12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 1/17
UnggahanSamuel SitorusLihat Profil UmumRecently ReadMy LibrarySocial FeedMy UploadsMy CollectionsMy StatsAkunHelpLog keluar
Search the world's digital library.
BrowseBy TypeBooks - FictionBooks - Non FictionBrochures & CatalogsComicsGovernment DocsHow-To Guides & ManualsNewspapers & MagazinesPresentationsMenus &RecipesResearchSchool WorkBy TopicArt & DesignBusinessCreative WritingEntertainmentFictionFoodGovernment & PoliticsHealth & FitnessReligionScienceLiteratureRead without ads and support Scribd by becoming a Scribd Premium Reader.See Premium Plans×Bahasa:Bahasa Indonesia
Page 2
12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 2/17
Page 3
12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 3/17
Page 4
12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 4/17
Page 5
12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 5/17
Jenis Pekerjaan : Beton Cor 1 : 2 : 3
Satuan/Unit : M3
Analisa : Anl. B.05
No. SatuanKuantitas/
Koefisien
Harga Satuan
Dasar (Rp)
Harga
(Rp.)
(1) (3) (4) (5) (6) = (4) x (5)
A. Tenaga Kerja
1 Pekerja OH 1.3200 45,000.00 59,400.00
2 Tukang OH 0.2050 50,000.00 10,250.00
3 Kepala Tukang OH 0.0200 55,000.00 1,100.00
4 Mandor OH 0.0600 46,000.00 2,760.00
73,510.00
B. Bahan
1 Semen PC Kg 326.0000 1,175.00 383,050.00
2 Pasir Pasang M3 0.5430 22,000.00 11,946.00
3 Kerikil M3 0.7620 90,000.00 68,580.00
4 Air Ltr 215.0000 50.00 10,750.00
474,326.00
C. Peralatan
1 Molen 0,35 m3 Unit/Hari 0.2000 192,000.00 38,400.00
ANALISA HARGA SATUAN PEKERJAAN
Uraian
(2)
Sub Jumlah A
Sub Jumlah B
Page 6
12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 6/17
38,400.00
D 586,236.00
E Overhead + Keuntungan 5 % x Sub Jumlah (D) 29,311.80
Jumlah Harga = ( D + E ) 615,547.80
Harga Satuan Pekerjaan (Dibulatkan) 615,547.00
Sub Jumlah C
Sub Jumlah ( A + B + C )
Jenis Pekerjaan : Drain Hole Dia. 1,0"
Satuan/Unit : Bh
Analisa : Dihitung
No. SatuanKuantitas/
Koefisien
Harga Satuan
Dasar (Rp)
Harga
(Rp.)
(1) (3) (4) (5) (6) = (4) x (5)
A. Tenaga Kerja
1 Pekerja OH 0.0080 45,000.00 360.00
2 Tukang OH 0.0800 50,000.00 4,000.00
4,360.00
B. Bahan
1 Pipa PVC Dia. 1,0" M 0.5000 2,000.00 1,000.00
2 Kerikil M3 0.0200 90,000.00 1,800.00
3 Ijuk Kg 0.2000 3,000.00 600.00
3,400.00
C. Peralatan
-
-
D 7,760.00
E Overhead + Keuntungan 5 % x Sub Jumlah (D) 388.00
Jumlah Harga = ( D + E ) 8,148.00
Harga Satuan Pekerjaan (Dibulatkan) 8,148.00
ANALISA HARGA SATUAN PEKERJAAN
Uraian
Sub Jumlah ( A + B + C )
(2)
Sub Jumlah A
Sub Jumlah B
Sub Jumlah C
Page 7
12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 7/17
DownloadKembaliAdd NoteTautan
TanamSimpan
9 dari 19
Readcast
Tidak diReadcast
Catatan: Anda akan selalu dapat mengklik di tombol Readcast untuk berbagi dengan pengikut Scribd Anda.
