8/8/2019 D2 S7 Thompson
1/35
Mine Machine Productivity 2006Mine Machine Productivity 2006
Employing best practice in designing,Employing best practice in designing,
constructing, monitoring andconstructing, monitoring and
maintaining haul roadsmaintaining haul roads
Alex T VisserAlex T Visser11
Roger J ThompsonRoger J Thompson22
11
Department of Civil & BioDepartment of Civil & Bio--systems Engineeringsystems Engineering22Department of Mining EngineeringDepartment of Mining Engineering
University of Pretoria, South AfricaUniversity of Pretoria, South Africa
Aim of PresentationAim of Presentation
What are the equipment, materials,What are the equipment, materials,
methods and procedures for roadmethods and procedures for road
construction based on life of road,construction based on life of road,usage and location?usage and location?
8/8/2019 D2 S7 Thompson
2/35
Aim of PresentationAim of Presentation
How to ensuring proper maintenanceHow to ensuring proper maintenance
of haul roads to increase the life ofof haul roads to increase the life of
trucks and tyrestrucks and tyres
Evaluating road maintenance strategiesEvaluating road maintenance strategies Measuring road roughness as a basis forMeasuring road roughness as a basis for
road maintenance management decisionsroad maintenance management decisions
Aim of PresentationAim of Presentation
To show how designTo show how design solutionssolutionscan becan be
benchmarked and evaluated, in termsbenchmarked and evaluated, in terms
of;of; philosophy of provisionphilosophy of provision
management (minemanagement (mine-- or contractoror contractor--driven)driven)
level of servicelevel of service
road maintenance capabilitiesroad maintenance capabilities
8/8/2019 D2 S7 Thompson
3/35
IntroductionIntroduction
UltraUltra--heavy mine haul trucks apply wheelheavy mine haul trucks apply wheel
loads in excess of 890kNloads in excess of 890kN albeit atalbeit at
relatively low traffic volumesrelatively low traffic volumes
Mine roads were empirically designed andMine roads were empirically designed andmanaged with little recognition of;managed with little recognition of;
IntroductionIntroduction
Cost of inadequate design on cost perCost of inadequate design on cost per
ton hauledton hauled
8/8/2019 D2 S7 Thompson
4/35
IntroductionIntroduction
Cost of inadequate design on cost perCost of inadequate design on cost per
ton hauledton hauled
Poor wearing course material selectionPoor wearing course material selection
and deteriorationand deterioration
IntroductionIntroduction
Cost of inadequate design on cost perCost of inadequate design on cost per
ton hauledton hauled
Poor wearing course material selectionPoor wearing course material selection
and deteriorationand deterioration
The role of road maintenance inThe role of road maintenance in
reducing total road user costsreducing total road user costs
8/8/2019 D2 S7 Thompson
5/35
Primary measure of mine roadPrimary measure of mine road
performance is often based onperformance is often based on rollingrolling
resistanceresistance
ButBut.what is rolling resistance and.what is rolling resistance andhow is it generated?how is it generated?
Rolling ResistanceRolling Resistance
Rolling resistance is the extraRolling resistance is the extra
resistance to truck motion due to;resistance to truck motion due to;
Road deformation under theRoad deformation under the tyretyre
TyreTyre penetration into the road surfacepenetration into the road surface
TyreTyre deformation effects on roaddeformation effects on road
surfacesurface
Rolling ResistanceRolling Resistance
8/8/2019 D2 S7 Thompson
6/35
TyreTyre penetration intopenetration into
the road surfacethe road surface
TyreTyre deformationdeformationeffects on roadeffects on road
surfacesurface
RoadRoad
deformationdeformation
under theunder the tyretyre
Rolling ResistanceRolling Resistance
What is the rolling resistance here?What is the rolling resistance here?
2%2%
3%3%
4%4%
5%??5%??
8/8/2019 D2 S7 Thompson
7/35
Rolling ResistanceRolling Resistance
And here?And here?
3%3%
4%4%
5%5%
6%??6%??
