Estimated annual cost of metallic corrosion in United State alone was between US$300 and US$350 billion. 40% of the mentioned cost could have been avoided using the current or existing technologies and by applying or implemented the proven best practices. The National Institute of Science and Technology
45
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Demo Ibm MaXRBI Houston-Conference

Estimated annual cost of metallic corrosion in United State alone was between US$300 and US$350 billion. 40% of the mentioned cost could have been avoided using the current

or existing technologies and by applying or implemented the proven best practices.

The National Institute of Science and Technology

Page 2: Demo Ibm MaXRBI Houston-Conference

Dangers, Losses and Damage of Corrosion

Pipeline Explosion Lights Up East Texas Sky~ a pipeline leaking natural gas exploded after a car drove over that leak, which was part of the Texas Gas Gathering Company .

Petro China Refinery Explosion Injures 30~ More than 30 people were hurt following an explosion at Petro China Co.’s Fushun refining complex in northwestern Liaoning province, the official Xinhua News Agency said, without citing anyone. No deaths were reported.

1

Page 3: Demo Ibm MaXRBI Houston-Conference

Corrosion and Corrosionist

Corrosion is the disintegration of an engineered material into its constituent atoms due to chemical reactions with its surroundings

He is a man who walks down those mean, corroded streets. A man you seldom know because when he makes your day -- which he does every day -- you won’t know him.

~ In the most common use of the word, this means electrochemical oxidation of metals in reaction with an oxidant such as oxygen.

~ Formation of an oxide of iron due to oxidation of the iron atoms in solid solution is a well-known example of electrochemical corrosion, commonly known as rusting.

2

Page 4: Demo Ibm MaXRBI Houston-Conference

Corrosion Control and Monitoring

Minimum requirements for corrosion control:* External Corrosion Control1. Buried DOT regulated pipelines will be coated and cathodically protected* Internal Corrosion Control1. Known corrosion rate based on historical data.2. Corrosion rate from a national standard data base.3. Data collected from laboratory prototype testing.* Above Ground External Corrosion Control1. Coat with an approved system with resistance to the soil and internal fluid temperature

3

Page 5: Demo Ibm MaXRBI Houston-Conference

API 580 – Provides with the basic elements for developing and implementing a risk-based inspection (RBI) program for fixed equipment and piping in the hydrocarbon and chemical process industries. These API Inspection codes and standards allow an owner/user latitude to plan an inspection strategy and increase or decrease the code-designated inspection frequencies based on the results of a RBI Assessment.  

API 581 –Provides quantitative procedures to establish an inspection program using risk-based methods for pressurized fixed equipment including pressure vessel, piping, tanks, pressure relief devices, and heat exchanger tube bundles.

maXRBI Based on API 580 / 581

4

Page 6: Demo Ibm MaXRBI Houston-Conference

In general, Risk is calculated as a function of time as follows:

In API RBI, the consequence of failure is assumed to be independent of

time, therefore:

The Probability Of Failure used in API RBI is

The Consequence of Failure or loss of containment for a pressurized component is expressed as an impact area (ft2) or in financial terms ($) . Final consequence areas are determined as a probability-weighted area of each of the individual event outcome areas

API 580/581 Risk Analysis

5

Page 7: Demo Ibm MaXRBI Houston-Conference

maXRBI UsageIBM MAXIMO delivers best-of-class asset lifecycle and maintenance management for all asset types on a single platform. providing insight for all of your enterprise assets, their conditions and work processes, for better planning and control.

maXRBI is a MAXIMO RBI Software add-on application to monitor and analyze Risk, Consequence and Probability of failure due to corrosion.

6

Page 8: Demo Ibm MaXRBI Houston-Conference

maXRBIUsage of maXRBI application is divided into four Major Stages

Preparation Stage

Data Recording and Documentation

Stage

Data Analysis Stage

7

Inspection Planning

Asset Registration for Corrosion

InspectionField Inspection

and Data Gathering

Work Order Generation

Preventive Maintenance (Work Type = “ INSP ” )

Inspection Program Job Plan

Field Inspection and Data

Gathering

Inspection/Testing (NDT /NDE) Application

maXcorrosionist (Asset) Application

NDT/NDE Log Tab Risk Assessment)

Risk Assessment (Quantitative Data)

maXcorrosionist (Asset)

Application

Inspection Planning Application

Inspection Planning

Optimize PM and Job Plans

Inspection/Testing (NDT /NDE) Application

NDT/NDE Recording Log Tab

NDT/NDE Recording Log Tab

Page 9: Demo Ibm MaXRBI Houston-Conference

maXRBILog-on to MAXIMO.

User name maxadmin

Password maxadmin

Start Center will be launched.

Access maXRBI , under maXRBI Module.

1

2

3

8

Page 10: Demo Ibm MaXRBI Houston-Conference

maXRBI (Preparation Stage)List Tab of the application will be launched.

