U.S. Army Corps of Engineers Water Resources Infrastructure: Deterioration, Investment, or Divestment? David Dzombak, Chair Carnegie Mellon University
22

David Dzombak, Chair Carnegie Mellon University

Jan 12, 2016

Download

Documents

zelia

U.S. Army Corps of Engineers Water Resources Infrastructure: Deterioration, Investment, or Divestment?. David Dzombak, Chair Carnegie Mellon University. Committee Roster. Dave Dzombak, Chairman , Carnegie Mellon University, Pittsburgh Patrick Atkins, Pegasus LLC, New York - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: David Dzombak, Chair Carnegie Mellon University

U.S. Army Corps of Engineers Water Resources Infrastructure:

Deterioration, Investment, or Divestment?

David Dzombak, ChairCarnegie Mellon University

Page 2: David Dzombak, Chair Carnegie Mellon University

Committee Roster

Dave Dzombak, Chairman, Carnegie Mellon University, PittsburghPatrick Atkins, Pegasus LLC, New YorkGreg Baecher, University of Maryland, College ParkLinda Blum, University of Virginia, CharlottesvilleRobert “Tony” Dalrymple, Johns Hopkins University, BaltimoreMike Demissie, Illinois State Water Survey, ChampaignTerry Fulp, U.S. Bureau of Reclamation, Boulder City, NevadaLarry Larson, Association of State Floodplain Managers, Madison, Wisc.Diane McKnight, University of Colorado, BoulderJ. Walter Milon, University of Central Florida, OrlandoDan Tarlock, Kent College of Law, ChicagoPeter Wilcock, Johns Hopkins University, Baltimore

NRC Study Director: Jeffrey Jacobs, Water Science and Technology Board

Page 3: David Dzombak, Chair Carnegie Mellon University

Statement of Task

“…identify alternatives and opportunities for improved decision making and prioritization in regard to maintenance, upgrades, and modernization of the navigation, flood management, hydropower, and related ecosystem infrastructure managed by the Corps.”

Page 4: David Dzombak, Chair Carnegie Mellon University

Report contents

• Federal Water Resources Development Act processes

• Corps mission areas and operations, maintenance, and rehabilitation (OMR)

• Options for improving OMR

Page 5: David Dzombak, Chair Carnegie Mellon University

• Existing Corps infrastructure – inland navigation locks and dams, flood protection structures, hydropower generation facilities, and port and harbor facilities and activities.

• Does not address related resources affected by Corps infrastructure and its operations, such as fisheries, sediment, and wetlands.

Report focus and scope

Page 6: David Dzombak, Chair Carnegie Mellon University

Federal Water Project Planning, Authorization, and Appropriations

• Federal water projects are authorized via occasional Water Resources Development Acts (WRDA)

• Maintenance and rehabilitation projects generally are not authorized via WRDA, although there are exceptions

• Congress and the OMB are the nation’s de facto water planners. However, no clearly defined distribution of responsibility among them (and the Corps) for setting national-level OMR priorities

• WRDA not designed to help set OMR priorities. Higher priority on OMR issues for Corps infrastructure will require some reorientation away from the present focus on WRDA

Page 7: David Dzombak, Chair Carnegie Mellon University

Corps Water Infrastructure and Mission Areas

• Navigation -- Inland and deep draft

• Flood Risk Management

• Hydropower Generation

Report does not consider ecosystem assets and resources as Corps ‘hard’ infrastructure

Page 8: David Dzombak, Chair Carnegie Mellon University

Corps Civil Works Appropriations 1960-2012

Page 9: David Dzombak, Chair Carnegie Mellon University

Corps Water Infrastructure and Mission Areas

NAVIGATION

Inland navigation – federal infrastructure showing widespread signs of deterioration; heavily dependent on general revenue from U.S. Treasury; users pay an Inland Waterways Fuel Tax ($0.20/gallon); proposals for ‘lockage fees’ are strongly resisted

Ports and harbors – little federally-owned infrastructure; Corps’ roles focused on maintaining navigable channel and docking depths; allows for more opportunities for partnerships with private sector.