6%6%
3%3%
Benchmark maximum rolling resistance 2%
8/8/2019 D2 S7 Thompson
8/35
Effect of rolling resistance on truck speed
1
2
3
4
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Percent REDUCTION in speed
P
ercentINCREASEinrolling
resistance
10 8 6 4 2 0 Grade of road (%)
Rolling ResistanceRolling Resistance
Basic rolling resistance 2%, 220t capacity 376tGVM RDTBasic rolling resistance 2%, 220t capacity 376tGVM RDT
S
R
PracticalPractical
ApplicationApplication
RampsRamps -- 1%RR1%RR 1010--13%KPH13%KPH Surface roadsSurface roads-- 1%RR1%RR 1818--2626%KPH%KPHBasic rolling resistance 2%, 220t capacity 376tGVM RDTBasic rolling resistance 2%, 220t capacity 376tGVM RDT
8/8/2019 D2 S7 Thompson
9/35
PracticalPractical
ApplicationApplication
Effect of rolling resistance on production and fuel
010
20
30
40
50
60
70
80
90
100
0 1 2 3 4
Percent INCREASE in roll ing resistance
PercentINCREASEinfuelcost
.
05
1015
2025
30
3540
4550
At 10% grade with 2% minimum rolling resistance
Percent
DECREASEinproduction
Fuel costs
Production
PracticalPractical
ApplicationApplication
How can you quicklyHow can you quickly eyeballeyeball rollingrolling
resistance?resistance?
Evaluate critical rolling resistance roadEvaluate critical rolling resistance roaddefectsdefects according to;according to;
How bad they are (Degree 1How bad they are (Degree 1 5)5) How much road is effected (Extent 1How much road is effected (Extent 1 5)5)
8/8/2019 D2 S7 Thompson
10/35
4949Total scoreTotal score
884422StonesStones -- fixedfixed
12124433Loose materialLoose material
15155533RuttingRutting
221122CorrugationsCorrugations
12123344PotholesPotholes
DegreeDegree
xx
ExtentExtent
ExtentExtent
(1(1--5)5)
DegreeDegree
(1(1--5)5)DefectDefect
PracticalPractical
ApplicationApplication
1
2
3
4
5
6
7
8
9
10
11
5 25 45 65 85 105 125
Defect total score
Rollingresistance(%)
5km/h
10km/h
15km/h
20km/h
25km/h
30km/h
35km/h
40km/h
45km/h
49
4,5%
PracticalPractical
ApplicationApplication
8/8/2019 D2 S7 Thompson
11/35
Best Practice inBest Practice in
Haul Road DesignHaul Road Design
How do we ensure the best possibleHow do we ensure the best possible
road design which minimises rollingroad design which minimises rolling
resistance?resistance?
Road design exerts a significantRoad design exerts a significant
influence on rolling resistance;influence on rolling resistance;
Structural designStructural design -- deformation underdeformation under tyretyre
Functional designFunctional design -- penetration andpenetration and tyretyre
deformationdeformation
Maintenance designMaintenance design reduction of rollingreduction of rolling
resistanceresistance
Best Practice inBest Practice in
Haul Road DesignHaul Road Design
8/8/2019 D2 S7 Thompson
12/35
Integrated Haul Road DesignIntegrated Haul Road Design
Functionaldesign
BASIC
DA
TA
Structuraldesign
MaintenanceManagement
System
Dust PalliativeManagement
Within limits no treatment required
Chemical
palliation
Water-based spraying
Modify wearing courseselection
Dust Model
PalliativePerformance
Model
Geometricdesign
Functionaldesign
BASIC
DA
TA
Structuraldesign
MaintenanceManagement
System
Dust PalliativeManagement
Within limits no treatment required
Chemicalpalliation
Water-based spraying
Modify wearing courseselection
Dust Model
PalliativePerformance
Model
Geometricdesign
Integrated Haul Road DesignIntegrated Haul Road Design
8/8/2019 D2 S7 Thompson
13/35
Geometric DesignGeometric Design
Use a structured approach to geometricUse a structured approach to geometric
design;design;
Firstly, a set of mine geometric designFirstly, a set of mine geometric design
standardsstandards Secondly, the conceptual designSecondly, the conceptual design
Finally, the asFinally, the as--built designbuilt design
Conceptual roadverti calandhorizontal layout
ConceptualConceptualroadverticalroadvertical
andhorizontal layoutandhorizontal layout
Truckminimumbrakingdistances(unassisted)Trucktypicalspeedsup-and down-gradeTrucksightdistancerequirements
Truckminimumbrakingdistances(unassisted)Trucktypicalspeedsup-and down-gradeTrucksightdistancerequirements
Layoutt heroadaccordingto 9-11%sustainedgradeAssumeinitialwidthofroad4,5xwidthof truck
includingbermsanddrainsHighlightlocationof
SwitchbacksCurves(horizontalandvertical)Intersections
Layoutthe roadaccordingto9-11%sustainedgradeAssumeinitial widthof road4,5xwidthof truck
includingbermsanddrainsHighlightlocationof
SwitchbacksCurves(horizontalandvertical)Intersections
Examineconceptualdesignfollowingvertical andhorizontalalignmentrequirements
ExamineconceptualExamineconceptual
designfollowingdesignfollowingvertical andhorizontalvertical andhorizontal
alignmentalignmentrequirementsrequirements
Locateswitch-backson sectionof roadwithnoverticalgrades
Locateswitch-backson sectionof roadwithnovertical grades
IntersectiondesignIntersection designIntersection design
DrainagedesignDrainagedesignDrainagedesign
Locateintersectionsonlevel withadequatesight,curvesandrun-out.