Auto-Readcasting: OnView Past Readcasts
Undo
Tambahkan komentar
Kirim
Auto-Readcasting: OnView Past Readcasts
TweetTweet
Like 0
SKPA : 0
Nama Pekerjaan : 0
Lokasi : 0
Kegiatan : 0
Tahun Anggaran : 0
A TENAGA KERJA
1 Pekerja Hari 45,000.00
2 Mandor Hari 46,000.00
3 Tukang Hari 50,000.00
4 Kepala Tukang Hari 55,000.00
5 Operator Hari 80,000.00
6 Co. Operator Hari 50,000.00
B BAHAN
1 Kerikil M3 90,000.00
2 Tanah Timbun M3 25,000.00
3 Semen PC 40 Kg Sak 47,000.00
Semen PC 40 Kg Kg 1,175.00
4 Wiremesh Dia. 5 mm (Ulir) M2 22,000.00
5 Pipa PVC dia 1" M 2,000.00
6 Ijuk Kg 3,000.00
7 Air Ltr 50.00
8 Solar Ltr 7,000.00
9 Bensin Ltr 7,000.00
10 Oli Mesin/Pelumas Ltr 30,000.00
C PERALATAN
1 Chainsaw Jam 35,900.00
2 Stamper Hr-Sewa 141,000.00
3 Molen 0,35 m3 Unit/Hari 192,000.00
4 Mesin Potong Besi Hari 150,000.00
KeteranganHarga (Rp)
DAFTAR HARGA UPAH, BAHAN, DAN PERALATAN
No. SatuanUraian
Nama Pekerjaan : 0
0
Kegiatan : 0
Tahun Anggaran : 0
1 hari kerja = 7.000 Jam
I. PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan
Volume : 200.00 M2
Peralatan Yang Dipakai : Manual + Alat Bantu (Chain Saw)
Bahan Yang digunakan
Faktor Tenaga Kerja : 0.013
Jumlah Tenaga Kerja : 3 Orang
Produktifitas : 76.923 M2 /Pekerja/Hari
Produksi per hari : 3.00 x 76.923 M2 = 230.77 M2 /Hari
Waktu dibutuhkan : 200.00 / 230.77 = 1.00 hari
1.00 Minggu
2 DewateringVolume : 1.00 Ls
Peralatan Yang Dipakai : Manual + alat Bantu (Pompa air)
Jumlah Tenaga Kerja : Sesuai kebutuhan
Waktu Yang Dibutuhkan : 98.00 Hari
: 14.00 Minggu
II. PEKERJAAN POKOK
ANALISA TEKNIS
Cari Dokumen Ini
Cari
Riwayat Pencarian:Mencari...
Page 8
12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 8/17
II. PEKERJAAN POKOK
1 Galian Tanah Biasa (MP)
Volume : 618.63 M3
Peralatan Yang Dipakai : Manual
Bahan Yang digunakan
Faktor Tenaga Kerja : 0.582
Jumlah Tenaga Kerja : 6 Orang
Produktifitas : 1.718 M3 /Pekerja/Hari
Produksi per hari : 6.00 x 1.718 M3 = 10.31 M3 /Hari
Waktu dibutuhkan : 618.63 / 10.31 = 61.00 hari
9.00 Minggu
