Top Banner
CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production and installation schedule Aging test Extended documentation on each item can be found at http://www.ba.infn.it/~iaselli/annual_review_2003/
36

CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

Mar 26, 2015

Download

Documents

Julia Turner
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

CMS

RESISTIVE PLATE CHAMBERS

Lecce, 25 September 2003

Content

Barrel single/double gap production and QC

Barrel chamber production and QC

Barrel production and installation schedule

Aging test

Extended documentation on each item can be found at

http://www.ba.infn.it/~iaselli/annual_review_2003/

Page 2: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Introduction

Introduction CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

GTHT

Bari

Pavia

Introduction

Sofia

The sites involved in the RPC construction are:

•gap production General Tecnica•double-gap prod General Tecnica•chamber assembling Bari, Sofia*, GT and HT**•chamber test Bari, Sofia* and Pavia**** from the 2004** from june 2003** from june 2003

The sites involved in the RPC construction are:

•gap production General Tecnica•double-gap prod General Tecnica•chamber assembling Bari, Sofia*, GT and HT**•chamber test Bari, Sofia* and Pavia**** from the 2004** from june 2003** from june 2003

NA 2fe 4.7 feNA 2fe 4.7 fe

Page 3: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

SG and DG validation flow-chartSG and DG validation flow-chart

DG assembled by GTDG assembled by GT

Gas leakage testGas leakage test

Control the gap “bubbles” in 30 sControl the gap “bubbles” in 30 s

Bring the DG at 9500V and measure the current:

reject if I > 5 A

Bring the DG at 9500V and measure the current:

reject if I > 5 A

2 SG validated by QC32 SG validated by QC3

SG couplingSG coupling

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Single/Double Gap

Production and QC

Single/Double Gap Production and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

SG assembled by GTSG assembled by GT

Gas leakage testGas leakage test

Overpressure testOverpressure test

Control the gap “bubbles” in 30 sControl the gap “bubbles” in 30 s

Reach an inside overpressure of 20 mbar: check if spacers or frame detach

Reach an inside overpressure of 20 mbar: check if spacers or frame detach

GT connects the HV wire.The SG type is assigned

GT connects the HV wire.The SG type is assigned

Bring the SG at 9500V and measure the current: reject if I > 5 A

Bring the SG at 9500V and measure the current: reject if I > 5 A

Page 4: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

SG Rejected/Accepted vs. SG_IDSG Rejected/Accepted vs. SG_ID

0102030405060708090

100

1-10

0

101-

200

201-

300

301-

400

401-

500

501-

600

601-

700

701-

800

801-

900

901-

1000

RejectedAccepted

The “gluing” crisisThe “gluing” crisis

Rejection is slowing decreasing ... SG are better quality now

Fully Tested 817

Accepted 81.40%

Rejected 19.60%

Fully Tested 817

Accepted 81.40%

Rejected 19.60%

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Single/Double Gap

Production and QC

Single/Double Gap Production and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 5: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

SG Test RejectionsSG Test Rejections

RejectionsPressure Test 133 87.50%HV Test 19 12.50%

Pressure Test HV Test

HV failures distributed (significantly?) more frequently in the first SG Types produced: RB3 and RB1

0

0.5

1

1.5

2

2.5

3

3.5

4

RB1 RB2-2 RB2-3 RB3

Rejected (%)

HV test

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Single/Double Gap

Production and QC

Single/Double Gap Production and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 6: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

SG Current distributionsSG Current distributions

0

50

100

150

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

I (uA)

# of

Sin

gleG

ap HV=9500V

0

50

100

150

200

250

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

I (uA)

# of

Sin

gleG

ap

HV=8000V From Jan 15th, 2003 on, HV tests are performed

up to 9500V, with a 96.5%

C2H2F4/3.5% iso-C4H10 gas mixture (*)

From Jan 15th, 2003 on, HV tests are performed

up to 9500V, with a 96.5%

C2H2F4/3.5% iso-C4H10 gas mixture (*)

be as close as possible to real operating conditions

Some of the older SG retested

*Before Jan 2002 HV test were performed in pure C2H2F4 up to 8 kV

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Single/Double Gap

Production and QC

Single/Double Gap Production and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 7: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

