CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE
44

CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Dec 17, 2015

Download

Documents

Sophia Briggs
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

CVE 4070

ENG-1000 Intro to EngineeringCVE-1000 Intro to Civil EngineeringConstruction OverviewProf. Ralph V. Locurcio, PE

Page 2: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Class Objectives…

Understand project delivery process Understand the phases of engineering Describe the construction profession

Construction contracts & issues Tools of the trade – skills you need Typical jobs in construction Leadership & management

Page 3: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Construction Intro…

The 4 phases of engineering1. Planning & Programming2. Design & Engineering3. Construction (Manufacturing)4. Maintenance

Page 4: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Design Process

Construction Process

Programming Process

Project Delivery Process…

Need for a projectIs recognized

Owner appointsProject Manager

Project Manager develops project

program: scope & cost parameters

Project is entered into an annual

capital program

Designer prepares concept design & preliminary cost

estimate

Designer completes plans &

specifications

Owner orders bid documents

Project Manager advertises for

construction bids

Contractors assemble team,

prepare & submit bid

Bids reviewed by owner

(with designer)

Builder’s credentials &

bonding approved

Owner approves program

Project Manager advertises for

designer

Owner hires designer

Owner authorizes final

design

Owner selectsbuilder

Notice to Proceed

Constructionbegins

Resident Engineeroversees

construction

Project phase(s)completed

All work completed final inspection

made

Progresspayment

Final paymentOwner accepts

facility

Page 5: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

About Construction…

It’s an extremely complex process… Many players, many variables, many unknowns Design is never perfect

Unlike manufacturing process… Teams are variable; not trained on this project Production site is crude & unprepared Very large projects – rarely build more than one Very large risks – owner’s first and last experience Large penalties for error or contract failure Money drives all aspects of the process One chance to get it right

CM goal is to deliver a perfect product

Page 6: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Construction History

The oldest profession? The master builders… architects? Growth of Project Management Growth of Quality Management Construction Management Emerges

Page 7: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Hammurabi’s Code – 1780 B.C.228. If a builder build a house for some one and

complete it, he shall give him a fee of two shekels in money for each sar of surface.

229. If a builder build a house for some one, and does not construct it properly, and the house which he built fall in and kill its owner, then that builder shall be put to death.

230. If it kill the son of the owner the son of that builder shall be put to death.

231. If it kill a slave of the owner, then he shall pay slave for slave to the owner of the house.

232. If it ruin goods, he shall make compensation for all that has been ruined, and inasmuch as he did not construct properly this house which he built and it fell, he shall re-erect the house from his own means.

233. If a builder build a house for some one, even though he has not yet completed it; if then the walls seem toppling, the builder must make the walls solid from his own means.

Page 8: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Contracting – 487B.C.Contract for Rent & Repair of a House, One Year Term, Thirty-fifth year of Darius, 487 B.C. This contract is most interesting. Such business methods are not, therefore, altogether modern.

•In addition to the rent of the house of Shamash-iddin, son of Rimut, fifteen shekels of money in cash (shall go) to Iskhuya, son of Shaqa-Bel, son of the priest of Agish, for this year.

•Because of the payment he shall repair the weakness (of the house), he shall close up the crack of the wall. He shall pay a part of the money at the beginning, a part of the money at the completion. He shall pay it on the day of Bel, the day of wailing and weeping.

•In case the house is unfinished by Iskhuya after the first day of Tebet, Shamash-iddin shall receive four shekels of money in cash into his possession at the hands of Iskhuya. •The names of three witnesses and a scribe then follow… •Dated at Shibtu, the twenty-first of Kislimu, the thirty-fifth year of Darius.

Page 9: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Public Construction & Economy!

