Top Banner
Mandalay Nay Pyi Taw Yangon Water Resources Utilization: Challenges on Tunneling and Hydropower Development Wunna Htun Deputy Director (Civil) Department of Hydropower Implementation
33

Challenges on Tunneling and Hydropower Development

Feb 01, 2023

Download

Documents

Khang Minh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Challenges on Tunneling and Hydropower Development

Mandalay

Nay Pyi Taw

Yangon

Water Resources Utilization:

Challenges on Tunneling and Hydropower Development

Wunna Htun Deputy Director (Civil)

Department of Hydropower Implementation

Page 2: Challenges on Tunneling and Hydropower Development

Nay Pyi Taw

Mandalay

Yangon

Hydropower Resources

and

Current Situation of Myanmar

Page 3: Challenges on Tunneling and Hydropower Development

River Basins

Sr. Name of River Basin Area (km2)

1. Ayeyarwaddy

2. Chindwin

3. Sittaung

4. Thanlwin

5. Mekong

6. Others

234,706

115,307

32,893

134,395

23,999

135,252

Total 676,552

Ayeyarwaddy

(35%)

Chindwin

(17%)

Sittaung

(5%)

Thanlwin

(20%)

Mekong (4%)

Others

(20%)

Rich water resources because of favorable

topography and tropical monsoon climate. Hydropower potential of Myanmar is estimated more

than 100,000 MW (ADB 2012). Currently identified hydropower potential is about

44,300 MW in total. At present, total installed capacity of electric power is

5,393 MW and 60% from hydro power. Just only 7% of the country potential had already been

developed and more than 93% of the country potential

is still remaining.

- 3 -

Page 4: Challenges on Tunneling and Hydropower Development

Item Grid System

(MW)

Isolated

(MW)

Total

(MW) Percentage

Installed Capacity 5,268 124.81 5392.81 100.00%

Hydroelectric 3,181 33.33 3214.33 59.60%

Gas 1967 - 1967 36.47%

Coal 120 - 120 2.23%

Diesel - 91.48 91.48 1.70%

Bio Mass - 4.7 4.7 0.09%

Peak Demand 2,756 MW (April, 2016)

Hydro (59.60%)

Gas (36.47%)

Coal Diesel Biomass

Overview of Current Generation Mix in Myanmar (As of Jan, 2017)

- 4 -

Page 5: Challenges on Tunneling and Hydropower Development

Sole investment by Ministry of Electricity and Energy

Investment by Local Entrepreneurs on B.O.T basis

Investment by Foreign Companies on J.V / B.O.T basis

Sector

MOEE Local

Entrepreneurs Foreign

Companies Total

(MW) Remark

No. Installed Capacity

(MW) No.

Installed Capacity

(MW) No.

Installed Capacity

(MW)

Hydro 4 1,494 9 864 40 41,925 44,283 65 %

Gas

Turbine 1 240 1 100 25 5,872 6,212 9 %

Coal - 3 385 9 9,160 9,545 14 %

Wind - - 5 6,538 6,538 10 %

Solar - - 5 1,510 1,510 2 %

Total 5 1,734 13 1,349 84 65,005 68,088 100 %

Hydro 65%

Gas Turbine 9%

Coal 14%

Wind 10%

Solar 2%

- 5 -

Page 6: Challenges on Tunneling and Hydropower Development

China

USA Japan

France

Germany UK

Austrilia

Brunei

Singapore

Myanmar

Laos

Cambodia

Indoniesia

Thiland

Malaysia

Vietnam

Philippines

0.300

0.400

0.500

0.600

0.700

0.800

0.900

1.000

0 2,000 4,000 6,000 8,000 10,000 12,000 14,000

UN

Hu

man

Dev

elop

men

t In

dex

Electricity Use Per Capita (kWh/y)

Development of Asian Countries 2016

The role of Hydropower will lead to the Development of Myanmar in future.

