NOTICE INVITING TENDER FOR SUPPLY OF IS 3589
CARBON STEEL PIPES FOR BPCL GROUP REFINERY
LOCATED AT KOCHI,INDIA.
REQUEST FOR QUOTATION
CRFQ NO. 1000166569
DUE DATE : 31/07/2012
CCCPPPOOO (((RRREEEFFFIIINNNEEERRRIIIEEESSS)))
BHARAT PETROLEUM CORPORATION LTD.
(A Govt. of India Undertaking)
Central Procurement Organization (Refineries)-CPO(R)
BPCL, Mumbai Refinery, Mahul, Mumbai-400 074
Phone: 91-22-25524129 / Fax: 91-22-25544082
NOTICE INVITING TENDER
(CRFQ NO:1000166569)
M/s BHARAT PETROLEUM CORPORATION LTD, Central Procurement Organization –
Refineries invites 3 part bids for Supply of IS 3 589 Carbon Steel Pipes for BPCL Group
Refinery located at Kochi, India.
Details of the tender are available at e-procurement platform https://bpcl.eproc.in.
The tender document can also be downloaded (for reference purpose) from our
website: www.bharatpetroleum.in Energizing Business Tenders
CPO(Refineries) or Government Central Procurement Portal
http://eprocure.gov.in/cppp.
Due date for submission of the Tender: 31.07.2012, 14.00 Hrs. IST.
Important: All updates, amendments, corrigenda etc, (if any) will be posted on the
above websites as and when required. There will not be any publication of the same
through newspapers or any other media.
Place: Mumbai Dy. General Manager, CPO (Refineries)
REQUEST FOR QUOTATION CRFQ -1000166569
1.0 INTRODUCTION
The bids are invited through E tendering platform under three-bid system (i.e. Part 1 – Pre-qualification Bid,
Part 2 - Techno-commercial/Unpriced Bid & Part 3 - Priced Bid) as outlined below. Bidders can downloa d
the complete set of tender documents from, our website www.bharatpetroleum.in Energizing Business
Tenders Refinery procurement - CRFQ No.1000166569 , Government Central Procurement
Portal http://eprocure.gov.in/cppp or at e-procurement platform https://bpcl.eproc.in.
be paid separately by Demand Draft (DD) / Banker’s
Cheque drawn in favour of Bharat Petroleum Corporation
TO NOTE AND CONFIRM
Limited and payable at Mumbai2.8.6 Alternatively EMD can also be remitted by way of “Bank
Guarantee” as per BG format attached (Annexure-14), from
any Bank recognized as Scheduled Bank by Reserve Bank
of India, in favour of M/s. Bharat Petroleum Corporation Ltd.
Mumbai.
TO NOTE AND CONFIRM
2.8.7 Bank Guarantee from any Foreign Bank is acceptable only
if the same is countersigned by their Indian Branches
(provided the Indian Branch of the Foreign Bank is
recognized Scheduled Bank by Reserve Bank of India) or
any Scheduled Indian Bank
TO NOTE AND CONFIRM
2.8.8 The Bank Guarantee in lieu of EMD shall be furnished on
non-judicial stamp paper of value not less than Rs. 100/-
(Rupees One hundred only) and in the prescribed Performa
given in the Tender Document
TO NOTE AND CONFIRM
2.8.9 The Bank Guarantee shall be kept valid for a period of 60
days beyond the validity period
TO NOTE AND CONFIRM
2.8.10 Original DD/Banker’s Cheque or BG as the case may be,
towards EMD shall be sent separately to DGM, CPO-
Refineries, BPCL. Copy the DD/Banker’s cheque /BG as
the case may be, along with proof of dispatch to be
uploaded along with pre qualification bid. Bids without EMD
are liable to be rejected
TO NOTE AND CONFIRM
2.8.11 EMD of unsuccessful bidders shall be released after
issuance of LOI /Purchase Order against this tender.
However, in case of successful bidder the EMD shall be
released on receipt of performance bank guarantee
TO NOTE AND CONFIRM
2.8.12 Forfeiture of EMD – A tenderer who has submitted their bid
shall not be permitted to alter/amend or withdraw the bid,
not withstanding that the bid(s) has/have not yet been
opened/finalised. A tenderer who purports to alter/modify
withdraw their offer after submission, within the validity of
the offer shall be liable to have their offer rejected and their
EMD forfeited/encashed.
TO NOTE AND CONFIRM
2.8.13 The Earnest Money deposited by successful tenderer shall
be forfeited if the successful tenderer fails to honour the
offer terms prior to ordering and Contractual terms after
issuance of FOI/PO
TO NOTE AND CONFIRM
Page 7
SNO INSTRUCTIONS VENDOR'S ACTION RESPONSE
GENERAL INSTRUCTION TO BIDDERS
2.9 INTEGRITY PACT
2.9.1 Proforma of Integrity Pact (IP) IAnnexure-16) shall be
uploaded by the Bidder/s along with the unpriced bid
documents duly signed by the same signatory who is
authorised to sign the bid documents. All the pages of the
Integrity Pact shall be duly signed. Bidder's failure to upload
the IP duly signed along with bid documents shall result in
the bid not being considered for further evaluation
TO NOTE AND CONFIRM
2.9.2 If the Bidder has been disqualified from the tender process
prior to the award of the contract in accordance with the
provisions of the IP, BPCL shall be entitled to demand &
recovered from Bidder Liquidated Damages amount by
forfeiting the EMD/Bid Security as per provisions of IP.
TO NOTE AND CONFIRM
2.9.3 If the contract has been terminated according to the
provisions of the IP, or if BPCL is entitled to terminate the
contract according to the provisions of the IP, BPCL shall
be entitled to demand & recovered from Contractor
Liquidated Damages amount by forfeiting the Security
Deposit/Performance Bank Guarantee as per provisions of
the IP
TO NOTE AND CONFIRM
2.9.4 Bidders may raise disputes/complaints, if any, with the
nominated Independent External Monitor (IEM). The IEM's
name, address & contact number is given below :
Mr.Janki Ballabh
Flat No. 605,Vesova Vinayak Co-Op Hsg Soc
Plot No:8, Near Vesova Telephone Exchange
Versova, Andheri(West)
Mumbai - 400053.
Tel : 022-2635 3456 (Res)
Mobile : 9833363066
TO NOTE
2.10 INSTRUCTIONS TO BIDDERS FOR E-TENDERING
2.10.1 The vendor is requested to download the tender from
BPCL’s e-tendering website https://bpcl.eproc.in and
participate in the tender as per the instructions given above
TO NOTE
participate in the tender as per the instructions given above
and herein, on or before the due date and time of the
tender. The tender available on the BPCL website can be
downloaded for reading purpose only. For participation in
the tender, please fill up the tender online on the e-tender
system available on https://bpcl.eproc.in.
2.10.2 For registration on the e-tender site https://bpcl.eporc.in,
you need to download the User Instruction Manual from the
site and read it. They shall have to select “Enrollment” and
complete the “Supplier Registration Form” by filling in all the
information correctly. Kindly remember the login id,
password entered therein. After you complete this process,
system will generate an e-mail wherein a system generated
“Challenge Phrase” will be mailed to you to complete
balance registration process.
TO NOTE
2.10.3 As a pre-requisite for participation in the tender, vendors
are required to obtain a valid Digital Certificate of Class IIB
and above as per Indian IT Act from the licensed Certifying
Authorities operating under the Root Certifying Authority of
India (RCIA), Controller of Certifying Authorities (CCA). The
cost of obtaining the digital certificate shall be borne by the
tenderer. In case any tenderer so desires, he may contact
our e-procurement service provider M/s. C1 India Pvt. Ltd.,
Mumbai (Contact no. 022-66865600) for obtaining the
digital signature certificate. Please note that generally, it
takes 5 working days for obtaining a digital certificate after
the submission of all required documents / fees. Non
availability of Digital Certificate shall be considered as the
vendor’s regret.
TO NOTE
Page 8
SNO INSTRUCTIONS VENDOR'S ACTION RESPONSE
GENERAL INSTRUCTION TO BIDDERS
2.10.4 Corrigendum/ amendment, if any, shall be notified on the
site https://bpcl.eproc.in. In case any
corrigendum/amendment is issued after the submission of
the bid, then such tenderers who have submitted their bids,
shall be intimated about the corrigendum/amendment by a
system-generated email. No written communication will be
circulated. It shall be assumed that the information
contained therein has been taken into account by the
tenderer. They have the choice of making changes in their
bid before the due date and time
TO NOTE
2.10.5 Tenderers are required to submit their bid online on or
before the due date and time of closing of the tender as
depicted in this document. Tenderers shall have to log on to
the website (https://bpcl.eproc.in) for submitting their bid.
The system time (IST) that will be displayed on e-
Procurement web page shall be the time considered for
determining the expiry of due date and time of the tender
and no other time shall be taken into cognizance.
Tenderers are advised in their own interest to ensure that
their bids are submitted in e-Procurement system well
before the closing date and time of bid. If the tenderer
intends to change/revise the bid already entered, he may
do so any number of times till the due date and time of
submission deadline. However, no bid can be modified after
the deadline for submission of bids. Once the entire
process of submission of online bid is complete, the
tenderers are required to go to option ‘own bid view’
through dashboard and take the print of the envelope
receipt as a proof of submitted bid.
