12/06/13 Contoh Analisa Teknik id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 1/17 Unggahan Samuel Sitorus Lihat Profil Umum Recently Read My Library Social Feed My Uploads My Collections My Stats Akun Help Log keluar Search the world's digital l Browse By Type Books - Fiction Books - Non Fiction Brochures & Catalogs Comics Government Docs How-To Guides & Manuals Newspapers & Magazines Presentations Menus & Recipes Research School Work By Topic Art & Design Business Creative Writing Entertainment Fiction Food Government & Politics Health & Fitness Religion Science Literature Read without ads and support Scribd by becoming a Scribd Premium Reader. See Premium Plans × Bahasa: Bahasa Indonesia
17
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Contoh Analisa Teknik

12/06/13 Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 1/17

UnggahanSamuel SitorusLihat Profil UmumRecently ReadMy LibrarySocial FeedMy UploadsMy CollectionsMy StatsAkunHelpLog keluar

Search the world's digital library.

BrowseBy TypeBooks - FictionBooks - Non FictionBrochures & CatalogsComicsGovernment DocsHow-To Guides & ManualsNewspapers & MagazinesPresentationsMenus &RecipesResearchSchool WorkBy TopicArt & DesignBusinessCreative WritingEntertainmentFictionFoodGovernment & PoliticsHealth & FitnessReligionScienceLiteratureRead without ads and support Scribd by becoming a Scribd Premium Reader.See Premium Plans×Bahasa:Bahasa Indonesia

Page 2: Contoh Analisa Teknik

12/06/13 Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 2/17

Page 3: Contoh Analisa Teknik

12/06/13 Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 3/17

Page 4: Contoh Analisa Teknik

12/06/13 Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 4/17

Page 5: Contoh Analisa Teknik

12/06/13 Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 5/17

Jenis Pekerjaan : Beton Cor 1 : 2 : 3

Satuan/Unit : M3

Analisa : Anl. B.05

No. SatuanKuantitas/

Koefisien

Harga Satuan

Dasar (Rp)

Harga

(Rp.)

(1) (3) (4) (5) (6) = (4) x (5)

A. Tenaga Kerja

1 Pekerja OH 1.3200 45,000.00 59,400.00

2 Tukang OH 0.2050 50,000.00 10,250.00

3 Kepala Tukang OH 0.0200 55,000.00 1,100.00

4 Mandor OH 0.0600 46,000.00 2,760.00

73,510.00

B. Bahan

1 Semen PC Kg 326.0000 1,175.00 383,050.00

2 Pasir Pasang M3 0.5430 22,000.00 11,946.00

3 Kerikil M3 0.7620 90,000.00 68,580.00

4 Air Ltr 215.0000 50.00 10,750.00

474,326.00

C. Peralatan

1 Molen 0,35 m3 Unit/Hari 0.2000 192,000.00 38,400.00

ANALISA HARGA SATUAN PEKERJAAN

Uraian

(2)

Sub Jumlah A

Sub Jumlah B

Page 6: Contoh Analisa Teknik

12/06/13 Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 6/17

38,400.00

D 586,236.00

E Overhead + Keuntungan 5 % x Sub Jumlah (D) 29,311.80

Jumlah Harga = ( D + E ) 615,547.80

Harga Satuan Pekerjaan (Dibulatkan) 615,547.00

Sub Jumlah C

Sub Jumlah ( A + B + C )

Jenis Pekerjaan : Drain Hole Dia. 1,0"

Satuan/Unit : Bh

Analisa : Dihitung

No. SatuanKuantitas/

Koefisien

Harga Satuan

Dasar (Rp)

Harga

(Rp.)