Myanmar

- 6 -

Page 7: Challenges on Tunneling and Hydropower Development

Nay Pyi Taw

Mandalay

Yangon

Tunneling Practices

on

Hydropower Projects

Page 8: Challenges on Tunneling and Hydropower Development

Most of railway tunnels are since pre war and hydropower tunnels start from 1997.

( As of 2013/08/20 )

0

5

10

15

20

25

30

35

40

45

Railway Hydropower

41.65

Len

gth

(k

m)

Types of Tunnel

Tunneling in Myanmar

Types of Tunnel

- 8 -

2.60

Page 9: Challenges on Tunneling and Hydropower Development

Hydropower is the most efficient way of power generation alternatives and has many favorable

characteristics such as renewable, clean, reliable and flexible.

For the hydropower development, dam and waterway hydraulic structures are main components .

For the construction of dam, diversion tunnel or conduit is vital structure.

For the power portion, waterway structure is essential and headrace tunnel is major structure

from the view points of safety, economic and environmental issue.

Tunnels are generally considered to be one of the greatest sources of cost and schedule risk for

the projects.

(Source: USACE, 2007)

(Source: JEPIC, 2008)

- 9 -

Page 10: Challenges on Tunneling and Hydropower Development

Ministry of Electricity and Energy (MOEE) had

been trying to implement large scale hydropower

projects to fulfill the electricity requirement of the

country. Most projects include tunneling works.

In general, tunnel excavation of hydropower

projects include those for power tunnel, diversion

tunnel and access tunnel etc.

Though tunnels of the projects in the region of

hard rock are simple, the tunnel construction in

poor geology face much complicated

disturbances leading to collapse, especially for

Sittaung valley projects which are giving many

lessons for tunneling in Myanmar.

- 10 -

Page 11: Challenges on Tunneling and Hydropower Development

Nay Pyi Taw

Mandalay

Yangon

Challenges on Tunneling

of

Sittaung Valley Hydropower Projects

Page 12: Challenges on Tunneling and Hydropower Development

Shwegyin

Kun

Thaukyegat 2

Paunglaung

Nancho

NO

RT

H

NAN

CHO

CHAU

NG

Rapid

NAM

CHO

CHAU

NG

NANCHO CHAUNG

Weir

Aqueduct

Headrace

Tunnel

Penstock

Power House

Head Tank

Intake

(1) Diversion Tunnel ( 531 m x 10 m x 10.8 m )

(2) Headrace Tunnel ( 540 m x Ø 8.5 )

Paunglaung Hydropower Project

Genera layout

Power Generating System

( 37 Tunnels, 3367 m )

Main dam

(131 m, 11.8 MCM

Spillway

(5000 m3/s)

230 KV Switch Yard

Paunglaung Bridge

Two Diversion Tunnels( 994 + 930 = 1924 m )

Granite, Granitic

Gneiss

Phyllite, Metasandstone

& Mudstone

- 12 -

Page 13: Challenges on Tunneling and Hydropower Development

Situation KUN Nancho Thaukyegat Paunglaung

1. Location

(1) Sittaung Vally Downstream most & West to Sittaung River

Upstream most & East to Sittaung

River

Middle Downstream & East to Sittaung

River

Upstream most & East to Sittaung River

2. Geological Condition

(1) Lithology

Meta-sandstone, Mudstone

(weak)

Granite, Granitic Gneiss (good)

Phyllite, Schist, Meta-sandstone,

(weak)

Granite, Granitic Gneiss

(good)

3. Structure

(1) Diversion Conduit/ Tunnel

1.5 x 3.8 m 2.5 x 3.75 m 531 x 11 x 13 m 994 x 10 x 14 m

(2) Headrace

Tunnel (L x Diameter)

1755 x 5.5 m 2352 x 4.72 m 538 x 8.5 m 80 x 8.5 m

4. Power Indices

(1) Installed Capacity (MW)

60 40 120 280

5. Organization

(1) Implementation by

Construction Division No.3

(MOEE)

Construction Division No.1

(MOEE)

Gold Energy Co., Ltd (Local Company)

Construction Division No.1

(MOEE)