TO NOTE
2.10.6 Bids / Offers shall not be permitted in e-procurement
system after the due date /time of tender. Hence, no bid
can be submitted after the due date and time of submission
has elapsed
TO NOTE
2.10.7 No manual bids/offers along with electronic bids/offers shall
be permitted
TO NOTE
be permitted2.10.8 Once the /PQ Bid/technical (or) un-priced bids are opened,
vendors can see the list of tenderers who have participated
in the bid by logging on to the portal under their user ID and
password and clicking on “Other Bids” view. Subsequently,
in case the price bids are opened in E Tendering platform,
tenderers can see the rates quoted by all the participating
bidders using the same option
TO NOTE
2.10.9 No responsibility will be taken by BPCL and/or the e-
procurement service provider for any delay due to
connectivity and availability of website. They shall not have
any liability to tenderers for any interruption or delay in
access to the site irrespective of the cause. It is advisable
that tenderers who are not well conversant with e-tendering
procedures, start filling up the tenders much before the due
date /time so that there is sufficient time available with
him/her to acquaint with all the steps and seek help if they
so require. Even for those who are conversant with this
type of e-tendering, it is suggested to complete all the
activities ahead of time. It should be noted that the
individual bid becomes viewable only after the opening of
the bid on/after the due date and time. Please be reassured
that your bid will be viewable only to you and nobody else till
the due date/ time of the tender opening. The non
availability of viewing before due date and time is true for e-
tendering service provider as well as BPCL officials.
TO NOTE
2.10.10 BPCL and/or the e-procurement service provider shall not
be responsible for any direct or indirect loss or damages
and or consequential damages, arising out of the bidding
process including but not limited to systems problems,
inability to use the system, loss of electronic information etc.
TO NOTE
2.10.11 In case of any clarification pertaining to e-procurement
process, the tenderer may contact the following agencies /
personnel1. For system related queries: M/s C1 India at contact
nos.022-66865600.
2. For tender related queries: M/s BPCL as indicated at
Clause 1.3.1
TO NOTE
Page 9
Annexure 2A The Declaration should be produced on Vendor’s Letter Head.
PROFORMA OF DECLARATION OF HOLIDAY LISTING In the case of a Proprietary Concern: I hereby declare that neither I in the name of my Proprietary concern M/s. ______________ which is submitting the accompanying Bid / Tender nor any other concern in which I am a proprietor nor in any partnership firm in which I am involved as a Managing Partner have been placed on holiday list declared by Bharat Petroleum Corporation Limited except as indicated below: (Here given particulars of holiday listing and in absence thereof state “NIL”). In the case of a Partnership Firm We hereby declare that neither we, M/s. __________________ submitting the accompanying Bid / Tender nor any partner involved in the management of the said firm either in his individual capacity or as proprietor of any firm or concern have or has been placed on holiday list declared by Bharat Petroleum Corporation Limited except as indicated below: (Here given particulars of holiday listing and in absence thereof state “NIL”). In the case of Company We hereby declared that we have not been placed on any holiday list declared by Bharat Petroleum Corporation Limited except as indicated below: (Here given particulars of holiday listing and in absence thereof state “NIL”). It is understood that if this declaration is found to be false in any particular, Bharat Petroleum Corporation Limited shall have the right to reject my / our bid, and, if the bid has resulted in a contract, the contract is liable to be terminated. Place: ____________ Signature of the Bidder______________ Date: ____________ Name of the Signatory_______________
(This Section to be enclosed with PQ Bid) Page 1
SNO INSTRUCTIONS VENDOR'S ACTION RESPONSE
Pre-Qualification Criteria: Bidder shall meet the following criteria
1.0 Technical Criteria:
1.1 Bidder shall have his own manufacturing unit for
supply of pipes.
NOTED & CONFIRMED
1.2 The Bidder shall have successfully completed
supply of carbon Steel Pipes as per IS/ASTM
standards to any Process Industry/Government
Department/ Quasi Government bodies in any of
the previous three years up to 31/3/2012,the
combined order value of the same in any one of
the three years should not be less than Rs. 5
crores.
CONFIRMED & RELEVANT
SUPPORTING DOCUMENT
ENCLOSED
2.0 Financial Criteria:
PRE-QUALIFICATION CRITERIA
ANNEXURE-2
M/s __________________________________(Bidder)
Signature : ___________________________
Name : ___________________________
BHARAT PETROLEUM CORPORATION LIMITED
(Mumbai Refinery )
Enquiry/CPRFQ No. : 1000166569
E mail ID:____________________________
Offer No./Dt ____________________(Bidder’s Ref.)
Tel. No. : _________________________
Fax No. : ___________________________ Official Seal : ___________________________
2.1 The turnover of the bidder during any of the
precedding three financial years up to 2011-
2012 should be minimum of Rs.11 Crores.
CONFIRMED & RELEVANT
SUPPORTING DOCUMENT
ENCLOSED
2.2 The financial net worth of the bidder shall be
positive as per latest audited annual report.
CONFIRMED & RELEVANT
SUPPORTING DOCUMENT
ENCLOSED
2.3 The Bidder should not be on holiday list of
BPCL.
NOTED & CONFIRMED
3.0 Bidders to Note the following:
3.1 The bidder alongwith the bid shall furnish
documentary evidence at the first instance itself
to substantiate their claim meeting the
requirement specified in pre qualification
criteria.Qualification may be completed based
on the details so furnished without seeking any
subsequent additional information.
NOTED & CONFIRMED
3.1 Even though bidder meets all the criteria
mentioned above, BPCL reserves the right to
assess the Bidder’s capability and capacity to
perform the job, in the overall interest of BPCL
and BPCL can reject the bid(s) at any time
without assigning any reason and without
incurring any liability to the affected bidders(s).
NOTED & CONFIRMED
Page 1
SNO INSTRUCTIONS VENDOR'S ACTION RESPONSE
PRE-QUALIFICATION CRITERIA
4.0 Bidders to submit the following Documents
along with the PQ Bid:
4.1 The Bidder shall submit copies of valid
purchase orders of pipes supplied in the
bidder’s own name as documentary evidence to
substantiate the requirements of the technical
criteria.
NOTED & RELEVANT
SUPPORTING DOCUMENT
ENCLOSED
4.2 The Bidder shall submit latest audited Balance
Sheet , financial statements including Profit &
Loss Accounts for last 3 financial years ending
upto 2011-12.
NOTED & RELEVANT
SUPPORTING DOCUMENT
ENCLOSED
Page 2
SNO INSTRUCTIONSVENDOR
RESPONS RESPONSE
SPECIAL TERMS & CONDITIONS
Fax No. : _________________________ Official Seal : _________________________
Tel. No. : _________________________
VENDORS SHALL FILL THIS QUESTIONNAIRE GIVING THEIR CONFIRMATION FOR ALL SPECIAL
TERMS & CONDITIONS, AS CALLED FOR IN EACH CLAUSE AND ENCLOSE THE SAME WITH THE UN-
PRICED BID. VENDOR MAY INDICATE “NOTED”, “ACCEPTED”, “CONFIRMED” OR SPECIFY
DEVIATIONS / DETAILS, ETC. AS REQUIRED IN THE REMARKS AGAINST IN EACH SPECIFIC
CLAUSE. NOTE THAT NO PRICE INDICATIONS ARE TO BE GIVEN IN THIS FORMAT. EACH PAGE
SHALL BE DULY SIGNED AND STAMPED BY THE VENDOR.
ANNEXURE-3
M/s ________________________(Bidder)
Signature : ___________________________
Name : ______________________________
BHARAT PETROLEUM CORPORATION LIMITED
(Mumbai Refinery )
Enquiry /CPRFQ No. : 1000166569
Offer No./Dt __________________ (Bidder’s Ref.)
E1.1 This is a Three Part Bid Tender, viz.
"Prequalification,un priced Bid and Priced-Bid.
The Bidders shall submit details required for each
type of Bid, as specified. Only those vendors
found acceptable in pre qualification ,shall be
considered for unpriced Bid.Only those vendors
found technically acceptable, shall be considered
for commercial evaluation. Accordingly, Priced
Bids of the techno-commercially qualified
vendors will only be opened for further evaluation.
All documents / Bids submitted shall be digitally
signed and sealed for authentication.
NOTE AND
CONFIRM
1.2 BPCL reserves the right to decide the tender,
based on the ‘Sealed Price Bid’ submitted by the
Bidder with their offer OR by conducting ‘Reverse
Auction’ (RA), with only the ‘techno-commercially
accepted Bidders’ after evaluation of the
Technical Bid. The Bidders should submit their
best prices in the ‘Sealed Priced bid’, however it
may be noted that in case BPCL opts for ’RA’, the
‘Sealed Price Bid’ submitted by the Bidder shall
not be opened. For conducting the RA, the
‘Opening / Start bid price’ and subsequent
‘Decrement value’ shall be specified by BPCL,
based on BPCL’s internal estimation process,
prior to the RA. As a prerequisite, all Bidders shall
have to confirm their compliance with the
‘Business Rule Document governing RA’
furnished at Annexure 17.
NOTE AND
CONFIRM
Page 1
SNO INSTRUCTIONSVENDOR
RESPONS
E
RESPONSE
SPECIAL TERMS & CONDITIONS
1.3 All the items in the Price bid format shall be
considered for evaluation. BPCL reserves the
right to place order for all tendered items or part
of the items .However individual item quantity
shall not be split.
