Page 1
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 1
File Name: ID-MEN-TNG-PDD Version 2.1
CLEAN DEVELOPMENT MECHANISM
PROJECT DESIGN DOCUMENT FORM (CDM-PDD)
Version 03 - in effect as of: 28 July 2006
CONTENTS
A. General description of project activity
B. Application of a baseline and monitoring methodology
C. Duration of the project activity / crediting period
D. Environmental impacts
E. Stakeholders‟ comments
Annexes
Annex 1: Contact information on participants in the project activity
Annex 2: Information regarding public funding
Annex 3: Baseline information
Annex 4: Monitoring plan
Page 2
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 2
File Name: ID-MEN-TNG-PDD Version 2.1
SECTION A. General description of project activity
A.1 Title of the project activity:
Title: “MEN-Tangerang 13.6MW Natural Gas Co-generation Project”
Version: Version 2.1
Date of Completion: 27 April 2007
A.2. Description of the project activity:
PT Manunggal Energi Nusantara (“MEN”) is developing a cogeneration project using natural gas as fuel.
The electricity the Project generates will be supplied to three textile manufacturing companies: PT Argo
Pantes; PT Argo Beni; and PT Argo Fajar; while steam will be supplied to PT Argo Pantes. The Project is
located within the PT Argo Pantes (hereafter referred as “Argo Pantes”) bonded zone in an industrial area
of Tangerang, in Greater Jakarta, Indonesia.
Project Activity
The purpose of the Project is generation of 13.6MW of electricity and 9.5tonnes per hour of high quality
steam at 8-10 bar pressure for industrial users who are currently using grid electricity and generating
steam from fuel with higher carbon intensity than natural gas. The Project scope is the installation of five
natural gas power generators; each is equipped with a waste heat recovery boiler.
The delivered electricity will replace part of the electricity needs of Argo Pantes, Argo Beni and Argo
Fajar (or “industrial users”), which are currently purchased from the grid. The steam will be sold only to
Argo Pantes and will replace the equivalent amount of thermal generation activity at Argo Pantes‟ site.
By replacing both grid electricity and fuel with higher carbon intensity than natural gas, the Project can
reduce green-house-gas emissions by 56,909 tCO2 a year.
Thermal Situation at Argo Pantes
At present, Argo Pantes requires 35.5T/hr or less steam to run its textile machineries. Due to current
business climate, Argo Pantes does not run its machineries at full capacity and this demand therefore does
not represent the potential maximum steam demand at Argo Pantes facility.
Table 1 shows Argo Pantes‟ steam demands and its current steam generating facilities and dispatch order.
Following increasing price of oil-based fuel in 2002, Argo Pantes switched from using residual oil boiler
to coal boilers as its primary heat generating source. With this switched, Argo Pantes residual oil boilers
becomes redundant and operated only when steam demand surpassed the capacity serviceable by the coal
boilers.
Table 1 - Boiler Despatch Order at Argo Pantes before the Project
Dispatch Rank No. of boilers Boiler Fuel Type Operation Status
Total Steam
Generating
Capacity (T/hr)
Current Demand
35.5T/hr
Potential Full
Demand
43T/hr
1 2 units Coal 27T/hr
27T/hr
27 (T/hr)
2 8 units Residual oil 8.5T/hr 16T/hr
50.4 (T/hr)
Page 3
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 3
File Name: ID-MEN-TNG-PDD Version 2.1
Total
77.4
Total
35.5T/hr
43T/hr
The Project’s Impact
The Project implementation changes the dispatch order of all heat generating equipments at Argo Pantes.
After the Project, steam provided by MEN will be the primary steam generating source as long as it
maintains to be more economical to purchase compared to the cost to operate the coal boilers.
The new dispatch order is presented in the following table.
Table 2 – Boiler Despatch Order after the Project
Dispatch Rank No. of boilers Boiler Fuel Type Operation Status
Total Steam
Generating
Capacity (T/hr)
Current Demand
35.5 T/hr
Potential Full Demand
43T/hr
1 MEN‟s
cogeneration
system
Natural Gas
purchased from
MEN‟s Project
9.5T/hr 9.5T/hr
9.5T/hr
2 2 units Coal 26T/hr
(1 T/hr spare
capacity)
27T/hr
27 T/hr
3 8 units Residual oil Not Running 6.5T/hr
50.4 T/hr
Total
77.4
Total
35.5T/hr
43T/hr
By comparing Table 1 and Table 2, it is demonstrated that at demand of 35.5T/hr, steam from residual oil
boilers and 1 T/hr of steam from coal are eliminated. At potential full demand, the coal boiler will run at
full operation and the residual oil boiler generation is reduced from 16T/hr to 6.5T/hr or reduction of
9.5T/hr.
Despite the possibility that the Project will partially displace coal boiler heat generation, for sake of
simplification and conservativeness, it will be assumed that the Project displaces only the residual oil
boiler operations.
Residual oil is therefore deemed appropriate as the „baseline fuel‟ for the Project.
Contribution to Sustainable Development
Utilization of Cleaner Fuel
The Project supports sustainable development by adopting a cleaner fuel for power and thermal
energy provision. The Project displaces the operation of residual oil boilers operation and potentially
reduces the load of the coal boilers at Argo Pantes. In addition to reducing GHG emissions and its
associated impact to climate, this reduction also assists in combating air pollution in the greater
Jakarta area - in line with Jakarta‟s administration recent campaign for cleaner air.
Without the Project, the current textile facilities will continue to:
generate steam using fuel with higher carbon intensity than natural gas; and
utilize electricity from the grid that is generated by power plants powered by fossil fuel with
higher carbon intensity than natural gas.
Page 4
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 4
File Name: ID-MEN-TNG-PDD Version 2.1
Energy Efficiency Practise
The cogeneration technology employed by the Project enables heat and electricity to be produced on
a single site. This operation reduces the total amount of energy used by recovering heat in the gas
engine‟s exhaust. The Project reduces as much as 24.8% (see Annex 5.1) of the energy previously
used to generate the same amount of power and heat even before accounting for transmission loss
which stands at 11.5% of generated electricity (at source) according to a PLN Report in 20051, and
consequently contributes to sustainable development by reducing residual fuel demand.
A.3. Project participants:
Table 3 - Project Participants
Name of party involved Private and/or public entities as project
participants
Indication if party involved is
considered as project
participant
Indonesia (host) PT Manunggal Energi Nusantara No
Japan Mitsubishi UFJ Securities Co. Ltd. No
The Project is wholly owned and operated by PT Manunggal Energi Nusantara which will enter into a
direct electricity purchase agreement with PT Argo Pantes, PT Argo Beni and PT Argo Fajar and thermal
sales agreement with PT Argo Pantes. The electricity delivery will be via a private electricity mini grid
and Argo Pantes‟ steam pipeline. The Project will not export any electricity to the PLN grid.
A.4. Technical description of the project activity:
A.4.1. Location of the project activity:
A.4.1.1. Host Party(ies):
Indonesia
A.4.1.2. Region/State/Province etc.:
Province of Banten
A.4.1.3. City/Town/Community etc:
The Project‟s geographical location relative to Jakarta, the capital city of Indonesia is
shown in Figure 1 in Section A.4.1.4.
The Project is located inside the Argo Pantes‟ textile manufacturing facility, Jl. MH
Thamrin KM4, Cikokol, City of Tangerang. The project location relative to its users are
shown in Figure 2 in Section A.4.1.4.
A.4.2. Category(ies) of project activity:
The Project falls under the following sectoral scopes:
Sectoral Scope 1 - Energy industries (renewable - / non-renewable sources)
Sectoral Scope 4 - Manufacturing industries
A.4.3. Technology to be employed by the project activity:
1 Based on PLN 2005 Annual Report
Page 5
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 5
File Name: ID-MEN-TNG-PDD Version 2.1
The Project involves the installation of five gas engines, each with maximum electrical output of
2,722kW and equipped with a Therm-plant Engine Steam Economizer (TESE) with overall heat
transfer capacity of 1,371kW. The TESE technology recovers heat from the hot gas engine
exhaust to generate 9.5tonnes per hour of superheated steam at 8-10bar pressure. All equipments
are supplied by GE Jenbacher and manufactured in Austria.
It is estimated that each engine will consume about 614m3/hr of natural gas with calorific value
of 45.54TJ/ktonnes and specific gravity of 0.6538 pipelined from an offshore field operated by
BP West Java and Pertamina via PT PGN‟s gas transmission infrastructure.