Page 10: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Construction vs. Engineering

Construction Engineering1.Mostly outdoor 1. Mostly Indoor2.Teamwork 2. Individual work3.Business skills 3. Technical skills4.Multi-skills 4. Specialized skills5.Variable locations 5. Fixed location6.Leadership 6. Self-discipline7.Total project 7. One component8.Large budget 8. Small budget9.Great risk 9. Small risk10.End product 10. Partial product

Page 11: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Construction skills…

Skills you need in construction Fundamentals: science, math, business Contracting: risk, legal issues, changes Project Controls: schedule, cost, estimates Construction Operations: responsibility,

authority, planning, documents, productivity, quality, documentation, safety, closeout

Leadership: teams, organization, motivation, success, ethics

Page 12: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Planning… Pyramid Construction

Time2 4 6 8 10 12 14 16

General Design

Planning Preparation Construct Core

Trim Exterior

Demobilize

Interior Design Room Const Interior Finishes

Bury Pharoah

Structure

Site Selection

Master Plan

Open Quarry Cut Blocks Cut Trim

Workforce

Train Train Train

Build Camp

DemobCamp

FinalInsp

Page 13: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Construction Schedule…

Page 14: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Constructing concrete columns

Page 15: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Concrete wall section

Page 16: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Concrete foundation/pier

Page 17: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

What’s involved…

Engineering: 1.design the columns2.size the rebars3.draw the plans 4.specify the materials5.write the contract6.select the site7.inspect the work8.advise the owner

Construction: 1.read the plans 2.hire the workers3.organize the site4.schedule the work5.form the columns6.install the rebars7.purchase the materials8.satisfy the owner

Page 18: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Concrete pump in action

Page 19: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Construction site management

Page 20: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Traffic & environmental impacts

Page 21: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Construction Process

Study the contract Study the site, labor, materials Plan the work

What teams are needed How will they interact in time Integrate materials & logistics Diagram the flow of work Check the timing from start to finish

Page 22: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Class example

Plan the construction of a dog house

What needs to be considered ???

Page 23: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Engineering phase…

Page 24: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Construction phase

Tape measure Hammer Square Circular saw Table saw (optional) Paintbrush Dust mask GogglesHearing Protection

4'x8' sheet of 5/8" exterior siding 1— 8' 2x4 (to be cut into 2x2's) 1— 10' 2x4, rated for outdoor use Nails—16d for base, 8d for house, and

short roofing nails if using shingles Shingles (optional) Finishing material (paint or nontoxic

wood preservative)

Tools

Materials

Construction Operations

CostTimingQualitySafetyLaborWeatherSitingTransportation

Page 25: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

The customer’s needs!

Page 26: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Time Phased Budget Control

Page 27: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Last Month Payment

This Month Request

Page 28: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Payment calculations…pipe

A B

A

B

Plan Length = 315 feet

In Place Length = 325 feet

Delivered Length = 400 feet

Payment Method = Linear Feet of Pipe… plan, delivered, placed?Pipe cost = $150/lf = $47,250 or $60,000 or $48,750???

Page 29: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Hidden Costs

Page 30: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Change order cost estimate…

Study the plans Organize your estimate Determine critical dimensions Determine critical materials & methods Determine take off quantities Calculate the cost of each quantity Add overhead & profit Negotiate with the contractor

Page 31: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Determine dimensions…

Page 32: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Foundation excavation-1…

3’

22’ 22’

19’

(18’10+16”+16 = 18’42”)

3’ 3’

3’3’

3’

(7’2”+6’4”+7’2”+7’16” = 27’24”)

4’(4’ = 7’-18”-18”

29’-6’=23’

Page 33: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Foundation-2…

Conc. 1.25’

3’

Excav

3’

3’

Page 34: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Foundation excavation-3…

Add the pieces…3’x22’3’x22’3’x23’3’x19’3’x4’3’x3’3’x3’

Total = 3’ x 96’=288 SF x 3’ depth = 864 CF = 32 CY

Page 35: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Concrete volume…

Add the pieces…3’x22’3’x22’3’x23’3’x19’3’x4’3’x3’3’x3’

Total = 3’ x 96’=288 SF x 1.25’ depth = 360 CF

Page 36: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Masonry walls…

W1

W2

W3/W6

W4

W5

W7

W8

W9

12”CMU

8” CMU

Insul

Brick

Page 37: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Floor slab…

FS-1

FS-2

FS-1=21’X19’=399 SF

FS-2=7’X19’=133SF

Page 38: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Cost Estimate of Change…Take-off item Label Units #Units Total #Units Cost/Unit Prod Hrs Tot Cost