Locateintersectionsonlevel withadequatesight,curvesandrun-out.
Designdrainagesystem,especiallyroad-side,culvertlocation,switchbackandintersectiondrainage.
Designdrainagesystem,especiallyroad-side,culvertlocation,switchbackandi ntersectiondrainage.
Separateverticalandhorizontal curveswherepossible
Separateverticalandhorizontalcurveswherepossible
Conceptual roadverti calandhorizontal layout
ConceptualConceptualroadverticalroadvertical
andhorizontal layoutandhorizontal layout
Truckminimumbrakingdistances(unassisted)Trucktypicalspeedsup-and down-gradeTrucksightdistancerequirements
Truckminimumbrakingdistances(unassisted)Trucktypicalspeedsup-and down-gradeTrucksightdistancerequirements
Layoutt heroadaccordingto 9-11%sustainedgradeAssumeinitialwidthofroad4,5xwidthof truck
includingbermsanddrainsHighlightlocationof
SwitchbacksCurves(horizontalandvertical)Intersections
Layoutthe roadaccordingto9-11%sustainedgradeAssumeinitial widthof road4,5xwidthof truck
includingbermsanddrainsHighlightlocationof
SwitchbacksCurves(horizontalandvertical)Intersections
Examineconceptualdesignfollowingvertical andhorizontalalignmentrequirements
ExamineconceptualExamineconceptual
designfollowingdesignfollowingvertical andhorizontalvertical andhorizontal
alignmentalignmentrequirementsrequirements
Locateswitch-backson sectionof roadwithnoverticalgrades
Locateswitch-backson sectionof roadwithnovertical grades
IntersectiondesignIntersection designIntersection design
DrainagedesignDrainagedesignDrainagedesign
Locateintersectionsonlevel withadequatesight,curvesandrun-out.
Locateintersectionsonlevel withadequatesight,curvesandrun-out.
Designdrainagesystem,especiallyroad-side,culvertlocation,switchbackandintersectiondrainage.
Designdrainagesystem,especiallyroad-side,culvertlocation,switchbackandi ntersectiondrainage.
Separateverticalandhorizontal curveswherepossible
Separateverticalandhorizontalcurveswherepossible
Conceptual road verticaland horizontal layout
ConceptualConceptual road verticalroad vertical
and horizontal layoutand horizontal layout
Truck minimum braking distances (unassisted)Truck typical speeds up-and down-gradeTruck sight distance requirements
Truck minimum braking distances (unassisted)
Truck typical speeds up- and down-gradeTruck sight distance r equirements
Lay out the road according to 9-11% sustained gradeAssume initial width of road 4,5x width of truck
includingberms and drains
Highlight location ofSwitchbacksCurves (horizontal and vertical)Intersections
Lay out the road according to 9-11% sustained grade
Assume initial width of road 4,5x width of truckincludingberms and drains
Highlight location ofSwitchbacks
Curves (horizontal and vertical)Intersections
Examine conceptualdesign followingvertical and horizontalalignment
requirements
Examine conceptualExamine conceptual
design followingdesign following
vertical and horizontalvertical and horizontal
alignmentalignment
requirementsrequirements
Locate switch-backs on section of road with novertical grades
Locate switch-backs on section of road with no
vertical grades
Intersection designIntersection designIntersection design
Drainage designDrainage designDrainage design
Locate intersections on level with adequate sight,
curves and run-out.
Locate intersections on level with adequate sight,curves and run-out.