A.4.4 Estimated amount of emission reductions over the chosen crediting period:
Year Period Annual Estimation of emission
reductions in tonnes of CO2e
1 September 2007 – September 2008 58,961
2 September 2008 – September 2009 58,961
3 September 2009 – September 2010 58,961
4 September 2010 – September 2011 58,961
5 September 2011 – September 2012 58,961
6 September 2012 – September 2013 58,961
7 September 2013 – September 2014 58,961
Total estimated emission reduction in the first crediting period
(t-CO2/yr)
412,727
Total number of crediting year 7 years
Annual average of estimated reductions over the crediting
period (t-CO2/yr)
58,961
A.4.5. Public funding of the project activity:
The Project does not involve any public funding.
Page 6
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 6
File Name: ID-MEN-TNG-PDD Version 2.1
A.4.1.4. Detail of physical location, including information allowing the unique identification of this project activity (maximum one
page):
Project
Location
Page 7
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 7
File Name: ID-MEN-TNG-PDD Version 2.1
Figure 2 - Project site relative to its users
ARGO
FAJAR
ARGO
BENI
ARGO
PANTES
PROJECT
SITE
Page 8
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 8
File Name: ID-MEN-TNG-PDD Version 2.1
SECTION B. Application of a baseline and monitoring methodology
B.1. Title and reference of the approved baseline and monitoring methodology applied to the
project activity:
Methodology: AM0014 Version 03
Title: “Natural gas-based package cogeneration”
B.2 Justification of the choice of the methodology and why it is applicable to the project
activity:
Methodology AM0014 is applicable for this project activity for the following reasons:
The Project involves installation of a cogeneration system using natural gas operated by an
independent party. The consuming facilities or the end users do not own or operate the project
facility.
The Project will supply all of its electrical or thermal outputs to industrial users. This situation is
likely to remain so within the crediting period as the Project is situated within the location of one
of its industrial users and does not own or run any other activities other than heat and power
generation. It is also unlikely that the industrial user who owns the site allows the project
proponent to conduct other energy-consuming business activity within its site other than what has
been agreed.
The Project will not export any excess electricity to the public grid and do not export any excess
heat to another user. This condition is unlikely to change throughout the crediting period as the
developer business license covers for general electricity trading only which does not allow
electricity sales to the public grid. The physical location of the Project within its industrial users
eliminates the possibility of trading heat to other users.
The project activity satisfies all of the applicability conditions of the chosen methodology, and therefore
application of AM0014 is deemed appropriate.
B.3. Description of the sources and gases included in the project boundary
The following gases and emission sources are included in the project boundary. As indicated in Section
A, the baseline fuel to the Project is residual oil.
Sources Gases Comments
BASELINE Combustion of baseline fuel for the
generation of steam at Argo Pantes
CO2 Included. Major source of emission
CH4 Included. A minor source of emission
N2O Included. A minor source of emission
Production, distribution &
transportation of baseline fuel
CO2 Excluded. This is conservative
CH4 Excluded. This is conservative
N2O Excluded. This is conservative
Grid-electricity generations CO2 Included. A major source of emission
CH4 Excluded.
N2O Excluded.
PROJECT Natural gas combustion during
project activity
CO2 Included. A major source of emission
CH4 Included. A minor source of emission
N2O Included. A minor source of emission
Page 9
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 9
File Name: ID-MEN-TNG-PDD Version 2.1
Sources Gases Comments
Natural gas released during
production, transmission, storage and
distribution.
CO2 Excluded.
CH4 Included. A major source of emission
N2O Excluded.
B.4. Description of how the baseline scenario is identified and description of the identified
baseline scenario:
Baseline Scenario Identification Process
The most likely baseline scenario is identified by assessing the seven scenarios provided in the
methodology. As demonstrated under Section A2, the Project displaces residual oil boiler operation and
potentially coal boiler for heat generation at low peak demand.
Table 4 - Baseline Scenario Assessment
No. Scenarios Scenario applied to Project situations Credible
1 Industrial plants continue
to operate with equipment
replacement as needed,
with no change in
equipment efficiency
Power: All users continue to import electricity from PLN grid.
Heat: Argo Pantes continues to run its residual oil boilers.
Assessment:
This scenario is the continuation of current practise and therefore a
very credible situation for the following reasons:
1. Table 1 (p.2) shows that at full operation, Argo Pantes consumes
only 16T/hr of steam from its residual boilers.
This represents only 30% of all residual oil boilers capacity of
50.4T/hr. These boilers, although ageing, are in perfectly good
condition. Hence, when the service life of the current boiler ends,
Argo Pantes can simply use the next available residual oil boiler –
and therefore does not need to add residue boiler capacity during
the crediting period.
2. This scenario represents a no-investment option for all users –
which is the most preferred option considering the current
business climate for the textile industry in Indonesia which does
not encourage further capital spending.
Yes
2 Industrial plants continue
to operate with improved
efficiency new equipment
at the time of equipment
replacement
using a less carbon
intensive fuel
Power: All users continue to import electricity from PLN grid
Heat: Argo Pantes continues to operate its boilers and replace it with
new boilers at the end of the service life of the existing boilers. The
new boiler will use fuel with lower emission factor than the residual
oil.
Assessment: This scenario is not credible due to several factors:
1. The excess capacity in the residual oil boilers available to Argo
Pantes as explained in Scenario 1.
2. Apart from natural gas, the only other less carbon-intensive fuel
alternatives is diesel fuel and it‟s price per unit energy is
significantly higher than residual oil (see Table 5, p.11).
It is possible that if the price of residual oil becomes
unsustainable, Argo Pantes will invest in a more cost-effective
technology to replace the operation of these boilers. However, it is
No
Page 10
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 10
File Name: ID-MEN-TNG-PDD Version 2.1
No. Scenarios Scenario applied to Project situations Credible
likely the newly installed technology will use coal as fuel due to
its cost effectiveness as has been the demonstrated case,
historically.
In 2001, when Argo Pantes was confronted with the same
situation of hiking oil prices, the company slashed energy
expenditure through the installation of three coal boilers.
However, due to sluggish business climate in the textile industry,
only two out of the three planned coal boilers were implemented.
Since then, the additional capacity has left residual oil boilers as
redundant assets of the company.
It is therefore highly unlikely that Argo Pantes will invest in
boilers using cleaner fuel considering the significantly low price
of coal-based energy.
3 Industrial plant upgrades
thermal generating
equipment and therefore
increases the efficiency of
boiler immediately
Power: All users continue to import electricity from PLN Grid
Heat: Argo Pantes immediately upgrades its thermal generating
facility by installing a new boiler which immediately increases its
efficiency and heat output.
Assessment:
The scenario involving the retrofitting of the existing boilers is
unlikely. The current coal boilers were installed in 2002 and are still in
very good condition and run with high efficiency therefore the benefit
of retrofitting is only marginal. Similarly, the residual oil boilers are
available in excess capacity at Argo Pantes such that retrofitting these
units to gain a few extra capacities is not economical.
As elaborated in Scenario 2, it is more likely that Argo Pantes
upgrades its thermal facility by installing a new coal boiler when it
needs to do so due to increased activity. The third coal boiler was not
installed due to the unfavourable business climate, but is likely to be
implemented if Argo Pantes‟ activity returns to its full capacity.
If the Project can continue to provide economical thermal energy for
Argo Pantes through exhaust gas heat recovery, then it is likely that
the project activity prevents the industrial user to invest in coal
technology – even when Argo Pantes activity resumes to near its full
capacity.
No
4 The heat and electricity
demand of the industrial
plant is reduced through
improvements in end-use
efficiency
Power/Heat: Industrial users initiate energy efficiency programme
through power demand management that reduces its electricity and
heat consumption.
Assessment:
This scenario is highly unlikely as reduction of energy demand can
only happen through replacement of the current textile machineries
with newer ones employing technology with a higher efficiency.
However, the textile industry in Indonesia has been hit with an
increase in labour costs coupled with a sudden increase in energy costs
in 2005-2006 which is then followed with declining purchasing parity,
as well as global competition from China. Argo Pantes itself is
currently not running at full capacity due to a combination of these
factors.
As explained above, the industrial users are currently not in the best
No
Page 11
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 11
File Name: ID-MEN-TNG-PDD Version 2.1
No. Scenarios Scenario applied to Project situations Credible
financial position to invest in major textile machinery replacement in
the next few years.