NOTE AND
CONFIRM
1.4 The supply of pipe required shallbe as per BPCL
specification as detailed in specification enclosed
as Annexure -4 and 4A.
NOTE AND
CONFIRM
1.5 DELIVERY SCHEDULE: Indian Bidders shall
deliver all the pipes at the BPCL Kochi i
Refinery ,India at the earliest, but , in any case
not later than 4 months from the date of LOI /
Purchase Order. For Non Indian Bidder, FOB
delivery shall be at the earliest, but, in any case
not later than 3 months from the date of LOI /
Purchase Order and CFR delivery shall be at the
earliest, but, in any case not later than 4 months
from the date of LOI / Purchase Order.
NOTE AND
CONFIRM
1.6 Transit insurance/Marine Insurance: It shall be
excluded from suppliers’ scope for the items
where only supply involved and the same shall be
arranged by the owner.
NOTE AND
CONFIRM
1.7 Transportation in India by theBidders:
1.7.1 Transportation for Indian Bidder:
1.7.1.1 Indian Suppliers shall quote firm freight charges
up to destination by road on freight pre-paid
door delivery basis through bank approved
transporters for all cases. If a supplier does not
quote freight charges, his offer shall beliable for
rejection.
NOTE AND
CONFIRM
1.7.2 Transportation for Non Indian Bidders
1.7.2.1
Ocean/Air transportation from FOB/ FCA Port of
Exit to Designated Indian Port/ Airport shall be
arranged by BPCL through their nominated
freight forwarder. Bidder shall arrange handing
over the material to BPCL freight forwarder at the
designated port of exit.
NOTE AND
CONFIRM
1.7.2.1 In cases where the NIT/CRFQ requires bidder to
quote Ocean/Air freight, BPCL reserves the right
to ask the bidder to arrange shipment through
bidders own freight forwarder at the quoted
freight depending on the approval from
chartering wing of the Ministry of Surface
Transport, New Delhi.
NOTE AND
CONFIRM
Page 2
SNO INSTRUCTIONSVENDOR
RESPONS
E
RESPONSE
SPECIAL TERMS & CONDITIONS
1.8 SHIPMENT, HANDLING, PACKAGING AND
TRANSPORTATION: The bidder shall be
responsible for the handling and transportation of
the supplied material at the sites as specified.
Packing and Marking of the goods to be supplied
shall be the responsibility of the Bidder and shall
be such as to protect the material from damages
due to transportation. All goods shall be packed in
suitable manner to avoid damage to the material
during transit and storage in accordance with best
commercial practices and requirements of
application specifications. The materials for
packaging, packing, shall be of recognized brands
and shall conform to best standards in the areas
in which the articles are packed. The packing shall
protect the material from impact, vibration, static
SPECIFICATION FOR IS 3589 CARBON STEEL PIPES FOR PR NO: 12950679 and PR
NO: 13072753.
1. SCOPE This specification covers carbon steel pipes of various sizes for use in refinery. The pipe shall correspond to IS 3589 and meet requirements of this specification and technical notes for IS 3589 pipes. 2. MATERIAL DESCRIPTION IN DETAIL
Applicable specification: (1) Technical notes for IS 3589 pipes. (2) Inspection and test plan for
welded pipes as per standard specification no: 6-81-0002 Rev.2.
********************************
TECHNICAL NOTES FOR IS 3589 PIPES
1.0 GENERAL
1.1 All pipes and their dimensions, tolerances, chemical composition, physical properties,
heat treatment, hydro test and other testing and marking requirements shall confirm to the
IS 3589 (latest) code and standards specified in the material requirements (MR).Vendors
shall strictly comply with Technical specification and no deviation shall be permitted.
1.2 TESTING
1.2.1 Test reports shall be supplied for all mandatory tests as per the applicable material
standard.
1.2.2 Material test certificates (physical property, chemical composition & heat treatment
report) shall also be furnished for the pipes supplied.
1.3 MANUFACTURING PROCESS
1.3.1 Steel made by acid Bessemer process shall not be acceptable.
1.3.2 The pipes shall be manufactured from plates and shall have only longitudinal continuous
welding.
1.4 Pipes shall be supplied in single random length of 5 to 7 meters. (Larger lengths of 6 to 7
meters preferable).
1.5 Pipes shall not have any circumferential seam joint in a random length.
1.6 Pipes shall not have more than one longitudinal seam joint.
1.7 Pipes with bevel ends shall be accordance with ASME B 16.25.
2.0 HYDROSTATIC TEST
2.1 Pipes shall be hydrostatically tested as per IS 3589 (latest) standard/ QAP as per EIL
SPECIFICATION no.6-81-002 Rev.2.
2.2 The mill test pressure shall be as per IS 3589 (latest) standard.
3.0 MARKING AND DESPATCH
3.1 Pipes shall be dry, clean and free from moisture, dirt and loose foreign materials of any
kind.
3.2 Pipes shall be protected from rust & corrosion.
3.3 Rust preventive used on machined surfaces to be welded shall be easily removable with a
petroleum solvent and the same shall not be harmful to welding.
3.4 Both ends of the pipe shall be protected with plastic cover.
4.0 INSPECTION AND TEST PLAN
4.1 Vendor shall provide a QAP as per EIL SPECIFICATION no.6-81-002 Rev.2 and get it
approved from BPCL (KR).
Bidder Name:
Bidder Sign:
Bidder Stamp:
ANNEXURE-5 (CRFQ 1000166569)
DEVIATION FORM (TECHNICAL) Name of vendor: Schedule of Deviations in reference to BPCL SPECIFICATIONS 1. Vendor may give here a consolidated list of technical deviations for all sections of
the SPECIFICATIONS, which for an appropriate offer is considered unavoidable by him.
2. Deviations mentioned elsewhere in the offer shall not be taken cognizance by the COMPANY and any such deviations if indicated elsewhere other than this form will render the offer non-responsive and shall liable to be rejected.
3. Vendor shall state the reasons for the deviations in the `Remark' column. 4. All other clauses of the SPECIFICATIONS (not mentioned in this form) shall be
deemed to be fully complied by the vendor 5. Only the deviations listed herein, in conjunction with the SPECIFICATIONS, shall
constitute the contract requirements for the award of job to the vendor.
Sr. No.
Annexure- No.
Clause No.
Requirement of the BPCL
SPECIFICATIONS
Deviations to the SPECIFICATIONS
Remarks
1 2 3 4 5 6
vendor Signature of the authorized signatory : Name of the authorized signatory : Stamp & Date :
Page:1
M/s ____________________________(Bidder)
Signature : ___________________________
Name : ______________________________
Official Seal : _________________________
SNO INSTRUCTIONS VENDOR'S ACTION RESPONSE
1.0 Indicate Despatch point TO SPECIFY
1.1 Confirm that the Prices shall be FIRM till complete
execution of the order and shall not be subject to
variation on any account.
TO NOTE AND CONFIRM
1.2 All material are subject to inspection by Third Party
Inspection agency(TPI). BPCL nominated third party
Inspection agency will be M/s International Certification
1.4.1 The scope of the vendor includes transportation of all
the supplied items to the respective sites, through Bank
Approved Transporters
TO NOTE AND CONFIRM
1.5 DELIVERY PERIOD
Page 1
SNO INSTRUCTIONS VENDOR'S ACTION RESPONSE
COMMERCIAL CONDITIONS (INDIAN BIDDERS)
1.5.1 Indian Bidders shall deliver all the material to BPCL
Mumbai Refinery site at the earliest, but, in any case
not later than 4 months from the date of LOI / Purchase
Order. The reciept of the material at site shall be
considered as Delivery date for calculation of Price
reduction for delay.
TO NOTE AND CONFIRM
1.6 VALIDITY
1.6.1 Confirm quoted prices are valid for acceptance up to
90 days from the final due date / extended due date of
RFQ/ date of reverse auction as applicable .
TO NOTE AND CONFIRM
Page 2
SNO INSTRUCTIONS VENDOR'S ACTION RESPONSE
COMMERCIAL CONDITIONS (INDIAN BIDDERS)
1.6.2 On account of exigencies, if the bidder is requested to
extend the validity of their offer, the same should be
extended without any deviation including change in
price.
TO NOTE AND CONFIRM
1.6.3 Confirm quoted prices shall remain firm and fixed till
complete execution of order. Price Variation shall not
be considered on any account. Confirm compliance.
TO NOTE AND CONFIRM
1.7 PERFORMANCE BANK GUARANTEE
1.7.1 Confirm that you will furnish performance guarantee
bond for 10% of order value by way of Bank
Guarantee in the prescribed format from any
Scheduled Indian Bank as per clause 14 of General
Purchase Conditions (GPC) and as per format of PBG
attached. (Annexure-15)
TO NOTE AND CONFIRM
1.7.2 The PBG should be valid for a period of 24 months
from the date of supply (Guarantee period of 18
months from the date of supply + 6 months claim
lodging period) or 18 months from the date of
commissioning (Guarantee period of 12 months from
the date of commissioning + 6 months claim lodging
period) whichever is earlier. The PBG should be sent to
us directly by your Banker.
TO NOTE AND CONFIRM
1.8 PART ORDER
1.8.1 Part order shall be accepted without any stipulation of
minimum order value/ quantity. (However individual
quantities will not be split)
TO NOTE AND CONFIRM
1.8.2 In case of part order all lumpsum charges quoted extra
if any viz. Documentation, testing,packing, other
charges etc., can be considered on prorata value
TO NOTE AND CONFIRM
charges etc., can be considered on prorata value
basis. Confirm compliance.
