Page 1: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

Copyright 2012 John Wiley & Sons, Inc.

Chapter 8

Scheduling

Page 2: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-22

Useful Abbreviations

CPM - Critical Path MethodPERT - Program Evaluation and Review

Technique

Page 3: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-33

Background

Schedule is the conversion of a project action plan into an operating timetable

Basis for monitoring a project One of the major project management tools Work changes daily, so a detailed plan is

essential Not all project activities need to be scheduled at

the same level of detail

Page 4: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-44

Background Continued

Most of the scheduling is at the WBS level, not the work package level

Only the most critical work packages may be shown on the schedule

Most of the scheduling is based on network drawings

Page 5: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-55

Network Scheduling Advantage

Consistent frameworkShows interdependencesShows when resources are neededEnsures proper communicationDetermines expected completion date Identifies critical activities

Page 6: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-66

Network Scheduling Advantage Continued

Shows which of the activities can be delayed

Determines start datesShows which task must be coordinatedShows which task can be run parallelRelieves some conflictAllows probabilistic estimates

Page 7: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-77

Network Scheduling Techniques: PERT (ADM) and CPM (PDM)

PERT was developed for the Polaris missile/submarine project in 1958

CPM developed by DuPont during the same time

Initially, CPM and PERT were two different approaches– CPM used deterministic time estimates and allowed

project crunching– PERT used probabilistic time estimates

Microsoft Project (and others) have blended CPM and PERT into one approach

Page 8: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-88

Terminology

Activity - A specific task or set of tasks that are required by the project, use up resources, and take time to complete

Event - The result of completing one or more activities

Network - The combination of all activities and events that define a project– Drawn left-to-right– Connections represent predecessors

Page 9: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-99

Terminology Continued

Path - A series of connected activitiesCritical - An activity, event, or path

which, if delayed, will delay the completion of the project

Critical Path - The path through the project where, if any activity is delayed, the project is delayed– There is always a critical path– There can be more than one critical path

Page 10: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-1010

Terminology Continued

Sequential Activities - One activity must be completed before the next one can begin

Parallel Activities - The activities can take place at the same time

Immediate Predecessor - That activity that must be completed just before a particular activity can begin

Page 11: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-1111

Terminology Continued

Activity on Arrow - Arrows represent activities while nodes stand for events

Activity on Node - Nodes stand for events and arrows show precedence

Page 12: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-1212

AON and AOA Format

Figure 8-3

Figure 8-2

Page 13: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-1313

Constructing the Network

Begin with START activityAdd activities without precedences as

nodes– There will always be one– May be more

Add activities that have those activities as precedences

Continue

Page 14: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-1414

Gantt (Bar) Charts

Developed by Henry L. GanttShows planned and actual progressEasy-to-read method to know the current

status

Page 15: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-1515

Advantages and Disadvantage

Advantages– Easily understood– Provide a picture of the current state of a

projectDisadvantage

– Difficult to follow complex projects

Page 16: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-1616

Microsoft Project Gantt Chart

Figure 8-11

Page 17: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-1717

Microsoft Project AON Network

Figure 8-12

Page 18: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-1818

Solving the Network

Table 8-1

Page 19: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-1919

The AON Network from the previous table

Figure 8-13

Page 20: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-2020

Calculating Activity Times

2

22

6

6

4

ab

bmaTE

Page 21: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-2121

The Results

Table 8-2

Page 22: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-2222

Critical Path and Time

Figure 8-15

Page 23: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-2323

Critical Path and Time Continued

Figure 8-16

Page 24: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-2424

Slack

Figure 8-16

Page 25: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-2525

Slack Values

Table 8-3

Page 26: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-2626

Precedence Diagramming

Finish to startStart to startFinish to finishStart to finish

Page 27: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-2727

Precedence Diagramming Conventions

Figure 8-17

Page 28: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-2828

Microsoft Projects

Table 8-4

Page 29: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-2929

Gantt Chart

Figure 8-18

Page 30: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-3030

AON Network

Figure 8-19

Page 31: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-3131

Microsoft Project Calendar

Figure 8-23

Page 32: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-3232

Uncertainty of Project Completion Time

Assume activities are statistically independent

Variance of a set of activities is the sum of the individual variances

Interested in variances along the critical path

Page 33: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-3333

Example

45.52645.1745.543

22.1745.5

7

33

4350)(2

ZD

DZ

Page 34: Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

8-8-3434

Toward Realistic Time Estimates

Calculations are based on 1% chance of beating estimates

Calculations can also be based on 5% or 10% Changing the percentage requires changing the

formulae for variance When using 5%, the divisor changes to 3.29 When using 10%, the divisor changes to 2.56