5 Installation of a
cogeneration system
owned by the industrial
plant
Power/Heat: Argo Pantes, being the company with the larger demand
for thermal energy, invests in a self-owned cogeneration facility. Argo
Beni and Argo Fajar purchase electricity from Argo Pantes or PLN
Assessment:
Without a new investment from an independent company like MEN,
the industrial users will not invest in a new non-core business
technology with a less-economic cleaner fuel and technology.
As elaborated in Scenario 4, this is because the industrial users and
Indonesian textile industry in general suffers an economic downturn.
Consequently, investment in textile machineries to compete in global
market is higher on the textile manufacturer agenda than investment in
a non-core energy business.
No
6 Installation of a package
cogeneration system
owned by a company other
than the industrial plant
Power/Heat: An independent company invests in a new natural gas
cogeneration facility to provide heat and electricity for the industrial
users.
This scenario is the Project scenario without CDM and deemed
plausible until the additionality analysis in Section B.5. is conducted.
To be decided
in
Section
B.5
7 Installation of
cogeneration system by a
third party
This is the same as Scenario 6 above.
Table 5 – Fuel price comparison per unit energy
Fuel Type Local Price
in USD2
Unit for
Price
Density NCV Price per TJ Emission
Factor
Kg/L MJ/t kgCO2/TJ
Coal $ 40.003 /tonnes 25523 $ 1,567 96,100
Natural Gas $ 5.124 MMBTU $ 4,853 64,200
Residual Oil $ 0.305 L 0.88 40400 $ 8,435 77,400
Diesel Oil $ 0.475 L 0.89 43000 $ 12,406 74,100
From the above assessment it is clear that the following scenarios are plausible and credible as possible
candidates for the baseline scenario:
Scenario 1 - the continuation of current practise where all users continue to import electricity
from PLN Grid and Argo Pantes continues to operate its current boilers without replacement within
the crediting period; and
Scenario 6 – installation of a natural gas based cogeneration package by a company other than
the industrial users or the Project without CDM.
It will be demonstrated under the additionality assessment in Section B.5 that Scenario 6 faces barriers to
be implemented without CDM leaving only Scenario 1 as the baseline scenario.
2 Converted from Rupiah to USD with rate of Rp9,000 per USD
3 Based on the most widely available mid-rank coal with calorific value of 6,100kcal/kg
4 Based on values from PGN or state gas company
5 Based on values published by PERTAMINA (fuel supplier)
Page 12
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 12
File Name: ID-MEN-TNG-PDD Version 2.1
B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below
those that would have occurred in the absence of the registered CDM project activity (assessment
and demonstration of additionality):
The project proponent chooses to use “Tool for demonstration and assessment of additionality” version
03 to demonstrate the Project‟s additionality.
Step 1 - Identification of alternatives to the project activity consistent with current laws and
regulations
Sub-step 1a. Define alternatives to the project activity:
In Section B.4, it was identified that the following are possible alternatives to the proposed CDM
project activity:
a. Scenario 1 – continuation of current practise where all users continue to import electricity
from the PLN Grid and Argo Pantes continues to operate its current boilers.
b. Scenario 6 – the proposed Project without CDM
Sub-step-1b. Consistencies with mandatory laws and regulations:
In Indonesia, the control of pollutant gases such as NOx, SOx, particulate matter, CO and THC are
both mandatory and monitored by the environmental regulatory body. Emissions from the existing
boilers at Argo Pantes are continuously checked and meet the national ambient air quality standards
applied by the environmental regulatory body for these gases. The Project activity is therefore not the
only option that is in compliance with all applicable regulations.
As required under the applicable methodology, the project proponent must demonstrate additionality
through an investment analysis.
Step 2. Investment Analysis
Sub step 2a – Determine appropriate analysis method
The project proponent receives economic benefit other than CDM related income as the sold
electricity and steam generates revenue for the Project. Consequently, Option I (Simple Analyis) is
not appropriate and the available options are either Option II (Comparison Analysis) or Option III
(Benchmark Analysis). The project proponent chose to apply Option III to demonstrate the Project‟s
additionality.
Sub step 2b – Identification of appropriate benchmark
The project developer chose to use IRR as the financial indicator of choice. The chosen benchmark is
the Indonesian central bank (Bank Indonesia) inter-bank interest rate (SBI) plus additional 4%
premium normally charged by the lending bank. The central bank interest rate stands at 9.5% in
November 2006. Therefore the minimum benchmark IRR is 13.5% for 10years.
Considering other risks that the Project is exposed to including (1) currency mismatched between
costs and revenue, (2) Rupiah historical volatility, and (3) historically high inflation, an additional 3%
premium is applied to the benchmark totalling to 16.5% of internal rate return for 10 years.
This benchmark very conservative, as it is only marginally higher than the average lending rate up to
the fourth quarter of 2006 which is 16% as reported by business newspaper Jakarta Post in January
2007.
Sub step 2c – Calculation and comparison of financial indicators
Project capital cost & financing
The Project‟s total capital outlay is USD12,500,000 of which 35% is MEN‟s equity. The remainder is
financed through a USD loan with a ceiling rate of 11% per annum over 10 years.
Page 13
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 13
File Name: ID-MEN-TNG-PDD Version 2.1
Project Revenue
Revenue is derived from the sales of electricity and steam to the industrial users. To attract industrial
users to enter into a purchase agreement, MEN offered a lower rate pegged to market values for both
energy types – which guarantees lower-than-market energy price for the industrial users at any given
time;
Revenue from electricity sales
The Project is expected to generate a net electrical output of 95,052,000kWh of electricity
annually. This electricity will be absorbed by industrial users at a rate 3% below PLN usage
rate payable by Argo Pantes within a period or Rp582/kWh6 or USD0.065
7 at the time of
Project‟s economic evaluation.
The Project‟s annual revenue from electricity sales is expected to be IDR 53,660,790,000 or
USD 5,962,310.
Revenue from steam
The Project will generate 9.5 tonnes of steam per hour or 76,000 tonnes per year. The steam
selling rate is Rp57 per kg of steam or USD6.36 per tonne. The Project‟s annual revenue
from steam sales is expected to be IDR 4,350,240,000 or USD481,333.
MEN‟s electricity revenue is tied into PLN‟s rate – which is revisable only through
government regulation. Historically, increase in electricity rate has been sluggish and meets
large opposition. Consequently, the financial analysis was projected with annual growth rate
of 2.5%.
Project costs
The major costs are derived from the cost to purchase natural gas, and annual operation costs such as
man-power and maintenance.
Costs to purchase natural gas
In mid-2006 when the project was under evaluation, the natural gas price applicable to MEN
was USD5.12/MMBTU8 or USD4,858/TJ. The Project will consume circa 730.6TJ/yr of
natural gas or annual spending of USD3,549,066 per year.
At the end of 2006, the state gas pipeline company PT PGN announced that this rate will be
increased to USD5.50 or 7.4% increase by 2007 before the project commissioning. Based on
this price hike, international gas price of USD7, and outlook of natural gas demand
domestically and globally, the IRR calculation applies a conservative 7% annual increase of
natural gas price.
Overhead costs
Overhead cost for the Project consists of the cost to maintain the unit (spare parts, etc.) and
staff salaries and expected to be no more than 5% of the capital outlay or USD 625,000.
Considering local inflation of 17% in 2005 and 6.16% in 2006, it is expected that this costs
will rise by at least 5% annually in subsequent years.
Calculated IRR
6 PLN rate is based on a basic price compounded with progressive rate based on load, therefore will vary with usage.
This rate is calculated based on the industrial user electrical consumption.
7 Currency exchange rate stands at Rp9,000 per 1 USD is assumed for Project‟s economic evaluation in 2006
8 PGN rate is based on a material price compounded with transmission rate (or toll charges), therefore will vary with
usage. This rate is calculated based on the Project projected natural gas consumption.
Page 14
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 14
File Name: ID-MEN-TNG-PDD Version 2.1
As stipulated by the Tool for demonstration and assessment of additionality, for benchmark
investment analysis, IRR is to be calculated as a Project IRR, not equity IRR and therefore not taking
into account the costs to finance the Project.
Based on the above-mentioned revenues, costs, and projected growth, the calculated cash flow Project
IRR for 10 years is 5% - well below the previously set benchmark, and as stipulated in Tool for
demonstration and assessment of additionality is not a financially attractive investment.
Sub step 2d – Sensitivity analysis
Increased sales price of electricity
The Project revenue from electricity sales is 3% below PLN‟s rate. PLN rate is therefore the
maximum selling price for industrial users to use MEN‟s services. If the rate of electricity is
increased to equal with PLN rate, the IRR increased to 8%. If the PLN rate is increased by
5%, the IRR moves to 10%.