SG Rejected/Accepted per typeSG Rejected/Accepted per type

Fully tested Accepted Rejected Pressure Fail. HV Fail.RB1 206 182 24 15 7RB2-2 159 110 49 47 2RB2-3 151 144 7 7 0RB3 271 229 42 33 9RB4 6 6 6 0No Type 24 24 24 0

Fully tested Accepted Rejected Pressure Fail. HV Fail.RB1 206 182 24 15 7RB2-2 159 110 49 47 2RB2-3 151 144 7 7 0RB3 271 229 42 33 9RB4 6 6 6 0No Type 24 24 24 0

0

5

10

15

20

25

30

35

RB1 RB2-2 RB2-3 RB3

Rejected (%)

Press. Failure

HV Failure

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Single/Double Gap

Production and QC

Single/Double Gap Production and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 8: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

SG Breakdown overpressuresSG Breakdown overpressures

02468

101214

1-5 6-10 11-15 16-20

Overpressure (mbar)

SG rejected

Warning: data on breakdown overpressures available only from SG 522 on

Warning: data on breakdown overpressures available only from SG 522 on

The first peak is mainly due to SG presenting spacers already detached at the beginning of the test ... When opened, sometimes, they presented small or missing glue on them.

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Single/Double Gap

Production and QC

Single/Double Gap Production and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 9: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

SG Production ImprovementSG Production Improvement

Tested Accepted Rejected Tested Accepted RejectedMay-Oct 2002 May-July 2003

RB1 101 85 16 83 78 5

Dic 2001-March 2002 March-June 2003RB3 166 132 34 92 87 5

Tested Accepted Rejected Tested Accepted RejectedMay-Oct 2002 May-July 2003

RB1 101 85 16 83 78 5

Dic 2001-March 2002 March-June 2003RB3 166 132 34 92 87 5

0

5

10

15

20

25

1st Per 2nd Per 1st Per 2nd Per

Rejections RB1 (%)

Rejections RB3 (%)

Comparison between production of the same kind

of SG in different periods

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Single/Double Gap

Production and QC

Single/Double Gap Production and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 10: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

DG Production StatusDG Production Status

Fully Tested 311

Accepted 96.10%

Rejected 3.90%

Fully Tested 311

Accepted 96.10%

Rejected 3.90%

Fully tested Accepted RejectedRB1 93 89 4RB2-2 55 52 3RB2-3 60 60 0RB3 120 115 5

Fully tested Accepted RejectedRB1 93 89 4RB2-2 55 52 3RB2-3 60 60 0RB3 120 115 5

0

1

2

3

4

5

6

RB1 RB2-2 RB2-3 RB3

Rejected (%)

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Single/Double Gap

Production and QC

Single/Double Gap Production and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 11: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

DG: Problems and ImprovementsDG: Problems and Improvements

Discharges: in some DG, a discharge between the gap edge and the copper ground plane has been found (mostly on the side were solderings with the termination resistors are made). This was evident at a later stage, when DG had already been included in CH.

From the production of the RB2 on, an additional “C” made of PET has been added; some of the older DG have been modified

Average current absorbed by a SG (in DG) before PET:

2.32 µA @ 8 kV

Average current absorbed by a SG (in DG) after PET:

0.83 µA @ 8 kV

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Single/Double Gap

Production and QC

Single/Double Gap Production and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 12: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

Chamber production status

20 RB1 chambers have to be modified (11 already modified at HT)See later for the problem found 20 chambers ready to be tested

4 chambers under test at PAVIA

Assembled chambers

Tested chambers

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 chamber

Production and QC

chamber Production and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

HT ( D. Piccolo) and Pavia (P.Vitulo) in operation

HT ( D. Piccolo) and Pavia (P.Vitulo) in operation

Page 13: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

QA/QC at assembly and test sites

Double gaps inventory

Cooling system test Gas flow test

LV system test Kapton-FEB connectivity test

DB update

HV test:I vs HVI vs time Noise rate strip by strip

QC during assembly

Check list filling

assembly

QC after assembly

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 chamber

Production and QC

chamber Production and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

HV connector mounting

DB update

Detector control

I vs. HVI vs. timeSingle rate vs. HV (strip by strip)T, P, Humidity mon.