Design drainage system, especially road-side,culvert location, switchback and intersectiondrainage.
Design drainage system, especially road-side,culvert location, switchback and intersectiondrainage.
Separate vertical and horizontal curves wherepossible
Separate vertical and horizontal curves wherepossible
8/8/2019 D2 S7 Thompson
14/35
Horizontal design andalignment
Horizontal design andHorizontal design and
alignmentalignment
Vertical design andalignment
Vertical design andVertical design and
alignmentalignmentEstablish minimum vertical curve lengths
based on change in grade (%) orheadlight distance for sag curves, forminimum stopping distance
Establish minimum vertical curve lengthsbased on change in grade (%) or
headlight distance for sag curves, forminimum stopping distance
Establish minimum horizontal curve lay-
back based on braking distance
Establish minimum horizontal curve lay-
back based on braking distance
Establish optimum grade 9-11%,.Establish optimum grade 9-11%,.
For every 1% increase inrolling resistance over 2%,
reduce optimum grade by 1%
For every 1% increase in
rolling resistance over 2%,reduce optimum grade by 1%
Establish cross-fall value or camber (2-
4%). Laden lane at uphill side of cross-fall.
Establish cross-fall value or camber (2-
4%). Laden lane at uphill side of cross-fall.
Where pit geometry does notallow for minimum
requirements, apply speedlimit to each curve not
meeting requirements
Where pit geometry does notallow for minimum
requirements, apply speedlimit to each curve not
meeting requirements
Establish width of road according to;
Truck width
Traffic (1-2 lanes)
Safety berm at outslope and
centre of road
Establish width of road according to;
Truck width
Traffic (1-2 lanes)
Safety berm at outslope andcentre of road
Establish run-outs based on curve super-elevation, cross-fall and camber.
Establish run-outs based on curve super-elevation, cross-fall and camber.
Berm designBermBerm designdesign
Design berms (median and outslope) withlargest truck and speed in mind.
Design berms (median and outslope) withlargest truck and speed in mind.
Establish minimum horizontal curveradius based on speed of truck and super-elevation (5% max)
Establish minimum horizontal curve
radius based on speed of truck and super-elevation (5% max)
Where pit geometry does notallow for minimum
requirements, apply speedlimit to each curve not
meeting requirements
Where pit geometry does notallow for minimum
requirements, apply speedlimit to each curve not
meeting requirements
Where pit geometry does not
allow for minimumrequirements, apply speedlimit to each curve notmeeting requirements
Where pit geometry does notallow for minimum
requirements, apply speedlimit to each curve notmeeting requirements
Final geometricdesign
Final geometricFinal geometric
designdesign
Drainage re-evaluationDrainage reDrainage re--evaluationevaluation
Horizontal design andalignment
Horizontal design andHorizontal design and
alignmentalignment
Vertical design andalignment
Vertical design andVertical design and
alignmentalignmentEstablish minimum vertical curve lengths
based on change in grade (%) orheadlight distance for sag curves, forminimum stopping distance
Establish minimum vertical curve lengthsbased on change in grade (%) or
headlight distance for sag curves, forminimum stopping distance
Establish minimum horizontal curve lay-
back based on braking distance
Establish minimum horizontal curve lay-
back based on braking distance
Establish optimum grade 9-11%,.Establish optimum grade 9-11%,.
For every 1% increase inrolling resistance over 2%,
reduce optimum grade by 1%
For every 1% increase in
rolling resistance over 2%,reduce optimum grade by 1%
Establish cross-fall value or camber (2-
4%). Laden lane at uphill side of cross-fall.
Establish cross-fall value or camber (2-
4%). Laden lane at uphill side of cross-fall.
Where pit geometry does notallow for minimum
requirements, apply speedlimit to each curve not
meeting requirements
Where pit geometry does notallow for minimum
requirements, apply speedlimit to each curve not
meeting requirements
Establish width of road according to;
Truck width
Traffic (1-2 lanes)
Safety berm at outslope and
centre of road
Establish width of road according to;
Truck width
Traffic (1-2 lanes)
Safety berm at outslope andcentre of road
Establish run-outs based on curve super-elevation, cross-fall and camber.
Establish run-outs based on curve super-elevation, cross-fall and camber.
Berm designBermBerm designdesign
Design berms (median and outslope) withlargest truck and speed in mind.
Design berms (median and outslope) withlargest truck and speed in mind.