- 13 -

Page 14: Challenges on Tunneling and Hydropower Development

0

20

40

60

80

100

120

140

160

180

200

220

240

260

2801 2 3 4 5 6 7 8 9

10

11

Mo

nth

ly P

ro

gress

(m

)

Month

Comparison of Tunneling Progress on Different Geological Area

Kun Waterway Tunnel (Weak Geology)

TYG Diversion Tunnel (Weak Geology)

NC Waterway Tunnel (Good Geology)

PL Diversion Tunnel (Good Geology)

All Projects – Tunnel excavation cannot much speedy on initial stage and inlet/ outlet

area of the mountain. After inlet/ outlet area, can speedy tunneling on

both weak or good geology conditions of the mountain.

Tunneling Progress – In the better geology area can excavate more progress than

weak geology and systematic geological observation is essential.

Heading 7.0m (H)

Avg: 110m/month

Full face 6.2m (Ø)

Avg: 26m/month

Heading 5.2m (H)

Avg: 45m/month

Full face 5.72m (Ø)

Avg: 39m/month

- 14 -

Page 15: Challenges on Tunneling and Hydropower Development
Page 16: Challenges on Tunneling and Hydropower Development

- 16 -

Page 17: Challenges on Tunneling and Hydropower Development

0

1

2

3

4

5

6

7

8

9

10

0 10 20 30 40 50 60 70 80 90 100

110

120

130

140

150

160

170

180

190

200

210

220

230

240

250

260

270

280

290

300

310

320

330

340

350

360

370

380

390

400

410

420

430

440

450

460

470

480

490

500

510

520

530

540

Q-I

ndex

Val

ue

Tunnel Distance (m)

Comparison of Rock Mass Conditions along Waterway Tunnel & Diversion Tunnel

Waterway Diversion

Poor (D)

Very Poor (E)

Fair (C)

y = -0.119x + 1.838R² = 0.017

0.00.51.01.52.02.53.03.54.04.55.05.56.06.57.0

0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0

Qd

Qw

Regression line of Actual Q-Index between Waterway & DiversionTunnel

- 17 -

Three Major Damages & 17 times collapse cases are occurred during

tunneling works for Waterway & Diversion !!

Page 18: Challenges on Tunneling and Hydropower Development

For both Projects, most of failure mechanisms were similar and severer situation on

tunnel excavation such as face failure, roof wedge failure and plain failure.

Depression Well

KUN KUN

KUN THAUKYEGAT

- 18 -

Page 19: Challenges on Tunneling and Hydropower Development

Situation KUN Nancho Thaukyegat Paunglaung

1. Geological Condition

1) Lithology Sandstone, Mudstone

(weak)

Granite, Granitic Gneiss

(good)

Sandstone, Mudstone

(weak)

Granite, Granitic Gneiss

(good)

2. Organization Condition

1) Manage: & Super: Good Good Good Good

2) Work Plan Normal Normal Normal Good

3) Cooperation Good Good Good Excellent

4) Skill of Workers Normal Normal Normal Good

5) Financial Support < Normal < Normal Good Good

6) Logistic Support < Normal < Normal Good Excellent

3. Construction Achievement

1) Completion Target 5 years Delay 4 years Delay 1.5 years Delay 2.5 years Delay

2) Project Cost 72% Over Run (Over all Cost)

45% Over Run (Over all Cost)

6% Over Run (Over all Cost)

Within Budget (Over all Cost)

- 19 -

Page 20: Challenges on Tunneling and Hydropower Development

Nancho HPP

Paunglaung

HPP

Kun HPP

Thaukyegat

HPP

Geology (Mechanical Factor)

Man

ag

em

en

t (H

um

an

Fa

cto

r)

Poor Good

Po

or

Go

od

Construction

Fail

Construction

Success

( Cost Overrun & Schedule Delay )

Geo-risk factors are mainly divided into two parts: “geological condition”

and “construction management system”, which are perceived as

“Natural Hazard” and “Man-made Hazard”, respectively.