1.9 PRICE REDUCTION SCHEDULE
1.9.1 Acceptance to price reduction for delay in delivery
beyond contractually agreed schedule @ ½% of
undelivered order value per week of delay or part
thereof, subject to a ceiling of 5% of total order value
as per Clause No. 20 of BPCL’s GPC.
TO NOTE AND CONFIRM
1.9.2 In case this point is not accepted by the vendor,
loading shall be done as per Clause 1.12.2
TO NOTE AND CONFIRM
1.10 PAYMENT TERMS
1.10.1 For Supply
1.10.1 100% within 30 days shall be paid after receipt and
acceptance of supplies and on submission of all
documents and also after submission of 10%
Performance Bank Guarantee.
TO NOTE AND CONFIRM
1.10.2 In the event of delay in delivery, payment shall be
released after deduction of price reduction mentioned
in 1.9.1 above.
TO NOTE AND CONFIRM
1.10.3 Excise duty, Service Tax shall be released only on
receipt of Cenvatable / vatable copy of corresponding
Invoice.
TO NOTE AND CONFIRM
1.10.4 No initial advance payment along with order shall be
made by Owner against supplies as well as services
(i.e., transportation, erection, site work etc.). If a
supplier insists on the same, the offer shall be rejected.
TO NOTE AND CONFIRM
1.10.5 Performance Bank Guarantee(s) shall be through
Nationalised/ Scheduled bank, as per pro-forma
enclosed.
TO NOTE AND CONFIRM
1.10.6 All payments shall be released as per GPC on receipt
of invoice and all requisite documents, complete in all
respects.
TO NOTE AND CONFIRM
1.10.7 All payments shall be released after receipt of invoice
and all requisite documents, complete in all respects.
TO NOTE AND CONFIRM
Page 3
SNO INSTRUCTIONS VENDOR'S ACTION RESPONSE
COMMERCIAL CONDITIONS (INDIAN BIDDERS)
1.10.8 In case, bidder does not agree to submit the PBG, 10%
payment shall be deducted and withheld till the
guarantee period.
TO NOTE AND CONFIRM
1.10.9 Non submission of Performance Bank Guarantee +
Non acceptance of withholding of 10% payment, Offer
shall be liable for rejection .
TO NOTE AND CONFIRM
1.10.10 All Bank Guarantees will be issued directly to BPCL by
the bank and Bidder shall enclose copy of the same
along with invoice.
TO NOTE AND CONFIRM
1.10.11 Bank charges shall be to respective Accounts TO NOTE AND CONFIRM
1.11 EVALUATION CRITERIA TO NOTE AND CONFIRM
Page 4
SNO INSTRUCTIONS VENDOR'S ACTION RESPONSE
COMMERCIAL CONDITIONS (INDIAN BIDDERS)
1.11.1 Bids shall be evaluated on the basis of landed cost
including Supply,all duties, and taxes, TPI charges
,loading on commercial deviations (if any) less Eligible
credit of Cenvat for supplies and Service Tax for
service portion.
TO NOTE AND CONFIRM
1.12 LOADING CRITERIA FOR COMMERCIAL
DEVIATION: The Indian Bids shall be loaded on
FOT Despatch Point prices.
TO NOTE AND CONFIRM
1.12.1 Deviation on Payment terms :
1.12.1.1 The differential payment terms offered by the vendor as
against our CRFQ terms shall be loaded at the rate of
13.25% for the applicable period.
TO NOTE AND CONFIRM
1.12.2 Deviation on Price Reduction for Delayed
Deliveries (Considering GPC clause of 0.5% per
week of delay- max 5% total order value) :
TO NOTE AND CONFIRM
1.12.2.1 In case the vendor does not accept the delayed
delivery clause or take exceptions to the % rate
mentioned in GPC, loading shall be done to the extent
of maximum of 5% on the total order value or the
differential % not agreed by the supplier
TO NOTE AND CONFIRM
1.12.3 Deviation on Performance Bank Guarantee:
1.12.3.1 If vendor does not accept to furnish Performance Bank
Guarantee, loading will be done for full amount for the
commercial evaluation of your offer.
TO NOTE AND CONFIRM
1.12.3.2 For differential Amount of PBG:Other than 10%: To be
loaded by percentage by which PBG is short of 10%.
TO NOTE AND CONFIRM
1.12.4 Indian taxes / duties:In case a supplier states that
taxes/duties are not applicable at present and will
be charged as applicable at the time of delivery then
his bid shall be loaded by the maximum rate of
taxes/duties applicable.
TO NOTE AND CONFIRM
1.12.5 Any other loading not explicitly covered above but as
required in the opinion of OWNER to bring the offers
on par shall also be considered for evaluation and
comparison.
TO NOTE AND CONFIRM
1.13 Confirm acceptance of BPCL’s `General Purchase
Conditions’ in toto.
TO NOTE AND CONFIRM
1.13.1 Indicate relationship with any of our Directors. TO NOTE AND CONFIRM
1.13.2 You are requested to furnish the following information
for e-payment:
a) Name of the vendor/contractor party
b) Account No. of the party
c) Bank & Branch Name where the above account is
maintained
d) Type of account (current/saving/cash credit A/c)
e) Branch code of the above bank branch
f) The 9 digit MICR code of the above branch (with is
printed in the cheques issued by the Branch available
with the A/c holder
TO NOTE AND CONFIRM
1.13.3 If the items are covered under DGS&D rate contract,
confirm that a copy of rate contract is enclosed with
your offer.
TO SPECIFY
Page 5
SNO INSTRUCTIONS VENDOR'S ACTION RESPONSE
1.1 Confirm that the offer contains firm prices on
FOB International Port of Exit.
TO CONFIRM
1.2 All material are subject to inspection by
Third Party Inspection agency(TPI) Lloyd or
equivelent . Confirm that the firm TPI charges
has been quoted as percentage of the Ex
works price in the format for Taxes,duties
,TPI and freight and this TPI charges shall
remain firm through out the currency of the
contract.
TO NOTE AND CONFIRM
1.3 Indicate International Seaport/Airport of Exit TO SPECIFY
1.4 Confirm that the firm Ocean freight charges
has been quoted as percentage of the Ex
works price for ocean transportation to
Mumbai port in the format for Taxes,duties
TO NOTE AND CONFIRM
ANNEXURE-7
M/s ____________________________(Bidder)
Signature : ___________________________
BHARAT PETROLEUM CORPORATION LIMITED
(Mumbai Refinery )
Enquiry/CRFQ No. :1000166569
Offer No./Dt ____________________ (Bidder’s Ref.)
Tel. No. : _________________________
COMMERCIAL CONDITIONS (NON INDIAN BIDDERS)
Fax No. ___________________________ Official Seal : _________________________
Name : ______________________________
Mumbai port in the format for Taxes,duties
and freight and this freight charges shall
remain firm through out the currency of the
contract.1.5 BPCL reserves the option to place order on
FOB or on CFR (Mumbai Port) basis during
the currency of the contract.
TO NOTE AND CONFIRM
1.6 Service charges to shipping agencies shall be
borne by the vendor if order is converted on
CFR basis.
TO NOTE AND CONFIRM
1.7 Prices quoted must exclude transit insurance
charges from FOB International Port as the
same shall be arranged by the Purchaser.
However, transit insurance charges for inland
transit up to FOB International Port of exit
must be included by you in your prices.
TO NOTE AND CONFIRM
1.8 TAXES & DUTIES
1.8.1 All taxes, duties and levies of any kind
payable upto FOB International Port of exit
shall be borne by the bidder.
TO NOTE AND CONFIRM
1.8.2 Export permit/license if required shall be
Bidder’s responsibility & any expenditure
towards same will be borne by the Bidder.
TO NOTE AND CONFIRM
1.9 DELIVERY PERIOD
1.9.1 In case of order on FOB Basis, the FOB
delivery period for all the material under the
scope of the vendor shall be at the
earliest,but, not later than 3 months from the
date of LOI / Purchase Order. The date of bill
of lading shall be considered as Delivery date
for calculation of Price reduction for delay.
TO NOTE AND CONFIRM
Page 1
SNO INSTRUCTIONS VENDOR'S ACTION RESPONSE
COMMERCIAL CONDITIONS (NON INDIAN BIDDERS)
1.9.2 In case the order is converted to CFR basis,
delivery period for the BPCL Mumbai Refinery
site for allthe material required under the
scope of the vendor shall be at the earliest,
but, not later than 4 months from the date of
LOI / Purchase Order. The reciept of the
supplies at Kochi port shall be considered as
Delivery date for calculation of Price reduction
for delay.
TO NOTE AND CONFIRM
1.9.3 Furnish Country of origin from where the
goods have been offered.
TO SPECIFY
1.9.4 Certificate for Country of Origin shall
accompany the shipping documents
TO NOTE AND CONFIRM
1.10 CURRENCY OF QUOTE
1.8.1 Furnish the currency of quote. TO SPECIFY
1.8.2 Change in currency once quoted will not be
allowed. Confirm compliance.
TO NOTE AND CONFIRM
1.9 VALIDITY
1.9.1 Confirm quoted prices are valid for
acceptance up to up to 90 days from the final
due date of CRFQ / extended due date of
CRFQ/date of RA which ever applicable.
