County of Fairfax, Virginia
Board Transportation Committee
Updates on Alternatives for Improving RoadwayServices in Fairfax County
Discussion of Converting the Fairfax County Parkwayand Franconia / Springfield Parkway
from a Secondary Road to Primary Road
9/20/11
County of Fairfax, Virginia
Updates on Alternatives for Improving RoadwayServices in Fairfax County
County of Fairfax, Virginia
Alternatives for Improving Roadway Services
• Thru Truck Studies on Secondary Roads
• No Parking Requests
• Advanced Street Name Signs
• Bus Shelters
• Traffic Signal Construction Funding
• Mowing
County of Fairfax, Virginia
Thru Truck Studies on Secondary Roads
• Approximately six requests processed a year.
• Current process time up to one year
• Process requires Fairfax County to conduct a public hearing and VDOT to either conduct a public hearing or collect public comments
• Would require a Code Change for Fairfax County to take responsibility for the process
• VDOT recommends a phased / interim approach before supporting a Code Change
County of Fairfax, Virginia
Thru Truck Studies on Secondary Roads – Process TimelinesExisting Process – 52 ½ weeks
Interim Process – 27 weeks
Full County Responsibility after Code Change – 17 weeks
County of Fairfax, Virginia
Thru Truck StudiesThru Truck Studies on Secondary Roads
Advantages
• Reduced process time from 12 + months to 4 to 5 months• Stream line process would only require one public
hearing / public comment period• Local jurisdiction adopts restriction by resolution
Consequences
• Requires additional manpower resources – 0.15 FTE• Requires funding for studies and associated traffic signs - $40,000• Requires VA Code Change for County responsibility of
program
County of Fairfax, Virginia
Staff Recommendations
FCDOT should assume a phased in / interim approach for the responsibility of conducting the necessary evaluation / study for restricting through trucks on the secondary system.
Once VDOT’s interim conditions are satisfied, County should pursue General Assembly action to shift authority for approving through truck restrictions on the secondary system to the County.
County of Fairfax, Virginia
No Parking Requests
• Existing No Parking programs include FCDOT residential permit parking and community parking district programs
• VDOT reviews 350 requests per year. VDOT’s program concentrates on restrictive zones for safety and capacity. Approximately 20% of requests result in the installation of No Parking signs.
• Once initiated, VDOT review time per request averages four hours
• Total VDOT processing time varies depending on backlog of requests
County of Fairfax, Virginia
No Parking Requests
Advantages
• Eliminates confusion by the public on who establishes the different No Parking programs• Places all parking programs under one jurisdiction’s responsibility• Better coordination with enforcement agency
County of Fairfax, Virginia
No Parking Requests
Consequences
• Requires additional manpower resources – 1 FTE• Requires additional funding resources for signs - $10,000• Requires that the Board conduct a public hearing and adopt
a resolution prior to placing restrictions – resulting in extended process timeline – a resolution is not required for
VDOT process• No time savings in overall process• Fairfax County would have to follow adopted standards and guidelines for the establishment of No Parking restrictions
County of Fairfax, Virginia
Staff Recommendation
Existing No Parking Programs remain in place.
Current Code of Virginia allows for the County to regulate parking on the secondary system after an public hearing and Board resolution.
Because of public hearing requirement and current VDOT backlog, unlikely that the County could improve upon current VDOT processing time.
County of Fairfax, Virginia
Advanced Street Name Sign Program
• VDOT has in place an advanced street name signing program for selected intersections with traffic signals
• Field observations concluded that there is some inconsistency in the application of VDOT’s program
• VDOT does not provide advance street name signs for streets with significant amounts of cross street traffic that are un-signalized
• Program guidelines need to be developed if the County assumes this program
County of Fairfax, Virginia
Advanced Street Name Sign Program
Advantages
• Provides a benefit to those motorists who are unfamiliar with the area and street system
• Improves traffic safety by allowing drivers to plan which turn lane to get into prior to approaching the intersection thus avoiding last minute lane changing
• Requires funding for installation of the associated traffic signs - $100,000
County of Fairfax, Virginia
Staff Recommendation
The County assume responsibility for development of this program, andthe installation of new guide signs should funding become available.
