Page 1: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

Construction Update

August 18, 2010

Rob Gaertner, P.E.

Director of Facilities

Page 2: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

Agenda

• Introduction Dr. Green

• Project Overview Rob Gaertner

• Questions/Comments

Page 3: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

Introduction

• Projects were included in the 2010/11 Capital Funding Plan

• Address ongoing maintenance of the District’s facilities.

• The total value of the major construction contracts that were awarded is $861,390.

Page 4: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

Roof Replacement at McKnight Elementary School

• Replaced 42,500 square feet of rubber roofing that was installed in 1990.

• Replace Greenhouse roofing, gutters and downspouts.

• Installed new roof insulation.• Replaced and relocated roof drains.• Installed new metal roof edge.• Project should be substantially completed

on August 25, 2010.

Page 5: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

McKnight Elementary School

Page 6: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

Installation of Elevators for the Cafeteria and Technology Education areas at NAI

• Replaced the existing chair lifts with elevators.• Modified existing building to provide space for the

two new elevators and equipment rooms.• Provide a Student Activities area in the lobby

outside of the Cafeteria.• The Café Elevator is scheduled to be inspected

on August 20, 2010.• The Tech Ed Elevator is tentatively scheduled for

inspection on August 27, 2010

Page 7: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

NAI Cafeteria Elevator Installation

Page 8: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

NAI Student Activities Area

Page 9: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

NAI Tech Ed Elevator Installation

Page 10: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

Masonry Repairs at Bradford Woods Elementary

• Removal and replacement of the glazed brick installed above the Kitchen and Receiving area doors.

• Removal and replacement of the five brick piers on the sides of the main entrance stairs.

• Project was completed on July 23, 2010.

Page 11: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

Masonry Repairs at BWE

Page 12: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

Greenhouse Masonry Repairs at McKnight

• This project included the repairs to the existing masonry around the base of the Greenhouse.

• Installation of a coating of mortar over the existing block to seal the existing masonry.

• Installation of a stainless steel flashing around the base of the greenhouse glazing to direct the water away from the masonry.

• Sealing of the new masonry coating.• This project was completed on August 13, 2010

Page 13: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

Greenhouse Masonry Repairs at McKnight

Page 14: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

Installation of Additional Exterior Cameras at NASH

• Installed fourteen additional digital cameras around the exterior of NASH.– Student Parking Lot – 4– Around the perimeter of the building - 10

• Installed ten additional digital cameras around the interior of NASH.– Inside the Stair Towers – 8– Cafeteria - 2

• This project should be completed by August 30, 2010.

Page 15: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

Installation of Exterior Door Card Key System at MMS

• Installed card key access control system on 4 exterior doors at MMS.– Auditorium Entrance– Gym Entrance– Receiving Area– Back of Gym

• This work was completed on August 17 , 2010.

Page 16: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

Other Projects

• Painting of the exterior steel at BWE.• Repairs to the gutters at BWE, MES, MMS

and the Baierl Center – In Progress.• Modifications to the ductwork for the IT

Server Room HVAC system.• Concrete Sidewalk and Curbs Repairs at:

– BWE, MES, McK, and NAI

• Driveway and Parking Lot Repairs at:– HES, IES, McK, NAI and Transportation

Page 17: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

Other Projects

• Subdivision of Room 107 at IMS.• Construction of the Cumberland Campus trail.• Replacement of the projection screen on the

stage at CMS.• Installation of wall pads in the small gym at NAI –

In Progress.• Repairs to the locker room shower controls at

NASH.• Installation of electronic ballasts in the classrooms

at NAI – On Going.

Page 18: Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.

Questions/Comments