Search for the asset due for inspection. Inter a filtering string (ex. Asset number, description, location, parent, etc) to search. Press enter to allow the system to process the search and displays all matched records.

5

4

9

Page 11: Demo Ibm MaXRBI Houston-Conference

6 Use the “Advance Search” option to look for the asset due for inspection. Enter specific filtering details and click “FIND” for the system to process the search.

maXRBI (Preparation Stage)

10

Page 12: Demo Ibm MaXRBI Houston-Conference

Asset information will be displayed.

Corrosion Information

Installation Properties.

Drawings

General Information Details

maXRBI (Preparation Stage)

11

7

Target Information

Equipment Details

Page 13: Demo Ibm MaXRBI Houston-Conference

maXRBI (Preparation Stage)The Operating Process tab is to display any information regarding the process details such as the fluid, operating temperatures and pressures, toxicity levels, etc.

12

8

Page 14: Demo Ibm MaXRBI Houston-Conference

maXRBI (Preparation Stage)

The Sub-assemblies Tab displays children assets or assets within the Pipe group or Pipe Circuit.

12

9

Page 15: Demo Ibm MaXRBI Houston-Conference

The meters tab

maXRBI (Preparation Stage)

13

10

Page 16: Demo Ibm MaXRBI Houston-Conference

User can update the “Testing and Inspection Plans”.11

Correspondingly, Job Plan associated to the Preventive Maintenance record will be automatically displayed or updated.

How to use RBI Software: maXRBI (Preparation Stage)

14

Page 17: Demo Ibm MaXRBI Houston-Conference

To start the Inspection Activity, user generates an INSP work order from the Preventive Maintenance Record due. Click the selector tool adjacent to the Inspection and Testing field to direct the page to Preventive Maintenance Application.

12

maXRBI (Preparation Stage)

User generates an INSP work order from the Preventive Maintenance record due.

15

Page 18: Demo Ibm MaXRBI Houston-Conference

maXRBI (Data Recording and Documentation Stage)

16

Data Recording and Documentation

Stage

Field Inspection and Data

Gathering

Inspection/Testing (NDT /NDE) Application

NDT/NDE Recording Log Tab

Page 19: Demo Ibm MaXRBI Houston-Conference

maXRBI (Data Recording and Documentation Stage)

Types of RBI Procedure

• Qualitative Approach

• Semi-Quantitative Approach

• Quantitative Approach

17

Page 20: Demo Ibm MaXRBI Houston-Conference

maXRBI (Data Recording and Documentation Stage)

After completing the on-site inspection and data gathering, the inspector uses “INSPECTION/ TESTING (NDT/NDE) APPLICATION”, to enter or document all gathered information into the application for analysis.

13

18

Page 21: Demo Ibm MaXRBI Houston-Conference

maXRBI(Data Recording and Documentation Stage)“INSPECTION/ TESTING (NDT/NDE APPLICATION” will be launched. Inspector can now create a new record of Inspection/ testing based on the inspected assets. Click on the “new record” icon to start.14

19

Page 22: Demo Ibm MaXRBI Houston-Conference

maXRBI(Data Recording and Documentation Stage)Update information on the NDT/NDE Log Tab. Enter “Semi-qualitative” data on this tab for analysis. Click on the new row, and enter the asset inspected. Enter result of inspection.15

20

Page 23: Demo Ibm MaXRBI Houston-Conference

maXRBI(Data Recording and Documentation Stage)Also has the option to input thickness readings from a data logger and also be imported from a xls file16

20

Page 24: Demo Ibm MaXRBI Houston-Conference

maXRBI (Data AnalysisStage)Damage Factor and Degradation Mechanism

Damage Factor – An adjustment factor applied to the generic failure frequency to account for damage mechanisms that are active in a equipment.

The damage factor is determined based on the applicable damage mechanisms for the equipment, the inspection history and condition of the equipment.

In API RBI, the damage factors for the protected equipment are calculated as a function of time.

25

Page 25: Demo Ibm MaXRBI Houston-Conference

maXRBI (Data AnalysisStage)

The mechanical integrity and functional performance of equipment depends on the suitability of the equipment to operate safely and reliably under the normal and abnormal (upset) operating conditions to which the equipment is exposed.

Risk: Combination of the probability of an event and its consequence. In some situations, risk is a deviation from the expected. When probability and consequence are expressed numerically, risk is the product.

23

Page 26: Demo Ibm MaXRBI Houston-Conference

maXRBI (Data Analysis Stage)

21

Data Analysis Stage

Inspection/Testing (NDT /NDE) Application

NDT/NDE Recording Log Tab

maXcorrosionist (Asset) Application

NDT/NDE Log Tab Risk Assessment

Page 27: Demo Ibm MaXRBI Houston-Conference

maXRBI (Data AnalysisStage)Access maXRBI Application again to do a Risk Assessment on the Inspection Result.17

22

Page 28: Demo Ibm MaXRBI Houston-Conference

maXRBI (Data AnalysisStage)Risk Matrix Analysis

Risk presented as a precise numeric value (as in a quantitative analysis) implies a greater level of accuracy when compared to a risk matrix (as in a qualitative analysis)

28

Page 29: Demo Ibm MaXRBI Houston-Conference

maXRBI (Data AnalysisStage)Risk Matrix Analysis

Risk Matrix: For risk ranking methodologies that use consequence and probability categories, presenting the results in a risk matrix is a very effective way of communicating the distribution of risks throughout a plant or process unit without numerical values.