(1) (3) (4) (5) (6) = (4) x (5)

A. Tenaga Kerja

1 Pekerja OH 0.0080 45,000.00 360.00

2 Tukang OH 0.0800 50,000.00 4,000.00

4,360.00

B. Bahan

1 Pipa PVC Dia. 1,0" M 0.5000 2,000.00 1,000.00

2 Kerikil M3 0.0200 90,000.00 1,800.00

3 Ijuk Kg 0.2000 3,000.00 600.00

3,400.00

C. Peralatan

-

-

D 7,760.00

E Overhead + Keuntungan 5 % x Sub Jumlah (D) 388.00

Jumlah Harga = ( D + E ) 8,148.00

Harga Satuan Pekerjaan (Dibulatkan) 8,148.00

ANALISA HARGA SATUAN PEKERJAAN

Uraian

Sub Jumlah ( A + B + C )

(2)

Sub Jumlah A

Sub Jumlah B

Sub Jumlah C

Page 7: Contoh Analisa Teknik

12/06/13 Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 7/17

DownloadKembaliAdd NoteTautan

TanamSimpan

9 dari 19

Readcast

Tidak diReadcast

Catatan: Anda akan selalu dapat mengklik di tombol Readcast untuk berbagi dengan pengikut Scribd Anda.

Auto-Readcasting: OnView Past Readcasts

Undo

Tambahkan komentar

Kirim

Auto-Readcasting: OnView Past Readcasts

TweetTweet

Like 0

SKPA : 0

Nama Pekerjaan : 0

Lokasi : 0

Kegiatan : 0

Tahun Anggaran : 0

A TENAGA KERJA

1 Pekerja Hari 45,000.00

2 Mandor Hari 46,000.00

3 Tukang Hari 50,000.00

4 Kepala Tukang Hari 55,000.00

5 Operator Hari 80,000.00

6 Co. Operator Hari 50,000.00

B BAHAN

1 Kerikil M3 90,000.00

2 Tanah Timbun M3 25,000.00

3 Semen PC 40 Kg Sak 47,000.00

Semen PC 40 Kg Kg 1,175.00

4 Wiremesh Dia. 5 mm (Ulir) M2 22,000.00

5 Pipa PVC dia 1" M 2,000.00

6 Ijuk Kg 3,000.00

7 Air Ltr 50.00

8 Solar Ltr 7,000.00

9 Bensin Ltr 7,000.00

10 Oli Mesin/Pelumas Ltr 30,000.00

C PERALATAN

1 Chainsaw Jam 35,900.00

2 Stamper Hr-Sewa 141,000.00

3 Molen 0,35 m3 Unit/Hari 192,000.00

4 Mesin Potong Besi Hari 150,000.00

KeteranganHarga (Rp)

DAFTAR HARGA UPAH, BAHAN, DAN PERALATAN

No. SatuanUraian

Nama Pekerjaan : 0

0

Kegiatan : 0

Tahun Anggaran : 0

1 hari kerja = 7.000 Jam

I. PEKERJAAN PERSIAPAN

1 Pembersihan Lapangan

Volume : 200.00 M2

Peralatan Yang Dipakai : Manual + Alat Bantu (Chain Saw)

Bahan Yang digunakan

Faktor Tenaga Kerja : 0.013

Jumlah Tenaga Kerja : 3 Orang

Produktifitas : 76.923 M2 /Pekerja/Hari

Produksi per hari : 3.00 x 76.923 M2 = 230.77 M2 /Hari

Waktu dibutuhkan : 200.00 / 230.77 = 1.00 hari

1.00 Minggu

2 DewateringVolume : 1.00 Ls

Peralatan Yang Dipakai : Manual + alat Bantu (Pompa air)

Jumlah Tenaga Kerja : Sesuai kebutuhan

Waktu Yang Dibutuhkan : 98.00 Hari

: 14.00 Minggu

II. PEKERJAAN POKOK

ANALISA TEKNIS

Cari Dokumen Ini

Cari

Riwayat Pencarian:Mencari...