Cosmic test

Efficiency vs. HV: - single gap - double gapCluster size vs. HvLocal efficiency withtracking

Chamber performances

Go to CERN

REJECTED ACCEPTED

Page 14: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

REJECTED

First 7 chambers assembled at HTNo SF6 in gas mixture

First 7 chambers assembled at HTNo SF6 in gas mixture

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Chamber

production and QC

Chamber production and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Current: summary

Dark current distribution at at 9400 V.

Dark current distribution at at 9400 V.

Dark current at working voltage

0

10

20

30

40

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Dark current (uA)

nu

mb

er

of

RP

Cs

rejected

accepted

Page 15: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

Efficiency: summary

HV at maximumefficiency

Lower efficiencydue to systematicEffects.

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Chamber

production and QC

Chamber production and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 16: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

Noise: summary

accepted

rejected

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Chamber

production and QC

Chamberproduction and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 17: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

Cluster: summary

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Chamber

production and QC

Chamberproduction and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 18: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

Chamber stability

Monitor of the Dark current for several days

DW

UP

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Chamber

production and QC

Chamber production and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 19: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

Final tests at ISR

Accepted chambers are sent to CERN and tested again at ISR.• I vs HV• I vs time• data taking with cosmics (work in progress)

Accepted chambers are sent to CERN and tested again at ISR.• I vs HV• I vs time• data taking with cosmics (work in progress)

About 70 chambers at ISR under test

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Chamber

production and QC

Chamber production and QC CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 20: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

The new production schema is based on the following assumptions:

--------------------------------------------------------------------------------------------

ITEM 2003 2004 2005

--------------------------------------------------------------------------------------------

gap production rate 3/day 4/day 5/day

double-gap prod. rate* 6-8/week 8/week 10/week

chamber prod rate** 2-3/week 4/week 5/week

chamber test rate*** 10/2weeks 10-5/2weeks 10-5/2weeks

The new production schema is based on the following assumptions:

--------------------------------------------------------------------------------------------

ITEM 2003 2004 2005

--------------------------------------------------------------------------------------------

gap production rate 3/day 4/day 5/day

double-gap prod. rate* 6-8/week 8/week 10/week

chamber prod rate** 2-3/week 4/week 5/week

chamber test rate*** 10/2weeks 10-5/2weeks 10-5/2weeks

* 6 bigaps/week if GT is assembling chambers too; 8 bigaps/week if not** GT 2 chambers/week; Bari, Sofia and HT 4 chambers/week*** Bari 10 chambers/2weeks; Pavia and Sofia 5 chambers/2weeks

phase I (from October 2003 to April 2004):

24 sectors 186 chambers 396 bigaps 792 gaps

phase II (from May 2004 to December 2004):

13 sectors 109 chambers 248 bigaps 608 gaps

phase III (from January 2005 to June 2005):

13 sectors 109 chambers 248 bigaps 608 gaps

phase IV (from July 2005 to April 2005):

10 sectors 80 chambers 179 bigaps 438 gaps

phase I (from October 2003 to April 2004):

24 sectors 186 chambers 396 bigaps 792 gaps

phase II (from May 2004 to December 2004):

13 sectors 109 chambers 248 bigaps 608 gaps

phase III (from January 2005 to June 2005):

13 sectors 109 chambers 248 bigaps 608 gaps

phase IV (from July 2005 to April 2005):

10 sectors 80 chambers 179 bigaps 438 gaps

Production scheme and rate

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Production and

installatin schedule

Production and installatin schedule CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 21: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

gap production (all)