Page 10: David Dzombak, Chair Carnegie Mellon University

Lock at Rock Island, IL

Page 11: David Dzombak, Chair Carnegie Mellon University
Page 12: David Dzombak, Chair Carnegie Mellon University

Federal Inland Waterway Project Financing Trends

Page 13: David Dzombak, Chair Carnegie Mellon University

Flood Risk Management Infrastructure

• Financial OMR responsibilities are very different than in the Corps’ navigation mission area

• Corps-constructed levees that are locally maintained are eligible for fed. maintenance in emergency situations under Public Law 84-99. P.L. 84-99 is not meant to cover routine levee maintenance

• Corps role in levee OMR across the nation generally is one of technical support

Page 14: David Dzombak, Chair Carnegie Mellon University

Flood Risk Management Infrastructure

• “In many parts of the nation, there are large numbers of property behind existing levees and other protective structures that have significant maintenance and rehabilitation needs . . .

Flood risks in these settings will not be reduced easily or quickly by nonstructural measures. At the same time, given limited availability of federal funding, there is a pressing need for less costly and more efficient measures to reduce risks to public safety and reduce flood damages.”

Page 15: David Dzombak, Chair Carnegie Mellon University

Cedar Rapids, IA, June 2008

Page 16: David Dzombak, Chair Carnegie Mellon University

Flood Risks: Multiple Sources and Shared Responsibilities

Page 17: David Dzombak, Chair Carnegie Mellon University

Hydropower Generation

• Not a primary mission area for the Corps, but they have numerous facilities and are a national leader in hydropower generation.

• These facilities generate considerable revenue for the federal treasury, and ongoing contractual relationships may present opportunities to increase funds available for OMR needs.

Page 18: David Dzombak, Chair Carnegie Mellon University

Total hours of forced outages at Corps hydropower projects

Page 19: David Dzombak, Chair Carnegie Mellon University

Options for Corps of Engineers Water Infrastructure

1) Business as UsualThis entails increased frequency of infrastructure failure and negative social, economic, and public safety consequences. The potential extent of these negative consequences is not well understood.

2) Increase Federal Funding for OMR

There has been a long-term declining trend in funding for Corps infrastructure OMR. The future viability of this option is unclear.

3) Divest or DecommissionThis would reduce OMR obligations, but would require action by Congress or the administration.

Page 20: David Dzombak, Chair Carnegie Mellon University

Options for Corps of Engineers Water Infrastructure

4) Increase revenues from Corps project operations

Opportunities exist to expand revenue capture from some projects, esp. inland navigation and hydropower. Legal barriers currently inhibit greater revenue capture from these sources.

5) Expand partnerships with states, communities, and private sectorMany partnership arrangements offer opportunities for more efficient OMR activities. Greater private sector participation in Corps OMR activities will not be desirable in all circumstances.

The Congress and/or administration should commission a study of the opportunities for more extensive partnerships for the OMR of Corps water infrastructure.

Page 21: David Dzombak, Chair Carnegie Mellon University

Federal Leadership and Action

More specific direction from the Congress regarding OMR priorities will be essential to sustaining the Corps’ highest priority and most valuable infrastructure.

The executive branch also could play a more aggressive role in promoting dialogue between the Corps and Congress on infrastructure OMR needs and priorities.

Page 22: David Dzombak, Chair Carnegie Mellon University

Summary

• Large Corps water resources infrastructure has accumulated over time

• Existing Corps water resources infrastructure cannot be adequately maintained with annual funding levels for OMR

• New approaches to management and funding of OMR – including more private, state, local involvement – is needed or system will be modified by deterioration, not by plan

• More specific direction from the Congress and Executive Branch regarding OMR priorities will be essential to defining and sustaining highest priority infrastructure