Agreement with VDOT, noting that VDOT would be responsible for the maintenance of the signs once they are installed.
County of Fairfax, Virginia
Traffic Signal Construction
• C & I funding could be used to fund the construction of new or the modification of existing traffic signals
• As of 9/1/2011 – VDOT has indicated that there are no approved traffic signals in their queue
• Signal installation largely dependent upon availability of right-of-way for signal equipment. County assumption of this activity would not eliminate this requirement
• No time savings for the County to assume study, design and construction of traffic signals.
County of Fairfax, Virginia
Bus Shelters
• Fairfax County recently entered into an agreement with an advertisement agency, that allows for advertisements on bus shelters.
• The advertisement agency is responsible for the maintenance and construction of all bus shelters in Fairfax County at no cost to the
County.
• A memo of understanding with VDOT and WMATA to be executed which will allow the advertisement agency to advertise on VDOT and WMATA shelters and allow for the advertisement agency to maintain and fund new bus shelter installations.
County of Fairfax, Virginia
Staff Recommendation
Pursue the MOU between Fairfax County, VDOT, WMATA and the advertisement agency, that allows for advertisements on bus shelters with the advertisement agency responsible for maintenance and installation of future shelters at no cost to Fairfax County
County of Fairfax, Virginia
Mowing
• Most VDOT Primary and Secondary mowing done by contractors.
• Interstate mowing excluded
• Current Contract: • 3 mowing cycles / season (May – July – Sept. / Oct.)• Approx. 30 days required for complete cycle• Includes litter removal• Approx. $160,000 - $200,000 per cycle• Excludes P-R lots, VDOT maintenance yards, miscellaneous
ad-hoc mowing by state forces• 2012 is 3rd year of 3-year contract
• Additional cycle(s) could be added relatively easily. Need contractor agreement
County of Fairfax, Virginia
Advantages
• Improved appearance of Primary and Secondary roadsides
• Potential improvement in sight distances / safety etc.
Through Truck Studies 0.15 $40,000signage and consultant data collection
No Parking Reviews 1 $10,000 signange costAdvance Street Name Sign Program (New Construction)
0.61 $100,000 signage cost
Traffic Signals 0 0Bus Shelter Maintenance and Construction
0 0
Mowing 0 $200,000
Total 1.76 $350,000
County of Fairfax, Virginia
Questions
County of Fairfax, Virginia
Discussion of Converting the Fairfax County Parkwayand Franconia / Springfield Parkway
from a Secondary Road to Primary Road
County of Fairfax, Virginia
VDOT Criteria for Transferring Secondary System Roads to the Primary System
Fairfax County Franconia/Springfield Parkway Parkway
--- The Road
Serves as a link between interstate or intrastate highways, or both;
Serves a site of historical or scenic interest;
Connects county seats;
Has a minimum traffic volume of 2,000 vehicles per day;
indirect connection
County of Fairfax, Virginia
Fairfax County Franconia/Springfield Parkway
Parkway--- The Road Carries a minimum of:
7 percent out-of-state-vehicles;
20 percent light and medium trucks;
2 percent tractor-trailers and buses.
20 percent of traffic is on trips of 25 miles or more; Was Not Studied Was Not Studied
5 percent of traffic is on trips of 100 miles or more. Was Not Studied Was Not Studied
Degree of The degree of conformance with each of the criteria should be considered.Conformance Those roads suited for additions to the Primary System should fully conform to a majority
of the criteria.
Reference Code of Virginia, § 33.1-34 and Commonwealth Transportation Board Minutes, 12/17/98
VDOT Criteria for Transferring Secondary Roads to the Primary System
County of Fairfax, Virginia
Staff Recommendations
Request VDOT to transfer the Fairfax County Parkway route 7100 and Franconia/Springfield Parkway route 7900from the secondary system to the primary system