- 20 -

Page 21: Challenges on Tunneling and Hydropower Development

Based on case study results, it would be recommended that the development of

tunneling in hydropower projects, the most important is strengthening on “poor

construction management system” human factors and “poor geological

condition” mechanical factors of tunneling practices.

In order to scope with difficulties associated “poor construction management

system” human factors, following remedial measure would be expected.

Skill of construction works.

Decision-making system.

Procurement system.

Financial system.

In order to scope with difficulties associated “poor geological condition”

mechanical factors, following remedial measure would be expected.

Improvement of underground geological investigation.

Evaluation on rock mass classification.

Establishment of database system on past hydropower tunnels data.

- 21 -

Page 22: Challenges on Tunneling and Hydropower Development

Nay Pyi Taw

Mandalay

Yangon

Moving Forwards

on

Hydropower Development in Myanmar

Page 23: Challenges on Tunneling and Hydropower Development

Sr. No. Power Stations Installed Capacity (MW) Type Completion Year Owner

1 Baluchaung-2 168 Dam & Waterway 1960/1974

Sta

te O

wn

ed

2 Kinda 56 Dam & Waterway 1985

3 Sedawgyi 25 Dam Type 1989

4 Baluchaung-1 28 Dam & Waterway 1992

5 Zaw Gyi-1 18 Waterway Type 1995

6 Zaw Gyi-2 12 Dam Type 1998

7 Zaung Tu 20 Dam Type 2000

8 Thaphenzeik 30 Dam Type 2002

9 Mone 75 Dam Type 2004

10 Paunglaung 280 Dam Type 2005

11 Yenwe 25 Dam & Waterway 2007

12 Khapaung 30 Dam & Waterway 2008

13 Keng Taung 54 Waterway Type 2009

14 Yeywa 790 Dam & Waterway 2010

15 Shwegyin 75 Dam Type 2011

16 Kyee-on-Kyee-wa 74 Dam Type 2011

17 Kun 60 Dam & Waterway 2012

18 Nancho 40 Waterway Type 2014

19 Phyu 40 Dam & Waterway 2014

20 Upper Paunglaung 140 Dam Type 2015

21 Myo Gyi 30 Dam Type 2016

22 Tuaukyekhet 120 Dam Type 2014

BO

T

23 Baluchaung-3 52 Dam & Waterway 2013

24 Shwe Li-1 600 Waterway Type 2009

JV

/BO

T

25 Ta Pein-1 240 Dam Type 2011

26 Chiphwe Nge 99 Dam Type 2013

Total 3,181

- 23 -

Page 24: Challenges on Tunneling and Hydropower Development

0

1

2

3

4

5

6

7

8

9

10

11

12

13

Pa

un

gla

un

g

(28

0M

W)

Ye

nw

e (

25

MW

)

Kh

ap

au

ng

(3

0M

W)

Ke

ng

Ta

un

g

(54

MW

)

Ye

yw

a

(79

0M

W)

Sh

we

gyin

(7

0M

W)

Ku

n (

60

MW

)

Na

nc

ho

(4

0M

W)

Ph

yu

(4

0M

W)

U-P

au

ng

lau

ng

(1

40

MW

)

Tu

au

kye

kh

et

(12

0M

W)

Ba

luc

ha

un

g-3

(5

2M

W)

Sh

we

Li-

1

(60

0M

W)

Ta

Pe

in-1

(2

40

MW

)

Ch

iph

we

N

ge

(99

MW

)

5.5

4 4 4

7

6 65 5

6

3.5 3

5

3

2

8

6

5 5

98

109

12

9

5

4

6

3 3

Comparison of Completion Period for Hydropower Construction (1997 ~ 2016)

Planning Period

Completion PeriodB.O.T JV / B.O.T MOEE

- 24 -

Page 25: Challenges on Tunneling and Hydropower Development

Sr.