2 Tanah Hasil Galian, Diratakan dan Dipadatkan (MP)
Volume : 307.37 M3Peralatan Yang Dipakai : Manual + alat Bantu (Stamper)
Faktor Tenaga Kerja : 0.342
Jumlah Tenaga Kerja : 3 Orang
Produktifitas : 2.924 M3 /Pekerja/Hari
Produksi per hari : 3.00 x 2.924 M3 = 8.77 M3 /Hari
Waktu dibutuhkan : 307.37 / 8.77 = 36.00 hari
6.00 Minggu
3 Timbunan Tanah Didatangkan, Diratakan dan Dipadatkan (MP)
Volume : 124.83 M3
Peralatan Yang Dipakai : Manual
Bahan Yang digunakan
- Tanah Timbun 1.200 M3 : 149.80 M3
Faktor Tenaga Kerja : 0.3420
Jumlah Tenaga Kerja : 2 Orang
Produktifitas : 2.924 M3 /Pekerja/Hari
Produksi per hari : 2.00 x 2.924 M3 = 5.85 M3 /Hari
Waktu dibutuhkan : 124.83 / 5.85 = 22.00 hari
4.00 Minggu
4 Wiremesh Dia. 5 mm (Ulir)Volume : 1,838.43 M2
Peralatan Yang Dipakai : Manual
Bahan Yang digunakan
- Wiremesh Dia. 5 mm (Ulir) 1.0500 M2 : 1,930.35 M2
Faktor Tenaga Kerja : 0.0788
Jumlah Tenaga Kerja : 4 Orang
Produktifitas : 12.698 M2 /Pekerja/Hari
Produksi per hari : 4.00 x 12.698 M2 = 50.79 M2 /Hari
Waktu dibutuhkan : 1,838.43 / 50.79 = 37.00 hari
6.00 Minggu
5 Beton Cor 1 : 2 : 3
Volume : 540.80 M3
Peralatan Yang Dipakai : Manual + Alat Batu (Molen)
Bahan Yang digunakan
- Semen 326.000 Kg : 176,300.80 Kg
- Pasir Pasang 0.543 M3 : 293.65 M3
- kerikil 0.762 M3 : 412.09 M3
- Air 215.000 Ltr : 116,272.00 Ltr Faktor Tenaga Kerja : 1.6050
Jumlah Tenaga Kerja : 13 Orang
Produktifitas : 0.623 M3 /Pekerja/Hari
Produksi per hari : 13.00 x 0.623 M3 = 8.10 M3 /Hari
Waktu dibutuhkan : 540.80 / 8.10 = 67.00 hari
10.00 Minggu
6 Drain Hole Dia. 1,0"
Volume : 147.00 Bh
Peralatan Yang Dipakai : Manual
Bahan Yang digunakan
'- Pipa PVC dia. 1 " 0.500 M : 73.50 M
- Kerikil 0.020 M3 : 2.94 M3
- Ijuk 0.200 Kg : 29.40 Kg
Faktor Tenaga Kerja : 0.0880
Jumlah Tenaga Kerja : 2 Orang
Produktifitas : 11.364 Bh /Pekerja/Hari
Produksi per hari : 2.00 x 11.364 Bh = 22.73 Bh /Hari
Waktu dibutuhkan : 147.00 / 22.73 = 7.00 hari
1.00 Minggu
Mencari...
Hasil00 dari00
00hasil untukhasil untuk
p.