Establish minimum horizontal curveradius based on speed of truck and super-elevation (5% max)
Establish minimum horizontal curve
radius based on speed of truck and super-elevation (5% max)
Where pit geometry does notallow for minimum
requirements, apply speedlimit to each curve not
meeting requirements
Where pit geometry does notallow for minimum
requirements, apply speedlimit to each curve not
meeting requirements
Where pit geometry does not
allow for minimumrequirements, apply speedlimit to each curve notmeeting requirements
Where pit geometry does notallow for minimum
requirements, apply speedlimit to each curve notmeeting requirements
Final geometricdesign
Final geometricFinal geometric
designdesign
Drainage re-evaluationDrainage reDrainage re--evaluationevaluation
Geometric DesignGeometric Design
Well documentedWell documented but take specialbut take special
care with;care with;
RampsRamps grade breaks and max productivegrade breaks and max productive
total resistance (grade + rolling)total resistance (grade + rolling)
8/8/2019 D2 S7 Thompson
15/35
Geometric DesignGeometric Design
Well documentedWell documented but take specialbut take special
care with;care with;
RampsRamps grade breaks and max productivegrade breaks and max productive
total resistance (grade + rolling)total resistance (grade + rolling)
Geometric DesignGeometric Design
Well documentedWell documented but take specialbut take special
care with;care with;
RampsRamps grade breaks and max productivegrade breaks and max productive
total resistance (grade + rolling)total resistance (grade + rolling)
Switchbacks and curvesSwitchbacks and curves large radius andlarge radius and
supersuper--elevatedelevated
8/8/2019 D2 S7 Thompson
16/35
Geometric DesignGeometric Design
Well documentedWell documented but take specialbut take special
care with;care with;
RampsRamps grade breaks and max productivegrade breaks and max productive
total resistance (grade + rolling)total resistance (grade + rolling) Switchbacks and curvesSwitchbacks and curves large radius andlarge radius and
supersuper--elevatedelevated
Geometric DesignGeometric Design
BermsBerms especially centreespecially centre bermsberms and atand at
switchbacksswitchbacks place a sand buffer on edgeplace a sand buffer on edgeto protectto protect tyrestyres
8/8/2019 D2 S7 Thompson
17/35
Geometric DesignGeometric Design
BermsBerms especially centreespecially centre bermsberms and atand at
switchbacksswitchbacks place a sand buffer on edgeplace a sand buffer on edge
to protectto protect tyrestyres DrainageDrainagecrosscross--fall or camber andfall or camber and
roadside drainage ditchesroadside drainage ditches
Geometric DesignGeometric Design
Make sure that what you haveMake sure that what you have designeddesignedisis
built and maintained correctlybuilt and maintained correctly
Make use of signage to assist grader andMake use of signage to assist grader and
truck operators to make maximal use of thetruck operators to make maximal use of the
roadroad
8/8/2019 D2 S7 Thompson
18/35
Structural DesignStructural Design
Load carrying capacity of the road. DesignLoad carrying capacity of the road. Design
for;for;
Better pavement response to applied loadsBetter pavement response to applied loads
Reduced deflection on surfaceReduced deflection on surface Eliminate deformation in subEliminate deformation in sub--grade or ingrade or in--situsitu
Structural DesignStructural Design
Mechanistic design approach usingMechanistic design approach using
pavement layer limiting vertical strain criteriapavement layer limiting vertical strain criteria
Limiting strain criteria tailored to trafficLimiting strain criteria tailored to traffic
volumes, type and life of mine road (ramp, pit orvolumes, type and life of mine road (ramp, pit or
main haul)main haul)
8/8/2019 D2 S7 Thompson
19/35
Structural DesignStructural Design
Case StudyCase StudyStructural design comparisons
0250500
7501000125015001750
200022502500
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000
Vertical (micro) strain in pavement
NewD
esignLayer
Depths(mm)
0250500
7501000125015001750
200022502500
Old Des ign New Design
OldDesignLayerDepths(mm)
W/course
Fill layer
Layer 3
In-situ
Selected
blasted waste
Layer 3
In-situ
W/course
Wearing course
Base
In-situ (soft)
Wearing course
Base
In-situ (soft)
Wearing course
Base
In-situ (soft)
Wearing course
Base
In-situ (soft)
Wearing course
Base
In-situ (soft)
Wearing course
Base
In-situ (soft)
PracticalPractical
ApplicationApplication
To apply the mechanistic design approachTo apply the mechanistic design approach
some basic data is required;some basic data is required;
InIn--situ material strength below roadsitu material strength below road
Truck wheel load and traffic volume (kt/day)Truck wheel load and traffic volume (kt/day)
Life of road (main haul, ramp, bench, etc.)Life of road (main haul, ramp, bench, etc.)