Increased sales price of steam
At the time of project economic assessment, Argo Pantes was able to produce steam using
coal at a rate of IDR60 per kg. The revenue contribution from steam sales is less significant
such that if the Project can increase the steam revenue to up to IDR65 per kg or 14% from the
original rate, the IRR is up by only 1% to 6%.
Increased sales and electricity revenue
If the rate of sales and electricity revenue described above are increased at the same time, the
IRR increases to 13%.
Lower capital expenditure
If the capital cost is lowered by 10%, the IRR improves to 10%.
Conclusion from sensitivity analysis
The sensitivity analysis above demonstrates that increases in revenues in addition to the
expected growth rate applied, improves the Project revenue only marginally. Consequently,
this shows that the financial model is robust and it can be concluded that the Project is not a
financially attractive investment without CDM.
Impact of CDM Revenue
CDM has been in an integral part of MEN‟s plans for the Project. MEN pursued CDM since August
2006 through consultation with MUS well before the company concluded an agreement with the
technology supplier GE Jenbacher.
Although an ERPA has not been concluded, CDM revenue is expected to increase the Project returns
to a level above the benchmark. The company‟s board of directors approved the investment on the
condition that the Project be pursued as a CDM project activity.
MEN‟s management believes that the CDM will assist the Project not only with additional revenues
from the sale of CERs, but also in giving the Project higher status and social recognition which will
help it ensure the uninterrupted supply of natural gas it requires for the continuation of the business.
Consistent with the “Tool for demonstration and assessment of additionality”, the Project‟s additionality
needs to be further demonstrated through a Common Practise analysis (Step 4).
Step 4. Common practise analysis
This project development is unique as it involves an independent company investing in a small scale
power project using a less economic and cleaner fuel than the standard industry practise without
Page 15
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 15
File Name: ID-MEN-TNG-PDD Version 2.1
selling electricity to the public grid. This arrangement (or so called “ESCO”) is almost non-existent in
Indonesia‟s power sector.
Sub-step 4a. Analyze other activities similar to the proposed project activity:
Project with similar business arrangement & technology
An ESCO arrangement, as interpreted in the methodology, is an arrangement where an
independent third party invests in a power/thermal facility located within the users‟
manufacturing facilities and sells the generated outputs to designated users directly without
going through public installations (grid or steam pipeline).
While this type of arrangement exists, it is not common in Indonesia and to the best
knowledge of the project developer, none are employing co-generation technology, ie
providing power only through conventional or combined cycle system. These establishments
are:
PT Cikarang Listrindo, Cikarang, a 1000MW combined cycle power station
PT Kabil Industrial Estate, Batam, a 48MW combined cycle power station
The project developer, PT Manunggal Energy Nusantara is an independent small-scale
energy service company investing in the energy sector. It is a recently established company,
and this Project is the first installation at the users‟ location with limited market.
Sub-step 4b Discuss any similar options that are occuring
Both of the above-mentioned entities were established and operated by the management of
industrial estates – with a wider committed buyer and better economy of scale. Both facilities
were built at the time of economic booming prior to Asian economic crises in 1997 and
signed power purchase agreement with PLN and long-term gas contract with PGN early on
with favourable rate compared to the Project. Consequently, these entities are not confronted
with barriers that are being faced by the project developer to implement the Project.
At only 13.6MW with no public electricity interest and favourable gas rate, it is clear that
Project is well outside the league of the afore-mentioned facilities. At this scale, MEN‟s
decision to proceed with natural gas deemed the company activity against the mainstream
business practise which favours coal. Therefore the project activity has no similar activities.
It is pertinent to note, the government of Indonesia promotes the utilization of natural gas as
one of the indigenous energy sources. However, the promotion is currently bottlenecked by
lack of gas transmission infrastructure between producing region (Sumatra & Borneo) and the
consuming region (Java). Transmitted gas is prioritized for usage in industries supporting
agriculture, strategic petrochemical, and project supporting public power sectors - excess are
sold to industrial users and has been historically plagued with interruptions.
The lack of infrastructure is not likely to end soon as domestic natural gas price structure
favours priority industries, which does not include the textile industry, and remains a barrier
for investment in natural gas pipeline. Priority industries – which mainly comprise of the
largest consumers of natural gas, is allowed to purchase gas well below the international price
leaving investment in gas pipeline infrastructure unattractive9.
This supply uncertainty coupled with higher natural gas price per energy remains a barrier for
industry players to rely on natural gas as primary energy source and favours coal. In 2006, the
critical needs of electricity and presumably limited alternative pushed the government to
9 The Gas Gamble, GlobeAsia, March 2007
Page 16
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 16
File Name: ID-MEN-TNG-PDD Version 2.1
initiate a power acceleration programme which involves the installation of 20,000MW of
low-rank coal power plants across the archipelago. A large proportion of this will be located
on the industrial Island of Java where the Project is located. This programme, particularly in
Java, has gained momentum with many foreign and local entities enter agreement with the
government of Indonesia to proceed with this plan. Upon full implementation of this plan, the
possibility of lower electricity tariff is not remote creating a harder environment for natural
gas based electricity to compete.
As elaborated under Sub-Step 4a and 4b, similar activities can be observed but there are clear
distinctions between the project activity and the identified similar activities. As stipulated by the Tool
for demonstration and additionality assessment, the project activity is additional.
B.6. Emission reductions:
B.6.1. Explanation of methodological choices:
BASELINE EMISSIONS
B.1 Baseline emission associated with the displacement of residual oil for heat generation,
The Project will displace approximately 9.5tonnes per hour of steam at 8-10 bar pressure that is currently
generated using residual oil at the baseline scenario. The amount of energy that would have been required
to generate this steam in the absence of the project (ABEC) is calculated based on the amount of heat
generated by the cogeneration plant and the efficiency of the residual oil boiler in the baseline situation or
equation 3.2 of the baseline methodology.
Equation 1
Where:
Variable Description Unit
ABEC Amount of energy that would have been consumed to generate heat in
the user‟s residual oil boiler
TJ/yr
CHOR Amount of heat generated by the Project TJ/yr
Efficiency of the baseline boiler. unitless
The green house gas emissions (CO2, CH4, and N2O) associated with ABEC is calculated by multiplying
ABEC with the emission factor of green house gas G from the combustion of baseline fuel in this case:
residual oil ( ) and the green house gas global warming potentials ( ).
Equation 2
Variable Description Unit
Baseline emissions from combustion of baseline fuel
(from CO2, CH4 and N2O)
t-CO2/yr
The amount of energy that would have been consumed to generate
steam in Argo Pantes‟ boiler
TJ/yr
Emission factor of green house gas g from the combustion of
baseline fuel.
t-gas /TJ
Page 17
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 17
File Name: ID-MEN-TNG-PDD Version 2.1
Global warming potential of greenhouse gas g. t-CO2
/t-gas
The emission factor from the baseline fuel (residual oil) is provided in the following table.
Table 6 – Emission Factors and Global Warming Potentials of greenhouse gases from residual oil
Emission factor from residual oil combustion CO2 CH4 N2O
Emission Factor of gas g in t-g/TJ, 77.4 0.003 0.0006
Global Warming Potential of gas g in t-CO2/t-g 1 21 310
Source for Emission Factor (default data used),
Table 2.2 Table 2.2 Table 2.2
2006 IPCC Guidelines for National
Greenhouse Gas Inventories
B.2 Baseline emission associated with grid-power displacement
The baseline emission from grid-power displacement is calculated based on the MWh produced by the
natural gas cogeneration unit multiplied by an emission coefficient, .
Equation 3
Variable Description Unit
Baseline emission from electricity grid displacement t-CO2/yr
The amount of electricity generated by the project net of its parasitic
consumption.
MWh/yr
Emission factor of the electricity grid t-CO2
/MWh
Calculation of combined margin emission coefficient,
As the Project‟s generating capacity is 13.6MWe falls below the 15MWe small-scale threshold, the
emission coefficient is calculated as a combined margin (CM) emission factor as prescribed by
methodology ID following the method described according to the approved methodology ACM0002
(Version 06).
The combined margin emission factor consists of the combination of operating margin ( ) and build
margin ( ) emission factors set ex-ante and calculated as the weighted average of both factors.
Equation 4
Variable Description Unit Monitored*
Combined Margin CO2 emission factor of power
plants connected the Java-Bali grid in year y.
t-CO2/MWh N/R
Operating Margin CO2 emission factor of power
plants connected at the Java-Bali grid in year y
t-CO2/yr Yes
Build Margin CO2 emission factor of power
plants connected to the Java-Bali grid in year y
t-CO2/TJ No
(ex-ante)
The Project is located on the Island of Java, the relevant boundary for the calculation of is the
power plants connected to the Java-Bali grid.