TO NOTE AND CONFIRM
1.9.2 On account of exigencies, if the bidder is
requested to extend the validity of their offer,
the same should be extended without any
deviation including change in price.
TO NOTE AND CONFIRM
1.9.3 Confirm quoted prices shall remain firm and
fixed till complete execution of order. Price
Variation shall not be considered on any
account. Confirm compliance.
TO NOTE AND CONFIRM
1.10 CONSIGNMENT DETAILS
1.10.1 Indicate shipping weight (net and gross) &
volume of the consignment.
TO SPECIFY
1.10.2 Vendor to provide Customs Tariff Number
(BTN Number) of the supplies.
TO SPECIFY
1.11 PERFORMANCE BANK GUARANTEE
1.11.1 Confirm that you will furnish performance
guarantee bond for 10% of order value
(Supply ) by way of Bank Guarantee in the
prescribed format from any Scheduled Indian
Bank as per clause 14 of General Purchase
Conditions (GPC) and as per format of PBG
attached. (Annexure-15)
TO NOTE AND CONFIRM
1.11.2 The PBG should be valid for a period of 24
months from the date of supply (Guarantee
period of 18 months from the date of supply +
6 months claim lodging period) or 18 months
from the date of commissioning (Guarantee
period of 12 months from the date of
commissioning + 6 months claim lodging
period) whichever is earlier. The PBG should
be sent to us directly by your Banker.
TO NOTE AND CONFIRM
1.12 PART ORDER
1.12.1 Confirm acceptance of part order without any
stipulation of minimum order value/ quantity.
(However individual quantities will not be split)
TO NOTE AND CONFIRM
Page 2
SNO INSTRUCTIONS VENDOR'S ACTION RESPONSE
COMMERCIAL CONDITIONS (NON INDIAN BIDDERS)
1.12.2 In case of part order confirm all lumpsum
charges quoted extra if any viz.
Documentation, testing,packing, crating,
handling, FOB charges etc., can be
considered on prorata value basis.
TO NOTE AND CONFIRM
1.13 PRICE REDUCTION SCHEDULE
1.13.1 Acceptance to price reduction for delay in
delivery beyond contractually agreed
schedule @ ½% of undelivered order value
per week of delay or part thereof, subject to a
ceiling of 5% of total order value as per
Clause No. 20 of BPCL’s GPC.
TO NOTE AND CONFIRM
1.13.2 In case this point is not accepted by the
vendor, loading shall be done as per Clause
1.16.2
TO NOTE AND CONFIRM
1.14 PAYMENT TERMS
1.14.1 For Supply
1.14.1.1 100% of the FOB value shall be paid through
an irrevocable letter of credit. The Letter of
credit shall be established only on receipt of
acceptance of BPCL’s Fax of acceptance
/Order along with submission of 10%
Performance Bank Guarantee.
TO NOTE AND CONFIRM
1.14.1.2 In the event of delay in delivery, payment
shall be released after making price reduction
from your bills and relevant clause in this
respect shall be inserted in L/C.
TO NOTE AND CONFIRM
1.14.1.3 In case the order is converted to CFR basis
with the transportation also being arranged
and paid by the bidder, the payment shall be
100% of the CFR Value.
TO NOTE AND CONFIRM
1.14.1.4 No initial advance payment along with order TO NOTE AND CONFIRM1.14.1.4 No initial advance payment along with order
shall be made by Owner against supplies as
well as services (i.e., transportation,etc.). If a
supplier insists on the same, the offer shall be
rejected.
TO NOTE AND CONFIRM
1.14.1.5 All Bank Guarantee(s) shall be issued through
Nationalised / Scheduled bank in India as per
pro-forma enclosed. All Bank Guarantees will
be issued directly to BPCL by the bank. In
case bank guarantee is issued by a branch of
bank situated outside India it should be
countersigned by a Scheduled Indian Bank.
TO NOTE AND CONFIRM
1.14.1.6 All bank charges and stamp duties payable
outside India in connection with payments
shall be borne by Supplier. All bank charges
and stamp duties payable in India shall be
borne by BPCL except L/C amendment
charges for delays in delivery and
confirmation charges for confirmed L/C shall
be borne by Supplier.
TO NOTE AND CONFIRM
1.14.1.7 In case, bidder does not agree to submit the
PBG, 10% payment shall be deducted and
withheld till the guarantee period.
TO NOTE AND CONFIRM
1.14.1.8 Non submission of PBG + Not accepting
withholding of 10% payment: Offer shall be
liable for rejection .
TO NOTE AND CONFIRM
1.14.1.9 Bidder to provide the bank details, Swift code
etc for the above purposes along with the
unpriced part of the bid
TO NOTE AND CONFIRM
Page 3
SNO INSTRUCTIONS VENDOR'S ACTION RESPONSE
COMMERCIAL CONDITIONS (NON INDIAN BIDDERS)
1.15 EVALUATION CRITERIA
1.15.1 Quoted prices in foreign currency shall be
considered for evaluation. Currency selling
rate as on the date previous to the date of
opening of the price bid shall be considered
for conversion for comparison of the quotes.
TO NOTE AND CONFIRM
1.15.2 Bids shall be evaluated on the basis of landed
cost at site which includesThird party
inspection ,Freight, all taxes and duties, etc
along with Letter of credit opening charges as
applicable, loading on commercial deviations
(if any) less eligible credit for Cenvat for
supplies.
TO NOTE AND CONFIRM
1.15.2.1 F.O.B. Price:As quoted by the bidder inclusive
of Packing & forwarding charges, inland
freight up to port of exit, Third Party
Inspection charges, etc.
TO NOTE AND CONFIRM
1.15.2.2 Add Ocean freight:Firm freight as quoted by
bidders.
TO NOTE AND CONFIRM
1.15.2.3 Add Marine insurance: @ 0.5% of FOB
price.
TO NOTE AND CONFIRM
1.15.2.4 Add Customs Duty:Prevailing rate on (CIF
value plus Landing Charges @ 1% of CIF
Value).
TO NOTE AND CONFIRM
1.15.2.5 Add Port handling charges:@ 2% of CIF
value.
TO NOTE AND CONFIRM
1.15.2.6 Add Inland freight charges from Port of Entry
in India to project site(s):Percentage of landed
TO NOTE AND CONFIRM
in India to project site(s):Percentage of landed
cost, i.e., S. No. 1 to 5 @1% For KR/MR.
1.15.2.7 Octroi/Entry Tax Charges, If any:Percentage
of landed cost, as applicable, i.e., S. No. 1 to
6.
TO NOTE AND CONFIRM
1.15.2.8 Add L/C and other Charges:@ 1% of FOB
Price.
TO NOTE AND CONFIRM
1.15.2.9 Commercial Loadings, If any:On FOB value. TO NOTE AND CONFIRM
1.15.2.10 Less Cenvatable Duties. TO NOTE AND CONFIRM
1.15.2.11 FOT SITE PRICE:Sum (1 to 9) - less (10) TO NOTE AND CONFIRM
1.16 LOADING CRITERIA FOR COMMERCIAL
DEVIATION: The Foreign Bids shall be
loaded on FOB Port of Exit prices
1.16.1 Deviation on Payment terms :
.1.16.1.1 Foreign suppliers shall not be permitted to
offer differential payment terms as against the
terms specified in the CRFQ/ GPC and in
case they insist, their offer shall be rejected.
TO NOTE AND CONFIRM
1.16.2 Deviation on Price Reduction for Delayed
Deliveries (Considering GPC clause of
0.5% per week of delay- max 5% total order
value) :
1.16.2.1 In case the vendor does not accept the
delayed delivery clause or take exceptions to
the % rate mentioned in GPC, loading shall
be done to the extent of maximum of 5% on
the total order value or the differential % not
agreed by the supplier
TO NOTE AND CONFIRM
Page 4
SNO INSTRUCTIONS VENDOR'S ACTION RESPONSE
COMMERCIAL CONDITIONS (NON INDIAN BIDDERS)
1.16.3 Deviation on Performance Bank
Guarantee:
1.16.3.1 If vendor does not accept to furnish
Performance Bank Guarantee, loading will be
done for full amount for the commercial
evaluation of your offer.
For differential Amount of PBG:Other than
10%: To be loaded by percentage by which
PBG is short of 10%.
Any other loading not explicitly covered above
but as required in the opinion of OWNER to
bring the offers on par shall also be
considered for evaluation and comparison.
GENERAL
1.17 Confirm acceptance of BPCL’s `General
Purchase Conditions’ in toto.
TO NOTE AND CONFIRM
1.18 Indicate relationship with any of our
Directors.
TO SPECIFY
INDIAN AGENT
1.19 Confirm if Indian agent is involved. Please
specify the name and details of the Indian
agent.
TO NOTE,CONFIRM &
SPECIFY
1.19.1 The commission payable to Indian agents, if
any, in Indian Rupees in terms of agreement
(enclosing the copy of the same) shall be paid
as per government guidelines prevailing for
such payments
TO NOTE AND CONFIRM
1.19.2 The commission to be paid to Indian agents
shall be made in Indian Rupees only based
on the exchange rate prevailing on the day of
TO NOTE AND CONFIRM
on the exchange rate prevailing on the day of
price bid opening and would not be subject to
exchange rate variation.
Page 5
SNO INSTRUCTIONS VENDOR'S ACTION RESPONSE
COMMERCIAL CONDITIONS (NON INDIAN BIDDERS)
1.19.3 The tenderers should also furnish the
following particulars of the Indian
agents/associates/and/or the foreign firms.