8/8/2019 D2 S7 Thompson
20/35
PracticalPractical
ApplicationApplication
From this data, a design catalogue can beFrom this data, a design catalogue can be
developed by the mine for each type anddeveloped by the mine for each type and
generic location of road to be builtgeneric location of road to be built
The selection of wearing course materialsThe selection of wearing course materials
Reduced rolling resistanceReduced rolling resistance
improved costimproved cost
per ton hauledper ton hauled
To provide a safe, economic and vehicleTo provide a safe, economic and vehicle
friendly ridefriendly ride
Functional DesignFunctional Design
8/8/2019 D2 S7 Thompson
21/35
Functional DesignFunctional Design
Correct functional design will;Correct functional design will;
Reduce road rolling resistanceReduce road rolling resistance throughthrough
reduced wearing course defectsreduced wearing course defects
Reduce road deterioration rates andReduce road deterioration rates andmaintenance frequencymaintenance frequency
Functional DesignFunctional Design
Wearing Course Selection
0
50
100
150
200
250
300
350
400
0 5 10 15 20 25 30 35 40 45 50
Grading Coefficient
ShrinkageProduct
Recommended (1) Recommended (2)
Dustiness Slippery when wet
Loose material
Loose stones
Tyre damage Corrugates
8/8/2019 D2 S7 Thompson
22/35
0
50
100
150
200
250
300
350
400
450
500
550
0 10 20 30 40 50
Grading coefficient
Shrinkageproduct
.
Dust inessWet sk id res is tance
Loose s ton iness
Corrugat ions
Loose mater ia l
Dry sk id res is tance
1
2
PracticalPractical
ApplicationApplication
0
50
100150
200
250
300
350
400
450
500
550
0 10 20 30 40 50
Grading coefficient
Shrin
kageproduct
.
Dust iness
Loose s ton iness
Dry sk id res is tance
1
PracticalPractical
ApplicationApplication
8/8/2019 D2 S7 Thompson
23/35
PracticalPractical
ApplicationApplication
Maintenance interval comparison with rolling
resistance
1.0
1.3
1.5
1.8
2.0
2.3
2.5
2.8
3.0
0 1 2 3 4 5 6 7 8 9 10Road maintenance interval (days)
Rollingresistance(%)
Exist ing road wearing course'Rehabilitated' wearing course'New' wearing course
PracticalPractical
ApplicationApplication
Functional Performance Model
020
40
60
80
100
120
140
160
0 1 2 3 4 5 6 7 8 9 10
Road maintenance interval (days)
AverageDefectScor
Existing road wearing course'Rehabilitated' wearing course'New' wearing course
8/8/2019 D2 S7 Thompson
24/35
To apply the functional design approachTo apply the functional design approach
some basic data is required;some basic data is required;
Materials available for wearing courseMaterials available for wearing course
Road indicator test dataRoad indicator test dataWhether a new or rehabilitated road is requiredWhether a new or rehabilitated road is required
PracticalPractical
ApplicationApplication
PracticalPractical
ApplicationApplication
From this data, a design catalogue can beFrom this data, a design catalogue can be
developed by the mine for each type of roaddeveloped by the mine for each type of road
8/8/2019 D2 S7 Thompson
25/35
MaintenanceMaintenance
ManagementManagement
Various road maintenance systems areVarious road maintenance systems are
applied on mines, including;applied on mines, including;
Routine road maintenanceRoutine road maintenance
ResurfacingResurfacing Rehabilitation / bettermentRehabilitation / betterment
MaintenanceMaintenanceManagementManagement
Routine haul road maintenance can beRoutine haul road maintenance can be
carried out by;carried out by;
AdAd--hochoc bladingblading
Scheduled (fixed)Scheduled (fixed) bladingblading
Maintenance management systems approachMaintenance management systems approach
RealReal--time management approachtime management approach
8/8/2019 D2 S7 Thompson
26/35
MaintenanceMaintenance
ManagementManagement
Process
Opportunity
tominimisetotalroad-usercosts
Ad-hoc blading
Scheduledblading
MMS
RT-MMS
Mana
gementandsystemc
omplexity
Low complexity Low management input Un-optimised total road user costs
Low complexity Some management input Un-optimised total road user costs
Intermediate complexity Some management input Optimised total road user costs