Page 18
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 18
File Name: ID-MEN-TNG-PDD Version 2.1
1. Operating Margin Emission Coefficient ( )
The OM calculations were based on combination of PLN10
published data for year 2004 to 2005 and 2006
data obtained directly from PT PLN (Persero) P3B11
Jawa-Bali using the Simple OM approach. This is
appropriate as (a) no dispatch data could be obtained, and (b) low-cost/must-run resources constitute less
than 50% of the Java-Bali grid as shown in Table 7 below.
Table 7 - Percentage of Low/Cost Must Run Resources
Source Generating Capacity (GWhr)
PLN Version Source Type 2006 2005 2004
PLTA (Hydroelectric) Renewable 5,208 6,248 5,428
PLTU Non-Renewable 64,629 37,264 37,033
PLTG Non-Renewable 1,891 4,749 2,148
PLTGU Non-Renewable 26,939 26,185 25,476
PLTP (Geothermal) Renewable 6,500 2,870 2,988
PLTD Non-Renewable 108 161 94
Purchased from IPP12
Renewable 23,477 22,236
Total Generation (GWh) 105,274 100,954 95,403
% of Low Cost/Must Run 11% 9% 9%
The operating margin emission coefficient for each year (Y) is calculated using Equation 2 of ACM0002
adapted to data available from PLN website which has grouped the power plant according to its fuel
usage.
Equation 5
Variable Description Unit
Operating Margin CO2 emission factor of power plants
connected at the Jawa-Bali grid in year Y
t-CO2
/MWh
Amount of fuel type j consumed by power plant connected to
electricity grid in year Y
kT
Net calorific value of fuel type j using default net calorific
value from Table 1.2 of 2006 IPCC Guideline
TJ/kT
CO2 emission factor of fuel type j obtained from Table 2.2 of
2006 IPCC Guideline
t-CO2/TJ
The generation capacity of power plant with non-renewable
fuel type j connected to the grid
MWh/yr
10 Indonesia State Electricity Company
11 Pengaturan dan Pusat Pengatur Beban (P3B) or Center for Electricity Control and Dispatch
12 Almost 20% of the total generated electricity is purchased by PLN from Independent Power Producers (IPPs)
using coal, geothermal, and hydro power plants. However PLN publication up to 2005 does not specify fuel
individual or specific consumptions from IPPs. For conservative estimate, these generation sources were added as
renewable energy – therefore does not have any impact to OM emission factor. The 2006 data includes this
information and therefore details are incorporated based on its generation source types.
Page 19
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 19
File Name: ID-MEN-TNG-PDD Version 2.1
Table 8 contains the Net Calorific Value (NCV) and CO2 Emission Factor (EFCO2) from each individual
fuel type used to calculate total emissions. NCV and EFCO2 Data for fuel oil is calculated as weighted
average between diesel oil and residue oil (marine fuel oil) based on 2006 fuel consumption data.
Table 8 - NCV and Emission Factor for Non-Renewable fuels
2006 IPCC Data NCV EF-CO2
TJ/kT T-CO2/TJ
Fuel Oil13
42.29 75.00
Coal14
25.5 96.1
Natural Gas 48 56.1
Table 9 shows the fuel consumptions from non-renewable generating sources connected to the Jawa-Bali
grid.
Table 9 - Fuel consumptions from non-renewable sources
Source Fuel Usage (kL)
2006 2005 2004
Fuel Oil
(kL=1m3)
High Speed Diesel 4,393,415 5,148,475 3,267,163
Industrial Diesel Oil - 14,288 9,586
Marine Fuel Oil 2,340,481 1,933,928 2,096,787
Total Fuel Oil 6,733,896 7,096,691 5,373,536
Coal (T) 26,978 15,014,433 13,425,337
Natural Gas (MMSCFD) 142,494 113,404 138,693
In order to estimate carbon emission for each type of fossil fuel, the fuel consumption data in Table 9 are
converted into its equivalent mass unit using its respective specific gravity: 840kg/m3 for diesel oil and
640kg/m3,15
for natural gas. The fuel consumption converted to mass unit is presented in Table 10.
Table 10 - Fuel consumption from non-renewable sources in mass unit
Fuel Type Fuel Usage (kT)
2006 2005 2004
Fuel Oil 5,656 5,961 4,514
Coal 26,978 15,014 13,425
Natural Gas 2,639 2,100 2,569
Total 35,274 23,076 20,508
The CO2 emission of each fossil fuel used in the electricity grid is calculated by multiplying the amount
of fuel used (Table 10) with the net calorific value and CO2 emission factor (Table 8). The result is
presented in Table 11 below.
Table 11 - Total CO2 emission from non-renewable sources
Fuel Type CO2 Emission (tCO2/yr)
2006 2005 2004
Fuel Oil 17,917,562 18,882,887 14,297,913
Coal 66,111,845 36,793,619 32,899,460
13 The NCV and EF of fuel oil is estimated as combined NCV or EF of diesel oil and marine fuel oil (residual oil)
based on its usage proportionality for the most recent year (in 2005)
14 The NCV of coal is estimated based on sub-bituminous mid-rank coal with calorific value of 6,100kcal/kg which
makes the large proportion of available coal in Indonesia.
15 Calculated using ideal gas at standard temperature and pressure, assuming 100% methane composition
Page 20
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 20
File Name: ID-MEN-TNG-PDD Version 2.1
Natural Gas 7,106,003 5,655,320 6,916,466
Total CO2 Emission (t-CO2) 91,135,409 61,331,826 54,113,840
The Simple OM CO2 Emission Factor for the electricity grid can be calculated by dividing the total CO2
emission from fossil fuel usage shown in Table 11 by the power generated from non renewable sources.
The results for individual year are shown Table 12. The calculated three years average OM emission
factor is 0.902t-CO2/MWh.
Table 12 - Ex-ante Operation Margin Emission Factor
Operating Margin 2005 2004 2003
Total CO2 Emission (t-CO2) 91,135,409 61,331,826 54,113,840
Total Power Generated (MWh) 105,274,140 100,954,150 95,403,210
Power from Renewable Energy (MWh)
Hydroelectric 5,207,670 6,248,000 5,428,220
Geothermal 6,499,760 2,870,000 2,988,240
Renewable 0 23,477,000 22,236,000
Total Renewable 11,707,430 32,595,000 30,652,460
Power from non-Renewable Sources (MWh) 93,566,710 68,359,150 64,750,750
Operating Margin Emission Factor (t-CO2/MWh) 0.974 0.897 0.836
Average for 3 years (t-CO2/MWhr) 0.902
2. Build Margin Emission Coefficient ( )
ACM0002 allows project developer to choose between Option 1 and Option 2 to calculate Build Margin.
Based on the consideration of limited access to reliable data, Option 1 is selected.
Option 1 calculates ex-ante build margin based on sample group m that consists of either:
(a) five power plants that have been built most recently, or
(b) power plant capacity additions the comprise 20% of the system generation that have been built most
recently
The methodology mandated to use whichever option that comprise the larger annual generation, as such
Option 1-b is deemed appropriate as the most recent five power plants only has total contribution of only
8.79% as shown in Table 13. The table lists the sample group m power plants from the most recent
(Cilegon), individual power plants fuel consumptions, and 2006 generations and its % contribution to the
total electrical generations from all power plants connected to Java-Bali grid.
Based on information provided by PT PLN (Persero) P3B, the most recently built power plant in the
Jawa-Bali grid and its generation output in 2006. The table lists power plants from based the most
recently installed (Cilegon).
Table 13 - Sample group m power plants
Sample group m power plant Fuel Type and
Consumptions
Cumulative generation
per total generations of
all power plants in the
Java-Bali grid (%)
Annual generation in
2006 (MWh)
Cilegon Gas 0.73% 773,676
1,948 kT
Tanjung Jati B Coal 4.55% 4,013,074
1,887 kT
Cilacap Coal 6.35% 1,901,659
965 kT
Muara Tawar 3-4 Fuel oil 7.91% 1,641,877
Page 21
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 21
File Name: ID-MEN-TNG-PDD Version 2.1
489kT
Wayang Windhu Geothermal 8.79% 922,299
No fossil fuel
Paiton PEC Coal 17.77% 9,451,482
4,556kT
Jawa Power Coal 26.74% 9,446,179
4,520kT
Total annual generation of power plant in sample group m 28,150,245
Total annual generation of all power plant in the Java-Bali grid 105,274,140
The build margin is calculated using equation analogous to Equation 5 of this PDD based on the selected
sample group m and information provided in Table 8. Table 14 shows the CO2 emission associated with
individual power plants in sample group m. The build margin emission factor is calculated to be
1.132tCO2/yr.
