Top Banner
Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning
45

Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

Dec 29, 2015

Download

Documents

Colin Mathews
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

Copyright 2012 John Wiley & Sons, Inc.

Part II

Project Planning

Page 2: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-22

Project Management

Page 3: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

Copyright 2012 John Wiley & Sons, Inc.

Chapter 6

Project Activity and Risk Planning

Page 4: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-44

Initial Project Coordination and the Project Charter

Early meetings are used to decide on participating in the project

Used to “flesh out” the nature of the project

Outcomes include:– Technical scope– Areas of responsibility– Delivery dates or budgets– Risk management group

Page 5: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-55

Outside Clients

When it is for outside clients, specifications cannot be changed without the client’s permission

Client may place budget constraints on the project

May be competing against other firms

Page 6: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-66

Project Charter Elements

PurposeObjectivesOverviewSchedulesResourcesPersonnelRisk management plansEvaluation methods

Page 7: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

KnowledgeAreas

Project Management Process Groups

Initiating Planning Executing Monitoring & Controlling

Closing

Integration Develop Project Charter

Develop Project Management Plan

Direct & Manage Project Execution

Monitor & Control Project WorkPerform Integrated Change Control

Close Project or Phase

Scope Collect RequirementsDefine ScopeCreate WBS

Verify ScopeControl Scope

Time Define ActivitiesSequence ActivitiesEstimate Activity ResourcesEstimate Activity Durations Develop Schedule

Control Schedule

Cost Estimate CostDetermine Budget

Control Costs

Quality Plan Quality Perform Quality Assurance

Perform Quality Control

HR Develop HR Plan Acquire Project TeamDevelop Project Team

Manage Project Team

Communications

Identify Stakeholders

Plan Communications DistributeInformation

Manage Stakeholder ExpectationsReport Performance

Risk Plan Risk Management Identify RisksPerform Qualitative Risk AnalysisPerform Quantitative Risk AnalysisPlan Risk Responses

Monitor & Control Risks

Procurement Plan Procurements Conduct Procurements

Administer Procurements

Close Procurements

Page 8: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

Develop Project CharterDevelop Project Management PlanDirect & Manage Project ExecutionMonitor & Control Project WorkPerform Integrated Change ControlClose Project or Phase

Integration Processes

Page 9: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

What goes into your Project Charter?

Project Charter

Page 10: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

• What goes into your Project Charter?– Title– Description– Who is the Project Manager? What is their authority?– What is the business need?– What is the justification?– What are the assigned resources?– Who are the stakeholders?– What are the known stakeholder requirements?– What are the deliverables?– What are the constraints?– What are the assumptions?

Project Charter

Page 11: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

Where does all this information come from?

Primarily, the sponsor.Who is the sponsor? What is their role?

Project Charter

Page 12: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

Inputs Tools & Techniques Outputs

Project Statement of Work

Expert Judgment Project Charter

Business Case

Contract

Enterprise Environmental Factors

Organizational Process Assets

Project Charter

Page 13: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

Project Statement of Work– Created by the customer or sponsor– Gives the description of the project scope– Links the project to the strategic plan– Think of it as a high level “contract” between

the sponsor and the Project Manager

Project Charter

Page 14: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

Business Case– What are some examples of a business

case?

Project Charter

Page 15: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

Business Case– Market demand– Organizational need– Customer request– Technological advance– Legal requirement– Ecological impact– Social need

Project Charter

Page 16: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

Contract– Many projects begin because a contract has

been signed– The contract will give us many details of what

we need to know– If this is the case, then include a copy of the

contract with the Project Charter

Project Charter

Page 17: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

Enterprise Environmental Factors– “Company culture and existing systems that

the project will have to deal with or can make use of.”

– Could be positive or negativeCompany organizationStakeholder tolerancesRelevant standards

– Think of as “the baggage”

Project Charter

Page 18: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

Enterprise Environmental Factors– Examples:

Company culture Government or industry standards

– Regulations, quality standards, etc Existing HR skills Personnel administration

– Hiring & firing guidelines– Past performance reviews of employees– Union contacts

PM Info Systems– Company ordering and scheduling tools, etc

Project Charter

Page 19: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

Organizational Process Assets– Processes, procedures, policies, corporate

knowledge bases and historical informationLessons learnedHistorical recordsTemplates

