Chapter 9 Cost Planning and Performance
25

Chapter 9 Cost Planning and Performance

Jan 12, 2016

Download

Documents

Chapter 9 Cost Planning and Performance. Learning Objectives. Items to consider when estimating cost Preparing a baseline budget Cumulating actual costs Determining the earned value of work performed Analyzing cost performance Forecasting project cost at completion - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Chapter 9 Cost Planning and Performance

Chapter 9Cost Planning and Performance

Page 2: Chapter 9 Cost Planning and Performance

222

Learning Objectives

Items to consider when estimating cost Preparing a baseline budget Cumulating actual costs Determining the earned value of work

performed Analyzing cost performance Forecasting project cost at completion Controlling project costs Managing cash flow

Page 3: Chapter 9 Cost Planning and Performance

333

Real World Example Vignette: eBay eBay understands the importance of analyzing project data to produce

performance indicators eBay’s mission is to provide a trading platform for people all over the world.

They do this by continually improving the user’s experience on the eBay site Decisions for change are based on measurable factors like the number of

visitors to the site, length of time customers spend on eBay, busiest day of the week for eBay transactions, etc.

Managers regularly collect data from the site to develop new marketing and merchandising techniques, continually improving the buy-sell process for eBay customers

Project managers should understand the valuable of measurable factors, and apply them to make responsible decisions about their projects

“If you can’t measure it, you can’t control it.”

Page 4: Chapter 9 Cost Planning and Performance

Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created

Transport for London to oversee the city’s road and transport services that were previously managed separately. Mission: to upgrade London’s transportation infrastructure with a toll system project to reduce crippling congestion

Trans. for London developed a plan to install a system (cameras) to identify & charge car owners entering defined congestion zones

Technological risks were identified, and the project was divided into 5 smaller components (to be managed separately, as opposed to purchasing one large system)

The project team worked together in one location on the five components to the system

The project was successfully implemented by February 2003. Transport for London reports that traffic in the congestion zone has decreased by 20%, with a 5% improvement in travel times

4

Page 5: Chapter 9 Cost Planning and Performance

5

Project Cost Estimates Cost planning starts with the proposal. The cost section may include:

Labor Materials Subcontractors and consultants (if used) Equipment and facilities rental Travel

Page 6: Chapter 9 Cost Planning and Performance

6

Project Budgeting: Two Steps

First, the project cost estimate is allocated to the various work packages in the project work breakdown structure.

Second, the budget for each work package is distributed over the duration of the work package.

Page 7: Chapter 9 Cost Planning and Performance

7

Allocating the Total Budgeted Cost Allocating total project costs for the

various elements to the appropriate work packages will establish a total budgeted cost (TBC) for each work package.

There are two approaches to establishing the TBC for each work package: top-down and bottom-up.

When all budgets are summed, they cannot exceed the TBC.

Page 8: Chapter 9 Cost Planning and Performance

8

Developing the Cumulative Budgeted Cost The second step is to distribute each TBC

over the duration of its work package. A cost is determined for each period. The cumulative budgeted cost (CBC) is

the amount that was budgeted to accomplish the work that was scheduled to be performed up to that point in time.

One uses the CBC as the standard against which actual cost is compared.

Page 9: Chapter 9 Cost Planning and Performance

9

Page 10: Chapter 9 Cost Planning and Performance

10

Page 11: Chapter 9 Cost Planning and Performance

11

Determining Actual Cost Track actual cost by establishing a

system to collect data on funds actually expended.

Periodically assign a portion of the total committed cost to actual cost. Funds may be committed but not yet paid

Total actual and committed cost by work package for comparison to the CBC.

Cumulative actual cost (CAC) should be calculated.

Page 12: Chapter 9 Cost Planning and Performance

12

Page 13: Chapter 9 Cost Planning and Performance

13

Page 14: Chapter 9 Cost Planning and Performance

14

Determining the Value of Work Performed Earned value is the value of the work

actually performed.

Determine earned value by collecting data on the percent complete for each work package.

Convert this percentage to a dollar amount by multiplying the TBC of the work package by the percent complete.

Page 15: Chapter 9 Cost Planning and Performance
Page 16: Chapter 9 Cost Planning and Performance

16

Page 17: Chapter 9 Cost Planning and Performance

17

Cost Performance Analysis Four Measures TBC (total budgeted cost) CBC (cumulative budgeted cost) CAC (cumulative actual cost) CEV (cumulative earned value)

Page 18: Chapter 9 Cost Planning and Performance

181

Cost Performance Index (CPI) A measure of the cost efficiency with

which the project is being performed.

CPI = Cumulative Earned Val -------------------------- Cumulative Actual Cost

Page 19: Chapter 9 Cost Planning and Performance

19

Cost Variance (CV) The difference between the cumulative

earned value of the work performed and the cumulative actual cost.

Cost variance = Cum earned value – Cum actual cost

Page 20: Chapter 9 Cost Planning and Performance

20

Cost Forecasting: Three Methods

Three methods for determining forecasted cost at completion (FCAC):

FCAC = TBC / CPI

• Project continues at same rate of efficiency

FCAC = CAC + (TBC - CEV)

• Remaining work performed at CPI = 1

FCAC = CAC + Re-estimate of remaining work

• New forecast for remaining work

Page 21: Chapter 9 Cost Planning and Performance

21

Cost Control The key is to analyze cost

performance on a regular and timely basis.

Identify cost variances and inefficiencies early.

Page 22: Chapter 9 Cost Planning and Performance

22

Cost Control (Cont.) Involves the following:

Analyzing cost performance to determine which work packages may require corrective action.

Deciding what corrective action should be taken

Revising the project plan.

Page 23: Chapter 9 Cost Planning and Performance

23

Ways to Reduce Costs of Activities

Substitute less expensive materials. Assign a person with greater

expertise to perform or help with the activity.

Reduce the scope or requirements. Increase productivity through

improved methods or technology.

Page 24: Chapter 9 Cost Planning and Performance

24

Managing Cash Flow Make sure that sufficient payments

are received from the customer in time for you to cover the costs of performing the project.

The key to managing cash flow is to ensure that cash comes in faster than it goes out.

Page 25: Chapter 9 Cost Planning and Performance

25

Project Management Software

All costs associated resources can be stored. The software calculates the budget for each work package and for the entire project.

The software allows the user to define different rate structures for each resource and when charges for those resources will be accrued.

Cost tables and graphs are available to help analyze cost performance.