High complexity existing system Low management input Optimised real-time total road
user costs
MaintenanceMaintenanceManagementManagement
Only the;Only the;
Maintenance management systems approachMaintenance management systems approach
RealReal--time management approachtime management approach
can minimise total roadcan minimise total road--user costsuser costs
8/8/2019 D2 S7 Thompson
27/35
MaintenanceMaintenance
ManagementManagement
Maintenance frequency
Rolling resistance
Max
Min
Minimum total
cost solution
Max
Min
Costs
Maintenance ManagementMaintenance Management RoadRoad--useruserCost Variation ExampleCost Variation Example
Percentage increase in total road-user costs with
maintenance interval
0
5
10
15
20
25
30
35
40
0 1 2 3 4 5 6 7 8 9 10
Days between maintenance
Percentchange
B02 B03 B04
B05 S Ramp
8/8/2019 D2 S7 Thompson
28/35
PracticalPractical
ApplicationsApplications
ID theID the KPSKPS KKeyey PPerformanceerformance SSegments onegments on
your road network;your road network;RampsRamps 1%RR1%RR 10%KPH10%KPH
Switchbacks, etc.Switchbacks, etc. Long term, high speed high tonnage roadsLong term, high speed high tonnage roads
Prioritize maintenance on these segmentsPrioritize maintenance on these segments
PracticalPractical
ApplicationsApplications
Visual inspectionsVisual inspections mark roads where maintenancemark roads where maintenance
should be done with red, yellow or green conesshould be done with red, yellow or green cones
prioritize.prioritize. Record maintenance intervention (what done) andRecord maintenance intervention (what done) and
frequencies (how often) per segmentfrequencies (how often) per segment establish aestablish a
rehabilitation schedulerehabilitation schedule prioritize BUTprioritize BUT..
8/8/2019 D2 S7 Thompson
29/35
PracticalPractical
ApplicationsApplications
Why is the segment maintenance intensive?Why is the segment maintenance intensive?Poor design and / or build specs;Poor design and / or build specs;
GeometricsGeometrics
Structure (layer works and materials)Structure (layer works and materials)
Functional (wearing courseFunctional (wearing course surfacingsurfacing
materials)materials)
PracticalPractical
ApplicationsApplications
Investigate the rootInvestigate the root--cause of the undercause of the under--
performanceperformance beforebeforedeciding on a remediationdeciding on a remediation
strategystrategy
8/8/2019 D2 S7 Thompson
30/35
Most large surface mines already use;Most large surface mines already use; OEM truck monitoring, data communication andOEM truck monitoring, data communication and
asset location systemsasset location systems
RealReal--time maintenance management systemtime maintenance management systemutilises existing data collation andutilises existing data collation and
communication protocolscommunication protocols
RealReal--time Road Maintenancetime Road Maintenance
ManagementManagement
Gradersentreal-time to
maintain road attriggerlocation
Event triggerand truck
location to D ispatch control
Haultruckdiagnostic data
GPS truck location
Implement and monitorC TMmanagement system module,integrating truck vital signs, hub
and dispatch protocols withroad
defect signature recognitionalgorithms
Management and controlofdefecttrigger levels and
maintenance transactions
Event triggering
Develop haulroaddefecteve nt signaturerecording, analysis and
event recognition
systems
Developmentofsystemarchitecture and communication
protocols between truck andModularMininghub
PHASE II
PHASE III
PHASE IV
KEY
Developmental phases forsystem
protocols, signatures and triggers
Operating system linksGradersentreal-time to
maintain road attriggerlocation
Event triggerand truck
location to D ispatch control
Haultruckdiagnostic data
GPS truck location
Implement and monitorC TMmanagement system module,integrating truck vital signs, hub
and dispatch protocols withroad
defect signature recognitionalgorithms
Management and controlofdefecttrigger levels and
maintenance transactions
Event triggering
Develop haulroaddefecteve nt signaturerecording, analysis and
event recognition
systems
Developmentofsystemarchitecture and communication