– Learning the organization has done in the past to help the projects of today

– Best practices

Project Charter

Page 20: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-2020

Starting the Project Plan: The WBS

What is to be doneWhen it is to be started and finishedWho is going to do it

Page 21: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-2121

Starting the Project Plan: The WBS Continued

Some activities must be done sequentially

Some activities may be done simultaneously

Many things must happen when and how they are supposed to happen

Each detail is uncertain and subjected to risk

Page 22: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-2222

Hierarchical Planning

Major tasks are listedEach major task is broken down into

detailThis continues until all the activities to be

completed are listedNeed to know which activities “depend

on” other activities

Page 23: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-2323

A Form to Assist Hierarchical Planning

Figure 6-2

Page 24: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-2424

Career Day

Figure 6-4

Page 25: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-2525

The Work Breakdown Structure (WBS)

A hierarchical planning processBreaks tasks down into successively finer

levels of detailContinues until all meaningful tasks or

work packages have been identifiedThese make tracking the work easierNeed separate budget/schedule for each

task or work package

Page 26: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-2626

A Visual WBS

Figure 6-3

Page 27: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-2727

Steps to Create a WBS

1. List the task breakdown in successive levels

2. Identify data for each work package

3. Review work package information

4. Cost the work packages

5. Schedule the work packages

6. Continually examine actual resource use

7. Continually examine schedule

Page 28: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-2828

Human Resources

Useful to create a table that shows staff needed to execute WBS tasks

One approach is an organizational breakdown structure– Organizational units responsible for each

WBS element– Who must approve changes of scope– Who must be notified of progress

WBS and OBS may not be identical

Page 29: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-2929

The Responsibility (RACI) Matrix

Another approach is the Responsible, Accountable, Consult, Inform (RACI) matrix– Also known as a responsibility matrix, a

linear responsibility chart, an assignment matrix, a responsibility assignment matrix

Shows critical interfacesKeeps track of who must approve what

and who must be notified

Page 30: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-3030

Sample RACI Matrix

Figure 6-7

Page 31: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-3131

Agile Project Planning and Management

When scope cannot be determined in advance, traditional planning does not work

Agile project management was developed to deal with this problem in IT

Small teams are located at a single site Entire team collaborates Team deals with one requirement at-a-time with

the scope frozen

Page 32: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-3232

Interface Coordination Through Integration Management

Managing a project requires a great deal of coordination

Projects typically draw from many parts of the organization as well as outsiders

All of these must be coordinatedThe RACI matrix helps the project

manager accomplish this

Page 33: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-3333

Managing Projects by Phases and Phase-Gates

Break objectives into shorter term sub-objectives

Project life cycle is used for breaking a project up into component phases

Focus on specific, short-term outputLots of feedback between disciplines

Page 34: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-3434

Risk Management

Projects are risky, uncertainty is highProject manager must manage this riskThis is called “risk management”Risk varies widely between projectsRisk also varies widely between

organizationsRisk management should be built on the

results of prior projects

Page 35: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-3535

Parts to Risk Management

Risk management planning Risk identification Qualitative risk analysis Quantitative risk analysis Risk response planning Risk monitoring and control The risk management register

Page 36: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-3636

Risk Management Planning

Need to know the risk involved before selecting a project

Risk management plan must be carried out before the project can be formally selected

At first, focus is on externalities– Track and estimate project survival

Project risks take shape during planning Often handled by project office

Page 37: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-3737

Risk Identification

Risk is dependent on technology and environmental factors

Delphi method is useful for identifying project risks

Other methods include brainstorming, nominal group techniques, checklists, and attribute listing

May also use cause-effect diagrams, flow charts, influence charts, SWOT analysis

Page 38: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-3838

Qualitative Risk Analysis

Purpose is to prioritize risksA sense of the impact is also neededEach objective should be scaled and

weightedConstruct a risk matrixSame approach can be used for

opportunities

Page 39: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-3939

Risk Matrix

Figure 6-12

Page 40: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-4040

Quantitative Risk Analysis

1. List ways a project can fail2. Evaluate severity3. Estimate likelihood4. Estimate the inability to detect5. Find the risk priority number (RPN)

(RPN = S L D)6. Consider ways to reduce the S, L, and

D for each cause of failure

Page 41: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-4141

A FMEA Example

Table 6-1

Page 42: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-4242

Decision Tree Analysis

Figure 6-13

Page 43: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-4343

Risk Response Planning

Threats– Avoid– Transfer– Mitigate– Accept

Opportunities– Exploit– Share– Enhance– Accept

Page 44: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-4444

Risk Monitoring and Control

Monitoring covered in detail in Chapter 10Control covered in Chapter 11

Page 45: Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.

6-6-4545

The Risk Management Register

Environments that may impact projectsAssumptions madeRisks identifiedList of categories and key wordsEstimates on risk, states of project’s

environment, or on project assumptionsMinutesActual outcomes