1) Name & address of the Indian agent, if any.
2) Confirmation that the Indian agent is
registered with the Directorate General of
Supplies & Disposals (DGS&D), New Delhi
(enclosing a copy of their valid registration
certificate).
3) If your Indian agent is not registered with
DGS&D, New Delhi, confirm that they will get
themselves registered with them immediately
and forward a copy of the same.
4) Agency commission payable, if any, shall
be paid in Indian Rupees only after receipt of
material at site subject to furnishing a valid
Registration Certificate from DGS&D, New
Delhi.
5) The precise relationship between the
foreign manufacturer/ principals & their Indian
Agents/Associate;
6) The mutual interests which the
manufacturer/principals and the Indian
agents/associates have in the business of
each other.
7) Any payment which the agent/associate
receives in India or abroad from the
manufacturer/principal whether as a
commission for the contract or as a general
retainer fee
8) Indian agent’s Income Tax PAN.
9) The foreign supplier’s Income Tax PAN
TO SPECIFY
Page 6
ANNEXURE-8
(CRFQ 1000166569) DEVIATION FORM (COMMERCIAL)
Name of vendor: Schedule of Deviations in reference to COMMERCIAL TERMS AND CONDITIONS 1. Vendor may give here a consolidated list of Commercial deviations for all
sections of the tender document, which for an appropriate offer is considered unavoidable by him.
2. Deviations mentioned elsewhere in the offer shall not be taken cognizance by the COMPANY and any such deviations if indicated elsewhere other than this form will render the offer non-responsive and shall liable to be rejected.
3. Vendor shall state the reasons for the deviations in the `Remark' column. 4. All other clauses of the COMMERCIAL TERMS AND CONDITIONS (not
mentioned in this form) shall be deemed to be fully complied by the PCMS vendor
5. Only the deviations listed herein, in conjunction with the COMMERCIAL TERMS AND CONDITIONS, shall constitute the contract requirements for the award of job to the vendor.
Sr. No.
Annexure- No.
Clause No.
Commercial terms and conditions
Deviations Remarks
1 2 3 4 5 6
Vendor Signature of the authorized signatory : Name of the authorized signatory : Stamp & Date :
Page 1
Signature : ______________________
Name : _________________________
Official Seal : ____________________
Vendor shall provide % rates against each item in response column. If any of the conditions are not applicable ve
specify Nil/NA
(Mumbai Refinery )
FORMAT FOR PROVIDING FREIGHT TAXES, DUTIES ETC (INDIAN BIDDERS
S No Commercial conditions description Vendor's Action
2.1.1 P&F Charges (% on Ex works price) Vendor to specify
2.1.2 Excise Duty with Cess (%) Vendor to specify
2.1.3 VAT (%) OR Vendor to specify
2.1.4 CST extra with C Form (%) OR Vendor to specify
2.1.5 CST extra without C Form (%) Vendor to specify
2.1.6 Freight charges including service Tax (%) Vendor to specify
2.1.7 Octroi with Service charges (%) Vendor to specify
2.1.8 Third Party Inspection charges Vendor to specify
2.1.9 Any other charges/Taxes (%) Vendor to specify
specify Nil/NA
Vendor's re
Page 1
M/s ____________________________(Bidder)
Signature : ___________________________
Name : ______________________________
Official Seal : _________________________
S No Commercial conditions description Vendor's Action Vendor's response
2.1.1 P&F Charges (% on Ex works price) Vendor to specify
2.1.2 Inland transportation charges to FOB Port of exit (% on Ex
works price)
Vendor to specify
2.1.3 FOB Charges (% on Ex works price) Vendor to specify
2.1.4 Third Party Inspection Charges (% on Ex Works Price ) Vendor to specify
2.1.5 Ocean Freight Charges (% on Ex works price) Vendor to specify
2.1.6 Any other charges/Taxes (%) Vendor to specify
2.1.7 Any other charges/Taxes (%) Vendor to specify
2.1.8 Any other charges/Taxes (%) Vendor to specify
Fax No. ___________________________
BHARAT PETROLEUM CORPORATION LIMITED
Enquiry /CRFQ No. : 1000166569
FORMAT FOR PROVIDING FREIGHT TAXES, DUTIES ETC (NON INDIAN BIDDERS).Vendor shall provide % rates against each item in response column. If any of the conditions are not applicable vendor to specify Nil/NA
…………………………………………………………………………………………….. hereinafter referred to as "The Bidder/ Contractor/ Supplier".
PPrreeaammbbllee
The Principal intends to award, under laid down organization procedures, contract/s for ……………………………………………………………………………………………………………………….… . The Principal values full
compliance with all relevant laws and regulations, and the principles of economic use of resources, and of fairness and transparency in its relations with its Bidder/s, Contractor/s and Supplier/s.
(1) The Principal commits itself to take all measures necessary to prevent corruption and to observe the following principles:
a) No employee of the Principal, personally or through family members, will in connection
with the tender, or the execution of the contract, demand, take a promise for or accept, for himself/ herself or third person, any material or immaterial benefit which he/she is not legally entitled to.
b) The Principal will, during the tender process, treat all Bidders with equity and reason. The
Principal will, in particular, before and during the tender process, provide to all Bidders the same information and will not provide to any Bidder confidential/ additional information through which the Bidder could obtain an advantage in relation to the tender process or the contract execution.
c) The Principal will exclude from the process all known prejudiced persons.
(2) If the Principal obtains information on the conduct of any of its employees which is a criminal offence under the relevant Anti-Corruption Laws of India, or if there be a substantive suspicion in this regard, the Principal will inform its Vigilance Office and in addition can initiate disciplinary actions.
dduurriinngg tthhee eexxeeccuuttiioonn ooff tthhee ccoonnttrraacctt.. b) The Bidder/ Contractor/ Supplier will not enter with other Bidders into any undisclosed
agreement or understanding, whether formal or informal. This applies in particular to prices, specifications, certifications, subsidiary contracts, submission or non-submission of bids or any other actions to restrict competitiveness or to introduce cartelisation in the bidding process.
c) The Bidder/ Contractor/ Supplier will not commit any offence under the relevant Anti-
Corruption Laws of India; further the Bidder/ Contractor/ Supplier will not use improperly, for purposes of competition or personal gain, or pass on to others, any information or document provided by the Principal as part of the business relationship, regarding plans, technical proposals and business details, including information contained or transmitted electronically.
d) The Bidder/ Contractor/ Supplier will, when presenting his bid, disclose any and all
payments he has made, is committed to, or intends to make to agents, brokers or any other intermediaries in connection with the award of the contract.
(2) The Bidder/ Contractor/ Supplier will not instigate third persons to commit offences outlined
above or be an accessory to such offences.
Section 3 - Disqualification from Tender Process and Exclusion from Future Contracts
IIff tthhee BBiiddddeerr,, bbeeffoorree ccoonnttrraacctt aawwaarrdd,, hhaass ccoommmmiitttteedd aa ttrraannssggrreessssiioonn tthhrroouugghh aa vviioollaattiioonn
tteerrmmiinnaattee tthhee ccoonnttrraacctt,, iiff aallrreeaaddyy ssiiggnneedd,, ffoorr ssuucchh rreeaassoonn.. (1) If the Bidder/ Contractor/ Supplier has committed a transgression through a violation of Section
2 such as to put his reliability or credibility into question, the Principal is also entitled to exclude the Bidder/ Contractor/ Supplier from future contract award processes. The imposition and duration of the exclusion will be determined by the severity of the transgression. The severity will be determined by the circumstances of the case, in particular the number of transgressions, the position of the transgressors within the company hierarchy of the Bidder and the amount of the damage. The exclusion will be imposed for a minimum of 6 months and maximum of 3 years.
(2) A transgression is considered to have occurred if the Principal after due consideration of the
available evidences, concludes that no reasonable doubt is possible. (3) The Bidder accepts and undertakes to respect and uphold the Principal's absolute right to
resort to and impose such exclusion and further accepts and undertakes not to challenge or question such exclusion on any ground, including the lack of any hearing before the decision to resort to such exclusion is taken. This undertaking is given freely and after obtaining independent legal advice.
Page 3
(4) If the Bidder/ Contractor/ Supplier can prove that he has restored/ recouped the damage
caused by him and has installed a suitable corruption prevention system, the Principal may revoke the exclusion prematurely.
(1) If the Principal has disqualified the Bidder from the tender process prior to the award according to Section 3, the Principal is entitled to demand and recover from the Bidder liquidated damages equivalent to Earnest Money Deposit/Bid Security.
(2) If the Principal has terminated the contract according to Section 3, or if the Principal is entitled
to terminate the contract according to Section 3, the Principal shall be entitled to demand and recover from the Contractor/ Supplier liquidated damages equivalent to Security Deposit/ Performance Bank Guarantee.
(3) The Bidder agrees and undertakes to pay the said amounts without protest or demur subject
only to condition that if the Bidder/ Contractor/ Supplier can prove and establish that the exclusion of the Bidder from the tender process or the termination of the contract after the contract award has caused no damage or less damage than the amount of the liquidated damages, the Bidder/ Contractor/ Supplier shall compensate the Principal only to the extent of the damage in the amount proved.