Page 8: Contoh Analisa Teknik

12/06/13 Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 8/17

II. PEKERJAAN POKOK

1 Galian Tanah Biasa (MP)

Volume : 618.63 M3

Peralatan Yang Dipakai : Manual

Bahan Yang digunakan

Faktor Tenaga Kerja : 0.582

Jumlah Tenaga Kerja : 6 Orang

Produktifitas : 1.718 M3 /Pekerja/Hari

Produksi per hari : 6.00 x 1.718 M3 = 10.31 M3 /Hari

Waktu dibutuhkan : 618.63 / 10.31 = 61.00 hari

9.00 Minggu

2 Tanah Hasil Galian, Diratakan dan Dipadatkan (MP)

Volume : 307.37 M3Peralatan Yang Dipakai : Manual + alat Bantu (Stamper)

Faktor Tenaga Kerja : 0.342

Jumlah Tenaga Kerja : 3 Orang

Produktifitas : 2.924 M3 /Pekerja/Hari

Produksi per hari : 3.00 x 2.924 M3 = 8.77 M3 /Hari

Waktu dibutuhkan : 307.37 / 8.77 = 36.00 hari

6.00 Minggu

3 Timbunan Tanah Didatangkan, Diratakan dan Dipadatkan (MP)

Volume : 124.83 M3

Peralatan Yang Dipakai : Manual

Bahan Yang digunakan

- Tanah Timbun 1.200 M3 : 149.80 M3

Faktor Tenaga Kerja : 0.3420

Jumlah Tenaga Kerja : 2 Orang

Produktifitas : 2.924 M3 /Pekerja/Hari

Produksi per hari : 2.00 x 2.924 M3 = 5.85 M3 /Hari

Waktu dibutuhkan : 124.83 / 5.85 = 22.00 hari

4.00 Minggu

4 Wiremesh Dia. 5 mm (Ulir)Volume : 1,838.43 M2

Peralatan Yang Dipakai : Manual

Bahan Yang digunakan

- Wiremesh Dia. 5 mm (Ulir) 1.0500 M2 : 1,930.35 M2

Faktor Tenaga Kerja : 0.0788

Jumlah Tenaga Kerja : 4 Orang

Produktifitas : 12.698 M2 /Pekerja/Hari

Produksi per hari : 4.00 x 12.698 M2 = 50.79 M2 /Hari

Waktu dibutuhkan : 1,838.43 / 50.79 = 37.00 hari

6.00 Minggu

5 Beton Cor 1 : 2 : 3

Volume : 540.80 M3

Peralatan Yang Dipakai : Manual + Alat Batu (Molen)

Bahan Yang digunakan

- Semen 326.000 Kg : 176,300.80 Kg

- Pasir Pasang 0.543 M3 : 293.65 M3

- kerikil 0.762 M3 : 412.09 M3

- Air 215.000 Ltr : 116,272.00 Ltr Faktor Tenaga Kerja : 1.6050

Jumlah Tenaga Kerja : 13 Orang

Produktifitas : 0.623 M3 /Pekerja/Hari

Produksi per hari : 13.00 x 0.623 M3 = 8.10 M3 /Hari

Waktu dibutuhkan : 540.80 / 8.10 = 67.00 hari

10.00 Minggu

6 Drain Hole Dia. 1,0"

Volume : 147.00 Bh

Peralatan Yang Dipakai : Manual

Bahan Yang digunakan

'- Pipa PVC dia. 1 " 0.500 M : 73.50 M

- Kerikil 0.020 M3 : 2.94 M3

- Ijuk 0.200 Kg : 29.40 Kg

Faktor Tenaga Kerja : 0.0880

Jumlah Tenaga Kerja : 2 Orang

Produktifitas : 11.364 Bh /Pekerja/Hari

Produksi per hari : 2.00 x 11.364 Bh = 22.73 Bh /Hari

Waktu dibutuhkan : 147.00 / 22.73 = 7.00 hari

1.00 Minggu

Mencari...

Hasil00 dari00

00hasil untukhasil untuk

p.

