McNary Northshore Fishway Hydro Project May 6, 2017 History & Lessons Learned
42

Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Apr 26, 2018

Download

Documents

phamtram
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

McNary Northshore

Fishway Hydro Project

May 6, 2017

History & Lessons Learned

Page 2: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

21th Annual TECHNICAL SEMINAR

Machines, Maintenance, and Management:

Keeping Hydro Facilities Up and Running

History & Lessons Learned McNary Northshore Fishway

Hydro Project

• McNary project history

• McNary re-powering project aka Runner install (part 1)

• Powerhouse crane failure & repair

• Rewind Project

• Runner install (part 2)

• Commissioning

• Lessons learned

Page 3: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

Page 4: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

McNary Lock and Dam

Page 5: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

5

Page 6: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

• On September 30, 1991, the Federal Energy Regulatory Commission (FERC)

issued a 50-year license to North Wasco County Peoples Utility District

(NWCPUD) to construct, operate and maintain a hydroelectric project at the

McNary Dam.

• Originally, BPA entered into a power purchase agreement with NWCPUD in 1993.

• BPA withdrew from the agreement in 1994.

• Klickitat PUD then joined with NWCPUD to develop the McNary Project.

• The PUD’s entered into an Ownership Agreement in August of 1995

• The McNary North shore hydroelectric project was completed and started

production on October 17th 1997.

• The total cost of the project was $29 million.

Brief Project History

Page 7: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Project Design7

• The project uses attraction water from the north shore fish ladder on the McNary Dam for power generation.

– Attraction water flow is diverted through penstocks, runs through the turbine and is then routed back to the entrance of the fish ladder to attract migrating fish and lamprey.

• The intake structure at McNary is located at the bottom of the dam and draws water from about 80 ft below the surface of the dam forebay.

• The generator at McNary produces approximately 10 MW of power, which is split equally between NWPCUD and KPUD.

– Over a year, this amounts to approximately 80,000 MWh of energy – enough power to provide electricity to about 8,000 homes

Page 8: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Construction Photos

4/8/2017

Page 9: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017Kurt Conger, NWCPUD9

Page 10: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

Page 11: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

Page 12: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

McNary Fishway Hydro Project

Unit Cross Section

Page 13: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

McNary Re-powering Project Runner Install - Part 1

4/8/2017

• Review repair history of turbine blade cracks

• Review welding procedures from past blade repairs.

• Evaluate failure risk and cost associated with a blade failure

• Recommend remedial protection measures, e.g. vibration

monitoring, startup/shutdown timing, other, that may mitigate

damage if a blade failure occurs.

• Make recommendations for repair or replacement of turbine

runner or other in-water equipment.

Page 14: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

• 10 MW vertical unit commissioned in 1997

• Orenco supplied Hangzhou turbine & generator,

manufactured in China

• History of propeller runner blade cracking

• Runner casting quality poor with dimensional problems

• Initial McMillen Jacobs site visit on June 17, 2014

• Annual outages with weld repairs

Project Information

Page 15: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

Early cracks near anti-cavitation fin

Page 16: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Cracks needing repair every 6 months

4/8/2017

Page 17: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

Cracks getting worse after each weld repair

Page 18: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Crack NDE

4/8/2017

Page 19: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Recommendations

4/8/2017

• Contract for additional engineering, including developing

contract documents

• Perform generator detailed inspection early 2015

• Bid and award new runner contract

• Bid and award runner install site work contract

Action: Owners direct McMillen to develop runner procurement

bid documents and runner installation bid documents.

Page 20: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Runner Procurement

4/8/2017

• Bid documents prepared and issued to bidders

• Bids evaluated and recommendation for award February 2015

• Weir – American Hydro awarded contract effective March 31,

2015

• Runner to be delivered within 311 days

Page 21: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

New Runner

4/8/2017

Page 22: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Old Runner

4/8/2017

Page 23: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Runner Installation Contract

4/8/2017

• Bid documents prepared and issued to bidders

• Bids evaluated and recommendation for award August

2015

• HCMS awarded contract effective September 9, 2015

• Runner to be installed by February 5, 2016

• Outage begins October 2015

Page 24: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

November 18, 2015 - Crane Failure

4/8/2017

• During the last lift of major equipment from the turbine pit, a

defective weld in the powerhouse crane failed.