0

200

400

600

800

1000

1200

1400

1600

1800

2000

2200

2400

2600

2800

3000

gen-02

mar-02

mag-02

lug-02

set-02

nov-02

gen-03

mar-03

mag-03

lug-03

set-03

nov-03

gen-04

mar-04

mag-04

lug-04

set-04

nov-04

gen-05

mar-05

mag-05

lug-05

set-05

nov-05

gen-06

date

# of

gap

s

producedplanned

stopped

20 gaps/week8 bigaps/week4 chambers/week

25 gaps/week10 bigaps/week5 chambers/week

15 gaps/week6 bigaps/week3 chambers/week

3% of rejected bigap 20% of rejected gapare included

Gap production

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Production and

installatin schedule

Production and installatin schedule CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 22: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

bigap production (all)

0

200

400

600

800

1000

1200

date

# of

big

aps

produced

planned

10 bigaps/week

8 bigaps/week

6 bigaps/week

3% of rejected bigap are included

Double gap production

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Production and

installatin schedule

Production and installatin schedule CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 23: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

chamber production (all)

0

50

100

150

200

250

300

350

400

450

500

gen-

02

mar

-02

mag

-02

lug-

02

set-

02

nov-

02

gen-

03

mar

-03

mag

-03

lug-

03

set-

03

nov-

03

gen-

04

mar

-04

mag

-04

lug-

04

set-

04

nov-

04

gen-

05

mar

-05

mag

-05

lug-

05

set-

05

nov-

05

gen-

06

date

# of

cha

mbe

rs

produced

planned

3 chambers/week 4 chambers/week 5 chambers/week

Chamber production

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Production and

installatin schedule

Production and installatin schedule CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 24: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

chamber producton per site (all)

0

50

100

150

200

250

300

350

400

450

500

date

# of

cha

mbe

rs

cham. HT

cham. GT

cham. BA/SF

Cham integral

BA/SF is only SOFIA in the 2004 and 2005TOTAL # of chambers

hot period in GT

Chamber production per site

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Production and

installatin schedule

Production and installatin schedule CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 25: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

Critical pathCritical path

Installation sequence

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Production and

installatin schedule

Production and installatin schedule CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

RPC chamber sequence installationname wheel # chamber when done to do tot instal.

RB3 W+1 10 nov-03 10 0 10RB2/2 W+1 5 nov-03 5 0 15RB2/3 W+1 5 nov-03 5 0 20RB3 W+2 10 nov-03 10 0 30

RB2/2 W+2 5 nov-03 5 0 35RB2/3 W+2 5 dic-03 5 0 40RB2/2 W-1 2 dic-03 2 0 42RB2/3 W-1 2 dic-03 2 0 44RB3 W-1 4 dic-03 4 0 48RB1 W0 down 10 gen-03 7 3 58

RB2/2 W0 down 5 gen-03 5 0 63RB2/3 W0 down 5 gen-03 0 5 68RB3 W0 down 10 gen-03 10 0 78RB1 W+2 10 feb-04 0 10 88RB1 W+1 10 feb-04 8 2 98RB1 W-2 4 feb-04 0 4 102

RB2/2 W-2 2 feb-04 2 0 104RB2/3 W-2 2 feb-04 2 0 106RB3 W-2 4 feb-04 4 0 110RB1 W-1 4 mar-04 0 4 114RB4 W0 (9-10-11) 4 mar-04 0 4 118RB4 W+1 (9-10-11) 4 mar-04 0 4 122RB4 W+2 (9-10-11) 4 mar-04 0 4 126

RB1 W0 up 10 apr-04 2 8 136RB2/2 W0 up 5 apr-04 5 0 141RB2/3 W0 up 5 apr-04 2 3 146RB3 W0 up 10 apr-04 10 0 156

RB4 m W0 up 8 apr-04 0 8 164RB4 l W0 up 0 apr-04 164RB4 s W0 up 4 apr-04 0 4 168RB4 m W+1 4 0 4 172RB4 l W+1 2 0 2 174RB4 s W+1 2 0 2 176RB4 m W+2 4 0 4 180RB4 l W+2 2 0 2 182RB4 s W+2 2 0 2 184RB4 m W-1 2 0 2 186RB4 l W-1 0 186RB4 s W-1 1 0 1 187RB4 m W-2 2 0 2 189RB4 l W-2 0 189RB4 s W-2 1 0 1 190