Wall 12" CMU x 8' (8'above + 2'below) W1 LF 18 SFWall 12" CMU x 8' W2 LF 7.25 SFWall 12" CMU x 8' W3 LF 7.75 SF 330 $10.46 $3,451.80Wall 8" CMU x 4' (3'above + 2'below) W4 LF 10 SFWall 8" CMU x 4' W5 LF 7.25 SFWall 8" CMU x 4' W6 LF 7.75 SF 125 $8.48 $1,060.00Wall 8" CMU x 8' W7 LF 19 SFWall 8" CMU x 8' W8 LF 21.3 SFWall 8" CMU x 8' (8'above + 2'below) W9 LF 9.25 SF 495.5 $8.48 $4,201.84Brick veneer x 4' V1 LF 10 SFBrick veneer x 4' V2 LF 7.25 SFBrick veneer x 4' V3 LF 7.75 SF 100 $4.24 $424.00Rigid insulation 2.5" x R10.9 I1 LF 67 SF 536 $1.28 $686.08Column C-3 x 2 ea @12' x 8"x8" C1 EA 2 EA 2 $461.50 $923.00Steel doors-double 2 EA 2 EA 2 $551.00 $1,102.00Steel doors-single 1 EA 1 EA 1 $275.50 $275.50Floor slab 4" FS1 SF 399 CFFloor slab 4" FS2 SF 133 CF 159.6 $4.11 $655.96Masonry bond beam=V1+V2+V3 BB LF 26 LF 26 $3.26 $84.76Foundation=sum (F1:F7) FO CF 120 CF 120.0 $4.11 $493.20Excavation for foundation=sumE1:E7 EX CF 864 CY 32.0 $35.55 1.5 2.13 $75.84(assume loader does 10 buckets/hr)For finishing, ceiling, HVAC, MEP FIN CF 4256 CF 4256.0 $3.50 $14,896.00

Total Raw Cost Job $28,329.98Add 10% Overhead Job $31,162.97Add 10% Profit Job $34,279.27Grand Total Job $34,279.27

Cross check cost/CF for Sci Blds. CF 4256 $7.75 (low 1/4) $32,984.00

Page 39: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Project Organization…Owner

Quality Control

Superintendent Project Engineer

Project Engineer

Contractor

Project Manager, Construction Manager

and/orContracting Officer

Subcontractor

Subcontractor

Subcontractor

Subcontractor

Subcontractor

Design Manager

ProjectArchitect

StructuralEngineer

CivilEngineer

MechEngineer

ElectricalEngineer

A

B

C

Quality Assure

OfficeEngineer

TechnicalInspectors

A/E Const Staff

Resident Engineer

UsingAgency

Page 40: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Project Organization-designOwner

ProjectArchitect

StructuralEngineer

CivilEngineer

MechanicalEngineer

Design Manager

Corporate Management

Project Manager

ConstructionContract

UsingAgency

ElectricalEngineer

Design Staff Design Staff Design Staff Design Staff Design Staff

Consultant A Consultant B Consultant C

Page 41: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Project Organization-const opns

Owner

Quality Control

Superintendent Project Engineer

Project Engineer

Corporate Management

Corporate staff

Field site

Interpret Drawings & SpecsShop Drawings

RFI controlMaterialsSamples

Construction operationsCoordination of trades

SchedulesPayments

Safety-OSHAChanges

RFI responsesClarification of drawings

Monitor compliance

Monitor QC processPrepare QC reportsMake inspections

Take corrective actionDocument QC checks

Project Manager

ConstructionContract

Subcontractor A Subcontractor B Subcontractor C Subcontractor D Subcontractor E

Sub-contracts

Contractor orConstruction

Manager

Page 42: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Jobs in construction

Contractor – owns a company Contract specialist – interprets contract Estimator – prepares bid Project Manager – runs complete job Project Engineer – approves/orders matl. Site Engineer – plans site layout Superintendent – manages crews Quality control – inspects work

Page 43: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

Construction vs. Engineering

Construction Engineering1.Mostly outdoor 1. Mostly Indoor2.Teamwork 2. Individual work3.Business skills 3. Technical skills4.Multi-skills 4. Specialized skills5.Variable locations 5. Fixed location6.Leadership 6. Self-discipline7.Total project 7. One component8.Large budget 8. Small budget9.Great risk 9. Small risk10.End product 10. Partial product

Page 44: CVE 4070 ENG-1000 Intro to Engineering CVE-1000 Intro to Civil Engineering Construction Overview Prof. Ralph V. Locurcio, PE.

The goal... happy customers!