DDT Konstract Inc. Silk Residences Project Quality Management

Oct 08, 2015

Download

Documents

Mapua Institute of Technology CE Practicum 2 (Vertical): DDT Konstract Inc. Silk Residences Project Quality Management
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    PROJECT QUALITY

    MANAGEMENT

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Project Quality Management

    The project quality management procedure is an assurance that the activities involved in

    the construction project would comply with the terms of the approved drawings, necessary designs,

    specifications and methodologies. Inspection and testing of materials and methodology shall be

    performed in accordance with the Project Quality Control Plan which is a set standard under the

    supervision of the Project Quality Control Engineer. On the other hand, the quality of work

    supervision is under the Project Quality Assurance Engineer.

    Process Flow Chart

    A. Concrete

    Start

    Inspection

    Batching

    Receiving

    Slump Test &

    Temperature

    Result NO

    Y

    NO

    Add

    Admixture

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Concrete Pouring

    Leveling

    Sample for

    Compressive

    Strength Test

    Return to Batching

    Plant

    B

    Result YES

    Y

    NO

    NO

    Y

    NO

    Result NO

    Y

    NO

    YES

    Y

    NO

    Result

    YES

    Y

    NO

    Remove the

    concrete poured section

    Retest the

    Reserve sample

    Finishing

    Curing

    End

    NO

    Y

    NO

    YES

    Y

    NO

    Result NO

    Y

    NO

    Add

    Admixture

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    B. Reinforcement Bars

    Start

    Material

    Delivery

    A

    Material Testing

    Installation

    of Material

    Fabrication

    Result

    Inspection

    of Installed

    Material

    End

    YES

    NO

    Y

    NO

    Return to Supplier

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    C. Formworks

    Start

    Survey

    Layout

    Rebar Work

    Form Enclosure

    Request

    Inspection

    Concrete

    Works

    Form Stripping

    Request

    End

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Major Work in Construction

    1. Concrete Activity

    a. Inspection

    This activity is done by check listing. Each reinforcement and formwork is

    checked if it is ready for pouring of concrete. Otherwise, the problem should be

    addressed, then it must be fixed to be able to pour the concrete and resume the

    immediate activities.

    b. Batching

    This activity is done when the project site calls the attention of the

    batching plant for the delivery of the concrete mix which would be used for

    certain structural members which are ready for concrete pouring.

    c. Receiving

    When the concrete mixer arrives in the site, they should receive and notify

    the Concrete Engineer. The condition of concrete should be first checked before

    the pouring activity should happen.

    d. Slump Test and Temperature Test

    Before pouring of concrete, concrete slump test and temperature testing

    should be conducted. Temperature test is done to know if the concrete is already

    in its ideal pouring temperature; otherwise, premature concrete pouring would

    cause problems. On the other hand, Slump Test is done to know and check the

    workability of the concrete.

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Figure1.1 Slump Test of Delivered Concrete

    e. Sample for Compressive Strength

    A four sample specimen of concrete cylinder should be attained to be able

    to conduct a compressive strength test. The samples represent the 7-day, 14-day,

    28-day and 56-day specimen which all are to be tested. If the first specimen fails,

    the following specimen should be tested for compressive strength.

    f. Concrete Pouring

    If all the samples are obtained and passed all the necessary tests, (Slump

    and Temperature Test, Compressive Strength Test) concrete should then be

    poured on the members which are ready to be poured on. In the case of Silk

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Residences, DDT Konstract Inc. used concrete bucket and concrete pump for

    pouring

    Figure 1.2 Concrete Pouring Using a Bucket

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    g. Levelling

    Levelling is applicable for slabs in which the levelness of the slab is

    checked for each poured section.

    h. Finishing

    Power trowel is used for finishing of concrete slab to have a smooth finish.

    i. Curing

    Curing process is done by spraying a chemical in the cured member of

    the structure.

    Forms needed in Concrete Activity

    Figure 1.A Concrete Placement Monitoring

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Figure 1.B Concrete Pouring Request Permit

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Figure 1.C Material Delivery Inspection Request

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Figure 1.D Testing Inspection Request

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    2. Reinforcement Bars

    a. Material Delivery

    Once the rebar is ordered, it is delivered in the site. Visual inspection

    shall be done by the Project Quality Assessment Engineer. The primary

    inspections is the diameter of the bar or of there are impurities, rusts on the

    delivered rebar. The quantity of the delivered rebar is also checked if it matches

    the quantity ordered. DDT Konstract, Inc. has an official form for this kind of

    Request named as Material Delivery Inspection Request. The form includes the

    description of the material, quantity, location of usage and remarks.

    b. Material Testing

    After the material is inspected, a four sample specimen for each delivered

    order is obtained. The sample is 500 mm in length and they obtain three for each

    batch of deliver. The four sample represent the 7-days, 14-days, 28-days, and 56-

    days specimen that is to be tested. The sample is tested with accordance of

    PNS49:2002. The test methods are ASTM A370-09 (Standard Test Methods and

    Definitions for Mechanical Testing of Steel Products) and PNS823/ ASTM E415-

    08 (Standard Test Method for Atomic Emission Vacuum Spectrometric Analysis

    of Carbon and Low-Alloy Steel). They also have form for testing entitled Testing

    Request (Off-Site) in which they have the instruction to testing laboratory.

    c. Fabrication

    When the rebar passed the material testing and complied with the

    standard, the rebar can then be used. It can be fabricated into what is used and in

    accordance with the cutting list.