Table 14 - CO2 Emissions from sample group m power plants
Sample group m power plant Fuel Type and Consumptions 2006 CO2 Emissions
Cilegon Gas 18,041
1,948 kT
Tanjung Jati B Coal 4,624,359
1,887 kT
Cilacap Coal 2,365,099
965 kT
Muara Tawar 3-4 Fuel oil 1,549,790
489kT
Wayang Windhu Geothermal 0
No fossil fuel
Paiton PEC Coal 11,188,819
4,556kT
Jawa Power Coal 11,076,927
4,520kT
Total CO2 emission of power plants in sample group m (tCO2) (A) 30,823,037
Total annual generation of power plants in sample group m (MWh) 28,150,245
Total renewable energy generation in sample group m (MWh) 922,299
Total non-renewable energy generation in sample group m (MWh) (B) 27,277,946
Build margin emission factor (tCO2/MWh) = (A)/(B) 1.132
Combined Margin (CM) Emission Factor of the grid (
As elaborated above, the grid operating margin emission factor and build margin emission factor are
calculated and set ex-ante as 0.902t-CO2/MWh and 1,132t-CO2/MWh respectively. Using Equation 4,
the emission factor of the electricity grid is calculated as 1.017t-CO2/MWhr.
PROJECT EMISSIONS
The combustion of natural gas emits CO2, CH4, and N2O in the exhaust gas. Consistent with the
methodology, the emission resulting from the natural gas combustion is counted as a source of project
emission and calculated as the amount of energy from natural gas consumption required for the Project
activity multiplied with the gas emission factors and global warming potentials.
Page 22
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 22
File Name: ID-MEN-TNG-PDD Version 2.1
In order to be consistent with monitoring implementation procedure16
, the amount of energy from natural
gas for the cogeneration is further broken down in terms of from the volume of natural gas consumption
multiplied by its density and net calorific value.
Equation 6
Variable Description Unit
Project emission from natural gas combustion t-CO2/yr
The amount of natural gas consumed for the project activity m3/yr
Specific gravity of natural gas kg/m3
Net calorific value for natural gas TJ/t
Emission factor of green house gas g from the combustion of natural
gas
t-g/TJ
Global warming potential of greenhouse gas g. t-CO2/t-g
The emission factor for each gas from the Project‟s fuel (natural gas) is provided in the following table.
Table 15 – Emission Factors and Global Warming Potentials of greenhouse gases from Natural gas
Emission factor from natural gas combustion CO2 CH4 N2O
Emission Factor of gas G in t-g/TJ ,
56.1 0.001 0.0001
Global Warming Potential of gas g in t-CO2/t-g ,
1 21 310
Source for Emission Factor (default data used) Table 2.2 Table 2.2 Table 2.2
2006 IPCC Guidelines for National
Greenhouse Gas Inventories
LEAKAGE EMISSIONS
The methodology requires methane from the production, processing, transmission, storage and
distribution to be considered as leakage emission. The highest possible methane emission factors from
these activities in non-OECD nations are used (Table 4.2.5 from 2006 IPCC Guideline) and tabulated
below.
Table 16 - Methane emission factor from natural gas production & distribution activities
Activity (k) Methane Emission Factors in Gg/10^6m3 of gas delivered
(totalled from fugitive & venting when applicable)
1 Gg = 1,000tonnes
Gas Production 0.024
Gas Processing (Sweet gas) 0.003528
Gas Transmission & Storage 0.001898
Gas Distribution 0.0025
The leakage emissions is calculated by multiplying the amount of natural gas consumed (in m3/yr) and
the emission factor for each activity (k) listed in Table 16
16 Natural gas consumption is procured in the unit of volume rather than energy for this Project
Page 23
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 23
File Name: ID-MEN-TNG-PDD Version 2.1
Equation 7
Variable Description Unit
LE Leakage emissions from production, processing, transmission,
storage, and distribution of natural gas
t-CO2/yr
VNG The amount of natural gas consumed for the project activity m3/yr
kMEF Methane emission factor from activity k Gg/m3
EMISSION REDUCTION
The emission reduction is calculated as the difference between the baseline emissions and the sum of the
leakage and project activity emissions.
Equation 8
Variable Description Unit
Baseline emissions from baseline fuel (residual oil) combustion
(from CO2, CH4 and N2O)
t-CO2/yr
Baseline emission from electricity grid displacement t-CO2/yr
Project emission from natural gas combustion t-CO2/yr
Leakage emissions from production, processing, transmission,
storage, and distribution of natural gas
t-CO2/yr
B.6.2. Data and parameters that are available at validation:
Data / Parameter:
Data unit: Fraction
Description: Efficiency of baseline boiler
Source of data used: Methodology default value
Value applied: 90%
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
Any comment:
Data / Parameter: Data unit: TJ/tonnes
Description: Net calorific value of natural gas used for the project activity
Source of data used: Pertamina gas data
Value applied: 45.5 TJ/k-tonnes
Justification of the
choice of data or
description of
measurement methods
Page 24
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 24
File Name: ID-MEN-TNG-PDD Version 2.1
and procedures actually
applied :
Any comment:
Data / Parameter: Data unit: kg/m3
Description: Specific gravity of natural gas
Source of data used: Gas supplier, PGN or Pertamina
Value applied: 0.6538kg/m3
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
Any comment:
Data / Parameter:
Data unit: t-CO2/t-g
Description: Global warming potential of gas G
Source of data used: IPCC
Value applied: CO2 = 1
CH4 = 21
N2O = 310
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
Any comment:
Data / Parameter:
Data unit: t-G/TJ
Description: Emission factor of greenhouse gas G from combustion of residual oil
Source of data used: Table 2.2, 2006 IPCC Guideline for National Greenhouse Gas
Inventories
Value applied: Combustion of residual oil
CO2 emission factor = 77.4t-CO2/TJ
CH4 emission factor = 0.003t-CH4/TJ
N2O emission factor = 0.0006t-N2O/TJ
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
Any comment:
Data / Parameter:
Data unit: t-G/TJ
Description: Emission factor of greenhouse gas G from combustion of natural gas in
the Project plant
Page 25
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 25
File Name: ID-MEN-TNG-PDD Version 2.1
Source of data used: Table 2.2, 2006 IPCC Guideline for National Greenhouse Gas
Inventories
Value applied: Combustion of residual oil
CO2 emission factor = 56.1t-CO2/TJ
CH4 emission factor = 0.001t-CH4/TJ
N2O emission factor = 0.0001t-N2O/TJ
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
Any comment:
Data / Parameter:
Data unit: Gg/m3 or 1,000 tonnes/m3
Description: Methane emission factor from activity k
Source of data used: Table 4.2.5 2006 IPCC Guideline
Value applied: 0.024 for gas production
0.003528 for gas processing (sweet gas)
0.001898 for gas transmission and storage
0.0025 for gas distribution
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
The above data totalled the fugitive and venting emission factor where
applicable and represent the upper end of emission in non-OECD
nation.
Any comment:
B.6.3 Ex-ante calculation of emission reductions:
BASELINE EMISSIONS
Baseline Emission from the Combustion of Baseline Fuel,
The project activity will displace approximately 9.8 tonnes per hour of saturated steam at 8 bar pressure
with heating value of 2,768kJ/kg17
. Based on the projected operating hours of 8,000 hours per year, the
generated steam is equivalent to 210TJ/yr.
The amount of energy required to generate the same amount of steam in the baseline boiler with default
efficiency of 90% is estimated as 233.7TJ/yr. Using the emission factor for green house gas CO2, CH4,
and N2O from residual oil combustion shown in Table 6, the emissions associated with the combustion of
avoided baseline fuels are calculated to be: 18,146t-CO2/yr.
17 Based on enthalpy of saturated steam at 8 bar
Page 26
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 26
File Name: ID-MEN-TNG-PDD Version 2.1
Baseline emission from grid-electricity displacement ( )
Based on 90% expected loading, operating hour of 8,000hr per year, maximum capacity of 13.61MWe
and 3% electrical consumption, the Project is expected to deliver about 95,052MWh/yr.