28

Page 30: Demo Ibm MaXRBI Houston-Conference

maXRBI (Inspection Planning Stage)

21

Inspection Planning Risk Assessment

maXcorrosionist (Asset)

Application

Inspection Planning Application

Inspection Planning

Optimize PM and Job Plans

Page 31: Demo Ibm MaXRBI Houston-Conference

maXRBI (Inspection Planning)

3 different cases in inspection planning19

24

A.) Example where the risk target is met before the plan date

B.) Example where the risk level is not met after inspection

C.) Example where the risk level is still above the risk target after inspection

Page 32: Demo Ibm MaXRBI Houston-Conference

maXRBI (Inspection Planning)

18

24

Access the Inspection Planning application.

Page 33: Demo Ibm MaXRBI Houston-Conference

maXRBI (Inspection Planning)The inspection planning application helps plan for the next inspection dates. for the component or equipment. It provides the means to evaluate the optimal inspection effectiveness, inspection effort and inspection interval for the component based on the current risk information (Risk-Based Inspection Date).

20

24

Page 34: Demo Ibm MaXRBI Houston-Conference

maXRBI (Inspection Planning)Inspection information allows user to see different risk results depending on the plan date and/or inspection details . It identifies recommended next inspection plan for the component based on the Risk Target. Risk target is defined as the level of acceptable risk defined for inspection planning. The risk target is in terms of area for area-based consequence analysis and in terms of financial limit for financial-based consequence analysis.

21

24

Page 35: Demo Ibm MaXRBI Houston-Conference

maXRBI (Inspection Planning)

What-if Calculator allows users to change any of the parameters such as the inspection date, corrosion rate, any damage factor information to see risk results

22

24

Page 36: Demo Ibm MaXRBI Houston-Conference

maXRBI (Systems)

Access the Systems application 23

24

Page 37: Demo Ibm MaXRBI Houston-Conference

maXRBI (Systems)Inspection information allows users to associate assets to a System and view what the current Risk Rating (Financial Risk and Area Risk) of a systems based on the current risk information of equipments associated to the system. It displays system’s hierarchy of equipments/components and its Risk information.

24

24

Page 38: Demo Ibm MaXRBI Houston-Conference

maXRBI (Management System Evaluation)

25

.

1. Access from the Select Action menu of MaXRBI application.

2. Management System Evaluation window opens.

Page 39: Demo Ibm MaXRBI Houston-Conference

maXRBI (Management System Evaluation)

263. Click the portion of Facility’s Management System to Evaluate.

Page 40: Demo Ibm MaXRBI Houston-Conference

API 581 – Generic Failures for Equipment Types

27

Page 41: Demo Ibm MaXRBI Houston-Conference

Comp. Damage Consequence Equation Constants

27

Page 42: Demo Ibm MaXRBI Houston-Conference

Risk rank Summary Report which includes:◦ Likelihood and consequence

ranking for each equipment ◦ Risk ranking for each piping

section◦ Identified active damage

mechanisms Corrosion Rate Difference by

Service and Type Corrosion Inhibition and Corrosion

Rate Correlation Internal/External Inspection

Comparison

MaXRBI Reports

29

Page 43: Demo Ibm MaXRBI Houston-Conference

Linear and Non-Linear Assets

Assets can have two categories: Linear and Non-Linear.Linear Assets have linear properties and often connect with each other by their relationship with the linear infrastructure itself.

A non Linear Asset occupy a defined space and can be tracked by their location or modeled as part of a parent-child hierarchy.

maXRBI supports both linear and non-linear assets.

30

Page 44: Demo Ibm MaXRBI Houston-Conference

Subsea Corrosion?For subsea corrosion inspection, we use DVRi equipment from Net MC Marine.27

31

Page 45: Demo Ibm MaXRBI Houston-Conference

maXRBI DocumentationD

ocu

men

t M

an

ag

em

en

t b

y

Uti

lizi

ng

FIL

EN

ET

maXFilenet is the seamless combination of Maximo enterprise asset management applications and FileNet DMS capabilities. They form the solution for paperless business operations, secured and categorized attachments in Maximo records, and tracked documentation.

With maXFilenet, documents uploaded in the FileNet Workplace are automatically added to the Maximo document library, and, attaching them to Maximo records is as easy as the usual Maximo document-attaching way, offering versioning and tracking.

Managing attachments can be done in two ways, either through Maximo or FileNet. After every modification on documents, the two systems are updated with details for audit trail

32