No. Projects

Installed

Capacity

(MW)

States/

Region

1. Shwe Li-3 1,050 Shan

2. Upper Yeywa 280 Shan

3. Tha-Htay 111 Rakhine

4. Upper Keng

Tawng 52.5 Shan

Total 1,493.5

By Ministry of Electricity and Energy (MOEE)

- 25 -

Page 26: Challenges on Tunneling and Hydropower Development

Under Implementation Hydropower Projects (MOEE)

Implementing all

over the country

Try to implement

with JV/BOT model

in some projects 0

20

40

60

80

100

Shweli-3(1,050 MW)

Upper Yeywa(280 MW)

Upper KengTawng (51 MW)

Tha-htay(111 MW)

Co

ns

tru

cti

on

Pro

gre

ss

(%

)

Remaining 2015~16 (July) 2014~15 2013~14 2012~13

2011~12 2010~11 2009~10 2008~09 2007~08

11% (1/2017)

26% (1/2017)

43% (1/2017)

33% (1/2017)

6 Years

Passed

5 Years

Passed

8 Years

Passed

9 Years

Passed

- 26 -

Page 27: Challenges on Tunneling and Hydropower Development

- 27 -

River - Shweli River

Inflow - 14259 Mm3

Dam - RCC Dam, 120 m Height

Progress - 11 %

Shweli (3) HPP (1,050 MW)

Under Implementation of Shweli (3) Hydropower Project (MOEE)

Page 28: Challenges on Tunneling and Hydropower Development

- 28 -

River - Myitnge River

Inflow - 11702 Mm3

Dam - RCC Dam, 97 m Height

Progress - 26%

Under Implementation of Upper Yeywa Hydropower Project (MOEE)

Upper Yeywa HPP (280 MW)

Page 29: Challenges on Tunneling and Hydropower Development

- 29 -

Upper Keng Tawng HPP (52.5 MW) River - Nam Teng River

Inflow - 2302 Mm3

Dam - Zoned Type Rockfill Dam, 57 m Height

Progress - 33%

Under Implementation of Upper Keng Tawng Hydropower Project (MOEE)

Page 30: Challenges on Tunneling and Hydropower Development

Under Implementation of Tha-htay Hydropower Project (MOEE)

- 30 -

Tha-htay HPP (111 MW) River - Tha-htay River

Inflow - 2876 Mm3

Dam - Zoned Type Rockfill Dam, 91 m Height

Progress - 43 %

Page 31: Challenges on Tunneling and Hydropower Development

Co

ns

tru

cti

on

P

rocu

rem

en

t F

ina

nc

e

Unforeseen Hydrology and Geology Condition should be investigated well.

Lack of Systematic Geological Observation should be evaluated well.

Poor Working Condition should be improved well.

Potential Challenges Evaluations

Insufficient major equipment should be prepared

well.

Resources constraint should be managed well.

Required machinery equipment should be enough for each Hydropower Projects.

To prepare resources ahead before starting the Construction Works.

Budget delay should be avoided well.

Budget insufficient should be supplied well.

Org

an

iza

tio

n

Technical Constraints should be improved well.

Lack of skilled workforce should be managed well.

Human mistake should be avoided well.

To prepare human resource development.

To allocate right person and enough capacity for the project site.

To organize and right decision for the project.

It can be investigated well by proper technique for hydrological and geological investigations.

Well observation and evaluation can minimize the geo-risk and cost effective on underground works.

To improve poor working condition, discussion and well preparation on job site is essential.

Delaying of budget is becoming the high risk factors for hydropower construction works.

Well preparation for construction is mainly depend on availability of budget, but insufficient of budget may defect on Construction time and Cost.

- 31 -

Page 32: Challenges on Tunneling and Hydropower Development

Moving Forwards on Hydropower Development

Hydro is cost-effective power resource blessed with rich national potential.

Focus on Sustainable and Responsible development of Hydropower.

Action plan should be secured by implementing priority projects.

Establishing a capacity building for engineers and career nurturing systems.

Evaluation and feed-back actions on Hydropower implementation.

Environmental and social impact awareness.

Moving to Public Private Partnership.

Subsidization and cross-subsidization by Government gradually released.

- 32 -

Page 33: Challenges on Tunneling and Hydropower Development

LOGO