Page 9: Contoh Analisa Teknik

12/06/13 Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 9/17

Nama Pekerjaan : 0

0

Lokasi : 0

Kegiatan : 0

Tahun Anggaran : 0

VOL. SAT KET

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I. PEKERJAAN PERSIAPAN

1 Pembersihan Lapangan 200.00 M2 0.066

0.033 0.033

2 Dewatering 1.00 Ls 0.239

0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017

II PEKERJAAN POKOK

1 Galian Tanah Biasa (MP) 618.63 M3 4.068

0.610 0.610 0.610 0.610 0.610 0.509 0.509

2 Tanah Hasil Galian, Diratakan dan Dipadatkan (MP) 307.37 M3 1.731

0.303 0.303 0.303 0.303 0.260 0.260

3 Timbunan Tanah Didatangkan, Diratakan dan Dipadatkan ( 124.83 M3 1.643

0.821 0.821

4 Wiremesh Dia. 5 mm (Ulir) 1,838.43 M2 12.420 1.130 1.130 1.130 1.130 1.130 1.130 1.130 1.130 1.130 1.130 1.118

5 Beton Cor 1 : 2 : 3 540.80 M3 79.547

3.977 5.966 6.761 6.761 6.761 6.761 7.159 7.955 7.955 7.955 7.955 3.580

6 Drain Hole Dia. 1,0" 147.00 Bh 0.286

0.041 0.041 0.041 0.041 0.041 0.041 0.041

TOTAL BOBOT 100.00

PROGRES RENCANA MINGGUAN (%) 0.033 0.660 1.757 5.735 7.723 8.519 8.458 8.458 8.253 8.650 9.446 9.446 9.390 8.231 4.418 0.821

PROGRES RENCANA KUMULATIF MINGGUAN (%) - 0.033 0.693 2.451 8.186 15.909 24.428 32.886 41.344 49.597 58.247 67.693 77.139 86.529 94.761 99.179 100.00

JADWAL WAKTU PELAKSANAAN

Bobot

Rencana

(%)

URAIAN KEGIATANNO. BULAN - III BULAN - IV

MASA PELAKSANAAN

BULAN - I BULAN - II

100

75

50

25

0

Page 10: Contoh Analisa Teknik

12/06/13 Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 10/17

Page 11: Contoh Analisa Teknik

12/06/13 Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 11/17

Page 12: Contoh Analisa Teknik

12/06/13 Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 12/17

Page 13: Contoh Analisa Teknik

12/06/13 Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 13/17

Page 14: Contoh Analisa Teknik

12/06/13 Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 14/17

Contoh Analisa Teknik

Unduh atau Cetak

Tambahkan ke Koleksi87

Reads

0Readcasts

0

Embed Views

Published by

ibaltc

Ikuti:

Cari Dokumen Ini

Cari

KIATTekanCtrl-F⌘F untuk mencari dengan cepat dibagian manapun dalam dokumen.

Get Scribd Mobile

To get Scribd mobile enter your number and we'll send you a link to the Scribd app for iPhone & Android.We've sent a link to the Scribd app. If you didn't receive it, try again.

(xxx) xxx-xxxx

Text me

We'll never share your phone number.

Or, click here and we'll send an email to your iPad and Android tablet.We've sent you an email with the link to the Scribd app. Didn't receive it? Try again.

iTunes App Store | Google Play Store

Info dan Peringkat

Kategori: Tidak ada kategori.

Peringkat

Tanggal diunggah: 04/03/2013

Hak Cipta: Attribution Non-commercial

Tag: No tags

Flag for inappropriate content

Unduh dan cetak dokumen ini

Baca offline di penampil PDF

Sunting dokumen ini dalam Adobe Acrobat,

Microsoft Excel, NotepadSimpan sebuah salinan kalau-kalau versi ini

dihapus dari Scribd

Baca dan cetak tanpa iklan

Kirimkan berkas lewat email

Pilih sebuah format untuk mengunduhdalam

.PDF

.XLSX