TEXAS DEPARTMENT OF TRANSPORTATION DALLAS DISTRICT 1107_121919 Connecting You With Texas ELLIS COUNTY CONSTRUCTION PROJECTS 2019 HIGHWAY PROJECTS: Dallas District Office 4777 E. Highway 80 Mesquite, TX 75150 CONTACT INFORMATION Danielle Boyd – Information Specialist Office: (214) 320 - 4480 Email: [email protected] TxDOT graphic * Not mapped. SOURCE: Texas Department of Transportation. ELLIS COUNTY PROJECTS UNDER CONSTRUCTION (WINTER Q4 2019) # CSJ Hwy Project Limits Description Letting Start/End Contractor Est. Cost % Complete 1 1159-01-022 FM 875 At Waxahachie Creek Replace bridge and approaches Jun-2015 May-2017/ Feb-2020 Massana Construction, Inc. $3.7 M 99% 2 0048-04-079 IH 35E US 77 N of Waxahachie to US 77 S of Waxahachie Reconstruct/widen from 4 lanes to 6 lanes Aug-2015 Mar-2016/ Mar-2021 OHL USA, Inc. $126.4 M 65% 3 1451-01-025 FM 55 At Big Onion Creek Replace bridge and approaches Aug-2015 Nov-2016/ Feb-2020 Surety company $1.5 M 99% 4 0172-08-053 US 287 South of SH 34 to IH 45 S in Ennis Widen 2-ln to 4-ln divided hwy. w/ grade separation. Jan-2017 May-2017/ Feb-2020 Fluor Heavy Civil, LLC $61.7 M 99% 5 1051-01-037 FM 664 Westmoreland Rd. to IH 35E in City of Red Oak Widen from 2 lanes to 6 lanes urban divided, including intersec. improv. May-2018 Oct-2018/ Sep-2020 Sterling Delaware Holding Co., Inc. $32 M 50% 6 1317-01-015 FM 1183 SH 34 to IH 45 Reconstruct Existing Pavement and Add Shoulders Jun-2018 Nov-2018/ Jul-2020 Knife River Corp. - South $8.1M 63% 7 1211-02-019 FM 984 From FM 877 to SH 34 Reconstruct Existing Pavement and Add Shoulders Dec-2018 Mar-2019/ Apr-2020 A.K. Gillis and Sons, Inc. $7.1 M 53% 8 0918-22-157* VA At various Locations Replace Turn Downs and Guardrail Jun-2018 Jan-2019/ Feb-2020 DBI Service, LLC $4.5M 92% 9 0048-08-051 IH 35E Hill County Line to US 77 South Full depth concrete repair Jan-2019 May-2019/ Mar-2020 O. Trevino Construction LLC $1.5 M 67% 10 0092-05-051 IH 45 At FM 1181 Construct intersection improvements Feb-2019 Jun-2019/ Mar-2020 Accelerated Critical Path, Inc. $1.4 M 37% 11 0172-05-122 US 287 Park School House Road Pavement repair and overlay Mar-2019 Jun-2019/ Mar-2020 Austin Bridge & Road Services L.P. $8 M 47% 12 0048-03-050 US 77 At UPRR and Waxahachie Creek Replace bridge and approaches Jun-2019 Dec-2019/ Feb-2022 Fluor Heavy Civil, LLC $21.6 M 0% 13 0172-05-115 US 287 At Walnut Grove Road Construct interchange Apr-2019 Jul-2019/ Jan-2022 OHL USA, Inc. $37 M 7% ESTIMATED TOTAL $314.5 M WINTER • Q4 2019 1 3 5 4 12 13 2 6 7 9 10 11 CORSICANA MIDLOTHIAN ENNIS CORSICANA ENNIS 45 77 77 77 77 67 287 67 45 45 45 35E 35E 35E Ferris Ovilla Pecan Hill Red Oak Trumbull Milford Palmer Maypearl Garrett Rice Emhouse Barry Frost Blooming Grove Alma Bardwell Italy Forreston JOHNSON CO. ELLIS CO. NAVARRO CO. ELLIS CO. NAVARRO CO. HILL CO. ELLIS CO. ELLIS CO. JOHNSON CO. ELLIS CO. K A U F M A N C O . E L L I S C O. DALLAS CO. ELLIS CO. DALLAS CO. TARRANT CO. ELLIS CO. Mid-Way Regional Airport 660 983 813 878 879 876 308 934 308 667 877 984 984 985 660 1182 1126 1722 916 157 875 875 663 34 34 34 34 22 22 287 287 287 66 66 66 55 55 Lancaster Airport Cedar Hill N 2 miles 664 664 1446 879 85 MIDLOTHIAN Westmoreland Rd. Bardwell Lake Joe Pool Lake Lake Waxahachie Rockett WAXAHACHIE City of Waxahachie Projects Under Construction TxDOT graphic SOURCE: Texas Department of Transportation. NOTICE: This map was produced for internal use within the Texas Department of Transportation. Accuracy is limited to the validity of the data as of WINTER Q4 2019.