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Figure 2.1 Fabrication of Ties

    d. Installation of Rebar

    After the fabrication procedure, installation of the fabricated rebar should

    take place. The form used is Inspection & Work Request/Permit. In this form, it is

    the nature of work is written and the signature for the approval for each engineer.

    e. Inspection of Installed Rebar

    In inspection of the installed reinforcement bars, the project Quality

    Assessment and Quality Control Engineer should check the arrangement and the

    number of reinforcement bar for each member. Checking of the spacing for each

    ties is also done.

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Figure 2.2 Inspection of Coupler and Rebar for Beams and Girders

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Forms needed in Reinforcement Bar Activity

    Figure 2.A Inspection & Work Request/Permit

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Figure 2.B Inspection Checklist (Rebar)

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Figure 2.C Material Delivery Inspection Request

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Figure 2.D Request for Inspection

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Figure 2.E Testing Inspection Request

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    3. Formworks Activity a. Survey Layout

    The Survey Layout has the actual location for the member and it conforms

    the elevation and level of the member. It has also a a form which has the actual

    survey location.

    Figure 3.1a Survey and Layout Request Form

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    b. Rebar Work

    The rebar work is the inspected rebar installation that is passed the

    inspection. It is also the process in the rebar for major work.

    c. Form Enclosure Request

    It is the request for the formwork to be installed on the certain structural member that is ready for concrete pouring.

    d. Concrete Work

    It is the time when the structural member is ready to be poured.

    e. Form Stripping Request

    It is the request when the poured concrete is passes on the certain hours

    after poured depending on the structural member.

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Forms needed in Formwork Activity

    Figure 3.A Form Enclosure Form

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Figure 3.B Form Stripping Request Permit

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Figure 3.C Inspection Checklist (Manpower)

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Figure 3.D Request for Inspection

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Figure 3.E Survey Layout Request

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Test for Rebars

    Steel, just like concrete, plays also a very significant role in any structural element. Since this backs concrete up, steel that will be used in any

    portion of a structure should have properties that are specified in the plan.

    Failure to have standard steel will cause weaker reinforcements and will make

    the structure fail under small external forces. Buildings that collapsed through

    the years are mainly caused by sub-standard reinforcements. To prevent this,

    the steel that will be used in any construction site is subjected to different test.

    Unlike concrete however, the tests are done in different laboratories and

    samples of each steel are only delivered to be examined. Tensile test is one of

    the most popular tests done on steel.The deliver rebar is tested by the supplier

    but the project is still get sample for the testing the tensile strength,

    mechanical properties and the chemical composition of the rebar. Whenever

    there is a delivered of rebar, they get a random sample. The rebar must passed

    all the test before using it. It is usually in the warehouse. The sample is tested

    in the testing company in which they will be given the result. When the rebars

    passed the test, the batch of rebars that is tested is already can be used but if

    the rebars failed, the batch of the rebars is returned to the supplier.

    Figure 3.1 Steel samples that will be delivered to a testing center to determine

    if its properties will match that of the standard.

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Figure 3.2 Sample Result of the Rebar Test

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Test for Concrete

    Concrete pouring is one of the most crucial methods in construction.

    Failure to successfully conduct this method will surely affect the schedule of

    the project and will later extend its duration that will surely significantly affect

    its cost. Likewise, the concrete used will dictate the strength of the building

    as a whole. If substandard mix will be used, it will definitely be a big problem.

    Preventive measures are therefore done before the concrete pouring is started.

    There are two tests done in the field before the said method: Compressive

    strength test and slump test. The former will tell them the strength of the

    concrete mix delivered as its name implies. It will be the basis of whether or

    not the concrete exhibits strength properties that are the same of that specified

    on the plan. The latter, on the other hand, shows the workability of the

    concrete. Different height of the slump is required for each particular purpose

    of the concrete. When the concrete mix delivered in the project site, it gets a

    sample for compressive strength of the concrete. It ensures that the delivered

    mix is correct. First they put oil on the mold then get a part of concrete on the

    mixture. After, the mold is fill 3 layers of equal volume and stomp it 25 times

    each with a rounded end of the rod. We used a rubber mallet to vibrate the

    side of the mold to avoid honeycombs to the concrete samples and also scrape

    the excess concrete sample at the top of the mold. After 24 hours, the mold is

    labeled and submerged on the curing tank. It is ideal to use potable water for

    curing and it must be protected from direct sunlight and contamination of the

    rain water. When its time to test, it is delivered on the testing company. The

    result will be given to the company. If the specimen passed the test, the pour

    concrete is good for use. But if the specimen failed, they used the back-up of

    the 56 days specimen and test it. If the retest is failed, they will rectify the

    whole section of the poured concrete.

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Slump Test done on site before the actual pouring.

    Figure 3.3 Sample Compressive Strength Result

    Figure 3.4 Samples that are subjected to Compressive Strength Test

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Figure 3.5 Slump Test Samples

  • CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA

    PROJECT QUALITY MANAGEMENT DDT KONSTRACT, INC: SILK RESIDENCES

    Site Instruction

    The site instruction is used by the Engineers whenever a work is not

    properly done and a certain member. If the subcontractor does not follow or

    fixed the inspected error in the work, the engineer will written this site

    instruction and the worker or the foreman must comply on the commitment

    date that is on the form. It is also in the form the observation of the quality

    assurance Engineer and the specific location where he/ she sees this defect.

    Also, it is on the form the proposed corrective action that is required on the

    specific problem.

    Figure 3.6 Sample form of Site Instruction