(1) The Bidder declares that no previous transgression occurred in the last 3 years with any other Company in any country conforming to the TI approach or with any other Public Sector Enterprise in India that could justify his exclusion from the tender process.
(2) If the Bidder makes incorrect statement on this subject, he can be disqualified from the tender
process or the contract, if already awarded, can be terminated for such reason.
Section 6 - Equal treatment of all Bidders/ Contractors/ Suppliers/
SSuubbccoonnttrraaccttoorrss
(1) The Bidder/ Contractor/ Supplier undertakes to demand from all subcontractors a commitment in conformity with this Integrity Pact, and to submit it to the Principal before contract signing.
(2) The Principal will enter into agreements with identical conditions as this one with all Bidders,
Contractors/ Suppliers and Subcontractors. (3) The Principal will disqualify from the tender process all Bidders who do not sign this Pact or
violate its provisions.
Section 7 - Punitive Action Against Violating Bidders/ Contractors/
(1) The Principal has appointed competent and credible Independent External Monitors for this Pact. The task of the Monitor is to review independently and objectively, whether and to what extent the parties comply with the obligations under this agreement.
(2) The Monitor is not subject to instructions by the representatives of the parties and performs his
functions neutrally and independently. He reports to the Chairperson of the Board of the Principal.
(3) The Bidder/ Contractor/ Supplier accepts that the Monitor has the right to access without
restriction to all Project documentation of the Principal including that provided by the Bidder/ Contractor/ Supplier. The Bidder/ Contractor/ Supplier will also grant the Monitor, upon his request and demonstration of a valid interest, unrestricted and unconditional access to this project documentation. The same is applicable to Subcontractors. The Monitor is under contractual obligation to treat the information and documents of the Bidder/ Contractor/ Supplier/ Subcontractor with confidentially.
(4) The Principal will provide to the Monitor sufficient information about all meetings among the
parties related to the Project provided such meetings could have an impact on the contractual relations between the Principal and the Bidder/ Contractor/ Supplier. The parties offer to the Monitor the option to participate in such meetings.
(5) As soon as the Monitor notices, or believes to notice, a violation of this agreement, he will so
inform the Management of the Principal and request the Management to discontinue or heal the violation, or to take other relevant action. The Monitor can in this regard submit non-binding recommendation. Beyond this, the Monitor has no right to demand from the parties that they act in a specific manner, refrain from action or tolerate action. However, the Independent External Monitor shall give an opportunity to the Bidder/ Contractor/ Supplier to present its case before making its recommendations to the Principal.
(6) The Monitor will submit a written report to the Chairperson of the Board of the Principal within 8
to 10 weeks from the date of reference or intimation to him by the 'Principal' and, should the occasion arise, submit proposals for correcting problematic situations.
(7) If the Monitor has reported to the Chairperson of the Board a substantiated suspicion of an
offence under relevant Anti-Corruption Laws of India, and the Chairperson has not, within reasonable time, taken visible action to proceed against such offence or reported it to the Vigilance Office, the Monitor may also transmit this information directly to the Central Vigilance Commissioner, Government of India.
(8) The word 'Monitor' would include both singular and plural.
SSeeccttiioonn 99 -- PPaacctt DDuurraattiioonn
This Pact begins when both parties have legally signed it. It expires for the Contractor/ Supplier 12 months after the last payment under the respective contract, and for all other Bidders 6 months after the contract has been awarded. If any claim is made/ lodged during this time, the same shall be binding and continue to be valid despite the
lapse of this pact as specified above, unless it is discharged/ determined by Chairperson of the Principal.
nnoott bbee aapppplliiccaabbllee ffoorr aannyy iissssuuee// ddiissppuuttee aarriissiinngg uunnddeerr IInntteeggrriittyy PPaacctt.. (2) Changes and supplements as well as termination notices need to be made in writing. Side
agreements have not been made. (3) If the Bidder/ Contractor/ Supplier is a partnership or a consortium, this agreement must be
signed by all partners or consortium members. (4) Should one or several provisions of this agreement turn out to be invalid, the remainder of this
agreement remains valid. In this case, the parties will strive to come to an agreement to their original intentions.
……………………… …………………………… For the Principal For the Bidder/ Contractor/
Supplier Place ……………… Witness 1 : ………………
(Signature/Name/Address)
Date ………………. Witness 2 : ……………… (Signature/Name/Address)
M/s. Phone No. : Fax No. : Company Website: Intimated later
Date & Time of Auction
Auction Date : Will be intimated later Online Reverse Auction Time : Will be intimated later (**Limited/ Unlimited extensions ) Auction Website: Will be intimated later
Documents Attached
1) Business rule for reverse auction 2) Terms & conditions of reverse auction 3) Online Reverse Auction Schedule (Appendix – I) 4) Process Compliance Statement (Appendix – II) 5) Price Confirmation (Appendix – III) 6) Contact Information
SPECIAL INSTRUCTIONS
Bidding in the last minutes and seconds should be avoided in the bidders own interest. Neither BPCL nor Service Provider will be responsible for any lapses / failure on the part of the bidder, in such cases.
BUSINESS RULES FOR ON LINE REVERSE AUCTION
Page 2 of 10
GENERAL TERMS & CONDITIONS
Against this Enquiry for the subject item/system with detailed scope of supply as per our specification, BPCL, CPO Refineries, Mumbai may resort to “Online Reverse Auction Mode” i.e. ONLINE BIDDING on INTERNET.
1. For the proposed Reverse Auction, technically and commercially acceptable bidders only shall be eligible to participate.
2. BPCL has engaged the services of a Service Provider, who will provide all necessary training and assistance before commencement of on line bidding on Internet.
3. BPCL will inform the bidders in writing, the details of the Service Provider in case of Reverse Auction, so as to enable them to contact the Service Provider and get trained.
4. Information like the Business rules, Reverse Auction event date, time, start price, bid decrement, extensions, etc. also will be communicated through the Service Provider for the compliance of the bidders.
5. Bidders have to email a scanned copy of the Process Compliance Form (Appendix - II) in the prescribed (provided by service provider) before start of Online Reverse Auction. Without this Compliance form, the bidders will not be eligible to participate in the online event.
6. BPCL will provide the calculation sheet (e.g.: EXCEL sheet) which will help to arrive at “total effective Cost to BPCL” for each the bidders to enable them to fill-in the price and keep it ready for keying in during the Reverse Auction.
7. Online Reverse Auction will be conducted on schedule date & time.
8. At the end of Reverse Auction event, the lowest bidder value will be known on the network for each item at each location.
9. The lowest bidder has to email a scanned copy of the price break-up duly signed, filled in prescribed format (as per BPCL’s price excel sheet format), as provided on case-to-case basis, to BPCL through Service Provider within 24 hours of the Reverse Auction without fail.
10. Any variation between the on-line bid value and signed document will be considered as sabotaging the tender process and will invite disqualification of bidder to conduct business with BPCL as per prevailing procedure.
11. Bidders shall note that in case BPCL conducts the Reverse Auction and finalizes this tender, the Sealed Priced-Bids submitted with the offer will not be opened.
12. In case BPCL decides not to conduct Reverse Auction, the Sealed Priced-Bids submitted with the offer, along with price impacts (if any) already available with BPCL, shall be opened as per BPCL standard practice for finalization of the tender.
13. Similarly, if for any unforeseen reason the Reverse Auction is conducted by BPCL for this particular tender and the results are found to be inconclusive by BPCL, then BPCL may open the Sealed Priced-Bids submitted with the offer, along with price impacts (if any) already available with BPCL, and finalize the tender as per BPCL standard practice.
14. Only those vendors, who submit their Process Compliance Form, will be eligible to participate in the Online English Reverse Auction.
15. The Reverse Auction will be treated as closed only when the bidding process gets closed in all respects for the items listed in the tender.
BUSINESS RULES FOR ON LINE REVERSE AUCTION
Page 3 of 10
MODALITY FOR FINALIZATION OF THE PROCUREMENT BPCL may finalize the procurement of the item against this Tender through online Reverse Auction mode. BPCL shall make arrangement with. (Name of the Service Provider), who shall be BPCL’s authorized Service Provider(SP) for the same. Please go through the guidelines given below and submit your acceptance to the same along with your Commercial Bid. 1. Computerized reverse auction shall be conducted by BPCL, on pre-specified date, while
the vendors shall be quoting from their own offices / place of their choice. Internet connectivity & other necessary requirements like power backup etc. shall have to be ensured by vendors themselves. In order to ward-off such contingent situation where the vendors are not able to bid for any of the above reason, they are requested to make all the necessary arrangements / alternatives whatever required so that they are able to circumvent such situation and still be able to participate in the reverse auction successfully. Failure of power / problem in Internet connectivity at the premises of vendors during the Online Reverse auction cannot be the cause for not participating in the reverse auction. On account of this, the time for the auction cannot be extended and neither BPCL nor SP is responsible for such eventualities.
2. Service provider shall arrange to train your nominated person (s), without any cost to you. They shall also explain you, all the Rules related to the Reverse Auction / Business Rules to be adopted along with the calculation sheet in excel format. You are required to give your compliance on it at least 24 hours before the start of bid process.
3. Material for Bid: Respective CRFQ No._____
4. Starting price & Bid Decrement: The start price applicable in the Online Reverse Auction for described item shall be visible to all bidders on their screen. (i.e. Starting basic Cost and bid decrement value will be displayed). This start price will be derived through BPCL’s internal estimation processes.
