started _(~pm) Completed Jam/pm)
Tvoe of insoection: (WindshiekLJ Site Walk Other
Inspected Status/Condition Comments
1. Vehicular Access o.ood ..., 2. Entrance
a. Gate/Chain "\cod bcr+~ q~~ \oc..\:eJ ...., 3. Landfill
Site/Cap Integrity
a. Vegetative Cover ~J b. Standing Water on Cap "'/1..c-Nl. 0
b~ve.J c. Animal Disturbances ~ o\..::>5,Q.r,.ved
d. Woody Vegetation Oiecd ~~ olo~ve.J ,.,,,_ c~ ~a e. Gully
Erosion/Soil Cover a.r.,.,J ""'nre..vtoL.)C'.,.\" ..-.o\eJ ,en:,~
O,...,.A"'-S ...., . . f. Runoff, Siltation ~ ~t-e9
g. Leachate ~ 0~11eJ
4. Monitoring Wells (5) '
a Locks in place? '\(ls-b. Condition ofCasing ~J
v
c. Well ID Legible v\a.? \J
5. Comments:
ff ..,, _c,,"' ,.. " \ "'k,.+
6. Description ofRepairs/Remedial Action needed:
* t.rnW~ (~) ..L... \,.,. ~i\~J ..l\.vJ 'V\ o_.nnrav~ Ci ll ch,+
·,s I '
Q.Jn !\,.W11
-
WEEKLY INSPECTION OF RAMSDELL QUARRY LANDFILL
Date: s \) -L l- ~ C::i\ \..\ Inspected by: ~ Q'"V~\ \\.
~\l'\t'1. f J\\ ~'("·,\\·\''f\.1\
-
Draft 2015 Annual Land Use Control Monitoring Report RVAAP-01
Ramsdell Quarry Landfill and RVAAP-05 Winklepeck Burning Grounds
Camp Ravenna, Ohio
\\BUFFALONAS\ContractFiles\Technical\VISTA_Reports\LUC_Reports\FY2015_LUC_Reports\Combined
Annual Report\Draft\Draft_FY15_ANNUAL_LUC_RPT.docx
593
594
595
596
597
598
Appendix B 599
RQL Soil Repair Memo 600
601
-
Memo To: Tim Morgan, State Environmental Supervisor
From: Al Brillinger, Program Manager, Vista Sciences
Corporation
cc: Katie Tait (OHARNG), Kevin Sedlak (NGB), Quyet C. La
(USACE)
Date: January 23, 2015
Re: Camp Ravenna Ramsdell Quarry Landfill Cap Repairs
Vista Sciences Corporation (VSC) filled 3 areas at the Ramsdell
Quarry Landfill (RQL) with clean, approved soil on January 21,
2015. A drawing of the RQL and the repaired areas is attached to
this memo.
Two (2) of the areas (labeled "A" and "B" on the attached
figure) were located on the Ramsdell Quarry Landfill cap, and
consisted of shallow (
-
/ I
I ~
" I c; ~ ~ \ ~ d
\ T" ... 6 \ ,I) c; i \ ~ - \ ~ j \ i \ ":;)
~ ~
5 I --,:..t:. 1 ~
i;:
-1 \ ..,.. ... d \ ? 0 - \
/ /
----
"\
\ J
- - ..........
I \
i\ 1 ~
........
\ \ J
/ uO
p II
~
i 'D 0 _. 0 rJ QI _. - '&. t'I
1 r" ..._ d ., t; -d ·~ -,
-
FIELD CHANGE REQUEST (FCR) FCR-RV AAPB1200-002
FCR NO. FCR-RVAAPB1200-002 DATE INITIATED 10/24/14 PROJECT
Building 1200 and Anchor Test Area Remedial Action CONTRACT NO. GSA
Contract No. W912QR-04-D-0028 Delivery Order No. 0001
REQUESTOR IDENTIFICATION NAME Jed Thomas ORGANIZATION --Leidos
PHONE 330-405-5802 --;::::.__--TITLE Deputy Project Manager
SIGNATURE ;__w __ l...i:_-.:.+z'!..~~==::---------BASELINE
IDENTIFICATION
BASELINE($) AFFECTED D Cost D Scope D Milestone igi Method of
Accomplishment
AFFECTED DOCUMENT (TITLE, NUMBER AND SECTION) Remedial Design
for Soil, Sediment. and Surface Water at RV AAP-13 Building 1200
and RV AAP-48
Anchor Test Area {Section 8.1)
DESCRIPTION OF CHANGE: Section 8.1 of the referenced Remedial
Design indicates the a previous backfill source will be utilized
for backfill once the cleanup goals are attained during the soil
excavation at the Building 1200 and Anchor Test Area AOCs. However,
the backfill source specified in the Remedial Design is no longer
available for use. Accordingly, Leidos identified and sampled a new
backfill source at Patrick Excavating and Trucking at 5839 State
Route 5, Ravenna, Ohio.
On September 11, 2014, the staged backfill source at Patrick
Excavating and Trucking was sampled. One ISM sample
{B12bf-060M-0014M-SO) was collected and analyzed for RVAAP full
suite parameters except voes. One discrete sample
{B12bf-060-0015-SO) was collected and analyzed for voes.
The results of the analyses are attached to this FeR. Data was
screened using the RVAAP surface soil background values and
Resident Receptor cleanup goals (CUGs) at 10-6 risk. The EPA
Regional Screening Level for resident for soil {10-6 risk) (May
2014) was used if an analyte did not have a CUG. A brief summary of
the results are presented below.
1) All analyte concentrations were below either the surface
background values or the screening level.
2) All pesticide. PCB, explosive, and VOC analyte concentrations
were either not detectable or had estimated concentrations.
3) All SVOC analyte concentrations were either not detectable or
were below the screening level. with the exception of benzo