190 105 85

Page 26: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

What is ready

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Production and

installatin schedule

Production and installatin schedule CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 27: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

What is ready

RB2, RB3 YB+2 bottom ReadyRB2, RB3 YB+1 bottom ReadyRB2, RB3 YB-1 sec 8-9 Ready

RB3, RB2 YB0 bottom November 03RB1 YB0 bottom Dicember 03

RB1 YB+1 bottom March 04RB1 YB+2 bottom March 04RB3 YB-2 sec 8-9 ReadyRB2 YB-2 sec 8-9 October 03

RB2, RB3 YB+2 bottom ReadyRB2, RB3 YB+1 bottom ReadyRB2, RB3 YB-1 sec 8-9 Ready

RB3, RB2 YB0 bottom November 03RB1 YB0 bottom Dicember 03

RB1 YB+1 bottom March 04RB1 YB+2 bottom March 04RB3 YB-2 sec 8-9 ReadyRB2 YB-2 sec 8-9 October 03

RB1 YB-2 sec 8-9 March 04RB1 YB-1 sec 8-9 March 04

RB4 YB0 sec 10 February 04RB4 YB+1 sec 10 February 04RB4 YB+2 sec 10 February 04RB4 YB0 sec 9,11 March 04RB4 YB+1 sec 9,11 March 04RB4 YB+2 sec 9,11 March 04

RB1 YB-2 sec 8-9 March 04RB1 YB-1 sec 8-9 March 04

RB4 YB0 sec 10 February 04RB4 YB+1 sec 10 February 04RB4 YB+2 sec 10 February 04RB4 YB0 sec 9,11 March 04RB4 YB+1 sec 9,11 March 04RB4 YB+2 sec 9,11 March 04

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Production and

installatin schedule

Production and installatin schedule CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 28: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

HV/LV

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 HV/LV

HV/LVCMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Dopo aver: • definito i “requirements”;• attentamente analizzato tutte le possibili configurazioni;• studiato il prototipo nato dalla collaborazione I.N.F.N.-

CAEN;• analizzate le altre ditte disposte a produrre i sistemi;• provato diversi modelli di connettori e cavi;• studiato e disegnato il modello del routing dei cavi;

siamo giunti alle seguenti conclusioni:1. bisogna ridurre il numero di canali di HV

da 1020 a 480 e quelli di LV da 1560 a 720;

1. Il sistema di HV è in Control Room, i LV sul Detector;

2. La CAEN è l’unica ditta capace di produrre oggi l’HV;

3. Il costo totale per i due sistemi è di 720 K€ (± 10%);

60 settori:12 LV + 8 HV1 + 1,33 boards

HV ch. 480

HV board 80

HV crate 12

LV ch. 720

LV boards 60

LV crate 20

HV 500 K€

LV 220 K€

Siamo pronti ad “ordinare” l’HV.Per i LV aspettiamo la contrattazione di CMS riduzione del costo ?

Page 29: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

Two different systems under test:

• High statistics test with small single gap chambers

•Test of production chambers (RB1s)

Two different systems under test:

• High statistics test with small single gap chambers

•Test of production chambers (RB1s)

Aim of the aging tests

Test the RPC under high gamma irradiation with and without the muon beam and monitor the performance for a collected charge equivalent to 10 years of operation at LHC condition

Test the RPC under high gamma irradiation with and without the muon beam and monitor the performance for a collected charge equivalent to 10 years of operation at LHC condition

Operation conditions in CMS Barrel

Rate: 30 Hz/cm2 (safety factor included)

Average total charge: 30 pC

Effective operation time: 5x107 s (10 LHC years)

Operation conditions in CMS Barrel

Rate: 30 Hz/cm2 (safety factor included)

Average total charge: 30 pC

Effective operation time: 5x107 s (10 LHC years)