5. Bidding Currency & Unit of Measurement: Bidders will enter price in their respective currency while evaluation will be conducted in Indian Rupees (INR) & the Unit of Measurement will be per Meter The price bid placed during the Online Reverse Auction shall be the price of respective CRFQ.
6. Bid Price: The Bidder has to quote as per excel sheet provided by BPCL.
The bidders are requested to note that the ranking would be generated on the condition that the bid submitted by the bidder is confirming to the Starting price & Minimum Decrement Value.
Calculation sheet in excel format to arrive at the Total Effective Cost to BPCL will be provided by Service provider.
7. The technical & commercial terms are as per respective CRFQ , Vendors’ technical and commercial bid and subsequent correspondences between BPCL and the vendors regarding commercial terms & conditions.
8. Validity of Bids: As per BPCL respective CRFQ doc. & agreed terms 9. Delivery: As per BPCL Respective CRFQ doc. & agreed terms
BUSINESS RULES FOR ON LINE REVERSE AUCTION
Page 4 of 10
10. At the end of the reverse auction, bidder has to provide a detailed break-up (as per BPCL’s price excel sheet format) to SP for his lowest accepted offer quoted during the Online Reverse Auction within 24 hours of the completion of the Online Reverse Auction.
11. Procedure of Online Reverse Auctioning:
i. Online English Reverse Auction: BPCL will declare its Start price, which shall be visible to the all vendors during the start of the Online Reverse Auction on their respective bidding screens. Please note that the start price of Online Reverse Auction is open to all the participating bidders. Any bidder can start bidding, in the Online Reverse Auction; from the start price itself. On submission of the bid, the rank would be generated for the item. Also, please note that the first online bid that comes in the system during the Online Reverse Auction can be equal to the auction's start price, or lesser than the auction's start price or by at least one decrement, or lesser than the same. The second online bid for any particular item and onwards which the bidder submits will have to be lesser than the respective bidder’s previous bid by at least one decrement value, or lesser than the same. Decrement in multiple would be “No”.
ii. Online English Reverse Auction shall be for a period of 45 minutes. If a bidder places a Bid in the last 5 minutes of Closing of the Auction, the auction shall get extended automatically for another 5 minutes. So, reverse auction will be continued till bid comes in last remaining 5 min. In case, there is no Bid in the last 5 minutes of closing of Auction, the Auction shall get closed automatically without any extension.
iii. After the completion of Online Reverse Auction, the Closing Price shall be available for further processing.
12. Successful vendor shall be required to submit the final prices, quoted during the Online
Reverse Auction, as per BPCL’s price excel sheet format, after the completion of Auction to SP, within 24 hours of the reverse auction, duly signed and stamped on their letterheads as token of acceptance without any new condition other than those already agreed to before start of auction. The Original Copy of the Price Breakup (as per excel sheet) & Price Confirmation (appendix III) should be submitted to the Service provider within 3 days of the completion of the Online Reverse Auction.
13. During the Online Reverse Auction, if no bid is received in the auction system / website
within the specified time duration of the reverse auction, then BPCL at its discretion, may decide to revise the auction's Start Price / scrap the online reverse auction process / proceed with the conventional mode of tendering / any other method as deem fit. The decision of BPCL in this regard will be final & binding on all the vendors.
14. Your bid will be taken as an offer to supply. Bids once made by you, cannot be
cancelled / withdrawn and you shall be bound to supply as mentioned above at your final bid price. Should you back out and not supply as per the rates quoted, BPCL shall take action as appropriate.
15. Login Name & Password: Each Bidder is assigned a Unique User Name & Password by
Service Provider. You are advised to change the Password and edit the information in the Registration Page after the receipt of initial Password from Service provider to ensure confidentiality. All bids made from the Login ID given to you will be deemed to have been made by your company
BUSINESS RULES FOR ON LINE REVERSE AUCTION
Page 5 of 10
16. Visibility to the Bidder: The respective bidder will be able to view the following on their screen along with the necessary fields in the Online Reverse Auction:
a. Bid Placed by you. b. Your Own Rank. c. Start Price & Minimum Bid Decrement value. d. Least Effective Cost(L1) of reverse auction quoted by the bidder
17. Lowest Bid of a Bidder: In case the bidder submits more than one bid, the lowest accepted bid will be considered as the bidder’s final offer to execute the work.
18. At the end of the Reverse Auction, BPCL will decide upon the successful bidder. BPCL’s
decision on award of Contract shall be final and binding on all the Bidders. 19. BPCL shall be at liberty to cancel the Online Reverse Auction process / tender at any
time, before ordering, without assigning any reason. 20. Other terms and conditions shall be as per your techno-commercial offers and other
correspondences till date. 21. You are required to submit your acceptance (Process Compliance Form – (Appendix – II))
before participating in the reverse auction.
22. Auction shall be on final bid basis without consideration of e-sealed price bid
submitted by you in e-bid system. All other terms and conditions shall be as per
the RFQ/ Offer/As agreed upon.
BUSINESS RULES FOR ON LINE REVERSE AUCTION
Page 6 of 10
BIDDERS TO SPECIFICALLY NOTE
1. The Bidder shall not involve himself or any of his representatives in Price manipulation of any kind by directly or indirectly communicating with other suppliers / bidders.
2. The Bidder shall not divulge either his Bids or any other exclusive details of BPCL to
any other party.
3. BPCL’s decision on award of Contract shall be final and binding on all the Bidders. Conducting Online Reverse Auction is not binding on BPCL for ordering. BPCL reserve the right for ordering & May / may not order for any / all the lot for which reverse auction is being held.
4. BPCL along with Service provider can decide to extend, reschedule or cancel
Auction. Any changes made by BPCL and / or the Service Provider, after the first posting will have to be accepted if the Bidder continues to access the site after that time.
5. BPCL & Service provider shall not have any liability to Bidders for any interruption
or delay in access to the site irrespective of the cause.
6. BPCL & Service provider are not responsible for any damages, including damages that result from, but are not limited to negligence.
7. BPCL & Service provider will not be held responsible for consequential damages,
including but not limited to systems problems, inability to use the system, loss of electronic information etc.
N.B.
- All the Bidders are required to submit the Process Compliance Form (Appendix - II) duly signed to the Service Provider, at least 24 hours before the auction date. After the receipt of the Process Compliance Form, Login ID & Password shall be allotted to the suppliers (bidders).
- All the bidders are requested to ensure that they have a valid digital certificate well in advance to participate in the online event. Under no circumstances will the bidders be allowed to participate in the online event without Digital Certificate.
- After the completion of the Auction event, all the Bidders have to submit the Price
Break-up (as per BPCL’s price excel sheet format) within 24 hours of the reverse auction to the Service Provider for further proceedings.
BUSINESS RULES FOR ON LINE REVERSE AUCTION
Page 7 of 10
APPENDIX – I The List of Items to be procured along with the Auction Start Time & Close Time is as follows: Item Description: Respective CRFQ No..
Date: - Will be intimated later.
Description Start Time End Time
CRFQ No.
** Auto Extensions as applicable
BUSINESS RULES FOR ON LINE REVERSE AUCTION
Page 8 of 10
APPENDIX – II
PROCESS COMPLIANCE FORM (The bidders are required to print this on their company’s letterhead, sign & stamp before emailing a scanned copy)
To, Service Provider Sub: Agreement to the Process related Terms and Conditions for the Reverse Auction Dear Sir, This has reference to the Business Rules and Terms & Conditions for the Online Reverse Auction mentioned in this document for respective CRFQ for supply of….. This letter is to confirm that:
1) The undersigned is authorized representative of the company. 2) We have studied the Commercial Terms and the Business rules governing the Reverse
Auction as mentioned in your letter and confirm our agreement to them. 3) We also confirm that we have taken the training on the auction tool and have
understood the functionality of the same thoroughly. 4) We have studied the calculation sheet carefully as per our offer submitted to BPCL. We
also confirm that we will email a scanned copy or fax the price break-up of our online quoted price, within 24 hours of the reverse auction, as per BPCL’s price excel sheet format.
5) We confirm that we will send the Original copy of the Price Breakup to Service provider within 3 working days of the completion of the Online Reverse Auction.
6) We, hereby, confirm that we will honor the Bids placed by us during the Online Reverse Auction process.
7) We also confirm that we will accept our Rank / Position that will be displayed when the Bidding Time is over of the Online Reverse Auction.
8) We confirm that we have changed the password on the auction website after first log in.
9) We also confirm that we have a valid digital certificate issued by a valid Certifying Authority.
With regards, Signature with company seal Name –Company / Organization – Designation within Company / Organization – Address of Company / Organization –
BUSINESS RULES FOR ON LINE REVERSE AUCTION
Page 9 of 10
APPENDIX – III
PRICE CONFIRMATION (The bidders are required to print this on their company’s letterhead, sign & stamp before emailing a scanned copy)
To, Service provider Sub: Final price quoted during Online Reverse Auction and Price Break up Ref: respectiva CRFQ No. for supply of…. Dear Sir, We confirm that we have quoted for CRFQ No. for supply of…. As detailed below.
CRFQ Item No. & Description Quoted Basic Value of the material Effective Cost of Material
as our prices during the Online Reverse Auction conducted on : The detailed price break-up as per the BPCL excel sheet format enclosed. Thanking you and looking forward to the valuable order from BPCL. Yours sincerely, For _________________ Name: Company: Date: Seal: