Top Banner
Briefing Session Temporary Traffic Arrangement at Campus Circuit For Site Formation Works at Area 39
11

Briefing Session

Jan 21, 2016

Download

Documents

Cosma Alexia

Briefing Session. Temporary Traffic Arrangement at Campus Circuit For Site Formation Works at Area 39. Area 39. Location Plan. Site formation to required level of +6.5 mPD. Land Application for Proposed CUHK Development. Preliminary Proposal. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Briefing Session

Briefing Session

Temporary Traffic Arrangement at Campus Circuit

For Site Formation Works at Area 39

Page 2: Briefing Session

Location Plan

Area 39

Page 3: Briefing Session

Land Application for Proposed CUHK Development

Site formation to required level of +6.5 mPD.

Page 4: Briefing Session

Preliminary Proposal

Page 5: Briefing Session

Temporary Traffic Arrangement on Campus Circuit

• To allow access for CEDD construction vehicles

• Restricted hours :

– 9:30am to 6:30pm

– Monday to Friday, except Public Holidays and University’s special event dates

• Volume of construction traffic :

– not exceed 21 round trip per hour at peak

– about 14 round trip per hour in average

• Commence on 15 January 2008 tentatively

• Last for about 1.5 years (1/2008 – 7/2009)

Page 6: Briefing Session

Preventive Measures

• Each and every CEDD construction vehicles shall bear a permit.

• No queue up or stay on Campus Circuit or within Campus.

• Access only allowed to the designated haul route area.

• Access to other area such as canteen, washroom is prohibited.

• No black smoke emission vehicle is allowed.

• No construction waste etc. can be disposed in the Campus.

• Daily in/out log sheets shall be submitted to Security and Transport Office.

Page 7: Briefing Session

Preventive Measures

• Dust mitigation measures such as wheel wash, canvas cover to loads.

• Daily cleaning on Campus Circuit.

• Cleaning at open area and watering nearby vegetation if found necessary.

• Noise Control Ordinance and its subsidiary regulations will be strictly complied.

• Junction of Bridge No. 2 and Campus Circuit is being widened.

Page 8: Briefing Session

Monitoring and Communication

• On top of CEDD’s monitoring measures, the University would set up a monitoring

system to carry out regular measurement and inspection.

• For better communication, University will set up a liaison group.

• Duties include

– periodic review and comment the arrangement of fill transportation works,

monitoring system, monitoring results and dust/noise mitigation measures.

– communicate with CEDD and the University community.

Page 9: Briefing Session

Liaison Group

• Convener :

– Professor Michael Hui, APVC

• Members :

– Security and Transport Office - Mr. Philip Wong

– University Steering Committee on Environmental - Mr. Jack Yung

– University Safety and Environment Office - Mr. S K Lam

– Campus Development Office - Mr. Arthur Ma

– Estates Management Office - Mr. Clement Wong

– Quartering Unit - Ms. Amanda Chan

– Representatives from residents, staff, and CEDD.

Page 10: Briefing Session

Enquires

• Enquires Hotline : 9468 8762

• Contact Person : Mr. Jack Yung, University Safety and Environment

Office

• E-mail : [email protected]

• Fax : 2603 6862

Page 11: Briefing Session

Opening hours at Eastern Gate

• The University has reviewed the current traffic using the Eastern Gate and

will extend its opening hour.

• Effective from 10 February 2008, the opening hour is

– from 7:00am to 12:00 mid-night daily, including Sundays and Public Holidays.