Using the calculated grid emission factor set ex-ante as 1.017tCO2/yr, the baseline emission from grid-
electricity displacement is 96,668t-CO2/yr
PROJECT EMISSION
Each gas engine is designed to consume 614m3/hr. With approximated operating hour of 8,000hr per year
the natural gas consumption for the five engines is totalled to 24,560,000m3 annually.
Gas specification sheets from the gas company stated that the natural gas has specific gravity of
0.6538kg.m3 and net calorific value of 0.0455TJ/t. Based on these data, and emission factor of natural gas
from IPCC shown in Table 15, the emissions from natural gas consumption is calculated as follow:
Annual natural gas consumption:
Emissions from natural gas consumption:
LEAKAGE EMISSION
Based on the gas activity coefficient data presented in Table 16, the methane emission (leakage) factor is
calculated as follow:
With calculated annual consumption of 24,560,000m3 of natural gas per year, the leakage emission
associated with natural gas production, processing, transmission and storage activities are calculated as
follow:
B.6.4 Summary of the ex-ante estimation of emission reductions:
Source Parameter Description Calcualted
Ex-Ante Values
(t-CO2/yr)
Baseline Baseline emission associated with combustion of 18,146
Page 27
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 27
File Name: ID-MEN-TNG-PDD Version 2.1
avoided residual oil
Baseline emission associated with the avoided grid
electricity
96,668
Total baseline emission 114,814
Project Project emission associated with the combustion of
natural gas for project activity
41,025
Leakage emission associated with natural gas
production, transmission, distribution, and storage
14,828
Total project emission 55,853
Total emission reduction 58,961
B.7 Application of the monitoring methodology and description of the monitoring plan:
B.7.1 Data and parameters monitored:
Data / Parameter: CHOR
Data unit: TJ/Yr
Description: Amount of heat recovered by the project waste heat boiler as
steam.
Source of data to be used: Combination of monitoring and calculation
Value of data applied for the
purpose of calculating
expected emission
reductions in section B.5
It is assumed that the steam is at saturated condition at 8 bar with
enthalpy of 2,767kJ/kg and flowrate of 9.5tonnes per hour or
210.33TJ/yr
Description of measurement
methods and procedures to
be applied:
1. Monitoring of the temperature (degC), pressure (kPa), and
flowrate (kg/year) of steam generated by the Project
2. Calculate enthalpy of steam at the monitored temperature
and pressure using accepted steam table (H) in kJ/kg
3. Calculate annual heat output of the Project by multiplying
enthalpy and steam flowrate.
QA/QC procedures to be
applied:
1. Flowrate, Pressure & Temperature monitoring gauge will be
calibrated using international standard to have a maximum
error of 1%
2. Steam enthalpy data will be sourced from acceptable
engineering data.
3. Data must be verified with sales invoices/receipt by Argo
Pantes.
Any comment: Data is recorded automatically by a computerized system able to
store information for up to 3 months. But information will be
logged on daily basis for a weekly emission reduction monitoring
report.
Data / Parameter: AOH
Data unit: Operating hours of the power plant
Description: hr/yr
Source of data to be used: Power plant on/off switch from all 5 gas engines
Value of data applied for the
purpose of calculating
expected emission
reductions in section B.5
8,000hour per year.
Description of measurement
methods and procedures to
The system is equipped with software applications that allow
monitoring of the plant operation. Records of this application
Page 28
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 28
File Name: ID-MEN-TNG-PDD Version 2.1
be applied: will be kept as basis for counting the operation hour of the gas
engines.
QA/QC procedures to be
applied:
The monitoring & record data transfer is automated and therefore
error is minimal
Any comment: Data is recorded automatically by a computerized system able to
store information for up to 3 months. But information will be
logged on daily basis for a weekly emission reduction monitoring
report.
Data / Parameter: ;
Data unit: t-CO2/MWh
Description: Operating Margin (OM) CO2 emission factor of power plant
connected to the Java-Bali electricity grid in year y
Build Margin (BM) CO2 emission factor of power plants
connected to Java-Bali electricity grid in year y
Source of data to be used: PLN published data
Value of data applied for the
purpose of calculating
expected emission
reductions in section B.5
0.936t-CO2/MWh
Description of measurement
methods and procedures to
be applied:
No measurement required. Data is obtained based on analysis of
PLN published information
QA/QC procedures to be
applied:
Not required
Any comment: Data is calculated on annual basis.
Data / Parameter: CEO
Data unit: MWh/yr
Description: The amount of electricity generated by the project net of its
parasitic consumption.
Source of data to be used: Electricity meter
Value of data applied for the
purpose of calculating
expected emission
reductions in section B.5
95,052MWh based on
90% load,
8,000 operation hour; and
gas engine capacity of 13.6MW
Description of measurement
methods and procedures to
be applied:
Record is collected quarterly from cumulative electricity meters
from individual engines
QA/QC procedures to be
applied:
Electricity meters are subject to laboratory standard calibration
with error less than 1%
Data is cross checked with sales invoices to Argo Pantes, Argo
Fajar and Argo Beni on monthly basis
Any comment: Data is recorded automatically by a computerized system able to
store information for up to 3 months. But information will be
logged on daily basis for a weekly emission reduction monitoring
report.
Data / Parameter: VNG
Data unit: m3/yr
Description: The amount of natural gas consumed by the project acitivity
Source of data to be used: Individual gas meters attached to the engine.
Value of data applied for the
Page 29
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 29
File Name: ID-MEN-TNG-PDD Version 2.1
purpose of calculating
expected emission
reductions in section B.5
29,528,373m3/yr
Description of measurement
methods and procedures to
be applied:
Data is obtained quarterly from the PGN gas meters
QA/QC procedures to be
applied:
Gas meter is subject to laboratory calibration
Data is verified with payment receipt from PGN.
Any comment: Data is recorded automatically by a computerized system able to
store information for up to 3 months. But information will be
logged on daily basis for a weekly emission reduction monitoring
report.
B.7.2 Description of the monitoring plan:
Data Collection and Reporting Structure
Operational data relevant for emission accounting will be logged by operator on daily basis using a pre-
prepared log-sheet form part of the operator log book. The report will be signed and checked by an
Operational Manager who will compile the report on weekly basis to determined:
thermal delivery from individual gas engine;
electrical output of individual gas engine; and
gas consumption of individual gas engine.
On monthly basis, the Operational Manager consolidates the above data, and cross-checked them against
receipt from user and sales invoice from gas suppliers. The compiled information is summarized into an
Emission Reduction Delivery Report (ERDF) to be submitted to MEN‟s General Manager who will issue
a six-monthly ERDF following an audit in reporting procedure and calibration report. This report will be
part of the Annual Monitoring Report that will be verified by the DOE.
Calibration Procedure
The instrumentations installed are new and has been calibrated to international standard before
commissioning. Regular calibration will be performed on regular basis during the annual maintenance
shut-down at the end of first year and subsequent years to all identified instrumentations up to error level
up to 1% or less for the electricity meter.
Every end of maintenance shut-down, a Calibration Report Status is composed to list all CDM-related
instruments, their details, calibration status and expected error. This calibration report status will be
subjected to checking by MEN‟s General Manager at the issuance of six-monthly ERDF and will be
provided as an attachment in the Annual Monitoring Report that will be verified by the DOE.
Archiving of Data
All emission reduction related data and reports will be archived for up to 3 years from the end of each
crediting period.
B.8 Date of completion of the application of the baseline study and monitoring methodology and
the name of the responsible person(s)/entity(ies)
Clean Energy Finance Committee
Mitsubishi UFJ Securities Co., Ltd.
Tokyo, Japan
Tel: +81 3 6213 6331
Junji Hatano
Email: [email protected]
Page 30
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 30
File Name: ID-MEN-TNG-PDD Version 2.1
The baseline information was completed in May 2007
SECTION C. Duration of the project activity / crediting period
C.1 Duration of the project activity:
C.1.1. Starting date of the project activity:
01/02/2007
C.1.2. Expected operational lifetime of the project activity:
21 years
C.2 Choice of the crediting period and related information:
C.2.1. Renewable crediting period
C.2.1.1. Starting date of the first crediting period:
18/08/2007 or immediately after registration
C.2.1.2. Length of the first crediting period:
7 years
C.2.2. Fixed crediting period:
C.2.2.1. Starting date:
N/A
C.2.2.2. Length:
N/A
Page 31
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 31
File Name: ID-MEN-TNG-PDD Version 2.1
SECTION D. Environmental impacts
D.1. Documentation on the analysis of the environmental impacts, including transboundary
impacts:
The Project is not expected to have adverse environmental impacts and therefore is not required to
prepare an Environmental Impact Analysis (EIA) under the applicable regulation.