protocols between truck andModularMininghub
PHASE II
PHASE III
PHASE IV
KEY
Developmental phases forsystem
protocols, signatures and triggers
Operating system links
RealReal--time Haul Roadtime Haul Road
MaintenanceMaintenance
RealReal--time Haul Roadtime Haul RoadMaintenanceMaintenance
317t GVM haul truck instrumented with317t GVM haul truck instrumented with
piezoelectric acceleration recorder and GPS;piezoelectric acceleration recorder and GPS;RoadRoad defect signaturesdefect signatures initially recognisedinitially recognised
qualitatively (in terms ofqualitatively (in terms of high Ghigh G events)events)
8/8/2019 D2 S7 Thompson
31/35
Cross-erosion area 1
-3.0
0.0
3.0
0.0 2.0 4.0
Time (sec)
Acceleratio
n(G's)
Wasboard area 1
-3.0
0.0
3.0
0.0 2.0 4.0Time (s)
Acceleration(G's)
Hump line 2-5
-3.0
0.0
3.0
0.0 2.0 4.0
Time(s)
Acceleration(G's)
Fixed stone 8-10
-3.0
0.0
3.0
0.0 2.0 4.0Time(s)
Acceleration(G's)
Ditch line 2-3
-3.0
0.0
3.0
0.0 2.0 4.0Time(sec)
Acceleration(G's)
Tinaja Hills Test Track, Tucson, ArizonaTinaja Hills Test Track, Tucson, Arizona
Prepared haul road with 15 GPS surveyedPrepared haul road with 15 GPS surveyed
defect locations over 18 000mdefect locations over 18 000m22;; TailorTailor--made defects typical of existing mine roadmade defects typical of existing mine road
functional defectsfunctional defects
Defect degree, extent, dimensions and locationDefect degree, extent, dimensions and location
recordedrecorded
RealReal--time Haul Roadtime Haul RoadMaintenanceMaintenance
8/8/2019 D2 S7 Thompson
32/35
Kumba Resources Grootegeluk Mine, South AfricaKumba Resources Grootegeluk Mine, South Africa
Defect geometry reconstruction fromDefect geometry reconstruction from
truck measured responsetruck measured response
Road defect recognition
-0.1
-0.05
0
0.05
0.1
0.15
0.2
0 0.5 1 1.5 2 2.5 3 3.5 4
Arbitrary time (s)
Roadsurface
elevation(m)
Actual road defect
Reconstructed road defect from truck response
8/8/2019 D2 S7 Thompson
33/35
RealReal--time Haul Roadtime Haul Road
MaintenanceMaintenance --Practical ApplicationsPractical Applications
Leverage existing communication and onLeverage existing communication and on--
board systems to assist in defining poor roadboard systems to assist in defining poor road
performance;performance;
Average segment speeds cw benchmark speedsAverage segment speeds cw benchmark speedsStrut pressure differentials (RACS, etc.)Strut pressure differentials (RACS, etc.)
PracticalPractical
ApplicationsApplications
Why is the segment maintenance intensive?Why is the segment maintenance intensive?Poor design and / or build specs;Poor design and / or build specs;
GeometricsGeometricsStructure (layer works and materials)Structure (layer works and materials)
Functional (wearing courseFunctional (wearing course surfacingsurfacing
materials)materials)
8/8/2019 D2 S7 Thompson
34/35
PracticalPractical
ApplicationsApplications
Investigate the rootInvestigate the root--cause of the undercause of the under--
performanceperformance beforebeforedeciding on a remediationdeciding on a remediation
strategystrategy
PracticalPractical
ApplicationsApplications
8/8/2019 D2 S7 Thompson
35/35
AcknowledgementsAcknowledgements
Aspects of this work were made possible through the support of oAspects of this work were made possible through the support of our industryur industry
partners and clients in South Africa and internationaly. In parpartners and clients in South Africa and internationaly. In particular, Angloticular, Anglo
Coal SA, Kumba Resources, the Technology and Human Resources forCoal SA, Kumba Resources, the Technology and Human Resources for
Industry Programme and the Mine Health and Safety Council of SouIndustry Programme and the Mine Health and Safety Council of South Africa.th Africa.
Further acknowledgement is also given to the Fulbright CommissioFurther acknowledgement is also given to the Fulbright Commission andn and
CDCCDC--NIOSH for assistance with aspects of the realNIOSH for assistance with aspects of the real--time maintenance systemtime maintenance system
development initiatives.development initiatives.