• The old runner, shaft, bearings, brackets and head-covers

dropped 18”.

• Parts of the crane fell into the powerhouse damaging the

stator and concrete.

• Nobody was injured!

Page 25: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

Powerhouse

Crane

Page 26: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

Page 27: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Crane Failure Damage

4/8/2017

• The crane failure damaged several major components of

the project:

• Generator stator windings and core

• Turbine bearing bracket that supports the runner and

shaft

• Lower guide bearing support bracket

• And the crane itself was no longer serviceable for the

runner installation work

Page 28: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Other Component Defects4/8/2017

• Stator winding defects

• Loose wedges and missing side/depth packing

• Caused excessive wear, winding damage and reduced life expectancy

• Lack of strand transpositions or internal transpositions resulting in higher losses

• Tin/lead solder results in higher losses and increased outage risk

• Other (PD evidence, inadequate end winding clearances)

• Wicket gates, bearing surface degradation, runout measurements too high

• Multiple inner and outer head cover defective welds

• Upper and lower bearing bracket defective welds

• Possible defective rotor welds investigated – need rewelding

Page 29: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Project Timeline

4/8/2017

• Late 2015: HCMS Stabilized the Project

• Early 2016: Disassembly of Plant Components

• Feb-Aug 2016: Off-site Component Repairs

• May-June 2016: Crane Repair and Installation

• April 2016: Boards Authorized Stator Rewind

• May-July 2016: Stator Rewind

• June-October 2016: Reassembly of Plant

• Nov 2016 – Feb 2017: Commissioning

Page 30: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Generator Rewind

4/8/2017

• Based on inspections during repair of damage to stator core

laminations a rewind was recommended

• Developed rewind bid documents and issued bid documents

• Evaluated bids and awarded a contract for stripping coils and

installing new to National Electric Coil (NEC)

• After coils were manufactured HCMS took short break while

installed new windings

Page 31: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

Page 32: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

Page 33: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Runner Install – Part 24/8/2017

• While rewind was underway 300 ton mobile crane used to service work

• Meanwhile powerhouse crane components are repaired/replaced

• HCMS weld repairs rotor spider following EME fracture mechanics analysis

• HCMS begins reassembly of unit in July 2016 following rewind

• Other work included: headcover line bored for wicket gate bushings, discharge

ring machined, wicket gate stems repaired, bracket weld repairs, etc.

• Unit alignment complete in November 2016

• Unit water up attempted mid-November 2016, but leakage from wicket gate

cartridges causes delay

• Corp of Engineers ladder outage (December 2016 through January 2017) delays

commissioning to February 2017.

• Commissioning begins February 7 and is complete February 12, 2017

Page 34: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

Page 35: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

Page 36: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Commissioning4/8/2017

Page 37: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

Page 38: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.0

11.0

12.0

40 45 50 55 60 65 70 75 80 85 90 95 100

Tu

rbin

e O

utp

ut

(MW

)

Servo %

Turbine Power vs. Servo %

Page 39: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

4/8/2017

Commissioning Conclusions

• Runner met guaranteed output

• Load rejection unit speed rise and pressure rise acceptable

• Generator temperature rise acceptable

• Bearing temperatures acceptable

• Vibration levels below maximum allowable

Page 40: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Lessons learned

4/8/2017

• Purchasing Chinese equipment is risky – extreme vetting is

needed

• Weld repair of CA6NM castings very difficult

• Crane load testing isn’t the final word

• Need a good team to recover from an extreme situation

• Be prepared to respond to changed conditions based on

disassembly inspections

• Watch out for bad paint system specifications

Page 41: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Acknowledgements

4/8/2017

• NWCPUD and KPUD staff

• HCMS

• American Hydro

• National Electric Coil

Congratulations to Bob Guidinger on his retirement!

Page 42: Commissioning McNary Fishway Hydro Project · History & Lessons Learned McNary Northshore Fishway Hydro Project ... Disassembly of Plant Components ... headcover line bored for wicket

Questions?

4/8/2017