The Project has obtained approval for the necessary environmental actions documentations (UPL/UKL)
from the Environmental Agency of the City of Tangerang (or Dinas Lingkungan Hidup Kota Tangerang)
in December 2006 with approval registration number 660.1/1469-APDL.
The documents detail possible environmental impacts that may arise from the project activity before
construction, after construction, and after operation as well as the necessary mitigation.
D.2. If environmental impacts are considered significant by the project participants or the host
Party, please provide conclusions and all references to support documentation of an environmental
impact assessment undertaken in accordance with the procedures as required by the host Party:
The Project is not expected to result in adverse environmental impact. Possible impacts arising from the
project activity will be further assessed in the sustainability analysis required to obtain the letter of
approval from the Indonesian government.
SECTION E. Stakeholders’ comments
E.1. Brief description how comments by local stakeholders have been invited and compiled:
The project participant hosts a stakeholder consultation meeting at the Argo Pantes office in Tangerang
on December 27th 2007. Invitations were distributed to various institutions including local environmental
agencies (BAPPEDAL), National Commission for Clean Development Mechanism (Komnas MPB or
DNA), industrial users to the Project, other industrial users located within Cikokol area, as well as
community members through the neighbourhood units (RT).
The meeting was attended by 21 people excluding
representative of industrial users to the Project and
management of MEN.
The meeting was opened by Head of Production of PT
Argo Pantes (Mr. Santo) and followed by an opening
statement by Mr. Prasetyadi Utomo from Komnas MPB.
Project information was presented by Mr. H. Soeyoto, the
Director of Manunggal Energi Nusantara.
E.2. Summary of the comments received:
The following summarized the inquiries raised during the stakeholder consultation.
Mr. Maman, representing the Tangerang City environmental Agency (Dinas KLH) inquires on the
Project‟s impact on waste, traffic, and employment opportunity to surrounding communities. He also
Page 32
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 32
File Name: ID-MEN-TNG-PDD Version 2.1
raised possibility of the Project developer to retail electricity to the residential areas at a rate lower or at
least equal to PLN.
To the first concern, MEN responded that the project construction will have a limited impact as it
will renovate an existing power house in Argo Pantes instead of erecting a new building for the
Project equipment. Impact to traffic during this time will also be minimal as the major equipment
would be assembled in Austria and delivered in three shipments. During operation, the project
needs water to operate its boiler, but there will be no incremental water usage from what is
already being consumed by Argo Pantes. Waste is expected to be generated by the project in the
form of the oil-based lubricant that is necessary to maintain the major equipments. The volume is
very small to raise any environmental concern and would be handled by the maintenance
company. Additional domestic waste water will be generated from the additional 20skilled
workers that will be hired to maintain the project‟s continuous operation. During the construction
time, limited workers are required and handled by the construction company.
To the second concerns, MEN responded by stating that this Project is the first in MEN‟s
portfolio and further development would be upon the Project‟s success. Unlike PLN, MEN do not
receives any subsidy or incentive from the Indonesian government to develop transmission
network for electricity retail. However, upon the industrial users relinquishing their PLN
utilization, more electricity would be available for the public.
Mr. Aris Munandar representing the Banten Province environmental agency (BAPPEDAL) requests
clarification on the Project‟s output dispatch status to the industrial users; the project capital investment;
and the impact of avoiding coal to the neighbourhood.
MEN‟s clarifies that industrial users will use the Project‟s output as the primary energy source and will
continue to use PLN as energy back-up in the first year. Upon the Project‟s successful performance, the
industrial users may decide to disconnect from PLN. The Project‟s capital investment is expected to be
circa USD12,5million. On the issue of coal avoidance, MEN‟s stated that the positive impacts are
reduction of potential air pollution and elimination of traffic for the transportation of coal. The economic
impact will be felt by both coal suppliers and PLN, not to surrounding community.
Mr. Mamang, Tangerang City government representative (Camat Tangerang) raised the issue of
completion of permits on which MEN responded by stating that the company activity has obtained the
necessary permit for general electricity provision from Serang District Mineral & Energy agency.
E.3. Report on how due account was taken of any comments received:
The Project and MEN‟s explanations were well accepted by the representative of environmental agencies
and there are no due accounts from the comments received during the stakeholder meeting. Community
members and local government representatives agree that the Project will have positive contribution to
the environment.
Page 33
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 33
File Name: ID-MEN-TNG-PDD Version 2.1
Annex 1
CONTACT INFORMATION ON PARTICIPANTS IN THE PROJECT ACTIVITY
Organization: PT Manunggal Energi Nusantara
Street/P.O.Box: Jl. Gatot Subroto Kav. 22
Building: 2nd
Floor Wisma Argo Manunggal
City: Jakarta
State/Region: DKI
Postfix/ZIP: 12930
Country: Indonesia
Telephone: +62 (21) 252 0065
FAX: +62 (21) 252 0029
E-Mail: [email protected]
URL:
Represented by: H. Soeyoto
Title: Director
Salutation:
Last Name: Soeyoto
Middle Name:
First Name: H.
Department:
Mobile:
Direct FAX:
Direct tel:
Personal E-Mail: [email protected]
Organization: Mitsubishi UFJ Securities Co., Ltd.
Street/P.O.Box: 2-5-2 Marunouchi, Chiyoda-ku
Building: 2F, Mitsubishi Building
City: Tokyo
State/Region:
Postfix/ZIP: 100-0005
Country: Japan
Telephone:
FAX:
E-Mail:
URL: http://www.mitsubishi-sec.co.jp/english_fs.html
Represented by:
Title: Chairman, Clean Energy Finance Committee
Salutation: Mr.
Last Name: Hatano
Middle Name:
First Name: Junji
Department: Clean Energy Finance Committee
Mobile:
Direct FAX: +81 3 6213 6331
Direct tel: +81 3 6213 6175
Personal E-Mail: [email protected]
Page 34
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 34
File Name: ID-MEN-TNG-PDD Version 2.1
Annex 2
INFORMATION REGARDING PUBLIC FUNDING
The Project does not involved any public funding
Annex 3
BASELINE INFORMATION
Refer to Section B.4
Annex 4
MONITORING INFORMATION
Refer to section B.7.2
Annex 5
OTHER INFORMATION
Annex 5.1 Energy savings resulting from implementation of Project
Energy Consumption Before the Project
Prior to the Project, heat is generated by means of residual boiler with maximum efficiency of
90%. Electricity is purchased from the grid. The following energy consumption is calculated
based on maximum electrical generation efficiency of 40% - without accounting for transmission
loss.
Table 17 shows the basis and assumptions taken to calculate energy input as well as calculation
result.
Table 17 - Baseline Energy Input
Baseline
Heat Generation (Residual Boiler) unit Value
1 Steam Enthalpy MJ/t 2767.5
2 Flowrate t/hr 9.5
3 Operation hour hr/yr 8000
4 Residual boiler efficiency fraction 0.9
Energy Input for Heat Generation TJ/yr 233.7
Electrical Generation (Grid electricity) unit Value
1 Electricity Output MW 11.88
2 Operation hour hr/yr 8000
3 Electrical generation efficiency (Max) fraction 0.4
Energy Input for Electricity Generation TJ/yr 855.36
Total Energy Input TJ/yr 1089.06
Energy Consumption After the Project
After the Project, no additional energy is required to generate steam as this will be generated
using the exhaust of the gas engine. Based on manufacturer specification, each gas engine needs
6,498kW to generate 2,722kW of electricity. This means that the electrical generation efficiency
of each gas engine is 41.8%.
Table 18 shows the basis and assumptions taken to calculate energy input as well as calculation
result.
Page 35
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 35
File Name: ID-MEN-TNG-PDD Version 2.1
Table 18 - Project's Energy Consumption
ProjecT
Heat Generation (Waste heat boiler) unit Value
Energy Input for Heat Generation TJ/yr 0
Electrical Generation (Natural Gas Engine) unit Value
1 Electricity Output MW 11.88
2 Operation hour hr/yr 8000
3 Electrical generation efficiency (Max) fraction 0.418
Energy Input for Electricity Generation TJ/yr 818.52
Total Energy Input TJ/yr 818.52
Total energy savings from implementation of Project
Without the Project, it is estimated that 1,089TJ/yr of energy is required to generate electricity and heat
equivalent to that generated by the Project. The Project improves the energy generation efficiency and
requires only 818.52TJ/yr. This means that the project implementation reduces the energy consumption
by nearly 25%.
- - - - -