The total expected charge is 5 10-2 C/cm2

LHCC comprehensive reviewCERN 23 September 2003

LHCC comprehensive reviewCERN 23 September 2003 Aging tests

Aging tests CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 30: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

down forw

Integrated charge

Accumulated charge by small gapsAccumulated charge by small gaps

Old gaps :> 10 years LHC equivalentreached in the OLD gaps

New gaps:~ 10 year LHC equivalent

Old gaps :> 10 years LHC equivalentreached in the OLD gaps

New gaps:~ 10 year LHC equivalent

LHCC comprehensive reviewCERN 23 September 2003

LHCC comprehensive reviewCERN 23 September 2003 Aging tests

Aging tests CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Chamber 250.028

Accumulated charge by the two RB1Accumulated charge by the two RB1

Chamber 26

up forw

0.025

Page 31: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

Performance of small gaps

Ch 3Ch 3

A slightly increase of operation voltage with source ON & Off

V eff90% (Source On) - V eff90% (Source Off)

A slightly increase of DV during the time

HV constant = 10. kV

Ch BCh B

LHCC comprehensive reviewCERN 23 September 2003

LHCC comprehensive reviewCERN 23 September 2003 Aging tests

Aging tests CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 32: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

Test with water on RPC #9

Motivation: Possibile increase of the bakelite resistivity due to the high gas flux

Since May until Sept:

• No gamma irradiation

• High gas flux rate (3 l/hour) 6 gas change/hour!!!

Since Sept. up to now: wet mixture

Iincrease of rate with wet mixture

Full efficiency with source restored

LHCC comprehensive reviewCERN 23 September 2003

LHCC comprehensive reviewCERN 23 September 2003 Aging tests

Aging tests CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 33: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

Efficiency@ 9200V 9 Sept.

Source OFFSource OFF

Performance of RB1s

cosmic beam

29 June

LHCC comprehensive reviewCERN 23 September 2003

LHCC comprehensive reviewCERN 23 September 2003 Aging tests

Aging tests CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

9 Sept.

29 June

Abs 1Abs 1

beam

Page 34: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

On 9 September the chambers were closer to the source 9 Sept about 800 Hz/cm2

29 June about 200 Hz/cm2

On 9 September the chambers were closer to the source 9 Sept about 800 Hz/cm2

29 June about 200 Hz/cm2

Performances of RB1s

Eff

icie

ncy

(%

)

9 Sept.

abs10

abs2

abs1

Off

LHCC comprehensive reviewCERN 23 September 2003

LHCC comprehensive reviewCERN 23 September 2003 Aging tests

Aging tests CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 35: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

Minimize the effort at GIF and concentrate on gas issues. Continue aging with the gas close loop system now in in operation at GIF.

Study the effectiveness of the filters to absorb all the impurities.

Optimise the following parameters versus impurities and chambers performance: -) percentage of gas recirculation -) gas flow rate -) percentage of humidity in the mixture

Minimize the effort at GIF and concentrate on gas issues. Continue aging with the gas close loop system now in in operation at GIF.

Study the effectiveness of the filters to absorb all the impurities.

Optimise the following parameters versus impurities and chambers performance: -) percentage of gas recirculation -) gas flow rate -) percentage of humidity in the mixture

Future plans

LHCC comprehensive reviewCERN 23 September 2003

LHCC comprehensive reviewCERN 23 September 2003 Aging tests

Aging tests CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Page 36: CMS RESISTIVE PLATE CHAMBERS Lecce, 25 September 2003 Content Barrel single/double gap production and QC Barrel chamber production and QC Barrel production.

Conclusions

INFN Gruppo I Lecce, 25 September 2003

INFN Gruppo I Lecce, 25 September 2003 Conclusion

Conclusion CMS RPC group

G. Iaselli

CMS RPC groupG. Iaselli

Barrel SG and DG production is going well and on schedule

Barrel chamber production almost on schedule.

New assembly sites and test sites operational.

GIF test on the way. Satisfactory results so far.

Worst is coming!! Manpower to run in parallel assembly/test sites, ISR and GIF may not be available.

Barrel SG and DG production is going well and on schedule

Barrel chamber production almost on schedule.

New assembly sites and test sites operational.

GIF test on the way. Satisfactory results so far.

Worst is coming!! Manpower to run in parallel assembly/test sites, ISR and GIF may not be available.