Page 9
12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 9/17
Nama Pekerjaan : 0
0
Lokasi : 0
Kegiatan : 0
Tahun Anggaran : 0
VOL. SAT KET
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
I. PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 200.00 M2 0.066
0.033 0.033
2 Dewatering 1.00 Ls 0.239
0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017
II PEKERJAAN POKOK
1 Galian Tanah Biasa (MP) 618.63 M3 4.068
0.610 0.610 0.610 0.610 0.610 0.509 0.509
2 Tanah Hasil Galian, Diratakan dan Dipadatkan (MP) 307.37 M3 1.731
0.303 0.303 0.303 0.303 0.260 0.260
3 Timbunan Tanah Didatangkan, Diratakan dan Dipadatkan ( 124.83 M3 1.643
0.821 0.821
4 Wiremesh Dia. 5 mm (Ulir) 1,838.43 M2 12.420 1.130 1.130 1.130 1.130 1.130 1.130 1.130 1.130 1.130 1.130 1.118
5 Beton Cor 1 : 2 : 3 540.80 M3 79.547
3.977 5.966 6.761 6.761 6.761 6.761 7.159 7.955 7.955 7.955 7.955 3.580
6 Drain Hole Dia. 1,0" 147.00 Bh 0.286
0.041 0.041 0.041 0.041 0.041 0.041 0.041
TOTAL BOBOT 100.00
PROGRES RENCANA MINGGUAN (%) 0.033 0.660 1.757 5.735 7.723 8.519 8.458 8.458 8.253 8.650 9.446 9.446 9.390 8.231 4.418 0.821
PROGRES RENCANA KUMULATIF MINGGUAN (%) - 0.033 0.693 2.451 8.186 15.909 24.428 32.886 41.344 49.597 58.247 67.693 77.139 86.529 94.761 99.179 100.00
JADWAL WAKTU PELAKSANAAN
Bobot
Rencana
(%)
URAIAN KEGIATANNO. BULAN - III BULAN - IV
MASA PELAKSANAAN
BULAN - I BULAN - II
100
75
50
25
0
Page 10
12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 10/17
Page 11
12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 11/17
Page 12
12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 12/17
Page 13
12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 13/17
Page 14
12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 14/17
Contoh Analisa Teknik
Unduh atau Cetak
Tambahkan ke Koleksi87
Reads
0Readcasts
0
Embed Views
Published by
ibaltc
Ikuti:
Cari Dokumen Ini
Cari
KIATTekanCtrl-F⌘F untuk mencari dengan cepat dibagian manapun dalam dokumen.
Get Scribd Mobile
To get Scribd mobile enter your number and we'll send you a link to the Scribd app for iPhone & Android.We've sent a link to the Scribd app. If you didn't receive it, try again.
(xxx) xxx-xxxx
Text me
We'll never share your phone number.
Or, click here and we'll send an email to your iPad and Android tablet.We've sent you an email with the link to the Scribd app. Didn't receive it? Try again.
iTunes App Store | Google Play Store
Info dan Peringkat
Kategori: Tidak ada kategori.
Peringkat
Tanggal diunggah: 04/03/2013
Hak Cipta: Attribution Non-commercial
Tag: No tags
Flag for inappropriate content
Unduh dan cetak dokumen ini
Baca offline di penampil PDF
Sunting dokumen ini dalam Adobe Acrobat,
Microsoft Excel, NotepadSimpan sebuah salinan kalau-kalau versi ini
dihapus dari Scribd
Baca dan cetak tanpa iklan
Kirimkan berkas lewat email
Pilih sebuah format untuk mengunduhdalam
.PDF
.XLSX
Page 15
12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 15/17
.TXT
Mengunduh
Direkomendasikan
1 p.Analisa Teknis Galian 0-2M
Johan Hartono
1001 Reads
1 p.
analisa irigasi
hendrikzainudin3905 Reads
18 p.
Metode Pelaksanaan PekerjaanSi Ghabe Naujui
26510 Reads
Lainnya Dari Pengguna Ini
4 p.Rab Pemasangan Sunda Plafond
ibaltc
Page 16
12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 16/17
16 Reads
1 p.
Pemasangan Waterproofing Membraneibaltc
11 Reads
1 p.
Aksesoris Body Yamaha Vixion
ibaltc
15 Reads
1 p.
Daftar Kuantitas Dah Hargaibaltc
14 Reads
Next
Notes
sitorus_samuel
Add a note. (Limit 400 characters)
Privacy:publicPost Note
Tentang
Tentang ScribdTeam
Blog
Bergabung dengan tim kami!Hubungi Kami
Premium
Premium Reader
Toko Scribd
Beriklan dengan kami
MemulaiAdChoices
Dukungan
Page 17
12/06/13 Contoh Analisa Teknik
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 17/17
Bantuan
FAQTekan
Mitra
Pengembang / API
Legal
Terms
Privasi
Hak cipta
Get Scribd Mobile
© Copyright 2013 Scribd Inc.
Bahasa:Bahasa Indonesia